FHS v. BC ( 1999 )


Menu:
  • USCA1 Opinion


                     United States Court of Appeals
    
    For the First Circuit





    No. 98-1744

    FHS PROPERTIES LIMITED PARTNERSHIP, ETC.,

    Plaintiff, Appellee,

    v.

    BC ASSOCIATES, ET AL.,

    Defendants, Appellants.



    APPEAL FROM THE UNITED STATES DISTRICT COURT

    FOR THE DISTRICT OF MASSACHUSETTS

    [Hon. Morris E. Lasker, Senior U.S. District Judge]



    Before

    Selya, Circuit Judge,
    Cyr, Senior Circuit Judge,
    and Stahl, Circuit Judge.




    John D. Donovan, Jr., with whom Randall W. Bodner, Brian G.
    Murphy, and Ropes & Gray, were on brief for appellants.
    Mitchell H. Kaplan, with whom Thomas F. Maffei, Robert
    DiAdamo, and Choate, Hall & Stewart, were on brief for appellee.





    April 29, 1999






    STAHL, Circuit Judge. In this diversity case,
    defendants-appellants BC Associates, et al. ("appellants") appeal
    a final judgment of the district court, issued in part on a jury
    verdict and in part as a matter of law. Appellants also challenge
    the court's denial of their motion for a new trial on damages. We
    reverse the district court's judgment as a matter of law and affirm
    the court's denial of the motion for a new trial.
    I. Facts
    On appeal, two partners dispute whether a 1991 settlement
    payment made to third parties by one of the partners should be
    characterized under the partnership agreements as a "Deficit Loan"
    or as an indemnification obligation. Insofar as appellants are
    challenging the judgment entered against them as a matter of law by
    the district court, we view the evidence in the light most
    favorable to them. See Gibson v. City of Cranston, 37 F.3d 731,
    733 (1st Cir. 1994). But insofar as they are challenging the
    jury's verdict, we view the evidence in the light most favorable to
    the verdict. See Dichner v. Liberty Travel, 141 F.3d 24, 27 (1st
    Cir. 1998). Defendants BCA-1 and BCA-2 (together "BCA") and
    plaintiff-appellee FHS Properties Limited Partnership ("FHS"), are
    respectively the managing partners and sole other general partner
    of two partnerships that developed and now own International Place,
    a two-tower office complex in downtown Boston. FHS has a sixty-
    percent interest in the two partnerships. BCA has a forty-percent
    interest. The partners envisioned developing the complex in two
    distinct phases and therefore formed Fort Hill Square Associates
    ("Partnership 1") to develop Phase 1 of the project and Fort Hill
    Square Phase 2 Associates ("Partnership 2") to develop Phase 2.
    The partners signed two partnership agreements ("Partnership
    Agreements"), essentially identical in their terms, which provided
    that the agreements would be construed in accordance with
    Massachusetts law.
    Phase 1 of the project was initially financed through a
    construction loan from Bank of Boston. When construction was
    complete, the construction loan was "taken out" and replaced with
    permanent financing by Teachers' Insurance and Annuity Association
    ("TIAA"). When the partners decided to proceed with Phase 2, Bank
    of Boston again agreed to finance the construction, subject to a
    permanent "take out" commitment from TIAA. The second construction
    loan was secured by all of the partnerships' assets, including a
    mortgage on Phase 1. Notwithstanding its security interest, Bank
    of Boston, in May 1990, approved a plan to distribute $15 million
    of partnership cash to the partners on three future distribution
    dates, provided that certain conditions were satisfied on those
    dates.
    The settlement obligation at issue in this case arose in
    January 1991, when two entities, who were then limited partners of
    BCA-1 and who shared an interest in Phase 1 but not Phase 2 of the
    project, sued defendants Partnership 1, BCA-1, FHS, Donald
    Chiofaro, Theodore Oatis, Bank of Boston, and TIAA, claiming that
    the general partners of BCA-1 had misused partnership assets by
    pledging them as security for the construction of Phase 2 (the
    "Dimeo" suit). The initiation of the suit distressed the
    partnerships' lenders. Bank of Boston sought an assurance from
    TIAA that notwithstanding the pendency of the suit, it would honor
    its promise to pay off the bank's construction loan and replace it
    with permanent financing once Phase 2 was complete. TIAA refused
    to give such an assurance. Bank of Boston responded by threatening
    to cease financing Phase 2 construction and insisted that the
    partnerships sign a "Forbearance Agreement," which became effective
    on March 14, 1991. That agreement stated that it would be an event
    of default under the construction loan if the Dimeo suit was not
    settled by April 15, 1991; and pending the April 15 deadline, the
    bank would finance only fifty percent of the requisitions made
    under the loan agreement, forcing the partnerships to cover the
    balance from other funds, which could potentially include the $15
    million earmarked for distribution.
    Not surprisingly, BCA and FHS jointly worked to resolve
    the Dimeo suit by the April 15 deadline. They negotiated on
    multiple occasions with the Dimeo plaintiffs' lawyers and met with
    Bank of Boston and TIAA in an effort either to borrow funds with
    which to settle the suit or to eliminate the terms of the
    Forbearance Agreement. On each occasion, the lenders refused to
    lend the necessary money or to change the terms of the Forbearance
    Agreement.
    On April 12, 1991, the last business day before the
    bank's deadline, BCA and FHS reached an oral agreement with the
    Dimeo plaintiffs to settle the suit for $5.6 million. Payment was
    due in one week, on April 19. The partners promptly informed Bank
    of Boston and TIAA that the case had been resolved.
    On April 18, however, FHS informed BCA, by notice to
    BCA's general partner Chiofaro, that BCA was forbidden from using
    Partnership 1 or Partnership 2 funds to satisfy the settlement, and
    threatened to remove BCA as managing general partner should it do
    so. FHS added that it would notify Bank of Boston and TIAA of its
    position. According to FHS, partnership funds could not be used to
    pay the settlement because the settlement was solely BCA's
    obligation.
    After deliberating through the evening of April 18,
    Chiofaro decided on the morning of April 19 to use only BCA funds
    to pay the settlement. That day, he paid the Dimeo plaintiffs
    $5.6 million. In return, the Dimeo plaintiffs forfeited to BCA
    their small, indirect equity interests in Phase 1, represented by
    the limited partnership interests in BCA-1.
    Section 5.2 of the Partnership Agreements permits a
    partner to lend the partnerships certain amounts as "Deficit Loans"
    if four conditions are met: (1) there must exist a "financial
    requirement" of the partnership, that (2) "cannot . . . reasonably
    be satisfied from partnership capital, additional capital,
    financing proceeds, revenues and other partnership moneys," (3)
    "the parties [have] use[d] their best efforts to obtain reasonable
    non-recourse institutional financing . . . of the required amounts"
    but have been unable to "obtain such financing," and (4) a partner
    has "elect[ed] . . . in its sole discretion" to loan the
    partnership the necessary funds." In November 1991, some six
    months after satisfying the Dimeo settlement, BCA sent a letter to
    FHS, asserting that its settlement payment constituted a "Deficit
    Loan," accruing interest at 18%. FHS responded that no such
    Deficit Loan had been made, and that BCA was not entitled to
    indemnification for any part of the $5.6 million payment. FHS then
    filed the instant action seeking a declaration that neither
    Partnership 1 nor Partnership 2 owed any sum to BCA.
    II. Prior Proceedings
    The parties tried the case to a jury over twelve days
    beginning October 14, 1997. Although denominated defendants,
    appellants assumed the burden of proof and proceeded through trial
    effectively as plaintiffs. Upon the close of appellants' evidence,
    FHS moved for judgment as a matter of law on the Deficit Loan
    issue, contending that the second requirement of Section 5.2 had
    not been met because "[t]here can be no question before the jury
    that the partnership[s] had money with which to pay this
    obligation." The court reserved ruling on the motion and submitted
    the question to the jury. The district court also instructed the
    jury on damages, advising that damages should reflect the $5.6
    million settlement payment made by BCA, less the value of any
    benefits obtained by it, including the limited partnership
    interests in Phase 1 obtained in the settlement and the value, if
    any, of the release from the lawsuit. Appellants did not object to
    this instruction.
    After deliberation, the jury answered special
    interrogatories establishing that appellants had proved each of the
    four conjunctive elements for a "Deficit Loan;" and alternatively,
    that appellants were entitled to be indemnified by the partnerships
    for the settlement payment. Following the return of the special
    verdict, the court gave a number of additional instructions on
    damages. In the end, the jury returned a verdict establishing
    appellants' damages at $2.1 million.
    Following the jury's verdict, FHS renewed its motion for
    judgment as a matter of law and appellants filed a motion for a new
    trial on damages. The court, on May 13, 1998, entered final
    judgment, ruling that a Deficit Loan did not exist under the
    partnership agreements as a matter of law and that appellants were
    only entitled to indemnification. According to the court, "the
    facts established at trial show that the Dimeo suit could
    reasonably have been paid from partnership funds." Additionally,
    the court denied appellants' motion for a new trial. In the end,
    the court entered judgment awarding appellants indemnification
    payments in the amount of $2.1 million accruing interest at 6% per
    annum. By contrast, as a Deficit Loan, the amount the partnerships
    owed appellants would have accrued interest at 18% per annum.
    Appellants appeal both the judgment as a matter of law
    and the denial of their motion for a new trial.
    III. Discussion
    A. Judgment as a Matter of Law
    We review a district court's granting of judgment as a
    matter of law de novo. See Correa v. Hospital San Francisco, 69
    F.3d 1184, 1191 (1st Cir. 1995). "A judgment as a matter of law
    may be granted only if the evidence, viewed from the perspective
    most favorable to the nonmovant, is so one-sided that the movant is
    plainly entitled to judgment, for reasonable minds could not differ
    as to the outcome." Gibson, 37 F.3d at 735. In considering the
    evidence, we, like the district court, "cannot evaluate the
    credibility of witnesses, resolve conflicts in testimony, or
    evaluate the weight of evidence." Criado v. IBM Corp., 145 F.3d
    437, 441 (1st Cir. 1998) (citation and internal quotation marks
    omitted).
    During trial, appellants contended that the partnerships'
    admittedly plentiful funds were not reasonably available to pay the
    Dimeo settlement because of restrictions imposed by the loan
    agreements. Appellants also argued that FHS's refusal to permit
    BCA to use partnership funds further hindered these funds from
    being reasonably available.
    The court, however, rejected these theories as a matter
    of law because it regarded as undisputed two facts: (1) Bank of
    Boston had permitted Partnership 1 to distribute up to $15 million
    to the partners and this money could have been used to fund the
    settlement; and (2) Chiofaro's and Oatis's testimony that before
    FHS's objection on April 18, 1991, they intended to pay the
    settlement from partnership funds without obtaining bank approval
    demonstrated that loan restrictions did not hinder the use of
    funds. The court additionally found that FHS's refusal to permit
    the use of partnership funds was irrelevant because BCA, as
    managing general partner, had the authority to settle the lawsuit
    with partnership funds regardless of FHS's position.
    Reviewing the record in the light most favorable to
    appellants, we disagree with the district court's assessment of the
    evidence as undisputed. In our view, the jury verdict was
    adequately supported by appellants' evidence that partnership funds
    were not reasonably available because of loan restrictions and
    FHS's lack of cooperation. The partnerships' loan documents
    provided that all of the partnerships' assets served as collateral
    for the construction loan. Specifically, section 14(c) of the
    Construction Loan Agreement and the related Pledge and Escrow
    Agreement of Cash Account stated that Bank of Boston had a security
    interest in all of the partnerships' assets and that neither
    partnership could apply funds for any purpose without bank consent.
    Witness testimony further supported this documentary evidence:
    Chiofaro and Oatis testified that funds could not be used to pay
    the settlement without bank permission, which was not forthcoming;
    and Coleman Benedict, an FHS representative, testified that the
    partnerships did not have enough free cash to fund the settlement.
    It is true that Bank of Boston authorized the
    disbursement of $15 million to the partners, but appellants
    introduced evidence that these funds were not reasonably available
    to pay the Dimeo settlement. Fifteen million dollars had been
    earmarked for distribution on three dates: $8 million on June 5,
    1990, $3 million six months thereafter, and $4 million six months
    thereafter. According to loan documents and Oatis's testimony,
    these earmarked funds could not be distributed without bank
    approval on each disbursement date. Moreover, according to Oatis,
    the earmarked funds were not sufficient on April 19, 1991 to pay
    the $5.6 million settlement. Eight million dollars had already
    been distributed to the partners as of the first release date and
    therefore were no longer part of the partnership assets. The next
    $3 million were not distributed on the scheduled second
    disbursement date because that amount had been used to fund fifty
    percent of the Phase 2 construction expenses during the pendency of
    the Forbearance Agreement. Finally, the last $4 million were
    earmarked for distribution in May 1991, after the settlement
    payment was due. While BCA theoretically could have used the $4
    million in anticipation of the forthcoming release date, the jury
    could have found that FHS's threats, as well as uncertainty
    regarding the bank's required consent, rendered the funds not
    reasonably available on April 19, 1991. In all events, simple
    arithmetic proves that $4 million is not $5.6 million.
    We also disagree with the district court's decision that
    Chiofaro's and Oatis's testimony that they had initially intended
    to pay the settlement from partnership funds without obtaining bank
    approval is conclusive evidence that bank restrictions did not
    encumber partnership funds. While such testimony tends to prove
    that partnership funds were reasonably available, it is not
    conclusive evidence on this point. The jury could have credited
    Oatis's testimony that he did not intend to obtain bank permission
    before April 19 because it was not until that date that he realized
    the distribution of funds necessary for payment could not occur
    without FHS's cooperation.
    The testimony introduced at trial therefore sufficiently
    supported the jury's finding that funds were not reasonably
    available to settle the Dimeo suit on April 19, 1991. Under these
    circumstances, the district court erred in ruling as a matter of
    law that the conditions for a Deficit Loan had not been met. Thus,
    we reverse the court's judgment as a matter of law, reinstate the
    jury's finding that the conditions for a Deficit Loan were met, and
    remand so that judgment may be entered in accordance with this
    opinion.
    B. Motion for New Trial
    Appellants also challenge the district court's refusal to
    grant a new trial on damages, contending that the court's
    instructions to the jury on damages were erroneous and
    alternatively, that the jury's valuation of their damages at only
    $2.1 million is not supported by the evidence. We review the
    court's denial of a motion for a new trial for an abuse of
    discretion. See Air Safety v. Roman Catholic Archbishop of Boston,
    94 F.3d 1, 4 (1st Cir. 1996).
    According to appellants, the district court erred in
    instructing the jury that it could deduct the value of the limited
    partners' release from its base damages when there was no evidence
    of the value of the release in the record. See Kelliher v. General
    Transp. Serv., Inc., 29 F.3d 750, 754 (1st Cir. 1994) (jury
    instruction may not be given if there is insufficient evidence to
    support it).
    Appellants, however, did not preserve this argument for
    appeal. Fed. R. Civ. P. 51 states, in relevant part, that "[n]o
    party may assign as error the giving or the failure to give an
    instruction unless the party objects thereto before the jury
    retires to consider its verdict, stating distinctly the matter
    objected to and the grounds of the objection."
    Although appellants contend that they objected to the
    jury instruction and further submission of the issue, we have been
    unable to discern any such objection. Rather, our reading of the
    record indicates that appellants failed to object when the court,
    at the close of the evidence, instructed the jury:
    In calculating damages, I instruct you that
    the base figure on which your calculation is
    made is the 5.6 million paid to settle the
    suit. From that amount, you should deduct the
    value, if any, of the assets which you find
    that Chiofaro purchased from [the limited
    partners] in settlement of the suit, that is,
    what you find to be the value, again, if any,
    of the 22« percent interest in the BCA[-1]
    partnership, as well as the value of the
    release given Chiofaro by [the limited
    partners].

    Appellants also failed to object when the jury, after a period of
    deliberation, requested by note that the court "supply parameters
    'for the value of the release.'" Appellants' assertion that during
    a resulting lobby conference, they "stated that there existed no
    testimony in the record as to the value of the release [and]
    objected to additional instruction concerning the value of the
    release and to further submission of the issue to the jury"
    misstates the record. During the lobby conference, the court asked
    the parties whether there was testimony on the value of the
    releases. Counsel for appellants responded: "The only testimony,
    I believe, was opinion testimony on the value of the interest. So
    subtraction works, but I think that's unfair." Counsel did not,
    however, object to the court's instructing the jury to subtract the
    value of the release from the $5.6 million base figure. Rather,
    the only so-called objection noted by counsel at that time was
    "[y]ou've got to repeat your [earlier] instruction and say the
    evidence is the evidence." These comments, together, fall short of
    Rule 51's requirement that the objection "stat[e] distinctly the
    matter objected to and the grounds of the objection."
    Absent a timely objection, an erroneous jury instruction
    warrants a new trial only where the assigned error "'caused a
    miscarriage of justice or . . . undermined the integrity of the
    judicial process.'" Play Time, Inc. v. LDDS Metromedia
    Communications, Inc., 123 F.3d 23, 29 (1st Cir. 1997) (quoting
    Scarfo v. Cabletron Sys., Inc., 54 F.3d 931, 940 (1st Cir. 1995)).
    We see no miscarriage of justice here and therefore hold that
    appellants have waived their objection to the jury instruction.
    See, e.g., Play Time, 123 F.3d at 30, n.8 (no miscarriage of
    justice where the issue "implicates only the question of damages
    for breach of a private agreement between the litigants;" and no
    damage to integrity of the judicial process where "the proceedings
    below were conducted with meticulous attention to the rights of
    both parties").
    Appellants also make the argument that even if the value
    of the release played no role in the jury's reduction of its
    recovery so that the $3.5 million reduction represents the value
    of limited partnership interests only they are still entitled to
    a new trial on damages because the jury's valuation is not
    supported by the record. In challenging the jury's damage award,
    appellants face a daunting task. Our review "is limited to
    examining whether evidence in the record supports the verdict. If
    the jury award has a rational basis in evidence, we must affirm
    it." Air Safety, 94 F.3d at 4 (citation and internal quotation
    marks omitted). "While 'the jury may not render a verdict based on
    speculation or guesswork,' a reviewing court will not tinker with
    the jury's assessment of money damages as long as it does not fall
    outside the broad universe of theoretically possible awards that
    can be said to be supported by the evidence." Dopp v. Pritzker, 38
    F.3d 1239, 1249 (1st Cir. 1994) (citation omitted). In the end,
    "[w]e will not disturb an award of damages for economic loss
    provided it does not violate the conscience of the court or strike
    such a dissonant chord that justice would be denied were the
    judgment permitted to stand." Vera-Lozano v. Int'l Broadcasting,
    50 F.3d 67, 71 (1st Cir. 1995) (citation and internal quotation
    marks omitted).
    Here, the jury's valuation of the limited partnership
    interests falls within the broad universe of awards supported by
    the evidence. Together, the limited partners had a 22.5% interest
    in BCA-1, which in turn had a 40% interest in Phase 1. Thus, the
    limited partners had a 9% interest in Phase 1. Oatis testified
    during trial that, in 1989, he prepared for FHS a valuation of
    Phase 1 for $150 to $200 million. Using the 9% figure, the limited
    partnership interests in this amount would have been $13 to $18
    million. Francis McCarthy, former comptroller of Chiofaro Company,
    one of Chiofaro's interests, testified that, some time after August
    1990, Chiofaro asked him to calculate certain tax consequences of
    acquiring one of the limited partner's interest at purchase prices
    ranging from $1.96 to $4 million. The jury could have determined
    that this testimony reflected a proper valuation of one of the
    limited partner's interest. Appellants themselves introduced into
    evidence a letter from Richard Renehan, lead trial counsel for
    defendants in Dimeo, to Earl Cooley, counsel for plaintiffs,
    stating that defendants were "prepared to buy your clients out for
    cash at the fair market value of their interests" and offering $1.6
    million. Kevin Currier, the Chief Financial Officer of Dimeo
    Construction Company ("Dimeo"), a limited partner with a 20%
    interest in BCA-1, testified that, based on this letter, he valued
    the sale of Dimeo's interest at $1.5 million on Dimeo's 1991 tax
    return (and the IRS challenged this valuation as insufficient).
    Finally, Coleman Benedict testified that during settlement
    negotiations he discussed with Chiofaro the limited partners'
    interest at values ranging from zero to $15 million, depending on
    "assumptions you used about the condition of the market in the
    future." Based on the sum of this evidence, the jury could have
    reasonably valued the limited partnership interests in BCA-1 at
    $3.5 million. We will not second-guess its decision to do so.
    IV. Conclusion
    For the foregoing reasons, we reverse the decision of the
    district court in part and affirm in part. No costs.