Farnsworth, III v. Towboat Nantucket Sound, Inc. , 790 F.3d 90 ( 2015 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 14-1903
    RODNEY FARNSWORTH, III,
    Plaintiff, Appellant,
    v.
    TOWBOAT NANTUCKET SOUND, INC.,
    Defendant, Appellee.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. F. Dennis Saylor, IV, U.S. District Judge]
    Before
    Howard, Chief Judge,
    Selya and Lynch, Circuit Judges.
    J. Patrick Yerby, with whom Brian Keane and The Kaplan/Bond
    Group were on brief, for appellant.
    David S. Smith, with whom Robert P. Snell, Amy Maher Rogers,
    Law Offices of Steven B. Stein, and Farrell McAleer & Smith LLP
    were on brief, for appellee.
    June 17, 2015
    LYNCH, Circuit Judge.       Out of this maritime case come
    useful lessons for those who seek to challenge the validity of
    arbitration clauses in contracts they have signed.
    Plaintiff Rodney Farnsworth, III, entered into a salvage
    contract with defendant Towboat Nantucket Sound, Inc. ("TNS"), to
    obtain help when Farnsworth's boat went aground on rocks one night
    near the Weepeckett Islands in Buzzards Bay.              Farnsworth later
    tried to rescind the whole contract, claiming that he had signed
    it under duress, and disputed the sum owed to TNS.
    The chronology of events is important.             The parties by
    agreement submitted the dispute to a panel of three arbitrators
    pursuant to a binding arbitration clause in the salvage contract.
    After the arbitration proceeding had started, Farnsworth chose to
    file this lawsuit, seeking a preliminary injunction against the
    arbitration   and   a    declaration   that   the   salvage    contract    was
    unenforceable because Farnsworth had entered into it under duress.
    His   complaint   drew   no   distinction     between   the   obligation    to
    arbitrate and the merits issue of what payment was owed to TNS.
    The district court denied the motion for injunctive relief and
    stayed the case pending the outcome of the arbitration.                    The
    arbitration panel found in favor of TNS and ordered Farnsworth to
    pay a salvage award of $60,306.85.          The district court confirmed
    - 2 -
    that award over Farnsworth's objection.
    Farnsworth appeals, arguing that the district court
    erred in confirming the arbitration award without first addressing
    his duress claim as to the arbitration clause.                                                    We hold that,
    because                   Farnsworth                           did   not    challenge   the   validity   of   the
    arbitration clause specifically in his complaint (or indeed at any
    time before the conclusion of the arbitration proceedings),1 the
    district court correctly found that the duress claim in all its
    aspects was for the arbitrator to resolve. Essentially, Farnsworth
    did too little, too late.                                            We affirm.
    I.
    On the evening of July 28, 2012, Farnsworth was anchoring
    his boat, the M/Y AURORA, in the Weepecket Island anchorage in
    Buzzards                     Bay.                    The        boat's     depth   sounder    malfunctioned   and
    Farnsworth inadvertently allowed the vessel to drift aground.
    1
    Even if Farnsworth had specifically challenged the
    validity of the arbitration clause in his verified complaint, he
    might still be vulnerable to the argument that he waived his right
    to judicial review by first consenting to and participating in
    arbitration.   See Opals on Ice Lingerie v. Bodylines Inc., 
    320 F.3d 362
    , 368 (2d Cir. 2003) ("[I]f a party participates in
    arbitration proceedings without making a timely objection to the
    submission of the dispute to arbitration, that party may be found
    to have waived its right to object to the arbitration."); ConnTech
    Dev. Co. v. Univ. of Conn. Educ. Props., Inc., 
    102 F.3d 677
    , 685
    (2d Cir. 1996) (collecting cases). However, TNS has not pressed
    a waiver argument, and so we do not address the issue.
    - 3 -
    Farnsworth requested a tow over his marine radio, and TNS's vessel
    the NORTHPOINT responded to his call. Farnsworth also made contact
    with the Coast Guard, which instructed him that, if he had any
    problems, he should "make the appropriate hail" and the Coast Guard
    would assist.
    The merits issue in this case turns on whether the
    contract which ensued was a towage or a salvage contract.                                           The
    difference between the two is important under maritime law because
    towage is compensated at a contract rate, whereas a salvor is
    entitled to an equitable award equal to a portion of the value of
    the salvaged property.                                         2 T.J. Schoenbaum, Admiralty and Maritime
    Law § 16-1 (5th ed. 2014); see also Faneuil Advisors, Inc. v. O/S
    Sea Hawk, 
    50 F.3d 88
    , 92 (1st Cir. 1995) (describing the law of
    salvage).                        Salvage service generally "commands a larger award,"
    and a salvage contract creates a preferred maritime lien.                                        Evanow
    v. M/V Neptune, 
    163 F.3d 1108
    , 1114 (9th Cir. 1998).2
    The parties sharply differ over what happened in the
    2
    "The existence of a marine peril distinguishes a salvage
    contract from one for towage." 
    Evanow, 163 F.3d at 1114
    ; accord
    Schoenbaum, supra, § 16-1. That is, towage is undertaken "from
    considerations of convenience," whereas salvage is aimed at saving
    a vessel that is "disabled, and in need of assistance." 
    Evanow, 163 F.3d at 1114
    (quoting The Flottbeck, 
    118 F. 954
    , 960 (9th Cir.
    1902)); see also Lloyd's Syndicate 1861 v. Crosby Tugs, L.L.C.,
    No. 13-5551, 
    2014 WL 3587375
    , at *3 (E.D. La. July 21, 2014)
    (collecting authorities).
    - 4 -
    hours     after   Farnsworth        made    contact    with    the     NORTHPOINT.
    Farnsworth's complaint alleges that the NORTHPOINT crew members
    "attempt[ed]      to   create   a    salvage"   by    taking   various     actions
    designed to make the AURORA's situation appear worse than it
    actually was.          The complaint maintains that the "AURORA was
    undamaged, completely buoyant, and watertight," and needed only a
    tow, rather than a salvage.                The complaint alleges that when
    Farnsworth    resisted     TNS's     efforts    to    create   a     salvage,   the
    NORTHPOINT intentionally pulled the AURORA onto charted rocks,
    damaging her hull; next ordered Farnsworth to drop anchor in
    dangerous, unprotected waters; and then sent two large men on board
    the AURORA to coerce Farnsworth to sign a contract giving TNS the
    rights to a salvage award for towing the AURORA.                     The complaint
    alleges that Farnsworth "attempted to refuse to sign the salvage
    contract three times," but finally relented "because he was alone
    aboard the vessel with two [TNS] employees, in a remote location,
    without hope of assistance, at a late hour (03:30 A.M.)," and
    because "[t]he employees indicated that they would not leave
    without the signed contract."
    During arbitration, John Mark Brown, one of the "large
    [TNS] employees" who Farnsworth says coerced him to sign the
    salvage    contract,     gave   a     starkly   different      account     of   the
    - 5 -
    encounter.                        Brown recounted that the AURORA was in serious danger.
    The          area             in         which                 the   AURORA   was   stranded,   Brown   said,   was
    "littered with rocks," a danger compounded by the severe weather
    conditions in the area that night.                                               Brown called Farnsworth on his
    cell phone and told him that, in light of those circumstances,
    TNS's services would not be covered under Farnsworth's towing
    policy; instead, Farnsworth would have to sign a "no cure, no pay"
    salvage contract.3                                             Brown said Farnsworth initially agreed to
    accept salvage services during the phone conversation, but later
    balked at the arrangement when Brown boarded the AURORA, and then
    relented when Brown reminded him of his earlier agreement to a
    salvage contract.                                          Brown also vigorously disputed Farnsworth's
    allegations that he and his partner threatened Farnsworth.                                                  Brown
    noted that Farnsworth had earlier spoken to the Coast Guard but
    "never attempted to contact the Coast Guard after we left."
    The contract executed by the parties is a standard form
    "no cure, no pay" marine salvage agreement.                                                Farnsworth wrote by
    hand the following addendum to the form contract: "Aurora was hard
    aground, Tow Boat prevented the Boat from going further aground,
    3
    Under the "no cure, no pay" principle, "a prerequisite
    of a salvage award is that at least some of the property must be
    saved."    Schoenbaum, supra, § 16-1 (noting that the policy
    underlying this principle "is that in 'pure' salvage, the reward
    is made out of the property that is spared from destruction").
    - 6 -
    and towed the boat when the Tide floated it off."4
    The contract contains an arbitration clause:
    Read Carefully -- Arbitration Provision -- In
    the event of any dispute arising out of this
    Contract including any dispute regarding this
    salvage or concerning the reasonableness of
    any fees or charges due hereunder, all parties
    agree to binding arbitration in the United
    States in accordance with the Rules for
    Recreational and Small Commercial Vessel
    Salvage Arbitration of the Society of Maritime
    Arbitrators, Inc.      Arbitrators shall be
    familiar with maritime salvage.      Any award
    hereunder shall include interest, attorneys'
    fees and costs, and arbitration administration
    expenses and shall be final and binding. For
    the purpose of enforcement, the Award may be
    entered for judgment in any court of competent
    jurisdiction.
    Farnsworth's                        buyers'      remorse     set   in        quickly.
    Approximately five days later, on August 3, 2012, Farnsworth sent
    a letter to TNS purporting to rescind the salvage contract,
    demanding that TNS preserve evidence relating to "the prospective
    litigation,"                            and           intimating      that    TNS   had   engaged    in   illegal
    business practices.                                            Farnsworth sent another letter to TNS on
    August 11 advising TNS of his belief that TNS had no salvage claim
    4
    Farnsworth contends that he wanted to "include
    handwritten language on the form to indicate his objection to
    signing it" but that "Brown refused to let [him] write what [he]
    wanted and insisted that the additional language include a
    reference to being 'hard aground.'"
    - 7 -
    and threatening to "fight to preserve [his] family tradition of
    venerable maritime activities."
    He sent yet another letter on August 20, this time to
    TNS's counsel, again demanding the preservation of evidence and
    stating his belief that Dan Carpenter, a TNS representative, had
    engaged in "spoliation of evidence" by selectively editing the
    recordings of Farnsworth's radio conversations on the night of the
    incident.
    On August 24, TNS's counsel wrote to Farnsworth with an
    invoice for payment of $95,546 due under the salvage contract.
    That amount represented TNS's estimate of a fair salvage award
    given the value of the salvaged property and principles of salvage
    law.   Farnsworth did not pay the invoice.
    Approximately a month later, TNS's counsel again wrote
    to Farnsworth, this time demanding arbitration pursuant to the
    arbitration clause of the salvage contract and nominating an
    arbitrator.    Farnsworth replied on October 5, alleging that TNS
    had violated Massachusetts' unfair trade practices statute and yet
    again demanding the preservation of evidence.   Although Farnsworth
    initially made a passing suggestion that the arbitration clause
    was void, he subsequently nominated, through his counsel, an
    arbitrator a little over a month later, in November 2012.    After
    - 8 -
    a period of discussions, the parties agreed that "all issues
    arising out of the events that took place on the evening in
    question must be heard by arbitrators."
    The parties submitted their respective claims to the
    arbitration panel in April 2013.           Farnsworth's statement of his
    counterclaims included allegations that he had signed the salvage
    contract "under duress, . . . alone, without hope of assistance,
    in the middle of the night."
    On May 15, 2013, Farnsworth filed a verified complaint
    in federal court, seeking a declaratory judgment that (1) the
    salvage contract was void because it was procured by duress; (2)
    the parties were not required to arbitrate the dispute; and (3)
    TNS was entitled to compensation only for towage, not for salvage.
    He also sought a preliminary injunction to stop the arbitration
    proceedings.     Farnsworth's purported justification for filing the
    lawsuit after he had already agreed to and commenced arbitration
    was that, after he reviewed recordings of his radio conversations
    produced by TNS, he "believe[d] [TNS] withheld, edited, or deleted
    unfavorable conversations pertaining to towing."
    On May 17, 2013, the district court denied Farnsworth's
    request for a preliminary injunction after a hearing and granted
    TNS's   motion   to   stay   the   case    pending   the   outcome   of   the
    - 9 -
    arbitration proceeding.                                        The arbitration went forward.
    On November 15, 2013, the arbitration panel issued a
    decision rejecting Farnsworth's duress defense and finding that
    the salvage contract was valid.                                         The panel ordered Farnsworth to
    pay $60,306.85 (a $50,000 salvage award plus interest) to TNS and
    dismissed                      Farnsworth's                    counterclaims.5   This   was   a   unanimous
    decision, with Farnsworth's arbitrator joining.
    TNS then filed a motion in the district court to confirm
    the panel's award and dismiss Farnsworth's lawsuit.                                               Farnsworth
    filed a lengthy opposition brief, requesting that the court vacate
    the arbitration award because the arbitrators lacked the authority
    to decide the dispute.                                         In that brief, Farnsworth for the first
    time argued to the court that he had been coerced to agree to the
    arbitration clause specifically, as opposed to the contract as a
    whole.
    The district court granted TNS's motion to confirm the
    arbitration award, rejecting Farnsworth's argument that the court,
    rather than the arbitrators, should have decided the duress as to
    arbitration issue.                                         The court reasoned that Farnsworth had failed
    5
    The arbitration panel did "not award attorneys' fees to
    either side as it consider[ed] that both parties needlessly engaged
    in a war of attrition over what should have been a relatively
    simple salvage dispute."
    - 10 -
    to challenge the validity of the arbitration clause specifically
    in his complaint, as he was required to do in order to obtain court
    review of his duress challenge, and that the arbitration clause in
    the salvage contract was sufficiently broad to encompass the
    dispute about the validity of the contract.6                                              This appeal followed.
    II.
    A.                           Legal Principles
    The Federal Arbitration Act (FAA), 9 U.S.C. § 1 et seq.,
    "reflects the fundamental principle that arbitration is a matter
    of contract."                              Rent-A-Center, W., Inc. v. Jackson, 
    561 U.S. 63
    , 67
    (2010).                    Under the FAA, courts must treat arbitration agreements
    in the same way as other contracts and "enforce them according to
    their terms."                              
    Id. Section 2
    of the Act provides in relevant part
    as follows:
    A   written   provision   in   any   maritime
    transaction or a contract . . . to settle by
    arbitration a controversy thereafter arising
    out of such contract or transaction, . . .
    shall be valid, irrevocable, and enforceable,
    save upon such grounds as exist at law or in
    equity for the revocation of any contract.
    9 U.S.C. § 2.
    The Supreme Court has differentiated between two types
    6              Farnsworth                        does   not    dispute   this   latter   holding   on
    appeal.
    - 11 -
    of challenges to the validity of arbitration agreements: (1)
    challenges to the validity of an entire contract which contains an
    arbitration clause, and (2) challenges to the validity of the
    specific agreement to resolve the dispute through arbitration.
    
    Rent-A-Center, 561 U.S. at 70
    ; Buckeye Check Cashing, Inc. v.
    Cardegna, 
    546 U.S. 440
    , 444 (2006).            In a line of cases beginning
    with Prima Paint Corp. v. Flood & Conklin Manufacturing Co., 
    388 U.S. 395
    (1967), the Court has held that challenges of the first
    type are for the arbitrator to decide, whereas challenges of the
    second type are for the courts to decide, if timely and properly
    made.   See, e.g., 
    Rent-A-Center, 561 U.S. at 70
    -71; Buckeye 
    Check, 546 U.S. at 444-45
    ; Prima 
    Paint, 388 U.S. at 402-04
    ; see also
    Dialysis Access Ctr., LLC v. RMS Lifeline, Inc., 
    638 F.3d 367
    ,
    376-77, 383 (1st Cir. 2011).
    This rule reflects two basic principles of arbitration
    law.    The first is that, because "arbitration is a matter of
    contract[,]   .   .   .   a   party   cannot    be   required   to   submit   to
    arbitration any dispute which he has not agreed so to submit."
    Howsam v. Dean Witter Reynolds, Inc., 
    537 U.S. 79
    , 83 (2002)
    (citation and internal quotation marks omitted).                The second is
    that, under § 2, a written arbitration agreement "is 'valid,
    irrevocable, and enforceable' without mention of the validity of
    - 12 -
    the contract in which it is contained."              
    Rent-A-Center, 561 U.S. at 70
    (quoting 9 U.S.C. § 2).          The first principle means that if
    a party challenges the validity of the arbitration clause itself,
    a court must determine the challenge, "[f]or one must enter into
    the system somewhere."         A.S. Rau, Everything You Really Need to
    Know About "Separability" in Seventeen Simple Propositions, 14 Am.
    Rev. Int'l Arb. 1, 5 (2003).         The second principle means that, if
    a party fails to challenge the validity of the arbitration clause
    itself, the agreement to arbitrate is enforceable and any dispute
    about   the    validity   of   the   contract   as    a    whole   goes   to   the
    arbitrator.     
    Rent-A-Center, 561 U.S. at 70
    -72.
    Another way to frame this analysis is to say, as the
    Supreme Court has, that "an arbitration provision is severable
    from the remainder of the contract."            Buckeye 
    Check, 546 U.S. at 445
    ; see also Dialysis Access 
    Ctr., 638 F.3d at 383
    .                           That
    severability is an issue of federal law.                  As the Supreme Court
    said in Buckeye Check, its cases establish that "as a matter of
    substantive federal arbitration law, an arbitration provision is
    severable from the remainder of the contract" and that, "unless
    the challenge is to the arbitration clause itself, the issue of
    the contract's validity is considered by the arbitrator in the
    first 
    instance." 546 U.S. at 445-46
    .        Or, as the Court put it in
    - 13 -
    Rent-A-Center, "even where . . . the alleged fraud that induced
    the whole contract equally induced the agreement to arbitrate which
    was part of that contract[,] we nonetheless require the basis of
    challenge to be directed specifically to the agreement to arbitrate
    before the court will 
    intervene." 561 U.S. at 71
    .
    It is also important in this analysis to distinguish
    between the issue of whether a contract containing an arbitration
    clause is valid and the issue of whether the contract was ever
    actually formed.                                       See Buckeye 
    Check, 546 U.S. at 444
    n.1.             The
    severability doctrine addresses only the former circumstance.                                              See
    
    Rent-A-Center, 561 U.S. at 70
    n.2.7
    B.                           Application
    This             case             does   implicate   the   severability   doctrine
    because, as the district court correctly held (and Farnsworth does
    not now dispute), the issue here is the contract's validity, not
    its formation.                                   Cf. 28 Williston on Contracts § 71:8 (4th ed.)
    (noting that duress usually renders a contract voidable by the
    7
    Our case does not implicate the latter circumstance. As
    to that circumstance, some courts have held that, if a party argues
    that no contract was consummated, a court must resolve that issue,
    since the party is claiming that there is no agreement as to
    anything at all, arbitration included. See, e.g., Sphere Drake
    Ins. Ltd. v. All Am. Ins. Co., 
    256 F.3d 587
    , 590-91 (7th Cir. 2001)
    (Easterbrook, J.) (collecting cases); see also Buckeye 
    Check, 546 U.S. at 444
    n.1 (collecting cases); 
    Rau, supra, at 14-15
    .
    - 14 -
    victim, rather than void, but that "in the relatively rare case
    where one person physically compels another to give apparent
    assent" there is no acceptance and hence no contract).8                                   Farnsworth
    alleges that he was induced to sign the contract by an improper
    threat on the part of TNS.                                     That duress allegation, if true, would
    make the contract invalid, but it would not mean that no contract
    was ever formed.                                       See SBRMCOA, LLC v. Bayside Resort, Inc., 
    707 F.3d 267
    , 273-74 (3d Cir. 2013); see also Simula, Inc. v. Autoliv,
    Inc., 
    175 F.3d 716
    , 726 (9th Cir. 1999) (holding that duress
    challenge to a contract was for the arbitrator).
    Farnsworth nevertheless argues that the district court
    erred in confirming the arbitration award for two reasons.                                    First,
    he notes that he specifically challenged the arbitration clause in
    the salvage contract in his opposition to TNS's motion to confirm
    the arbitration award, and contends that the district court should
    have resolved that challenge under Prima Paint and its progeny.
    Second, he argues that his allegation of duress in the complaint
    logically went to the validity both of the salvage contract as a
    whole and of the arbitration clause contained within the salvage
    8
    To the extent Farnsworth does make an argument that no
    contract was formed because his signature was the product of
    "physical duress," the argument is entirely cursory and so waived.
    See United States v. Zannino, 
    895 F.2d 1
    , 17 (1st Cir. 1990).
    - 15 -
    contract, and so the district court should have resolved the duress
    issue   even   had   Farnsworth   not   raised   the   validity   of   the
    arbitration clause specifically in his opposition brief.
    The second argument is a nonstarter under Supreme Court
    precedent. Under the Prima Paint line of cases, a party must claim
    that the arbitration clause itself is invalid in order to obtain
    court resolution of the duress issue.        Farnsworth protests that
    this "analytical framework does not facilitate precision when
    analyzing a contractual defense such as physical duress . . . where
    the defense cannot easily be applied to some clauses at the
    exclusion of others." The Supreme Court has unequivocally rejected
    this argument, explaining that even where the claimed basis for
    invalidity of the contract is logically applicable to the entire
    contract, courts "nonetheless require the basis of challenge to be
    directed specifically to the agreement to arbitrate before the
    court will intervene."      
    Rent-A-Center, 561 U.S. at 71
    .         Thus,
    Farnsworth's general claim of duress in his complaint -- even if
    it did, as he asserts, "naturally appl[y] to every clause in the
    Salvage Contract specifically as well as the Salvage Contract as
    a whole" -- was not used to support a direct challenge to the
    arbitration provision and so was not specific enough to permit
    court adjudication of the duress as to arbitration clause claim.
    - 16 -
    This brings us to Farnsworth's challenge to the validity
    of the arbitration clause in his opposition brief to TNS's motion
    to confirm the arbitration award.        On appeal, Farnsworth, relying
    on the general principle that a party has the right to "refine and
    clarify general allegations made in a complaint," argues that the
    district court erred in "ignor[ing]" that challenge.
    That general principle does not help Farnsworth here.
    Farnsworth had ample opportunity to refine and clarify the general
    allegations   made    in   his   complaint   so   as   to    comply     with   the
    severability principle.      He simply failed to avail himself of it.
    Indeed, TNS pointed out in its opposition to Farnsworth's motion
    for a preliminary injunction staying the arbitration proceedings
    that the complaint alleged only a general challenge to the validity
    of the Salvage Contract, not a specific challenge to the validity
    of the arbitration clause.       The district court then held a hearing
    on the motion, and there is no indication in the record that
    Farnsworth sought to amend his complaint or contest TNS's position
    regarding    that    proposition.      Farnsworth's         challenge    to    the
    validity of the arbitration clause itself came only after TNS moved
    to confirm the panel's award, which went against him.                   That was
    - 17 -
    far too late.9
    "Under                 the          FAA,    courts   may   vacate     an    arbitrator's
    decision 'only in very unusual circumstances.'"                                                         Oxford Health
    Plans LLC v. Sutter, 
    133 S. Ct. 2064
    , 2068 (2013) (quoting First
    Options of Chi., Inc. v. Kaplan, 
    514 U.S. 938
    , 942 (1995)).
    Judicial                    review                 of          binding    arbitration     awards    is    necessarily
    limited so as to "'maintain[] arbitration's essential virtue of
    resolving                      disputes                        straightaway.'"      
    Id. (quoting Hall
      Street
    Assocs., L.L.C. v. Mattel, Inc., 
    552 U.S. 576
    , 588 (2008)); see
    also Booth v. Hume Pub., Inc., 
    902 F.2d 925
    , 932 (11th Cir. 1990)
    (characterizing § 9 confirmation proceedings as "summary" and
    noting that the FAA "expresses a presumption that arbitration
    9
    This case is readily distinguishable from Bridge Fund
    Capital Corp. v. Fastbucks Franchise Corp., 
    622 F.3d 996
    (9th Cir.
    2010), the case upon which Farnsworth primarily relies. There,
    the plaintiff filed a lawsuit before arbitration was even
    contemplated, and the defendant, wishing to go to an arbitral forum
    instead, filed a motion to stay the lawsuit pending arbitration.
    The plaintiff contested the validity of the arbitration clause in
    motion papers opposing the defendant's motion. See 
    id. at 999,
    1001-02. The challenge to the arbitration clause thus came before
    arbitration started.
    Because Farnsworth's challenge to the validity of the
    arbitration clause simply came too late, we need not decide the
    extent to which courts may (or must) take into account timely
    allegations outside the complaint in determining whether a given
    dispute is subject to arbitration. Cf. Escobar-Noble v. Luxury
    Hotels Int'l of P.R., Inc., 
    680 F.3d 118
    , 121-22 (1st Cir. 2012)
    (noting that a court's review "centers on the factual allegations
    of the complaint" (citing Dialysis Access 
    Ctr., 638 F.3d at 378
    )).
    - 18 -
    awards will be confirmed").                                          After the arbitration panel renders
    its decision, upon application by one party to a court to confirm
    the award, "the court must grant such an order unless the award is
    vacated, modified, or corrected as prescribed in" 9 U.S.C. § 10
    and § 11.                       See 9 U.S.C. § 9 (emphasis added); accord Hall 
    Street, 552 U.S. at 590
    ("[Sections] 10 and 11 provide exclusive regimes
    for the review provided by the statute . . . ."); FleetBoston Fin.
    Corp. v. Alt, 
    638 F.3d 70
    , 78 n.8 (1st Cir. 2011) (noting that the
    Supreme Court has "made clear that, absent vacating or modifying
    an         award               under               those        provisions,    an    arbitral   award   must   be
    enforced").                           None of the circumstances listed in § 10 or § 11 is
    present                     here,                 and          Farnsworth     does    not   argue     otherwise.
    Accordingly, the district court had no proper basis on which to
    refuse to confirm the arbitration panel's award.                                                    Farnsworth's
    belated attempt to press his duress claim in another forum by
    advancing allegations that he should have made when he sought to
    enjoin the arbitration provided no reason not to confirm.10                                                    Cf.
    10
    Farnsworth argues in his reply brief that his challenge
    to the validity of the arbitration clause should have been resolved
    "regardless of the restrictions in section 10." But the cases he
    cites in support do not support his argument. In Seacoast Motors
    of Salisbury, Inc. v. DaimlerChrysler Motors Corp., 
    271 F.3d 6
    (1st Cir. 2001), we expressly declined to decide whether a party
    could move to vacate under § 10 on non-enumerated grounds. See
    
    id. at 8-9.
    In MCI Telecommunications Corp. v. Exalon Industries,
    Inc., 
    138 F.3d 426
    (1st Cir. 1998), we held only that the
    - 19 -
    
    Rent-A-Center, 561 U.S. at 75-76
    (declining to consider challenge
    to validity of specific arbitration clause that had not been raised
    below).
    III.
    We affirm the judgment of the district court.   Costs are
    awarded against Farnsworth.
    "enforcement provisions of the FAA[] do not come into play unless
    there is a written agreement to arbitrate." 
    Id. at 430.
    There
    was concededly an agreement to arbitrate here; the question is
    whether it was valid.
    - 20 -
    

Document Info

Docket Number: 14-1903

Citation Numbers: 790 F.3d 90

Filed Date: 6/17/2015

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (20)

Dialysis Access Center, LLC v. RMS Lifeline, Inc. , 638 F.3d 367 ( 2011 )

United States v. Ilario M.A. Zannino , 895 F.2d 1 ( 1990 )

Seacoast Motors of Salisbury, Inc. v. Daimlerchrysler ... , 271 F.3d 6 ( 2001 )

Faneuil Advisors, Inc. v. O/S Sea Hawk , 50 F.3d 88 ( 1995 )

MCI Telecommunications Corp. v. Exalon Industries, Inc. , 138 F.3d 426 ( 1998 )

FleetBoston Financial Corp. v. Alt , 638 F.3d 70 ( 2011 )

Bridge Fund Capital Corp. v. Fastbucks Franchise , 622 F.3d 996 ( 2010 )

Sphere Drake Insurance Limited, Formerly Known as Odyssey ... , 256 F.3d 587 ( 2001 )

Conntech Development Company v. University of Connecticut ... , 102 F.3d 677 ( 1996 )

Alan A. Booth, Counter-Defendant v. Hume Publishing, Inc., ... , 902 F.2d 925 ( 1990 )

simula-inc-an-arizona-corporation-simula-automotive-safety-devices , 175 F.3d 716 ( 1999 )

opals-on-ice-lingerie-designs-by-bernadette-inc , 320 F.3d 362 ( 2003 )

david-evanow-phillip-albee-raymond-dunham-v-mv-neptune-a-tug-her , 163 F.3d 1108 ( 1998 )

Prima Paint Corp. v. Flood & Conklin Mfg. Co. , 87 S. Ct. 1801 ( 1967 )

First Options of Chicago, Inc. v. Kaplan , 115 S. Ct. 1920 ( 1995 )

Howsam v. Dean Witter Reynolds, Inc. , 123 S. Ct. 588 ( 2002 )

Buckeye Check Cashing, Inc. v. Cardegna , 126 S. Ct. 1204 ( 2006 )

Hall Street Associates, L. L. C. v. Mattel, Inc. , 128 S. Ct. 1396 ( 2008 )

Rent-A-Center, West, Inc. v. Jackson , 130 S. Ct. 2772 ( 2010 )

Oxford Health Plans LLC v. Sutter , 133 S. Ct. 2064 ( 2013 )

View All Authorities »