S&S Paving v. Berkley ( 2016 )


Menu:
  •                                IN THE
    ARIZONA COURT OF APPEALS
    DIVISION ONE
    S&S PAVING AND CONSTRUCTION, INC., an Arizona corporation,
    Plaintiff/Appellant,
    v.
    BERKLEY REGIONAL INSURANCE COMPANY, a Delaware
    corporation, Defendant/Appellee.
    No. 1 CA-CV 15-0239
    FILED 5-12-2016
    Appeal from the Superior Court in Maricopa County
    No. CV 2013-055438
    The Honorable Michael D. Gordon, Judge
    AFFIRMED
    COUNSEL
    Carmichael & Powell, P.C., Phoenix
    By Trysta M. Puntenney, David J. Sandoval
    Counsel for Plaintiff/Appellant
    Jennings, Haug & Cunningham, LLP, Phoenix
    By Chad L. Schexnayder, Robert John Lamb
    Counsel for Defendant/Appellee
    OPINION
    Judge Margaret H. Downie delivered the opinion of the Court, in which
    Presiding Judge Andrew W. Gould and Judge John C. Gemmill joined.
    S&S PAVING v. BERKLEY
    Opinion of the Court
    D O W N I E, Judge:
    ¶1             S&S Paving and Construction, Inc. (“S&S”) appeals the
    dismissal of its bad faith claim against Berkley Regional Insurance
    Company (“Berkley”). We hold that a surety on a payment bond issued
    under Arizona’s “Little Miller Act” may not be sued for bad faith and
    therefore affirm the judgment of the superior court.
    FACTS AND PROCEDURAL HISTORY
    ¶2            The City of Prescott retained Spire Engineering, LLC
    (“Spire”) to act as general contractor for the Demerse Avenue Overlay
    Project (“the Project”). Berkley issued a payment bond for the Project. See
    Ariz. Rev. Stat. (“A.R.S.”) § 34-222(A)(2) (requiring payment bonds for
    public projects).
    ¶3             In October 2011, S&S’s attorney sent a demand letter to
    Berkley, stating that S&S had performed paving work for the Project
    pursuant to its subcontract with Spire and had not been paid $23,763.
    Berkley acknowledged the claim, requested additional information, and
    advised that its review of S&S’s demand “does not toll the running of any
    statute of limitations or other time period.”
    ¶4            S&S provided Berkley with the requested information,
    which included a proof of claim. Berkley acknowledged receipt of the
    documentation in December 2011 and stated that it needed to ascertain
    Spire’s position regarding S&S’s claim, after which it would communicate
    further. Berkley reiterated that its investigation of the claim “in no way
    waives or alters any rights, interests or defenses that we may have under
    our bond or applicable law.” No further communication occurred
    between the parties until May 2013, when counsel for S&S sent another
    demand letter, and Berkley responded that S&S’s claim was untimely.
    ¶5            In November 2013, S&S sued Berkley for breach of contract
    and bad faith.1 Berkley moved for summary judgment on both claims.
    The superior court ruled that the breach of contract claim was barred by
    the statute of limitations. See A.R.S. § 34-223(B) (one-year statute of
    limitations for public work payment bonds). The court also dismissed
    1       S&S also sued Spire for breach of contract, but the judgment at
    issue on appeal relates only to Berkley and includes a Rule 54(b)
    certification.
    2
    S&S PAVING v. BERKLEY
    Opinion of the Court
    S&S’s bad faith claim, concluding there was no “contractual relationship
    or special relationship for the claim to survive.” The court denied S&S’s
    motion for reconsideration and awarded Berkley attorneys’ fees.
    ¶6            S&S timely appealed. We have jurisdiction pursuant to
    A.R.S. §§ 12-120.21(A)(1) and –2101(A)(1).
    DISCUSSION
    ¶7             We review a grant of summary judgment de novo. Chalpin v.
    Snyder, 
    220 Ariz. 413
    , 418, ¶ 17 (App. 2008). Summary judgment is
    appropriate if “there is no genuine dispute as to any material fact and the
    moving party is entitled to judgment as a matter of law.” Ariz. R. Civ. P.
    56(a). We will affirm the judgment if it is correct for any reason. Ariz. Bd.
    of Regents v. State ex rel. Ariz. Pub. Safety Ret. Fund Manager, 
    160 Ariz. 150
    ,
    154 (App. 1989).
    ¶8            In 1969, Arizona adopted the Little Miller Act, A.R.S.
    §§ 34-221, et seq. (“the Act”). See SCA Constr. Supply v. Aetna Cas. & Sur.
    Co., 
    157 Ariz. 64
    , 65–66 (1988). Modeled after the federal Miller Act, 40
    U.S.C. § 270a, et seq., the Act requires contractors on public works projects
    to furnish payment bonds “for the protection of claimants supplying labor
    or materials to the contractor or his subcontractors.” A.R.S. § 34-222(A)(2).
    A claimant who is not paid in full for labor or materials “shall have the
    right to sue on such payment bond.” A.R.S. § 34-223(A). “The purpose
    behind both of the Miller Acts is to provide security for those who supply
    materials or labor in the construction of public projects.” SCA 
    Constr., 157 Ariz. at 66
    . Such statutory protection is necessary because no lien rights
    exist on public projects. See F.D. Rich Co. v. United States ex rel. Indus.
    Lumber Co., 
    417 U.S. 116
    , 122 (1974) (liens “cannot attach to Government
    property,” so the Miller Act is intended “to provide an alternative remedy
    to protect” suppliers on public works projects).
    ¶9            S&S does not challenge the dismissal of its breach of contract
    claim on statute of limitations grounds. See A.R.S. § 34-223(B) (No suit
    “shall be commenced after the expiration of one year from the date on
    which the last of the labor was performed or materials were supplied by
    the person bringing . . . suit.”). It instead contends the superior court
    erred by dismissing its bad faith claim because sureties issuing payment
    bonds under the Act have a duty to “undertake an investigation adequate
    to determine whether a claimant’s claim is tenable or valid.” According to
    S&S, sureties owe the same duty of good faith to claimants under the Act
    as insurance companies owe to insureds.
    3
    S&S PAVING v. BERKLEY
    Opinion of the Court
    ¶10            S&S asks us to graft a common law remedy onto a statutory
    scheme that includes within its ambit both the availability of complete
    relief and specific conditions precedent to recovery. But “where a statute
    expressly provides a particular remedy or remedies, a court must be chary
    of reading others into it.” Transamerica Mortg. Advisors, Inc. v. Lewis, 
    444 U.S. 11
    , 19 (1988); see also State ex rel. Horne v. Autozone, Inc., 
    229 Ariz. 358
    ,
    362–63 (2012) (declining to read disgorgement remedy into statutory
    scheme “unless and until” the Arizona Legislature makes such a
    determination).
    ¶11             The Arizona Legislature has defined the breadth of liability
    under the Act. Section 34-222(F) dictates the terms that payment bonds
    must include — one of which is the statement that “all liabilities on this
    bond shall be determined in accordance with the provisions, conditions
    and limitations of title 34, chapter 2, article 2, Arizona Revised Statutes, to
    the same extent as if they were copied at length in this agreement.”
    (Emphasis added.) “All liabilities” is a broad term. Recognizing a
    common law bad faith remedy would be inconsistent with the
    legislature’s defined liability for Act sureties. And this Court has long-
    recognized that “[w]hen a corporate surety undertakes an obligation on a
    bond pursuant to a specific statutory requirement, its liabilities are
    measured by the terms of that statute.” Brown Wholesale Elec. Co. v.
    Merchs. Mut. Bonding Co., 
    148 Ariz. 90
    , 95 (App. 1984); see also Norquip
    Rental Corp. v. Sky Steel Erectors, Inc., 
    175 Ariz. 199
    , 202 (App. 1993) (“The
    liability of a surety on a statutory bond, including who can make a claim
    on the bond and the required procedure for making such a claim, is
    measured by the terms of the statute requiring the bond.”).
    ¶12            In addition to defining a surety’s liability, the Act dictates
    the procedures that claimants must follow in order to recover against
    payment bonds. See R.E. Monks Constr. Co. v. Aetna Cas. & Sur. Co., 
    189 Ariz. 575
    , 579 (App. 1997) (“To recover against the payment bond, a
    claimant must comply with statutory procedures.”). When a statutory
    scheme “creates a right and also provides a complete and valid remedy
    for the right created, the remedy thereby given is exclusive.” Blankenbaker
    v. Jonovich, 
    205 Ariz. 383
    , 387, ¶ 18 (2003).
    ¶13           But for its failure to timely file suit, S&S had a “complete and
    valid remedy” under the Act. See 
    id. Because a
    payment bond is
    “sufficient to pay all claims, and is the sole source from which laborers
    and materialmen are to be paid, it necessarily follows that laborers and
    materialmen who do not timely avail themselves of this remedy fall into
    4
    S&S PAVING v. BERKLEY
    Opinion of the Court
    the category of general creditors of the contractor.” Gen. Acrylics v. U.S.
    Fid. & Guar. Co., 
    128 Ariz. 50
    , 55 (App. 1980). Concluding that S&S is
    relegated to the status of general creditor and may not assert a bad faith
    claim against Berkley is consistent with the treatment of private project
    claimants under Arizona’s mechanics’ lien statutes. Cf. Trio Forest Prod.,
    Inc. v. FNF Constr., Inc., 
    182 Ariz. 1
    , 2 (App. 1994) (The Act is intended to
    “provide protection comparable to that afforded by state mechanic’s lien
    laws on private contracts.”). Mechanics’ lien claimants are required to
    strictly comply with various statutory requirements, or lien-based
    recovery is barred. See, e.g., Scottsdale Mem’l Health Sys. v. Clark, 
    157 Ariz. 461
    , 470 (1988) (claim barred if no action initiated within six months of
    recording); MLM Constr. Co. v. Pace Corp., 
    172 Ariz. 226
    , 232 (App. 1992)
    (failure to prove service of preliminary notice bars recovery); James Weller,
    Inc. v. Hansen, 
    21 Ariz. App. 217
    , 223 (1973) (requiring strict compliance
    with “statutory time elements in the recording of notices and claims”).
    ¶14            S&S relies heavily on Dodge v. Fidelity & Deposit Co. of
    Maryland, 
    161 Ariz. 344
    (1989) — a case we find distinguishable. In Dodge,
    the plaintiff-homeowners contracted with a residential contractor for the
    construction of a home. Their contract required a performance bond,
    which the defendant-surety provided. After the contractor failed to
    complete the project, the homeowners filed suit. As relevant here, they
    alleged bad faith against the surety. The surety prevailed in the superior
    court and on appeal to this Court. The Arizona Supreme Court reversed,
    however, holding that the bad faith claim could proceed, and stating:
    The purpose of the construction performance bond required
    by plaintiffs’ contract with [the contractor] was not for
    plaintiffs’ commercial advantage, but to protect plaintiffs
    from calamity—[the contractor’s] default on the contract. A
    contractor’s default has the potential for creating great
    financial and personal hardship to a homeowner. Surety
    insurance is obtained with the hope of avoiding such
    hardships. Imposing tort damages on a surety who in bad
    faith refuses to pay a valid claim will deter such conduct.
    
    Id. at 346.
    ¶15           The most fundamental distinction between Dodge and this
    case is that the former did not involve a statute, let alone a carefully
    crafted statutory scheme that seeks to balance the competing interests
    inherent in public works projects. And unlike Dodge, where the court
    found that the surety lacked incentive to address the homeowners’ claim,
    5
    S&S PAVING v. BERKLEY
    Opinion of the Court
    a surety under the Act has a strong pecuniary motive to pay valid claims
    without litigation. Not only is a successful litigant under the Act entitled
    to recover “sums justly due,” but an award of attorneys’ fees is
    mandatory. See A.R.S. §§ 34-222(F), -223(A). Interest under the Prompt
    Pay Acts is also due prevailing claimants. See A.R.S. §§ 32-1129.02(H),
    34-221(J).
    ¶16              Finally, S&S alleged that Berkley had a legal duty to
    “undertake an investigation adequate to determine” whether its claim was
    valid. But the Act neither imposes nor appears to contemplate any pre-
    litigation investigative or processing duties by sureties. Cf. O’Connor v.
    Star Ins. Co., 
    83 P.3d 1
    , 6 (Alaska 2003) (“The statute nowhere states or
    implies that licensing bond sureties have a duty to independently
    investigate claims made against bonded contractors. The statutory
    language only requires that licensing bonds be conditioned on a promise
    to pay amounts adjudged against the contractor.”). Indeed, the Act makes
    no mention of pre-litigation claims at all. An unpaid subcontractor’s right
    is “to sue on such payment bond for the amount . . . unpaid at the time of
    institution of such suit and to prosecute such action to final judgment
    . . . .” A.R.S. § 34-223(A).
    ¶17            Although the Act is “a remedial statute that must be liberally
    construed to protect subcontractors providing labor and materials for a
    public construction project,” courts may not disregard established
    limitations on liability and recovery. See R.E. 
    Monks, 189 Ariz. at 576
    –77.
    Should the Arizona Legislature deem it appropriate to permit bad faith
    claims against Act sureties in addition to existing statutory remedies, it is
    free to enact legislation that effectuates that policy determination. Cf. B.J.
    Cecil Trucking, Inc. v. Tiffany Constr. Co., 
    123 Ariz. 31
    , 34 (App. 1979)
    (“[L]imitations on liability under contractors’ bonds have historically been
    governed by practical considerations relating to the nature of the business
    and the ability of the contractor to control his costs.”).
    6
    S&S PAVING v. BERKLEY
    Opinion of the Court
    CONCLUSION
    ¶18          We affirm the judgment of the superior court. We deny
    S&S’s request for an award of attorneys’ fees on appeal because it has not
    prevailed. We will award Berkley a reasonable sum of attorneys’ fees
    incurred on appeal pursuant to A.R.S. § 34-222(B), (F), as well as taxable
    costs, upon compliance with Arizona Rule of Civil Appellate Procedure
    21.
    :ama
    7