Keystone v. New England Power ( 1997 )


Menu:
  • USCA1 Opinion











    United States Court of Appeals
    For the First Circuit
    ____________________


    No. 96-1800

    KEYSTONE SHIPPING COMPANY,

    Plaintiff - Appellant,

    v.

    NEW ENGLAND POWER COMPANY,

    Defendant - Appellee.

    ____________________

    APPEAL FROM THE UNITED STATES DISTRICT COURT

    FOR THE DISTRICT OF MASSACHUSETTS

    [Hon. George A. O'Toole, Jr., U.S. District Judge] ___________________

    ____________________

    Before

    Cyr, Circuit Judge, _____________
    Campbell, Senior Circuit Judge, ____________________
    and Stahl, Circuit Judge. _____________

    ____________________

    Joseph D. Steinfield with whom Joshua A. Davis, C. Dylan Sanders, ____________________ _______________ ________________
    and Hill & Barlow were on brief for appellant. _____________
    Stanley McDermott, III, with whom James D. Kleiner, Piper & ______________________ ________________ _______
    Marbury L.L.P., and John F. Sherman, III, were on brief for appellee. ______________ ____________________

    ____________________

    March 20, 1997
    ____________________




















    STAHL, Circuit Judge. This case involving an STAHL, Circuit Judge. _____________

    underlying dispute over who is to pay for some $14 million in

    repairs to a coal cargo ship requires us to resolve one

    question: whether claims asserted by defendant-appellee New

    England Power Company ("NEP") against plaintiff-appellant

    Keystone Shipping Co. ("Keystone") are arbitrable. We reach

    two conclusions pointing to the same result. First, because

    the issue has already been litigated by the parties in

    Massachusetts state court, it is precluded from relitigation

    under the doctrine of issue preclusion. Second, even if the

    issue were not precluded, we find that Keystone and NEP have

    a legally-enforceable agreement to arbitrate disputes like

    the one here. We thus affirm.

    Background and Prior Proceedings Background and Prior Proceedings ________________________________

    In order to resolve this appeal we must consider a

    long series of agreements and disputes between Keystone and

    NEP concerning the S.S. Energy Independence, now named the

    S.S. Energy Enterprise ("the Vessel"). The Vessel was

    constructed in the early 1980s by the New England Collier

    Company ("NECCO"), an unincorporated joint venture between

    Keystone and an NEP affiliate, New England Energy

    Incorporated ("NEEI"). NEP, in turn, chartered the Vessel

    from NECCO to deliver coal to its electric power plants. The

    joint venture agreement and the NEP time charter both

    contained arbitration provisions.



    -2- 2













    The relationship was not an entirely happy one and

    a dispute between the parties followed. In 1987, Keystone

    commenced arbitration against NEEI under the joint venture

    agreement, while NEP commenced arbitration against NECCO

    under the time charter. In a previous appeal to this Court,

    we held that the two arbitrations were amenable to

    consolidation by federal court order. See New England Energy ___ __________________

    Inc. v. Keystone Shipping Co., 855 F.2d 1, 8 (1st Cir. 1988), ____ _____________________

    cert. denied, 489 U.S. 1077 (1989). _____ ______

    Before the arbitration was concluded, the parties

    settled their differences through a settlement agreement

    signed by Keystone, NEP, and NEEI in October 1989 ("the 1989

    settlement agreement"). Under the agreement's terms,

    ownership of the Vessel was to pass from NECCO to Keystone or

    a Keystone nominee. The parties further agreed that the

    Vessel's new owner would time charter the Vessel to NEP on

    "terms and conditions agreed to by Keystone and NEP." They

    annexed a draft of the proposed new time charter ("the draft

    charter") to the settlement agreement. Like the then-

    operative NEP time charter, the draft charter contained a

    sweeping arbitration provision. In particular, Section 41 of

    the draft charter provided that "[a]ny and all differences

    and disputes of whatsoever nature arising out of this Charter

    which cannot be resolved by the parties shall be put to





    -3- 3













    arbitration in the City of Boston . . . before a board of

    three persons."

    Keystone nominated Intercoastal Bulk Carriers, Inc.

    ("IBC") to be the Vessel's new owner.1 In accordance with

    the settlement agreement, NECCO sold the Vessel to IBC and

    IBC, in turn, chartered the Vessel to NEP through a time

    charter agreement executed by IBC and NEP on December 27,

    1989 ("the 1989 time charter"). The executed time charter was

    substantially similar to the October draft charter, but not

    exactly identical. The arbitration provisions in the two

    documents, however, were alike in all respects. That same

    day, December 27, Keystone and IBC entered into a management

    agreement which provided that Keystone would continue to

    manage the Vessel.

    The executed 1989 time charter gave NEP the option

    to purchase the Vessel and terminate the charter with six

    months' prior, written notice. In 1994, NEP decided to

    exercise its option, resell the Vessel to International

    Shipholding Corp. ("ISC"), and then recharter the Vessel from

    ISC. On October 27, 1994, NEP and ISC signed a Memorandum of

    Agreement to this effect. Several days later, on November 1,

    1994, NEP notified Keystone and IBC that it was exercising

    its six-month purchase option and would buy the Vessel on May


    ____________________

    1. Like Keystone itself, IBC is a wholly-owned subsidiary of
    Chas. P. Kurz & Co. ("Kurz").

    -4- 4













    1, 1995. NEP concurrently demanded arbitration of its right

    to do this, because Keystone had previously communicated that

    it would contest NEP's right to exercise the purchase option.

    Keystone alleged that in the negotiations that produced the

    1989 settlement agreement NEP had represented that it would

    not exercise the time charter's purchase option. NEP's

    exercise of the option, Keystone suggested, indicated that

    NEP had made misrepresentations at the time of the settlement

    negotiations and had violated Mass. Gen. Laws ch. 93A. A

    three-member arbitration panel was convened to hear the

    parties' dispute.

    On March 15, 1995, the arbitration panel decided

    four threshold issues concerning NEP's service of the

    purchase notice and demand for arbitration in favor of NEP.

    IBC responded by filing an action in federal district court

    under 9 U.S.C. 10 to vacate the arbitrators' ruling, but

    the court dismissed the complaint as premature. See ___

    Intercoastal Bulk Carriers, Inc. v. New England Power Co., _________________________________ ______________________

    No. 95-10880 RW2, (D. Mass. May 18, 1995). Thereafter,

    Keystone and IBC resumed arbitration of the dispute. On May

    17, 1995, Keystone and IBC announced that they were

    withdrawing the challenge to NEP's right to exercise the

    purchase option from arbitration, leaving to the panel the

    issue of whether NEP's actions had violated Mass. Gen. Laws

    ch. 93A.



    -5- 5













    That same day, May 17, Keystone sued NEP in

    Massachusetts state court, claiming that NEP had made

    misrepresentations during the negotiations over the 1989

    settlement agreement. NEP moved to dismiss Keystone's claims

    on the ground that they were governed by the arbitration

    provision of the 1989 time charter. Keystone responded that

    its claims against NEP did not arise under the 1989 time

    charter signed by NEP and IBC, but instead arose out of the

    1989 settlement agreement, which did not have an arbitration

    provision. The state court agreed with NEP and dismissed

    Keystone's complaint. The state court concluded that the

    settlement agreement's provisions meant that Keystone was

    bound by the 1989 time charter's arbitration clause,

    notwithstanding the fact that Keystone had not signed the

    charter, which had been executed by its nominee, IBC, and

    NEP. See Keystone Shipping Co. v. New England Power Co., No. ___ _____________________ _____________________

    95-1141-B (Mass. Superior Court, Essex County, August 17,

    1995).

    The dispute thus returned to the original

    arbitration panel, which, on August 21, 1995, concluded that

    NEP had the right to exercise the purchase option in the 1989

    time charter. The arbitrators ordered IBC to sell the Vessel

    to NEP. Two days later, IBC filed an action in federal

    district court seeking to vacate the arbitrators' latest

    rulings. See Intercoastal Bulk Carriers, Inc. v. New England ___ _________________________________ ___________



    -6- 6













    Power Co., C.A. No. 95-11881-GAO. Shortly thereafter, on __________

    September 5, 1995, Keystone filed a notice of appeal from the

    state court's decision to dismiss its state cause of action

    against NEP.

    This was the state of legal affairs between the

    parties when, on September 20, 1995, IBC and NEP entered into

    a new settlement agreement ("the 1995 settlement agreement").

    Under the new settlement agreement, IBC agreed to transfer

    the Vessel in accordance with NEP's wishes to ISC's nominee,

    Enterprise Ship Co. ("Enterprise"). The parties expressly

    acknowledged that the arbitration clause found in the 1989

    time charter would govern the new settlement agreement. The

    settlement agreement also provided for the mutual release of

    claims by Keystone and IBC in favor of NEP and vice versa.

    There was one exception to this general release. Exhibit B

    of the agreement expressly provided that NEP did not release

    Keystone and IBC from "claims, if any, by reason of the

    Vessel not being in class at the Closing based upon a survey

    . . . when the Vessel is drydocked immediately after the

    Closing."

    On September 28, 1995, the Vessel's new owner,

    Enterprise, took title and sent the Vessel to a shipyard for

    the agreed-upon inspection. The survey that followed

    revealed corrosion damage to the Vessel's bulkheads and cargo

    holds exceeding the tolerances established by the American



    -7- 7













    Bureau of Shipping, thereby making the Vessel unseaworthy.

    The ship inspectors refused to allow the Vessel to sail until

    the needed repairs were completed. NEP alleges that the bulk

    of the corrosion damage was a direct result of Keystone's

    failure to maintain the Vessel. The total cost to bring the

    Vessel to standard is claimed to be approximately $14 million

    dollars. NEP argues that Keystone and IBC are responsible for

    much of that amount under the terms of the 1989 time charter.

    On December 20, 1995, NEP notified the arbitration

    panel that it desired to arbitrate its claims for the

    Vessel's repair costs against Keystone and IBC. Keystone

    denied that it was required to arbitrate NEP's claims, and on

    February 27, 1996 filed suit in federal district court

    seeking a stay of arbitration pursuant to Mass. Gen. Laws ch.

    251, 2(b). NEP cross-moved under the Federal Arbitration

    Act, 9 U.S.C. 4, to compel arbitration. On May 24, 1996,

    the district court granted NEP's motion to compel, concluding

    that the arbitrability of NEP's claims against Keystone was

    an issue that had been previously decided in Massachusetts

    state court, and, in any event, was the result compelled by

    the merits. This appeal ensued.

    Standard of Review Standard of Review __________________

    We review de novo the district court's application __ ____

    of the doctrine of issue preclusion because "[t]he

    applicability vel non of preclusion principles is a question ___ ___



    -8- 8













    of law." Monarch Life Ins. Co. v. Ropes & Gray, 65 F.3d 973, ______________________ ____________

    978 (1st Cir. 1995). Accordingly, "[n]o special deference is

    owed to the district court's determination." Grella v. Salem ______ _____

    Five Cent Sav. Bank, 42 F.3d 26, 30 (1st Cir. 1994). ___________________

    Similarly, we exercise plenary review over

    determinations regarding arbitrability. "[A]rbitrability

    depends on contract interpretation, which is a question of

    law." PaineWebber Inc. v. Elahi, 87 F.3d 589, 592 (1st Cir. ________________ _____

    1996) (construing Commercial Union Ins. Co. v. Gilbane Bldg. __________________________ _____________

    Co., 992 F.2d 386, 388 (1st Cir. 1993)). ___

    The Issue Preclusion Question The Issue Preclusion Question _____________________________

    In issuing its order to compel arbitration, the

    district court concluded that the Massachusetts state court

    judgment precludes Keystone from relitigating the question of

    arbitrability under the 1989 time charter. On appeal,

    Keystone maintains that the district court misapplied the

    issue preclusion doctrine. We disagree.

    Initially, we note that "[t]he full faith and

    credit statute, 28 U.S.C. 1738, requires us to give 'the

    same preclusive effect to state court judgments -- both as to

    claims and issues previously adjudicated -- as would be given

    in the state court system in which the federal court sits.'"

    Kyricopoulos v. Town of Orleans, 967 F.2d 14, 16 (1st Cir. ____________ _______________

    1992) (per curiam) (quoting Willhauck v. Halpin, 953 F.2d _________ ______

    689, 704 (1st Cir. 1991)). Massachusetts law thus governs



    -9- 9













    the preclusion question in this case. However, we have

    previously recognized that Massachusetts courts "apply the

    doctrine of issue preclusion in a traditional manner."

    Willhauck, 953 F.2d at 705 (citing Martin v. Ring, 514 N.E.2d _________ ______ ____

    663, 664 (Mass. 1987); Fireside Motors, Inc. v. Nissan Motor ______________________ ____________

    Corp., 479 N.E.2d 1386 (Mass. 1985); Restatement (Second) of _____

    Judgments 27 (1982)). Because our cases apply the same

    traditional preclusion principles that would control in a

    Massachusetts court, our previous pronouncements in this area

    of law are persuasive.

    "The principle of collateral estoppel, or issue

    preclusion," we have explained, "bars relitigation of any

    factual or legal issue that was actually decided in previous ________

    litigation 'between the parties, whether on the same or a

    different claim.'" Grella, 42 F.3d at 30 (quoting Dennis v. ______ ______

    Rhode Island Hosp. Trust, 744 F.2d 893, 899 (1st Cir. 1984) ________________________

    (quoting Restatement (Second) of Judgments 27 (1982))).

    When the parties in a subsequent action are the same as those

    in a prior one, a party seeking to invoke the doctrine of

    issue preclusion needs to establish four essential elements:

    "(1) the issue sought to be precluded must be the same as

    that involved in the prior action; (2) the issue must have

    been actually litigated; (3) the issue must have been

    determined by a valid and binding final judgment; and (4) the

    determination of the issue must have been essential to the



    -10- 10













    judgment." Grella, 42 F.3d at 30; accord Ropes & Gray, 65 ______ ______ _____________

    F.3d at 981. Each of these elements is present in the

    instant case.

    First, the arbitrability of NEP's claims in this

    case raises the same issue raised in the Massachusetts state

    cause of action. Keystone ingeniously attempts to argue that

    there are two separate and distinct arbitrability issues.

    Keystone in particular maintains that the state court decided

    that claims against it under the 1989 settlement agreement

    were arbitrable, but that this case raises a different issue:

    "whether claims asserted by NEP against Keystone under the

    1989 Time Charter and 1995 NEP-IBC Settlement Agreement are

    arbitrable." Keystone fails to persuade for a very simple,

    but inescapable, reason. The state court concluded that

    Keystone was bound to arbitrate claims concerning the Vessel

    under the 1989 settlement agreement because (1) it was bound

    to arbitrate such claims under the terms of the executed 1989

    time charter, and (2) Keystone had expressly agreed in the

    1989 settlement agreement that ownership of the Vessel would

    pass to Keystone or a Keystone nominee and that the Vessel's

    new owner would time charter the Vessel to NEP on "terms and

    conditions agreed to by Keystone and NEP." Because

    arbitrability of claims concerning the Vessel was one such

    term and condition in the executed time charter, the state

    court concluded that the settlement agreement's express



    -11- 11













    language bound Keystone to arbitrate such claims. Put in

    another fashion, the state court found that Keystone, in the

    1989 settlement agreement, had expressly agreed that it or a

    nominee would execute a time charter on terms and conditions

    agreeable to Keystone, and thus was bound to arbitrate all

    disputes because the executed time charter, like the draft

    charter attached to the settlement agreement and initialed on

    every page by Keystone, made claims concerning the Vessel

    arbitrable.

    Keystone's argument about the 1995 settlement

    agreement likewise fails to persuade because the parties to

    the agreement expressly acknowledged that the arbitration

    clause found in the 1989 time charter would apply and govern

    the new settlement agreement. While it is true that the

    settlement agreement provided for the mutual release of

    claims by Keystone and IBC in favor of NEP and vice versa,

    the agreement expressly carved out an exception to the

    general release for "claims, if any, by reason of the Vessel

    not being in class at the Closing." Because NEP did not

    release such claims, and because such claims arise under the

    1989 settlement agreement and are arbitrable under the terms

    of that agreement and the 1989 time charter, their

    arbitrability in the instant case is the very same issue

    previously litigated and decided in Massachusetts state

    court.



    -12- 12













    This point carries us to the second element of the

    issue preclusion standard: the issue raised here on appeal

    has been "actually litigated." Grella, 42 F.3d at 30. ______

    Keystone opposed NEP's motion to dismiss the Massachusetts

    state cause of action before the state court with briefs,

    affidavits, and at a motion hearing. Keystone feebly argues

    that the state court should not have disposed of its cause of

    action by motion, but instead should have conducted an

    evidentiary hearing. As NEP correctly notes, the

    Massachusetts court had before it the relevant contractual

    documents, read and heard the litigants' opposing views on

    what meaning and effect should be afforded to those documents

    and the history of the parties' arbitration efforts, and

    properly concluded that the arbitrability question could be

    decided on motion. Well-settled principles of law indicate

    that the arbitrability issue was actually litigated for

    preclusion purposes because it was "subject to an adversary

    presentation and consequent judgment" that was not "a product

    of the parties' consent and is a final decision on the

    merits." Jack H. Friedenthal et al., Civil Procedure ________________

    14.11, at 672, 673 (1985).

    We thus reach the third and fourth essential

    elements of collateral estoppel: the issue sought to be

    precluded must have been determined by a valid and binding

    final judgment and the issue's determination must have been



    -13- 13













    essential to the judgment. See Ropes & Gray, 65 F.3d at 978; ___ ____________

    Grella, 42 F.3d at 30. Keystone does not challenge the ______

    validity and binding nature of the state court judgment.

    Rather, Keystone argues that the state court judgment focused

    on the 1989 settlement agreement and thus did not determine

    the arbitrability of NEP's current claims because the court

    did not decide whether claims against Keystone are arbitrable

    under either the 1989 time charter or the 1995 settlement

    agreement. This argument is nothing more than a recycled

    version of the contention we have just rejected. As we have

    seen, the state court determined that Keystone was bound to

    arbitrate under the 1989 settlement agreement because that

    agreement contemplated the 1989 time charter, which contained

    a sweeping arbitration clause. The arbitrability of any

    claims, including NEP's present ones, under the 1989 time

    charter was an essential component in the state court's prior

    determination, even if it itself was not the ultimate issue

    the court decided. As we recently explained, an "issue may

    be actually litigated and resolved 'even if it is not

    explicitly decided,' as long as it is logically necessary to

    [the court's] final decision." Ropes & Gray, 65 F.3d at 982 ____________

    (quoting and construing Grella, 42 F.3d at 30-31) (emphasis ______

    in original omitted).

    Our review of the record indicates that the

    arbitrability of NEP's present claims against Keystone is an



    -14- 14













    issue that has already been litigated and decided by the

    parties in Massachusetts state court. Under the doctrine of

    issue preclusion, Keystone cannot seek to undo or redo in

    federal court what has already been done in state court.

    The Merits of the Arbitrability Issue The Merits of the Arbitrability Issue _____________________________________

    Our decision today would be the same even if

    principles of collateral estoppel did not bar Keystone's

    attempt to relitigate the arbitrability of NEP's current

    claims against it. Our review of the record and the relevant

    contractual documents contained therein convinces us that

    Keystone is bound to arbitrate NEP's claims regarding the

    Vessel. In view of the detailed factual discussion we have

    already undertaken, we do not feel it necessary to replay all

    of the evidence. We shall only briefly explain why we

    conclude that Keystone is bound to arbitrate such claims as

    those NEP presently advances.

    Keystone entered into the 1989 settlement agreement

    with NEP. In that agreement, Keystone expressly agreed that

    ownership of the Vessel would pass to it or a Keystone

    nominee and that the Vessel's new owner would time charter

    the Vessel to NEP on "terms and conditions agreed to by

    Keystone and NEP." Attached to the settlement agreement was a

    draft of the contemplated time charter that Keystone

    initialed on every page. The draft charter contained a

    sweeping arbitration clause, which provided that "[a]ny and



    -15- 15













    all differences and disputes of whatsoever nature arising out

    of this Charter which cannot be resolved by the parties shall

    be put to arbitration in the City of Boston." Keystone

    subsequently nominated IBC to take title to the Vessel and

    IBC, in turn, executed the time charter with NEP that was

    contemplated in the 1989 settlement agreement. The executed

    time charter contained the exact same arbitration provision

    as the draft attached to the settlement agreement. The

    inescapable conclusion from the foregoing is that Keystone

    agreed to time charter the Vessel to NEP, via its nominee

    IBC, under the terms and conditions established in the

    executed time charter, including the terms and conditions

    regarding the arbitrability of claims.

    The 1995 settlement agreement between IBC and NEP

    does not change this legal state of affairs. Both parties to

    the agreement expressly acknowledged that the arbitration

    clause found in the 1989 time charter would govern the new

    settlement agreement. While the new settlement agreement

    provided for the mutual release of claims by Keystone and IBC

    in favor of NEP and vice versa, as we have said, the

    agreement expressly carves out one exception from this

    general release. The relevant language could not be more

    clear: NEP does not release Keystone and IBC from "claims, if

    any, by reason of the Vessel not being in class at the

    Closing based upon a survey . . . when the Vessel is



    -16- 16













    drydocked immediately after the Closing." Because NEP does

    not release such claims against Keystone, and because such

    claims arise under the 1989 settlement agreement and are

    arbitrable under the executed time charter contemplated by

    that earlier settlement agreement, Keystone is obligated to

    arbitrate NEP's present claims.

    The fact that Keystone itself did not sign either

    the 1989 time charter or the 1995 settlement agreement is not

    dispositive. Keystone is bound by the terms and conditions

    of the executed time charter because of the commitments it

    undertook in the 1989 settlement agreement. And the fact

    that Keystone is not a signatory to the 1995 settlement

    agreement is nothing more than a clever red herring because

    that agreement specifically preserves Keystone's prior

    exposure and liability under the 1989 settlement agreement

    and time charter, for "claims, if any, by reason of the

    Vessel not being in class at the Closing."

    Having weighed the merits vel non of this appeal, ___ ___

    we find that the balance swings clearly in NEP's favor. We

    conclude that NEP's claims are arbitrable and decline

    Keystone's invitation to visit additional corollary issues.

    Conclusion Conclusion __________

    Principles of collateral estoppel (issue

    preclusion) raise a bar to Keystone's attempt to litigate the

    arbitrability of NEP's present claims for recovery of repair



    -17- 17













    costs to the Vessel. Even if this were not the case, NEP's

    claims against Keystone are arbitrable as a consequence of

    Keystone's contractual commitments. We thus conclude that

    the district court's order to compel arbitration was correct.

    Affirmed. Costs to appellee. Affirmed. Costs to appellee.











































    -18- 18