Pat Wood and Johnny Wood v. Carpet Tech, Ltd. ( 2016 )


Menu:
  •                                         In The
    Court of Appeals
    Seventh District of Texas at Amarillo
    No. 07-16-00029-CV
    PAT WOOD AND JOHNNY WOOD, APPELLANTS
    V.
    CARPET TECH, LTD., APPELLEE
    On Appeal from the 72nd District Court
    Lubbock County, Texas
    Trial Court No. 2013-509,583, Honorable Ruben Gonzales Reyes, Presiding
    November 2, 2016
    MEMORANDUM OPINION
    Before QUINN, C.J., and CAMPBELL and HANCOCK, JJ.
    Pat and Johnny Wood (the Woods) appeal from a judgment denying them
    recovery against Carpet Tech, Ltd. (Carpet Tech).1 Their two issues implicate the legal
    and factual sufficiency of various fact findings executed by the trial court. Through the
    first they contend that neither legally nor factually sufficient evidence supports the trial
    court’s decision to reject their claim of usury. Through the second they assert that the
    decision to deny them damages similarly lacks evidentiary support. We affirm.
    1
    Carpet Tech filed a cross-appeal. It has since been dismissed per Carpet Tech’s motion.
    Background
    The dispute arose from a house fire experienced by the Woods. They hired
    Carpet Tech to conduct remediation efforts. Those efforts included both the salvaging
    of personalty and the demolition and reconstruction of various parts of the house. The
    combined bill for doing those tasks exceeded $200,000 and much of it was paid by the
    Woods as the work proceeded. However, they withheld a final payment approximating
    $25,860 because they believed the work done was deficient in several respects. Carpet
    Tech eventually assessed an interest charge on the outstanding sum at 1.5 % per
    month or 18% per annum. So too did it sue to recover the debt. In turn, the Woods
    filed their counterclaim against Carpet Tech, alleging multiple causes of action including
    one sounding in breached contract and another in usury.
    Trial was to the court. Thereafter, judgment was entered denying recovery to all
    the parties. Findings of fact and conclusions of law were also executed by the trial court
    in support of its judgment.
    Issue One — Usury
    In denying the claim of usury, the trial court found that “Carpet Tech did not
    improperly charge interest on the amounts it contended were due and owing by the
    Woods.”    The Woods now “challenge[] the legal and factual sufficiency of the trial
    court’s finding that Carpet Tech’s charge of at least 18% on the contents job invoice
    was legal.” Allegedly, they established as a matter of law the elements of usury, which
    elements consisted of proof that “(a) Carpet Tech loaned money to Wood by extending
    credit for the contents remediation services it rendered, (b) Wood had an absolute
    obligation to repay the contents invoice, and (c) Carpet Tech charged interest that
    2
    exceeded the maximum allowed by law.” The maximum, according to them, was 6%
    per annum. We overrule the issue.
    As argued by the Woods, they had to prove 1) the existence of a loan of money
    or extension of credit, 2) an absolute obligation to repay the principal, and 3) the
    exaction of greater compensation than that allowed by law for the borrower’s use of the
    money or credit.2 First Bank v. Tony’s Tortilla Factory, 
    877 S.W.2d 285
    , 287 (Tex.
    1994). It is the second element that we address.
    An absolute obligation to pay connotes the absence of any contingency. See
    Anglo-Dutchman Petroleum Int’l, Inc. v. Haskell, 
    193 S.W.3d 87
    , 96-97 (Tex. App.—
    Houston [1st Dist.] 2006, pet. denied) (stating that “appellees’ right to recover their
    principal and any return on their investment was contingent upon Anglo-Dutch’s cash
    recovery, if any, in the Halliburton lawsuit” which meant that “[p]er the unambiguous
    terms of the agreements, Anglo-Dutch did not have an absolute obligation to repay the
    principal amounts that appellees invested.”). In other words, if the obligation to pay is
    contingent, it is not an absolute one.      Id.; Wagner v. Austin Sav. & Loan Ass’n, 
    525 S.W.2d 724
    , 730-31 (Tex. Civ. App.—Beaumont 1975, no writ) (holding that there was
    no usury since repayment was dependent upon the occurrence of various
    contingencies, one of which encompassed the installation of the utilities in accordance
    with governing ordinances); Pansy Oil Co. v. Federal Oil Co., 
    91 S.W.2d 453
    , 457 (Tex.
    Civ. App.—Texarkana 1936, writ ref’d) (holding that there was no usurious transaction
    because repayment of any amount under said contract or the arrangement rested on
    contingencies of, first, drilling and, second, producing minerals in paying quantities).
    2
    We make no comment on whether such elements must be established in every claim of usury.
    Because the Woods argued that they applied here and attempted to show that those elements were
    proven, we address whether they met the burden.
    3
    The record before us shows that the Woods executed a “Repair & Pay
    Authorization” provided by Carpet Tech before initiation of the work. The document
    apparently reflects aspects of the agreement between the parties.       A portion of it
    specified that the Woods understand “that the full amount for the services provided will
    be due upon completion.” (Emphasis added). The record further reveals that they
    made payments to Carpet Tech as the work progressed. However, those payments
    eventually stopped.   They did so, according to the trial court, “. . . because [they]
    maintained that several parts of the jobs were improperly performed or not completed.”
    The trial court also found that Carpet Tech had “failed to fully perform under the
    agreement. . . .” No one disputes those findings. Nor do the Woods question the
    verbiage of the “Repair & Pay Authorization.” And, looking at that language again, it is
    clear that the Woods’ obligation to pay Carpet Tech was contingent upon Carpet Tech
    completing, or performing, its duties. So, there is some evidence of record upon which
    a rational factfinder could conclude that the Woods had no absolute obligation to pay
    monies demanded by Carpet Tech, especially when they and the trial court actually
    believed Carpet Tech did not fully perform. So, they did not prove their claim of usury,
    as a matter of law, as argued. See Torres v. McCann, No. 13-15-00187-CV, 2016 Tex.
    App. LEXIS 6079, at *15 (Tex. App.—Corpus Christi June 9, 2016, no pet.) (mem. op.)
    (stating that “[i]f sufficient evidence was presented such that ‘reasonable minds could
    differ about the fact determination to be made by the jury,’ then appellants are not
    entitled to judgment as a matter of law”). And, when the entire record is considered, we
    cannot say that the trial court’s decision to reject the usury claim was contrary to the
    overwhelming weight of the evidence so as to render the decision manifestly wrong or
    4
    unjust.     See Hardwick v. Smith Energy Co., No. 07-15-00083-CV, 2016 Tex. App.
    LEXIS 6805, at *4-5 (Tex. App.—Amarillo June 27, 2016, no pet.) (stating that when a
    party raises the claim of factual insufficiency, we consider all the evidence and set aside
    the finding only if the evidence supporting the finding is so weak or so against the
    overwhelming weight of the evidence that the finding is clearly wrong and unjust).
    Issue Two — Damages
    Next, the Woods aver that the trial court’s finding of no damages lacks the
    support of both legally and factually sufficient evidence. We disagree.
    The trial court entered a factual finding and legal conclusion directly pertaining to
    the damages. In the former, it ruled that with respect to the “estimated amounts to
    repair or complete the construction portion of the agreement,” the Wood’s expert “failed
    to provide any evidence that these amounts were reasonable or necessary.” Although
    the witness “recited that the amounts were customary or reasonable,” neither he nor the
    Woods “offer[ed] additional evidence to show any basis or support for the
    reasonableness of [the] amounts.”         Through the conclusion of law, it held that the
    Woods “failed to provide legally sufficient evidence to support any damage.” Our effort
    to assess whether this finding and conclusion are accurate begins with a brief
    discussion about the law of damages applicable to the breach of construction contracts.
    There are two ways to measure damages for breaching such an agreement.
    One involves remedial damages which are determined by “the cost to complete or
    repair less the unpaid balance on the contract price.” McGinty v. Hennen, 
    372 S.W.3d 625
    , 627 (Tex. 2012); CCC Group, Inc. v. South Cent. Cement, Ltd., 
    450 S.W.3d 191
    ,
    200 (Tex. App.—Houston [1st Dist.] 2014, no pet.). The other measure is known as the
    5
    “difference-in-value damages” or damages represented by the difference between the
    value of the building as constructed and its value had it been constructed according to
    the contract. McGinty v. 
    Hennen, 372 S.W.3d at 627
    .
    Where the first measure (i.e. remedial damages) is used, as here, the party
    seeking relief must prove that the damages sought were reasonable and necessary. 
    Id. To do
    so demands more than merely proffering evidence illustrating the nature of the
    injuries, the character of and need for the services rendered, and the amounts charged
    for the services. 
    Id. “Instead, some
    other ‘evidence showing that the charges are
    reasonable’ is required.” 
    Id., quoting, Dallas
    Ry. & Terminal Co. v. Gossett, 
    156 Tex. 252
    , 
    294 S.W.2d 377
    , 383 (Tex. 1956).     While one need not have a witness utter the
    buzzwords “reasonable and necessary” to satisfy the test, CCC Group, Inc. v. South
    Cent. Cement, 
    Ltd., 450 S.W.3d at 200
    , simply uttering those words is not enough
    either. See Nigalye v. Orr, No. 11-12-00003-CV, 2013 Tex. App. LEXIS 11247, at *10-
    11 (Tex. App.—Eastland August 30, 2013, no pet.) (mem. op.) (stating that “we do not
    agree that the evidence conclusively proves that $2,479,220.89 was the reasonable and
    necessary cost to complete the construction of the home” because the party seeking
    damages presented no evidence “of what work had to be performed . . . to complete the
    construction of the home as originally designed . . . [and] . . . other than Orr’s and
    Simpson’s conclusory testimony that the costs were reasonable and necessary,
    Appellants did not present any specific evidence explaining how [they] determined that
    the costs were reasonable and necessary.”); see also Dilston House Condo Ass’n v.
    White, 
    230 S.W.3d 714
    , 718 (Tex. App.—Houston [14th Dist.] 2007, no pet.) (involving
    an award of attorney’s fees and stating that general statements of reasonableness are
    6
    insufficient); Silverberg v. Texas Commerce Bank, N.A., No. 01-95-00564-CV, 1996
    Tex. App. LEXIS 3348, at *21 (Tex. App.—Houston [1st Dist.] 1996, no pet.) (involving
    an award of attorney’s fees and holding that conclusory statements in an affidavit are
    insufficient to defeat summary judgment and a general statement that the fee amount
    sought is reasonable and necessary will not support a finding of reasonableness). As
    indicated in Nigalye, there must be evidence explaining how or why the expense was
    reasonable and necessary. Nigalye v. 
    Orr, supra
    . Requiring the latter is no more than
    heeding the directive in Houston Unlimited, Inc. v. Mel Acres Ranch, 
    443 S.W.3d 820
    (Tex. 2014). There we were told that if the basis for an expert opinion is missing or the
    basis actually provides no support for the opinion, then the opinion is a mere conclusory
    statement lacking in evidentiary value. 
    Id. at 829.
    This is so because the evidentiary
    value of an expert’s testimony comes “from the basis [of his opinion], not from the mere
    fact that the expert said it.” 
    Id. With the
    foregoing in mind, we turn to the record before us. No doubt it contains
    testimony from an expert explaining what repairs or construction he thought needed to
    be done due to the breach by Carpet Tech.               They included 1) “[r]emoval and
    replacement of exterior siding per foot of ‘pine or equal’ siding and paint and caulk at
    $8.50 @ 1,581 sq. ft.= $13,438,” 2) “[w]idening of the garage opening and installation of
    18 foot door, paint and finish out $4,200,” 3) “[r]einstall interior 21 foot glass wall $8,000-
    $12,000,” 4) “[i]nterior repairs including paint, repair of paneling, repair cigarette
    damage on the mantle, close open space under sink, and miscellaneous $1,500-
    $3,000,” 5) “[r]eplace or repair windows $1,500-$3,000,” 6) “[r]oof repair $1,000-$5,000,”
    7) “[f]loor vents $500-$1,000,” 8) “[d]emolition of existing area and re-install kitchenette
    7
    in 4th bedroom $10,000,” and 9) “[o]verhead and profit = 20%.” When asked, the
    witness also testified that the charges or range of costs mentioned were “reasonable
    and customary.” And, when asked about the price range applicable to the listed tasks,
    he said normally if the work to be done was not as extensive as he may have thought,
    then the lower number would be appropriate or the cost would be less. That alone may
    lead a factfinder to reasonably deduce that some of the work factored into his estimate
    may not be necessary or that the expert may not have known about the extent of work
    actually needed.
    Nor can one easily ignore the difference between the sum depicting the lower
    range and that depicting the higher. In many cases the higher amount was twice that of
    the lower. That again could be viewed, by the factfinder, as casting doubt on what
    repairs were actually needed.
    Most importantly, though, is the general absence of information regarding how he
    derived either the lower or higher number or any number between them. Whether they
    generally reflected the average costs of materials or labor in the area or anywhere else
    is unknown. Nor was their evidence explaining (or providing a reasonable estimate of)
    the amount of materials needed to complete the work, the cost of the materials
    themselves, the quantum of manpower needed, and the cost of that manpower.3 In
    3
    For instance, the estimate for removing and replacing exterior siding was $13,438, according to
    the expert. The sum was derived by multiplying 1,581 sq. ft by $8.50 a sq. ft. One would think that the
    $8.50 a foot charge encompassed the cost of materials and labor. But, the expert did not explain what
    portion of the sum constituted the materials and what constituted labor. Nor did he explain why the costs
    of materials and labor implicit in the amount was reasonable. The same is true regarding the $1500-
    $3000 estimate for interior repairs. While he may have mentioned various components factored into the
    sum (e.g. 3 people working for 3 days at $50 and hour), he did not describe why or explain how the
    number of hours to be expended or the charge was reasonable. Nor did he discuss the materials to be
    used, their cost, and why that cost is reasonable. As acknowledged in McGinty, explaining how the figure
    was derived does not itself necessarily make the figure reasonable. McGinty v. Hennen, 
    372 S.W.3d 625
    , 628 (Tex. 2012).
    8
    other words, the basis for the dollar figures to which the expert opined is missing. Like
    the situation in Nigalye, no one explained “how [the expert] determined that the costs
    were reasonable and necessary.” Consequently, the expert’s opinions about the sums
    being “reasonable and customary” are mere conclusions and, therefore, no evidence,
    and no other evidence fills the void.4
    The trial court did not err in finding that no evidence illustrated that the damages
    sought by the Woods were reasonable and necessary. There being no evidence of the
    matter, it cannot be said that the evidence contradicting the trial court’s finding was so
    overwhelming as to merit a new trial. So, the Woods satisfied neither burden imposed
    by the standards of review applicable to claims of legal and factual insufficiency.
    Each issue is overruled, and the judgment is affirmed.
    Brian Quinn
    Chief Justice
    4
    This is not a situation where proof of damage was tendered via affidavit provided by § 18.001 et.
    seq of the Texas Civil Practice and Remedies Code. Our decision is not intended to address those cases
    holding that a mere statement that damages are reasonable and necessary is enough when the
    statement is uncontroverted. See e.g. Cactus Well Serv., Inc. v. Energico Prod., No. 02-13-00186-CV,
    2014 Tex. App. LEXIS 12573, at *22 (Tex. App.—Fort Worth November 29, 2014, pet. denied) (mem. op.)
    (holding that “Knight’s affidavit, which was uncontroverted and verified that Cactus’s charges and services
    were reasonable and necessary, was ‘sufficient evidence to support a finding of fact by judge or jury that
    the amount charged was reasonable or that the service was necessary” per § 18.001(b) of the Texas Civil
    Practice and Remedies Code).
    9