Tresca v. Truck Drivers ( 1994 )


Menu:
  • UNITED STATES COURT OF APPEALS
    FOR THE FIRST CIRCUIT
    No. 93-1965
    TRESCA BROTHERS SAND AND GRAVEL, INC.,
    Plaintiff, Appellant,
    v.
    TRUCK DRIVERS UNION, LOCAL 170,
    Defendant, Appellee.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Joseph L. Tauro, U.S. District Judge]
    Before
    Cyr, Circuit Judge,
    Aldrich, Senior Circuit Judge,
    and Stahl, Circuit Judge.
    Robert P. Corcoran, with whom Gleeson & Corcoran was on brief for
    appellant.
    Raymond J. Reed, with whom Reed & Reed was on brief for appellee.
    March 25, 1994
    CYR,  Circuit Judge.   Tresca  Brothers Sand  & Gravel,
    CYR,  Circuit Judge.
    Inc. (Tresca) brought  suit under section 303(b) of  the National
    Labor Relations Act  (NLRA), 29 U.S.C.    187(b), charging defen-
    dant-appellee Truck Drivers  Union, Local 170  (Local 170 or  the
    Union) with unfair labor practices  during contract negotiations.
    Following  a two-day  bench trial,  the district  court concluded
    that a  subcontracting proposal  advanced by  the Union during  a
    strike had indeed violated both  NLRA sections 8(b)(4) and  8(e),
    29 U.S.C.   158(b)(4), (e), which prohibit, respectively, compul-
    sion against an employer  to require any self-employed  person to
    join  a labor organization, and  to require an  employer to cease
    doing business with  any party.  The  district court nevertheless
    found that Tresca  had not established  a sufficient causal  link
    between the unlawful Union conduct and the injury Tresca alleged-
    ly sustained as a result of the strike.
    In  March 1991,  Tresca, in  coalition with  four other
    ready-mix  concrete  companies  (collectively  "the  Companies"),
    began contract  renewal negotiations  with Local  170.1   By  all
    accounts,  negotiations were  contentious from  the outset.   The
    Companies sought  significant  work-rule modifications  (e.g.,  a
    reduction from eight to four guaranteed hours' pay for each day a
    driver is  called to work) and  benefit eligibility restrictions,
    which  the Union  considered  unacceptable.   The Union  proposed
    1We outline only the  background necessary to an understand-
    ing of the narrow issue presented on appeal.
    2
    forty-two   separate  modifications  to  the  existing  contract,
    including  the  elimination of  the  arbitration  clause and  the
    addition of a subcontracting  clause, both deemed unacceptable by
    the Companies.   After five acrimonious  bargaining sessions, the
    parties  remained at loggerheads.  On May 4, 1991, the membership
    of  Local 170 rejected the latest contract proposal by the Compa-
    nies and voted to go out on strike.  Although additional bargain-
    ing  sessions  were convened  during  the  strike, the  stalemate
    continued.
    The focal  point of  this appeal is  the subcontracting
    proposal  made  by the  Union at  the  May 9  bargaining session,
    whereby the Companies  would be required to  sever their business
    relationships with all non-union owner-operators hauling sand and
    gravel for the Companies.  The parties agree that the Union's May
    9 proposal was unlawful.
    At a  June 13  bargaining session, after  the Companies
    had  filed a complaint  with the  National Labor  Relations Board
    (NLRB), the  Union formally withdrew  the unlawful May  9 subcon-
    tracting proposal.2  The  Companies' most recent "final" contract
    proposal,  containing demands for  significant work-rule changes,
    was rejected by the membership of Local 170 the very next day, on
    June  14.  In short order, the employers' coalition dissolved and
    individual  companies began  separate contract  negotiations with
    2The  NLRB declined to  issue a complaint.   Teamsters Local
    170, N.L.R.B. Nos. 1-CC-2363 (1-2) (Aug. 15, 1991).
    3
    the Union.  Tresca and the Union were never able to resolve their
    differences.    Replacement workers  were  hired  and the  strike
    continues to this day.
    The central  dispute at trial concerned  the importance
    attached by  the Union leadership  and membership to  the Union's
    unlawful subcontracting  proposal  and its  significance  in  the
    decision to strike.  The Union contended that economic issues and
    the work-rule concessions sought by the Companies  were always at
    the  heart  of the  dispute.   Tresca  insisted that  the illegal
    subcontracting  proposal was  presented  as an  ultimatum by  the
    Union's negotiators and dominated the contract negotiations.
    DISCUSSION
    DISCUSSION
    Both parties  endorse the applicable legal  standard as
    explained by the district court:
    In order to make  a legal claim under Section
    303(b) of  the NLRA, a party  must prove that
    it was injured "by reason of" an unfair labor
    practice. [This phrase] has  been interpreted
    to mean  there must be some  causal nexus be-
    tween the unfair labor practice and the inju-
    ry allegedly suffered.  Mead v. Retail Clerks
    Int'l Ass'n, 
    523 F.2d 1371
    , 1378-79  n.9 (9th
    Cir. 1975) (no liability  if an illegal moti-
    vation is  merely "an object"  of a  strike),
    cited with approval, John B. Cruz Constr. Co.
    v. [United] Bhd.  of Carpenters and  Joiners,
    
    907 F.2d 1228
    , 1232  (1st  Cir.  1990); see
    Feather v. United Mine Workers, 
    903 F.2d 961
    ,
    965-66 (3rd  Cir. 1990).  Under  what has be-
    come known  as the  Mead test,  injury occurs
    "by  reason  of" particular  unlawful conduct
    only if that conduct "materially contributes"
    4
    to the injury or is a "substantial factor" in
    bringing it about. Mead, 
    523 F.2d at 1376
    .
    Tresca  Brothers Sand & Gravel v. Truck Drivers Union, Local 170,
    CA  No. 91-11590-T,  slip  op. at  3 (D.  Mass.  July 29,  1993).
    Although Tresca attempts on  appeal to couch its contention  as a
    challenge  to  the  district  court's  application  of  the  Mead
    multiple-motivation test,3  its assignments of error  all presume
    "clear error"  in the  district court's  central finding  of fact
    that "[a]t no time were the Union's subcontracting proposals ever
    a  motivation  for  the strike."    Id.  at  8 (emphasis  added).
    Obviously,  unless the  unlawful  subcontracting proposal  was  a
    motivation,  it could  not have  been a  "substantial  factor" in
    bringing about the strike; and Tresca cannot prevail on its Mead-
    test contention however characterized.
    We  review the  district court's  findings of  fact for
    clear error.    John  B.  Cruz Constr.  Co.  v.  United  Bhd.  of
    Carpenters  and Joiners,  
    907 F.2d 1228
    , 1230  (1st Cir.  1990).
    Thus,  the central  finding in  this case  "will be  given effect
    unless,  after  reading  the  record with  care  and  making  due
    allowance for the trier's  superior ability to gauge credibility,
    3Tresca argues that the  district court failed to appreciate
    that  a strike  may be  motivated by  more than  one "substantial
    factor,"  Frito-Lay,  Inc. v.  International  Bhd.  of Teamsters,
    Local 137, 
    623 F.2d 1354
    , 1363 (9th Cir.), cert. denied, 
    449 U.S. 1013
      (1980),  and that  unlawful  conduct may  be  a substantial
    motivating factor even though  other factors standing alone would
    have  been sufficient to prompt  a strike, see  Feather v. United
    Mine Workers, 
    903 F.2d 961
    , 966 n.11 (3d Cir. 1990).
    5
    [we  form] 'a strong, unyielding  belief that a  mistake has been
    made.'"   Dedham Water Co.  v. Cumberland Farms  Dairy, Inc., 
    972 F.2d 453
    ,  457   (1st  Cir.  1992)  (quoting  Cumpiano v.  Banco
    Santander  Puerto Rico, 
    902 F.2d 148
    , 152 (1st  Cir. 1990)); see
    Anderson  v. Bessemer  City, 
    470 U.S. 564
    ,  573 (1985)  ("If the
    district court's account of the evidence is plausible in light of
    the record viewed in its  entirety, the court of appeals may  not
    reverse  it even though convinced that had it been sitting as the
    trier of fact, it would have weighed the evidence differently.").
    A careful review of the entire record discloses no clear error in
    the finding that  the unlawful subcontracting proposal was  not a
    motivation for the strike.
    First,  the  unlawful subcontracting  proposal  was not
    made until  after Local  170 voted  to strike  Tresca  on May  4.
    Second,  Tresca  concedes that  the  Union  membership was  never
    motivated  by  the subcontracting  proposal.    Third, the  Union
    membership rejected  another contract  proposal by  the Companies
    immediately  after the  Union's unlawful  subcontracting proposal
    was withdrawn on June 13.  Thus, there is no dispute that before,
    during, and  after the time the  unlawful subcontracting proposal
    was on the  bargaining table, the Union  membership was motivated
    by other concerns    unrelated to the subcontracting proposal
    for   which  the   membership  was   ready  to   strike.     This
    circumstantial evidence alone provided  plausible support for the
    district court finding.
    6
    There remains  only the question of  the motivations of
    Union negotiators.4  Tresca  insists that there is uncontroverted
    evidence  that  the  Union  negotiators  presented  the  unlawful
    subcontracting proposal as an ultimatum.  The record simply  does
    not  bear this out.   The witnesses  presented by the  parties at
    trial  gave  diametrically  opposed   accounts  as  to  when  the
    subcontracting  proposal was presented and whether subcontracting
    was  the key issue, as  Tresca maintains, or  simply a bargaining
    chip, as  the Union claims.   The only  objective non-testimonial
    evidence presented  by Tresca  indicates that  the subcontracting
    proposal first surfaced at the May 9 bargaining session.  But the
    timing of  the subcontracting proposal, while  relevant, does not
    determine the outcome of the motivation test required under Mead.
    Rather, in the present context,  the question whether the strike,
    or its prolongment, was  motivated by the subcontracting proposal
    turns  on the  actions and  intent of  the  Union representatives
    responsible for the decision  to inject it as  an element in  the
    collective bargaining.
    The chief negotiator for the  Union specifically denied
    that the May 9  subcontracting proposal was ever presented  as an
    4The record does not support Tresca's unnatural reading that
    the district  court's findings on motivation for  the strike, see
    supra at  p.4, addressed  only the  motivations  of the  striking
    employees and not those  of the Union negotiators.   The district
    court finding itself contains no such qualification, nor is there
    any  evidence  that  the   strike  motivations  harbored  by  the
    membership  differed  substantially  from  those  of  the   Union
    negotiators.
    7
    ultimatum, and expressly denied that it was ever a motivation for
    the strike.  The district court clearly credited the testimony of
    Local 170's chief negotiator.5
    "[W]hen  factual findings  are based  on determinations
    regarding the credibility of witnesses,  Rule 52 demands that the
    appeals court accord even greater deference to the  trial court's
    findings."   Rodriguez-Morales v. Veterans Admin.,  
    931 F.2d 980
    ,
    982 (1st Cir. 1991)  (citing cases); see also Anderson,  
    470 U.S. at 573
    .  Based  on its credibility determination relating  to the
    Union's   motivation,   and   the  undisputed   fact   that   the
    subcontracting proposal was not a strike motivation for the Union
    membership,  there  was no  clear  error  in the  district  court
    finding  that  the  May  9  subcontracting  proposal  was  not  a
    motivation behind the strike.   Accordingly, we affirm its ruling
    that Union liability under NLRA   303(b) was foreclosed.
    Affirmed.
    Affirmed.
    5Near  the end of the trial, the district court outlined for
    counsel the credibility problem confronting Tresca:
    You  have had a witness on the stand here who said that
    [the  Union's negotiator] says "I am  going to get this
    [subcontracting]  proposal . . . I have been wanting to
    do  it a  hundred  years and  this  is life  or  death.
    Without this, nothing."
    .  .  .  I  presume  that  somebody  is  going  to
    corroborate it.  These are the people that were  there.
    Are they going to corroborate it or aren't they?  There
    is no subtlety here.  Either it happened or it didn't.
    If  it  happened, you've  got a  slam dunk.  If it
    didn't, you have a problem.
    Trial Tr. at 42-43, July 22, 1993.
    8