J-Way Southern, Inc. v. United States Army Corps of Engineers ( 2022 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 21-1144
    J-WAY SOUTHERN, INC.,
    Plaintiff, Appellant,
    v.
    UNITED STATES ARMY CORPS OF ENGINEERS,
    Defendant, Appellee.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Patti B. Saris, U.S. District Judge]
    Before
    Thompson, Lipez, and Kayatta,
    Circuit Judges.
    Ian J. Pinta, with whom Christopher Weld, Jr. and Todd & Weld
    LLP were on brief, for appellant.
    Anne Murphy, Attorney, Appellate Staff, Civil Division, with
    whom Nathaniel R. Mendell, Acting United States Attorney, Brian M.
    Boynton, Acting Assistant Attorney General, and Charles W.
    Scarborough, Attorney, Appellate Staff, Civil Division, were on
    brief, for appellee.
    May 10, 2022
    THOMPSON, Circuit Judge.         Today, we write primarily for
    the parties named in this case's caption, and we therefore assume
    their familiarity with the facts and travel, as well as the issues
    raised and arguments presented.        This allows us to get straight to
    it, offering the basics and some supplemental information as needed
    along the way.
    This matter arises out of a terminated June 2015 contract
    for dredging waterways in Menemsha Harbor, Martha's Vineyard --
    i.e., moving "sandy material from the channels and anchorage of
    . . .    Menemsha   Creek"   to    Lobsterville   Beach   via   a   temporary
    hydraulic pipeline.     J-Way Southern ("J-Way") got this gig after
    it was the lowest bidder on a United States Army Corps of Engineers
    ("USACE")    solicitation    for    the   dredging   work.      But   J-Way's
    performance, in     USACE's view, was deficient:             J-Way did not
    complete the work within the timeframe set forth in the contract.
    There was some procedural scuffling regarding J-Way's default on
    the contract, and, ultimately, USACE terminated the contract.1             J-
    1 A first termination for default was rescinded by USACE after
    J-Way argued in an administrative claim under the Contract Disputes
    Act ("CDA") that its delay was excusable, and that was followed by
    an agreement between J-Way and USACE to proceed. But J-Way again
    experienced delays and USACE determined the failure to perform was
    not excusable, and it therefore issued a second termination notice
    for default. USACE made a demand upon J-Way's performance bond to
    get the work done, and, thereafter, USACE and J-Way's surety
    executed a Takeover Agreement that led to a new contractor being
    procured by the surety. For its part, J-Way eventually (two-plus
    years   after   the   default   termination)    submitted   another
    administrative claim under the CDA, arguing the second default
    - 2 -
    Way filed suit, alleging improper termination and breach of the
    contract by USACE. In response, USACE moved to dismiss for failure
    to state a claim.          The district court granted USACE's dismissal
    motion, ruling (as is relevant to our decision today) that J-Way's
    claims were time-barred.         J-Way S., Inc. v. United States, 
    516 F. Supp. 3d 84
    , 94 (D. Mass. 2021).           J-Way appeals.
    After careful de novo review (see, e.g., N.R. by &
    through S.R. v. Raytheon Co., 
    24 F.4th 740
    , 746 (1st Cir. 2022))
    of   the    record,   the    parties'     appellate   submissions,    and   the
    applicable law, we spy no basis to disturb the district court's
    decision, which is comprehensive and well-reasoned.                  And "when
    lower      courts   have    supportably    found   the   facts,   applied   the
    appropriate legal standards, articulated their reasoning clearly,
    and reached a correct result, a reviewing court ought not to write
    at length merely to hear its own words resonate."            deBenedictis v.
    Brady-Zell (In re Brady-Zell), 
    756 F.3d 69
    , 71 (1st Cir. 2014);
    see also Vargas-Ruiz v. Golden Arch Dev., Inc., 
    368 F.3d 1
    , 2 (1st
    Cir. 2004) ("[W]hen a trial court accurately sizes up a case,
    applies the law faultlessly to the discerned facts, decides the
    matter, and articulates a convincing rationale for the decision,
    there is no need for a reviewing court to wax longiloquent.").
    termination was unlawful. No action was taken by USACE on that
    claim because it understood the claim to be time-barred.  That
    second default termination is the impetus for the instant
    litigation.
    - 3 -
    This case fits that mold.      We thus affirm substantially on the
    basis of Judge Saris' thorough decision.
    Before we reach our brief discussion of the arguments
    advanced on this appeal, though, we must pause to have a look at
    a jurisdictional issue that was much debated below.     That debate
    hasn't been revisited before us on appeal, but "[t]his Court has
    an independent duty to assess the existence of subject matter
    jurisdiction."    Almeida-León v. WM Cap. Mgmt., Inc., 
    993 F.3d 1
    ,
    11 n.13 (1st Cir. 2021) (citing Espinal-Domínguez v. Puerto Rico,
    
    352 F.3d 490
    , 495 (1st Cir. 2003)).
    Jurisdiction
    When J-Way filed its complaint in district court, it
    asserted admiralty jurisdiction because the parties' dispute arose
    out of a maritime contract under the CDA, 
    41 U.S.C. § 7102
    (d).
    Disagreeing with that jurisdictional premise, the government moved
    to dismiss or transfer for lack of subject matter jurisdiction,
    arguing, inter alia, that "[t]he contract is a standard Army Corps
    construction contract, . . . and disputes arising from such
    contracts have been resolved at specialty government contract
    appeal boards or in the U.S. Court of Federal Claims for over 150
    years."   According to the government, its contract with J-Way was
    "not a maritime contract in whole or in part" -- the contract
    contemplated "digging earth, not [water] navigation," and thus was
    "a   standard    federal   construction   contract."   Indeed,   the
    - 4 -
    government, citing a history of dredging-contract-dispute cases
    being heard in the Court of Federal Claims, insisted that court,
    as well as agency boards, have always exercised jurisdiction over
    matters such as this.             J-Way retorted that the dispute did not
    arise from a construction contract at all; rather, the dispute
    clearly had its genesis in a maritime contract, with the contract's
    principal purpose being the traditionally maritime activity of
    dredging to make a waterway more navigable to promote commerce.
    Accordingly, J-Way argued, the federal district court in which it
    had   filed     its   case    actually       enjoyed   exclusive   jurisdiction
    pursuant to 
    28 U.S.C. § 1333
    (1) (providing that "[t]he district
    courts shall have original jurisdiction, exclusive of the courts
    of the States, of . . . [a]ny civil case of admiralty or maritime
    jurisdiction") and the CDA, 
    41 U.S.C. § 7102
    (d) (excepting appeals
    "arising out of maritime contracts" from the jurisdiction of the
    Court of Federal Claims or the agency boards of contract appeals).
    After hearing argument on the issue, the district court
    denied    the    motion      to    dismiss    for   lack   of   subject   matter
    jurisdiction, holding that it had admiralty jurisdiction over the
    dredging contract dispute.           J-Way S., Inc. v. United States, 
    460 F. Supp. 3d 65
    , 70 (D. Mass. 2020). That decision wasn't appealed.2
    2We note that an appeal of that decision wouldn't have landed
    on our desks; it would've gone to the Federal Circuit pursuant to
    
    28 U.S.C. § 1292
    (d)(4)(B).
    - 5 -
    Before     us,   the   government       now    agrees    that   "[t]he
    district court had jurisdiction over this Contract Disputes Act
    action under 
    28 U.S.C. § 1333
    (1), and 
    41 U.S.C. §§ 7102
    (d) and
    7104(b)."      But     we    are   dutybound       to    probe    subject   matter
    jurisdiction nonetheless.            We, like the district court, find
    subject matter jurisdiction exists, and we agree with the district
    court's    reasoning    that   led     to   this    conclusion.        By   way    of
    explanation, we borrow extensively from the district court's sound
    analysis (again, see In re Brady-Zell, 756 F.3d at 71) and pepper
    that solid reasoning with a few of our own observations.
    Generally, the United States Court of Federal Claims has
    exclusive jurisdiction over contract claims against the U.S. in
    excess of $10,000, see 
    28 U.S.C. §§ 1346
    (a)(2), 1491(a)(1), but
    the CDA vests admiralty jurisdiction in the federal district courts
    for lawsuits against the U.S. that "aris[e] out of maritime
    contracts," 
    41 U.S.C. § 7102
    (d).3              See also 
    28 U.S.C. § 1333
    (providing    exclusive      federal    district        court    jurisdiction     for
    "[a]ny civil case of admiralty or maritime jurisdiction"); 46
    3   
    41 U.S.C. § 7102
    (d) provides:
    Maritime contracts. – Appeals under section 7107(a) of
    this title and actions brought under sections 7104(b)
    and 7107(b) to (f) of this title, arising out of maritime
    contracts, are governed by [the Suits in Admiralty Act]
    or [the Public Vessels Act], as applicable, to the extent
    that those [Acts] are not inconsistent with this
    chapter.
    - 6 -
    U.S.C. § 30906 (instructing that civil actions in admiralty against
    the U.S. must be brought in federal district court); El–Shifa
    Pharm. Indus. Co. v. United States, 
    378 F.3d 1346
    , 1353 (Fed. Cir.
    2004) (noting that 
    28 U.S.C. § 1333
     "grant[s] exclusive and
    original jurisdiction to federal district courts over civil cases
    in admiralty and maritime jurisdiction"); Thrustmaster of Tex.,
    Inc. v. United States, 
    59 Fed. Cl. 672
    , 673-74 (2004) (observing
    that exclusive jurisdiction to hear CDA claims regarding maritime
    contracts lies with the federal district courts).
    Whether a contract is a maritime contract is a difficult
    question given the conceptual (rather than spatial) boundaries of
    admiralty jurisdiction, Norfolk S. Ry. Co. v. Kirby, 
    543 U.S. 14
    ,
    23 (2004), and "the answer 'depends upon . . . the nature and
    character of the contract,'" 
    id. at 24
     (alteration in original)
    (quoting N. Pac. S.S. Co. v. Hall Bros. Marine Ry. & Shipbuilding
    Co., 
    249 U.S. 119
    , 125 (1919)).   "[T]he true criterion" for making
    this determination is "whether [the contract in question] has
    'reference to maritime service or maritime transactions.'"     
    Id.
    (quoting Hall Bros., 
    249 U.S. at 125
    ).    Indeed, "the fundamental
    interest giving rise to maritime jurisdiction is the protection of
    maritime commerce."   Id. at 25 (cleaned up) (quoting Exxon Corp.
    v. Cent. Gulf Lines, Inc., 
    500 U.S. 603
    , 608 (1991)).
    In view of that interest, a court's inquiry should be
    focused "on whether the principal objective of a contract is
    - 7 -
    maritime commerce."          Id.; see also P.R. Ports Auth. v. Umpierre-
    Solares, 
    456 F.3d 220
    , 224 (1st Cir. 2006) (describing this inquiry
    as    one   focused     on    "whether      the    contract    'relate[s]      to    the
    navigation, business or commerce of the sea'" (alteration in
    original) (quoting Cunningham v. Dir., OWCP, 
    377 F.3d 98
    , 109 n.11
    (1st Cir. 2004))).            Because "[w]hile it may once have seemed
    natural       to   think     that    only    contracts       embodying    commercial
    obligations between the 'tackles' (i.e., from port to port) have
    maritime objectives, the shore is now an artificial place to draw
    a line" -- "[m]aritime commerce has evolved along with the nature
    of transportation and is often inseparable from some land-based
    obligations."         Kirby, 
    543 U.S. at 25
    ; cf. 
    id. at 27
     ("If a
    [contract]'s sea components are insubstantial, then the [contract]
    is not a maritime contract.").
    The government's argument against the district court's
    exercise of jurisdiction over the contract dispute boiled down to
    a customs/historical practice position:                Citing cases dating back
    to 1857, the government observed that the Court of Federal Claims
    (and    its    predecessor,         the   United    States    Claims     Court)     have
    exercised jurisdiction over government dredging contract disputes
    since that time.        But, as the district court explained, "no court
    has squarely considered whether a government dredging contract is
    a    maritime      contract,"   and       "[t]he   Supreme    Court,     the   Federal
    Circuit, and the Court of Federal Claims have all held that they
    - 8 -
    are 'not bound by a prior exercise of jurisdiction in a case where
    it was not questioned and it was passed sub silentio.'"               J-Way,
    460 F. Supp. 3d at 69 (quoting United States v. L.A. Tucker Truck
    Lines, Inc., 
    344 U.S. 33
    , 38 (1952), and citing Huston v. United
    States, 
    956 F.2d 259
    , 261 (Fed. Cir. 1992); Red River Holdings,
    LLC v. United States, 
    87 Fed. Cl. 768
    , 796 n.33 (2009)).               "The
    Court of Federal Claims' exercise of jurisdiction over government
    dredging contract disputes has never been analyzed."           
    Id.
    And so, plotting a course through these new waters, the
    district court deployed that "principal objective" analysis the
    Supreme Court set out in Kirby, 
    543 U.S. at 25
    , to determine
    whether the contract was a maritime contract such that the district
    court had jurisdiction over the dredging contract dispute before
    it.   Here's how that went.
    "The undisputed purpose of the contract was to dredge a
    navigable waterway and then deposit sand on a beach."             J-Way, 460
    F. Supp. 3d at 69 (citing the contract's explanation that "[t]he
    work of this project will consist of the maintenance dredging of
    shoaled areas within the existing Federal Navigation Channel").
    Dredging    a   navigable    waterway   is   traditionally    a    maritime
    activity,   and   such   a   dredging   contract   facilitates     maritime
    commerce, which anchors maritime jurisdiction.               Id. at 69-70
    (citing Misener Marine Constr., Inc. v. Norfolk Dredging Co., 
    594 F.3d 832
    , 837 (11th Cir. 2010) (concluding that a dredging contract
    - 9 -
    was a maritime contract because its "primary objective . . . was
    dredging a navigable waterway," and that "had a direct effect on
    maritime services and commerce")); see also Weston/Bean Joint
    Venture v. United States, 
    123 Fed. Cl. 341
    , 375 (2015) (observing
    that the U.S. Army Corps manual defines "maintenance dredging" as
    "[t]he cyclic dredging of the same area over a period of time to
    remove accumulating sediments and to maintain ship and barge
    traffic" (alteration in original)).4
    The district court was unpersuaded by the government's
    argument, based on federal regulations referring to dredging as a
    type of construction, that the principal objective of this contract
    was construction, rather than maritime commerce -- indeed, the
    "regulatory description does not determine the jurisdictional
    question   where,   as   here,    the     primary   objective   of   the
    'construction' was to assist maritime commerce."         J-Way, 
    460 F. 4
     And Puerto Rico Ports Authority, 
    456 F.3d at 225
    , found a
    maritime contract when parties entered into it for the purpose of
    securing removal of a sunken boat from San Juan Harbor's navigable
    waters since its purpose thus was removing an obstruction to
    maritime navigation and commerce. See 
    id.
     (comparing D.M. Picton
    & Co., Inc. v. Eastes, 
    160 F.2d 189
    , 192-93 (5th Cir. 1947)
    (reasoning that "it would be difficult to imagine a contract more
    completely maritime" than a contract for removal of materials that
    were "menaces to navigation," and, accordingly, holding that a
    claim for breach of contract "to remove hazards to navigation" was
    within admiralty jurisdiction), with R. Maloblocki & Assocs., Inc.
    v. Metro. Sanitary Dist., 
    369 F.2d 483
    , 485 (7th Cir. 1966)
    (explaining that the purpose of the dredging contract there was
    flood control and "any effect the project may have had upon
    navigability was, at best, incidental," so the contract was not
    maritime in nature (internal quotation marks omitted))).
    - 10 -
    Supp. 3d at 70.        The district court was similarly unpersuaded by
    the government's point that substantial portions of the contract's
    period were meant to be spent on what it viewed as purely non-
    maritime     things,     like    grading        the   beach,     mobilizing       and
    demobilizing    equipment,       constructing         a   temporary     land-borne
    pipeline, and, in doing these things, using equipment that was not
    vessel-borne.    That's all well and good.            But no legal support was
    offered to explain "why these considerations should outweigh the
    contract's plain language and compensation scheme."                
    Id.
            Overall,
    "the contract provisions demonstrate that the primary purpose of
    the dredging was to facilitate maritime commerce."                 
    Id.
    And while it was true that the contract's additional
    objectives    included       protecting    local      wildlife    and    restoring
    Lobsterville Beach (where the dredged sediment was to be deposited,
    recall), the government simply had "not produced any evidence from
    which th[e c]ourt [could] find that those objectives were the
    primary purpose of the contract" under Kirby's test.                    
    Id.
        "[T]he
    plain language of the contract indicates that J-Way was paid based
    on the amount of sediment dredged," and "[t]he contract provided
    no separate remuneration for depositing the sediment or grading
    the beach."      
    Id.
     (citing Kirby, 
    543 U.S. at 25
     (noting that
    maritime   commerce     is    "often    inseparable       from   some   land-based
    obligations")); see also Kirby, 
    543 U.S. at 27
     ("[A contract's]
    character as a maritime contract is not defeated simply because it
    - 11 -
    also provides for some land carriage.").            This was driven home by
    the government's concession "that less time was allocated to
    grading the beach than to dredging the sediment."                    J-Way, 460 F.
    Supp. 3d at 70.
    Therefore,    the    district     court      concluded       that,   with
    "[s]ubstantial    portions    of   the    contract     .    .    .   dedicated    to
    improving the navigability of a waterway," "[j]urisdiction over
    this contract dispute properly lies in the federal district court."
    Id.
    And we agree -- this contract is, as the saying goes, of
    a "genuinely salty flavor." Kirby, 
    543 U.S. at 22
     (quoting Kossick
    v. United Fruit Co., 
    365 U.S. 731
    , 742 (1961) (Harlan, J.)).                     Its
    nature and character sound in maritime services, with the contract
    aimed at protecting and effectuating maritime commerce via the
    goal of improving navigability of the waterway.                 See generally id.
    at 23-25, 27; P.R. Ports Auth., 
    456 F.3d at 224
    .                     Its principal
    objective was maritime commerce.          See Kirby, 
    543 U.S. at 25
    .             For
    all of these reasons, the federal district court had jurisdiction
    over this maritime contract dispute.
    Merits
    Jurisdiction navigated, we turn now to the merits.
    The    CDA,   as    regulated     by   the       Federal     Acquisition
    Regulations ("FAR"), which govern contracts with the government,
    specifies that an appeal of a final default decision must be made
    - 12 -
    to the appropriate agency board within ninety days from the date
    of its receipt or to the federal court within twelve months from
    the date of its receipt.   See 
    41 U.S.C. § 7104.5
         J-Way's improper
    default   termination   claim   wasn't   filed   within   the   statutory
    deadline, and J-Way does not attempt to argue otherwise.         Instead,
    as it argued below, J-Way insists that its claim should not be
    time-barred because the 2017 termination notice was defective in
    that it didn't comply with the FAR:        It failed to inform J-Way
    that it was a final decision and referred J-Way only to the
    contract's disputes clause, which states nothing about the appeals
    process or J-Way's appellate rights. J-Way argues it detrimentally
    relied on that fatally flawed notice.       What's more, says J-Way,
    its claim could also be considered timely under the               Fulford
    doctrine, see Fulford Mfg. Co., 
    ASBCA No. 2143
    , 
    ASBCA No. 2144
    (May 20, 1955), since that doctrine extends the time in which a
    contractor can challenge a default termination if the contractor
    is assessed reprocurement costs.    J-Way's thinking is that, "where
    5 As explained above, the jurisdictional provision of the
    Suits in Admiralty Act, 
    46 U.S.C. § 30906
    , overrides that of the
    CDA to govern this maritime contract. The Suits in Admiralty Act
    also provides for a two-year statute of limitations, 
    id.
     § 30905
    -- one year longer than that of the CDA, 
    41 U.S.C. § 7104
    (b)(3).
    In their briefs on appeal, neither party argues that the longer
    limitations period should govern this maritime contract or would
    bear on the issue of notice. And J-Way's suit (filed more than
    two years after the default termination), see J-Way, 460 F. Supp.
    3d at 67, would have been untimely even under a two-year
    limitations period. We therefore express no view on the question.
    - 13 -
    a surety pays a replacement contractor and then assesses those
    reprocurement costs against the defaulted contractor," the Fulford
    doctrine should be extended to apply to that situation as well.
    J-Way acknowledges no court has actually done what it's asking us
    to do on this point, but says "it stands to reason that" the
    doctrine could apply as J-Way wants.        And J-Way tells us its other
    distinct breach of contract claims also are timely -- they don't
    arise from the default termination and were filed within six years
    of USACE's independent breaches of the dredging contract.6            See 
    41 U.S.C. § 7103
    (a)(4)(A) (setting a six-year limitations period for
    contract claims against the government).
    As we said when we kicked off today's opinion, the
    district   court   thoughtfully    dealt    with   these   issues   already,
    concluding that, under the applicable legal framework, all of J-
    Way's claims are time-barred, and none of J-Way's above-listed
    arguments against that conclusion persuade.           J-Way, 516 F. Supp.
    3d at 89-93.   We substantially echo the district court's reasoning
    on each issue.     Specifically:
    6 J-Way also alleged assigned claims on behalf of J-Way's
    surety, and the district court had to figure out whether the
    assignment of the surety's claims to J-Way was invalid.        It
    concluded that the surety could not assign its claims to J-Way.
    J-Way, 516 F. Supp. 3d at 94. Before us, J-Way does not challenge
    this aspect of the district court's ruling.
    - 14 -
    •   The   second   termination    notice    was      missing   the   required
    regulatory     language,   yes.7      But   it    provided   J-Way   with
    adequate notice nonetheless.           It explained J-Way was in
    default but could appeal pursuant to the contract's disputes
    clause -- and the disputes clause (which consists of § 52.233-
    1 of the FAR, as incorporated by reference in the contract)
    in turn states the contracting officer's decision on a claim
    is "final unless the Contractor appeals or files a suit as
    provided in 41 U.S.C. chapter 71" (with § 7104 laying out the
    ninety-day or twelve-month time limit for appealing).              Id. at
    7 The   missing   regulatory   language   comes   from   FAR
    33.211(a)(4)(v).    Pursuant to 
    41 U.S.C. § 7103
    (e), "[t]he
    contracting officer's decision shall state the reasons for the
    decision reached and shall inform the contractor of the
    contractor's rights as provided in this chapter."     And the FAR
    provision instructs that "the contracting officer shall . . .
    [p]repare a written decision that shall include . . . [p]aragraphs
    substantially as follows:"
    This is the final decision of the Contracting Officer.
    You may appeal this decision to the agency board of
    contract appeals. If you decide to appeal, you must,
    within 90 days from the date you receive this decision,
    mail or otherwise furnish written notice to the agency
    board of contract appeals and provide a copy to the
    Contracting Officer from whose decision this appeal is
    taken.   The notice shall indicate that an appeal is
    intended, reference this decision, and identify the
    contract by number.
    
    48 C.F.R. § 33.211
    (a)(4)(v). It also explains that a contractor
    can "bring an action directly in the United States Court of Federal
    Claims (except as provided in 41 U.S.C. [§] 7102(d), regarding
    Maritime Contracts) within 12 months of the date [the contractor]
    receive[s] th[e] decision." Id.
    - 15 -
    90-91; see also RMA Eng'g S.A.R.L. v. United States, 
    140 Fed. Cl. 191
    , 216 (2018) (finding that a notice of termination was
    valid   under    the   CDA   where   the   notice   stated    that     the
    contractor had the right to appeal under the disputes clause).
    This means that even though the notice omitted the regulatory
    language,   it   was   not   prejudicially    defective      because    it
    provided J-Way with adequate notice.
    •   Because we conclude that the notice was not defective from an
    adequate-notice standpoint, we need not weigh in on J-Way's
    argument that it detrimentally relied on a defective notice.
    (That said, we tend to agree with the district court's
    explanation that J-Way's asserted detrimental reliance was
    unreasonable because it failed to allege any facts to "support
    a reasonable belief that the [g]overnment would reconsider
    the second Termination for Default."         J-Way, 516 F. Supp. 3d
    at 91.)
    •   Next, we decline to extend the scope of the Fulford doctrine
    in the novel way J-Way urges us to.          The doctrine "allows a
    contractor to challenge a [g]overnment assessment for excess
    reprocurement costs by challenging the underlying termination
    for default, even if a challenge to the termination for
    default would otherwise be time-barred."            Id. at 92 (citing
    MES, Inc. v. United States, 
    104 Fed. Cl. 620
    , 635 (2012)).
    The purpose of the doctrine is not to allow contractors to
    - 16 -
    bring untimely claims in the circumstances in which J-Way
    finds itself, i.e., the government has made no claim for
    reprocurement costs against J-Way.   
    Id.
       So J-Way cannot lean
    on Fulford to resuscitate untimely claims that have nothing
    to do with excess reprocurement costs.8
    •   And the district court was right that the breach of contract
    claims are all based on the same set of facts and seek the
    same relief as the improper termination claim, amounting to
    impermissible "back-door challenges" to the decision to issue
    the second default termination notice.      
    Id.
     at 93 (citing
    Mil. Aircraft Parts, 
    ASBCA No. 60139
    , 
    16-1 BCA ¶ 36390
     (June
    3, 2016) (declining to field a breach of contract claim in a
    similar situation, i.e., when the "affirmative claim sets
    8We take this opportunity to explain a bit more about why we
    decline to extend Fulford to situations in which the government
    has made no claim against the contractor in default. Aside from
    what we've just explained, there are several reasons for our
    rejection of J-Way's invitation to do so: (1) The contractor will
    know when demand is placed on its surety; indeed the contractor
    will in most cases of charged default -- as here -- know that there
    is a risk of reprocurement costs; (2) Appealing or suing within
    the statutory period is a readily available safe harbor; (3) The
    risk of engaging in litigation that turns out to have been
    unnecessary can be mitigated with a standstill or tolling
    agreement; and (4) If contractors could wait until the surety
    actually makes demand on the contractor, there would be no final
    decision by the government to trigger the appeal clock, and the
    government would lose the ability to secure repose. In so holding,
    we doubt that we create a trap for the unwary: J-Way was notified
    at the time of its termination that the government was making a
    claim on J-Way's performance bond, and should have anticipated
    that its surety would seek to recoup any excess costs.
    - 17 -
    forth actions on the part of [the government] . . . that may
    have constituted [contract] breaches," but the breach of
    contract   claim   "is   based   on   the   same   set   of   facts,
    circumstances, and actions preceding the default terminations
    and is inextricably bound up with the issue of the propriety
    of those terminations" (alterations in original))).
    And so we reject J-Way's arguments against the operation
    of the time bar and decline to breathe new life into the untimely
    complaint.   All we'll add -- though we think it plenty clear on
    the face of the district court's decision -- is this.                The
    termination notice bespeaks finality over and over, plus, from the
    adequate-notice standpoint, it provided the relevant regulatory
    and statutory breadcrumbs a reader could (and should) follow to
    find the appellate logistics.9 There is nothing unreasonable about
    expecting a company with the benefit of counsel (like J-Way) to
    follow the sources from one to the other to obtain the appellate
    9 No one says the notice provided the required regulatory
    language -- the government didn't try to, nor could it. In its
    brief, the government indicates that the notice provided "was
    technically defective under the FAR, but it contained the critical
    information necessary for J-Way to appeal." At oral argument, the
    government tried to walk that back, stating it was not conceding
    the notice was defective. In any event, we would have echoed the
    district court's call for the government to "include the specific
    language provided in FAR 33.211(a)(4)(v) in future notices," J-
    Way, 516 F. Supp. 3d at 91 n.9, but, as the government explained
    at oral argument, it has since done exactly that "as a matter of
    best agency practice."
    - 18 -
    rights information that is clearly laid out in the disputes
    clause's provisions. See, e.g., Turner Constr. Co., Inc. v. United
    States, 
    367 F.3d 1319
    , 1321 (Fed. Cir. 2004) (explaining that
    parties to government contracts are responsible for knowing what
    laws   apply    to     the     contract,       "and   reasonable   professional
    competence     in    reading    .   .   .    contracts   is   presumed").   The
    government met its obligation to inform J-Way of its rights by
    giving adequate notice.
    Conclusion
    The district court's order granting the government's
    motion to dismiss is affirmed.              Each side shall bear its own costs.
    - 19 -