Perdoni Brothers Inc v. Concrete Sytems Inc ( 1994 )


Menu:
  • USCA1 Opinion












    UNITED STATES COURT OF APPEALS
    FOR THE FIRST CIRCUIT

    ____________________
    No. 93-2178

    PERDONI BROTHERS, INC.,

    Plaintiff, Appellee,

    v.

    CONCRETE SYSTEMS, INC.,

    Defendant, Appellant.


    ____________________

    APPEAL FROM THE UNITED STATES DISTRICT COURT

    FOR THE DISTRICT OF MASSACHUSETTS

    [Joyce L. Alexander, U.S. Magistrate Judge]
    _____________________


    ____________________

    Before

    Breyer,* Chief Judge,
    ___________

    Campbell, Senior Circuit Judge,
    ____________________

    and Cyr, Circuit Judge.
    _____________


    ____________________

    John M. Lovely, with whom Daniel F. Cashman and Gelerman &
    _______________ ___________________ ___________
    Cashman were on brief for appellant.
    _______
    Valeriano Diviacchi, with whom Diviacchi Law Office was on brief
    ___________________ ____________________
    for appellee.


    ____________________

    September 2, 1994

    ____________________


    ____________________

    *Chief Judge Stephen Breyer heard oral argument in this matter,
    but did not participate in the drafting or the issuance of the panel
    opinion. The remaining two panelists therefore issue this opinion
    pursuant to 28 U.S.C. 46(d).














    CYR, Circuit Judge. Defendant-appellant Concrete
    CYR, Circuit Judge
    ______________

    Systems, Inc. (CSI), a New Hampshire producer of pre-cast con-

    crete products, contracted in 1985 with plaintiff-appellee

    Perdoni Brothers, Inc. (Perdoni), a Massachusetts-based construc-

    tion firm, to manufacture and deliver 121 custom-designed man-

    holes, at a total contract price of $51,670.47, for installation

    in a new sewer system in the Town of Ashland, Massachusetts. CSI

    contends that the district court committed reversible error in

    denying its post-verdict motion for judgment as a matter of law.

    See Fed. R. Civ. P. 50. For the reasons hereinafter discussed,
    ___

    we affirm the district court judgment.



    I
    I

    BACKGROUND
    BACKGROUND
    __________


    The first five manholes were delivered to the Perdoni

    job site by CSI on July 2, 1985. The remaining 116 manholes were

    delivered intermittently in twenty-six shipments extending over

    the next thirteen months and invoiced by individual shipment.

    Dissatisfied with the CSI manholes (which leaked and

    had to be patched),1 Perdoni brought this diversity action in

    ____________________

    1Sewer line manholes must be watertight. A common point of
    leakage is the area where the sewer lines enter the manhole
    structure. Precise casting, as well as installation of rubber
    "boots" to ensure a tight fit between the wall of the structure
    and the sewer line itself, is necessary to ensure the integrity
    of the manhole. At trial, Perdoni adduced evidence that CSI had
    used a defective hole former to cast the manholes for the Ashland
    project. Consequently, the pipe openings in the sides of the
    manholes were misshapen and the seals between the boot and rim of
    the openings were not watertight.

    2














    federal district court on April 25, 1990, demanding $134,000 in

    compensatory damages for breach of the implied warranties of

    merchantability and fitness for a particular purpose (implied

    warranty claims), see Mass. Gen. L. ch. 106 2-314, 2-315, and
    ___

    additional damages based on a deceptive trade practices claim

    under Mass. Gen. L. ch. 93A ("Chapter 93A"). CSI counterclaimed

    for $18,561 allegedly due from Perdoni on the Ashland project and

    another contract.

    Trial was held before a magistrate judge, with the

    consent of the parties. See 28 U.S.C. 636(c). The implied
    ___

    warranty claims were tried to a jury, while the Chapter 93A claim

    was tried to the presiding magistrate judge. It was not until

    after the close of all the evidence that CSI first moved for

    judgment as a matter of law on the implied warranty claims

    relating to 108 of the 121 manholes. The uncontroverted evidence

    demonstrated that only 13 manholes had been delivered by CSI

    within four years of the commencement of the present action. CSI

    accordingly contended that Perdoni's implied warranty claims

    relating to the other 108 manholes were time-barred under Mass.

    Gen. L. ch. 106 2-725(1) (prescribing four-year limitation on

    Uniform Commercial Code warranty actions); id. 2-725(2) (action
    ___

    for breach of warranty under UCC accrues on "tender of delivery"

    of goods). The magistrate judge denied CSI's motion for judgment

    as a matter of law.

    Thereafter, the magistrate judge convened a charge

    conference to consider the jury instructions, including the


    3














    instruction on the statute-of-limitations defense. Neither party

    requested an instruction on the law governing the severability-
    ___

    entirety issue. Although Perdoni unsuccessfully sought an

    instruction that the contract should be considered an entirety,

    CSI made no corresponding request for an instruction that the

    contract be considered severable. Consequently, the magistrate

    judge simply instructed the jury that CSI had the burden of

    proving that the action was time-barred, and that the four-year

    limitation period ran from the "time of delivery." Although both

    parties argued the severability-entirety issue, the court made no

    explicit reference to it and neither party objected to the jury

    instruction as given.2 The jury found in favor of Perdoni-

    ____________________

    2The instruction relating to the statute of limitations
    follows:

    [T]here is also an issue arising from [CSI's]
    asserted defense based on . . . the statute
    of limitations.
    This is simply a provision that a suit
    be commenced on certain types of claims with-
    in a prescribed period of time, otherwise,
    the suit is barred or precluded. For a
    breach of warranty claim, the applicable
    statute of limitations for an action on a
    contract for the sale of goods is four years.
    That means that a plaintiff has four
    years to bring a suit for a breach of war-
    ranty. The time limit placed upon Perdoni
    ___ ____ _____ ______ ____ _______
    began to run at the time of delivery of the
    _____ __ ___ __ ___ ____ __ ________ __ ___
    manholes, regardless of whether Perdoni knew
    _________ __________ __ _______ _______ ____
    of the breach. Thus within four years of the
    __ ___ ______
    time which Perdoni received the manholes, it
    must have commenced this lawsuit.
    * * *
    It is [CSI's] burden to show that Perd-
    oni has not complied with the statute of
    limitations, thus [CSI] has the burden of
    establishing that Perdoni filed a suit more
    than four years after the delivery of the

    4














    for $48,961, and in favor of CSI for $18,561 on its counter-

    claim. CSI then renewed its Rule 50 motion for judgment as a

    matter of law and, alternatively, moved for a new trial under

    Fed. R. Civ. P. 59. The magistrate judge did not address the

    merits of the CSI motion, however, ruling instead that CSI had

    waived its severability claim, both by failing to object to the

    jury instruction and by failing to raise the severability argu-

    ment in its pre-verdict Rule 50 motion.3 Nonetheless, the

    ____________________

    manholes, and if Perdoni did not commence the
    suit within the four-year period, Perdoni may
    not recover on its warranty theories.

    Trial Tr. at 168 (April 16, 1993) (emphasis added).

    3The magistrate judge noted that:

    This Court instructed [the jury] that,
    as an affirmative defense, CSI had the burden
    of proving . . . that Perdoni filed the suit
    more than four years after delivery of the
    manholes. CSI did not object to this
    instruction. Nor did CSI submit an
    instruction based on the law governing divis-
    ibility of performance, entire contracts,
    separate contracts and installment contracts.
    CSI was apparently content to treat the
    question of what constitutes the time of
    delivery as an issue of fact. CSI did move
    ___
    for a directed verdict on this issue, but,
    again, this motion was predicated on the
    evidence being clear as to the tender of
    delivery and included no argument as to the
    ________ __ ________ __ __ ___
    law governing divisibility of performance,
    ___ _________ ____________ __ ___________
    entire contracts, separate contracts and
    ______ __________ ________ _________ ___
    installment contracts. CSI's pretrial
    ___________ _________
    memorandum was no more edifying on this
    point. . . . This court finds it late in the
    day to be raising the legal issue, and deems
    the issue waived.

    Perdoni Bros., Inc. v. Concrete Sys., Inc., Civ. 90-11046-WF,
    ____________________ ____________________
    Memorandum Order at 7-8 (D. Mass. August 27, 1993) (emphasis
    added).

    5














    magistrate judge, sitting as trier of fact, found Perdoni's

    Chapter 93A claim time-barred as it pertained to 108 of the 121

    manholes. CSI appealed the denial of its post-verdict motion for

    judgment as a matter of law or for a new trial on the implied

    warranty claims. See Fed. R. Civ. P. 50(b), 59. CSI's primary
    ___

    appellate target is the district court's waiver ruling on the

    severability issue.



    II
    II

    DISCUSSION
    DISCUSSION
    __________


    Leaving aside CSI's failure to object to the jury

    instruction on the statute-of-limitations defense, the district

    court waiver ruling is fully supported by CSI's failure to raise

    the severability argument in its pre-verdict motion for judgment

    as a matter of law. The law is crystal clear that a "party may

    not base its motion for a judgment n.o.v. on a ground that was

    not argued in its motion for directed verdict." Sweeney v.
    _______

    Westvaco Co., 926 F.2d 29, 37 (1st Cir.) (citing Systemized of
    _____________ _____________

    New England, Inc. v. SCM, Inc., 732 F.2d 1030, 1035 (1st Cir.
    __________________ _________

    1984)), cert. denied, 112 S. Ct. 274 (1991); see also 9 Charles
    _____ ______ ___ ____

    A. Wright & Arthur R. Miller, Federal Practice & Procedure 2537
    ____________________________

    (1971) ("Since it is technically only a renewal of the motion . .

    . made at the close of evidence, [a post-verdict Rule 50 motion]

    cannot assert a ground that was not included in the motion for a

    directed verdict."); 5A James W. Moore, Moore's Federal Practice
    ________________________

    50.08 (2d ed. 1994) (same). Sweeping invocations of conclusory

    6














    theories or abstract principles will not suffice: "The motion

    must . . . be made with sufficient specificity to allow the

    district court to understand precisely why the evidence is

    insufficient." Wells Real Estate, Inc. v. Greater Lowell Bd. of
    _______________________ _____________________

    Realtors, 850 F.2d 803, 810 (1st Cir.), cert. denied, 488 U.S.
    ________ _____ ______

    955 (1988); Pstragowski v. Metropolitan Life Ins. Co., 553 F.2d
    ___________ __________________________

    1, 3 (1st Cir. 1977) (where Rule 50 motion was silent as to the

    legal theory that plaintiff was obliged to establish malice on

    the part of the defendant, there was no basis for an appellate

    challenge to the sufficiency of the evidence on the element of

    malice). Ultimately, of course, "[a]ppellate review may be

    obtained only on the specific ground stated in the motion for

    directed verdict." Wells Real Estate, 850 F.2d at 810; Pstragows-
    _________________ __________

    ki, 553 F.2d at 3 (same).
    __

    The pre-verdict motion for judgment as a matter of law,

    see Fed. R. Civ. P. 50(a),(b), stressed the undisputed fact that
    ___

    108 manholes were delivered more than four years prior to suit,

    but presented no authority or argumentation whatever that the

    contract should be considered severable (i.e., that Massachusetts
    ____

    law permitted or required that the individual shipments of

    manholes receive separate treatment for statute-of-limitation

    purposes, rather than as an entire contract for 121 manholes).

    The consequences of CSI's cryptic approach were foreordained.

    Most importantly, the district court was never fore-

    warned of the legal basis for the severability claim first

    surfaced by CSI following the adverse jury verdict. Under our


    7














    precedent, therefore, on appeal CSI was not entitled to challenge

    the sufficiency of the evidence supporting the jury verdict on

    the limitations issue. See Wells Real Estate, 850 F.2d at 10;
    ___ _________________

    Pstragowski, 553 F.2d at 3. The magistrate judge correctly ruled
    ___________

    that CSI was bound by its own pre-verdict decision to entrust its

    severability claim to the jury with no further legal definition

    than the unchallenged instruction that "accrual" under the

    Massachusetts UCC occurs at the "time of delivery." See United
    ___ ______

    California Bank v. Eastern Mountain Sports, Inc., 546 F. Supp.
    _______________ ______________________________

    945, 964 (D. Mass. 1982) ("Under Massachusetts law, 'it is clear

    that a cause of action . . . accrues when delivery is made

    regardless of the buyer's knowledge of the breach.'") (quoting

    Wolverine Ins. Co. v. Tower Iron Works, 370 F.2d 700, 702 (1st
    __________________ ________________

    Cir. 1966)), aff'd, 705 F.2d 439 (1st Cir. 1983); accord Bay
    _____ ______ ___

    State-Spray & Provincetown S.S., Inc. v. Caterpillar Tractor Co.,
    _____________________________________ _______________________

    533 N.E.2d 1350, 1353 (Mass. 1989).4

    Under Article 2 of the Uniform Commercial Code, the

    severability or entirety of a contract of sale turns on the


    ____________________

    4Counsel argued the severability-entirety issue in their
    closings. CSI argued that the parties' performance under the
    contract demonstrated their practice of treating each separately
    ________
    invoiced shipment of manholes as a distinct transaction. See
    ________ ___
    Trial. Tr. at 141 ("really what is occurring here is a series of
    contracts . . . . All the manholes were made to order. The
    manholes that were shipped . . . in 1986 have no relation to the
    manholes that were delivered as of November 14, 1985.") Perdoni,
    on the other hand, urged the jury to view the contract as a
    unitary whole, and to recognize that Perdoni required all of the
    manholes in order to complete its contract project. Id. at 157
    ___
    ("if you ordered 12 eggs, and you get 10, you don't say, 'Thank
    you for delivering my eggs.' . . . . [T]he full quantity ordered
    was not delivered until July of 1986.").

    8














    intent of the contracting parties, see, e.g., Carlo Bianchi & Co.
    ___ ____ ___________________

    v. Builders' Equip. & Supplies Co., 199 N.E.2d 519, 528 (Mass.
    _______________________________

    1964) (severability or entirety of contract dependent on intent

    of parties) (citing, inter alia, Bianchi Bros., Inc. v. Gendron,
    _____ ____ ___________________ _______

    198 N.E. 767, 770 (Mass. 1935)); Belanger v. Haverlock, 537 A.2d
    ________ _________

    604 (Me. 1988) (same); Lake LBJ Mun. Util. Dist. v. Coulson &
    ___________________________ _________

    C.A.E., Inc., 771 S.W.2d 145 (Tex. 1988) (same); Scruggs v.
    _____________ _______

    Quality Elec. Serv., Inc., 320 S.E.2d 49 (S.C. 1984) (same); In
    _________________________ __

    re Estate of Wilson, 405 N.E.2d 220 (N.Y. 1980); 1901 Wyoming
    ____________________ _____________

    Ave. Coop. Assoc. v. Lee, 345 A.2d 456 (D.C. 1975); see also 17A
    _________________ ___ ___ ____

    Am. Jur. 2d 415 (1991) ("Whether a contract is entire or

    severable is a question of fact"), a quintessential jury ques-

    tion. There can be no question that CSI elected to forego a more
    _______

    definitive jury instruction on the law governing the severabili-

    ty-entirety issue pressed on appeal. As was its right, CSI

    simply attempted to persuade the jury that the parties intended a

    severable contract. Having once embarked on this course, howev-

    er, CSI was not entitled to set out on a new one after its chosen

    litigation tactic failed. See Brody v. President & Fellows of
    ___ _____ _______________________

    Harvard College, 664 F.2d 10, 12 (1st Cir. 1981) (noting that
    _______________

    litigants ordinarily are bound by their tactical decisions at

    trial), cert. denied, 455 U.S. 1027 (1982). Thus, the district
    _____ ______

    court did not err in denying the motion for judgment as a matter

    of law, since CSI "forfeited its right to raise the [severability

    claim] by waiting to raise it until after the jury reached its




    9














    verdict." Sweeney, 926 F.2d at 37.5
    _______

    Next, even assuming that it failed to preserve its

    severability claim for appeal, CSI argues that a new trial is

    required due to alleged inconsistencies between the jury's award

    of damages on the implied warranty claims and the magistrate

    judge's resolution of the limitations defense relating to the

    Chapter 93A claim. We do not agree.

    First, as no special interrogatory was submitted to the

    jury on the limitations defense relating to the implied warranty

    claims, it would be conjectural to conclude that the damages

    awarded by the jury and the finding made by the magistrate judge

    are irreconcilable. See Fed. R. Civ. P. 49(a) (right to trial on
    ___

    particular issue waived absent request for specific jury find-

    ing); Kavanaugh v. Greenlee Tool Co., 944 F.2d 7, 11 (1st Cir.
    _________ __________________

    1991) (applying Rule 49 waiver provision). In determining the

    intent of the contracting parties in this case, the jury may

    either have found (1) that the contract was severable, and made a

    generous award of damages (i.e., 37% of the total damages re-
    ____

    quested by Perdoni on only 11% of the units supplied by CSI); or

    (2) that the contract was not severable, and made a meager award

    (i.e., 37% of the total damages requested by Perdoni on 100% of
    ____

    the units supplied by CSI). The inconsistency posited by CSI is


    ____________________

    5As CSI advances the same arguments in support of its appeal
    from the denial of its Rule 59 motion, we conclude that the
    district court likewise acted well within its discretion in
    denying CSI's motion for new trial on the merits. See Phav v.
    ___ ____
    Trueblood, Inc., 915 F.2d 764, 766 (1st Cir. 1990) ("abuse of
    _______________
    discretion" standard governs review of denial of Rule 59 motion).

    10














    predicated on the assumption that the jury made a meager award of

    damages, yet there is no record basis for such a conclusion.

    Given the strong presumption of regularity attending jury ver-

    dicts, see, e.g., Veiga v. McGee, 26 F.3d 1206, 1215 (1st Cir.
    ___ ____ _____ _____

    1994) (noting that reviewing court is compelled to uphold jury

    verdict under Rule 50 "even in a close case" unless no reasonable

    jury could have reached the same conclusion), we decline to

    disturb the verdict on the basis of the assumed inconsistency

    posited by CSI.

    Second, CSI posits an inconsistency between the results

    reached by different decisionmakers on distinct claims, and

    incorrectly assumes that the jury verdict must yield. Where an

    irreconcilable inconsistency exists between a bench decision and

    a jury verdict on different claims arising out of the same

    transaction, the jury finding must take precedence in the Seventh

    Amendment context: "when a party has a right to a jury trial on

    an issue involved in a legal claim, the judge is of course bound

    by the jury's determination of that issue as it affects his

    disposition of an accompanying equitable claim." Lincoln v.
    _______

    Board of Regents, 697 F.2d 928, 934 (11th Cir.) (citing Curtis v.
    ________________ ______

    Loether, 415 U.S. 189, 196 n.11 (1974); Dairy Queen, Inc. v.
    _______ __________________

    Wood, 396 U.S. 469, 470-73 (1962)), cert. denied, 464 U.S. 826
    ____ _____ ______

    (1983); Los Angeles Police Protective League v. Gates, 995 F.2d
    _____________________________________ _____

    1469, 1473 (9th Cir. 1993) (same); Fowler v. Land Management
    ______ ________________

    Groupe, Inc., 978 F.2d 158, 163 (4th Cir. 1992) (same); Wade v.
    ____________ ____

    Orange Cty. Sheriff's Office, 844 F.2d 951, 954 (2d Cir. 1988)
    _____________________________


    11














    (same); see also Walsh v. Chestnut Hill Bank & Trust Co., 607
    ___ ____ _____ ________________________________

    N.E. 2d 737, 740-41 (Mass. 1993) (noting "equitable" nature of

    claims under Chapter 93A; no right to jury trial). Moreover, in

    the Chapter 93A context, the court has recognized that judge and

    jury, sitting as independent triers of fact, may reach

    conflicting conclusions. Wallace Motor Sales, Inc. v. American
    __________________________ ________

    Motors Sales Corp., 780 F.2d 1049, 1063-67 (1st Cir. 1985)
    ____________________

    (rejecting claim that judge's findings must always conform to

    those of the jury; upholding findings made by district judge on

    Chapter 93A claim and by jury on Dealers Act claim); accord
    ______

    Fowler, 978 F.2d at 162-63 (concluding that under certain circum-
    ______

    stances "it is entirely acceptable that the two fact-finders

    reach conflicting conclusions on the issues"). Thus, even

    assuming inconsistent findings, CSI's claim must fail. Cf.
    ___

    Kavanaugh, 944 F.2d at 9 (noting this court's "substantial
    _________

    reluctance to consider inconsistency [within] civil jury verdicts

    a basis for new trials.")

    Finally, permitting CSI to employ the bench ruling on

    the severability issue as a lever with which to upset the jury

    verdict would circumvent the important Rule 50 corollary that "a

    party who move[s] for a directed verdict may obtain appellate

    review only on the specific ground stated in the motion."
    ____

    Pstragowski, 553 F.2d at 3 (emphasis added); accord Fleming James
    ___________ ______

    Jr. et al., Civil Procedure 7.30 (4th ed. 1992) (observing that
    _______________

    post-judgment motions for judgment as a matter of law are "limit-

    ed to the assertion of issues or grounds specifically raised in


    12














    the prior motion"); see also Doty v. Sewall, 908 F.2d 1053, 1057
    ___ ____ ____ ______

    n.4 (1st Cir. 1990) (noting that failure to bring issue underly-

    ing new trial claim to district court's attention is significant

    because "'[b]y doing so . . . [the party] got a chance to see the

    verdict and then to seek to overturn it.'") (quoting Caldarera v.
    _________

    Eastern Airlines, Inc., 705 F.2d 778, 782 (5th Cir. 1983).
    ________________________

    Challenges to jury verdicts must be evaluated against the back-

    drop of the case "as submitted" to the jury. See, e.g., Griffin
    ___ ____ _______

    v. Matherne, 471 F.2d 911, 915 (5th Cir. 1973), quoted in 1
    ________ ______ __

    Steven A. Childress & Martha S. Davis, Federal Standards of
    _____________________

    Review 3.10 (2d ed. 1992).
    ______

    Affirmed.6
    Affirmed.























    ____________________

    6Although counsel fees have been awarded on occasion for an
    appellate defense of a judgment on a Chapter 93A claim, see,
    ___
    e.g., Manzaro v. McCann, 401 Mass. 880, 885 (1988), there is no
    ____ _______ ______
    basis for a fee award to Perdoni, since CSI did not challenge the
    district court judgment on the Chapter 93A claim.

    13







Document Info

Docket Number: 93-2178

Filed Date: 9/6/1994

Precedential Status: Precedential

Modified Date: 9/21/2015

Authorities (20)

Leon H. Brody v. President & Fellows of Harvard College , 664 F.2d 10 ( 1981 )

Wolverine Insurance Co. v. Tower Iron Works, Inc. , 370 F.2d 700 ( 1966 )

Stephen S. Pstragowski v. Metropolitan Life Insurance ... , 553 F.2d 1 ( 1977 )

Systemized of New England, Inc. v. Scm, Incorporated , 732 F.2d 1030 ( 1984 )

Wells Real Estate, Inc. v. Greater Lowell Board of Realtors , 850 F.2d 803 ( 1988 )

Dolores Sweeney v. Westvaco Company, Dolores Sweeney v. ... , 926 F.2d 29 ( 1991 )

H. Anita Lincoln, Cross-Appellant v. Board of Regents of ... , 697 F.2d 928 ( 1983 )

Michael James Kavanaugh, Jr. And Mary Kavanaugh, Etc. v. ... , 944 F.2d 7 ( 1991 )

Veiga v. McGee , 26 F.3d 1206 ( 1994 )

Arthur Doty v. Richard Sewall, Arthur Doty v. Richard Sewall , 908 F.2d 1053 ( 1990 )

Chat Phav v. Trueblood, Inc. , 915 F.2d 764 ( 1990 )

wallace-motor-sales-inc-ralph-e-wallace-and-third-party-v-american , 780 F.2d 1049 ( 1985 )

barbara-johnston-fowler-v-land-management-groupe-incorporated-john-long , 978 F.2d 158 ( 1992 )

willie-o-wade-v-orange-county-sheriffs-office-aka-orange-county , 844 F.2d 951 ( 1988 )

Elvis Griffin v. Victor Matherne and Otto Candies, Inc. , 471 F.2d 911 ( 1973 )

los-angeles-police-protective-league-and-roger-gibson-v-daryl-f-gates , 995 F.2d 1469 ( 1993 )

Peter Joseph Caldarera, Jr., Etc. v. Eastern Airlines, Inc.,... , 705 F.2d 778 ( 1983 )

Manzaro v. McCann , 401 Mass. 880 ( 1988 )

Curtis v. Loether , 94 S. Ct. 1005 ( 1974 )

United California Bank v. Eastern Mountain Sports, Inc. , 546 F. Supp. 945 ( 1982 )

View All Authorities »