Riggs v. Curran , 863 F.3d 6 ( 2017 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 16-2083
    BENJAMIN RIGGS; LAURENCE EHRHARDT; and
    RHODE ISLAND MANUFACTURERS ASSOCIATION,
    Plaintiffs, Appellants,
    v.
    MARGARET CURRAN, PAUL ROBERTI, and HERBERT DESIMONE, JR.,
    in their official capacity as members of the Rhode Island Public
    Utilities Commission; NARRAGANSETT ELECTRIC COMPANY, INC., d/b/a
    NATIONAL GRID; and DEEPWATER WIND BLOCK ISLAND, LLC,
    Defendants, Appellees.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF RHODE ISLAND
    [Hon. William E. Smith, U.S. District Judge]
    Before
    Torruella, Thompson, and Kayatta,
    Circuit Judges.
    Andrew A. Rainer, with whom Brody, Hardoon, Perkins & Kesten,
    LLP, J. William Harsch, and J. William W. Harsch, Esq. & Associates
    were on brief, for appellants.
    Gerald J. Petros, with whom Adam M. Ramos and Hinckley, Allen
    & Snyder LLP were on brief, for appellee Deepwater Wind Block
    Island, LLC.
    Leo J. Wold, Assistant Attorney General, Department of
    Attorney General, was on brief, for appellees Curran, Roberti, and
    Desimone, Jr.
    Michael J. Fitzpatrick, with whom Day Pitney LLP was on brief,
    for appellee Narragansett Electric Company, Inc.
    July 10, 2017
    -2-
    TORRUELLA,       Circuit Judge.              Benjamin Riggs, Laurence
    Ehrhardt,     and      the    Rhode       Island     Manufacturers        Association
    (collectively,        "Plaintiffs")        challenge      the    development      of   an
    offshore wind farm (the "Wind Farm") near Block Island, Rhode
    Island.     The district court dismissed Plaintiffs' claims, ruling
    that they were barred by Rhode Island's three-year personal injury
    statute of limitations.            We affirm.
    I.   BACKGROUND
    A.   Factual Background
    In     2009,     the    Narragansett         Electric      Company,   d/b/a
    National Grid ("National Grid") entered into a power purchase
    agreement with Deepwater Wind Block Island, LLC ("Deepwater"),
    pursuant to a Rhode Island statute seeking to facilitate the
    development      of   a    "newly      developed    renewable       energy   resources
    project of ten (10) megawatts or less" near Block Island.                           2009
    R.I. Pub. Laws ch. 53, § 1.               Under the agreement, National Grid
    was to pass on the cost of constructing and operating the Wind
    Farm   to   mainland       Rhode       Island     ratepayers,     increasing      their
    electricity rates for up to twenty years.
    On     December      10,     2009,    National      Grid    submitted      the
    agreement    for      approval      to   the     Rhode   Island     Public   Utilities
    Commission (the "PUC"), which, on March 30, 2010, rejected the
    application because it was not commercially reasonable.                        The PUC
    -3-
    found, among other things, that ratepayers would pay above-market
    rates for the entire twenty-year period and that the project
    offered poor value when measured against other renewable-energy
    projects.
    On June 30, 2010, National Grid submitted a slightly-
    revised power purchase agreement (the "PPA") after the Rhode Island
    General Assembly amended the statutory definition of "commercial
    reasonableness" applicable to the Wind Farm and directed the PUC
    to apply this amended standard in reviewing any future application.
    See 2010 R.I. Pub. Laws ch. 32, § 1 (codified at 39 R.I. Gen. Laws
    § 39-26.1-7).     The PPA provided that "[t]he effectiveness of this
    Agreement . . . is conditioned upon and shall not become effective
    or binding until the receipt of the PPA Regulatory Approval,"
    meaning "the PUC's approval of this Agreement without material
    modification or conditions pursuant to [R.I. Gen. Laws § 39-
    26.1-7]."    On August 11, 2010, the PUC granted the approval, in
    large part due to the newly-adopted standard.           The PUC issued the
    order memorializing its decision on August 16, 2010 (the "PUC
    Order"), stating that the PPA "met the intent and requirements of
    the 2010 Amendments to R.I. Gen. Laws § 39-26.1-7."
    The   PUC     Order    contained   no   conditions     precedent,
    although    the   PPA's    terms    allowed    Deepwater   to    subsequently
    terminate the approved and effective PPA if certain tax credit
    -4-
    deadlines in the Internal Revenue Code were not extended, if
    Deepwater could not secure tax equity financing, or if Deepwater
    failed    to   timely   receive   additional   approvals   from     other
    government entities, including:
    1.    Approval and a license from the Rhode           Island
    Coastal Resources Management Council;
    2.    Permits under the federal Rivers and Harbors Act
    and the federal Clean Water Act from the U.S. Army
    Corps of Engineers;
    3.    A Conformity Determination/Air Emissions Permit and
    a General Stormwater Permit from the Environmental
    Protection Agency; and
    4.    Approval from the Rhode Island Department of
    Transportation, the Rhode Island Natural History
    Survey, and several municipal entities for laying
    the cable transmitting power from the Wind Farm to
    the mainland.
    After obtaining the PUC's approval, Deepwater applied for and
    received all required permits by the end of 2014.      In 2015, after
    the project received new financing, construction of the Wind Farm
    became imminent.1
    Throughout this period, the Wind Farm faced numerous
    challenges.     Multiple parties, including members of the Rhode
    Island Manufacturers Association, intervened in the PUC proceeding.
    Some parties then challenged the PUC Order on state law grounds in
    1  Deepwater states that it began constructing the Wind Farm in
    2015 and the Wind Farm became operational in December of 2016,
    but that is not part of the record.
    -5-
    the Rhode Island Supreme Court, and on August 1, 2011, that court
    affirmed the PUC Order.       In re Review of Proposed Town of New
    Shoreham Project, 
    19 A.3d 1226
    (R.I. 2011).
    Thereafter,    Benjamin    Riggs     filed      two   administrative
    petitions with the Federal Energy Regulatory Commission ("FERC")on
    August 22, 2012 and April 21, 2015, alleging that the PUC Order
    violated the Federal Power Act (the "FPA"), the Public Utilities
    Regulatory Policies Act ("PURPA"), and the Supremacy and Commerce
    Clauses of the U.S. Constitution.           On October 18, 2012 and June 18,
    2015, FERC issued notices of its intention not to act on the
    petitions   and   stated   that   "Mr.       Riggs    may    himself   bring   an
    enforcement action against the Rhode Island Commission in the
    appropriate court."       141 F.E.R.C. ¶ 61,172 (2012); 151 F.E.R.C.
    ¶ 61,222.
    B.   Procedural History
    Plaintiffs are Rhode Island ratepayers who claim that
    their economic interests will be adversely affected because the
    PPA will raise their electricity bills.              On August 14, 2015, four
    years and 364 days after the issuance of the PUC Order, Plaintiffs
    filed this lawsuit against three PUC commissioners, in their
    official capacities, National Grid, and Deepwater (collectively,
    "Defendants") in the United States District Court for the District
    of Rhode Island, arguing that the PUC Order violated the FPA,
    -6-
    PURPA,   and       the     Commerce      and    Supremacy      Clauses    of    the     U.S.
    Constitution.            The     district      court   never    reached    the    merits.
    Instead,      it    held    that       Plaintiffs'     complaint    was    time-barred.
    Riggs v. Curran, 
    196 F. Supp. 3d 338
    (D.R.I. 2016).                          It reasoned
    that 28 U.S.C. § 2462, the federal statute of limitations for civil
    enforcement actions, did not apply, as the case is neither a
    government enforcement action nor an enforcement action brought by
    a private attorney general.                
    Id. at 340-41.
    Instead, the district
    court applied Rhode Island's three-year statute of limitations for
    personal injury actions to Plaintiffs' claims.                      
    Id. at 341-42.
    The    district       court      then    determined     that      the   clock
    started to run on Plaintiffs' claims on August 16, 2010, when the
    PUC Order was issued.                  
    Id. at 340.
           It rejected Plaintiffs'
    arguments that their causes of action accrued only when Defendants
    obtained all of the permits required by the PPA, when Plaintiffs
    were first charged higher rates, or after Plaintiffs exhausted all
    of their administrative remedies.                    
    Id. at 342-44.
    II.    ANALYSIS
    We review a district court's order granting a motion to
    dismiss under Rule 12(b)(6) de novo.                   Guadalupe-Báez v. Pesquera,
    
    819 F.3d 509
    , 514 (1st Cir. 2016).                     "In conducting this review,
    we   accept    the       truth    of    all    well-pleaded     facts     and    draw   all
    reasonable inferences therefrom in the pleader's favor."                                
    Id. -7- (quoting
    Grajales v. P.R. Ports Auth., 
    682 F.3d 40
    , 44 (1st Cir.
    2012)).
    A.   Rhode Island's Three-Year Personal Injury          Statute   of
    Limitations Applies to Plaintiffs' Claims
    The parties dispute which statute of limitations applies
    to this action.    The statutes governing Plaintiffs' causes of
    action do not contain specific statutes of limitations, so we first
    must determine whether a general federal statute of limitations
    applies to any of Plaintiffs' causes of action.       If no general
    federal statute of limitations applies, the statute of limitations
    governing Rhode Island's most analogous state cause of action
    applies "if it is not inconsistent with federal law or policy."
    Barrett ex rel. Estate of Barrett v. United States, 
    462 F.3d 28
    ,
    38 (1st Cir. 2006) (quoting Wilson v. García, 
    471 U.S. 261
    , 266-
    67 (1985)).
    Plaintiffs'   constitutional     claims,   brought   under
    28 U.S.C. § 1983, are governed by Rhode Island's statute of
    limitations for personal injury actions.     See Marrapese v. Rhode
    Island, 
    749 F.2d 934
    (1st Cir. 1984) (applying Rhode Island's
    three-year statute of limitations for personal injury actions to
    a § 1983 action alleging constitutional violations); Walden, III,
    Inc. v. Rhode Island, 
    576 F.2d 945
    (1st Cir. 1978) (same).
    Rhode Island's three-year statute of limitations for
    personal injury actions also applies to Plaintiffs' claims under
    -8-
    the FPA and PURPA, although Plaintiffs urge us to apply the five-
    year statute of limitations in 28 U.S.C. § 2462, a general statute
    of limitations for "action[s], suit[s] or proceeding[s] for the
    enforcement of any civil fine, penalty, or forfeiture, pecuniary
    or otherwise."   Plaintiffs cite a number of federal cases applying
    § 2462 to actions brought under the FPA, PURPA, or other similar
    enforcement statutes.    Many of those cases, however, involve an
    enforcement action by a federal agency.2        Others include private
    plaintiffs, but they are enforcement actions brought by private
    attorneys   general   standing   in   the   government's   shoes.   For
    example, Plaintiffs cite National Parks Conservation Ass'n v.
    Tennessee Valley Authority, 
    480 F.3d 410
    (6th Cir. 2007), a
    private-citizen suit to enforce the pollution limitations imposed
    by the Clean Air Act.   But the Clean Air Act authorizes "any person
    [to] commence a civil action on his own behalf" against anyone who
    violates emission standards and authorizes the district courts "to
    apply any appropriate civil penalties" in those private suits.
    2  Cases cited by Plaintiffs that fall into this category include:
    3M Co. (Minn. Mining & Mfg.) v. Browner, 
    17 F.3d 1453
    , 1455-60
    (D.C. Cir. 1994) (applying § 2462 to an administrative civil
    penalty case brought by the Environmental Protection Agency); FERC
    v. Barclays Bank PLC, 
    105 F. Supp. 3d 1121
    , 1131 (E.D. Cal. 2015),
    as amended (May 22, 2015) ("The parties agree that the applicable
    statute of limitations is governed by 28 U.S.C. § 2462 . . . .");
    Fed. Election Comm'n v. Nat'l Right to Work Comm., Inc., 916 F.
    Supp. 10, 13 (D.D.C. 1996) (applying § 2462 to enforcement of civil
    penalties by the Federal Election Commission).
    -9-
    42 U.S.C. § 7604(a); see also Nat'l 
    Parks, 480 F.3d at 415
    n.3.3
    Private attorneys general enjoy this five-year tolling statute
    because they do not "personally benefit from bringing the action."
    Sierra Club v. Chevron U.S.A., Inc., 
    834 F.2d 1517
    , 1522 (9th Cir.
    1987) (applying § 2462 to a private enforcement action under the
    Clean Water Act).    Rather, they stand in the shoes of a regulatory
    agency.
    Plaintiffs, however, do not stand in FERC's shoes to
    enforce the FPA or PURPA; they seek to redress their own economic
    injuries caused by increased electricity rates.           Therefore, Rhode
    Island's   statute   of   limitations    for   personal   injury   actions,
    rather than § 2462, applies to Plaintiffs' FPA and PURPA claims.4
    3  Other cases cited by Plaintiffs that fall into this category
    include: Catskill Mountains Chapter of Trout Unlimited, Inc. v.
    City of New York, 
    451 F.3d 77
    , 88 n.14 (2d Cir. 2006) (applying
    § 2462 to a private enforcement action under the Clean Water Act);
    Trawinski v. United Techs., 
    313 F.3d 1295
    , 1298 (11th Cir. 2002)
    (applying § 2462 to a private enforcement action under the Energy
    and Policy Conservation Act); Sierra Club v. Chevron U.S.A., Inc.,
    
    834 F.2d 1517
    , 1522 (9th Cir. 1987) (applying § 2462 to a private
    enforcement action under the Clean Water Act for violation of
    Chevron's National Pollutant Discharge Elimination System permit);
    Tri-Dam v. Schediwy, No. 1:11-CV-01141 AWI-SMS, 
    2011 WL 6692587
    ,
    at *5 (E.D. Cal. Dec. 21, 2011) ("Tri-Dam brought this action . . .
    alleging that Defendants violated a permit" and "[t]he parties
    have identified 28 U.S.C. § 2642 as a relevant federal statute of
    limitations.").
    4  Plaintiffs do not dispute that, if § 2462 does not apply, Rhode
    Island's personal injury statute of limitations is the appropriate
    analogue.
    -10-
    B.   Plaintiffs' Claims Are Barred by the Applicable Statute of
    Limitations
    Plaintiffs assert that, even under Rhode Island's three-
    year statute of limitations, their claims survive because they did
    not become ripe for adjudication until late 2014, when Deepwater
    had received all of the permits necessary to complete the Wind
    Farm, at the earliest.         Defendants, meanwhile, defend the district
    court's ruling that the clock began to run when the PUC Order
    issued on August 16, 2010.
    1.   Legal Background
    We    have   previously    decided    three    cases    that     are
    particularly relevant to this dispute:                 City of Fall River v.
    FERC, 
    507 F.3d 1
    (1st Cir. 2007); Weaver's Cove Energy, LLC v.
    Rhode Island Coastal Resources Management Council, 
    589 F.3d 458
    (1st Cir. 2009); and Town of Barnstable v. O'Connor, 
    786 F.3d 130
    (1st Cir. 2015).
    In Fall River, the plaintiffs challenged a FERC order
    granting conditional approval to an energy company to construct a
    liquefied natural gas ("LNG") 
    terminal. 507 F.3d at 3
    .          In its
    order granting the conditional approval, FERC imposed numerous
    conditions        precedent,    "including      approval    of     the     vessel
    transportation plan by the United States Coast Guard (the "USCG")
    and consistency with the Wild and Scenic Rivers Act, as determined
    by   the   Department     of   the   Interior   (the    "DOI")."     
    Id. The -11-
    plaintiffs brought their suit before either the USCG or the DOI
    had made a final decision.     
    Id. at 5.
        We held that FERC's order
    was not ripe for review.    
    Id. at 6.
       FERC's approval was "expressly
    conditioned on approval by the USCG and the DOI," but neither
    agency had approved the project at the time of the appeal, and
    both had "expressed serious reservations about the project."       
    Id. at 7.
        Because FERC's approval was not final without decisions by
    the USCG and the DOI, we thought it "wiser to allow the agencies
    to continue their decision-making process at least until final
    authorization [was] granted by all three agencies."        
    Id. at 7-8.
    We observed that this would not cause undue hardship to the
    plaintiffs because "the statute of limitations period [would] not
    begin to run . . . until [the energy company] obtain[ed] those
    approvals," and so they could renew their claims at a later date.
    
    Id. at 7.
    Weaver's Cove involved the same LNG 
    terminal. 489 F.3d at 465
    .    In that case, a Rhode Island agency raised two "regulatory
    barriers" to the project.    
    Id. at 461.
       Whether the energy company
    could meet the requirements of the conditional FERC approval at
    issue in Fall River and obtain a necessary approval from the Army
    Corp of Engineers were potentially contingent on the validity of
    those barriers.     
    Id. at 465.
       We determined that the issue was
    ripe for review.       
    Id. at 468.
          We distinguished Fall River
    -12-
    because, in that case, FERC's order was contingent on other
    conditions, including the decisions of the USCG and the DOI, and
    so "we could not be sure our opinion would not be advisory."            
    Id. at 468-69.
      In Weaver's Cove, however, the Rhode Island agency's
    requirements "would cease to be barriers to ultimate approval of
    the project," and so our decision would be final even though it
    "might not secure the project's ultimate approval."         
    Id. at 469.
    In Barnstable, the third and final case, the plaintiffs
    sued   commissioners   of    the   Massachusetts   Department   of   Public
    Utilities ("DPU"), Cape Wind Associates ("Cape Wind"), and NSTAR
    Electric Company 
    ("NSTAR"). 786 F.3d at 133-34
    .    The plaintiffs
    alleged that the DPU commissioners violated the Commerce Clause
    and the Supremacy Clause by approving, and possibly forcing, a
    power purchase agreement between Cape Wind and NSTAR for power
    generated by Cape Wind's proposed offshore wind project.             
    Id. at 137.
      The district court dismissed the plaintiffs' claims, and
    before we could hear the plaintiffs' appeal, NSTAR terminated the
    contract with Cape Wind, although Cape Wind contested the validity
    of that termination.        
    Id. at 142.
       After supplemental briefing,
    we found that the case was ripe, even in light of the recent
    contract dispute, because the basic question raised by the suit
    -- whether the DPU "unconstitutionally forced NSTAR to enter a
    contract with Cape Wind" -- depended only on "events that ha[d]
    -13-
    already occurred."        
    Id. at 143.
           Therefore, although the contract
    dispute between the parties raised the likely possibility that the
    case    would     be   moot   in    the   future,   that   possibility    did   not
    implicate whether the precise issue currently before the court was
    ripe for decision.            
    Id. We reiterated
    that a case is ripe for
    decision if a holding on the merits would cause the contested
    agency action to "cease to be barriers to ultimate approval of the
    project."       
    Id. (quoting Weaver's
    Cove, 589 F.3d at 468-69
    ).
    2.     Plaintiffs' Claims Accrued More Than Three Years Before
    They Filed Their Complaint
    This case is distinguishable from Fall River, on which
    Plaintiffs rely, for one crucial reason:                   FERC's order in Fall
    River was specifically conditioned on the energy company obtaining
    favorable determinations from the USCG and the 
    DOI. 507 F.3d at 3
    .        There was no final order because the conditions precedent
    in FERC's conditional order had not been satisfied.                      Thus, the
    challenge to FERC's order was not ripe.
    This    case    is   more    similar   to    Weaver's     Cove   and
    Barnstable, where we found the plaintiffs' claims ripe.                   Although
    there were numerous hurdles to completing the Wind Farm when the
    PUC Order issued, the same was true in those two cases, including
    similar approvals from other regulatory bodies in Weaver's Cove.
    But, like the regulatory decisions in Weaver's Cove, the PUC Order
    was a discrete, final decision; later decisions by other agencies
    -14-
    could not change the PUC Order, unlike FERC's conditional order in
    Fall River.     The PUC Order also affected the "ultimate approval
    of the project," Weaver's 
    Cove, 589 F.3d at 469
    , because if it was
    unconstitutional or exceeded the PUC's authority, the Wind Farm
    might never be constructed.
    Plaintiffs' argument that their claims were not ripe
    because   the   project   could    be   derailed      by   future    regulatory
    decisions or a lack of financing is foreclosed by Barnstable.                  The
    PUC Order is unrelated to those other potential barriers, and
    Plaintiffs'     constitutional     claims   were   not     affected     by    the
    existence of future contingencies.            The fact that the project
    might be derailed implicates mootness, not ripeness.                An earlier-
    filed case could have become moot if the Wind Farm was not
    completed, but "[i]f we were to find the possibility of future
    mootness to be the type of contingency that would create a lack of
    ripeness, we would simply be changing mootness doctrine to signal
    a lack of jurisdiction not merely when a controversy is moot, but
    also when it might become moot."        
    Barnstable, 786 F.3d at 143
    .
    Plaintiffs'    claims    thus    accrued    when   the    PUC     Order
    became final.5     Because Plaintiffs filed their claims more than
    5  The district court ruled that the PUC Order was final on
    August 16, 2010, the day PUC issued it. We note that the Rhode
    Island Supreme Court did not affirm the PUC Order until August 1,
    2011. No party argues that the PUC Order became final on that
    date, however, and even if it did, that decision also issued more
    -15-
    three years later, their claims are barred by the applicable three-
    year statute of limitations.
    III.    CONCLUSION
    For the reasons stated, we affirm the district court's
    judgment.   Costs to appellees.
    Affirmed.
    than three years before Plaintiffs filed their complaint.       We
    therefore need not address whether that appeal affected        the
    finality of the PUC Order.
    -16-