Blueridge Homes v. Method Air , 2019 UT App 149 ( 2019 )


Menu:
  •                       
    2019 UT App 149
    THE UTAH COURT OF APPEALS
    BLUERIDGE HOMES INC., JARED OESER, RYAN CLARK,
    AND JULIANNE OESER,
    Appellants,
    v.
    METHOD AIR HEATING AND AIR CONDITIONING, K&K STUCCO
    & STONE LLC, HILL & MEHR HEATING & COOLING, CURTIS MINER
    ARCHITECTS, PARRISH CONSTRUCTION COMPANY, DAVE’S CUSTOM
    SIDING, AND HERCULES CONSTRUCTION INC.
    Appellees.
    Opinion
    No. 20180310-CA
    Filed September 6, 2019
    Fourth District Court, Provo Department
    The Honorable Samuel D. McVey
    The Honorable Kraig Powell
    No. 140401785
    Richard K. Glauser and Richard Bissell, Attorneys
    for Appellants
    Joseph E. Minnock, Attorney for Appellee Method
    Air Heating and Air Conditioning
    Scott C. Powers and Erik R. Hamblin, Attorneys
    for Appellee K&K Stucco & Stone LLC
    Vincent J. Velardo and Thomas J. Rollins, Attorneys
    for Appellee Hill & Mehr Heating & Cooling
    Craig R. Mariger, Brad M. Liddell, and C. Michael
    Judd, Attorneys for Appellee Curtis Miner Architects
    Peter H. Barlow and Andrew D. Day, Attorneys
    for Appellee Parrish Construction Company
    Stephen F. Edwards, Attorney for Appellees
    Dave’s Custom Siding
    Blueridge Homes v. Method Air
    Joseph J. Joyce and Jeremy G. Knight, Attorneys for
    Appellee Hercules Construction Inc.
    JUDGE DAVID N. MORTENSEN authored this Opinion, in which
    JUDGES GREGORY K. ORME and KATE APPLEBY concurred.
    MORTENSEN, Judge:
    ¶1      In this appeal, third-party plaintiffs in a construction
    defect case seek to avoid a statute of repose but fail in that effort.
    Plaintiff filed suit against its general contractor, Blueridge
    Homes Inc. (Blueridge), in December 2014, alleging construction
    defects in a condominium development project. In July 2015,
    Blueridge filed a third-party complaint against its various
    subcontractors, alleging that if Blueridge was liable to Plaintiff,
    then subcontractors were liable to Blueridge. Although Plaintiff’s
    claims against Blueridge survived a motion to dismiss, the
    district court dismissed Blueridge’s third-party claims as time-
    barred under Utah Code section 78B-2-225 (Builders’ Statute of
    Repose). Blueridge argues that the district court erred by
    (1) dismissing its third-party complaint because it should have
    related back to Plaintiff’s December 2014 filing and (2) denying
    its post-trial motions. We affirm the district court on both points.
    BACKGROUND
    ¶2    Plaintiff entered into a contract with Blueridge as the
    general contractor for a condominium development in Saratoga
    Springs, Utah (Project). The Project consisted of nine buildings.
    Upon substantial completion of each building, certificates of
    occupancy were issued between May 2, 2007, and June 9, 2009.
    ¶3     On December 22, 2014, Plaintiff filed a complaint naming
    Blueridge as defendant and raising various claims related to
    alleged construction defects on the Project. Blueridge was first
    20180310-CA                      2                
    2019 UT App 149
    Blueridge Homes v. Method Air
    notified of the suit when the complaint was served on February
    13, 2015. Over five months later on July 15, 2015, Blueridge filed
    a third-party complaint against subcontractors Method Air
    Heating and Air Conditioning, K&K Stucco & Stone LLC, Hill
    & Mehr Heating & Cooling, Curtis Miner Architects, Parrish
    Construction Company, Dave’s Custom Siding, and Hercules
    Construction Inc. (collectively, Appellees), alleging that
    Appellees were ultimately responsible for the construction
    defects raised in the initial complaint.
    ¶4      On November 30, 2015, Miner filed a motion to dismiss,
    arguing that the Builders’ Statute of Repose barred Blueridge’s
    third-party claims. See Utah Code Ann. § 78B-2-225(3)(a)
    (LexisNexis 2018) 1 (“An action . . . based in contract or warranty
    shall be commenced within six years of the date of completion of
    the improvement . . . .”). The district court granted Miner’s
    motion on the grounds that the Builders’ Statute of Repose had
    run on June 9, 2015, six years after the last certificate of
    occupancy was issued, Blueridge’s third-party complaint was
    not filed until July 15, 2015, and Blueridge’s third-party
    complaint did not relate back to the filing of Plaintiff’s initial
    complaint because Appellees were not named parties in the
    initial complaint.
    ¶5     The remaining Appellees followed suit by filing motions
    for summary judgment, arguing that the Builders’ Statute of
    Repose barred Blueridge’s third-party complaint. Blueridge
    opposed the motions, arguing that the Builders’ Statute of
    Repose did not bar its claims because rule 14 of the Utah Rules of
    Civil Procedure permitted it to “bring in a third party at any
    time after the commencement of the action.” In other words,
    1. Because the statutory provision in effect at the relevant time
    does not differ in any material way from the provision now in
    effect, we cite the current version of the Utah Code.
    20180310-CA                     3               
    2019 UT App 149
    Blueridge Homes v. Method Air
    Blueridge argued that under rule 14, its third-party complaint
    should relate back to the initial complaint.
    ¶6      The district court rejected Blueridge’s argument and
    granted the motions for summary judgment in favor of
    Appellees. The court ruled that where the last certificate of
    occupancy on the nine buildings for the Project was issued on
    June 9, 2009, and the third-party complaint was filed on July 15,
    2015, the six-year Builders’ Statute of Repose had run. The
    district court further ruled that if third-party complaints
    automatically related back to the filing of the original complaint,
    then rule 14 would become “an all-encompassing rule that
    would eliminate all limitations on third-party actions.” (Citing
    Perry v. Pioneer Wholesale Supply Co., 
    681 P.2d 214
    , 217 (Utah
    1984).)
    ¶7     Blueridge later filed a motion to reconsider and motion to
    alter or amend pursuant to rule 59(e) for relief from judgment
    under rule 60(b) of the Utah Rules for Civil Procedure (Motions
    for Reconsideration). 2 In its Motions for Reconsideration,
    Blueridge raised three issues for the first time: (1) the existence of
    three certificates of occupancy for one of the nine buildings
    created a genuine dispute of material fact—which should
    preclude summary judgment—concerning when the Builders’
    Statute of Repose began to run for that building, (2) an exception
    to the Builders’ Statute of Repose should have applied to
    Appellees, and (3) the Builders’ Statute of Repose was
    unconstitutional as applied. The district court denied the
    Motions for Reconsideration, stating, “Having considered the
    written and oral arguments of the parties, the Court finds no
    persuasive grounds to reconsider its orders or to alter or amend
    its judgments.”
    2. A new judge was assigned to the case prior to Blueridge filing
    its Motions for Reconsideration.
    20180310-CA                      4                
    2019 UT App 149
    Blueridge Homes v. Method Air
    ¶8    Blueridge appeals.
    ISSUES AND STANDARDS OF REVIEW
    ¶9     Blueridge argues that the district court erred in granting
    Miner’s motion to dismiss and Appellees’ motions for summary
    judgment. “A district court’s grant of a motion to dismiss based
    upon the allegations in the plaintiff’s complaint presents a
    question of law that we review for correctness.” Osguthorpe v.
    Wolf Mountain Resorts, LC, 
    2010 UT 29
    , ¶ 10, 
    232 P.3d 999
    (cleaned up). “We review the district court’s grant of summary
    judgment for correctness and accord no deference to its
    conclusions of law.” Gardiner v. Anderson, 
    2018 UT App 167
    , ¶ 14,
    
    436 P.3d 237
     (cleaned up).
    ¶10 Blueridge also contends that the district court erred by
    denying its Motions for Reconsideration. “Because [district]
    courts are under no obligation to consider motions for
    reconsideration, any decision to address or not to address the
    merits of such a motion is highly discretionary.” Mower v.
    Simpson, 
    2017 UT App 23
    , ¶ 43, 
    392 P.3d 861
     (cleaned up).
    Accordingly, “we will not disturb a district court’s decision to
    grant or deny such a motion absent an abuse of discretion.” 
    Id.
    (cleaned up).
    ANALYSIS
    I. The Builders’ Statute of Repose Barred Blueridge’s
    Third-Party Claims.
    ¶11 The Builders’ Statute of Repose provides that “[a]n action
    . . . based in contract or warranty shall be commenced within six
    years of the date of completion of the improvement.” Utah Code
    Ann. § 78B-2-225(3)(a) (LexisNexis 2018) (emphasis added). The
    date of completion is “established by the earliest of: (i) a
    20180310-CA                    5               
    2019 UT App 149
    Blueridge Homes v. Method Air
    Certificate of Substantial Completion; (ii) a Certificate of
    Occupancy issued by a governing agency; or (iii) the date of first
    use or possession of the improvement.” 
    Id.
     § 78B-2-225(1)(c).
    ¶12 Here, the final certificate of occupancy on the Project was
    issued on June 9, 2009, and the third-party complaint was filed
    on July 15, 2015—more than six years later. Accordingly,
    Blueridge concedes that its third-party complaint was filed after
    the Builders’ Statute of Repose had run. 3 Blueridge contends,
    however, that its third-party complaint should relate back to the
    filing of the initial complaint because rule 14 of the Utah Rules of
    Civil Procedure allows for filing a third-party complaint at any
    time after the commencement of the initial complaint.
    ¶13 Rule 14 of the Utah Rules of Civil Procedure provides that
    “[a]t any time after commencement of the action a defendant, as
    a third-party plaintiff, may cause a summons and complaint to
    be served upon a person not a party to the action.” While we
    agree that rule 14 permits a party to file a third-party complaint
    at any time during the pendency of an action, it does not follow
    that rule 14 also bars third-party defendants from raising a
    statute of limitations or repose as an affirmative defense. See
    Raithaus v. Saab-Scandia of Am., Inc., 
    784 P.2d 1158
    , 1161 n.5 (Utah
    1989) (“[T]he statute of repose [is] a separate affirmative
    defense.”). In other words, the language Blueridge relies on
    merely dictates when a third-party complaint can be filed—not
    3. Blueridge contended in its Motions for Reconsideration and
    on appeal that a genuine dispute of material fact exists
    concerning whether its third-party complaint was timely for one
    of the nine buildings due to the existence of three certificates of
    occupancy for that building. As discussed below we conclude
    that this argument is without merit, infra ¶ 20, and further find
    that the district court did not abuse its discretion in declining to
    reach this issue in the first instance, infra ¶ 21.
    20180310-CA                     6                
    2019 UT App 149
    Blueridge Homes v. Method Air
    what the substantive effect of the third-party complaint is or
    what defenses may be raised against the claims stated in a third-
    party complaint. See Choate v. United States, 
    233 F. Supp. 463
    , 464
    (W.D. Okla. 1964) (acknowledging that a statute of limitations
    can be an affirmative defense to third-party claims properly
    raised under rule 14 of the Federal Rules of Civil Procedure).
    Therefore, we conclude that the district court did not err in
    dismissing Blueridge’s third-party complaint because, although
    Blueridge was permitted to file its third-party complaint at any
    time under rule 14, rule 14 did not bar application of the
    Builders’ Statute of Repose.
    ¶14 In spite of this, Blueridge argues that Sharon Steel Corp. v.
    Aetna Casualty & Surety Co., 
    931 P.2d 127
     (Utah 1997),
    demonstrates that its third-party complaint should relate back.
    In Sharon, the federal government sued a steel corporation,
    which then tendered the claim to three insurers. 
    Id.
     at 130–31.
    Later, the corporation filed suit against all three insurers,
    claiming they were obligated to defend and indemnify the
    corporation in the initial suit. 
    Id.
     The court determined that all
    three insurers had an obligation to defend and indemnify the
    company. Id. at 131. One of the three insurers paid the bulk of
    the defense costs on behalf of the corporation in the initial suit.
    Id. That insurer later filed a crossclaim against the two other
    insurers, both of whom were defendants in the action, to recover
    defense costs in excess of its obligation. Id. The insurers named
    in the crossclaim argued that the statute of limitations barred the
    crossclaim. Id. Our supreme court held, however, that the
    crossclaim would relate back because the parties in the
    complaint were the same as those in the crossclaim. Id. at 133.
    ¶15 Blueridge’s reliance on Sharon is misplaced. In Sharon, the
    two defendant insurers named in the crossclaim were initially
    named as defendants when the steel corporation sued all three
    insurers for indemnification. Id. at 130–31. Thus, where the two
    defendant insurers had been timely brought into the case by the
    20180310-CA                     7               
    2019 UT App 149
    Blueridge Homes v. Method Air
    initial complaint, the crossclaim could relate back. See Utah R.
    Civ. P. 15(c). But in this case, Appellees were not parties to the
    suit until the third-party complaint was filed and served.
    Therefore the Builders’ Statute of Repose was properly applied
    to Blueridge’s claims. See Gables & Villas at River Oaks
    Homeowners Ass’n v. Castlewood Builders, LLC, 
    2018 UT 28
    , ¶ 3,
    
    422 P.3d 826
     (“[W]e conclude that the homeowners association’s
    claims are time-barred because no viable complaint was filed
    within the [Builders’ Statute of Repose] period and the
    complaint did not relate back to a timely pleading.”).
    ¶16 Conversely, Appellees cite Perry v. Pioneer Wholesale
    Supply Co., 
    681 P.2d 214
     (Utah 1984)—a case with nearly
    identical facts to this case. In Perry, a subcontractor provided
    doors to a general contractor for construction of a medical center.
    
    Id. at 216
    . The subcontractor ordered the doors from a
    distributor, who ordered them from a manufacturer. 
    Id.
     The
    doors were deemed defective, and the general contractor sued
    the subcontractor. 
    Id.
     Almost three years later, the subcontractor
    brought a third-party complaint against the distributor and the
    manufacturer. 
    Id.
     When the distributor and the manufacturer
    brought motions for summary judgment on the ground that the
    subcontractor’s claims were barred by a statute of repose, the
    subcontractor argued that the third-party complaint should
    relate back to the filing of the initial complaint. 
    Id.
     Our supreme
    court rejected this argument, holding that the relation back
    doctrine does not apply to a pleading that “adds new parties
    who have no identity of interest with existing parties.” 
    Id. at 217
    .
    ¶17 Perry is applicable to these facts and further demonstrates
    that Blueridge’s third-party complaint does not relate back to the
    initial complaint in this case. Simply put, Perry illustrates that
    when a pleading adds new parties to an action—as is the case
    here—that pleading cannot relate back to the initial complaint.
    See 
    id. at 216
    . This holding is consistent with myriad other Utah
    cases related to complaints or amendments which add new
    20180310-CA                     8                
    2019 UT App 149
    Blueridge Homes v. Method Air
    parties. See, e.g., Noor v. State, 
    2019 UT 3
    , ¶ 42, 
    435 P.3d 221
    (“[A]n amended pleading may relate back as long as the parties
    in an action have been reasonably put on notice of the new
    claims before the statute of limitations has expired.”); 2010-1
    RADC/CADC Venture, LLC v. Dos Lagos, LLC, 
    2016 UT App 89
    ,
    ¶ 11, 
    372 P.3d 683
     (stating that the relation back “rule generally
    does not apply to an amendment which substitutes or adds new
    parties” (cleaned up)), aff’d, 
    2017 UT 29
    , 
    408 P.3d 313
    .
    ¶18 In light of the fact that Blueridge’s third-party complaint
    was filed after the Builders’ Statute of Repose had run and our
    conclusion that third-party complaints adding new parties do
    not relate back to prior pleadings under rule 14 or Utah case law,
    we conclude that the district court properly dismissed
    Blueridge’s third-party complaint as time-barred.
    II. The District Court Did Not Err in Denying Blueridge’s
    Motions for Reconsideration.
    ¶19 Blueridge raised three arguments in its Motions for
    Reconsideration: First, that the existence of three certificates of
    occupancy for building two created a genuine dispute of
    material fact that should have precluded summary judgment
    (for claims related only to that building); second, that the district
    court should have applied an exception to the Builders’ Statute
    of Repose to Appellees; and third, that the Builders’ Statute of
    Repose is unconstitutional as applied. Importantly, the court
    never ruled on the merits of these arguments. 4 Instead, having
    4. We note that Blueridge’s claims related to its Motions for
    Reconsideration are potentially unpreserved, see Wilde v. Wilde,
    
    2001 UT App 318
    , ¶ 37 n.5, 
    35 P.3d 341
     (“Raising an issue in a
    post-trial motion fails to preserve that issue for appeal without
    evidence that the [district] court considered and ruled on the
    (continued…)
    20180310-CA                      9               
    2019 UT App 149
    Blueridge Homes v. Method Air
    reviewed the motions and entertained extensive oral argument,
    the district court found “no persuasive grounds to reconsider its
    orders or to alter or amend its judgments.”
    ¶20 “Whether to reconsider a prior ruling is ordinarily within
    the sound discretion of the district court . . . .” Colony Ins. Co. v.
    Human Ensemble, LLC, 
    2013 UT App 68
    , ¶ 6, 
    299 P.3d 1149
    .
    “Factors that weigh in favor of the district court’s decision
    to reconsider include, but are not limited to, (1) the matter
    being presented in a new or different light, (2) a change in the
    governing law, (3) the discovery of new evidence, or (4) a
    conviction that the prior decision was clearly erroneous.” 
    Id.
     5
    Importantly, when a district court determines that these
    factors do not weigh in favor of reconsideration, as the district
    court did here, we will reverse only if the court has abused
    its discretion. See Bergmann v. Bergmann, 
    2018 UT App 130
    , ¶ 12,
    
    428 P.3d 89
    . Conversely, when a district court reaches the
    merits of a motion to reconsider and provides legal analysis
    and legal conclusions, we would reach the merits of its
    ruling. See State v. Boyden, 
    2019 UT 11
    , ¶ 21, 
    441 P.3d 737
    .
    Accordingly, on appeal we must decide whether the district
    court acted within its discretion in declining to reconsider
    its rulings.
    (…continued)
    merits of the issue.”), but because neither party has briefed the
    apparent preservation flaw, we address these arguments.
    5. The fact that a new judge had been assigned to this case for the
    Motions for Reconsideration, supra ¶ 7 n.2, has no bearing on our
    review, see McLaughlin v. Schenk, 
    2013 UT 20
    , ¶ 23, 
    299 P.3d 1139
    (“[T]he replacement judge was free to reconsider the fairness
    hearing issue that had been previously ruled upon by the retired
    judge.”).
    20180310-CA                      10               
    2019 UT App 149
    Blueridge Homes v. Method Air
    ¶21 We conclude that the district court did not abuse
    its discretion because all of the evidence and arguments raised
    for the first time in Blueridge’s Motions for Reconsideration
    existed and could have been asserted when the underlying
    motion to dismiss and/or motions for summary judgment were
    briefed, argued, and ruled upon. The existence of three
    certificates of occupancy for building two was disclosed to
    Blueridge prior to Appellees’ motions for summary judgment
    and it was available through public records all the while. 6 Thus,
    the other certificates of occupancy were not “new” evidence as
    Blueridge argues. Similarly, Blueridge’s other arguments—that
    an exception to the Builders’ Statute of Repose should have
    applied to Appellees and that the Statute is unconstitutional—
    were legal points that could have been raised by Blueridge at the
    time the dispositive motions were before the court in the first
    instance. We thus see the Motions for Reconsideration as nothing
    more than an effort to secure a do-over, and the district court
    acted well within its discretion in refusing to address the issues
    anew.
    ¶22 In sum, Blueridge has not shown that the evidence
    presented in its Motions for Reconsideration was “new” or that
    any arguments asserted could not have been made initially
    before the district court ruled on the motions to dismiss and for
    summary judgment. Therefore, the district court here did not
    6. Without expressly ruling on the issue, we are hard-pressed to
    see how the existence of more than one certificate of occupancy
    would delay the time to file under the Builders’ Statute of
    Repose because the plain language of the statute provides that
    the time to file begins at the earliest occurrence of a number of
    events, one being the issuance of a certificate of occupancy
    (whether or not additional certificates are issued later in time).
    See Utah Code Ann. § 78B-2-225(1)(c) (LexisNexis 2018).
    20180310-CA                    11              
    2019 UT App 149
    Blueridge Homes v. Method Air
    abuse its discretion in declining to reconsider its previous
    rulings and denying Blueridge’s motions.
    CONCLUSION
    ¶23 The district court did not err in granting summary
    judgment and dismissing Blueridge’s third-party claims, because
    they were time-barred by the Builders’ Statute of Repose.
    Further, we decline to reach the merits of the issues raised for
    the first time in the Motions for Reconsideration because the
    district court did not address the merits and Blueridge has not
    shown that the court abused its discretion in declining to do so.
    ¶24   Affirmed.
    20180310-CA                   12               
    2019 UT App 149