Constructora Andrade v. American Internation ( 2006 )


Menu:
  •            United States Court of Appeals
    For the First Circuit
    No. 05-2303
    CONSTRUCTORA ANDRADE GUTIÉRREZ, S.A.,
    Plaintiff, Appellee,
    v.
    AMERICAN INTERNATIONAL INSURANCE COMPANY OF PUERTO RICO,
    Defendant/Third-Party Plaintiff, Appellee,
    C&M CONSTRUCTORA, S.A.,
    Third-Party Defendant, Appellant.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF PUERTO RICO
    [Hon. Jay A. García-Gregory, U.S. District Judge]
    Before
    Torruella and Lynch, Circuit Judges,
    and Hansen,* Senior Circuit Judge.
    Thomas E. Abernathy, IV, with whom Iván R. Fernández-Vallejo
    was on the brief for appellant.
    Jennifer L. Swize, with whom Jaime Brugueras and Donald B.
    Ayer were on the brief for appellee Constructora Andrade Gutiérrez,
    S.A.
    Francisco A. Rosa-Silva for appellee American International
    Insurance Company of Puerto Rico.
    October 27, 2006
    *
    Of the United States Court of Appeals for the Eighth Circuit,
    sitting by designation.
    HANSEN, Senior Circuit Judge.      C&M Constructora, S.A. (C&M)
    appeals from the July 13, 2005, amended judgment nunc pro tunc of
    the district court in which the district court granted summary
    judgment in favor of Constructora Andrade Gutierrez, S.A. (CAG) on
    its claim against American International Insurance Company of
    Puerto Rico (AIICO); granted summary judgment in favor of AIICO on
    its   third-party   claim   for   indemnification   against   C&M;   and
    dismissed C&M's cross-claims against CAG on the basis that the
    cross-claims were subject to mandatory arbitration.           We affirm
    those portions of the district court's judgment that are properly
    the subject of this appeal.
    I. Background
    C&M, a construction company headquartered in the Dominican
    Republic, entered into an agreement titled "Agreement on Grouping
    Enterprises" (hereinafter "Joint Venture Agreement") in November
    1995 with CAG, a Brazilian corporation, for the sole purpose of
    bidding on the reconstruction of the Pont Sondé-Mirebalais Highway
    in the Republic of Haiti.    In the event that the joint venture won
    the contract, CAG agreed to provide 100% of the guarantees for
    performance and payment to the Republic of Haiti, and C&M agreed to
    provide counter-guarantees to CAG for C&M's participation in the
    project.
    The Republic of Haiti awarded the project to the joint venture
    in May 1996. Pursuant to the Joint Venture Agreement, CAG obtained
    -2-
    a performance and payment bond on behalf of the joint venture for
    the benefit of the Republic of Haiti, and C&M obtained a bond from
    AIICO for the benefit of CAG in proportion to C&M's participation
    in the construction project.        The AIICO bond stated that it was "an
    irrevocable and unconditional guarantee . . . for the completion by
    the   contractor    of    its   obligations      to   [CAG]   pursuant   to    the
    stipulations of the contract dated May 6, 1996." (Appellant's App.
    at 165.)
    The parties were unable to settle disputes that developed
    during the construction project, and on February 11, 1998, C&M and
    CAG entered into an agreement titled "Modifications to Agreement of
    Enterprise Group" (Modifications Agreement) in which participation
    in the construction project was reallocated 99% to C&M and 1% to
    CAG. The Modifications Agreement incorporated a letter of the same
    date (Letter Agreement) written by C&M and approved by CAG, wherein
    the   parties    agreed    that   C&M    would    pay   $967,000   to    CAG   as
    reimbursement for expenses incurred by CAG, to the extent that
    amount was supported by a to-be-performed audit, and C&M would pay
    $440,000 to CAG for loss of business and profits.                   The Letter
    Agreement contemplated that C&M would provide CAG with a bank bond
    or insurance guarantee for the amounts specified in the Letter
    Agreement.      Although C&M provided two surety bonds, CAG returned
    the bonds, and no additional bonds were ever issued on the Letter
    Agreement.
    -3-
    The    subsequent      audit    performed   pursuant     to    the   Letter
    Agreement revealed that CAG was responsible for cost overruns while
    it controlled the project, and that C&M's resulting losses far
    exceeded the amounts C&M had agreed to pay in the Letter Agreement.
    C&M thereafter refused to pay the agreed-upon amounts pursuant to
    the terms of the Letter Agreement.            On July 19, 1999, CAG filed a
    complaint against AIICO in the United States District Court for the
    District of Puerto Rico, invoking the district court's diversity
    jurisdiction and seeking to recover on the AIICO bond for the
    amounts specified in the Letter Agreement that C&M refused to pay.
    C&M attempted to intervene in CAG's complaint against AIICO to
    protect its interests.           Meanwhile, AIICO filed a third-party
    complaint against C&M in the original action, seeking to invoke the
    separate indemnity agreement it had entered into with C&M to cover
    any payments that AIICO might be required to make on the bond it
    had issued on C&M's behalf in favor of CAG.           Thereafter, C&M filed
    cross-claims against CAG, claiming that CAG had breached the Joint
    Venture Agreement.
    After much litigation, the district court filed an Opinion and
    Order on February 26, 2003, granting summary judgment in favor of
    CAG   on    its   original    claim    against    AIICO   in   the    amount   of
    $1,407,000, finding that the bond issued by AIICO was in actuality
    an unconditional guarantee essentially payable on demand.                  In an
    Opinion and Order filed on February 27, 2003, the district court
    -4-
    granted   CAG's    motion    to   dismiss   C&M's   cross-claims   without
    prejudice, finding that the claims were subject to mandatory
    arbitration.      The district court then entered judgment on CAG's
    claim against AIICO and on C&M's cross-claims against CAG on
    February 27, 2003, in accordance with the aforementioned Opinions
    and Orders.
    On November 1, 2004, the district court filed a Memorandum and
    Order finding that C&M was liable to AIICO on the third-party
    complaint against C&M for indemnification of the amounts that AIICO
    was ordered to pay to CAG pursuant to the February 26, 2003,
    Opinion and Order.          The district court then filed an amended
    judgment on November 1, 2004, amending the February 27, 2003,
    judgment to add the judgment against C&M in favor of AIICO.
    Finally, on July 13, 2005, the district court granted CAG's motion
    to include prejudgment interest on the amount of $1,407,000 that
    AIICO was ordered to pay to CAG in the February 26, 2003, order.
    The district court entered an Amended Judgment Nunc Pro Tunc
    reflecting the three prior judgments and the newly awarded pre-
    judgment interest.
    From this final judgment, both C&M and AIICO filed separate
    notices of appeal. AIICO's appeal was docketed as No. 05-2302, and
    its caption does not list C&M as a party to that appeal.             C&M's
    appeal was docketed as No. 05-2303.         The appeals were consolidated
    for oral argument.     AIICO eventually settled its dispute with CAG
    -5-
    by paying $1,600,000 to CAG and moved to dismiss its appeal in this
    court on November 2, 2005.              Accordingly, this court dismissed
    appeal No. 05-2302.        C&M's appeal No. 05-2303 is therefore the
    subject of the case before us.
    II. Issues on Appeal and Standard of Review
    C&M filed its notice of appeal on August 3, 2005, in which it
    appealed
    from a final amended judgment nunc pro tunc (and
    memorandum and order) entered on July 13, 2005 by the
    Hon. Jay A. Garcöa [sic], amendingan [sic] amended
    judgment (and memorandum and order) entered on November
    1, 2004 granting defendant and third-party plaintiff
    [AIICO]'s motion for summary judgment and ruling that C&M
    was obligated to indemnify AIICO for any disbursements
    made to plaintiff, [CAG], as well as any costs and
    attorneys fees resulting from the court's February 25,
    2003 judgment and February 27, 2003 Opinion and Order
    entered in CAG's favor.
    (Appellant's App. at 1067.)         One week later, C&M filed an amended
    notice of appeal, which was nearly identical in language to the
    original notice of appeal, but added the phrase "dismissing C&M's
    cross claims against plaintiff [CAG], without prejudice, finding
    that they were subject to mandatory arbitration" to its description
    of which portions of the July 13, 2005, amended judgment nunc pro
    tunc it was appealing.2         (Id. at 1071-72.)     AIICO filed its notice
    of   appeal   on   the   same   date,    specifying   the   district   court's
    judgment granting CAG $1,407,000 plus prejudgment interest.
    2
    The amended notice of appeal also changed "February 27, 2003
    Opinion and Order" in the last line to "February 26, 2003 Opinion
    and Order." This does not affect our analysis.
    -6-
    In their briefing to this court, both CAG and AIICO declined
    to address the validity of the district court's judgment ordering
    AIICO to pay CAG on the bond.          CAG claims that the issue is moot in
    light of its settlement with AIICO. AIICO claims that the validity
    of the underlying judgment ordering AIICO to pay CAG on the bond is
    irrelevant      because      C&M   entered    into     a   separate     unconditional
    indemnity agreement that was not contingent on the correctness of
    the district court's judgment against AIICO.
    Putting the issues of the relevance and the mootness of the
    underlying judgment aside, we question first whether the separate
    order    of     February     26,   2003,     finding       that   the   bond    was   an
    unconditional guarantee and ordering AIICO to pay $1,407,000 to
    CAG, is even properly before this court as a part of C&M's appeal.
    As quoted above, C&M filed a very specific original notice of
    appeal    and    an   even    more   specific     amended         notice   of   appeal.
    Compliance with Federal Rule of Appellate Procedure 3, specifying
    the contents of a notice of appeal, is jurisdictional and cannot be
    waived.       See Torres v. Oakland Scavenger Co., 
    487 U.S. 312
    , 317
    (1988).       We must therefore determine which orders are encompassed
    within C&M's amended notice of appeal before we proceed to the
    merits of the appeal.          See Diaz-Rodriguez v. Pep Boys Corp., 
    410 F.3d 56
    , 58 (1st Cir. 2005) (addressing appellate jurisdiction even
    though it was not raised by the parties).
    A notice of appeal must "designate the judgment, order, or
    -7-
    part thereof being appealed," Fed. R. App. P. 3(c)(1)(B), before it
    confers jurisdiction on a court of appeals to hear a case, see
    Nieves-Marquez v. Puerto Rico, 
    353 F.3d 108
    , 122 (1st Cir. 2003).
    "[T]he general rule is that '[i]f an appellant . . . chooses to
    designate specific determinations in his notice of appeal-rather
    than simply appealing from the entire judgment-only the specified
    issues may be raised on appeal.'" United States v. Universal Mgmt.
    Servs., Inc., 
    191 F.3d 750
    , 756 (6th Cir. 1999) (quoting McLaurin
    v. Fischer, 
    768 F.2d 98
    , 102 (6th Cir. 1985)), cert. denied, 
    530 U.S. 1274
     (2000).   The failure to include a particular issue in a
    notice of appeal can be fatal to this court's jurisdiction over
    that issue.   See Poy v. Boutselis, 
    352 F.3d 479
    , 486 (1st Cir.
    2003) (declining to address an issue on appeal concerning another
    party that was not raised in the notice of appeal); see also Lehman
    v. Revolution Portfolio L.L.C., 
    166 F.3d 389
    , 395 (1st Cir. 1999)
    ("Failure to make a sufficient specification ordinarily debars the
    appellant from arguing the propriety of an unspecified ruling on
    appeal."); Spound v. Mohasco Indus., Inc., 
    534 F.2d 404
    , 410 (1st
    Cir. 1976) ("Nor was plaintiff correct in his further allegation
    that his specific and limited prior appeal raised matters contained
    in entirely different paragraphs."), cert. denied, 
    429 U.S. 886
    (1976), abrogated on other grounds by Pioneer Inv. Servs. Co. v.
    Brunswick Assocs. Ltd. P'ship, 
    507 U.S. 380
     (1993).
    Notwithstanding   the   jurisdictional   nature   of   the   Rule   3
    -8-
    requirements, we construe those requirements liberally, analyzing
    "the notice of appeal in the context of the entire record."
    Blockel v. J.C. Penney Co., Inc., 
    337 F.3d 17
    , 23-24 (1st Cir.
    2003).   "This principle of liberal construction does not, however,
    excuse   noncompliance    with   the   Rule.    Rule   3's   dictates    are
    jurisdictional in nature, and their satisfaction is a prerequisite
    to appellate review."     Smith v. Barry, 
    502 U.S. 244
    , 248 (1992).
    This   case   involves      multiple      parties;   three   separate
    substantive claims: CAG's original claim against AIICO on the bond,
    AIICO's third-party claim against C&M for indemnity, and C&M's
    cross-claims against CAG for breach of the Joint Venture Agreement;
    and three separate district court orders addressing each claim.
    Following the district court's amended judgment nunc pro tunc, C&M
    specifically appealed from the district court's order requiring C&M
    to indemnify AIICO.      C&M then filed an amended notice of appeal,
    adding to its appeal the district court's order dismissing C&M's
    cross-claims because they were subject to arbitration.                  AIICO
    separately appealed the district court's order holding it liable on
    the bond but dismissed that appeal upon settlement with CAG. While
    C&M's amended notice of appeal mentioned the February 26, 2003,
    order that determined that AIICO was liable on the bond, the notice
    of appeal was specifically limited to "any costs and attorneys fees
    resulting from" that order.      (Appellant's App. at 1071-72.)
    Given the circumstances of this case and the specific nature
    -9-
    of C&M's notice of appeal and amended notice of appeal, we conclude
    that C&M did not appeal the district court's February 26 order
    requiring AIICO to pay on the bond.   C&M knew the limited scope of
    its original notice of appeal as evidenced by its amended notice,
    in which it added another of the district court's specific rulings.
    Even after AIICO dismissed its appeal, C&M did not attempt to
    include the underlying judgment on the CAG claim against AIICO
    within its own appeal.   C&M's actions bring to mind the ancient
    maxim, "expressio unius est exclusio alterius" (the expression of
    one thing is an intention to exclude all others).    Kotler v. Am.
    Tobacco Co., 
    981 F.2d 7
    , 11 (1st Cir. 1992) (holding that a notice
    of appeal's exclusion of one order, coupled with the designation of
    a distinct and independent order, "loudly proclaims plaintiff's
    intention not to appeal from the former order"); see also C&S
    Acquisitions Corp. v. Nw. Aircraft, Inc., 
    153 F.3d 622
    , 625 (8th
    Cir. 1998) (declining to apply the rule that an appeal from a final
    order permits the review of issues decided in prior orders because
    the notice of appeal specified a grant of summary judgment, which
    applied only to one count, and did not encompass the district
    court's separate order confirming an arbitration award).    C&M is
    the master of its notices, and we are limited to reviewing only
    those orders fairly raised within those notices.   We conclude that
    we lack jurisdiction to disturb the district court's judgment
    ordering AIICO to pay CAG on the bond, and we limit our discussion
    -10-
    accordingly.
    We review a district court’s grant of summary judgment de
    novo.    Lexington Ins. Co. v. Gen. Acc. Ins. Co. of Am., 
    338 F.3d 42
    , 46 (1st Cir. 2003).    We apply Puerto Rico substantive law to
    this diversity action.    See 
    id.
     (applying state substantive law
    when sitting in diversity).   Under Puerto Rico law, we accord the
    terms of a contract their plain meaning, reading the contract as a
    whole.   Jewelers Mut. Ins. Co. v. N. Barquet, Inc., 
    410 F.3d 2
    , 16
    (1st Cir. 2005).
    III. Application of the Agreement of Indemnity
    Several weeks after issuance of the bond by AIICO to CAG,
    AIICO and C&M entered into a separate Agreement of Indemnity, which
    provided that
    The Principals and Indemnitors [C&M] shall exonerate,
    indemnify, and keep indemnified the Surety [AIICO] from
    and against any and all liability for losses and/or
    expenses of whatsoever kind or nature (including, but not
    limited to, interest, court costs, and counsel fees) and
    from and against any and all such losses and/or expenses
    which the Surety may sustain and incur: (1) By reason of
    having executed or procured execution of the Bonds. . . .
    Payment by reason of the aforesaid causes shall be made
    to the surety by the Principals and Indemnitors as soon
    as liability exists or is asserted against the Surety
    whether or not the Surety shall have made payment
    therefor. . . . In the event of any payment by the Surety
    the Principals and Indemnitors further agree that in any
    accounting between the Surety and the Principals, . . .
    the Surety shall be entitled to charge for any and all
    disbursements made by it in good faith in and about the
    matters herein contemplated by this Agreement under the
    belief that it is or was liable for the sums and amounts
    so disbursed, or that it was necessary or expedient to
    make such disbursements, whether or not such liability,
    necessity or expediency existed . . . .
    -11-
    (Appellant’s App. at 138.)     Because the bond obligated AIICO "to
    pay the aforementioned amount on first demand by" CAG (id. at 165),
    the Agreement of Indemnity further required C&M as the Indemnitor
    to:
    immediately and upon the Surety's first written or simple
    demand (which shall be conclusive evidence that such sum
    is due and payable) pay to the Surety or place with the
    Surety (subject to the Bond amount) the sum required to
    make such payment without any question or delay and
    whether or not such demand is in the Indemnitor's opinion
    a proper demand.
    (Id. at 140.)
    Puerto Rico law recognizes the relationship between a surety
    and a debtor and requires a debtor to indemnify a surety even when
    the security is paid without the debtor's knowledge.           See 31 P.R.
    Laws Ann. § 4911.    Furthermore, Puerto Rico law "implicitly allows
    for a surety to compromise a debt."       U.S. Fid. & Guar. Co. v. PR
    Enters., No. 03-1338, 
    2005 WL 2244283
    , at *4 (D.P.R. Sept. 15,
    2005) (relying on 31 P.R. Laws Ann. §§ 4911-13).        Generally, when
    an indemnity agreement gives a surety broad discretion to pay
    claims triggering the indemnity agreement, the only defense an
    indemnitor   may    raise   against   a   claim   by   the    surety   for
    indemnification is that the surety committed fraud or collusion, or
    otherwise acted in bad faith in paying the claim.            See Fireman's
    Ins. Co. of Newark, N.J. v. Todesca Equip. Co., 
    310 F.3d 32
    , 35-36
    & n.6 (1st Cir. 2002) (discussing Rhode Island law and noting
    -12-
    slight variations in other jurisdictions).3
    Although we lack jurisdiction to disturb the district court's
    ruling that the bond was in actuality an unconditional guarantee,
    C&M argues that the district court's alleged error in that ruling
    makes the Agreement of Indemnity inapplicable.            In other words,
    according to C&M, there should have been, and there is, nothing to
    indemnify because AIICO should not have been required to pay CAG on
    the bond.    In limited circumstances third-party defendants "may
    raise on appeal claims of error based in the main action," where
    the "third-party liability . . . is entirely derivative of the
    [underlying] judgment . . ., and will cease to exist if that
    judgment is defeated."       United States v. Lumbermens Mut. Cas. Co.,
    
    917 F.2d 654
    , 658 n.5 (1st Cir. 1990) (reversing third-party
    judgment against insurance agent in favor of insurer based on
    erroneous    ruling   that   insurance     policy   provided    coverage   in
    underlying suit and refusing to disturb judgment holding insurer
    liable where insurer did not appeal underlying judgment). Separate
    and apart from appealing the underlying ruling, a third-party
    defendant may assert, as the basis for appealing the ruling against
    it on the third-party claim, that the underlying judgment was
    erroneous.      
    Id.
          Thus,    while    we   will   not     disturb   (for
    3
    Puerto Rico law allows a debtor to use against the surety
    those defenses it would have against the creditor, but only when
    the surety pays on a debt without informing the debtor. See 31
    P.R. Laws Ann. § 4913. C&M does not rely on this defense, and we
    do not address it.
    -13-
    jurisdictional reasons) the district court's judgment holding that
    the bond was an unconditional guarantee by AIICO, we can review the
    correctness of that ruling as a defense to C&M's liability under
    the indemnity agreement if C&M's liability is "entirely derivative"
    of CAG's judgment against AIICO.       Id.
    In   this   case,   C&M's   liability   to   AIICO   is   not   entirely
    derivative of CAG's judgment against AIICO. In fact, its liability
    is not derivative of the underlying judgment at all.           Even if AIICO
    had paid on CAG's demand before CAG filed suit, C&M would have been
    liable to indemnify AIICO under the very broad terms of the
    separate Agreement of Indemnification upon AIICO's good faith
    payment on the demand.      The sweeping language can be reduced to
    five words: "If we pay -- you pay."       Regardless of the correctness
    of the district court's underlying decision, the fact remains that
    AIICO did in fact pay on the bond.           Even if we now found that
    ruling to be incorrect, it would not change the fact of payment or
    alter the judgment as between AIICO and CAG, which is now final as
    to those parties.    See id. at 662 (refusing to grant relief from an
    erroneous judgment to a nonappealing party); Marin Piazza v. Aponte
    Roque, 
    909 F.2d 35
    , 39 (1st Cir. 1990) (dismissing as untimely an
    appeal brought by four defendants following the fifth defendant's
    successful appeal and noting that "the inescapable consequence of
    failure to appeal a judgment within the time allowed is that the
    judgment becomes final" as to the nonappealing party). AIICO would
    -14-
    still be out its payment on the bond.           The Agreement of Indemnity
    clearly and unequivocally required C&M to indemnify AIICO upon
    AIICO's good faith payment on the bond based on AIICO's belief that
    it was liable on the claim, "or that it was necessary or expedient
    to    make    such   disbursements,   whether    or   not   such   liability,
    necessity or expediency existed."              (Appellant's App. at 138.)
    Thus, we need not, and do not, decide the correctness of the
    underlying judgment in favor of CAG against AIICO; either way, C&M
    is liable to AIICO under the Agreement of Indemnity because AIICO
    paid on CAG's demand.
    We note that in ruling on the underlying claim between CAG and
    AIICO, the district court found the bond to be an unconditional
    letter of credit and that the two conditions precedent to liability
    on the letter of credit had been met, namely that (1) CAG provided
    written notice to AIICO prior to the expiration date of the bond,
    and (2) the written notification contained the amount to be paid
    and stated that C&M had not performed its contractual obligations.
    The district court did not address the defenses raised by C&M to
    justify its failure to pay on the Letter Agreement, nor did it need
    to,   given    its   conclusion   that   the   bond   was   an   unconditional
    guarantee.      See generally 38A C.J.S. Guaranty § 17 (2006) ("The
    general rule that where the principal contract is invalid the
    guaranty is rendered invalid does not apply where the contract of
    guaranty is an entirely separate and independent contract, such as
    -15-
    an absolute guaranty." (internal footnotes omitted)). The judgment
    granted to CAG against AIICO has no effect on the underlying
    disputes between CAG and C&M concerning C&M's liability (or lack
    thereof or defenses thereto) on the Letter Agreement.
    C&M did not argue in its briefs that AIICO's payment on the
    bond was made in bad faith, but relied solely on its claim that the
    district   court   erred    in   holding      that   the   AIICO   bond   was   an
    unconditional guarantee.         During oral argument, counsel for C&M
    argued that AIICO settled the CAG-AIICO appeal in bad faith because
    it did not first consult C&M before paying the settlement.
    We generally do not address arguments made for the first time
    during oral argument, especially when the arguments are contrary to
    the   arguments    made    in    the   briefs.       See    United   States     v.
    Pizarro-Berríos,     
    448 F.3d 1
    ,   4    (1st   Cir.    2006)   ("We   have
    consistently held that, except in extraordinary circumstances,
    arguments not raised in a party's initial brief and instead raised
    for the first time at oral argument are considered waived.").
    AIICO was not aware until oral argument that the issue of its good
    faith settlement of the appeal was at issue.
    Even if we were to reach the merits of the bad faith argument,
    we could not agree that AIICO's settlement was made in bad faith.
    AIICO vigorously disputed its liability on the bond in the district
    court and filed an appeal of the final judgment against it.
    Whatever its reason for settling after filing its notice of appeal,
    -16-
    we cannot say that compliance with a judgment duly entered by a
    United States District Court evidences bad faith on the part of the
    losing party.
    The district court properly granted summary judgment in favor
    of AIICO and against C&M based on the unambiguous and entirely
    separate Agreement of Indemnity.         See Plaza Athénée, S.E. v. U.S.
    Fid. and Guar. Co., No. 01-2597, 
    2005 WL 1114368
    , at *9-10 (D.P.R.
    May 9, 2005) (granting partial summary judgment in favor of surety
    where surety settled claim with creditor without consulting debtor;
    nothing in the surety agreement limited surety's discretion or
    ability to respond to the creditor's claim).
    IV. Cross-Claims Dismissed as Subject to Mandatory Arbitration
    Finally, C&M challenges the district court's dismissal of its
    cross-claims    against   CAG,   in    which   C&M   claimed   that   CAG   had
    breached the Joint Venture Agreement.          The Joint Venture Agreement
    between C&M and CAG included an arbitration clause, which stated:
    Any difference related to the interpretation or the
    execution of the present agreement will be settled in
    accordance with the Rules of Reconciliation and
    Arbitration of the International Chamber of Commerce, by
    a referee designated under the conditions provided by
    said rule. The arbitration will take place at Genéve,
    Switzerland, the applicable law being used i[s] the
    Canton of Genéve.
    (Appellant's App. at 105.)       C&M recognizes the enforceability of
    mandatory arbitration agreements, but argues that CAG waived its
    right to enforce arbitration by bringing the action against AIICO
    -17-
    on the bond in federal court, relying on Jones Motor Co. v.
    Chauffeurs, Teamsters, & Helpers Local Union No. 633 of N.H., 
    671 F.2d 38
    , 42 (1st Cir.) ("[P]arties are free to waive their rights
    to arbitration under a contract and proceed to present their
    contractual dispute to a court."), cert. denied, 
    459 U.S. 943
    (1982).
    The importance of arbitration agreements in the commercial
    world,    particularly   related   to     international   agreements,   is
    indisputable.    Congress enacted the Federal Arbitration Act (FAA)
    to
    promote[] a liberal federal policy favoring arbitration
    and [to] guarantee[] that "[a] written provision in . . .
    a contract evidencing a transaction involving commerce to
    settle by arbitration a controversy thereafter arising
    out of such contract or transaction . . . shall be valid,
    irrevocable, and enforceable, save upon such grounds as
    exist at law or in equity for the revocation of any
    contract."
    Campbell v. Gen. Dynamics Gov't Sys. Corp., 
    407 F.3d 546
    , 551-52
    (1st Cir. 2005) (quoting 
    9 U.S.C. § 2
    ) (alterations within internal
    quotation in original).
    The district court determined that the bond was in actuality
    an unconditional guarantee, a determination that permitted the
    district court to avoid deciding whether C&M had breached either
    the Joint Venture Agreement or the Letter Agreement before it
    ordered AIICO to pay on the bond.         Even if the district court was
    wrong in holding that the bond's character was independent of the
    Joint Venture Agreement, an issue we do not decide today, the fact
    -18-
    remains that the district court interpreted only the bond.                       It did
    not construe the Joint Venture Agreement or related amendments in
    holding AIICO liable on the bond.             In bringing its original action
    against   AIICO    on       the    bond   then,    CAG    did   not    invoke   federal
    jurisdiction      to    decide      issues   related       to   the    Joint    Venture
    Agreement,   and       it    did    not    waive    its    right      to   enforce   the
    arbitration clause.               Accordingly, the district court properly
    dismissed C&M's cross-claims because they are subject to mandatory
    arbitration.
    V. Summary
    To the extent C&M attempts to appeal the underlying judgment
    in favor of CAG against AIICO, we dismiss that part of its appeal
    for want of jurisdiction.            We affirm the district court's judgment
    holding that C&M was required to indemnify AIICO for the payment it
    made to CAG, including costs and attorneys fees pursuant to the
    July 13, 2005, order, and we affirm the district court's judgment
    dismissing without prejudice C&M's cross-claims against CAG because
    those claims are subject to mandatory arbitration. Costs of appeal
    are awarded to AIICO and CAG.             As it now stands, CAG holds AIICO's
    money, and C&M is liable to indemnify AIICO for the amount AIICO
    has paid to CAG.            Assuming the parties invoke arbitration, the
    correct distribution or allocation of those funds held by CAG as
    between CAG and C&M will be determined by the results of the
    arbitration proceedings in Genéve, in which CAG's claims against
    -19-
    C&M based on the Letter Agreement and C&M's dismissed cross-claims
    for breach of the Joint Venture Agreement should be resolved.
    Affirmed.
    -20-
    

Document Info

Docket Number: 05-2303

Filed Date: 10/27/2006

Precedential Status: Precedential

Modified Date: 12/21/2014

Authorities (20)

Poy v. Boutselis , 352 F.3d 479 ( 2003 )

Albert M. Spound v. Mohasco Industries, Inc., Albert M. ... , 534 F.2d 404 ( 1976 )

Fireman's Insurance v. Todesca Equipment Co. , 310 F.3d 32 ( 2002 )

Blockel v. J.C. Penney Company , 337 F.3d 17 ( 2003 )

Nieves-Marquez v. Commonwealth of PR , 353 F.3d 108 ( 2003 )

Jewelers Mutual Insurance v. N. Barquet, Inc. , 410 F.3d 2 ( 2005 )

United States v. Pizarro-Berrios , 448 F.3d 1 ( 2006 )

Lexington Insurance Company v. General Accident Insurance ... , 338 F.3d 42 ( 2003 )

Magda Marin Piazza v. Awilda Aponte Roque , 909 F.2d 35 ( 1990 )

Joanne Kotler, Individually and as Administratrix, Etc. v. ... , 981 F.2d 7 ( 1992 )

Campbell v. General Dynamics Government Systems Corp. , 407 F.3d 546 ( 2005 )

United States v. Lumbermens Mutual Casualty Company, Inc., ... , 917 F.2d 654 ( 1990 )

Diaz-Rodriguez v. Pep Boys Corp. , 410 F.3d 56 ( 2005 )

Lehman v. Revolution Portfolio LLC , 166 F.3d 389 ( 1999 )

Robert L. McLaurin v. Josef E. Fischer, and University of ... , 768 F.2d 98 ( 1985 )

C & S Acquisitions Corp., Successor by Assignment of Cis ... , 153 F.3d 622 ( 1998 )

united-states-v-universal-management-services-inc-corporation-natural , 191 F.3d 750 ( 1999 )

Torres v. Oakland Scavenger Co. , 108 S. Ct. 2405 ( 1988 )

Smith v. Barry , 112 S. Ct. 678 ( 1992 )

Pioneer Investment Services Co. v. Brunswick Associates Ltd.... , 113 S. Ct. 1489 ( 1993 )

View All Authorities »