Mirra Co. v. School Administrative District 35 , 251 F.3d 301 ( 2001 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 00-1958
    MIRRA COMPANY, INC.,
    Plaintiff, Appellant,
    v.
    SCHOOL ADMINISTRATIVE DISTRICT #35
    A POLITICAL SUBDIVISION OF THE STATE OF MAINE
    WITH PRINCIPAL OFFICES IN SOUTH BERWICK, MAINE,
    Defendant Appellee.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MAINE
    [Hon. D. Brock Hornby, U.S. District Judge]
    Before
    Boudin, Circuit Judge,
    Stahl, Senior Circuit Judge,
    and Lynch, Circuit Judge.
    David P. Ray, with whom Burns Ray DeLano & Macdonald, P.A.,
    Frank P. Spinella, Jr., and Hall, Morse, Anderson, Miller &
    Spinella, P.A., were on brief, for appellant.
    Jerrol A. Crouter, with whom Drummond Woodsum & MacMahon,
    were on brief, for appellee.
    June 5, 2001
    STAHL, Senior Circuit Judge.      This case arose from a
    dispute between the parties to a construction contract.                 The
    Maine School Administrative District No. 35 (MSAD 35) and the
    Mirra Company, Inc.(Mirra), had entered into a contract which
    obligated Mirra to do site work at a high school project in the
    district.    Problems soon arose, and now each party has claims
    against the other. The sole question before us is whether the
    parties must submit these claims to binding arbitration.              Mirra
    argues   that   the   contract   requires   disputes    to   be   resolved
    through arbitration, while MSAD 35 claims that there is no such
    agreement in the final version of the parties' contract.                The
    district court agreed with MSAD 35 and held that the contract
    unambiguously did not require arbitration.        We affirm.
    I. BACKGROUND
    In early 1997, the State of Maine Bureau of General
    Services (BGS) advertised for bids for site work at the new
    Marshwood High School in South Berwick, Maine.           MSAD 35 is the
    public   school   district   for   that   town.   The    bid      documents
    provided that the     Standard General Conditions for construction
    contracts would apply, subject to certain amendments, listed in
    the attached Supplementary General Conditions.               As relevant
    here, the Standard General Conditions stated:
    Article 42. ARBITRATION
    -3-
    If, in the performance of this
    contract, there arises a dispute between the
    Owner and the Contractor which cannot be
    settled,   then   this  dispute   shall   be
    submitted to Arbitration and both the Owner
    and the Contractor shall be bound by the
    decision of the Arbitrator.
    The   membership  of   the   American
    Arbitration Association shall be used as
    Arbitrators and the procedures used for
    Arbitration shall be in conformity with the
    Construction Industry Arbitration Rules as
    administered by the American Arbitration
    Association.
    The Supplementary General Conditions used two different
    methods to amend the General Conditions.           Where only a few words
    were to be changed, the Supplementary General Conditions merely
    referenced the article number and title of the relevant General
    Condition    to    be   changed   and    the    minor     alterations   were
    described.     But where an entire article was to be substituted
    with a new one, the Supplemental General Conditions referenced
    the   relevant     article   number     and    title    and   set   forth   an
    instruction to delete the article               in its entirety and to
    substitute a      new one with a new heading.          This second procedure
    was used with respect to the agreement’s original arbitration
    provision resulting in the following change:
    Article 42 - ARBITRATION: Delete in
    its entirety and substitute:
    Article 42 - DISPUTE RESOLUTION:
    If, in the performance of this
    Contract,    there arises a dispute between
    -4-
    Contractor and Owner that cannot be resolved
    by the parties to the Contract, the dispute
    shall be referred to the Director of the
    Bureau of General Services, who, at his/her
    discretion, will submit the dispute to non-
    binding Alternate Dispute Resolution or
    binding arbitration (ADR).   If the parties
    in dispute are not satisfied with the
    results of ADR Owner or Contractor may re-
    submit the dispute to the Director for
    binding arbitration.
    On May 15, 1997, Mirra submitted its bid to BGS, which
    was the lowest of all received, and BGS forwarded it to MSAD 35.
    On June 9, 1997, MSAD 35 sent Mirra a addendum designed to
    further modify the Bidding and Contract Documents.        The addendum
    did not delete and replace any articles wholesale, as the BGS's
    Supplementary General Conditions had done, but merely referenced
    each article it was to modify and set forth what was to be
    deleted and what was to be added within the relevant article as
    it most recently stood.      On June 23, 1997, Mirra explicitly
    acknowledged the changes wrought by the addendum and executed
    the   contract.   The   addendum    modified   the   parties’   dispute
    resolution agreement as follows:
    1.04   Supplementary   General    Conditions,
    Section 3-B-4, Article 42
    DELETE:   The entire paragraph
    ADD:           "Any disputes arising out
    of or in the course of this Agreement,
    which   cannot    be   settled    through
    discussion between parties, shall be
    submitted   to   mediation   before   any
    lawsuit or Demand for Arbitration is
    filed.    When either party requests
    -5-
    mediation, the parties, [sic] shall
    attempt to agree on a single mediator to
    mediate the dispute. The mediator shall
    assist the parties in attempting to
    solve their dispute by agreement.    The
    parties agree to participate in good
    faith during the mediation process
    including the selection of the mediator.
    The parties agree that they will engage
    in mediation for at least three days,
    unless a shorter period is set by the
    mediator, before abandoning the process.
    The cost of mediation shall be borne
    equally by each party.
    Notwithstanding this provision, either
    party may file suit before or during
    mediation if the party in good faith
    deems it necessary to avoid losing the
    right to sue. If suit is filed before
    good   faith   mediation   efforts   are
    completed, the party filing suit will
    agree to stay until all mediation
    efforts have been completed.
    In   early   2000,   as    the   project   neared   completion,
    various disputes arose between the parties, and each asserted
    claims against the other.            As required by the contract, the
    parties participated in mediation on May 17, 2000, but without
    success.   MSAD 35 then filed suit against Mirra on May 19, 2000,
    in the Maine Superior Court.          On May 22, 2000, Mirra filed this
    diversity action    requesting an order to compel arbitration.          On
    July 1, 2000, the district court held that "the contract is
    unambiguous and does not require arbitration."             Mirra appeals
    that decision.
    II. DISCUSSION
    -6-
    The interpretation of unambiguous contract language is
    a matter of law reserved to the courts.           Golden Rule Ins. Co. v.
    Atallah,   
    45 F.3d 512
    ,   516   (1st   Cir.   1995)   ("Under   Maine's
    general
    law of contracts, the interpretation of a contract is a question
    for the fact finder only if the court first determines that the
    contract is ambiguous, a question of law.").              For this reason,
    we afford de novo review to the district court’s ruling.               Paul
    Revere Variable Annuity Ins. Co. v. Kirschhofer, 
    226 F.3d 15
    ,
    18-19 (1st Cir. 2000).
    Arbitration is a contractual matter, and no party may
    be forced to arbitrate a dispute unless she has expressly agreed
    to do so by contract.     Air Line Pilots Ass'n v. Miller, 
    523 U.S. 866
    , 876 (1998).        In determining whether the parties to a
    contract have agreed to arbitrate their disputes, courts "should
    apply ordinary state-law principles that govern the formation of
    contracts."     First Options of Chicago, Inc. v. Kaplan, 
    514 U.S. 938
    , 944 (1995).       Maine requires "clear contractual language
    evidencing an intent to be bound to [arbitrate]."              Maine Cent.
    R.R. v. Bangor & Aroostook R.R., 
    395 A.2d 1107
    , 1116 (Me. 1978);
    see also Roosa v. Tillotson, 
    695 A.2d 1196
    , 1197-98 (Me. 1997).
    Here, there is no language in the final version of the
    contract that clearly suggests an intent to arbitrate.              Article
    -7-
    42,   as   revised    by   the   addendum,       only    requires     non-binding
    mediation,    after    which     either    party       may   file   suit    or    seek
    arbitration (with the consent of the other party).                       Mirra does
    not   suggest    a    different    interpretation            of   this     language.
    Rather, its central argument is that, when the final addendum
    deleted the     ADR paragraph from the revised Article 42, it also
    deleted the preceding instruction to delete the original Article
    42, thus resulting in its reinstitution.
    We do not agree.       The Supplementary General Conditions
    removed the arbitration clause found in the Standard General
    Conditions,     and   replaced     it     with    an    entirely     new     dispute
    resolution clause. The addendum merely changed the language of
    that new clause so as to require mediation rather than ADR.                        The
    contract unambiguously does not require arbitration.                             Thus,
    either party is free to bring a lawsuit against the other for
    damages arising from a breach of the contract.
    The judgment of the district court is affirmed.
    -8-