Weaver's Cove Energy, LLC v. Rhode Island Coastal Resources Management Council , 589 F.3d 458 ( 2009 )


Menu:
  •            United States Court of Appeals
    For the First Circuit
    No. 08-2440
    WEAVER'S COVE ENERGY, LLC,
    Plaintiff, Appellee,
    v.
    RHODE ISLAND COASTAL RESOURCES MANAGEMENT COUNCIL; MICHAEL M.
    TIKOIAN, in his capacity as Chairman of the Rhode Island Coastal
    Resources Management Council; PAUL E. LEMONT, in his capacity as
    Vice Chairman of the Rhode Island Coastal Resources Management
    Council; THOMAS RICCI; DAVID ABEDON; DONALD GOMEZ; K. JOSEPH
    SHEKARCHI; NEIL GRAY; W. MICHAEL SULLIVAN; RAYMOND C. COIA; GERALD
    P. ZARRELLA; BRUCE DAWSON; in their capacities as Members of the
    Rhode Island Coastal Resources Management Council,
    Defendants, Appellants.
    ON APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF RHODE ISLAND
    [Hon. William E. Smith, U.S. District Judge]
    Before
    Lynch, Chief Judge,
    Torruella and Ripple,* Circuit Judges.
    Michael Rubin, Assistant Attorney General, with whom Patrick
    C. Lynch, Attorney General of the State of Rhode Island, Paul J.
    Roberti, Assistant Attorney General, Brian A. Goldman, and the
    Goldman Law Offices were on brief for the appellants.
    Carol Iancu, Assistant Attorney General, and Martha Coakley,
    Attorney General of Massachusetts, on brief for the Commonwealth
    of Massachusetts and the City of Fall River, amicus curiae.
    *
    Of the Seventh Circuit, sitting by designation.
    Bruce F. Kiely, with whom Adam J. White, Baker Botts L.L.P.,
    Gregory L. Benik, and Benik and Associates P.C. were on brief for
    the appellees.
    October 26, 2009
    LYNCH, Chief Judge.      The Rhode Island Coastal Resources
    Management Council ("CRMC") challenges a decision by the federal
    district court, which has rejected two regulatory barriers CRMC
    imposed to plans to build a Liquified Natural Gas ("LNG") terminal
    in the City of Fall River with a berth in Massachusetts coastal
    waters of Mount Hope Bay.       Weaver's Cove Energy, LLC ("Weaver's
    Cove") is the sponsor of the LNG terminal.          Weaver's Cove Energy,
    LLC v. R.I. Coastal Res. Mgmt. Council, 
    583 F. Supp. 2d 259
     (D.R.I.
    2008).    The barriers, which CRMC has attempted to impose, are to
    necessary dredging by Weaver's Cove in Rhode Island navigable
    waters, in a federal navigation channel.              The Federal Energy
    Regulatory Commission ("FERC") generally approved the project in
    2005, subject to certain conditions.         Until those conditions are
    met, Weaver's Cove cannot start construction.         The Commonwealth of
    Massachusetts, joined by the City of Fall River, has filed a brief
    as amicus curiae in support of CRMC.
    We address three main issues.          The first is whether we
    have Article III jurisdiction to decide these matters.         The second
    is whether the district court erred in holding that CRMC's failure
    to respond within six months to Weaver's Cove's application for
    federal consistency review requires there be a presumption of
    concurrence in the project, pursuant to 
    16 U.S.C. § 1456
    (c)(3)(A)
    of the Coastal Zone Management Act of 1972 ("CZMA").          The third is
    whether   CRMC's   use   of   its   state   law   licensing   program   for
    -3-
    alterations to the coast, 04-
    000-010 R.I. Code R. §§ 100.1
    , 300.1,
    to block the project is preempted by the Natural Gas Act ("NGA").
    For the reasons set forth below, we affirm the district
    court's decision.
    I.
    We first briefly explain the regulatory framework that
    governs this case.
    Central to this dispute are two federal statutes, the
    NGA, 
    15 U.S.C. §§ 717
    -717z, and the CZMA, 
    16 U.S.C. §§ 1451-66
    .
    The NGA was originally passed in the 1930s to facilitate the growth
    of    the    energy-transportation        industry     and   requires     FERC
    authorization for the importing of natural gas.                15 U.S.C. §
    717b(a).     FERC's authority under the to NGA to regulate facilities
    engaged in the import of natural gas has long been interpreted as
    "plenary and elastic," Distrigas Corp. v. Federal Power Comm'n, 
    495 F.2d 1057
    , 1064 (D.C. Cir. 1974), and courts have interpreted the
    NGA to preempt state regulatory authority within the scope of
    FERC's jurisdiction, see, e.g., Schneidewind v. ANR Pipeline Co.,
    
    485 U.S. 293
       (1988).   Following      a   2005   amendment,   the   NGA
    explicitly grants FERC "exclusive authority to approve or deny an
    application for the siting, construction, expansion, or operation
    of an LNG terminal."     
    Id.
     § 717b(e)(1).       Parties wishing to build
    an LNG terminal must file an extensive application with FERC, 18
    -4-
    C.F.R. § 157.6, which must then consult with states regarding
    safety and environmental questions, 15 U.S.C. § 717b-1(b).
    The NGA creates a consolidated regulatory process for
    approving    LNG   facilities     that    maintains     the   role     of    federal
    agencies and, in circumscribed areas, state agencies.                  It does so
    by limiting FERC's exclusive authority in two ways relevant to this
    case.    First, the NGA, except where expressly provided, does not
    affect   "any     Federal    agency's     authorities    or   responsibilities
    related to LNG terminals."        Id. § 717b(e)(1) (emphasis added).              In
    addition,    the    NGA     explicitly    states   that,      unless       otherwise
    provided, it does not affect the rights of states under three
    federal regulatory statutes, of which only the CZMA is pertinent to
    this case.      Id. § 717b(d)(1).
    The    CZMA   establishes     the   relationship     between      state
    bodies, like the Rhode Island CRMC, and federal agencies during the
    permitting process for LNG terminal construction projects that
    impact   coastal     zones.      It     provides   states     with     a    limited
    opportunity to review applications to ensure they are consistent
    with state regulations, 
    16 U.S.C. § 1456
    (c)(3)(A), and, in doing
    so, grants states "a conditional veto over federally licensed or
    permitted projects," Weaver's Cove, 
    583 F. Supp. 2d at 267
    .                    That
    conditional veto, however, is itself subject to review.
    In order to conduct a consistency review, state agencies
    must first have obtained approval from the federal National Oceanic
    -5-
    Atmospheric      Administration         ("NOAA"),   a   Department     of    Commerce
    agency, for the state agency's own coastal management plan. 
    16 U.S.C. §§ 1454
    , 1455(d)-(e), 1456(c)(3)(A).                    Coastal management
    plans    set     forth    general   state       policies   for     developing    and
    maintaining coastal areas and, as is the case in Rhode Island, may
    include not only the conditions for federal consistency review but
    also for state licensing programs.
    Once a state coastal management plan has been approved,
    an applicant for a federal permit wishing to undertake any activity
    the state plan regulates must certify with the local agency that
    the proposed activity is consistent with the coastal management
    plan.1   
    Id.
     § 1456(c)(3)(A).            In support of the application, the
    applicant       must     submit   all    "necessary     data     and   information"
    identified       in      the   coastal     management      plan.        
    15 C.F.R. § 930.58
    (a)(2).          Under federal law, the state agency has thirty
    days from the time the application was submitted to notify the
    applicant and the federal agency if it takes the position that the
    applicant has failed to submit all of the required information.
    
    Id.
     § 930.60(a)(2).
    Importantly, the CZMA limits the time a state may conduct
    such a review, in order to prevent frustration of federal purposes.
    1
    A state is prohibited from undertaking interstate
    consistency review of activities occurring in a different state
    unless the state requests and obtains interstate review authority
    from NOAA. 
    15 C.F.R. § 930.154
    (e).
    -6-
    Whether CRMC failed to act within this limit is a key issue in this
    case. Once an applicant submits its consistency certification, the
    state agency has six months either to concur with the certification
    or    to   object    if    it   concludes    that   the   proposed   activity    is
    inconsistent        with    the    coastal   management     plan.      
    16 U.S.C. § 1456
    (c)(3)(A).          If the state agency fails to respond within six
    months, the state's concurrence will be "conclusively presumed."
    
    Id.
         If the application is incomplete and the state agency so
    informs the applicant within the required thirty-day time period,
    "the State agency's six-month review period will commence on the
    date of receipt of the missing necessary data and information." 
    15 C.F.R. § 930.60
    (a)(2).              However, the state agency's review of
    whether the application is complete "is not a substantive review of
    the adequacy of the information received," and the agency's request
    for clarification of the information provided or its assertion that
    the information is "substantively deficient" does not toll the six-
    month review period.              
    Id.
     § 930.60(c).        These rules encourage
    states to act quickly when reviewing applications so that no one
    state      can   delay    the   federal   approval    process.       Congress   was
    sufficiently concerned about the ability of local state agencies to
    delay projects that it did not use a generalized standard, such as
    "a reasonable period of time" as it did, for instance, in the
    Telecommunications Act of 1996, 
    47 U.S.C. § 332
    (c)(3)(B), but
    capped the time at six months.
    -7-
    The CZMA also limits state authority to delay or prohibit
    projects subject to consistency review, by providing for federal
    review of state agency determinations. If the state agency objects
    to consistency certification, the applicant may appeal the decision
    to the Secretary of Commerce, who can override the objection on a
    finding "that the activity is consistent with the objectives of
    this chapter or is otherwise necessary in the interest of national
    security."    16 U.S.C. 1456(c)(3)(A).      The Secretary's decision, in
    turn, may be reviewed in federal district court.2 See, e.g.,
    Millennium Pipeline Co., L.P. v. Gutierrez, 
    424 F. Supp. 2d 168
    ,
    173-74 (D.D.C. 2006).
    One other federal statute relevant to this case is the
    Rivers and Harbors Act, at section 10.             
    33 U.S.C. § 403
    .         It
    prohibits    construction    or   other    work,   such   as    dredging,   in
    navigable U.S. waters without congressional authorization or a
    recommendation by the Army Corps Chief of Engineers as well as the
    Secretary    of   the   Army's   authorization.     
    Id.
            Because   FERC's
    exclusive authority under the NGA does not disturb the Army Corps's
    authority under the Rivers and Harbors Act, 15 U.S.C. § 717b(e)(1),
    parties seeking FERC approval for LNG terminal proposals that
    2
    A state may reopen review of a certification if the
    applicant makes a "major amendment" to the project.    
    15 C.F.R. §§ 930.51
    (b)-(c), (e), 930.66(b). That provision is inapplicable
    here.
    -8-
    include dredging in navigable waterways, like Weaver's Cove, must
    also apply for approval from the Army Corps.
    In Rhode Island, the federally designated agency under
    the    CZMA    is    the     appellant,    CRMC.        CRMC    is   responsible     for
    administering Rhode Island's coastal management plan, the Rhode
    Island Coastal Resources Management Program ("CRMP"). When a party
    wishes to conduct an activity listed in the CRMP, such as dredging
    in Rhode Island, under state law, that party should obtain from the
    CRMC a state law license called an "Assent."                    04-
    000-010 R.I. Code R. § 100.1
    .         The more extensive "Category B Assent" process under
    state law is required for approval of all projects that involve
    major alterations proposed for Rhode Island tidal waters, shoreline
    features,      or    areas     contiguous      with   shoreline       features.      
    Id.
    §§ 100.1(A), (D), 300.1.              If the party's proposed listed activity
    is also part of a project that is subject to federal licensing,
    CRMC   is     the    body    tasked    with    providing       the   required    federal
    consistency review.
    CRMC's document, labeled the Federal Consistency Manual,
    emphasizes       that       although    the    Assent    and     consistency      review
    processes may overlap, they are distinct approvals.                      R.I. Coastal
    Res. Mgmt. Council, Federal Consistency Manual 7, available at
    http://www.crmc.ri.gov/regulations/Fed_Consistency.pdf.                         The same
    list of activities that require Assents also require consistency
    review.       Id. at 12.      Major alterations to the Rhode Island coastal
    -9-
    area that trigger the more extensive Category B Assent process
    trigger the same level of review for consistency certifications.
    Id. at 8.
    Finally, the manual states that a grant or denial of an
    Assent in an application when a consistency review is ongoing
    constitutes a concurrence or an objection for the purposes of the
    review.     Id. at 13.     A key difference between the two forms of
    review is that whereas the CZMA limits consistency review through
    the six-month time limit, administrative review by the Secretary of
    Commerce, and federal judicial review, no federal statute limits
    how long state decisions regarding Category B Assent may take or
    provides for federal review.
    The   substantive       provision   of    the   state    CRMP   most
    pertinent to this case is section 300.9(C), which requires approval
    by the CRMC for all dredging activities.             Particularly in dispute
    in this case is the meaning of section 300.9(C)(7) of the CRMP,
    which requires that "[w]hen disposal is proposed for approved
    upland    facilities,     the    applicant   shall    provide    a   letter   of
    acceptance from that facility, unless the disposal is approved for
    the central landfill."          04-
    000-010 R.I. Code R. § 300.9
    (C)(7).
    The CRMC also coordinates some of its responsibilities
    with   another    state    agency,     the   Rhode    Island    Department    of
    Environmental Management ("RIDEM").          Particularly relevant to this
    case is RIDEM's role in identifying a list of approved upland sites
    -10-
    for disposal of dredged material, which CRMC is responsible for
    incorporating      into       a    comprehensive        plan   for    dredged      material
    management.      R.I. Gen. Laws § 46-6.1-5.
    II.
    Weaver's      Cove       proposes      to    build    and    operate     a    LNG
    terminal    in    Fall    River.        The   proposed         project   received        FERC
    approval in 2005, subject to certain conditions.3                           Weaver's Cove
    Energy, LLC, 112 F.E.R.C. ¶ 61,070, at 61,528 (2005).                          FERC found
    that the proposal "will promote the public interest by increasing
    the   availability       of       natural   gas    supplies      in   the    New    England
    market."    Id.
    Under the original LNG proposal, submitted in 2003, ships
    carrying LNG would pass through waters in both Rhode Island and
    Massachusetts, traveling up the Taunton River to the terminal
    location.     This has changed.             According to Weaver's Cove's 2009
    "Offshore Berth Amendment," the proposal now calls for ships to
    deliver their cargo to an offshore berth in Mount Hope Bay, from
    which the LNG would be transported via a submerged pipeline to the
    onshore terminal.             The offshore berth, the pipeline, and the
    terminal would all be located in Massachusetts.                              In both the
    3
    LNG, produced by cooling natural gas to a liquid state,
    has less volume and so can be more economically transported. The
    terminal proposed by Weaver's Cove would receive imported LNG from
    tanker ships, regasify it, and inject it into the U.S. natural gas
    grid.   According to Weaver's Cove, the proposed terminal would
    supply fifteen percent of New England's "peak day" natural gas
    demand in 2010. Weaver's Cove, 
    583 F. Supp. 2d at 262-63
    , 262 n.2.
    -11-
    original      proposal    and    the    amended   version,       the    only    planned
    activity in Rhode Island waters is dredging in a federal navigation
    channel to ensure the safe passage of the LNG tankers.                                That
    dredging is the subject of this litigation.
    On December 19, 2003, Weaver's Cove filed an application,
    pursuant      to   the   NGA,    for    FERC   approval   of     the    proposed      LNG
    facility.      FERC, as said, approved the application in 2005 subject
    to a number of conditions, one of which was that Weaver's Cove was
    to "file . . . prior to construction documentation of concurrence
    from the [CRMC] that the project is consistent with the Rhode
    Island   [CRMP]."        Weaver's       Cove   Energy,    LLC,    112    F.E.R.C.      at
    ¶¶ 61,550-51 (emphasis in original).
    Turning    to     state    regulatory      requirements,         such    as
    Category B Assent, FERC added that "state or local permits issued
    with respect to the jurisdictional facilities authorized herein
    must be consistent with the conditions in this order." Id. at
    ¶   61,546.        Although     FERC    encouraged    Weaver's     Cove    and    local
    authorities to cooperate during local review of Weaver's Cove's
    proposal, it made clear that "this does not mean that state and
    local agencies, through application of state or local laws, may
    prohibit or unreasonably delay the construction or operation of
    facilities approved by this Commission."                 Id.
    Following cross-motions for rehearing, FERC reaffirmed
    this order in 2006 in all respects relevant to this case.                      Weaver's
    -12-
    Cove Energy, LLC, 114 F.E.R.C. ¶ 61,058, at 61,164 (2006).    This
    court declined then to review the conditional order on ripeness
    grounds.   City of Fall River v. Fed. Energy Regulatory Comm'n, 
    507 F.3d 1
    , 6 (1st Cir. 2007).
    Because the proposed dredging activities also required
    approval from the Army Corps under the Rivers and Harbors Act,
    Weaver's Cove filed an application to the Army Corps on March 18,
    2004.   Dredging is a listed activity in Rhode Island's federally
    approved CRMP. 04-
    000-010 R.I. Code R. § 300.9
    .      On filing its
    application to the Army Corps, Weaver's Cove was therefore also
    required by the CZMA to file a consistency certification with CRMC,
    which it did in July 2004.    With this application, Weaver's Cove
    also applied for Rhode Island's state law license for dredging,
    Category B Assent.   However, Weaver's Cove informed CRMC that it
    believed the Assent unnecessary.
    Within the thirty-day window to inform applicants for
    concurrence that their applications are incomplete required by the
    CZMA, CRMC informed Weaver's Cove by phone that its consistency
    certification and Category B Assent application were, in CRMC's
    view, incomplete on two grounds.   The validity of those grounds is
    at issue in this case.    The first, quickly remedied by Weaver's
    Cove, was that it had failed to submit the engineering plans with
    the stamp of a Rhode Island engineer.   The second ground, at issue
    in this case, was that Weaver's Cove's application was incomplete,
    -13-
    and so the six-month clock was not ticking, because Weaver's Cove
    had     failed    to   provide    documentation,           pursuant     to     section
    300.9(C)(7) of the CRMP, that dredged materials would be accepted
    by "an approved upland facilit[y]."                In a letter dated August 2,
    2004, Weaver's Cove replied that because the dredged materials were
    to be disposed of in Massachusetts, and not in Rhode Island,
    section 300.9(C)(7) of the CRMP did not apply.                On August 26, 2004,
    CRMC responded, informing Weaver's Cove that its application was
    still    incomplete    because    it   failed       to    file   a   Water     Quality
    Certificate but making no mention of the upland disposal issue.
    After additional communications, the parties failed to resolve the
    dispute.         Because   it    claimed      to    lack    necessary        data   and
    information, CRMC did not commence review of Weaver's Cove's
    consistency certification or its Category B assent.                    It still has
    not done so.      In short, as of this date, the appellant state agency
    has not acted on the merits of an application which has been
    pending before it since July 2004.
    Over a year after its original application to CRMC,
    Weaver's    Cove    made   separate    filings       to    NOAA,     FERC,    and   the
    Secretary of Commerce, requesting a determination that CRMC's
    concurrence be "conclusively presumed" because CRMC had failed to
    act on Weaver's Cove's application within the statutorily required
    six-month deadline.        
    16 U.S.C. § 1456
    (c)(3)(A).                 NOAA took no
    action, FERC concluded it did not have authority to address the
    -14-
    issue, and the Secretary of Commerce determined that he could not
    review the matter without an actual objection from CRMC. This left
    the matter of whether CRMC's concurrence should be conclusively
    presumed to the courts for resolution.
    Weaver's Cove filed suit in the U.S. District Court for
    the   District     of    Rhode      Island    on    June     29,   2007.          It    sought
    declaratory and injunctive relief, claiming that the disposal
    information       and    the       water    quality    certification,           which     the
    appellant    CRMC       had    requested,      were    not      "necessary        data     and
    information," as required by the CZMA.                 Weaver's Cove asserted the
    CZMA's     six-month         deadline      should   not    be      tolled      and     CRMC's
    concurrence      should       be    conclusively      presumed.           In   an      amended
    complaint, Weaver's Cove also argued that Category B Assent was
    preempted by provisions of the NGA that grant FERC "exclusive
    authority" in approving LNG facilities, 15 U.S.C. § 717b(e)(1), and
    unlawful under the dormant Commerce Clause.
    The district court granted summary judgment in favor of
    Weaver's Cove, on both the CZMA and the NGA claims.                       Weaver's Cove,
    
    583 F. Supp. 2d at 262
    .             The court found that neither the disposal
    information, nor the water quality certificate were necessary data
    and   information,           and   so   Weaver's      Cove    application           was   not
    incomplete.       
    Id. at 272-73
    .            Thus, CRMC had failed to meet the
    statutory deadline and its concurrence was conclusively presumed.
    
    Id. at 275
    .         In    particular,      with    respect       to     the      disposal
    -15-
    information, the court found, based on statutory interpretation and
    the interpretation which the other state agency of Rhode Island,
    RIDEM, had adopted, that the term "approved upland facilities" in
    section   300.9(C)(7)     of    the   CRMP   referred    only   to   disposal
    facilities in Rhode Island.           Weaver’s Cove, 
    583 F. Supp. 2d at 270-75
    .     Since Weaver's Cove intended to dispose of the dredged
    material out of state (in Massachusetts) at that time,4 the court
    concluded that CRMC could not require proof that the material would
    be accepted.     
    Id.
       The district court, acting under the NGA, also
    held the Category B Assent process utilized by CRMC was preempted
    on three grounds.      First, it found the process expressly preempted
    by the language of 15 U.S.C. § 717b(3)(1), granting FERC "exclusive
    authority to approve or deny an application" to build an LNG
    terminal.    Weaver’s Cove, 
    583 F. Supp. 2d at 280-83
    .          Second, the
    court found the assent process implicitly field preempted because
    "Congress clearly intended that the NGA occupy the entire field of
    LNG regulation." 
    Id. at 283-84
    . Finally, the district court found
    the   Category    B    Assent    process     preempted   here   because   it
    specifically conflicted with FERC's jurisdiction to regulate LNG
    facilities.    
    Id. at 284-85
    .     The court also held that the case was
    not rendered moot by the changes in the project that occurred after
    4
    The original proposal to the Army Corps set forth a
    Massachusetts disposal site but also considered offshore disposal
    at a federal ocean disposal site approved by the Environmental
    Protection Agency and the Army Corps.
    -16-
    the date Weaver's Cove submitted its consistency certification.
    
    Id. at 275-76
    .         It did not reach the dormant Commerce Clause
    question.
    III.
    A.             Jurisdiction
    We first hold that we have jurisdiction to hear this
    case.       CRMC does not raise any challenge to standing, mootness, or
    ripeness.5      Massachusetts, in its brief amicus curiae to this court
    (but not to the district court), argues broadly that there is no
    case or controversy here, based on standing, mootness, and lack of
    ripeness.       Amici cannot insert new arguments, not made by a party,
    into a case.      Pharm. Research & Mfrs. of Am. v. Concannon, 
    249 F.3d 66
    , 74 n.5 (1st Cir. 2001).          Nonetheless, we review standing,
    mootness, and ripeness in the constitutional sense to see whether
    we have Article III jurisdiction because we are independently
    obligated to do so, regardless of whether the parties raise the
    issue.       Pagan v. Calderon, 
    448 F.3d 16
    , 26 (1st Cir. 2006).   For
    the reasons discussed below, we are satisfied we have jurisdiction.
    We first address standing.   Massachusetts asserts that
    because Weaver's Cove has not shown that a decision in their favor
    5
    Because CRMC has not itself challenged the district
    court's finding with respect to mootness, we do not address CRMC's
    challenge to the jurisdictional questions raised in footnote 18 of
    the district court's opinion. In re Williams, 
    156 F.3d 86
    , 90 (1st
    Cir. 1998) ("[F]ederal appellate courts review decisions,
    judgments, orders, and decrees--not opinions, factual findings,
    reasoning, or explanations.").
    -17-
    "will relieve a discrete injury" to them, Weaver's Cove lacks
    standing.     Massachusetts v. EPA, 
    549 U.S. 497
    , 525 (2007) (quoting
    Larson   v.    Valente,     
    456 U.S. 228
    ,    243   n.15     (1982))    (internal
    quotation marks omitted).             It argues that "events completely
    unrelated     to   CRMC's    regulatory      processes"      have    prevented     the
    project from proceeding.           Massachusetts is not entirely clear in
    explaining     what   those       events    are,     but    its    brief's    earlier
    description of the project suggests it is referring to challenges
    Weaver's Cove has faced in satisfying other state and federal
    permitting requirements. Because CRMC's regulatory requirements do
    affect   Weaver's     Cove's      ultimate        ability   to     receive    federal
    approval, we conclude that Weaver's Cove has standing.
    A plaintiff wishing to establish standing must show "a
    concrete and particularized injury in fact, a causal connection
    that permits tracing the claimed injury to the defendant's actions,
    and a likelihood that prevailing in the action will afford some
    redress for the injury."          City of Bangor v. Citizens Commc'ns Co.,
    
    532 F.3d 70
    , 92 (1st Cir. 2008) (quoting Me. People's Alliance &
    Natural Res. Def. Council v. Mallinckrodt, Inc., 
    471 F.3d 277
    , 283
    (1st Cir. 2006)) (internal quotation marks omitted). The plaintiff
    need not show that "the defendant's actions are the very last step
    in the chain of causation" for the injury.                  Bennet v. Spear, 
    520 U.S. 154
    , 169 (1997).             It suffices if the plaintiff can show
    -18-
    "injury produced by determinative or coercive effect upon the
    action of someone else."         
    Id.
    In this case, CRMC's actions have directly affected the
    federal   regulatory       processes     that    determine     whether      the    LNG
    terminal project can proceed.            Consistency review is a condition
    for FERC approval, and FERC has stated it has no authority to
    address CRMC's refusal to act.6           While CRMC's inaction may not be
    the exclusive reason federal approval has not been granted, it is
    clear    that   failure     to   obtain    concurrence        from   CRMC    has    a
    "determinative       or   coercive     effect"    on    the   federal    agencies.
    Bennet, 
    520 U.S. at 169
    .         Weaver's Cove therefore has standing to
    make its CZMA-related claims.
    In addition, Weaver's Cove has standing to make its
    preemption claims because it suffers a concrete injury from Rhode
    Island subjecting it to a preempted state law.                    Even if CRMC's
    concurrence     in   Weaver's    Cove's    consistency        certification       were
    presumed, Category B Assent would still bar LNG construction if we
    did not address it here.               This "would impose a palpable and
    considerable hardship" on its project.                 Pac. Gas & Elec. Co. v.
    State Energy Res. Conservation & Dev. Comm'n, 
    461 U.S. 190
    , 201-02
    (1983).
    6
    The Army Corps also requires Weaver's Cove to submit
    verification that its application to CRMC is complete before it can
    complete its review.
    -19-
    This case is not rendered moot by Weaver’s Cove's failure
    to achieve complete regulatory approval for its original proposal
    or by its submission of the Offshore Berth Amendment.                  “[A] case is
    moot when the issues presented are no longer ‘live’ or the parties
    lack a legally cognizable interest in the outcome.”                        Powell v.
    McCormack, 
    395 U.S. 486
    , 496 (1969).                We will only find a case moot
    if an intervening event “makes it impossible for the court to grant
    any effectual relief.”         Gulf of Me. Fisherman’s Alliance v. Daley,
    
    292 F.3d 84
    , 88 (1st Cir. 2002) (quoting Church of Scientology v.
    United States, 
    506 U.S. 9
    , 12 (1992)) (internal quotation marks
    omitted).
    Weaver’s Cove’s efforts to obtain regulatory approval for
    the   LNG   terminal    from    all   of     the    relevant      actors   do    indeed
    constitute a live issue.              These efforts are ongoing and the
    Offshore Berth Amendment represents an attempt by Weaver's Cove to
    address     some   of   the   concerns       that    may   have    earlier      delayed
    approval.      While    Weaver’s      Cove    still     has   conditions        to   meet
    following the amendment, Weaver's Cove did, for example, get
    approval from the Coast Guard, which previously had been a hurdle.
    Since CRMC's consistency certification remains a requirement of
    FERC and of the Army Corps, that question is clearly live.                      This is
    especially so because the Offshore Berth Amendment itself does not
    render moot the dispute here with Rhode Island.                   As the Army Corps
    has itself noted, the planned dredging activities in Rhode Island
    -20-
    have not changed, even under the amendment.7       A decision in favor
    of the plaintiff in this case would provide "effectual relief"
    because it would clear a barrier to achieving approval for the
    project.
    This case is also ripe.     Although federal regulatory
    approval for the Offshore Berth Amendment is ongoing, our review of
    this case is neither “advisory” nor “irrelevant to the ultimate
    approvability of the project.”      Fall River, 
    507 F.3d at 8
    .
    Massachusetts cites Fall River in an attempt to argue
    that this case will lack ripeness until the project receives
    authorization from several key federal agencies. But it disregards
    important differences in the facts and procedural background of
    this case.        In Fall River, we held that a challenge to FERC's
    conditional approval of this project was not ripe because the
    decision was not final until the completion of reviews by the
    United States Coast Guard and the Department of the Interior.        
    Id. at 7
    .       Because FERC's decision was not final we could not be sure
    our opinion would not be advisory.        
    Id. at 7-8
    .   In contrast, the
    plaintiff's requested relief in this case would be final.        CRMC's
    consistency review and Category B Assent requirements would cease
    7
    We affirm the district court's holding that the Offshore
    Berth Amendment does not affect CRMC's consistency review.
    Weaver's Cove, 
    583 F. Supp. 2d at 275-78
    . That FERC is reviewing
    the Offshore Berth Amendment is irrelevant and does not moot this
    appeal regarding findings by a Rhode Island agency. What effect
    that amendment may have on dredging activities in Massachusetts is
    not at issue before us.
    -21-
    to be barriers to ultimate approval of the project.          Another
    difference from Fall River is that FERC and the other relevant
    agencies have expressly declined to resolve the issue raised by
    this appeal on the grounds that they have no authority to do so.
    It is true that resolutions of these issues might not secure the
    project's ultimate approval, but it would neither be "advisory" nor
    "irrelevant."
    B.        CZMA Consistency    Review:   "Conclusive   Presumption   of
    Concurrence"
    We hold that CRMC’s concurrence with Weaver’s Cove’s
    dredging plans must be conclusively presumed under 
    16 U.S.C. § 1456
    (c)(3)(A). We affirm the district court. Weaver’s Cove, 
    583 F. Supp. 2d at 270-75
    .
    A district court may grant summary judgment on a finding
    that "there is no genuine issue as to any material fact and that
    the movant is entitled to judgment as a matter of law."      Fed. R.
    Civ. P. 56(c).   "An issue is genuine 'if the evidence is such that
    a reasonable jury could return a verdict for the nonmoving party,'
    and a fact is material if it has the 'potential to affect the
    outcome of the suit.'"   Velázquez-García v. Horizon Lines of P.R.,
    Inc., 
    473 F.3d 11
    , 15 (1st Cir. 2007) (quoting Anderson v. Liberty
    Lobby, Inc., 
    477 U.S. 224
    , 248 (1986); Santiago-Ramos v. Centennial
    P.R. Wireless Corp., 
    217 F.3d 46
    , 52 (1st Cir. 2000)) (citation
    omitted). On appeal, we review a district court's grant of summary
    -22-
    judgment de novo. Torrech-Hernandez v. General Elec. Co., 
    519 F.3d 41
    , 46 (1st Cir. 2008).
    We review the district court’s holding that, in this
    case, a letter certifying acceptance of dredged material, as listed
    in section 300.9(C)(7) of the CRMP, did not constitute necessary
    data and information within the meaning of 
    15 C.F.R. § 930.58
    (a)(2)
    because Weaver’s Cove did not intend to dispose of the waste in
    Rhode Island.8         Weaver’s Cove, 
    583 F. Supp. 2d at 271-72
    .          If, as
    CRMC       contends,   the   letter   is    necessary    data   and   information
    required by the CRMP, CRMC is not compelled to commence reviewing
    the consistency certification until Weaver's Cove provides it.                 
    15 C.F.R. § 930.60
    (a)(2).    The      six-month    deadline   for   presumed
    concurrence would be tolled until that time.              
    Id.
       If, on the other
    hand, the letter is not necessary data and information, as the
    district court found, the six-month period from Weaver's Cove's
    submission of the consistency certification in July 2004 has
    clearly expired, and we are required to find CRMC's concurrence
    8
    We note that Weaver’s Cove no longer intends to dispose
    of the dredged materials at any “upland facilit[y]” and instead now
    plans to dispose of the waste at an offshore site. As CRMC points
    out in its reply brief, this was not the case at the time of the
    original consistency review application.     Weaver’s Cove at that
    time planned to dispose of the waste at its Fall River Facility.
    We do not address this change, because it occurred after the time
    concurrence would have been presumed, and neither party has raised
    it on appeal.
    -23-
    presumed.     
    16 U.S.C. § 1456
    (c)(3)(A).               We affirm the district
    court's conclusion.
    As the district court noted, the state CRMP does not
    define "approved upland facilit[y]."              Weaver's Cove, 
    583 F. Supp. 2d at 271
    .    However, other Rhode Island laws have shed light on the
    language's meaning.     Rhode Island's Marine Waterways and Boating
    Facilities Act of 2001 ("Waterways and Boating Act"), R.I. Gen.
    Laws §§ 46-6.1-1 to -10, and associated regulations, set forth a
    comprehensive system regulating dredging activities and disposal of
    dredged materials in the state. The district judge relied on these
    regulations to conclude that facilities outside of Rhode Island are
    not among the "approved upland facilities" from which the CRMP
    requires a letter of acceptance.          Weaver’s Cove, 
    583 F. Supp. 2d at 271-72
    .
    We agree with the district court that the language of
    section   300.9(C)(7)      of    the   CRMP    can    only   be   read   to    cover
    facilities located in the state of Rhode Island because the state's
    regulatory     framework        for    dredging      only    provides    for     the
    identification of "approved upland facilities" within the state.
    We begin with the Rhode Island statutes that govern
    regulation of dredging in the state.              Rhode Island law makes the
    CRMC responsible for "prepar[ing], adopt[ing] and maintain[ing]
    . . . a comprehensive plan for dredged material management for
    dredging that takes place in the coastal zone."                   R.I. Gen. Laws.
    -24-
    § 46-6.1-5(a).    But the same statute delegates to RIDEM the task of
    "adopt[ing] by rule a list of upland sites and types of areas
    suitable for beneficial use and disposal of dredged materials."
    Id. § 46-6.1-5(b). This list is then "incorporated in the [CRMC's]
    comprehensive plan for dredged material management."                 Id.    The
    Waterways and Boating Act does not define "upland sites," but it
    does define "[u]pland areas" as "areas that are not in the coastal
    zone."   Id. § 46-6.1-4(16).         Thus, while both agencies may be
    responsible for interpreting whether "upland disposal facilities"
    can include out of state disposal facilities, only RIDEM is charged
    with approving upland sites.
    RIDEM    has   in   turn    promulgated       its   own   Rules   and
    Regulations for Dredging and the Management of Dredged Material
    ("Dredging Regulations") pursuant to the Waterways and Boating Act.
    R.I. Dept. of Envtl. Mgmt., Rules and Regulations for Dredging and
    the   Management    of   Dredged       Material     §    2,    available     at
    http://www.dem.ri.gov/pubs/regs/regs/water/dred0203.pdf
    [hereinafter "R.I. Dredging Regulations"].          These regulations are
    also intended to be consistent with the CZMA, id., and must be
    implemented according to a written protocol jointly adopted by CRMC
    and RIDEM, id. § 3.   Among the stated purposes of these regulations
    is to "[i]dentify and list upland sites suitable for beneficial use
    and/or disposal of dredged material," id. § 1.5, and, as the
    district court noted, the Dredging Regulations "apply to all
    -25-
    aspects of dredging proposed in marine waters of the State of Rhode
    Island," id. § 3.      The Dredging Regulations do not contain an
    express definition for "approved upland facilities," but they do
    define "Upland Areas" more narrowly than the corresponding term in
    the Waterways and Boating Act, R.I. Gen. Laws § 46-6.1-4(16), as
    "[a]ll areas of the state that are not in the coastal zone."         R.I.
    Dredging Regulations § 4.20 (emphasis added).
    Since RIDEM is tasked with approving upland disposal
    facilities, R.I. Gen. Laws § 46-6.1-5(b), and it only approves
    upland facilities within the state of Rhode Island, R.I. Dredging
    Regulations    §   4.20,   it   follows   that   the   "approved   upland
    facilities" referred to by section 300.9(C)(7) of the CRMP should
    be read to be facilities within the state of Rhode Island.           "To
    hold otherwise would render the C[R]MP's specific language a
    nullity."    Weaver’s Cove, 
    583 F. Supp. 2d at 272
    .
    In any event, appellant has not pointed to any regulatory
    process for the approval of upland sites outside of Rhode Island,
    nor has it produced a list of approved facilities outside of the
    state.    Absent language in Rhode Island law to the contrary, we
    presume state laws, like this one, not to have extraterritorial
    effect.   Cf. Carnero v. Boston Sci. Corp., 
    433 F.3d 1
    , 7 (1st Cir.
    2006).
    CRMC responds that it has an interest in confirming that
    material dredged from its coast is properly disposed, regardless of
    -26-
    the ultimate location, and that the district court improperly
    relied on another agency's interpretation of the Waterways and
    Boating Act, which it administers.            Citing language from both the
    Waterways and Boating Act, R.I. Gen. Laws § 46-6.1-3(1), and the
    CRMC's organic statute, id. § 46-23-1(e), that designate CRMC as
    the "lead agency" for purposes of regulating dredging activities,
    CRMC       argues   that   federal   courts     must    defer   to   its   broader
    interpretation of its own regulations for its own purposes.                     It
    explains that although RIDEM may, in its limited role of approving
    disposal sites, only be concerned with upland facilities within
    Rhode Island, CRMC is more broadly concerned with ensuring the
    proper disposal of dredged material.9
    CRMC cites no authority in support of its view, and in
    this context, the view is untenable.              Since for the purposes of
    CZMA       consistency     review,   we   are    only     concerned    with    the
    requirements of the CRMP, CRMC's argument that it is entitled to
    deference in its interpretation of the Waterways and Boating Act is
    inapposite.         We are concerned only with its interpretation of
    9
    Thus, in order to prevent a hypothetical "trash barge to
    nowhere scenario," in which Rhode Island is forced to dispose of
    dredged material that no one else will accept, CRMC is entitled to
    demand proof that Weaver's Cove's proposed upland disposal facility
    will accept it.     Of course, this is not a barge to nowhere
    situation, because Weaver's Cove has identified a disposal site
    subject to the jurisdiction of other agencies that play a role
    under the CZMA.
    -27-
    section 3009.(C)(7) of the CRMP, and complementary regulatory
    schemes to the extent they shed light on its meaning.
    It is true, as CRMC points out, that federal agency
    interpretations       of    their     own    regulations    (when    authorized    by
    Congress)       are   "controlling            unless   'plainly      erroneous     or
    inconsistent with the regulation.'" Auer v. Robbins, 
    519 U.S. 452
    ,
    461 (1997) (quoting Robertson v. Methow Valley Citizens Council,
    
    490 U.S. 332
    , 359 (1989)).                  However, even if we applied that
    standard here, CRMC cannot satisfy it because the plain language of
    section       300.9(C)(7)       of   the    CRMP   calls   for    "approved     upland
    facilities" (emphasis added).               Thus, even if upland facilities can
    be interpreted to include facilities outside of Rhode Island, CRMC
    has not pointed to any regulatory scheme that deals with the
    approval of out-of-state facilities or even a list of approved out-
    of-state facilities.             The only regulatory scheme for approving
    upland       facilities    is    that      administered    by    RIDEM,   and   CRMC's
    interpretation of its regulation is therefore clearly erroneous.10
    This construction of state law also permits us to avoid
    an issue of whether a different construction would violate federal
    law.        As noted, see supra note 1, an individual state may not
    10
    We also reject CRMC's argument that it deserves deference
    under Mountain Rhythm Resources v. Fed. Energy Regulatory Comm'n,
    
    302 F.3d 958
     (9th Cir. 2009).     That case involved review of a
    federal agency's decision to adopt a state's interpretation of its
    coastal management plan under the arbitrary and capricious
    standard. 
    Id. at 966
    . Here we are reviewing the state agency's
    interpretation itself.
    -28-
    purport to undertake out of state regulation for consistency review
    purposes without getting NOAA's consent.       
    15 C.F.R. § 930.154
    (e).
    C.         Preemption of State Category B Assent to Dredging by
    Section 3 of the Natural Gas Act and by FERC's
    Conditional Approval
    We review the district court's finding that CRMC's state
    law licensing program for coastal dredging, the Category B Assent
    process, is preempted by the NGA, at least on the facts here.         At
    stake is whether CRMC may still delay the project based on Weaver's
    Cove's failure to satisfy section 300.9(C)(7) of the CRMP or other
    CRMP requirements, despite our conclusion that concurrence in
    Weaver's Cove's consistency certification should be presumed.        Our
    standard when reviewing a district court's finding of preemption is
    de novo.   Fitzgerald v. Harris, 
    549 F.3d 46
    , 52 (1st Cir. 2008);
    SPGGC, LLC v. Ayotte, 
    488 F.3d 525
    , 530 (1st Cir. 2007).
    While the district court found the Category B Assent
    process preempted on a number of grounds, Weaver’s Cove, 
    583 F. Supp. 2d at 279-85
    , we affirm for the narrowest reason, that of
    conflict preemption.
    In its order, FERC analyzed Weaver's Cove's proposed
    dredging   activities   in   both   Rhode   Island   and   Massachusetts,
    assessed the environmental impact the dredging would have and
    compared it with alternatives, and analyzed the effect on the water
    and wildlife, land use, recreation, ship traffic, and air quality.
    Weaver's Cove Energy, LLC, 112 F.E.R.C. at ¶ 61,540 (discussing
    -29-
    environmental issues reviewed and adopting the findings of FERC's
    Final Environmental Impact Statement ("FEIS")); Office of Energy
    Projects, Fed. Energy Regulatory Comm'n, Docket No. CP04-36-000,
    Weaver's Cove LNG Project Final Environmental Impact Statement (May
    2005) [hereinafter "Weaver's Cove FEIS"].     Further, FERC concluded
    that the dredging was part of the construction and operation of the
    terminal project.     Thus, Category B Assent clearly conflicts with
    FERC's "exclusive authority," as exercised here, to license the
    "siting, construction, expansion, or operation" of LNG terminals.
    15 U.S.C. § 717b(e)(1).11
    To simplify a complex area of law, preemption arguments
    are generally divided into three categories.     Fitzgerald, 
    549 F.3d at 52
    .      The first, express preemption, results from language in a
    statute revealing an explicit congressional intent to preempt state
    law.    Barnett Bank of Marion County, N.A. v. Nelson, 
    517 U.S. 25
    ,
    31 (1996).      The second, field preemption, is that Congress may
    implicitly preempt a state law by creating a pervasive scheme of
    regulation.     Fitzgerald, 
    549 F.3d at 52
    ; N. Natural Gas Co. v. Iowa
    Utils. Bd., 
    377 F.3d 817
    , 823 (8th Cir. 2004) (holding a state's
    11
    This provision of the NGA was not in effect until August
    8, 2005, after FERC issued its order on July 15, 2005. However,
    FERC's interpretation of its own preemptive authority under the NGA
    to regulate construction of LNG facilities was clearly articulated
    before this provision came into force. Weaver's Cove Energy, LLC,
    112 F.E.R.C. at ¶ 61,546. Further, FERC reaffirmed its approval of
    Weaver's Cove's application after the provision became effective.
    Weaver's Cove Energy, LLC, 114 F.E.R.C. at ¶ 61,185-86.
    -30-
    site-specific environmental review field preempted because FERC has
    authority under the NGA to consider environmental issues).       The
    third category is conflict preemption. In this category, state law
    is "pre-empted to the extent it actually conflicts with federal
    law, that is, when compliance with both state and federal law is
    impossible, or when the state law stands as an obstacle to the
    accomplishment and execution of the full purposes and objectives of
    Congress."    Id. at 53 (quoting Good v. Altria Group, Inc., 
    501 F.3d 29
    , 47 (1st Cir. 2007)).
    Weaver's Cove asks us to find preemption under the first
    two grounds.    It also stresses the district court's application of
    a field preemption test set forth in a NGA preemption case.
    Weaver’s Cove, 
    583 F. Supp. 2d at
    285 (citing Schneidewind, 
    485 U.S. at 301
    ).
    We prefer to decide on the narrowest grounds: conflict
    preemption.     In this case, FERC has interpreted the dredging
    activities in the Weaver's Cove's project, including those in Rhode
    Island, to be within its preemptive jurisdiction.    See Fitzgerald,
    
    549 F.3d at 55
     ("The proposition that federal agency action, taken
    pursuant to its interpretation of a statute, may itself preempt is
    quite correct.").    CRMC does not argue that the proposed dredging
    is not a part of the LNG terminal's "siting, construction, . . . or
    operation" under 15 U.S.C. § 717b(e)(1), although Massachusetts, as
    -31-
    amicus, does.12   In its original order, FERC extensively reviewed
    the dredging as part of the overall terminal construction and
    operational plan.    Weaver's Cove Energy, LLC, 112 F.E.R.C. at
    ¶ 61,535-36, 61,545, 61,550.    Here, FERC carefully reviewed the
    very dredging Rhode Island seeks to further regulate and, after
    considering environmental impacts, authorized the project.    Id. at
    61,546.   The FEIS, adopted by reference in the FERC order, id. at
    61,540, found that the dredging was necessary "to accommodate the
    passage of LNG ships" to the facility, Weaver's Cove FEIS, at 2-25
    (May 2005), and that it would be impossible to "reduce the volume
    or extent of dredging and still satisfy the objectives of the
    project at the proposed site," id. at 3-70.     Thus, FERC concluded
    that the dredging was part of the construction and the operation of
    the terminal facility. That ruling is final and binding because no
    objections were made to FERC's findings on these points in the
    parties' request for rehearing.13     Further, the dredging is in an
    approved federal navigation channel.
    12
    Rather CRMC argues that Section 10 of the River and
    Harbors Act saves Category B Assent from preemption by the NGA, a
    contention we consider below.
    13
    The parties never raised objections to these findings in
    their request for rehearing to FERC and thus courts have no
    jurisdiction to review this determination by FERC.      15 U.S.C.
    § 717r(a) ("No proceeding to review any order of the Commission
    shall be brought by any person unless such person shall have made
    application to the Commission for a rehearing thereon.").
    -32-
    By finding the dredging activities were part of the
    construction and operation of the terminal facility, FERC has
    interpreted the Rhode Island dredging at issue in this case to be
    within its jurisdiction.      Thus, the Category B Assent process
    utilized by Rhode Island clearly collides with FERC's delegated
    authority and is preempted.     FERC made this clear in its order
    regarding Weaver's Cove's application, which stated that state
    agencies could not use state law to "prohibit or unreasonably delay
    the construction or operation of facilities approved by this
    Commission."   Weaver's Cove Energy, LLC, 112 F.E.R.C. at ¶ 61,546.
    FERC affirmed this point on rehearing, in response to the City of
    Fall River's challenge. Weaver's Cove Energy, LLC, 114 F.E.R.C. at
    ¶ 61,185-86.
    CRMC's handling of the Category B Assent process both
    conflicts with and is an obstacle to the authority FERC has
    asserted in this case.     Unlike CZMA consistency review, which
    allows the CRMC to review the dredging proposals, limited by a six-
    month deadline and administrative and federal judicial review, the
    Category B Assent process contains no such limitations, and to this
    date the appellant has not processed this application or reached
    any decision on the merits.    CRMC has taken the position that it
    must carry out the Category B Assent process concurrently with the
    consistency review, and because the consistency review has not
    commenced, it cannot address the application for Category B Assent.
    -33-
    Thus, even if concurrence were presumed, CRMC's position is that
    the Category B Assent process would itself independently block full
    licensing of the facility. This is clearly an application of state
    law that delays or has the potential to prohibit the ultimate
    licensing and construction of the LNG terminal.      Weaver's Cove
    Energy, LLC, 112 F.E.R.C. at ¶ 61,546.   Further, CRMC's two bites
    at the apple approach necessarily conflicts with the federal
    process for and interest in defining what is necessary data.
    Because CRMC's actions here conflict with FERC's jurisdiction and
    the limits for consistency review, it is preempted.14
    14
    CRMC and Massachusetts also incorrectly argue that the
    district court based its Category B Assent preemption on the
    doctrine of federal navigational servitude and that a finding of
    preemption under the servitude was improper because Congress failed
    to invoke it expressly within the NGA. The argument misreads the
    district court's holding and is irrelevant. Congress's power to
    preempt state regulation here emanates not only from its power to
    regulate navigation but also from its power to regulate commerce
    itself. U.S. Const. art. I, § 8, cl. 3; 
    43 U.S.C. § 1314
    (a) ("The
    United States retains all its navigational servitude and rights in
    and powers of regulation and control of said lands and navigable
    waters for the constitutional purposes of commerce, [and]
    navigation . . . ."); see also First Iowa Hydro-Elec. Coop. v.
    Federal Power Com., 
    328 U.S. 152
    , 182 (1946) ("The states possess
    control of the waters within their borders, 'subject to the
    acknowledged jurisdiction of the United States under the
    Constitution in regard to commerce and the navigation of the waters
    of rivers.'" (quoting United States v. Appalachian Elec. Power Co.,
    
    311 U.S. 377
    , 404 (1940)).
    In its reply brief, CRMC raises a new argument that while
    Congress could preempt commercial regulation under the Commerce
    Clause, it could not displace Rhode Island's property rights
    without invoking the navigational servitude doctrine.       Because
    arguments raised for the first time in reply briefs are
    procedurally barred, we need not consider this contention. United
    States v. Hall, 
    557 F.3d 15
    , 20 n.3 (1st Cir. 2009). In any event,
    the argument is wrong.     The Supreme Court has held that state
    -34-
    D.         Rivers and Harbors Act
    Finally, CRMC argues that the federal Rivers and Harbors
    Act saves its state Category B Assent process from preemption.
    Pointing   to   language   in    the    NGA    qualifying   FERC's   exclusive
    authority to the extent that it affects law "related to" the
    authority of other federal agencies, 15 U.S.C. § 717b(e)(1), CRMC
    argues that the NGA preserves not only the Army Corps's role in
    approving dredging activities but also the entire body of law
    "related to" that role.         Since the Army Corps's approval process
    under the Rivers and Harbors Act does not preempt state licensing
    schemes, CRMC argues that the savings clause in the NGA must
    therefore protect Category B Assent.
    These arguments, assuming arguendo they were preserved in
    the district court, are meritless.            The language of § 717(b)(e)(1)
    is plainly aimed at preserving the authority of federal agencies
    and not that of state agencies like CRMC.           CRMC's argument that its
    state licensing program is "related to" the authority of FERC is
    also untenable.    As CRMC points out in other parts of its brief,
    CRMC's authority to require Category B Assent derives from Rhode
    Island's status as a sovereign, whereas the Army Corps's authority
    derives from the federal government.            The fact that the Rivers and
    property interests in land may not preempt federal statutes enacted
    pursuant to the Commerce Clause. Douglas v. Seacoast Prods., Inc.,
    
    431 U.S. 265
    , 283-84 (1977).
    -35-
    Harbors Act does not itself preempt Category B Assent is therefore
    irrelevant to the NGA's preemptive effect.
    Under   its   exclusive   authority,   FERC   considers   the
    dredging in Rhode Island to be a part of the LNG construction.
    FERC, as required by the NGA, has provided CRMC an opportunity to
    review the project through CZMA consistency review.       CRMC cannot
    now avoid presumed concurrence by relying on a nearly identical
    state law licensing procedure.
    The district court's judgment is affirmed.
    -36-
    

Document Info

Docket Number: 08-2440

Citation Numbers: 589 F.3d 458

Judges: Lynch, Ripple, Torruella

Filed Date: 10/26/2009

Precedential Status: Precedential

Modified Date: 8/3/2023

Authorities (30)

Torrech-Hernandez v. General Elec. Co. , 519 F.3d 41 ( 2008 )

Spggc, LLC Metabank U.S. Bank, N.A. v. Kelly A. Ayotte, New ... , 488 F.3d 525 ( 2007 )

Gulf of Maine Fishermen's Alliance v. Daley , 292 F.3d 84 ( 2002 )

Velázquez-García v. Horizon Lines of Puerto Rico, Inc. , 473 F.3d 11 ( 2007 )

Williams v. United States (In Re Williams) , 156 F.3d 86 ( 1998 )

Pharmaceutical Research & Manufacturers of America v. ... , 249 F.3d 66 ( 2001 )

Good v. Altria Group, Inc. , 501 F.3d 29 ( 2007 )

Maine People's Alliance & Natural Resources Defense Council ... , 471 F.3d 277 ( 2006 )

City of Bangor v. Citizens Communications Co. , 532 F.3d 70 ( 2008 )

Pagan v. Calderon , 448 F.3d 16 ( 2006 )

Fitzgerald v. Harris , 549 F.3d 46 ( 2008 )

City of Fall River v. Federal Energy Regulatory Commission , 507 F.3d 1 ( 2007 )

United States v. Hall , 557 F.3d 15 ( 2009 )

Santiago-Ramos v. Centennial P.R. Wireless Corp. , 217 F.3d 46 ( 2000 )

northern-natural-gas-co-northern-border-pipeline-company-v-iowa , 377 F.3d 817 ( 2004 )

Douglas v. Seacoast Products, Inc. , 97 S. Ct. 1740 ( 1977 )

First Iowa Hydro-Electric Cooperative v. Federal Power ... , 66 S. Ct. 906 ( 1946 )

Distrigas Corporation v. Federal Power Commission, Pacific ... , 495 F.2d 1057 ( 1974 )

Weaver's Cove Energy, LLC v. Rhode Island Coastal Resources ... , 583 F. Supp. 2d 259 ( 2008 )

Millennium Pipeline Co., LP v. Gutierrez , 424 F. Supp. 2d 168 ( 2006 )

View All Authorities »