Combustion v. Miller Hydro ( 1994 )


Menu:
  • USCA1 Opinion









    January 3, 1994 UNITED STATES COURT OF APPEALS
    FOR THE FIRST CIRCUIT
    ___________________

    No. 93-1266

    COMBUSTION ENGINEERING, INC.

    Plaintiff, Appellant,

    v.

    MILLER HYDRO GROUP, ET AL.,

    Defendants, Appellees.

    ____________________

    No. 93-1267

    COMBUSTION ENGINEERING, INC.,

    Plaintiff, Appellee,

    v.

    MILLER HYDRO GROUP, ET AL,

    Defendants, Appellants.

    ____________________

    ERRATA SHEET

    The opinion of this Court issued on December 30, 1993, is
    amended as follows:

    On page 25, 1st full paragraph, line 5, "When a directed
    verdict was served," should be "after a directed verdict was
    ordered,".































    UNITED STATES COURT OF APPEALS
    FOR THE FIRST CIRCUIT
    ____________________

    No. 93-1266

    COMBUSTION ENGINEERING, INC.,

    Plaintiff, Appellant,

    v.

    MILLER HYDRO GROUP, ET AL.,

    Defendants, Appellees.
    ____________________

    No. 93-1267

    COMBUSTION ENGINEERING, INC.,

    Plaintiff, Appellee,

    v.

    MILLER HYDRO GROUP, ET AL.,

    Defendants, Appellants.
    ____________________

    APPEALS FROM THE UNITED STATES DISTRICT COURT

    FOR THE DISTRICT OF MAINE

    [Hon. Gene Carter, U.S. District Judge]
    ___________________
    ____________________

    Before

    Boudin and Stahl, Circuit Judges,
    ______________

    and Fuste,* District Judge.
    ______________

    ____________________





    ____________________

    *Of the District of Puerto Rico, sitting by designation.

















    John H. Montgomery with whom Gordon F. Grimes, David A. Soley,
    ___________________ ________________ _______________
    Diane S. Lukac, Faith K. Bruins and Bernstein, Shur, Sawyer & Nelson
    ______________ ________________ _________________________________
    were on briefs for plaintiff.
    George S. Isaacson with whom David W. Bertoni and Brann &
    ____________________ __________________ ________
    Isaacson were on briefs for defendant Miller Hydro Group.
    ________
    Roy S. McCandless with whom Robert S. Frank, Mark K. Googins and
    __________________ _______________ _______________
    Verrill & Dana were on brief for party-in-interest appellee Kansallis-
    ______________
    Osake-Pankki.

    ____________________
    December 30, 1993
    _________________






















































    BOUDIN, Circuit Judge. This appeal arises out of a
    _____________

    complex commercial dispute, with overtones of deception,

    relating to the construction of a hydroelectric facility in

    Maine. In the ensuing litigation, neither the builder,

    Combustion Engineering, Inc., nor the owner, Miller Hydro

    Group, succeeded in recovering against the other. Both

    appeal. We affirm the district court.

    I. BACKGROUND

    In the early 1980's, Miller Hydro set about creating a

    hydroelectric facility on the Androscoggin River near Lisbon

    Falls, Maine, to generate electricity. It first negotiated a

    contract with Central Maine Power Company by which the latter

    agreed to purchase a set amount of power from the planned

    facility. Miller Hydro also obtained financing from a

    Finnish bank, Kansallis-Osake-Pankki, and a license to build

    the project from the Federal Energy Regulatory Commission

    ("FERC").

    In May 1986, Miller Hydro entered into a contract--the

    central document at issue in this case--with Combustion

    Engineering for the latter to build the facility on a

    "turnkey" basis. The turnkey contract, by cross-reference,

    provided for a facility including turbines with a capacity of

    7800 cubic feet of water per second.1 Under its contract


    ____________________

    1The 7800 cfs figure, which is important to this case,
    appears in technical specifications annexed to the turnkey
    contract. A shorter and more general "project description,"

    -3-
    -3-















    with Maine Central Power, Miller Hydro was expected to

    provide power capacity of 14 megawatts, and the Miller Hydro

    contract with Combustion Engineering also referred to this

    requirement by cross-reference.

    Subject to these and other specifications, it was

    entirely up to Combustion Engineering to design and build the

    new facility. The turnkey contract contained incentive and

    penalty provisions, one of which lies at the heart of this

    case. The price set for construction was fixed at just under

    $24 million, but the contract provided that Combustion

    Engineering would earn a sliding-scale bonus for efficiency

    to the extent that the facility produced power in excess of

    77,500 megawatt hours per year; a corresponding penalty

    provision reduced Combustion Engineering's fixed price to the

    extent that the facility was less efficient than a specified

    minimum output of 73,500 megawatt hours per year.

    The turnkey contract provided that the bonus or penalty

    would be determined by certain tests that would be performed

    by an independent tester at the completion of construction.

    A protocol specified how the test would be conducted,

    including a requirement that the facility be tested at a

    "total flow of 7800 cfs." It also permitted Miller Hydro to

    require a retest by a different tester if it were



    ____________________

    also annexed, refers to turbine discharge capacity of
    "approximately 8,000" cfs.

    -4-
    -4-















    dissatisfied with the initial test. It appears that if

    Combustion Engineering had built a highly efficient plant of

    the size specified, Miller Hydro might have been liable for a

    bonus payment as large as $850,000.

    What happened instead is that Combustion Engineering

    built a far larger plant with turbines having a maximum flow

    capacity of over 9000 cfs or more and a power capacity of 18

    to 19 megawatts. Miller Hydro claims that this increase in

    size was done deliberately and secretly by Combustion

    Engineering in order to manipulate the bonus provisions of

    the construction contract. Miller Hydro and Kansallis-Osake-

    Pankki both say that they did not learn of the increase until

    it was too late to modify the facility.

    When the facility was tested at a total flow of 9000 or

    more cfs, the tester reported results that equated to a bonus

    of over $8 million. In Miller Hydro's view, Combustion

    Engineering had invested $1 million or so of its own money in

    increasing the facility's size in order to reap a ten-fold

    increase in the incentive bonus. Miller Hydro also objected

    to the test itself and invoked its right to a retest. It

    also refused to state its "final acceptance" of the facility,

    or to make final construction payments. Instead of agreeing

    to a retest, Combustion Engineering promptly brought suit

    against Miller Hydro in district court.





    -5-
    -5-















    In its complaint Combustion Engineering set forth claims

    based on contract, unjust enrichment, and promissory

    estoppel, and it sought to enforce a mechanic's lien against

    the facility. As damages, it demanded an incentive bonus of

    $8.16 million, a final construction payment of $45,364, a

    further payment of $1,236,427 in amounts withheld from prior

    payments, and a claimed early completion bonus of $893,894.

    Kansallis-Osake-Pankki intervened, arguing that Combustion

    Engineering had by contract subordinated its rights under the

    mechanic's lien statute to the bank's mortgage on the

    facility.

    Miller Hydro counterclaimed against Combustion

    Engineering asserting contract, fraud, and racketeering

    claims. Miller Hydro tells us that Central Maine Power has

    not agreed to buy the extra power that the facility can

    generate and that Miller Hydro will or may incur additional

    costs as a result of the facility's enlarged size. In

    particular, it says that it may face penalties from FERC for

    building a facility larger than the license permits, and that

    it may have to reconstruct fish-protection facilities that

    were keyed to the originally planned smaller turbines.

    Because the case presented both legal and equitable

    claims, the district court bifurcated the trial. In the

    first phase, Combustion Engineering tried its contract claims

    to the jury and Miller Hydro tried its contract and fraud



    -6-
    -6-















    counterclaims to the same jury. (Miller Hydro's racketeering

    counterclaim was dismissed by the court in circumstances

    recounted below.) In the second phase the trial judge

    proposed to rule himself on Combustion Engineering's

    equitable claims (unjust enrichment and promissory estoppel)

    and to resolve any outstanding issues concerning the

    mechanic's lien claim, including priority as between

    Combustion Engineering and Kansallis-Osake-Pankki.

    After Combustion Engineering presented its case in chief

    to the jury, the district court entered judgment as a matter

    of law against Combustion Engineering on its contract claims.

    The court held that Combustion Engineering had materially

    breached its contract in testing the facility at a total flow

    in excess of 7800 cfs and in other departures from the test

    protocol. The court found it unnecessary to reach Miller

    Hydro's argument that the refusal of Combustion Engineering

    to agree to a retest was also a breach of contract that

    barred recovery.

    Miller Hydro's own contract and fraud counterclaims

    against Combustion Engineering were submitted to the jury

    together with a special verdict form. On January 23, 1992,

    the jury returned its verdict, finding that Combustion

    Engineering had breached the contract by designing the

    facility for a maximum flow in excess of 7800 cfs, and not in

    accordance with the FERC license. It found the actual



    -7-
    -7-















    maximum flow to be at least 9000 cfs and the power output

    capacity to be 18 megawatts. It also found that Combustion

    Engineering had provided materially false information to

    Miller Hydro. Nevertheless, the jury awarded no damages to

    Miller Hydro either for breach of contract or fraud, finding

    (in response to special verdict questions) that Miller Hydro

    had not proved damages from the breach of contract or the

    misrepresentations.

    On October 6, 1992, the trial judge filed a decision

    denying Combustion Engineering recovery on its equitable

    claims. The court held that under Maine law material

    breaches of contract did not automatically preclude an

    equitable recovery but that the plaintiff's good faith effort

    to perform was a prerequisite; and the court ruled that

    Combustion Engineering "did not seek in good faith to meet

    its obligations under the turnkey contract," given the

    deliberate breaches and misrepresentations found by the jury.

    The jury findings, the court said, were binding on the court

    in deciding the equitable claims.

    On the same day, the trial judge denied a motion by

    Combustion Engineering requesting the court to order a

    retesting of the facility, to appoint a special master, and

    to allow the filing of a supplemental complaint. The court

    ruled that this motion, filed on June 3, 1992, well after the

    jury verdict, came too late. Not only had extensive



    -8-
    -8-















    discovery been conducted but the jury trial had already been

    held and the case was nearing completion. Further delay,

    said the court, would be unfair to both of the other parties.

    Finally, by decision entered on December 22, 1992, the

    trial judge ruled on Combustion Engineering's mechanic's lien

    claim. It rejected the claim on the ground that enforcement

    of such a lien required a valid underlying claim and that

    Combustion Engineering had been found to lack such a valid

    claim. The court granted Kansallis-Osake-Pankki's request to

    discharge the mechanic's lien. It also granted Miller

    Hydro's requests, made in its counterclaims, for declarations

    of breach of contract and misrepresentation by Combustion

    Engineering.

    On January 11, 1993, the court entered final judgment in

    the case. Combustion Engineering has appealed the directed

    verdict against it on its contract claims, and the denial of

    its equitable claims, its mechanics lien claim, and its

    motion to retest. Miller Hydro has appealed the earlier

    dismissal of its racketeering counterclaim. Neither side has

    explicitly sought to disturb the judgment on Miller Hydro's

    contract and fraud counterclaims entered upon the jury

    verdict.

    II. DISCUSSION

    Combustion Engineering advances a series of different

    arguments on appeal, variously involving the directed verdict



    -9-
    -9-















    against it on its contract claims, the dismissal of its

    equitable claims, the district court's refusal to order a

    retest, and the ruling discharging the mechanic's lien. We

    begin with these issues, reserving for the end a discussion

    of Miller Hydro's cross-appeal.

    Combustion Engineering's first, and most extensively

    briefed, point on appeal is its attack on the district

    court's grant of a directed verdict--now renamed judgment as

    a matter of law, Fed. R. Civ. P. 50(a)--dismissing Combustion

    Engineering's contract claims against Miller Hydro. We

    review such a dismissal de novo, asking whether on the
    ________

    evidence presented a reasonable jury could find for the

    plaintiff. Murray v. Ross-Dove Co., 5 F.3d 573, 576 (1st
    ______ ____________

    Cir. 1993). In considering this question, it is assumed that

    issues of credibility are resolved, and inferences from

    evidence drawn, in favor of the non-moving party. Id.
    ___

    At the threshold one might think that the attack on the

    directed verdict is barred by the jury's subsequent findings.

    These findings, on Miller Hydro's counterclaims, establish

    that Combustion Engineering breached the turnkey contract by

    building a plant well in excess of the contracted for

    capacity. Miller Hydro claims that Combustion Engineering

    has forfeited its right to challenge those findings by

    failing to "appeal" from the jury verdict; Combustion

    Engineering replies that appeals are from judgments, not



    -10-
    -10-















    findings, and that it has appealed the judgment rejecting its

    contract claims.

    We think that in this case the jury findings do not

    settle the propriety of the directed verdict. The jury

    verdict might insulate the directed verdict if the jury in

    deciding the counterclaims had independently reached the same
    _____________

    conclusion on the same issue. But here the trial judge, in

    submitting the counterclaims to the jury, instructed the jury

    that as a matter of law "the turnkey contract required the

    construction of a hydroelectric facility . . . . designed to

    accommodate a maximum hydraulic flow of 7800 cubic feet per

    second."2

    A central theme of Combustion Engineering's argument on

    appeal is that the contract did not make 7800 cfs a maximum

    figure. We think it would be odd to uphold the directed

    verdict on the ground that the jury found the same thing as

    the district judge (namely, that the 7800 cfs figure was a

    ceiling) when in fact the district judge told it to do so.

    This is not to say that the district court erred in so

    instructing the jury--on the contrary, we agree with its

    reading of the contract--but rather to explain why we think


    ____________________

    2The court also told the jury that the court itself had
    rejected Combustion Engineering's contract claims because the
    court had found (in directing a verdict) a material breach of
    contract by Combustion Engineering, namely, its failure to
    show compliance "with the testing requirement of testing at a
    total flow of 7800 cfs" as required by the protocol annexed
    to the turnkey contract.

    -11-
    -11-















    that the directed verdict decision by the district court is

    not insulated by the jury verdict and should be reviewed on

    the merits.

    Turning to the merits, the first issue before us in

    relation to the directed verdict is whether the testing

    protocol required that the final acceptance test be conducted

    at a maximum of 7800 cfs. Although formally this is a

    separate issue from whether the turnkey contract made 7800

    cfs the maximum size for the facility, we think that the

    reality here is that the two issues are interrelated. One

    might be able to read the 7800 cfs figure differently in the

    test protocol and the contract design specifications, but

    would be unlikely to do so in this case. Combustion

    Engineering treats the two issues together, and so do we.

    The district court construed the turnkey contract and

    ruled as a matter of law that the 7800 cfs figure was a

    target and ceiling figure for both construction and testing

    of the facility. As noted above, the 7800 cfs figure does

    appear in annexed technical specifications although

    apparently not in the body of the contract itself. This

    cross-reference might not be conclusive if it stood alone,

    but it does not stand alone. Two other pieces of evidence

    intrinsic to the contract--the FERC license and the test
    _________

    protocol--support the view that the 7800 cfs figure was both

    target and ceiling for the project.



    -12-
    -12-















    First, the FERC license was incorporated in the turnkey

    contract by cross reference, the contractor promising to

    construct the facility in accordance with the license. The

    FERC license refers to the project as having turbines with a

    total capacity of 14 megawatts, a figure that the turnkey

    contract treats as a counterpart to the 7800 cfs figure. As

    already noted, the turnkey contract refers to 14 megawatts

    and the annexed technical specifications to 7800 cfs.3

    Second, the test protocol annexed to the turnkey project

    clearly provided for testing at "a total flow of 7800 cfs."

    One can imagine a contract providing for a facility with a

    large capacity while limiting the test to some lower figure

    (perhaps the expected normal flow). Here, however, the

    reference to the same figure in the technical specifications

    and in the test protocol strongly suggests as a matter of

    common sense that the facility was to be built and tested at

    that figure.

    Combustion Engineering's brief argues that the 7800 cfs

    figure was actually intended as a minimum, urging that the
    _______

    figure be read as akin to other figures in the contract that

    are allegedly performance minima. Combustion Engineering



    ____________________

    3There was also evidence that the license application
    initially reflected a flow of 6800 cfs and that approval of
    FERC to increase this to 7800 was obtained in 1985. However,
    there is some doubt that this evidence could be described as
    intrinsic, at least in the form submitted, and we do not rely
    upon it to sustain the directed verdict.

    -13-
    -13-















    also suggests that in any event the 7800 figure was only a

    rough approximation. It also argues that the parties

    contemplated modifications in whatever figure was chosen.

    Finally, it claims that Miller Hydro learned of the increase

    and waived its objection. Some of these arguments are in

    tension with others, and none is persuasive.

    There may be figures in the turnkey contract that are

    performance minima. But certainly the normal reading of a

    performance or capacity figure in a license is that, like the
    _______

    speed limit sign on a highway, it is intended as a maximum.

    Here, the contract said that the facility was to be built in

    accordance with the license, and the license provided for a

    14 megawatt facility, a figure that the contract's technical

    specifications equated to a facility having a capacity of

    7800 cfs. Thus, we think that 7800 cfs was a target and

    ceiling and not a minimum.

    We agree with Combustion Engineering's claim that, even

    treating 7800 cfs as a ceiling, there may be room for minor

    deviations; but an increase to over 9000 cfs--there was some

    testimony that 9600 cfs or more was the real capacity--is

    hardly a minor change. Correspondingly, the megawatt

    capacity increased from 14 megawatts to 18 megawatts or more,

    hardly a minor adjustment. The engineer who assisted

    Combustion Engineering testified that a change from 7800 cfs

    to 9000 cfs or more would be material.



    -14-
    -14-















    There were provisions for modification of the turnkey

    contract by agreement, but Combustion Engineering has not

    proved any agreement by Miller Hydro permitting the

    contractor to exceed the 7800 cfs figure. As for the claim

    of waiver or estoppel, that issue was submitted to the jury.

    The jury's verdict that Combustion Engineering breached the

    contract by constructing a facility in excess of 7800 cfs

    appears implicitly to reject the waiver or estoppel defense.

    This is quite understandable since there is no clear evidence

    that Miller Hydro knew of the change in capacity until it was

    too late to alter course, and substantial evidence indicates

    that Combustion Engineering sought to conceal its deviation.

    Combustion Engineering argues that at the very least the

    contract was ambiguous, so that extrinsic evidence should

    have been admitted and the issue submitted to a jury. Some

    jurisdictions follow the traditional binary rule that an

    integrated contract is either clear or ambiguous and, in the

    former case, extrinsic evidence is excluded; other states

    follow the so-called modern approach, allowing extrinsic

    evidence to "interpret" even a seemingly unambiguous

    document. See A. Farnsworth, Contracts 7.12, at 521-23
    ___ _________

    (1990). But we need not decide in this case precisely how

    Maine resolves the problem, because Combustion Engineering

    has not properly pointed to any extrinsic evidence that could

    alter the result.



    -15-
    -15-















    We say "properly" pointed because Combustion

    Engineering's brief does have an entire page of capsule

    summaries of documents, events or testimony purporting to

    comprise relevant extrinsic evidence. In this page of

    summaries, not a single reference appears to a transcript

    page or an exhibit number or to an appendix or addendum page.

    There is some similar material in the fact statement of the

    brief, with record or appendix references, and we have sought

    to match up the summaries with relevant portions of the fact

    statement. Having done so as best we can, our conclusion is

    that this "evidence," even if considered, does not create

    ambiguities warranting jury resolution.

    To take Combustion Engineering's first capsule summary

    as an example, the brief says that an engineer working for

    both Combustion Engineering and Miller Hydro told the latter

    that "the Turbine Specifications were minimums that did not

    limit Combustion Engineering's right to select appropriate

    equipment." The engineer's actual letter, however, merely

    affirms the contractor's right to design the generator and

    electrical equipment and says that "the overall performance

    expected of the equipment was outlined in the minimum

    criteria . . . ." Nothing in the quotation associates the

    general reference to minimum criteria with the 7800 cfs

    figure. The balance of the evidence summarized by Combustion

    Engineering is even less persuasive.



    -16-
    -16-















    Later in its brief, Combustion Engineering makes a quite

    different argument. It says that even assuming that a

    violation of the test protocol occurred, this should not

    debar Combustion Engineering from all recovery under the

    contract. It argues that testing was directed to fixing the

    efficiency bonus or penalty, and that proper testing should

    not be found to be a "condition precedent" to recovery of

    other amounts, such as the final payment due under the

    contract or sums retained temporarily from prior payments.

    The company also invokes the notion that "substantial

    performance" is sufficient to allowit to sue on the contract.

    It may be a close question whether standing alone the

    breach of a testing protocol--among other breaches,

    Combustion Engineering tested the facility at a flow far

    greater than 7800 cfs--should preclude recovery of the

    balance of the contract price as well as the possible bonus.

    If this were the posture of the case, we would be obliged to

    engage in a close reading of the test protocol and its

    relation to the rest of the contract. One can certainly

    conceive of a case in which the contractor failed to fulfil a

    requirement needed to earn a bonus payment but would not, in

    ordinary circumstances, be deemed to lose the right to

    collect the basic price for work done.

    Here, however, Combustion Engineering violated not only

    the test protocol but the contract specifications by building



    -17-
    -17-















    an oversized facility, and the breach was substantial and

    deliberate. The jury verdict alone confirms the substantial

    breach, and its deliberate character is patent from

    Combustion Engineering's misrepresentations and efforts at

    concealment. Even if the violation of the testing protocol

    did not preclude all further recovery under the contract,

    assuredly the substantial and deliberate breach did so and

    precludes a contractual claim based on substantial

    performance.

    This premise of a substantial and deliberate breach also

    disposes of Combustion Engineering's equitable claims for

    unjust enrichment and promissory estoppel. We agree with the

    district court that, even if such claims may be permitted

    under Maine law where contractual claims have been lost,

    Maine law appears to make good faith a condition of such

    equitably based recoveries.4 Here Combustion Engineering's

    good faith is disproved by the jury verdicts. The verdicts





    ____________________

    4The most recent Maine decision to which we are cited,
    says that an equitable recovery may be allowed when the
    builder provided materials or services "in an honest
    endeavor" to perform the contract. Loyal Erectors v.
    _______________
    Hamilton & Son, Inc., 312 A.2d 748, 755-56 (Me. 1973);
    ______________________
    Accord, Levine v. Reynolds, 54 A.2d 514, 517 (Me. 1947).
    ______ ______ ________
    Even if Maine law is more fluid, allowing the judge some
    flexibility in weighing the equities, see A. Horton & P.
    McGehee, Maine Civil Remedies, 11-17 (2d ed. 1992), we are
    ____________________
    certain from its statements here that the district court
    would exercise that discretion to disallow recovery, and we
    would have no difficulty sustaining that decision.

    -18-
    -18-















    were binding on the court, see Dairy Queen, Inc. v. Wood, 369
    ___ ________________ ____

    U.S. 469 (1962), and are amply supported by the evidence.

    This outcome becomes even more compelling when one

    appreciates that the deliberate and substantial breach placed

    Miller Hydro at risk of significant harm. There may be cases

    where building "more" than one promised is a benefit to the

    owner; but that is hardly assured in the case of a federally

    licensed dam. Indeed, it may be that Miller Hydro itself

    will ultimately suffer because of violation of its federal

    license terms or because the fish protection facilities will

    have to be rebuilt. Nor is it clear that it has gained by

    obtaining extra power that it says it can neither sell to

    CentralMaine Power nor economically wheel to other customers.

    Miller Hydro alludes to these possibilities without

    providing much supporting detail. We have no way of knowing

    how much substance there is to them, nor whether short term

    disadvantages may be offset in part, or even outweighed, by

    the long-term benefits of a larger facility with a greater

    capacity to produce power. What we do know is that

    Combustion Engineering was not entitled to create such risks

    for Miller Hydro by secretly deviating--substantially and

    deliberately--from the terms of the contract. That one

    behaving in this fashion now forfeits the balance due under

    the contract does not seem in the least unfair.





    -19-
    -19-















    Combustion Engineering has two remaining arguments that

    require little discussion. It first argues that the court

    should have granted its motion for a retest of the facility

    in accordance with the protocol. This demand was made not

    only after Combustion Engineering had turned down Miller

    Hydro's own request for retest, but after the directed

    verdict and the jury verdict in this case. The district

    court's refusal to grant this highly belated, if not

    impudent, request for equitable relief was well within its

    discretion.

    The other argument is Combustion Engineering's attack on

    the district court's refusal to grant it relief under the

    Maine mechanic's lien statute. It may be an

    oversimplification to say that the statute creates only an

    additional remedy and not a new right; but it is clear that

    under Maine law, as in many jurisdictions, the mechanic's

    lien depends on the claimant having a valid underlying claim

    for monetary recovery based on the construction performed.

    Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co., 116
    ________________________________ ____________________

    A.2d 664, 666 (Me. 1955). Combustion Engineering has no such

    valid underlying claim in this case, so the district court

    properly discharged the mechanic's lien.

    There remains Miller Hydro's own appeal. As already

    noted, the jury found (in deciding Miller Hydro's

    counterclaims) that Combustion Engineering had breached its



    -20-
    -20-















    contract and engaged in misrepresentation but that the proof

    did not support a finding of damages from the breach or

    falsehoods. Miller Hydro does not challenge these verdicts,

    which limited its judgment on these claims to declaratory

    relief. Rather, it argues that the district court erred by

    dismissing its remaining racketeering counterclaim and

    declining to submit that claim to the jury.

    The remaining counterclaim comprised three related

    counts under the Racketeer Influenced and Corrupt

    Organizations Act, 18 U.S.C. 1961, et seq. ("RICO"). In
    _______

    substance, these RICO counts, asserted in a pleadings

    amendment, charged Combustion Engineering and various of its

    employees with a fraudulent scheme to obtain inflated bonuses

    from one or more power-plant construction projects. Various

    uses of the mails or telephone system in aid of the

    fraudulent scheme were alleged. For the RICO violations,

    Miller Hydro sought damages, injunctive relief, and

    attorney's fees.

    After the RICO counts were added, Combustion Engineering

    on April 16, 1991, moved to dismiss the counts under Fed. R.

    Civ. P. 12(b)(6) for failure to state a claim; it asserted as

    grounds for dismissal various somewhat technical defects in

    the RICO counterclaims (e.g., that a separate "enterprise"
    ____

    had not been sufficiently alleged). On October 4, 1991, the

    district court granted the motion to dismiss but on a ground



    -21-
    -21-















    only barely suggested by a footnote in the motion, namely,

    that an earlier, October 19, 1990, discovery order by the

    magistrate judge had found a failure of Miller Hydro to make

    out a prima facie case of fraud by Combustion Engineering.
    _____ _____

    The magistrate judge's order had been entered in

    resolving discovery disputes including Miller Hydro's claim

    that Combustion Engineering had lost the protection of the

    attorney client privilege as to certain materials because its

    attorney was participating in a fraudulent scheme.

    Interpreting Maine law governing the privilege, see Me. R.
    ___

    Evid. 502(d)(1), the magistrate judge found that Miller

    Hydro's evidence thus far made out the necessary prima facie
    _____ _____

    case on "the first three elements of fraud [knowing or

    reckless misrepresentation of a material fact] but not the

    final two [purpose and effect of inducing reliance]." Absent

    sufficient proof of each element needed to prove fraud, the

    magistrate judge found no loss of the privilege and refused

    to order protection of the documents in issue.

    On appeal, Miller Hydro complains sharply that in

    resolving the Rule 12(b)(6) motion the district judge had no

    right to rely on materials beyond the pleadings without

    giving Miller Hydro notice and an opportunity to counter the

    extra-pleading material. Although Rule 12(b)(6) does require

    "a reasonable opportunity" to counter material outside the

    pleadings, the magistrate judge's finding of no prima facie
    _____ _____



    -22-
    -22-















    case was cited in Combustion Engineering's motion to dismiss

    and arguably Miller Hydro had the necessary opportunity to

    counter it. This court has looked through form to substance

    in applying the rule's requirement. See Moody v. Town of
    ___ _____ _______

    Weymouth, 805 F.2d 30, 31 (1st Cir. 1986).
    ________

    What is more troublesome is Miller Hydro's further,

    substantive argument that the magistrate judge's finding

    cannot support the district court's order dismissing the RICO

    claims. All that the finding showed, says Miller Hydro, is

    that in October 1990, while discovery was still underway, it

    lacked enough evidence to show that all elements of fraud had

    been made out to the extent needed to vitiate the attorney

    client privilege.5 Even assuming that the standards are the

    same for proving fraud in relation to the attorney-client

    privilege issue and in relation to a RICO claim, it does not

    follow that evidence was equally lacking in October 1991

    after further discovery had been conducted.

    The district court did not discuss any of the evidence

    in its brief order of dismissal in October 1991. Further,

    the court actually allowed the Maine fraud claims made by

    Miller Hydro to go the jury. Yet common alleged acts of

    fraud underlay both the Maine fraud and the RICO fraud



    ____________________

    5The standard of proof is rather elusive since a prima
    _____
    facie case does not require definitive proof; yet the fraud
    _____
    claim itself has to be proved under Maine law by clear and
    convincing evidence.

    -23-
    -23-















    counts. Indeed, Miller Hydro argues that RICO fraud is

    easier to prove than fraud under Maine law because the latter

    requires that each element be proved by clear and convincing

    evidence. The district court's seeming concession that there

    was enough evidence of fraud under Maine law adds to doubts

    whether we could sustain the court's dismissal of the RICO

    counts based on the magistrate judge's finding.

    We need not resolve the matter, however, because the

    jury's verdict taken together with other circumstances

    persuades us that Miller Hydro was not prejudiced by the

    dismissal of the RICO claims. The jury found that no damages

    had been proved by Miller Hydro on the two counterclaims that

    did reach the jury even though the jury found both breach of

    contract by Combustion Engineering and acts amounting to

    fraud. The central damage claims argued to the jury by

    Miller Hydro--e.g., delay costs, prospective rebuilding of
    ____

    the fishways--are common to the Maine fraud and RICO fraud

    claims, and the jury finding of no damages on the former

    suggests the same outcome would have resulted on the latter.

    Miller Hydro argues, although without much detail, that

    its damage claims based on breach of contract were somewhat

    narrower than those covered by fraud. Its theory is that

    contract damages must be within the contemplation of the

    parties but fraud damages need not be, and we will assume

    that this is so. But Miller Hydro does not suggest



    -24-
    -24-















    (attorney's fees aside) that its actual damages for fraud

    were narrower under Maine law than under RICO and, given the

    common acts of alleged fraud, it is hard to see why the

    damage claims under RICO would be broader. Instead, Miller

    Hydro simply asserts that the fraud damage claims under Maine

    law required clear and convincing evidence while those under

    RICO required merely a preponderance of the evidence.

    It is by no means clear that the jury was told that the

    fraud damages under Maine law had to be proved by clear and

    convincing evidence.6 But even if the jury had been

    explicitly told clear and convincing evidence was required in

    computing damages, we would still find no showing of

    prejudice in this case. Perhaps where the issue of damages

    is shown to be very close--turning, for instance, on a clash

    of expert opinions--the asserted difference in burden of

    proof between a common law fraud and a civil RICO claim could

    be decisive. See Wilcox v. First Interstate Bank of Oregon,
    ___ ______ _______________________________

    815 F.2d 522, 531 (9th Cir. 1987). But the burden of showing





    ____________________

    6The district court's generally lucid instructions did
    tell the jury that the elements of fraud under Maine law had
    to be established by clear and convincing evidence. But when
    the court came to instructing on the computation of damages,
    where it discussed contract and fraud damages together, it
    did not say that any of these determinations had to be made
    _____
    by clear and convincing evidence. Indeed, the jury could
    easily have inferred the contrary because the court went on
    to say that an award of exemplary damages did require a
    finding of malice by clear and convincing evidence.

    -25-
    -25-















    prejudice is upon the party claiming error, and we think that

    here that burden has not been met.

    Miller Hydro's main efforts at trial appear to have been

    devoted to establishing Combustion Engineering's breach of

    contract and fraud, findings very important in shoring up

    Miller Hydro's own defense to Combustion Engineering's claims

    against it. When a directed verdict was served, after a

    directed verdict was ordered, Miller Hydro chose to present

    no case in chief of its own in support of its own

    counterclaims. Instead, Miller Hydro relied upon the

    evidence that Combustion Engineering had offered in its own

    case in chief before the directed verdict was granted. It is

    not surprising that, absent an affirmative independent

    showing as to how Miller Hydro would suffer from the larger

    facility, the jury awarded no damages. Miller Hydro's

    decision to stop while ahead was probably good tactics, but

    it does not suggest that an adjustment in the burden of proof

    would have altered the result.

    More important, there is nothing in Miller Hydro's reply

    brief--which offers the burden of proof distinction as the

    basis for presuming prejudice--that discusses the evidence of

    damages in any detail or provides any basis for believing

    that a different standard of proof could alter the result in

    this case. In the present circumstances, including the

    nature of the jury instructions and the seemingly limited



    -26-
    -26-















    weight placed on damages at trial, we think that the

    theoretical possibility of a different result is not enough.

    And absent a showing that would suggest a real possibility of

    a different result, it is time for this already lengthy

    litigation to come to an end.

    Having considered consequential damages, it remains to

    address two other possible differences in remedy. First, the

    RICO statute allows attorney's fees to a person "injured in

    his business or property" by a RICO violation. 18 U.S.C.

    1964(c). It is far from clear, however, that such attorney's

    fees would be available where, as here, the jury finds that

    no actual injury has been proved. Again, given the absence

    of some showing by Miller Hydro that a jury could award

    damages limited solely to attorney's fees, we think that no

    showing of prejudice has been made.

    Second, Miller Hydro argues that under RICO it would

    have been entitled to injunctive relief that remains of

    continuing importance to it. Specifically, it asserts that

    Combustion Engineering, having had its belated motion for a

    retest denied by the district court, is now trying (how is

    not explained) to pursue its demand for a retest though other

    means. This conduct, says Miller Hydro, constitutes

    continuing RICO fraud that the district court would have been

    asked to enjoin if the RICO claims had not been dismissed.





    -27-
    -27-















    See 18 U.S.C. 1964(a) (injunctive remedy available under
    ___

    RICO).

    We think this is too thin a reed on which to hang a

    remand and further litigation under RICO. Taken together,

    the district court's dismissal of Combustion Engineering's

    contract and equitable claims and the court's denial of the

    belated motion for a retest establish definitively that

    Combustion Engineering has no further claim for a retest or

    any other remedy under the turnkey contract. If Combustion

    Engineering were to pursue any such claim through an

    independent law suit, we think that sanctions for baseless

    litigation might well be available.

    III. CONCLUSION

    This case could plausibly have been settled at the

    outset by, for example, payment of any remaining amounts due

    under the contract but without any bonus payment. Now, after

    wearisome and no doubt expensive litigation over an imperfect

    contract and imperfect conduct, neither side has gained what

    it sought at the outset. This may itself be a form of

    justice, but it could have been achieved at a lower price.

    Affirmed. No costs.
    ________











    -28-
    -28-