Commonwealth of Massachusetts v. US Nuclear Regulatory Commissi , 708 F.3d 63 ( 2013 )


Menu:
  •             United States Court of Appeals
    For the First Circuit
    Nos. 12-1404, 12-1772
    COMMONWEALTH OF MASSACHUSETTS,
    Petitioner,
    v.
    U.S. NUCLEAR REGULATORY COMMISSION; THE UNITED STATES OF AMERICA,
    Respondents,
    ENTERGY NUCLEAR OPERATIONS, INC.;
    ENTERGY NUCLEAR GENERATION COMPANY,
    Intervenors.
    PETITIONS FOR REVIEW OF ORDERS OF THE
    U.S. NUCLEAR REGULATORY COMMISSION
    Before
    Lynch, Chief Judge,
    Torruella, Circuit Judge,
    and DiClerico,* District Judge.
    Matthew Brock, Assistant Attorney General, Office of the
    Attorney General, Environmental Protection Division, with whom
    Martha Coakley, Attorney General, was on brief, for petitioner.
    James E. Adler, Attorney, Office of the General Counsel, U.S.
    Nuclear Regulatory Commission, with whom Ignacia S. Moreno,
    Assistant Attorney General, J. David Gutner II, Attorney, Appellate
    Section, Environmental and Natural Resources Division, U.S.
    Department of Justice, Marian L. Zobler, Acting General Counsel,
    *
    of the District of New Hampshire, sitting by designation.
    John F. Cordes, Jr., Solicitor, and Lauren Woodall, Attorney,
    Office of General Counsel, U.S. Nuclear Regulatory Commission, were
    on brief, for respondents.
    Kevin P. Martin, with whom Elise N. Zoli, Goodwin Procter LLP,
    David R. Lewis, Paul A. Gaukler, Timothy J. V. Walsh, and Pillsbury
    Winthrop Shaw Pittman LLP, were on brief, for intervenors Entergy
    Nuclear Operations, Inc. and Entergy Nuclear Generation Company.
    February 25, 2013
    -2-
    LYNCH, Chief Judge.        The Commonwealth of Massachusetts
    petitions for review from the Nuclear Regulatory Commission's
    ("NRC"   or   "Commission")     March     8,    2012      order    denying   the
    Commonwealth's    petition    for   review     of   the   Atomic    Safety   and
    Licensing Board's ("ASLB") denial of Massachusetts's motion to
    admit a new contention, and other related requests (12-1404).                The
    NRC rejected the Commonwealth's claims that the environmental
    findings in the environmental impact statement ("EIS"), prepared
    under the National Environmental Policy Act ("NEPA"), 
    42 U.S.C. § 4321
     et seq., were inadequate in light of the damage to the
    Fukushima Daiichi ("Fukushima") nuclear power plant in Japan in
    March of 2011.1    The Commonwealth also petitions for review from
    the NRC's May 25, 2012 vote to renew the license of the Pilgrim
    Nuclear Power Station in Plymouth, Massachusetts, and the May 29,
    2012 renewed license (12-1772).
    The Commonwealth's substantive challenges to the NRC's
    decisions are not based in any alleged failure on the part of the
    NRC to ensure basic health and safety under the Atomic Energy Act
    ("AEA"), 
    42 U.S.C. § 2011
    , et seq. Rather, the Commonwealth argues
    1
    Entergy Nuclear Operations, Inc., and Entergy Nuclear
    Generation Company (collectively, "Entergy"), the operators of
    Pilgrim Nuclear Power Station, filed an application with the NRC on
    January 25, 2006, to renew the plant's operating license, which was
    set to expire on June 8, 2012, for an additional twenty years. 
    71 Fed. Reg. 15,222
     (Mar. 27, 2006). Pilgrim has been operating since
    1972. After the NRC issued its final EIS for Pilgrim in July of
    2007, but before the renewed license was issued, the Great East
    Japanese Earthquake occurred on March 11, 2011.
    -3-
    that the Commission's failure to file supplemental analysis on the
    environmental impacts of relicensing in light of purported new and
    significant   information   learned    from   Fukushima   violated   its
    obligations under NEPA and NRC regulations.
    The claims made by Massachusetts to the NRC roughly fall
    into three categories.   The first two categories go to whether, in
    light of Fukushima, the EIS was adequate in its environmental
    assessments of: (1) spent fuel pool fires; and (2) core damage2
    events.   The third category questions whether the decision to
    proceed with relicensing was contrary to law.        The Commonwealth
    also asserts that the NRC failed to sufficiently consider its own
    Task Force's report that contained purportedly new and significant
    information, or explain why it did not require supplementation of
    the EIS, and Massachusetts claims that it was denied a hearing in
    violation of the AEA.
    Under the applicable standards of judicial review, we
    deny the petition for review.
    I.
    The regulatory scheme governing this license renewal
    falls under two statutes, the AEA and NEPA.      NEPA and the right to
    2
    The term "core damage" refers to damage to the portion of
    the nuclear reactor containing the nuclear fuel the plant uses to
    create heat for electricity generation.
    -4-
    a hearing under the AEA are at issue here.   The AEA3 requires the
    NRC to provide "adequate protection" for the health and safety of
    the public, 
    42 U.S.C. § 2232
    (a), which the NRC seeks to ensure on
    an ongoing basis through an "evolving set of requirements and
    commitments for a specific plant that are modified as necessary
    over the life of a plant to ensure continuation of an adequate
    level of safety."   
    60 Fed. Reg. 22,461
    , 22,473 (May 8, 1995).4
    Those safety provisions under the AEA are not at issue here.   The
    AEA also states that the NRC shall grant a hearing to a person
    affected by a relicensing, 
    42 U.S.C. § 2239
    (a), but as we discuss
    later, the NRC determined that the Commonwealth did not meet the
    procedural requirements, and that decision was not arbitrary and
    capricious.
    3
    The AEA is the NRC's organic statute, authorizing the NRC to
    issue licenses to operate nuclear power plants for a period not to
    exceed 40 years. 
    42 U.S.C. § 2133
    (c). The AEA also permits the
    renewal of operating licenses, 
    id.,
     and delegates to the NRC the
    authority to determine appropriate rules and regulations,
    Massachusetts v. United States, 
    522 F.3d 115
    , 119 (1st Cir. 2008);
    see also Siegel v. AEC, 
    400 F.2d 778
    , 783 (D.C. Cir. 1968) (AEA is
    "a regulatory scheme which is virtually unique in the degree to
    which broad responsibility is reposed in the administering agency,
    free of close prescription in its charter as to how it shall
    proceed in achieving the statutory objectives"); 
    10 C.F.R. § 54.31
    (b) (permitting renewal up to 20 years before expiration for
    no more than 20 additional years beyond the current license's
    expiration date).
    4
    At the license renewal stage, the NRC has decided to focus
    its safety review on managing the aging of important plant
    structures, components, and systems. See Massachusetts, 
    522 F.3d at 119
    ; 
    10 C.F.R. §§ 54.21
    , 54.29(a).
    -5-
    NEPA, by contrast, requires federal agencies to prepare
    an EIS for major federal actions that would significantly affect
    the quality of the human environment, including a discussion of
    "the environmental impact of the proposed action," "any adverse
    environmental effects which cannot be avoided should the proposed
    action be implemented," and "alternatives to the proposed action."
    
    42 U.S.C. § 4332
    (C)(i)-(iii). Relicensing requires the preparation
    of an EIS.    
    10 C.F.R. §§ 51.20
    (b)(2) (requiring EIS for renewal),
    51.95(c) (discussing what EIS must address).
    NEPA's EIS requirement serves two purposes.          First, "it
    places upon an agency the obligation to consider every significant
    aspect of the environmental impact of a proposed action."            Balt.
    Gas & Elec. Co. v. Natural Res. Def. Council, Inc., 
    462 U.S. 87
    , 97
    (1983) (quoting Vt. Yankee Nuclear Power Corp. v. Natural Res. Def.
    Council, Inc., 
    435 U.S. 519
    , 553 (1978)) (internal quotation marks
    omitted).     Second, it provides assurance that the agency will
    inform the public that it has considered environmental concerns in
    its decisionmaking process.         
    Id.
     (citing Weinberger v. Catholic
    Action of Haw./Peace Educ. Project, 
    454 U.S. 139
    , 143 (1981)). Put
    differently,    NEPA   seeks   to   guarantee   process,   not    specific
    outcomes.    Town of Winthrop v. FAA, 
    535 F.3d 1
    , 4 (1st Cir. 2008).
    In short, NEPA requires the agency to take a "hard look" at the
    environmental consequences of a major federal action.        Balt. Gas &
    Elec. Co., 
    462 U.S. at 97
    .
    -6-
    It is significant to this petition that the NRC assesses
    environmental impacts through two different procedures.            One, for
    site-specific impacts, is done in the course of the individual
    plant relicensing.    The other, for impacts that are generic to all
    plants of a particular type, is done through rulemaking rather than
    individual licensing proceedings.           The Commonwealth confuses the
    two, and attempts to raise in the petition seeking review of the
    relicensing issues which both belong in generic rulemaking, see
    Massachusetts v. United States, 
    522 F.3d 115
    , 127 (1st Cir. 2008)
    (environmental impacts of spent fuel pools dealt with through
    rulemaking), and are in fact being addressed in that rulemaking.
    As to relicensing, the NRC requires an applicant to
    submit an environmental report with its relicensing application.
    
    10 C.F.R. § 51.53
    (c)(1).     That was done here in 2006.         The report
    for a license renewal must analyze the environmental impacts of the
    proposed    action   and   include     a     severe   accident   mitigation
    alternatives ("SAMA") analysis.            
    Id.
     § 51.53(c)(3)(ii)(L).   The
    SAMA analysis, in the most basic sense, is a cost-benefit analysis
    that addresses whether the expense of implementing a mitigation
    measure not mandated by the NRC is outweighed by the expected
    reduction in environmental cost it would provide in a core damage
    event.5    See Duke Energy Corp., 
    56 N.R.C. 1
    , 7-8 (2002) ("Whether
    5
    Included as benefits are averted costs such as public
    exposure, offsite property damage, occupational exposure costs,
    cleanup and decontamination costs, and replacement power costs.
    -7-
    a SAMA may be worthwhile to implement is based upon a cost-benefit
    analysis -- a weighing of the cost to implement the SAMA with the
    reduction in risks to public health, occupational health, offsite
    and onsite property.").
    As to the second mechanism for environmental impacts that
    are not plant-specific, but instead apply to all like plants, the
    Supreme Court has held that the NRC is permitted to make generic
    determinations to meet its NEPA obligations.         Balt. Gas & Elec.
    Co., 
    462 U.S. at 101
     (stating generic method is "clearly an
    appropriate method of conducting the hard look required by NEPA").
    The NRC has labeled these issues as "Category 1" issues and has
    adopted generic EISs for them.      See 10 C.F.R. pt. 51, subpt. A,
    app. B (listing NEPA issues for license renewal and assigning them
    Category 1 or 2 classification); 
    61 Fed. Reg. 28,467
     (June 5, 1996)
    (explaining generic EIS).    Those environmental impacts need not be
    included in an environmental report nor need they be considered on
    a site-specific basis in the EIS.       See 
    10 C.F.R. §§ 51.53
    (c)(3)(i)
    (environmental    report),     51.71(d)     (EIS).       These    generic
    determinations need not be addressed in individual proceedings. As
    we held in an earlier case, the generic rulemaking includes the
    subject   of   environmental    impacts     of   spent   fuel    pools.
    Massachusetts, 
    522 F.3d at 127
    .
    Going back to these relicensing proceedings, in certain
    instances where an EIS has been prepared, and the relicensing has
    -8-
    not yet occurred, the emergence of new information will require
    federal agencies to supplement an EIS.                  Marsh v. Or. Natural Res.
    Council, 
    490 U.S. 360
    , 372-73 (1989).                 Even so, to ensure that the
    agency    decisionmaking        process      is   not     delayed       unnecessarily,
    supplementation     of    the    EIS    is      not    required     every     time   new
    information arises.       
    Id. at 373
    .         Rather, a supplemental EIS only
    need be prepared if there are "significant new circumstances or
    information."     Town of Winthrop, 
    535 F.3d at 7
     (quoting 
    40 C.F.R. § 1502.9
    (c)(1))        (emphasis      omitted);         see     also      
    10 C.F.R. § 51.92
    (a)(2) (requiring final EIS be supplemented with "new and
    significant"     information).          That      means    new    information        must
    "paint[] a dramatically different picture of impacts compared to
    the description of impacts in the EIS." Town of Winthrop, 
    535 F.3d at 12
    ; see also Wisconsin v. Weinberger, 
    745 F.2d 412
    , 418 (7th
    Cir.     1984)   (supplementation           required      where     new     information
    "provides    a   seriously      different       picture    of     the     environmental
    landscape").
    To obtain a hearing on this claim of new information,
    requestors must meet certain requirements.                  In this case, two NRC
    regulations are relevant. First, where the record has been closed,
    a party must meet the record reopening standards to have its new
    information      considered      in    an    adjudication.           See     
    10 C.F.R. § 2.326
    (a)(1)-(3).            The     NRC's         regulations       impose    three
    requirements:
    -9-
    (1) The motion must be timely. However, an
    exceptionally grave issue may be considered in
    the discretion of the presiding officer even
    if untimely presented;
    (2) The motion must address a significant
    safety or environmental issue; and
    (3) The motion must demonstrate that a
    materially different result would be or would
    have been likely had the newly proffered
    evidence been considered initially.
    
    Id.
    Second, the requestor seeking a formal hearing must also
    meet the Commission's general contention admissibility standards.
    The request for a hearing must:
    (i) Provide a specific statement of the issue
    of law or fact to be raised or controverted
    . . . ;
    (ii) Provide a brief explanation of the basis
    for the contention;
    (iii) Demonstrate that the issue raised in the
    contention is within the scope of the
    proceeding;
    (iv) Demonstrate that the issue raised in the
    contention is material to the findings the NRC
    must make to support the action that is
    involved in the proceeding;
    (v) Provide a concise statement of the alleged
    facts or expert opinions which support the
    requestor's/petitioner's position on the issue
    and on which the petition intends to rely at
    hearing, together with references to the
    specific sources and documents on which the
    requestor/petitioner   intends   to  rely   to
    support its position on the issue;
    (vi) In a proceeding other than one under 10
    C.F.R. 52.103, provide sufficient information
    to show that a genuine dispute exists with the
    applicant/licensee on a material issue of law
    or fact. . . .
    
    Id.
     § 2.309(f)(1)(i)-(vi).
    -10-
    II.
    A.        Proceedings Prior to Fukushima
    As said, Entergy's relicensing application included an
    environmental report containing a SAMA analysis.        The analysis
    included scenarios dealing with complete loss of offsite power,
    various sorts of operator failures during core damage events, the
    possibility of hydrogen build up in a core damage event leading to
    an explosion, and the use of filtered vents.
    The   environmental    report    did    not   address   the
    environmental impacts of spent fuel pool accidents6 because the NRC
    had adopted a generic EIS on that issue.          Office of Nuclear
    Regulatory Research, U.S. Nuclear Regulatory Comm'n, NUREG-1437, 1
    Generic Environmental Impact Statement for License Renewal of
    Nuclear Plants: Main Report (May 1996).7         This court rejected
    Massachusetts's earlier challenge that this spent fuel pool issue
    6
    Spent fuel rods are a radioactive waste product of nuclear
    power plants and are often stored in racks in water-filled storage
    pools located at the plant. See Massachusetts, 
    522 F.3d at 122
    .
    When Pilgrim was originally licensed in 1972, there was a national
    policy of eventually disposing of the spent fuel through
    reprocessing, but that policy was abandoned in the mid-1970s. 
    Id.
    Without reprocessing, and without a national repository, spent fuel
    has accumulated at onsite storage facilities. 
    Id.
    7
    The regulation in place stated that "[t]he expected increase
    in the volume of spent fuel from an additional 20 years of
    operation can be safely accommodated on site with small
    environmental effects through dry or pool storage at all plants if
    a permanent repository or monitored retrievable storage is not
    available."   Massachusetts, 
    522 F.3d at
    121 n.4 (alteration in
    original) (quoting 10 C.F.R. pt. 51, subpt. A, app. B).
    -11-
    had to be heard in the relicensing rather than in rulemaking and
    preserved for the Commonwealth its ability to present its arguments
    in rulemaking after it had made the wrong choice as to which
    vehicle was proper.   Massachusetts, 
    522 F.3d at 127-33
    .8   The staff
    issued a final EIS in July of 2007.      Office of Nuclear Reactor
    Regulation, U.S. Nuclear Regulatory Comm'n, NUREG-1437, Generic
    Environmental Impact Statement for License Renewal of Nuclear
    Plants, Supplement 29 Regarding Pilgrim Nuclear Power Station (July
    2007).   Upon completing consideration of a contention filed by
    Pilgrim Watch in the relicensing, the ASLB9 closed the record in
    June of 2008.   See Entergy Nuclear Generation Co., 
    68 N.R.C. 590
    ,
    595-97 & n.26 (2008).   In March of 2010, the NRC partially reversed
    an earlier ASLB decision and remanded one limited issue, regarding
    a meteorological model used in the SAMA analysis, to the ASLB for
    8
    The NRC later denied that rulemaking petition because the
    studies presented by Massachusetts did not constitute new and
    significant information and the NRC's findings related to the
    storage of spent nuclear fuel in pools remained valid. 
    73 Fed. Reg. 46,204
    , 46,212 (Aug. 8, 2008). The Second Circuit upheld the
    NRC's denial of the Commonwealth's petition for rulemaking. New
    York v. NRC, 
    589 F.3d 551
    , 553-55 (2d Cir. 2009) (per curiam).
    9
    The NRC "appoints [ASLBs] to conduct public hearings and to
    make intermediate or final decisions in administrative proceedings"
    relating to licensing decisions. Johnston v. NRC, 
    766 F.2d 1182
    ,
    1183 (7th Cir. 1985). A Board consists of three members, one of
    whom is qualified in the conduct of administrative proceedings and
    two of whom have technical or other qualifications the NRC deems
    appropriate. 
    42 U.S.C. § 2241
    (a). ASLBs now preside over most
    licensing hearings. Citizens Awareness Network, Inc. v. United
    States, 
    391 F.3d 338
    , 357 n.6 (1st Cir. 2004) (Lipez, J.,
    concurring).
    -12-
    further hearing.     Entergy Nuclear Generation Co., 
    71 N.R.C. 287
    (2010).
    B.         Fukushima and the NRC Response
    On March 11, 2011, before the ASLB had issued a decision
    on the remanded issue, an earthquake and tsunami occurred off the
    coast of Japan.    The tsunami hit the Fukushima nuclear power plant
    causing a blackout at five of the six units and resulting in core
    damage at three of the units.             Notably, however, virtually no
    damage occurred to any of the spent fuel pools on site and there
    were no spent fuel pool fires.
    The NRC took action within days to respond to the grave
    events at Fukushima, establishing a Task Force by a March 23, 2011
    memorandum, and requiring the Task Force "to conduct a methodical
    and systematic review of [the NRC's] processes and regulations to
    determine whether the agency should make additional improvements to
    [its]   regulatory   system   and    to    make    recommendations   to   the
    Commission for its policy direction."             The NRC also directed its
    staff to complete a review and implement lessons learned by 2016.
    On July 12, 2011, the Task Force issued its report,
    making twelve overarching recommendations, including on emergency
    preparedness and mitigation measures.             The Task Force also made
    clear that a sequence of events like that at Fukushima is unlikely
    to occur in the United States and that "continued operation and
    -13-
    continued licensing activities do not pose an imminent risk to
    public health and safety."
    On    March     12,   2012,    the     NRC     issued       three       orders
    implementing certain Task Force recommendations.                    First, the NRC
    ordered    license    holders     to    "develop,    implement          and     maintain
    guidance and strategies to restore or maintain core cooling,
    containment, and [spent fuel pool] cooling capabilities in the
    event of a beyond-design-basis external event."                     Second, the NRC
    ordered    all    boiling   water      reactors    with    Mark     I   and     Mark    II
    containments (including Pilgrim) to install hardened vents to
    ensure proper venting of the structure.                  Third, the NRC required
    "provisions for reliable spent fuel pool indications," because
    during the Fukushima event "[t]he lack of information on the
    condition    of    the    spent     fuel   pools     contributed         to     a     poor
    understanding of possible radiation releases and adversely impacted
    effective prioritization of emergency response actions by decision
    makers."    Each applies to Pilgrim.
    C.          Massachusetts's Post-Fukushima Motion to the NRC to Admit
    Contention
    On June 2, 2011, slightly less than three months after
    Fukushima, Massachusetts moved to admit a contention and to reopen
    the   Pilgrim     record,   arguing      that    Fukushima    revealed          new    and
    significant information that the environmental impact analysis and
    SAMA analysis needed to address.            The Commonwealth contended that
    Fukushima showed: (1) the likelihood of spent fuel pool accidents
    -14-
    was higher than estimated in the existing EIS;10 and (2) the
    frequency of core-melt accidents was also higher than estimated in
    the existing EIS, and relatedly, in light of new information on a
    variety     of   matters   concerning   core   damage   events,11   certain
    mitigation measures that the SAMA analysis ignored or rejected
    might be cost-effective.12
    Massachusetts   also   included   a   petition   for   waiver,
    seeking to litigate the spent fuel pool accident issues in the
    individual adjudication, 
    10 C.F.R. § 2.335
    (b), as opposed to
    challenging it through rulemaking. In the alternative, if a waiver
    was denied, Massachusetts requested that the NRC rescind the spent
    fuel    pool     determinations   through   rulemaking,    and   that   the
    relicensing proceedings be suspended until that rulemaking request
    was resolved.
    10
    Massachusetts's expert stated in his report that the loss
    of water in an event could lead to a pool fire and that the
    Fukushima incident "provide[d] direct experience of events that
    could be precursors of pool fires."
    11
    These included operators' ability to mitigate an accident,
    the effects of secrecy about mitigation measures, the risk of
    hydrogen explosions during core damage events, and the use of
    filtered venting.
    12
    Earlier in the relicensing proceeding, the agency had
    considered some similar issues raised in a contention by a
    different group, including the accuracy of the probabilistic risk
    assessment's ("PRA") estimation of core damage frequency in the
    SAMA analysis and the use of filtered vents, which were rejected by
    the agency in an October 16, 2006 order.
    -15-
    The contention was accompanied by an expert report by Dr.
    Gordon Thompson, a senior research scientist at Clark University.
    Massachusetts moved, on August 11, 2011, to supplement its filing
    with the released Task Force Report, which Massachusetts stated
    "provide[d] further support for its contention."     Massachusetts
    filed a supplemental declaration from Dr. Thompson, which discussed
    the reasons he felt the report supported his views in support of
    the contention.
    On November 28, 2011, the ASLB denied Massachusetts's
    motion for a hearing, as well as the waiver motion, and the request
    for a stay.   The ASLB determined that: (1) the spent fuel concerns
    were not unique to Pilgrim and so denied the waiver petition; and
    (2) each portion of the contention concerning core damage events
    failed to meet the agency's record reopening standards and/or its
    general admissibility standards.13
    The NRC affirmed14 the ASLB's decision on March 8, 2012.
    On the spent fuel pool issues, the NRC denied the waiver petition,
    referred the rulemaking petition to its staff, and denied the
    request to suspend the proceedings pending resolution of that
    13
    One member of the Board concurred, agreeing that the
    contention should be denied, but concluding that the contention was
    premature, and Fukushima-related contentions should be allowed when
    "relevant information becomes ripe for consideration."
    14
    The Chairman concurred in the majority's decision to deny
    the waiver petition and suspension request, but dissented in the
    majority's decision to apply the usual record reopening standards.
    -16-
    petition.   The NRC rejected the contention on all other issues.        It
    noted that Massachusetts had not provided sufficient information to
    make a significant difference in the environmental review. The NRC
    considered the core damage frequency claim and each of the related
    claims that new information on core damage events might affect the
    SAMA analysis, finding for many reasons that each aspect of the
    contention either failed to meet the agency's reopening standards
    or its admissibility standards.    In particular, the NRC explained
    that the failure to sufficiently link the Fukushima events to the
    Pilgrim environmental analysis was the basic problem with the
    contention.
    On May 25, 2012, the majority of the NRC approved the
    renewal of Pilgrim's operating license.     The Chairman was the sole
    dissenter, preferring to wait on making the licensing decision
    until all issues before the agency were resolved.             The other
    Commissioners made no direct response, but two noted that if the
    renewed license were set aside on judicial review, the previous
    license would be reinstated pursuant to 
    10 C.F.R. § 54.31
    (c).
    Massachusetts   petitioned   this   court   for   review.
    Massachusetts's primary arguments are that the NRC violated NEPA
    and acted arbitrarily and capriciously by failing to take a hard
    look at the lessons from Fukushima and by failing to require
    supplementation of the EIS as to both the spent fuel pool and core
    damage concerns before granting a renewed license.      It also argues
    -17-
    that, under NEPA, the NRC should have heard its rulemaking petition
    and completed all the post-Fukushima review before granting the
    license.
    The record shows that the NRC gave a hard look to the
    information Massachusetts presented to it, and it engaged in
    reasoned decisionmaking in explaining why it refused to reopen the
    record and why it denied the contention.   The NRC did not need to
    wait to grant the relicensing based on conjecture that additional
    information might arise in the future.       Indeed, the NRC gave
    assurances that if such information did arise, and resulted in new
    requirements,   those   requirements   would,   under   its   normal
    procedures, be applied to Pilgrim.
    III.
    Because there is no apparent conflict between the NRC's
    record reopening and general admissibility standards and NEPA's
    standard for requiring supplementation of an EIS, we proceed to
    determine if the NRC permissibly applied its procedural rules.   We
    start with the NRC's denial of the waiver of rulemaking petition on
    the spent fuel pool issue.   We then move on to the NRC's rejection
    of the other portions of the contention.   In doing so, we address
    both the record reopening standards and the general admissibility
    standards. We do so because the NRC relied on different provisions
    in those distinct requirements in rejecting the various parts of
    -18-
    the Commonwealth's contention.15 On some substantive issues the NRC
    relied on both standards, and on other issues, rested on just a
    provision in the reopening or the admissibility standards.
    Therefore, we address both standards in order to fully deal with
    the Commonwealth's challenge and the NRC's rejection of the entire
    contention.   For ease of organization, we address each substantive
    issue separately, including the reopening and/or the admissibility
    standards that are the basis for the rejection.            Finally, we
    consider the NRC's decision to proceed with licensing.
    A.         Standard of Review
    Our   review   of    NEPA   claims   is   governed   by   the
    Administrative Procedure Act, 
    5 U.S.C. § 501
    , et seq. ("APA"). See
    Dubois v. U.S. Dep't of Agric., 
    102 F.3d 1273
    , 1284 (1st Cir.
    1996).    The APA "authorizes this court to displace the [NRC's]
    decisions only to the extent that they are 'arbitrary, capricious,
    an abuse of discretion, or otherwise not in accordance with law.'"
    Massachusetts, 
    522 F.3d at 126
     (quoting 
    5 U.S.C. § 706
    (2)(A)).
    Errors of law are reviewed de novo.      Dubois, 
    102 F.3d at 1284
    .
    An agency's decision is not arbitrary and capricious if
    that decision was based on consideration of the relevant factors,
    and if the agency did not commit a clear error of judgment.          Town
    15
    For example, and as will be discussed more below, the NRC
    rejected Massachusetts's "secrecy" argument regarding accident
    mitigation measures only on the basis that it was outside the scope
    of the proceedings, failing to meet one of the general
    admissibility standards. 
    10 C.F.R. § 2.309
    (f)(1)(iii).
    -19-
    of Winthrop, 
    535 F.3d at 8
    .     A decision fails "if the agency relied
    on improper factors, failed to consider pertinent aspects of the
    problem, offered a rationale contradicting the evidence before it,
    or reached a conclusion so implausible that it cannot be attributed
    to a difference of opinion or the application of agency expertise."
    Associated Fisheries of Me., Inc. v. Daley, 
    127 F.3d 104
    , 109 (1st
    Cir. 1997).     "This general posture of deference toward agency
    decision-making      is   particularly      marked    with       regards   to   NRC
    actions,"    including     relicensing,      because    of       the   amount   of
    discretion the AEA grants to the Commission.                 Massachusetts, 
    522 F.3d at 126
    .
    Moreover, in "determining what constitutes significant
    new information," a reviewing court "owes considerable deference"
    to the agency's determination because "that is a factual question
    requiring technical expertise."        Town of Winthrop, 
    535 F.3d at 8
    .
    Thus,   "[c]onsiderable      deference      is   owed       to   the   [agency's]
    determination   of    whether   [a   completed       EIS]    remains    accurate,
    adequate, and current."      
    Id.
    We also give substantial deference to an agency when it
    adopts reasonable interpretations of its own regulations.                  Auer v.
    Robbins, 
    519 U.S. 452
    , 461 (1997).           "We must accept the agency's
    position unless it is plainly erroneous or inconsistent with the
    regulation."    Massachusetts, 
    522 F.3d at 127
     (quoting Auer, 
    519 U.S. at 461
    ) (internal quotation marks omitted).
    -20-
    Still, our role is to ensure that the agency took a "hard
    look" at the purportedly new information and determine whether its
    decisions were arbitrary or capricious. Dubois, 
    102 F.3d at 1284
    .16
    B.        Denial of the Spent Fuel Pool Waiver Petition
    One   of   Massachusetts's   main   claims   before   the   NRC
    concerned the risk of spent fuel pool accidents.            That is a
    Category 1 issue, addressed globally for all nuclear power plants,
    10 C.F.R. pt. 51, subpt. A, app. B, through rulemaking, and that is
    where the NRC is dealing with this issue. Further, NRC regulations
    generally prohibit the challenging of such generic determinations
    in individual adjudicatory proceedings, see 
    10 C.F.R. § 2.335
    (a),
    but under certain specified conditions,17 the NRC will waive that
    16
    At times, Massachusetts's brief appears to make a weak
    argument that the NRC's procedural rules (particularly its record
    reopening standards) are incompatible with NEPA. However, in its
    reply brief, Massachusetts disavows that and asserts it is only
    arguing that the NRC "cannot unreasonably interpret or misapply its
    contention admissibility standards."
    17
    One exception to the prohibition on a challenge in an
    individual proceeding is for a party to seek a waiver under 
    10 C.F.R. § 2.335
    (b), which provides that "[t]he sole ground for
    petition of waiver or exception is that special circumstances with
    respect to the subject matter of the particular proceeding are such
    that the application of the rule or regulation (or provision of it)
    would not serve the purposes for which [it] was adopted." The NRC
    has interpreted the regulation to require a waiver petitioner to
    meet four factors: (1) the rule's strict application would not
    serve the purpose for which it was adopted; (2) there are special
    circumstances that were not considered, explicitly or implicitly,
    in the rulemaking proceeding; (3) those circumstances are "unique"
    to the facility and not common to a large class of facilities; and
    (4) a waiver is necessary to reach a significant safety problem.
    Dominion Nuclear Conn., Inc., 
    62 N.R.C. 551
    , 559-60 (2005). The
    NRC's decision that Massachusetts did not meet the standards was
    -21-
    rule and hear issues in a particular relicensing proceeding.
    Although some may doubt whether Massachusetts has explicitly,
    rather than implicitly, challenged the NRC's ruling on the waiver
    petition, we nonetheless address it briefly.
    In    denying    Massachusetts's    waiver    petition,     the    NRC
    permissibly reasoned that Massachusetts did not show that the spent
    fuel pool issues in its contention were unique to Pilgrim. Rather,
    they   applied    to   all   nuclear    power   plants   and   would    be    more
    appropriately handled through rulemaking.                We add that onsite
    storage of spent fuel is one of the issues being considered in the
    Commission's post-Fukushima review of lessons learned, as the
    Commission itself has noted.
    We also reject the argument that NEPA was violated by the
    NRC decision to go ahead with relicensing.           In addition to denying
    the waiver request and sending the spent fuel pool issue to
    rulemaking, the NRC also considered whether to delay relicensing,
    in light of the information Massachusetts presented.               It stated,
    referring at least in part to the spent fuel pool issue, that "we
    do   not   have   sufficient    information     at   this   time   to   make    a
    significant difference in the Pilgrim environmental review."
    Massachusetts has conceded that "affirmative evidence of a pool
    fire has not emerged" from the Fukushima accident. The record also
    reasonable.
    -22-
    supports    the    NRC's      conclusion   that    there    was    no    apparent
    significant damage to the spent fuel at Fukushima.
    C.          The NRC's Denial of the Commonwealth's Position on Core
    Damage Issues
    1.    The "Direct Experience" Core Damage Frequency Model
    The second major portion of Massachusetts's contention is
    that the existing SAMA analysis in the EIS underestimated core
    damage frequency by an order of magnitude as shown by the Fukushima
    event and thus needed to be supplemented.             The NRC rejected this
    portion of the contention based on its record reopening standards.
    It reasoned that under its record reopening standards: (1) the
    claim was untimely because it could have been raised from the
    outset,    
    10 C.F.R. § 2.326
    (a)(1);   and   (2)     the   claim   did   not
    demonstrate the existence of a significant environmental issue, 
    id.
    § 2.326(a)(2).      These decisions, based on the reopening standards,
    were reasoned and we have no basis to set them aside.18
    18
    The NRC acted reasonably in deciding to apply its record
    reopening standards, a decision Massachusetts does not challenge.
    The ASLB closed the record in June of 2008. See Entergy Nuclear
    Generation Co., 68 N.R.C. at 595-96 & n.26.       Although the NRC
    remanded a portion of another party's contention in 2010, different
    from the one at issue here, the record remained closed as to all
    other issues. Agencies are permitted to impose requirements or
    thresholds for parties seeking to reopen a closed record. See,
    e.g., Vt. Yankee, 
    435 U.S. at 554-55
    . Further, the NRC's reopening
    standards have been upheld by other courts. See N.J. Envtl. Fed'n
    v. NRC, 
    645 F.3d 220
    , 233 (3d Cir. 2011) ("We have upheld the
    motion to reopen standard and deferred to the NRC's application of
    its rules, so long as it is reasonable."); Oystershell Alliance v.
    NRC, 
    800 F.2d 1201
    , 1207 (D.C. Cir. 1986) ("In examining
    petitioners' plea to reopen the record, we rely on the same court-
    sanctioned test applied by the Commission . . . .").
    -23-
    It   is   quite    clear there       was    nothing   new    about    the
    purportedly new methodology used to determine the frequency of core
    damage events.        The methodological issue could have been raised
    from the beginning of the relicensing proceeding by Massachusetts,
    but was not.      
    10 C.F.R. § 2.326
    (a)(1).              Massachusetts belatedly
    asserts that by taking five historical core damage events (Three
    Mile Island, Chernobyl, and three units at Fukushima) and dividing
    that number by the number of operating years of all nuclear power
    plants   worldwide,      the    frequency    of        core   damage    events    is
    approximately ten times higher than the estimate in the SAMA
    analysis.    The same methodological argument could have been made
    before Fukushima occurred.            As the ASLB and the NRC agreed,
    applying the purported "direct experience" methodology at the time
    the initial opportunity for a hearing was announced, pre-Fukushima,
    would have produced a frequency approximately five times greater
    than that contained in the SAMA analysis.                     Although Fukushima
    increased the order of magnitude of the frequency of core damage
    events if assessed under another underlying methodology -- the
    "direct experience" methodology -- the fact that the Fukushima
    disaster occurred is beside the point here as it did not change the
    fact that the underlying methodological challenge was not new.
    Even if it were new, the NRC reasonably concluded this
    methodology contention, timely or not, did not raise a significant
    environmental     issue.       
    10 C.F.R. § 2.326
    (a)(2).          Indeed,   it
    -24-
    reasonably concluded it was already using a better methodology.
    The NRC uses a site-specific and plant-specific PRA methodology,
    which answers three questions: (1) what can go wrong; (2) how
    likely is it; and (3) what are the consequences.19
    The NRC had adequate evidence20 that the "Pilgrim-specific
    PRA is expected to yield a much more accurate estimate of risk
    (including     [core   damage   frequency])   than   a   historical   rate
    calculation using an extremely limited set of data points that
    aggregates all different plant designs, operational practices, and
    site conditions around the world." Further, Massachusetts also did
    not explain how Dr. Thompson's methodology, based on a limited data
    set, would be used to develop a new spectrum of core damage
    frequencies.
    "[A]gencies are entitled to select their own methodology
    as long as that methodology is reasonable," and we give deference
    19
    This requires an evaluation of the combinations of plant
    failures that can lead to core damage, and for each core damage
    sequence identified, an evaluation of core damage progression and
    possible containment failure. R. at 1216. Importantly, the PRA
    methodology is both site-specific and plant-specific, and takes
    into account hazards, the design of the plant, and plant-specific
    operational practices that affect how the plant responds to
    potential challenges. R. at 1903. The overall probability that
    core damage will occur at the plant is calculated by aggregating
    the individual probabilities of various accident scenarios. R. at
    1094.
    20
    By contrast, Dr. Thompson's report admitted his methodology
    relied on "a data set that is comparatively sparse and therefore
    does not provide a statistical basis for a high-confidence estimate
    of [core damage frequency]."     He stated that the data set and
    method provided at most a "reality check" to the PRA estimates.
    -25-
    to that decision here.     Town of Winthrop, 
    535 F.3d at 13
     (quoting
    Hughes River Watershed Conservancy v. Johnson, 
    165 F.3d 283
    , 289
    (4th Cir. 1999)) (internal quotation mark omitted).
    2.   The NRC's Denial of the SAMA Specific Issues
    Massachusetts's contention also raised more specific
    information that it said should be considered or reevaluated in a
    SAMA analysis, arguing that the information concerned the cost-
    effectiveness of mitigation alternatives.            The NRC rejected each
    one, offering a reasoned basis under the reopening and/or the
    admissibility standards for each, which we do not disturb.
    First,     Massachusetts    asserted   that   operators    at   the
    nuclear power plant at Fukushima were unable to perform mitigation
    actions, which could affect the probability of a radioactive
    release and should be considered in a SAMA analysis.          Most of this
    portion of the contention and expert report focused intently upon
    spent fuel storage pools, which, as noted, the Commission had
    referred to the rulemaking process.21
    To   the   extent   the    claim   dealt   with   other   operator
    mitigation issues, the NRC again required Massachusetts to meet its
    record reopening standard.          The NRC found that the reopening
    standard was not met because Massachusetts had not demonstrated
    21
    To the extent the claim deals with environmental impacts
    from spent fuel pools, it failed to meet the admissibility
    standards because it is outside the scope of the proceedings, 
    10 C.F.R. § 2.309
    (f)(1)(iii), for the reasons we described earlier.
    -26-
    sufficiently that a materially different result (in the SAMA
    analysis)    would   have    been      likely      had   the      information    been
    considered    initially.         See    
    10 C.F.R. § 2.326
    (a)(3).        That
    determination is supported by the fact that operator actions not
    involving spent fuel pools were considered in Entergy's license
    renewal application, a fact which Massachusetts did not even
    address in its contention. Further, Massachusetts did not indicate
    how those already stated analyses would be affected by the proposed
    new information.     The NRC was not arbitrary in concluding that the
    Commonwealth's    mere    pointing       to    a   piece     of    information     and
    speculating that the results of the SAMA analysis may be different
    was   not    sufficient     to   meet        the   requirement      of   
    10 C.F.R. § 2.326
    (a)(3).
    Second, Massachusetts argues "the NRC's excessive secrecy
    regarding accident mitigation measures and the phenomena associated
    with spent-fuel-pool fires degrades the licensee's capability to
    mitigate an accident." Dr. Thompson's report explains that secrecy
    could result in managers and operators not having a thorough
    understanding of the measures they are to implement.                          The NRC
    permissibly decided this portion of the contention failed to
    satisfy the general admissibility standards because it fell outside
    the scope of the proceeding, 
    id.
     § 2.309(f)(1)(iii), stating that
    the "concerns appear to be directed more generally at policy issues
    governing access and categorization of non-public information."
    -27-
    Third, relying on its earlier assertion that Fukushima
    presents new and significant information about the likelihood of
    spent fuel pool accidents, Massachusetts's expert asserted that a
    new SAMA analysis should consider low-density, open-frame storage
    racks.    The NRC properly determined this claim failed to satisfy
    the general admissibility standards because it fell outside the
    scope of the proceeding, id. § 2.309(f)(1)(iii), in light of its
    denial of the waiver petition and the referral of the rulemaking
    petition to its staff.
    Fourth,    Massachusetts       argues   new   information     about
    hydrogen explosions during reactor accidents could alter the SAMA
    analysis.      Dr. Thompson's report contends that "the potential for
    such explosions has not been adequately considered in the Pilgrim
    license extension proceeding," and that "containment venting and
    other hydrogen control systems at the Pilgrim plant should be
    upgraded, and should use passive mechanisms as much as possible."
    The NRC rejected this claim on two grounds: (1) under the
    record reopening standard, Massachusetts had not shown a likelihood
    of   a   materially    different     result   had   the    hydrogen     control
    information been considered initially, id. § 2.326(a)(3); and (2)
    whether   or    not   the   record   was    reopened,     under   the   general
    admissibility standards, Massachusetts did not raise a genuine
    dispute with the existing SAMA analysis, id. § 2.309(f)(1)(vi).
    For present purposes, we deal only with the second, more merits-
    -28-
    based ground for rejection, and find it permissible.                In fact,
    neither Massachusetts's     contention     nor    Dr.   Thompson's reports
    addressed the consideration of hydrogen explosions present in the
    existing SAMA analysis.     The analysis examined "the potential loss
    of containment integrity," including as a result of "hydrogen
    deflagration or detonation." Massachusetts did not even attempt to
    explain how the extant analysis was inadequate or how the new
    information would alter it, and failed to raise a genuine dispute.
    Finally,   Massachusetts      raised    a    claim    relating   to
    filtered   venting    of    reactor      containment.           Specifically,
    Massachusetts stated "it appears likely that filtered venting . . .
    could substantially reduce the atmospheric release of radioactive
    material from an accident at the Pilgrim [nuclear power plant]."
    Its expert therefore recommended that filtered vents should be
    considered in a new SAMA analysis.
    The claim that the EIS was inadequate for these reasons
    was   rejected   on   two   grounds:     (1)   Massachusetts      failed    to
    demonstrate the likelihood of a materially different result under
    the reopening standards, 
    10 C.F.R. § 2.326
    (a)(3); and (2) in any
    event, to the extent that Massachusetts would require filtered
    vents, the general admissibility standards were not met because it
    was outside the scope of the proceeding, 
    id.
     § 2.309(f)(1)(iii).
    The first ground (record reopening) is supported by the fact that
    Massachusetts did not discuss the costs and benefits of adding
    -29-
    filters, which is fatal to its claim because a SAMA analysis is a
    cost-benefit analysis.       Further, the SAMA analysis did in fact
    consider filtered vents, finding that the cost was three times
    greater than the projected benefit. Massachusetts's contention and
    supporting     materials   did   not    acknowledge    or   challenge   that
    analysis. The NRC also permissibly rejected the claim, through its
    admissibility standards, as outside the scope of the proceeding,
    because the claim was not that the consideration was inadequate,
    but that filtered vents were mandated.        That is clearly beyond the
    scope.   See Robertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    ,   350   (1989)   (stating   NEPA    "does   not   mandate   particular
    results").
    In sum, the NRC's decision to reject the contention as to
    each issue raised was not arbitrary or capricious and constituted
    reasoned decisionmaking. See Allentown Mack Sales & Serv., Inc. v.
    NLRB, 
    522 U.S. 359
    , 374 (1998) (agency adjudications must be
    reasoned decisionmaking).
    Although whether the NRC complied with NEPA's "hard look"
    requirement is a separate and independent question, the process and
    reasoning provided by the NRC, discussed above, demonstrates that
    the "hard look" requirement was plainly met: information proffered
    by Massachusetts was considered before the ASLB and NRC, the agency
    obtained opinions from the NRC staff, and from experts outside the
    agency, including those of Massachusetts and Entergy. The NRC also
    -30-
    offered a reasoned explanation.                This meets the requirement of
    taking a "hard look" at such information. See, e.g., Hughes River,
    165 F.3d at 288 (listing obtaining opinions from agency's own
    experts, outside experts, giving scientific scrutiny, and offering
    responses to legitimate concerns as evidence of a sufficiently
    "hard look" (citing Marsh, 
    490 U.S. at 378-85
    )).
    Massachusetts fleetingly argues that its rights to a
    hearing under the AEA were somehow violated.               Not so.    The hearing
    right provided in the AEA "does not confer the automatic right of
    intervention upon anyone." Union of Concerned Scientists v. NRC,
    
    920 F.2d 50
    , 55 (D.C. Cir. 1990) (quoting BPI v. Atomic Energy
    Comm'n, 
    502 F.2d 424
    , 428 (D.C. Cir. 1974)) (internal quotation
    marks    omitted).       The      NRC   may    certainly    impose    procedural
    requirements for obtaining a hearing where the statute provides no
    additional guidance, and because the decision that those standards
    were not met was not arbitrary and capricious, as just discussed,
    the AEA claim fails.           See Am. Trucking Ass'ns, Inc. v. United
    States, 
    627 F.2d 1313
    , 1321 (D.C. Cir. 1980) (stating that agencies
    have    wide    discretion   in    establishing     and    applying    rules   for
    hearings).
    IV.
    Rather than argue explicitly about the findings of the
    NRC, as to whether the portions of the contention met the reopening
    and/or the admissibility standards, in rejecting the Commonwealth's
    -31-
    contention, Massachusetts devotes a substantial portion of its
    brief to arguing that the NRC acted arbitrarily and capriciously,
    alleging that: (1) the NRC failed to explain why the Task Force
    Report did not support Massachusetts's claims; and (2) the NRC's
    explanations for denying the contention were somehow inconsistent
    with the fact that the Task Force made recommendations, some of
    which the NRC adopted, based on the events at Fukushima.          We reject
    both arguments.         There is a disconnect in the Commonwealth's
    argument that the NRC ignored its own Task Force's work product,
    which it cited and which it is now implementing and reviewing.
    As a factual matter, the argument is simply wrong.         The
    NRC dealt with the Task Force Report as part of its analysis in
    rejecting     the     Commonwealth's   contention.      First,    the   NRC
    acknowledged that Massachusetts claimed that the ASLB had ignored
    the   Task    Force    Report   in   its    decision.   Second,   the   NRC
    incorporated the Report into its analysis of each issue where
    relevant,22 and found the NRC's reopening and/or admissibility
    requirements were still not met.23
    22
    In reaching its determination that "[a]t bottom,
    Massachusetts has not shown that its contention should be litigated
    in this proceeding because it has failed to demonstrate a
    sufficiently supported link between the Fukushima Dai-ichi events
    and the Pilgrim environmental analysis," the NRC cited to Dr.
    Thompson's supplemental declaration on the Task Force Report at
    least seven times.
    23
    To the extent Massachusetts's complaint is not the merits
    of the rejection, but that the NRC did not explicitly explain why
    it issued certain orders based on the Task Force Report while not
    -32-
    The NRC also stated that its review of the Fukushima
    event is ongoing and that all plants will be required to comply
    with NRC directions resulting from that review.   At the time of its
    decision, however, the NRC said the Commonwealth had not presented
    sufficient information from the Fukushima incident to make a
    significant difference in Pilgrim's environmental review.
    The Task Force Report did not make environmental-impact
    estimates, assess the implementation costs of its recommendations,
    or engage in any PRA, as even Massachusetts's own expert admitted.
    It used direct mechanisms under the AEA to address safety and did
    not reveal the type of information used in a NEPA analysis.
    "The basic thrust of the agency's responsibilities under
    NEPA is to predict the environmental effects of a proposed action,"
    Am. Bird Conservancy, Inc. v. FCC, 
    516 F.3d 1027
    , 1033 (D.C. Cir.
    2008) (emphasis added), and NEPA does not require substantive
    outcomes.   The Task Force Report is not in conflict with the NRC's
    decision not to supplement the EIS in the Pilgrim relicensing.24
    updating the environmental analysis, Massachusetts never raised the
    issue before the NRC and cannot raise it newly here.       Further,
    there is no representation from the Commonwealth as to why this
    would lead to any different conclusions.
    24
    Three Commission orders were issued in response to the Task
    Force recommendations. Two orders, one on mitigation strategies
    for beyond-design-basis external events and one on hardened vents,
    were issued as "adequate protection" requirements under the AEA and
    were issued without plant-specific PRAs or cost-benefit analyses,
    which are normally part of a SAMA analysis. See Entergy Nuclear
    Generation Co., CLI-12-15, slip op. at 4-5 & n.11 (June 7, 2012);
    see also 
    10 C.F.R. § 50.109
    (a)(4)(ii) (no backfit analysis required
    -33-
    At heart, Massachusetts's argument is simply a variant of
    the argument that the NRC should not have reached the licensing
    question, but should have deferred until more information could be
    collected or obtained to create a more complete picture.               The
    argument fails.
    V.
    We are still left with the question of whether the NRC
    lawfully acted within its discretion when it denied Massachusetts's
    request to suspend license renewal proceedings pending resolution
    of the Commonwealth's petition for rulemaking.            As to the spent
    fuel pool issue, the rulemaking petition asks the NRC to rescind
    its regulations that this is a Category 1 issue that need not be
    addressed   on   a   site-specific    basis   in   an   EIS.   
    10 C.F.R. § 51.71
    (d).      The NRC referred the rulemaking petition to the
    Commission's staff, but denied the accompanying suspension request.
    The NRC contends that Massachusetts failed to preserve
    its challenge to the denial of the suspension request.                 The
    Commonwealth may well have failed to preserve the issue, but we
    choose to rely on the alternate merits ground.
    for action necessary to ensure adequate protection). The third
    order, requiring reliable spent fuel pool instrumentation, was
    exempted from a cost-benefit analysis. Nothing in the orders calls
    into question the accuracy of the EIS.
    -34-
    A.           The NRC's Application of its Suspension of Relicensing
    Test
    The NRC did not act arbitrarily or capriciously in its
    application of its suspension standard.               In Private Fuel Storage,
    LLC, 
    54 N.R.C. 376
     (2001), the NRC said that, in deciding whether
    to suspend licensing proceedings, it will consider whether moving
    forward would (1) "jeopardize the public health and safety," (2)
    "prove an obstacle to fair and efficient decisionmaking," or (3)
    "prevent appropriate implementation of any pertinent rule or policy
    changes that might emerge from [the Commission's] important ongoing
    evaluation of []related policies."              
    Id. at 380
    .       Here, the NRC
    reasonably weighed each of the Private Fuel Storage factors and
    concluded    that,   on    balance,    suspension      of   the   Pilgrim   plant
    proceedings was not warranted.           Massachusetts does not challenge
    the NRC's determination that the Private Fuel Storage factors favor
    the denial of the Commonwealth's suspension request.
    The NRC concluded that moving forward with the Pilgrim
    license renewal proceedings would not jeopardize the public health
    or safety, and the Commonwealth has presented no basis to say this
    was not a reasonable conclusion.           To be clear, this issue is not
    about whether Pilgrim would continue to operate in the interim
    under NRC rules.        It would.   See 
    10 C.F.R. § 2.109
    (b).
    Further, the AEA explicitly authorizes the NRC to modify
    or revoke a license after it is granted if "conditions revealed
    by   .   .    .   any     report,     record,    or     inspection    or    other
    -35-
    means . . . would warrant the Commission to refuse to grant a
    license on an original application."              
    42 U.S.C. § 2236
    (a).25      This
    provision "reflects a deliberate policy choice on the part of
    Congress . . .      to render licenses for nuclear facilities subject
    to postlicensing review under evolving licensing standards."                    Ft.
    Pierce Utils. Auth. v. United States, 
    606 F.2d 986
    , 996 (D.C. Cir.
    1979).
    The    NRC    has   represented       that   it   fully   intends   to
    undertake    post-licensing       review     of    environmental      and    safety
    conditions    at    the    Pilgrim   plant     where     such   review      becomes
    warranted. The relicensing of Pilgrim does not mean the plant will
    not receive the benefit of the lessons learned from Fukushima. The
    NRC has stated that "[a]ll affected nuclear plants ultimately will
    be required to comply with NRC direction resulting from lessons
    learned from the Fukushima accident, regardless of the timing of
    issuance of the affected licenses."
    Moreover, if it should occur that the NRC adopts more
    stringent licensing standards going forward and does not apply
    those standards to Pilgrim, then the Commonwealth can request that
    the NRC initiate proceedings to determine whether the Pilgrim plant
    license would have been granted under the new criteria.                     See 10
    25
    See also 
    42 U.S.C. § 2237
     (statutory authority to modify
    licenses); 
    10 C.F.R. §§ 2.202
    , 2.206 (implementing regulations).
    -36-
    C.F.R. § 2.206(a).26        And, if that request is denied, Massachusetts
    can petition to the court of appeals, see Fla. Power & Light Co. v.
    Lorion, 
    470 U.S. 729
    , 741 (1985), where there is judicial review
    to   ensure    that   the    Commission    has   not   "default[ed]   on   its
    fundamental      responsibility     to    protect   the   public   safety."
    Massachusetts v. NRC, 
    878 F.2d 1516
    , 1522 (1st Cir. 1989); see also
    Mass. Pub. Interest Research Grp. v. NRC, 
    852 F.2d 9
    , 19 (1st Cir.
    1988).
    B.            NEPA Did Not Require Suspension of License Renewal
    Massachusetts, nonetheless, makes the novel claim that
    under NEPA, the Commission must, as a matter of law, complete its
    review of the lessons learned from Fukushima before it renews the
    Pilgrim plant license, but does not cite any pertinent authority.
    We have already determined that the NRC met its obligation under
    NEPA to take a "hard look" at the environmental consequences of the
    Pilgrim plant license renewal; the Commission is, of course, free
    26
    When a person requests that the NRC initiate proceedings to
    modify or revoke a license, the director of the relevant NRC office
    must determine "[w]ithin a reasonable time" whether the request
    will be honored and, if not, must state the reasons for his or her
    decision in writing. 
    10 C.F.R. § 2.206
    (b). In other words, the
    NRC's own regulations state that any challenge to the Pilgrim plant
    license based on information gleaned from the rulemaking process
    will be considered promptly by the Commission's staff, and the
    Commission has provided a procedural mechanism "to allow interested
    parties to prevent agency reliance on previous determinations when
    new information or other pertinent concerns demand special
    consideration." Nuclear Info. Res. Serv. v. NRC, 
    969 F.2d 1169
    ,
    1178 (D.C. Cir. 1992) (en banc).
    -37-
    to take a harder look at the spent fuel pool issue and other
    generic issues through the rulemaking process.
    Massachusetts's premise, that the NRC must wait for even
    more information to become available before the license can be
    renewed, finds no support.      Massachusetts relies particularly on
    its reading of two Supreme Court decisions:               Baltimore Gas &
    Electric Co., 
    462 U.S. 87
    , and Robertson, 
    490 U.S. 332
    .           Both are
    inapposite.
    Baltimore Gas & Electric says nothing about the need to
    delay licensing when currently unavailable information might come
    to light in the future.      Rather, it upheld an NRC rule directing
    licensing boards to assume for purposes of NEPA that permanent
    storage of certain nuclear waste at plant sites would have no
    significant environmental impact and that the risk of leakage need
    not be considered in individual licensing proceedings. 
    462 U.S. at 89-90, 93-95
    .
    Massachusetts cites Robertson for the proposition that an
    agency must consider potential environmental impacts before taking
    a major federal action to "ensure[] that important effects will not
    be   overlooked   or   underestimated    only   to   be   discovered   after
    resources have been committed or the die otherwise cast." 490 U.S.
    at 349.   But that general language about the purpose of NEPA and
    the need to consider environmental impacts imposes no requirement
    on the NRC to hold off on taking action where information is either
    -38-
    unavailable or insufficient to change an existing environmental
    analysis.27
    To the contrary, in Town of Winthrop, 
    535 F.3d 1
    , we
    found that it was reasonable for an agency to decline to study, in
    a supplemental EIS, a pollutant for which there was not yet a
    standard method of measurement or analysis.      
    Id. at 13
    .   It is
    similarly reasonable not to delay relicensing until even more
    information becomes available because the process could otherwise
    become unending, as new information is always developing.       Cf.
    Marsh, 
    490 U.S. at 373
     (explaining that requiring an updated EIS
    every time new information arises is not practical because agencies
    would always be "awaiting updated information only to find the new
    information outdated by the time a decision is made").
    NEPA imposed no obligation on the NRC to withhold the
    granting of a renewed license here because of the possibility that
    currently unavailable information might become available in the
    future.
    VI.
    The petitions for review are denied.
    27
    To the extent Massachusetts seeks to impose a substantive
    requirement that the NRC must require certain mitigation measures
    under NEPA, that is foreclosed by the fact that NEPA is not outcome
    driven. Robertson, 
    490 U.S. at 353
     ("[I]t would be inconsistent
    with NEPA's reliance on procedural mechanisms -- as opposed to
    substantive, result-based standards -- to demand the presence of a
    fully developed plan that will mitigate environmental harm before
    an agency can act.").
    -39-
    

Document Info

Docket Number: 12-1404, 12-1772

Citation Numbers: 708 F.3d 63

Judges: DiCLERICO, Lynch, Torruella

Filed Date: 2/25/2013

Precedential Status: Precedential

Modified Date: 8/6/2023

Authorities (26)

Associated Fisheries v. US Secretary of , 127 F.3d 104 ( 1997 )

Town of Winthrop v. FAA , 535 F.3d 1 ( 2008 )

Massachusetts v. United States , 522 F.3d 115 ( 2008 )

Roland C. Dubois and Restore: The North Woods v. United ... , 102 F.3d 1273 ( 1996 )

Commonwealth of Massachusetts v. United States Nuclear ... , 878 F.2d 1516 ( 1989 )

Citizens Awareness Network, Inc. v. United States , 391 F.3d 338 ( 2004 )

American Bird Conservancy, Inc. v. FCC , 516 F.3d 1027 ( 2008 )

Bpi and James T. Nodland v. The Atomic Energy Commission ... , 502 F.2d 424 ( 1974 )

paul-siegel-v-atomic-energy-commission-and-united-states-of-america , 400 F.2d 778 ( 1968 )

Joseph W. Johnston v. Nuclear Regulatory Commission of the ... , 766 F.2d 1182 ( 1985 )

State of Wisconsin, and County of Marquette, Michigan, ... , 745 F.2d 412 ( 1984 )

nuclear-information-resource-service-v-nuclear-regulatory-commission-and , 969 F.2d 1169 ( 1992 )

New Jersey Environmental Federation v. United States ... , 645 F.3d 220 ( 2011 )

massachusetts-public-interest-research-group-inc-v-united-states-nuclear , 852 F.2d 9 ( 1988 )

union-of-concerned-scientists-v-united-states-nuclear-regulatory , 920 F.2d 50 ( 1990 )

Oystershell Alliance v. United States Nuclear Regulatory ... , 800 F.2d 1201 ( 1986 )

american-trucking-associations-inc-v-united-states-of-america-and , 627 F.2d 1313 ( 1980 )

ft-pierce-utilities-authority-of-the-city-of-ft-pierce-v-united-states , 606 F.2d 986 ( 1979 )

Allentown MacK Sales & Service, Inc. v. National Labor ... , 118 S. Ct. 818 ( 1998 )

Weinberger v. Catholic Action of Hawaii/Peace Education ... , 102 S. Ct. 197 ( 1981 )

View All Authorities »