John Hancock Life v. Abbott Laboratories ( 2006 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 05-2710
    JOHN HANCOCK LIFE INSURANCE COMPANY;
    JOHN HANCOCK VARIABLE LIFE INSURANCE COMPANY;
    and INVESTORS PARTNER LIFE INSURANCE COMPANY,
    Plaintiffs, Appellees,
    v.
    ABBOTT LABORATORIES,
    Defendant, Appellant;
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT MASSACHUSETTS
    [Hon. Douglas P. Woodlock, U.S. District Judge]
    Before
    Torruella and Lipez, Circuit Judges
    and Stafford,* District Judge.
    Lawrence R. Desideri, with whom Stephen V. D'Amore, Peter E.
    Gelehaar, Michael S. D'Orsi, Winston & Strawn, LLP, and Donnelly,
    Conroy & Gelharr LLP were on brief, for the appellant.
    Brian A. Davis, with whom Joseph H. Zwicker, Stacy Blasberg,
    and Choate, Hall & Stewart LLP were on brief, for the appellee.
    September 28, 2006
    AMENDED OPINION**
    *
    Of the Northern District of Florida, sitting by designation.
    ** This opinion has been amended solely to comport with sealing
    orders issued by the district court and this court. The amendments
    do not in any way affect the substance of the opinion.
    LIPEZ,     Circuit    Judge.      John    Hancock     Life    Insurance
    Company    and   two   of   its   subsidiaries       (collectively       "Hancock")
    contracted with Abbott Laboratories ("Abbott") to join in financing
    the development of some pharmaceutical compounds.                   In exchange,
    Abbott promised to share with Hancock any profits the compounds
    would generate.        It soon became apparent that a number of the
    compounds had no good prospect of commercial success.                          Abbott
    scaled    back   and   delayed    its   planned      investment    in    the   joint
    project.    Arguing that Abbott had failed to uphold its part of the
    bargain, Hancock stopped contributing funds altogether.                     Hancock
    then sued for a declaratory judgment, asking the district court to
    rule that, under the contract between the parties, Abbott's delayed
    investment allowed Hancock to terminate its payments but retain its
    share of any future profits.        Abbott countersued, arguing that the
    contract explicitly allowed it to delay its contributions to the
    project.    The parties consented to have the district court decide
    the case on the papers submitted, and, on cross motions, the
    district court entered judgment for Hancock.                    Abbott appeals,
    essentially arguing that the district court incorrectly construed
    the contract.     We affirm.
    I.
    We discuss the contract between Hancock and Abbott and then
    their course of dealings.         We leave some details for discussion in
    connection with Abbott's appellate arguments.
    -2-
    A.   The contract
    In 1999, Hancock and Abbott began negotiating the joint
    venture at issue.   While the specifics evolved through 40 contract
    drafts, the basics of the final agreement are relatively simple.
    Abbott and Hancock would select a "basket" of research compounds
    that Abbott had identified as possible pharmaceutical products and
    that Hancock thought were promising.     Hancock would contribute
    multiple millions each year for four consecutive years towards the
    development of these compounds.   Abbott would spend at least 1.86
    times as much as Hancock over this initial period of development.
    The parties would share any profits from the compounds for roughly
    fifteen years from the contract's inception, and Abbott would pay
    Hancock set amounts when the joint project accomplished certain
    development or regulatory goals.     In short, Hancock agreed to
    provide substantial start-up investment for the project, and Abbott
    agreed to match that investment.      Because Hancock would share
    profits only for a set number of years, it stood to gain if the
    compounds were developed quickly (and if they turned out to be
    useful) and stood to lose if development were delayed (or if the
    compounds were unsuccessful).
    For our purposes, the final contract between the parties,
    which was signed on March 13, 2001, can be summarized.
    ! The parties agreed to partner in the development
    of a basket of     compounds, with each compound
    thought to have a potential pharmaceutical use.
    -3-
    ! Hancock agreed to reimburse multiple millions of
    Abbott's spending on the joint project in four
    multiple million dollar payments – one for each
    year 2001 through 2004.
    ! Abbott agreed to provide an additional annual
    minimum contribution of un-reimbursed funds to the
    project in each of the four years.
    ! Abbott also agreed that its and Hancock's
    combined spending on the project would be "at
    least" the Aggregate Spending Target over the
    "Program Term," which the contract defined as "a
    period of four (4) consecutive Program Years."1 In
    other words, by December 31, 2004, Abbott would
    provide approximately two-thirds of the Aggregate
    Spending Target to the project above and beyond the
    one-third of the Aggregate Spending Target that
    Hancock promised to contribute.
    ! Abbott was "permitted" to "change its funding
    obligations [] only as follows":
    (a) If Abbott expended Hancock's yearly
    contribution during a "Program Year" but did
    not contribute its annual minimum contribution
    of its own un-reimbursed funds, Abbott could
    "carryover" its obligation to the following
    year.     The balance of Abbott's yearly
    obligation, termed the "Annual Carryover
    Amount," would be added to Abbott's minimum
    contribution for the "subsequent Program
    Year."      If   Abbott   carried   over   its
    contribution, Hancock's obligations for the
    "subsequent Program Year" would be suspended
    until Abbott spent the "Annual Carryover
    Amount."
    (b) If Abbott did not spend the entire
    Aggregate Spending Target "during the Program
    Term," it could "carryover" the balance to the
    "subsequent year commencing immediately after
    1
    The contract defined a "Program Year" as a full calendar year
    beginning on January 1 and ending on December 31, except that the
    first "Program Year" would be shortened to begin of the day the
    contract was signed and to end on December 31, 2001.
    -4-
    the end of the Program Term." If there was
    such a carryover, the difference between the
    Aggregate Spending Target and the amount
    actually spent by the end of the "Program
    Term" would be called the "Aggregate Carryover
    Amount."
    ! Abbott would update Hancock at least yearly about
    the project, providing an "Annual Research Plan"
    with a budget for future spending.     Abbott would
    also provide yearly "Status Reports" stating the
    company's spending on the joint project so far.
    Hancock's payments were due 30 days after receiving
    these documents.
    ! In certain enumerated circumstances, including if
    Abbott "does not demonstrate in its Annual Research
    Plan its intent and reasonable expectation" to
    spend at least the Aggregate Spending Target in
    joint funds on the project "during the Program
    Term,"   Hancock's   funding    obligations   would
    terminate but the rest of the contract (detailing
    how the parties would share profits) would remain
    in effect.
    ! Even if one of the enumerated terminable events
    came to pass and Hancock's payment obligations were
    cancelled, Hancock would still have to pay its
    contributions for the year in which the terminable
    event took place.
    B.   The parties' dealings
    2001
    Abbott's first "Annual Research Plan" was appended to the
    final contract, which was executed on March 13, 2001.        It called
    for total project spending almost double the Aggregate Spending
    Target by the end of 2004.     Under this plan, Abbott would spend
    many millions of dollars of its own funds, or roughly five times as
    much as Hancock, through the end of 2004.       During 2001, Abbott
    decided to halt development of some compounds. In November, Abbott
    -5-
    sent Hancock a document titled "2002 Preliminary Annual Research
    Plan," which called for total spending of less than Abbott's first
    Annual Research Plan but more than the Aggregate Spending Target
    through 2004. In December, Abbott sent the "2001 Status Report" on
    the year's spending, revealing that spending on the project would
    total multiple millions less by year's end (compared to the amount
    that had been planned). Abbott's cover letter for the "2001 Status
    Report" stated that Hancock's 2001 payment was due in 30 days, an
    indication that Abbott believed its contractual obligations for the
    year had been satisfied.      This was so even though the only "Annual
    Research Plan" Abbott had given Hancock was marked "Preliminary."
    Abbott did not manifest any intention to send an update to the
    "2002 Preliminary Annual Research Plan."         Apparently agreeing that
    the "Preliminary" plan satisfied Abbott's reporting obligation for
    2001, and that Abbott's obligations for that year were complete,
    Hancock timely provided its 2001 contribution of multiple millions.
    2002
    In   2002,   Abbott    decided   to    terminate   development   of   an
    additional compound because the scientific results did not warrant
    further development.       Abbott also dramatically reduced efforts on
    some other compounds.       As a result, less than two years into the
    joint project, Abbott was      pursuing a significantly smaller number
    of the    original basket of compounds with full effort.              Abbott
    submitted its "2002 Status Report" and the "2003 Preliminary Annual
    -6-
    Research Plan" together on December 20, 2002.                The Status Report
    revealed that 2002 spending on the project would be far less than
    the "2002 Preliminary Annual Research Plan" had promised. The Plan
    stated that spending for 2003 would also be significantly less than
    Abbott had estimated the year before.                 The Plan, however, was
    silent as to 2004.          Unlike the previous year's version, the Plan
    divulged the company's planned spending only for the next year.
    (Abbott later explained that the 2004 numbers had not been listed
    in   the   "2003   Preliminary      Annual     Research   Plan"    because     of   a
    computer error.)       As it had the previous year, Abbott stated in a
    cover    letter,     also   sent   on    December   20,   that    Hancock's    2002
    contribution was due in 30 days.                Again, Abbott manifested no
    intention to update its "Preliminary" report and gave no indication
    that the document was not the planning statement required by the
    contract.     Hancock timely provided its reimbursement of multiple
    millions.2
    2003
    During further review of the "2003 Preliminary Annual Research
    Plan,"     Hancock    noticed      the   document's    failure     to   make    any
    prediction of spending in 2004, a lapse that the company appears to
    have overlooked on its initial review.              During a September 9, 2003
    conference call, Hancock asked Abbott to supplement the plan with
    2
    The 30th day after December 20 was January 19, a Sunday. Hancock
    tendered its payment the next business day. Abbott accepted the
    payment without comment and agrees that it was timely.
    -7-
    the missing information.       Abbott's Controller then sent Hancock a
    letter, dated September 22, 2003, stating the following:
    I went back to review the data and spend estimates
    made about 1 year ago for 2003. On 8/26/02, the
    estimated program spend for 2003 was at [more than
    indicated in the 2003 Preliminary Annual Research
    Plan].   By October 14, 2002, after the Executive
    Committee's portfolio review, the estimated spend
    for 2003 had dropped to [approximately the same
    amount as in the 2003 Preliminary Annual Research
    Plan] and for 2004, it was at [an amount that when
    added to the spending for 2001, 2002 and 2003 was
    less than the Aggregate Spending Target].
    This was an important admission.            Abbott confirmed that if there
    had   been   no   computer   error   and    the   "2003    Preliminary   Annual
    Research Report" had included planned spending for 2004, it would
    have shown that Abbott planned to spend only an amount less than
    previously projected, which would mean that spending through the
    end of 2004 would total -- at the most -- an amount less than the
    Aggregate    Spending   Target.       The    earlier      status   reports   had
    indicated that Abbott's spending for 2001 and 2002 would be higher.
    In its October 2002 reviews, Abbott had projected higher spending
    for 2003 and for 2004.
    To the same September 22, 2003 letter, Abbott attached a
    document it called "the Final 2003 Plan."          This version of the 2003
    plan indicated that Abbott's spending during the Program Term would
    be even lower than it had projected in October 2002.                     Abbott
    forecasted total spending of less than the Aggregate Spending
    Target through 2004 and an additional amount in 2005.               Under this
    -8-
    projection, total spending through 2004 would fall many millions
    short of the Aggregate Spending Target.                    However, Abbott would
    exceed the threshold if 2005 spending were included.
    After reviewing the updated 2003 plan, Hancock sent Abbott a
    letter, dated October 10, stating that its "obligation to make any
    remaining   Program    Payments       to    Abbott   for    [2003   and    2004]   is
    terminated" because "the Final 2003 Plan, in conjunction with the
    more limited information contained in the Preliminary 2003 Annual
    Research Plan . . . did not, and does not, reasonably demonstrate
    Abbott's intent and reasonable expectation to" spend the Aggregate
    Spending Target on the joint project "during the Program Term."
    Shortly thereafter, Abbott sent Hancock a "2004 Preliminary
    Annual Research Plan," which projected total project spending                      for
    2004 and 2005.     Cumulative spending on the project would be less
    than the Aggregate Spending Target through 2004 and more than the
    Aggregate   Spending      Target   through       2005.       The    same   document
    indicated that Abbott would spend well below the annual minimum in
    2003 provided for under the contract.
    Hancock never made a contribution for 2003.                        Rather, the
    company   sued   Abbott    in   the    district      court    for   a   declaratory
    judgment that its payment obligations had terminated.                         After
    pretrial proceedings, the parties consented to have the district
    court resolve their dispute on the papers as a "case stated,"
    meaning that the district court "could make findings of fact
    -9-
    instead    of   granting    inferences    to    each   non-movant   in   turn."
    DiGregorio v. Hartford Comp. Employee Ben. Serv. Co., 
    423 F.3d 6
    ,
    12 (1st Cir. 2005).         In due course, the district court issued a
    thorough 65-page opinion, finding in Hancock's favor both on the
    question of whether Abbott was required to plan on spending at
    least the Aggregate Spending Target through 2004, and on whether
    Abbott's failure to do so allowed Hancock to cancel its 2003
    payment, as well as its payment for 2004.
    II.
    The district court determined that, for the most part, the
    contract    between   the    parties     was   "unambiguous   and   that   the
    interpretation proffered by Hancock is the only reasonable one."
    The district court did identify two ambiguities in the contract
    that were relevant to the dispute between the parties.              As to one
    of these ambiguities, which we explain later in this opinion, the
    district court considered extrinsic evidence and made findings of
    fact on the intent of the contracting parties.           As we also explain,
    the other "ambiguity" identified by the district court was really
    an issue of contract interpretation, and was resolved as such.               On
    both issues, the district court concluded that Hancock had the
    stronger case.
    On appeal, Abbott challenges the district court's findings and
    conclusions with three arguments.              First, Abbott says that the
    contract allowed it to plan to spend the Aggregate Spending Target
    -10-
    over    five   years   instead      of    four.     Anticipating       the   possible
    rejection      of   this   claim,    Abbott       also   makes   two    alternative
    arguments that, if accepted, would entitle it to Hancock's 2003
    payment of multiple millions.             Abbott says that the event allowing
    Hancock to stop paying happened in 2003, not 2002, and so Hancock
    had to make its payment for that year.3              Even if the relevant event
    happened in 2002, meaning that Hancock was potentially freed of its
    obligation to make a 2003 payment, Abbott contends that Hancock
    waived that right by failing to recognize the 2002 event promptly.
    We address these arguments in turn.
    A.     Jurisdiction and standard of review
    Like the district court, we will accept the parties' agreement
    on forum selection and choice of law.                    The contract allows any
    disputes between the parties to be decided in the federal district
    court in Massachusetts.        Based on the parties' complete diversity
    of citizenship and the dollar amount at issue, this case is
    properly in federal court.               See 
    28 U.S.C. § 1332
    .         The contract
    calls on us to apply Illinois contract law (Abbott is based in
    Illinois), which the parties agree should govern.                 We are "free to
    forego independent inquiry and accept that agreement."                   Cochran v.
    Quest Software, Inc., 
    328 F.3d 1
    , 6 (1st Cir. 2003).
    As to matters of law decided on summary judgment, such as
    3
    As we noted above, the contract provided, "For the avoidance of
    doubt, [Hancock's] Program Payments for the Program Year in which
    [a terminable] event occurs shall still be due and payable."
    -11-
    contract interpretation, our review is de novo.             See Utica Mutual
    Ins. Co. v. Weathermark Investments, Inc., 
    292 F.3d 77
    , 80 (1st
    Cir. 2002).      If it were necessary to review the district court's
    factual findings, our review would be far more deferential.                 See
    Principal Mutual Life Ins. Co. v. Racal-Datacom, Inc., 
    233 F.3d 1
    ,
    3 (1st Cir. 2000).       However, as we will discuss, we believe that
    the   contract    is   unambiguous   on   the   points    necessary   for   the
    disposition of this appeal, permitting us to affirm on the plain
    meaning of the contract alone.              See States Res. Corp. v. The
    Architectural Team, Inc., 
    433 F.3d 73
    , 80 (2005) (recognizing that
    the court of appeals can affirm a grant on summary judgment on any
    basis made apparent by the record).
    B. Abbott's planning obligations
    Hancock's position is easily summarized. The contract allowed
    Hancock to stop paying if Abbott did not "reasonably demonstrate in
    its Annual Research Plan, its intent and reasonable expectation to
    expend on Program Related Costs during the Program Term an amount
    in excess of [the Aggregate Spending Target]" (emphasis added).
    The contract defines "Program Term" as "a period of four (4)
    consecutive Program Years" (emphasis added).             The contract defines
    "Program Year" as "a period of twelve (12) consecutive calendar
    months commencing on January 1 of each year, except that the first
    Program Year shall commence on the Execution Date and end on
    December 31, 2001."       This means, according to Hancock, that the
    -12-
    "Program Term" ended on December 31, 2004, and that Abbott was
    required to budget in its "Annual Research Plans" to spend the
    Aggregate Spending Target by that date.                   Since Abbott planned to
    spend less than the Aggregate Spending Target by the end of 2004,
    Hancock could stop paying.
    Abbott's more complicated position relies on the fact that the
    "carryover" provisions in the contract allowed the company to
    postpone    actual    attainment        of   the   Aggregate      Spending   Target
    threshold    until    the   end    of   2005.       According     to   Abbott,    the
    carryover provisions, by implication, also freed the company of any
    obligation to plan to spend all of the Aggregate Spending Target by
    the end of 2004. Hancock counters that the carryover provisions do
    not by their terms apply to Abbott's planned spending, but only to
    its actual spending.        The sense of this distinction, Hancock and
    the district court agreed, is that unforseen circumstances during
    the   fourth   year    might      reasonably       have    been   thought    by   the
    contract's     drafters     to     excuse      strict      compliance    with     the
    contractually agreed spending, even if a mere change in plans on
    Abbott's part would not.
    Hancock has by far the stronger argument.                   As the district
    court recognized, Abbott's approach is belied by the contract's
    definition of "Program Term."
    In Illinois, as elsewhere, "[i]t is a basic and fundamental
    tenet of contract law [] that even if a contract offers only a
    -13-
    limited definition of a term, it must be applied as written."
    Conn. Specialty Ins. Co. v. Loop Paper Recycling, Inc., 
    824 N.E.2d 1125
    , 1133 (Ill. App. 2005).   Put another way: "A court . . . may
    not interpret [a] contract in a way contrary to the plain and
    obvious meaning of its terms."    Krilich v. American Nat. Bank &
    Trust Co. of Chicago, 
    778 N.E.2d 1153
    , 1164 (Ill. App. 2002).   See
    also In re Blinds to Go Share Purchase Litigation, 
    443 F.3d 1
    , 7
    (1st Cir. 2006) ("Where the parties to a contract take pains to
    define a key term specially, their dealings under the contract are
    governed by that definition."); Alexian Bros. Health Providers
    Ass'n v. Humana Health Plan, Inc., 
    330 F. Supp. 2d 970
    , 975 (N.D.
    Ill. 2004) ("[P]arties to a contract may serve as their own
    lexicographers and may assign a particular meaning to any word they
    choose.").
    In light of these precedents, we need look no further than the
    contract's own definition of "Program Term" as "a period of four
    (4) consecutive Program Years."       When the contract said that
    "Hancock's obligation to make any remaining Program Payments    . .
    . shall terminate" if Abbott did not "reasonably demonstrate in its
    Annual Research Plan, its intent and reasonable expectation to
    expend on Program Related Costs during the Program Term an amount
    in excess of [the Aggregate Spending Target]" (emphasis added), the
    contract meant that Hancock could stop paying if Abbott did not
    "demonstrate . . . its intent and reasonable expectation" to spend
    -14-
    the money by the end of 2004.     Abbott insists that "[n]owhere does
    [the contract] provide that Abbott must forfeit Hancock's payments
    if Abbott forecasts [] that it will need [a] fifth year" to spend
    the Aggregate Spending Target.     But the contract provides exactly
    that.
    As the district court stated, reading the contract as it was
    written does not somehow make the contract illogical, irrational,
    or "commercially unreasonable."     Cf. Beanstalk Group, Inc. v. A.M.
    Gen. Corp., 
    283 F.3d 856
    , 860 (7th Cir. 2002) ("[A] contract will
    not be interpreted literally if doing so would produce absurd
    results that the parties, presumed to be rational persons pursuing
    rational ends, are unlikely to have agreed to seek.").          Abbott and
    Hancock reasonably could agree that Abbott would be bound by the
    contract to make all reasonable efforts to spend the Aggregate
    Spending Target on the joint project by the end of 2004.          Hancock
    had obvious reasons to prefer such an obligation: the more Abbott
    spent on the project during its first four years, the greater
    Hancock's returns were likely to be.         Abbott had good reasons to
    accede to Hancock's demands: Hancock provided an enormous infusion
    of funds on favorable terms.       And Abbott and Hancock reasonably
    could   agree   that,   despite   Abbott's    obligation   to   make   all
    reasonable attempts to spend the Aggregate Spending Target through
    2004, the company should have the ability to stretch its actual
    expenditure of funds into a fifth year, if unexpected events during
    -15-
    2004 made it impossible to spend the money as soon as planned.   The
    parties shared an interest in avoiding unnecessary or inefficient
    last-minute spending on the project.   In light of these plausible
    goals, it made sense for the contract to provide that Abbott was
    required to plan to spend the Aggregate Spending Target by December
    31, 2004, but that it was not required to actually spend the money
    by that time.     Whether this was the best, fairest, or most
    efficient way to structure the contract is not our concern.4
    Referring to the rule that a contract must be read as a whole,
    Abbott places great reliance on the appearance of the phrase "any
    extension period of the Program Term" in the contractual definition
    of "Program Related Costs." "Program Related Costs," not otherwise
    relevant here, were costs that Abbott could count as expenditures
    on the joint program.   The definition provided:
    "Program Related Costs" shall mean (i) all direct
    and indirect costs and expenses that are incurred
    by Abbott during a given Program Year . . . and
    (ii) the milestone and license fees paid during a
    given Program Year or during any extension period
    4
    Abbott says repeatedly -- in its brief and at oral argument --
    that the contract must be read to impose a two to one ratio of
    Abbott's spending to Hancock's.    Abbott criticizes the district
    court for allowing actual spending in roughly a four to one ratio.
    But the contract never required Hancock to spend half as much as
    Abbott. Indeed, Abbott's initial projection was that it would spend
    five times as much as Hancock. What the contract did not allow was
    for Abbott to spend less than 1.87 times as much as Hancock
    (Hancock's maximum contribution was approximately one-third of the
    Aggregate Spending Target, and Abbott's minimum was approximately
    two-thirds of the Aggregate Spending Target). Our resolution of
    this dispute is fully consistent with these principles agreed to by
    the parties.
    -16-
    of the Program Term . . ..
    According to Abbott, the phrase "extension period" in the above-
    quoted paragraph frees the company from any obligation to plan for
    spending the Aggregate Spending Target by the end of 2004.
    The district court found Abbott's "extension period" argument
    unpersuasive.        We agree, though for different reasons.5          The
    language Abbott relies on does not purport to alter the meaning of
    "Program Term," which is the definition that matters in the section
    allowing Hancock to terminate its payments.        As the district court
    stated, "the Agreement defines 'Program Term' specifically and
    without exception as 'a period of four (4) consecutive Program
    Years. . . .    Thus, the Program Term, as defined by the Agreement,
    ran   from   March    13,   2001   through   December   31,   2004."   The
    contractual relationship between Abbott and Hancock would continue
    beyond the end of 2004, the district court recognized, because
    Abbott would remain responsible for making payments to Hancock.
    But that continuation did not free Abbott from its obligation to
    plan to spend the Aggregate Spending Target during the "Program
    Term" itself.    Additionally, there are contextual clues far more
    5
    The district court found the "extension period" language
    ambiguous. It then conducted a skillful and convincing analysis of
    some 40 contract drafts that preceded the final version. On the
    basis of that review, the district court found that "extension
    period" was a "vestige" from a previous draft that the parties
    mistakenly failed to delete from the final contract. If we were
    not able to resolve the issue on the plain language of the
    contract, we would readily adopt the district court's factual
    findings on the ambiguity.
    -17-
    relevant to this controversy that eliminate any chance that the
    parties to the contract intended the "Program Term" to be five
    years    rather   than   four.    For   instance,   the   very   carryover
    provisions Abbott relies on refer to the "Program Term" and "the
    subsequent year commencing immediately after the end of the Program
    Term."    The only plausible reading of the contract is that "the
    subsequent year commencing immediately after the end of the Program
    Term" is the year 2005.          The "Program Term" itself ended on
    December 31, 2004.
    In short, the contract required that Abbott plan to spend the
    Aggregate Spending Target during the "Program Term."         The contract
    defined the "Program Term" as the period beginning on the day the
    contract was signed and ending on December 31, 2004.                Abbott
    unambiguously revealed in its 2003 plan that it did not plan to
    spend the Aggregate Spending Target by the end of 2004. Therefore,
    under the terms of the contract, Hancock could terminate its
    payments.
    C.   The year of the terminable event -- 2002 or 2003?
    Abbott argues in the alternative that, even if Hancock could
    withhold its 2004 payment in light of Abbott's failure to forecast
    spending the Aggregate Spending Target through 2004, Hancock could
    not cancel its 2003 payment. Abbott rests this argument on wording
    in the same section of the contract that allowed Hancock to stop
    paying if Abbott did not "reasonably demonstrate in its Annual
    -18-
    Research Plan, its intent and reasonable expectation to expend on
    Program Related Costs during the Program Term an amount in excess
    of [the Aggregate Spending Target]."    The wording states: "For the
    avoidance of doubt, [Hancock's payments] for the Program Year in
    which [an event that allows the termination of payments] occurs
    shall still be due and payable."   Abbott says that Hancock stopped
    paying on the basis of events that happened in 2003 and that the
    2003 payment was therefore still due.     In response, Hancock says
    that the event allowing it to terminate its payments was Abbott's
    December 2002 "2003 Preliminary Annual Research Plan," which failed
    to manifest any intention by Abbott to spend the Aggregate Spending
    Target on the joint project by the end of 2004.   We agree with the
    district court that Hancock was not required to make a 2003
    payment.
    Abbott argues that the December 20, 2002 document cannot be
    considered a ground for termination for two reasons: because it was
    marked "Preliminary" and because it did not include any statement
    of planned spending for 2004.      Neither of these rationales is
    convincing.   Hancock was not obligated to wait for an annual
    research plan labeled "Final."   When Abbott sent Hancock the "2003
    Preliminary Annual Research Plan" in December 2002, it also said
    that the 30-day period for Hancock's payment was running, a sure
    indication that Abbott considered its yearly reporting obligations
    -19-
    to be complete.6   This demand for payment conformed to Abbott's
    practice from the previous year of treating a "Preliminary" annual
    plan as the "Annual Plan" required by the contract.   Additionally,
    Abbott gave no indication that another plan, which might indicate
    satisfactory planned spending for 2004, was coming.
    Abbott also says that the December 2002 document was not a
    terminable event because it did not contain any projections for
    2004. This argument fails in light of the contractual language and
    Abbott's later admissions.   As we discussed above, the contract
    allowed Hancock to terminate its payments if Abbott did "not
    demonstrate in its Annual Research Plan its intent and reasonable
    expectation" to spend at least the Aggregate Spending Target in
    joint funds on the project "during the Program Term."    The "2003
    Preliminary Annual Research Plan," submitted in 2002, plainly did
    "not demonstrate" any intention by Abbott to spend the Aggregate
    Spending Target through 2004.     Actually, due to the computer
    glitch, the document "did not demonstrate" a plan to spend anything
    at all in 2004.    But -- as Abbott later admitted -- even if the
    document had been complete, it would have shown "the estimated
    6
    Under the contract, Abbott was supposed to send Hancock the
    Annual Research Plan "at least forty-five (45) days prior to the
    start of each Program Year" and the Status Report "no later than
    thirty (30) days before the last day of each Program Year."
    Hancock was not expected to make its payments any earlier than
    December 1 of the year in which they were due.       The contract
    allowed Hancock to delay its payments until 30 days after it had
    received both the Status Report and the Annual Research Plan.
    -20-
    spend for 2003 had dropped to [approximately the same amount as in
    the 2003 Preliminary Annual Research Plan] and for 2004, it was at
    [an amount that when added to the spending for 2001, 2002 and 2003
    was   less   than   the   Aggregate    Spending   Target]."   Given   this
    admission by Abbott, Abbott's "2003 Preliminary Annual Research
    Plan," submitted in December 2002, failed to manifest the company's
    intent to spend the required amount through 2004.             As Hancock
    points out, it was not relieved of its payment obligations merely
    because another party failed to correct a computer glitch.             If
    Hancock had requested clarification of the December 20, 2002 plan,
    Abbott would have stated that it no longer planed to spend the
    Aggregate Spending Target by the end of 2004.
    The district court provided a slightly different gloss on the
    same conclusion that the terminable event happened in 2002, relying
    on the principle of contract interpretation that "if possible,
    effect must be given to all of the language so that provisions
    which appear to be conflicting or inconsistent may be reconciled
    and harmonized."     In re Halas, 
    470 N.E.2d 960
    , 964 (Ill. 1984).      We
    also find the district court's analysis persuasive.7
    As the district court concluded:
    7
    While the district court suggested that there was an ambiguity to
    resolve in this analysis, the district court also stated that the
    issue "translated into a contractual interpretation argument" and
    required no parol evidence.    Because a careful reading of the
    contract itself resolved the issue, there was no need to resolve
    any ambiguity.
    -21-
    [I]t is clear [from the contract language]
    that the parties intended Abbott to present an
    [Annual Research Plan] prior to the start of
    each Program Year that would include . . .
    budgets for the remaining Program Years in the
    Program Term. Thus, the parties intended that
    the [Annual Research Plan] for 2003 would be
    submitted to Hancock in 2002 and it would
    include . . . budgets for 2003 and 2004. As a
    result . . . Abbot's failure to demonstrate
    its intent and reasonable expectation to
    expend at least [the Aggregate Spending Target
    by the end of] 2004 [] took place in 2002, not
    2003.
    (Emphasis added.)       To hold otherwise, the district court reasoned,
    would allow      Abbott "to obtain two Program Payments (for 2002 and
    2003) for the price of one payment obligation termination." As the
    district court emphasized, the contract gives Abbott one yearly
    Hancock payment for each conforming year of Abbott's performance.
    The contract would be subverted if Abbott could require an extra
    payment   by    Hancock   merely    because   it   was   late   in   submitting
    complete projections.
    D.   Waiver or estoppel
    Abbott's final fallback argument is that Hancock waived the
    right to cancel its 2003 payment by waiting until the fall of 2003
    to   notify    Abbott   that   it   considered     its   payment     obligations
    terminated.      We agree with the district court that Hancock did
    nothing that could establish a waiver or estoppel under Illinois
    law.
    In Illinois, waiver is the "voluntary relinquishment of a
    known right, claim, or privilege."            Vaughn v. Speaker,533 N.E.2d
    -22-
    885, 890 (Ill. 1988).        It may be "express or implied."               Geier v.
    Hamer   Enters.     Inc.,    
    589 N.E.2d 711
    ,     722   (Ill.   App.    1992).
    Equitable estoppel may be found where a party indicates through its
    conduct that it will not enforce its contractual rights in a timely
    fashion and the other party reasonably relies on that conduct to
    its detriment.       See Geddes v. Mill Creek Country Club, 
    751 N.E.2d 1150
    , 1157 (Ill. 2001).            Abbott's waiver and estoppel arguments
    share a common problem: they do not establish that Hancock conveyed
    any intention to relinquish a contractual "right or privilege." We
    discuss    briefly    Abbot's      three   principal     waiver      and   estoppel
    arguments, resolving them on this common ground.
    Abbott first argues that Hancock should have made an earlier
    notification that it planned to terminate its payments.                    However,
    the contract does not contain any requirement that Hancock notify
    Abbott when a terminable event occurred.                 To the contrary, the
    contract   states     that   "Hancock's       entire    obligation     [under   the
    contract] shall be limited to providing [its] program payments."
    Further, the contract provides that "[t]he waiver by either party
    hereto of any right hereunder or the failure to perform or of a
    breach by the other party shall not be deemed a waiver of any other
    right hereunder . . .."            Hancock could not waive its right to
    terminate payments by failing to provide a notification that it was
    not required to make.
    -23-
    Abbott also contends that Hancock indicated that it was
    satisfied with the December 2002 "2003 Preliminary Annual Research
    Plan" by tendering its 2002 payment upon receipt of that document,
    and that Abbott relied on that payment as an indication that the
    December 20, 2002 plan was sufficient.             But Hancock's payment for
    2002 could not have been any indication that Hancock considered the
    "2003 Preliminary Annual Research Plan" as compliant with Abbott's
    planning obligations. Even if Hancock considered the plan a breach
    by Abbott, Hancock had no choice but to make its 2002 payment.
    After all, the contract provided that Hancock's payment "for the
    Program Year in which [an event that allows the termination of
    payments] occurs shall still be due and payable."                Abbott's breach
    occurred in 2002.        Hancock paid for 2002.      That is merely what the
    contract required.
    Abbott finally claims that Hancock forfeited its right to deem
    the    December   2002    "2003    Preliminary     Annual    Research    Plan"   a
    terminable event by failing to make a timely request for a 2003
    Annual Research Plan that included planned spending for 2004. This
    argument    represents      an    attempt    by   Abbott    to   shift   its   own
    responsibilities to Hancock. The contract made it abundantly clear
    that all responsibility for planning and funding rested with
    Abbott.    Hancock's only obligation was to provide large payments
    when    Abbott    submitted      conforming   documentation.         Given     this
    arrangement, it was reasonable for both parties to accept the "2003
    -24-
    Preliminary Annual Research Plan," submitted in December 2002, as
    Abbott's final word on the subject.             That December 2002 plan
    allowed Hancock to terminate its payments because it did not
    manifest Abbott's intention to spend the contractually prescribed
    amount   during   the   Program   Term   (and   because   any   request   for
    clarification of the document merely would have confirmed that
    Abbott did not intend to spend enough during the Program Term).
    Hancock did not have to ask for clarification before it deemed the
    December 2002 Plan a breach by Abbott allowing it to terminate its
    payments.
    Affirmed.
    -25-