PRASA v. Constructory Lluch ( 1999 )


Menu:
  •              United States Court of Appeals
    For the First Circuit
    No. 98-1331
    PUERTO RICO AQUEDUCT AND SEWER AUTHORITY,
    Plaintiff, Appellant,
    v.
    CONSTRUCTORA LLUCH, INC., AND CNA CASUALTY
    OF PUERTO RICO, INC.,
    Defendants, Appellees.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF PUERTO RICO
    [Hon. Hctor M. Laffitte, U.S. District Judge]
    Before
    Torruella, Chief Judge,
    Hall, Senior Circuit Judge,
    and Lipez, Circuit Judge.
    Carlos A. Rodrguez-Vidal, with whom Goldman Antonetti &
    Crdova was on brief, for appellant.
    Jos M. Biaggi-Junquera, with whom Jos Enrique Otero was on
    joint brief, for appellees.
    February 18, 1999
    TORRUELLA, Chief Judge.  Before the Court is plaintiff-
    appellant Puerto Rico Aqueduct and Sewer Authority's ("PRASA")
    appeal from the district court's denial of PRASA's motion for a
    second partial new trial on damages.  At the first partial new
    trial, the jury awarded PRASA no damages despite an earlier verdict
    finding defendant-appellee Constructora Lluch, Inc. ("Lluch") to be
    negligent and in breach of the construction contract between the
    two.  PRASA also appeals from a jury award on Lluch's counterclaims
    against PRASA for breach of contract and for amounts owed on the
    contract.  For the reasons stated in this opinion, we affirm the
    judgment awarding Lluch $756,471.59 on its counterclaims, but
    vacate the judgment awarding PRASA no damages on its claims and
    remand for a second partial new trial on the issue of damages.
    BACKGROUND
    This case arises out of the collapse, during
    construction, of the steel roof structure of the Mayaguez
    Composting Facility in October of 1989.  PRASA entertained bids for
    the project and eventually awarded the project's design to Lebrn
    Associates, an engineering and architecture firm.  In May of 1988,
    PRASA entered into a construction contract with Lluch to build the
    facility.  Several months later, Lluch subcontracted with Richmond
    Steel, Inc. ("RSI") to manufacture and install the facility's steel
    components, including the roof.
    The Mayaguez facility was to be a compost treatment plant
    comprised of a main building to deposit and treat compost and a
    separate administrative building.  The main building was designed
    as two adjacent bays with three lines of columns to support two
    separate steel frame roofs.   Among the plans and specifications
    developed by Lebrn was a procedure to be followed for the
    preparation and consolidation of the soil.  Under the procedure,
    Lluch was required: (1) to place a permanent landfill on the site;
    (2) to install wicks and pertinent instrumentation; (3) to place a
    surcharge on the site; and (4) to leave the surcharge undisturbed
    for a period of seven and a half months.  However, before the
    consolidation of the soil was completed, Lluch removed the
    surcharge from the soil in order to begin the concrete construction
    and in order to allow RSI to begin the steel erection.
    On October 22, 1989, after RSI had erected a substantial
    part of the east portion of the steel roof structure, the
    uncompleted west portion of the steel roof structure collapsed.
    After the collapse, Lluch removed the collapsed steel frames and
    debris, began to repair the damaged columns, and continued with
    construction of the remaining phases of the project, all with
    PRASA's authorization and under PRASA's supervision.  After Lluch
    had substantially completed the construction of the project -- with
    the exception of the steel roof structure -- PRASA demolished the
    entire project, over Lluch's objection.
    On October 10, 1990, this action was filed in United
    States District Court for the District of Puerto Rico by RSI,
    seeking monetary and declaratory relief against PRASA, Lluch,
    Lebrn, and their bonding and surety companies.  Several
    counterclaims, cross-claims, and third-party claims followed, most
    of which were dismissed before trial.  Included in those rulings,
    the district court dismissed PRASA's cross-claim under Article 1483
    of the Puerto Rico Civil Code against Lluch and RSI.  See Richmond
    Steel, Inc. v. Legal and Gen. Assurance Soc'y, Ltd., 
    825 F. Supp. 443
    , 445 (D.P.R. 1993).
    At the first trial in 1993, some of the parties entered
    into various stipulations, including the dismissal of original
    plaintiff RSI.  The district court then realigned the parties to
    continue the trial.  As a result, PRASA became the plaintiff, and
    Lluch, Lebrn, and CNA Casualty of Puerto Rico, Inc. ("CNA")
    remained as defendants.  On August 9, 1993, after a twenty-four day
    trial, the jury, in a special verdict form, found: (1) that Lluch
    improperly removed the surcharge from the construction site or in
    some other way breached its contract with PRASA by negligent
    construction work; (2) that this breach caused the collapse of the
    roof structure; (3) that this breach caused damages to PRASA; (4)
    that PRASA's demolition of the remains of the structure was
    unjustified; and (5) that PRASA suffered $4,587,202.77 in damages
    as a result of Lluch's breach.  With regard to the counterclaims
    against PRASA, the jury found: (1) that PRASA breached its contract
    with Lluch; (2) that this breach caused damages to Lluch in the
    amount of $138,758; (3) that PRASA owed Lluch $617,713.59 for work
    performed on the contract; and (4) that PRASA owed Lebrn
    $40,148.28 on the contract.  As a result of these findings, the
    jury awarded: (1) $4,587,202.77 to PRASA for Lluch's negligence and
    breach of contract; (2) $756,471.59 to Lluch on its counterclaims
    against PRASA for breach of contract and money owed on the
    contract; and (3) $40,148.28 to Lebrn on its counterclaim against
    PRASA for money owed on the contract.
    On October 15, 1993, the district court issued a judgment
    consistent with the damages awarded by the jury.  In an order
    issued the same day, the district court advised counsel that all
    post-trial motions were required to be filed or renewed within 10
    days of the date of the judgment.  On October 21, 1993, CNA and
    Lluch filed a timely motion for a new trial on PRASA's claims.  On
    November 4, 1993 -- twenty days after the entry of judgment --
    PRASA filed a motion for judgment as a matter of law with regard to
    Lluch's counterclaims.
    On July 27, 1994, the court granted CNA and Lluch's
    motion for a new trial, subject to PRASA's acceptance of a
    remittitur.  The court concluded that the jury award was excessive
    in light of the evidence presented.  The court then gave PRASA the
    option of accepting a remitted award of $1,224,000 or a partial new
    trial on damages.  PRASA opted for a new trial.
    On March 24, 1995, the court denied PRASA's motion for
    judgment as a matter of law on Lluch's counterclaims.  The court
    found that the evidence was sufficient to allow a reasonable jury
    to reach a verdict in favor of Lluch on those claims.
    On February 7, 1996, the court set the scope of the
    partial new trial on damages for PRASA's claims.  The court held
    that the new trial would be limited only to the extent of PRASA's
    damages at the time of the collapse.  The court concluded that,
    because the jury in the first trial found that PRASA was
    unjustified in demolishing the structure, damages would be limited
    to the cost to repair the collapse as of October 22, 1989, the date
    of the collapse.
    At the partial new trial, PRASA presented evidence that
    the soil conditions at the site were unstable and were experiencing
    settlement beyond what was expected.  PRASA's experts testified
    that the soil had to be improved in order to repair the collapse,
    either through placing a new surcharge on the site or by installing
    piles to support the structure.  PRASA's experts testified that
    only the option of installing piles was feasible, but that it would
    cost in excess of $6 million to do.  Lluch and CNA presented
    testimony that the soil did not have to be improved to repair the
    collapse and that it would have cost approximately $500,000 to
    repair the damage.  Lluch and CNA also presented testimony that
    Lluch intended to absorb the costs of repair and that PRASA was
    never going to be charged for those costs.
    The court instructed the jury: (1) that PRASA was
    entitled to claim the extent of any damages it suffered at the time
    of the collapse on October 22, 1989; and (2) that those damages
    were limited to the cost to repair the collapse.  The court also
    instructed the jury to accept as established facts: (1) that Lluch
    improperly removed the surcharge or breached its contract in some
    other way by negligent construction; (2) that this breach or
    negligence caused the collapse; and (3) that PRASA's subsequent
    demolition of the structure was unjustified.  The court informed
    the jury that if PRASA failed to establish the amount of damages
    caused by Lluch, then PRASA was not entitled to collect any
    damages.  The court then submitted a verdict form to the jury that
    asked whether PRASA suffered any damages, and if so, the amount of
    those damages.
    On July 15, 1997, the jury returned the verdict form
    indicating that it found that PRASA suffered no damages.  Judgment
    was entered the next day, ordering that PRASA take nothing from
    Lluch and CNA.
    On August 1, 1997, PRASA filed a motion for a second
    partial new trial on the issue of damages or for reinstatement of
    the 1993 verdict.  On December 11, 1997, the court entered an
    Opinion and Order denying PRASA's motion.  On December 22, 1997,
    PRASA filed a motion to alter or amend the December 11, 1997
    Opinion and Order.  On January 22, 1998, the court denied PRASA's
    motion to alter or amend by Endorsed Order.  The Court photocopied
    the motion, wrote "Denied" in the margin of the photocopy, and
    referred the parties to the December 11, 1997 Opinion and Order.
    On January 27, 1998, PRASA filed a notice of appeal from the
    July 16, 1997 judgment, the December 11, 1997 Opinion and Order,
    and the January 22, 1998 Endorsed Order.
    DISCUSSION
    I.  Jurisdiction
    Before we reach the merits, we must first address
    appellees' contention that we lack jurisdiction over PRASA's
    appeal.  The docket reflects the following chain of relevant
    events:
    July 16, 1997 - The district court entered judgment
    awarding no damages to PRASA;
    August 1, 1997 - PRASA filed a Rule 59(b) motion for a
    second partial new trial on damages or for
    reinstatement of the prior verdict;
    December 11, 1997 - The district court entered an
    Opinion and Order denying PRASA's motion for a second
    partial new trial on damages;
    December 22, 1997 - PRASA filed a motion to alter or
    amend the December 11, 1997 Opinion and Order;
    January 22, 1998 - The district court denied PRASA's
    motion to alter or amend by entering an Endorsed Order.
    The Endorsed Order consisted of a photocopy of PRASA's
    motion to alter or amend, with a notation in the margin
    signed by the district judge.  The notation stated:
    "Denied.  See docket no. 624  ."  Docket No. 624 is the
    court's December 11, 1997 Opinion and Order;
    January 27, 1998 - PRASA filed its notice of appeal
    from the July 16, 1997 judgment, the December 11, 1997
    Opinion and Order, and the January 22, 1998 Endorsed
    Order.
    Appellees argue that appellate jurisdiction is lacking
    because PRASA's December 22, 1997 motion to alter or amend the
    December 11, 1997 Opinion and Order did not toll the time to appeal
    the judgment or the Opinion and Order.  Federal Rule of Appellate
    Procedure 4(a)(4)(C) provides that the filing of a motion to alter
    or amend the judgment under Federal Rule of Civil Procedure 59(e)
    tolls the time for appeal until the district court issues an order
    disposing of the motion.  Appellees claim that PRASA's motion is
    not really a motion to alter or amend the December 11, 1997 Opinion
    and Order because it requested the same relief sought by the motion
    for a second partial new trial, and did so on the same grounds.
    Appellees argue that PRASA's motion to alter or amend is really a
    motion to reconsider the July 16, 1997 judgment.  Appellees point
    out that the motion to alter or amend is, in some places, an exact
    verbatim copy of the motion for a new trial.  Appellees further
    claim that even the non-verbatim portions merely recast the
    arguments of the motion for a new trial with the addition of
    quotations from the trial transcript.
    Appellees correctly note that the filing of a motion to
    reconsider will only toll the time for appeal if the motion is
    filed no later than ten days after the entry of the judgment from
    which reconsideration is sought.  See Fed. R. App. P. 4(a)(4)(F).
    Appellees claim that since PRASA's December 22, 1997 motion is
    really a motion to reconsider the July 16, 1997 judgment, it needed
    to be filed within ten days of July 16, 1997 to have any effect on
    the time to appeal.  In support of this position, appellees cite
    Acevedo-Villalobos v. Hernndez, 
    22 F.3d 384
     (1st Cir.), cert.
    denied, 
    513 U.S. 1015
     (1994).  In Acevedo-Villalobos, the Court was
    faced with a situation in which the district court entered a
    judgment of dismissal and the plaintiffs filed one post-judgment
    motion within 10 days of the judgment and another post-judgment
    motion more than 10 days from the entry of judgment.  See id. at
    389-90.  Even though the second motion purported to request
    reconsideration of the denial of the first motion, the Court found
    that the second motion was "an obvious attempt to have the district
    court revisit the legal basis for" the original judgment of
    dismissal.  Id. at 390.  The Court noted that the second motion
    requested the same relief that the first motion requested, and did
    so on the same grounds.  See id.  Therefore, the Court treated the
    second motion as a motion to reconsider the original judgment of
    dismissal.  See id.  Because the second motion was untimely as such
    a motion to reconsider, the Court found: (1) that it did not extend
    the tolling of the time to appeal the original judgment of
    dismissal; and (2) that it did not toll the time to appeal the
    denial of the first post-judgment motion.  See id.
    Appellees argue that the same result should follow in the
    present case because the December 22, 1997 motion is really a
    motion to reconsider the July 16, 1997 judgment and because the
    motion was filed over five months after the July 16, 1997 judgment.
    From this, appellees argue: (1) that the time to appeal the
    July 16, 1997 judgment was tolled only by the filing of the Rule
    59(b) motion for a second partial new trial and therefore expired
    on January 11, 1998; (2) that the time to appeal the December 11,
    1997 Opinion and Order was never tolled and also expired on
    January 11, 1998; and (3) that there was no time to appeal the
    January 22, 1998 Order, because the untimeliness of the motion to
    reconsider deprived the district court of jurisdiction to decide
    it.
    We cannot accept appellees' contentions.  We are faced
    with a different situation than that presented in Acevedo-
    Villalobos.  In that case, the Court found that the tolling
    terminated with the denial of the first post-judgment motion.  SeeAcevedo-Villalobos, 
    22 F.3d at 390
    .  In the present case, however,
    the December 11, 1997 Opinion and Order -- the order denying
    PRASA's first post-judgment motion -- did not stop the tolling of
    the time to appeal the July 16, 1997 judgment because, as discussed
    below, it was not a "final judgment" in compliance with the
    "separate document" rule of Federal Rule of Civil Procedure 58.
    Federal Rule of Appellate Procedure 4(a)(4) provides that
    the tolling commenced by the filing of a proper post-judgment
    motion continues until "the entry of the order disposing of the
    last such motion outstanding."  Fed. R. App. P. 4(a)(4).
    Subsection (a)(7) states that "a judgment or order is entered
    within the meaning of this Rule 4(a) when it is entered in
    compliance with Rules 58 and 79(a) of the Federal Rules of Civil
    Procedure."  Fed. R. App. P. 4(a)(7).  Therefore, in order to halt
    the tolling of the time to appeal, an order denying a tolling post-
    judgment motion must comply with Rule 58.  See also Kersey v.
    Dennison Mfg. Co., 
    3 F.3d 482
    , 484-85 (1st Cir. 1993) (finding that
    the tolling of the time to appeal from a certified judgment never
    stopped because, even though the district court "announced" its
    denial of a tolling post-judgment Rule 59(e) motion in an order, it
    never issued a separate document); Fiore v. Washington Cty. Com.
    Mental Health Ctr., 
    960 F.2d 229
    , 233 (1st Cir. 1992)(en
    banc)(noting Rules 4(a)(4) and 4(a)(7) and stating that those
    subsections expressly impose Rule 58's separate document
    requirement on denials of post-judgment motions that toll the time
    for appeal).  Because we find below that the December 11, 1997
    Opinion and Order did not comply with Rule 58, we find that it did
    not stop the tolling of the time to appeal the July 16, 1997
    judgment.
    Rule 58 states that "[e]very judgment shall be set forth
    on a separate document" and that "[a] judgment is only effective
    when so set forth."  Fed. R. Civ. P. 58.  In Fiore v. Washington
    Cty. Com. Mental Health Ctr., this Court held that Rule 58 shall be
    applied to all final orders denying and granting post-judgment
    motions under Rules 50(b), 59(b), 59(e), and 60(b).  See Fiore, 
    960 F.2d at 232-33
    ; see also Credit Francais Int'l, S.A. v. Bio-Vita,
    Ltd., 
    78 F.3d 698
    , 704 n.12 (1st Cir. 1996) ("[T]he 'separate
    document' rule does apply to orders denying Rule 59(e) motions.").
    In doing so, the Fiore Court concluded that "technical compliance
    with the [separate document requirement] is as necessary in the
    post-judgment context as it is in disposing of the merits."  Fiore,
    
    960 F.2d at 235
    .  Because PRASA's motion for a second partial new
    trial was a Rule 59(b) motion, it fits within Fiore's "uniform
    approach for all orders denying post-judgment motions under Rules
    50(b), 52(b) and 59(b) and (e), as well as under Rule 60(b)."  Id.at 232.  Thus, the Opinion and Order denying PRASA's motion for a
    second partial new trial must comply with Rule 58.
    The December 11, 1997 Opinion and Order was a five-page
    opinion which considered PRASA's motion for a second partial new
    trial.  In the Opinion and Order, the district court addressed and
    rejected each of PRASA's arguments in turn, using explanatory
    language to give its reason for each rejection.  The Opinion and
    Order concluded with the following statements: "Accordingly, the
    Court hereby denies the motion for a new trial.  IT IS SO ORDERED."
    Appellees argue that the Opinion and Order, by itself,
    was a separate document, as contemplated by Rule 58.  Appellees
    claim that the Opinion and Order was originated by the district
    court as a separate piece of paper and that the Opinion and Order
    discussed the merits of PRASA's motion for a new trial.  Appellees
    further claim that there was no margin for confusion or uncertainty
    as to the finality of the order.  Appellees cite Hollywood v. City
    of Santa Mara, 
    886 F.2d 1228
    , 1231 (9th Cir. 1989), for its
    holding that a separate document was not required to accompany a
    nine-page order denying a Rule 59 motion for a new trial.  In that
    case, the Ninth Circuit noted that it had previously held that
    compliance with Rule 58 "requires entry of a document distinct from
    any opinion or memorandum."  
    Id.
     at 1231 (citing Allah v. Superior
    Court, 
    871 F.2d 887
    , 890 (9th Cir. 1989); Vernon v. Heckler, 
    811 F.2d 1274
    , 1276 (9th Cir. 1987)).  The Hollywood court then refused
    to extend this rule to the context of orders denying Rule 59
    motions.  See 
    id.
      The court found that the risk of confusion
    regarding finality does not exist in the context of denials of Rule
    59 motions for a new trial.  See id. at 1232.  The court held that
    the order denying the Rule 59 motion "definitively signaled the end
    of the litigation."  Id.
    In relying on Hollywood, appellees make an argument
    directly at odds with this Court's holding in Fiore.  In Fiore, the
    Court held that "technical compliance with the [separate document
    requirement] is as necessary in the post-judgment context as it is
    in disposing of the merits."  Fiore, 
    960 F.2d at 235
    .  The Court
    recognized that the uncertainty that prompted the separate document
    rule would be less likely to occur with respect to post-judgment
    orders than for initial judgments.  See 
    id. at 234
    .  Nonetheless,
    the Court stated that, because some uncertainty will always exist,
    consistency and clarity would be better achieved by following the
    rules as written than by trying to distinguish one type of judgment
    or order from another.  See 
    id.
      In footnote 9, the Court stated
    that Hollywood was "at odds with our conclusion that post-judgment
    motions should be treated identically with judgments on the
    merits."  
    Id.
     at 235 n.9.  Therefore, appellees' reliance on
    Hollywood is misplaced; we are bound by Fiore's holding that orders
    denying Rule 59(b) motions are subject to the separate document
    requirement of Rule 58.
    Appellees cannot escape the fact that the December 11,
    1997 Opinion and Order was a five-page explanatory opinion denying
    PRASA's motion that was not accompanied by a separate one-line
    judgment.  This does not comply with the separate document
    requirement of Rule 58.  Several courts have found that detailed
    opinions similar to the December 11, 1997 Opinion and Order violate
    the separate document requirement because they were not accompanied
    by a short separate judgment.  See, e.g., Baker v. Mercedes Benz of
    North America, 
    114 F.3d 57
    , 60 (5th Cir. 1997) (holding that Rule
    58 was not satisfied by an extensive written opinion concluding
    with the sentence: "This is a final judgment", because there was no
    separate document judgment); Barber v. Whirlpool Corp., 
    34 F.3d 1268
    , 1275 (4th Cir. 1994)(holding that an eleven-page order
    setting forth findings of fact and conclusions of law and
    dismissing defendant's post-trial motions did not satisfy the
    separate document rule); Clough v. Rush, 
    959 F.2d 182
    , 184-85 (10th
    Cir. 1992) (holding that the absence of a separate document
    rendered an order nonfinal, even though the order granting summary
    judgment was fifteen pages long and contained detailed legal
    reasoning).  We recognize the irony in finding that an Opinion and
    Order is not an effectively final judgment because it contains
    pages of explanatory language and reasoning.  However, this Court's
    concerns for certainty and predictability in Fiore gave rise to a
    uniform rule of technical compliance.  Consequently, we find that
    the December 11, 1997 Opinion and Order did not comply with the
    separate document requirement of Rule 58.  Therefore, the
    December 11, 1997 Opinion and Order did not stop the tolling of the
    time to appeal the July 16, 1997 judgment.
    Even though the December 11, 1997 Opinion and Order was
    not a final judgment in compliance with the separate document
    requirement of Rule 58, we nevertheless have jurisdiction over the
    appeal if the parties are found to have waived the separate
    document requirement.  In Bankers Trust v. Mallis, 
    435 U.S. 381
    ,
    386 (1978), the Supreme Court stated that judicial efficiency
    requires that the parties be able to waive the separate document
    requirement in order to avoid the pointless exercise of dismissing
    the appeal only to have it refiled when the district court enters
    the required separate document.  The Court then went on to find
    waiver in that case because the petitioner (who was the appellee at
    the circuit level) did not object to the taking of the appeal in
    the absence of a separate judgment.  See 
    id. at 387-88
    .  We have
    previously applied this waiver principle "where both parties waive
    the requirement and neither party would be prejudiced or misled by
    the lack of a separate document."  Wang Laboratories, Inc. v.
    Applied Computer Sciences, Inc., 
    926 F.2d 92
    , 96 (1st Cir. 1991);
    see also Smith v. Massachusetts Dep't of Correction, 
    936 F.2d 1390
    ,
    1394 (1st Cir. 1991).  We have also stated that "the separate
    document requirement should always be interpreted to prevent the
    loss of the right to appeal, not to facilitate loss."  Fiore, 
    960 F.2d at 236-37
     (internal quotation marks omitted).
    In the present case, both PRASA and appellees have waived
    the separate document requirement.  PRASA clearly waived the
    requirement when it filed its notice of appeal in the absence of a
    true final judgment.  See 
    id.
     at 236 n.10.  Appellees waived the
    requirement by failing to object at any point to the taking of an
    appeal in the absence of a separate document.  To date, appellees
    have never claimed that no separate document has issued or that
    this appeal may not proceed because no separate document has
    issued.  Appellees moved to dismiss the appeal for lack of
    jurisdiction, but this motion claimed that the January 27, 1998
    notice of appeal was untimely, an argument which is predicated on
    the validity and finality of the December 11, 1997 Opinion and
    Order.  Appellees did not raise the separate document issue in any
    form until the Court denied the motion to dismiss the appeal and
    specifically inquired about compliance with the separate document
    rule.  Appellees' current position is that the Opinion and Order is
    a separate document and therefore the notice of appeal was
    untimely, so appellees do not, even today, object to the taking of
    an appeal in the absence of a separate document.
    Nor does it appear that either PRASA or appellees have
    been prejudiced or misled by the lack of a separate document.
    Appellees apparently did not even suspect that the December 11,
    1997 Opinion and Order was insufficient until the Court's request
    for briefing on the issue.  PRASA was not prejudiced or misled by
    the lack of a separate document because it took steps -- in the
    form of the December 22, 1997 motion to alter or amend and the
    January 27, 1998 notice of appeal -- to ensure that it was not
    sleeping on its appellate rights.  Therefore, under Bankers Trust,
    Smith, and Wang, we find that the parties have waived the separate
    document requirement of Rule 58.  Consequently, we have
    jurisdiction over the present appeal even though the December 11,
    1997 Opinion and Order was not a valid final judgment in compliance
    with Rule 58.
    II. The District Court's Denial of PRASA's Motion For a Second
    Partial New Trial on the Issue of Damages
    PRASA argues that the district court abused its
    discretion in denying PRASA's motion for a second partial new trial
    on the issue of damages.  PRASA argues that a second partial new
    trial should have been granted because: (1) the jury verdict
    awarding no damages was against the demonstrable weight of the
    evidence; (2) the district court erred in allowing the jury to
    redetermine issues already determined by the first jury; and (3)
    appellees' counsel made improper and prejudicial remarks to the
    jury during opening and closing statements.
    The denial of a new trial is reviewed for abuse of
    discretion.  Bogosian v. Mercedes-Benz of North America, Inc., 
    104 F.3d 472
    , 482 (1st Cir. 1997).
    A.       Jury Verdict Against the Weight of the Evidence
    PRASA first argues that the 1997 jury verdict was against
    the weight of the evidence because it was inadequate to compensate
    PRASA for its damages.  A verdict may be set aside and a new trial
    ordered "when the verdict is against the clear weight of the
    evidence, or is based upon evidence which is false, or will result
    in a clear miscarriage of justice."  Phav v. Trueblood, Inc., 
    915 F.2d 764
    , 766 (1st Cir. 1990)(citing Torres-Troche v. Municipality
    of Yauco, 
    873 F.2d 499
     (1st Cir. 1989)).
    PRASA argues that the clear weight of the evidence at the
    partial new trial established that PRASA suffered significant
    damages.  The jury in the first trial found that Lluch had been
    negligent in breaching its contract with PRASA, that Lluch's breach
    caused the collapse of the structure, and that this breach caused
    damages to PRASA.  While the district court set aside the amount of
    damages awarded as excessive, it did not set aside the jury's
    finding of negligence or the jury's finding that this negligence
    caused PRASA damages.  Rather, the district court specifically
    instructed the second jury to accept those two determinations.
    Then, the district court set the parameters for the amount PRASA
    could recover by instructing the second jury that:
    PRASA is entitled to recover an amount which
    will reasonably compensate it for any damages
    it had suffered as a result of Lluch's breach
    of contract or negligence as of the date of
    the collapse on October 22, 1989.
    Specifically, PRASA is entitled to recover the
    cost to repair the collapse.
    PRASA argues that the clear weight of the evidence
    presented at the partial trial showed that it suffered significant
    damages as of the date of the collapse.  PRASA breaks down the cost
    of repair into two components: (1) the cost of preparing the soil
    to support the repaired roof structure; and (2) the cost of
    repairing the roof structure itself.  The first component was
    sought by PRASA as the cost of the stabilization of the soil or the
    installation of piling support at the construction site.  PRASA
    notes that the first jury determined: (1) that Lluch improperly
    removed the surcharge from the soil at the construction site or in
    other ways acted negligently in breaching its contract with PRASA;
    and (2) that Lluch's improper removal caused the collapse of the
    roof structure.  PRASA argues that the cost of repair must include
    the cost of stabilization or piling support because it would be
    futile to attempt to install the roof structure again without first
    improving or supporting the soil.
    In an attempt to prove that the soil at the site must be
    improved or supported before repair of the structure could begin,
    PRASA offered the testimony of Engineers Carlos Ortiz, Angel
    Herrera, and Alan Crumley.  Ortiz testified that he conducted soil
    exploration at the site after the collapse and that he determined
    that the soil had settled nearly 70 cm, almost twice the settlement
    expected when the site was originally analyzed in 1986.  Ortiz also
    detected settlement of the concrete columns on which the new roof
    structure would be installed.  Ortiz concluded that because the
    consolidation and settlement of the soil was ongoing at the time of
    the collapse, the soil needed to be treated in order to build on
    it.  Herrera, an expert in design, construction and estimates of
    costs of repairs of failures or collapses of structures, testified
    that, at the time of the collapse, the soil at the site was notcompetent to support the building as designed. Crumley testified
    that he analyzed the soil in 1995 and found that primary
    settlements were still occurring and were therefore occurring at
    the time of the collapse at a rapid rate.  Crumley opined that
    repairing the collapse in 1989 would have required either improving
    the soil or installing piles.
    The district court apparently agreed with PRASA's
    assertion that the soil had to be improved before the structure
    could be repaired.  Appellees objected to testimony regarding soil
    improvement measures as beyond the scope of the cost of repairing
    the collapse, but the court overruled those objections and stated
    that "to repair he's got to do that."
    PRASA attempted to quantify how much it would cost to
    improve the soil or install piles through Herrera's testimony.
    Herrera first considered the option of surcharging the soil, but
    rejected that alternative because of the uncertainty of the
    settlement.  Therefore, Herrera recommended the second alternative:
    installing piles for support.  Herrera testified that properly
    installing piles for support would require the following steps (and
    costs): (1) removing portions of the floor slab ($82,500); (2)
    installing piles ($3,201,000); (3) raising the existing footings
    ($440,000); (4) installing new footings to connect the piles with
    the existing footings ($423,835); (5) building concrete foundation
    beams ($510,044); and (6) building a new floor slab ($1,220,740).
    Herrera testified that these steps would cost $5,878,119, plus a
    six percent consulting fee, for a total cost of improving the soil
    of $6,230,806.
    The second component of the cost of repair sought by
    PRASA was the repair of the roof structure itself.  PRASA argues
    that the evidence of the cost of reinstalling the collapsed roof
    varied from $470,000 to $2,513,211.48.  PRASA first points to the
    testimony of Lluch's expert, Engineer Rafael Jimnez.  Jimnez
    testified that repairing the roof structure would require repairing
    and installing the steel trusses ($420,000), repairing the concrete
    columns ($21,000), and removing the twisted steel ($70,000), for a
    total of $511,000.  Engineer Edison Lluch also testified for
    defendants regarding the cost to repair the collapse.  Eng. Lluch
    agreed with Jimnez that those three steps needed to be undertaken,
    but disagreed with Jimnez's estimate of cost.  Eng. Lluch
    estimated the steps to cost $421,000, $20,000, and $29,000,
    respectively, for a total of $470,000.
    For the highest estimated cost of repair, PRASA points to
    the cross-examination of Eng. Lluch, during which PRASA claims that
    Eng. Lluch acknowledged that he had written a letter to Seaboard
    Surety Company claiming $2,513,211.48 for repair of the structure.
    In that letter, PRASA claims that Eng. Lluch included estimates on
    how much it would cost: (1) to remove the collapsed structure; (2)
    to replace the damaged steel structure; (3) to install the steel
    structure; and (4) to repair the damage to the concrete columns.
    However, Eng. Lluch also testified that much of the claimed amount
    was not related to the collapse, but was related to the fact that
    Richmond abandoned the project.  PRASA does not itemize the
    $2,513,211.48 claim to explain how much was claimed by Lluch as
    repair for the collapse and how much was claimed because Richmond
    abandoned the project.
    In total, PRASA claims that the jury was presented
    evidence that the soil would cost $6,230,806 to improve and that
    the steel roof structure would cost anywhere from $470,000 to
    $2,513,211.48 to repair. PRASA argues that the jury verdict
    awarding no damages was clearly contrary to the weight of this
    evidence.
    In response, appellees offer two arguments.  First,
    appellees raise the legal argument that PRASA was not legally
    entitled to compensation for the collapse.   Appellees argue that
    Clauses V and VIII of the construction contract provided PRASA with
    a choice of remedies in the event of a breach by Lluch.  Clause V
    provided that if Lluch failed in the performance of the contract,
    PRASA could hire a substitute contractor to complete the work at
    Lluch's expense.  Appellees describe this remedy as the "in natura"
    remedy for breach of contract.  Clause VIII was a penalty clause
    that obligated Lluch to pay PRASA $1,400 for each day that
    completion of the project was delayed due to Lluch's failure to
    fulfill its obligations.
    Appellees argue that Clauses V and VIII, in conjunction,
    provide the only remedies available to PRASA:  specific performance
    or substitute performance, with Lluch paying the liquidated late
    fees or cost overruns.  Appellees cite Article 1106 of the Puerto
    Rico Civil Code for the proposition that, in obligations that
    include a penalty clause, the penalty shall substitute indemnity
    for damages.  See P.R. Laws Ann. tit. 31,  3131.  Appellees also
    cite Rodrguez Cancel v. A.E.E., 
    16 P.R. Offic. Trans. 542
     (1995),
    in support of their argument that, by contracting for the "in
    natura" remedy, the parties precluded the recovery of monetary
    damages.  Appellees argue that, instead of choosing one of those
    remedies, PRASA unjustifiably demolished the entire structure,
    making it impossible for either Lluch or a substitute contractor to
    finish the project.  From this, appellees claim that PRASA opted
    out of both remedies available to it, and therefore is not entitled
    to recover monetary damages now.
    We reject appellees' first argument because it ignores
    the fact that PRASA did not bring its claim solely under a breach
    of contract theory.  Appellees may well be correct that PRASA's
    remedies for a pure breach of contract action are limited to the
    remedies provided in the contract.  However, while the exact nature
    of PRASA's claims is not at all clear from the record, this was not
    a pure breach of contract action.  The district court treated the
    action as a breach of contract action in which the claimed breach
    of contract was Lluch's negligent construction.  The district court
    asked the first jury: "Do you find that Constructora Lluch
    improperly removed the surcharge from the construction site or in
    any other way breached its contract with PRASA by negligent
    construction work?"   Similarly, the district court instructed the
    second jury to accept as an established fact that Lluch "breached
    its contract with PRASA by negligent construction work."  In
    numerous instances, the court used hybrid language that makes it
    clear that it entertained both contract and tort theories and
    remedies in this case, and properly so.  At oral argument,
    appellees agreed with PRASA that, under Ramos v. Orientalist Rattan
    Furniture, Inc., 
    1992 WL 755597
     (Puerto Rico 1992), if a party is
    damaged by acts or omissions that constitute both a breach of
    contract and a breach of duty, the damaged party may make a tort
    claim based on the breach of contract.  Appellees argue that this
    was not the case here, but we disagree.  Lluch's negligence
    breached both the construction contract and its duty not to cause
    damage to others, so PRASA may seek to recover under either a tort
    or contract theory.
    PRASA attempted to recover damages under a negligence
    tort theory.  Article 1054 of the Puerto Rico Civil Code states:
    Those who in fulfilling their obligations are
    guilty of fraud, negligence, or delay and
    those who in any manner whatsoever act in
    contravention of the stipulations of the same
    shall be subject to indemnity for the losses
    and damages caused thereby.
    P.R. Laws Ann. tit. 31,  3018.
    Nowhere in the construction contract do the parties agree
    to limit Lluch's liability for any damages suffered by PRASA due to
    Lluch's negligence.  Consequently, appellees may not assert the
    contractual limits on breach of contract damages as a bar to
    PRASA's recovery in this case.  In short, the collapse of the roof
    structure was found to be caused by Lluch's negligent construction
    and was clearly a reasonably foreseeable consequence of such
    negligence.  Therefore, the cost of repairing the structure
    following the collapse was properly recoverable by PRASA under a
    tort theory.  See 
    id.
     (providing for recovery of "losses and
    damages" against those who are negligent in fulfilling their
    obligations); P.R. Laws Ann. tit. 33,  3024 (defining "losses and
    damages" as those foreseen or which may have been foreseen at the
    time of entering into the obligation).
    Appellees' second argument is that PRASA could prove no
    damages in the amount of the cost to repair the structure because
    PRASA would never have incurred any such damages; Lluch would have.
    The district court instructed the jury that PRASA was entitled to
    recover any amount which will reasonably compensate it for any
    damages it suffered as a result of Lluch's breach of contract or
    negligence as of the date of the collapse on October 22, 1989;
    specifically, the cost to repair the collapse.  Appellees argue
    that PRASA would never have actually incurred the cost of repairing
    the collapse, because that amount would have been absorbed by
    Lluch.  Appellees argue that because Lluch had contracted to
    deliver the completed structure, Article 1481 of the Civil Code
    allocated to Lluch any loss caused by destruction of the project
    before delivery.  See P.R. Laws Ann. tit. 33,  4122 ("If the
    person who contracted for the work bound himself to furnish the
    materials, he shall suffer the loss in case of the destruction of
    the work before it is delivered, unless there has been a delay in
    receiving it.").  From this, appellees argue that, up until PRASA's
    unjustified demolition of the entire structure, Lluch was
    responsible for absorbing the cost of repairing the collapsed
    structure, not PRASA.  Appellees argue that this responsibility
    disappeared when PRASA demolished the entire structure because
    Lluch could no longer deliver the completed structure.
    We cannot accept this argument as an explanation for how
    the jury could reasonably have determined, consistently with its
    duty to follow the court's instructions, that PRASA was entitled to
    no damages.  Appellees' argument regarding the allocation of the
    burden of the collapse is a strictly legal theory that was never
    presented to the jury.  At oral argument, counsel for appellees was
    asked whether this theory was ever presented to the jury.  Counsel
    stated that the theory had been explained in the form of Eng.
    Lluch's and Jimnez's testimony that the cost of repair was to be
    absorbed by Lluch and was never to have been invoiced to PRASA.
    However, the fact that the jury heard testimony regarding Lluch's
    alleged intent that would give life to appellees' legal theory does
    not mean that the jury was instructed on the legal theory itself.
    The jury was specifically instructed that PRASA was entitled to
    recover the cost of repairing the collapse.  The jury was not asked
    to first determine whether PRASA would have actually suffered the
    cost of repair if it had not demolished the structure.  Appellees
    do not argue that they objected to this instruction and do not
    cross-appeal on this issue.  In fact, Appellees do not even appear
    to argue that this portion of the instruction was incorrect.
    Rather, what appellees seem to argue is that the jury properly
    awarded no damages despite the existence of this instruction.  At
    oral argument, appellees' counsel was asked whether it was
    erroneous to instruct the jury that PRASA was entitled to recover
    the cost of repairing the collapse.  Counsel responded that it was
    not erroneous to do so, but that PRASA failed to prove the amount.
    As a result of appellees' failure to object, we accept this
    instruction as correct and as the law of the case.
    We are left with a situation in which the court
    instructed the jury that PRASA could recover the cost of repairing
    the collapse, and PRASA showed that the cost of repairing the
    collapse was significant.  We do not rule on whether the soil
    needed to be improved before the structure could be repaired or
    whether the cost of repairing the roof structure itself was closer
    to $470,000 or to $2,513,211.48.  We find only that, under any of
    those theories, the evidence before the jury was that the cost of
    repair was at least $470,000.  Consequently, a verdict of no
    damages is not consonant with both the instructions given and the
    evidence presented.  We find that the jury abdicated its duty to
    follow the instructions given by the district court, which resulted
    in a verdict that is against the clear weight of the evidence.
    Additionally, we find that it was an abuse of the district court's
    discretion to deny PRASA's motion for a second partial new trial on
    the issue of damages.  The judgment awarding PRASA no damages is
    vacated, and we remand for a new trial on the issue of damages.
    B.  Redetermination of Settled Issues By the Second Jury
    in Violation of the Seventh Amendment
    PRASA also argues that the district court abused its
    discretion in allowing the second jury, due to misleading jury
    instructions and verdict forms, to redetermine the issues of
    Lluch's liability and the existence of PRASA's damages.  PRASA
    claims that these two issues were revisited by the second jury in
    violation of the Seventh Amendment, which states that "no fact
    tried by jury, shall be otherwise reexamined in any Court of the
    United States, than according to the rules of the common law."
    U.S. Const. amend. VII.
    We summarily dismiss PRASA's claim that the jury was
    allowed to redetermine the issue of Lluch's liability.  PRASA
    offers nothing more than the absence of a jury award in support of
    its argument.  However, the jury was specifically instructed: (1)
    that it had already been established that Lluch was negligent and
    breached its contract with PRASA; (2) that Lluch's breach caused
    the collapse of the structure; and (3) that PRASA was entitled to
    recover any damages it suffered due to Lluch's negligence or
    breach.  In light of these instructions, it simply cannot be said
    that the 1997 jury was allowed to redetermine the question of
    Lluch's liability.  In fact, the jury was specifically told that
    this issue had been determined and that they should disregard any
    testimony to the contrary.  Thus, we turn to PRASA's contention
    that the jury was improperly allowed to redetermine the existence
    of PRASA's damages.
    PRASA argues that the district court violated the Seventh
    Amendment when it did not set aside the first jury's determination
    that Lluch's negligence caused PRASA damages, but still allowed the
    second jury to redetermine the existence of PRASA's damages.  PRASA
    argues that the second jury should only have determined the extentof PRASA's damages, not whether PRASA suffered any damages at all.
    PRASA argues that the second jury was allowed to revisit this issue
    because the district court: (1) failed to instruct the jury that it
    was already established that PRASA suffered damages; and (2)
    specifically instructed the jury that it had the option of finding
    that PRASA had not suffered any damages.
    PRASA cites several cases for the proposition that the
    Seventh Amendment requires district courts to conduct successive
    trials in such a way that the same issue is not reexamined by
    different juries.  Without addressing the questions of whether the
    authority cited by PRASA adequately demonstrates such a Seventh
    Amendment principle or whether that principle is applicable in the
    context of a partial new trial on the issue of damages, we note
    that no such principle was violated in this case.  The district
    court did not allow the second jury to redetermine the issue of
    whether PRASA suffered damages.  It is true that the second jury
    was not instructed that it had already been established that PRASA
    suffered damages.  And it is also true that the second jury was
    instructed that it could fail to award PRASA any damages at all.
    However, this instruction was given in the context of explaining to
    the jury that it was PRASA's duty to establish the amount of any
    damages caused by Lluch's negligence or breach of contract.  Seeid.  It is neither inaccurate nor an infringement on PRASA's
    Seventh Amendment rights to instruct the jury that PRASA could not
    recover any damages if it failed to prove any damages at the
    partial new trial, whether the previous jury found that PRASA
    suffered any damages or not.  To hold otherwise would be to hold
    that the jury was obligated to award PRASA damages even if PRASA
    failed to put on any evidence at all at the partial new trial.
    This cannot be the case.  Thus, the district court did not err in
    instructing the jury that it could fail to award PRASA any damages
    at all, despite the first jury's determination that PRASA was
    damaged by Lluch's negligence.
    In short, the district court did not err in failing to
    order a second partial new trial because of the alleged
    reexamination of issues by the second jury.  No such reexamination
    of issues actually occurred.
    C.  Unfair Influence on the Verdict Through Appellees'
    Counsel's Prejudicial Comments During Opening Statements
    and Closing Arguments
    PRASA's final contention as to why the district court
    should have granted a second partial new trial on the issue of
    damages is that appellees' counsel unfairly influenced the verdict
    with two impermissible and prejudicial arguments to the jury.
    PRASA claims: (1) that CNA's counsel made improper reference to the
    limits of Lluch's insurance policy with CNA during CNA's opening
    statement; and (2) that Lluch's counsel made improper reference to
    PRASA's demolition of the structure during Lluch's closing
    argument.
    Absent an abuse of discretion, we will defer to the
    district court's denial of a motion for a new trial on the basis of
    improper argument or conduct of counsel.  See Meyers v. Moody, 
    693 F.2d 1196
    , 1220-21 (5th Cir. 1982), cert. denied, 
    464 U.S. 920
    (1983); see also Johnson v. National Sea Prods., Ltd., 
    35 F.3d 626
    ,
    631 (1st Cir. 1994).  In assessing the effect of improper conduct
    by counsel, the Court must examine the totality of the
    circumstances, including the nature of the comments, their
    frequency, their possible relevancy to the real issues before the
    jury, the manner in which the parties and the court treated the
    comments, the strength of the case, and the verdict itself.  SeeForrestal v. Magendantz, 
    848 F.2d 303
    , 309 (1st Cir. 1988)(quoting
    City of Cleveland v. Peter Kiewit Sons' Co., 
    624 F.2d 749
    , 756 (6th
    Cir. 1980)).  We reverse only upon a showing of prejudice.  SeeGonzlez-Marn v. Equitable Life Assurance Soc'y, 
    845 F.2d 1140
    ,
    1147 (1st Cir. 1988).
    PRASA first complains of CNA's counsel's reference to
    Lluch's policy limits in CNA's opening statement.  PRASA claims
    that this was done for the sole reason of appealing to jury
    sympathy.  CNA pointed out that Lluch would have to pay most of the
    millions sought by PRASA from its own funds, because the insurance
    policy limit was $500,000.  However, the parties agree that the
    insurance policy was admitted into evidence as Joint Exhibit VII.
    Because the jury could have easily discovered the policy limits for
    itself, we cannot say that the district court abused its discretion
    in refusing to grant a new trial on the basis of CNA's improper
    argument.
    PRASA next complains that it was improper for Lluch's
    counsel to make reference to PRASA's demolition of the structure in
    his closing argument.  However, because PRASA did not make a timely
    objection to this statement, we review only for plain error.  SeeFernndez v. Corporacin Insular de Seguros, 
    79 F.3d 207
    , 210 (1st
    Cir. 1996);  Johnson, 
    35 F.3d at 631
     (citations omitted).
    We do not find it to be plain error: (1) to allow Lluch's
    counsel to refer to the demolition of the structure; or (2) to fail
    to grant a new trial on the basis of such a reference.  It was a
    stipulated fact that the demolition of the structure occurred in
    the weeks following January 25, 1993.  Also, the jury was
    specifically instructed that it had already been established that
    PRASA's demolition of the structure was unjustified.  In light of
    the evidence and instructions with which the jury was provided, we
    do not believe that Lluch's mention of the demolition during
    closing argument resulted in any prejudice to PRASA.
    In sum, the district court did not err in failing to
    grant a second partial new trial due to the reference to Lluch's
    policy limits during CNA's opening statement or the reference to
    PRASA's demolition of the structure during Lluch's closing
    argument.
    III.  Jury Verdict in Favor of Lluch's Counterclaims
    PRASA's final argument regards a portion of the 1993
    verdict that was not remitted:  the award of $756,471.59 in favor
    of Lluch on its counterclaims for breach of contract and amounts
    owed on the contract.  PRASA complains that this award was also
    against the weight of the evidence.
    A.  Preservation of This Issue On Appeal
    A motion for a new trial must be made in the first
    instance before the trial court, particularly where the weight of
    the evidence is at issue.  See Velzquez v. Figueroa-Gmez, 
    996 F.2d 425
    , 427 (1st Cir.), cert. denied, 
    510 U.S. 993
     (1993); Wells
    Real Estate v. Greater Lowell Bd. of Realtors, 
    850 F.2d 803
    , 811
    (1st Cir.) (citing 6A Moore's Federal Practice  59.15[3], at 326-
    27 (2d ed. 1987)), cert. denied, 
    488 U.S. 955
     (1988).  The failure
    to move for a new trial waives the issue on appeal.  See Velzquez,
    
    996 F.2d at 427
    ; Wells Real Estate, 850 F.2d at 811.
    PRASA did not move for a new trial on Lluch's
    counterclaims.  However, following the judgment on Lluch's
    counterclaims, PRASA filed a two-page motion for judgment as a
    matter of law on those claims.  On October 27, 1995, the district
    denied PRASA's motion.  The district court found that Lluch
    presented evidence: (1) that PRASA breached the contract; (2) that
    this breach caused damages to Lluch; and (3) that PRASA owed Lluch
    monies on the contract.  The district court found that the evidence
    presented was sufficient to allow a reasonable jury to reach a
    verdict in favor of Lluch on its counterclaims.
    While PRASA's failure to file a motion for a new trial
    would ordinarily require this Court to find that the issue has been
    waived, the fact that PRASA filed a motion for judgment as a matter
    of law helps PRASA to avoid that result.  In Velzquez, the
    appellants sought to challenge the verdict as against the weight of
    the evidence.  See Velzquez, 
    996 F.2d at 427
    .  We held that, even
    though the appellants failed to make the appropriate motion for a
    new trial before the district court, the issue was not waived
    because the appellants made a motion to set aside or amend the
    verdict.  See 
    id.
      We found that because the purpose of the
    appellants' motion was to challenge the verdict as against the
    weight of the evidence, the appellants should not have been deemed
    to have waived the issue.  See 
    id.
      We noted that the district
    court addressed the sufficiency argument and denied the motion
    because the jury's verdict was supported by the evidence.  See 
    id.
    Consequently, we treated the appellants' motion as a motion for a
    new trial and treated the appeal as an appeal of the denial of that
    motion for a new trial.  See 
    id.
    The same situation is presented in the present appeal:
    (1) PRASA made a motion challenging the verdict as against the
    weight of the evidence; (2) the district court addressed the
    sufficiency argument; and (3) the district court denied the motion
    because the jury's verdict was supported by the evidence.
    Therefore, we treat this appeal as an appeal from the denial of
    PRASA's motion for a new trial on Lluch's counterclaims.
    B.  Denial of PRASA's Motion for a New Trial on Lluch's
    Counterclaims
    Again, the denial of a motion for a new trial is reviewed
    for abuse of discretion.  See Bogosian, 
    104 F.3d at 482
    .  A verdict
    may be set aside and a new trial ordered "when the verdict is
    against the clear weight of the evidence, or is based upon evidence
    which is false, or will result in a clear miscarriage of justice."
    Phav, 
    915 F.2d at 766
    .
    PRASA points to the testimony of Jos A. Toro-Mercado, a
    certified public accountant who PRASA claims testified on behalf of
    Lluch that PRASA owed Lluch $2,121,956.35 as a result of change
    orders, additional work, materials, and extended office overhead.
    PRASA claims that Toro-Mercado's testimony was based on three main,
    but faulty, premises: (1) that Lebrn, the designer of the project,
    was at fault for the collapse of the steel roof structure; (2) that
    all delays in the construction project were attributable to PRASA;
    and (3) that Lluch had worked at the project between August 1, 1988
    and October 20, 1990.
    PRASA argues that the first of these three premises was
    contradicted by the 1993 jury verdict itself.  PRASA claims that
    the 1993 jury specifically ruled that Lluch, not Lebrn, was solely
    liable to PRASA for the negligent removal of the surcharge that
    caused the collapse of the structure.  PRASA argues that the second
    premise was also contradicted by the 1993 jury verdict and the
    evidence adduced at trial.  PRASA notes that the 1993 jury omitted
    any finding that PRASA had been solely responsible for the delays
    in the project.  PRASA also claims that all of the evidence
    regarding job certifications that was presented at trial showed
    that Lluch or its subcontractors were as much responsible for the
    delays as was PRASA.  PRASA also notes that "the certifications
    were reconciled during trial by the parties, clearly showing that
    PRASA was not remotely the sole responsible party for the delays in
    the project."  Regarding the third premise, PRASA argues that there
    was "better evidence" of the time period of Lluch's presence at the
    project.
    PRASA's argument fails in several respects.  First, while
    the 1993 jury found Lluch to have been liable, it did not find that
    Lebrn was faultless.  The liability of Lebrn was not before the
    jury, and the jury made no determinations regarding this issue.
    Second, the "omission" of a finding that PRASA was solely
    responsible for project delays is hardly a finding that PRASA was
    not responsible for any delays that may have caused Lluch damages.
    Third, PRASA does not direct the Court to any of the evidence it
    claims demonstrated Lluch's responsibility for delay in
    construction.  Fourth, even if the certifications were "reconciled"
    during trial, PRASA does not explain to the Court how that "clearly
    show[s] that PRASA was not remotely the sole responsible party for
    the delays in the project."  Fifth, PRASA makes no attempt to
    identify the "better evidence" of an allegedly more accurate time
    period of Lluch's involvement in the project.
    Finally, and most importantly, the jury awarded Lluch
    $756,471.59 on its counterclaims, even though PRASA admits that
    Toro-Mercado testified that PRASA owed Lluch $2,121,956.35.  It is
    quite possible that the jury questioned Toro-Mercado's three
    premises and reduced the damages award accordingly.  For example,
    the jury may have reduced the award by the amount it determined
    that Lluch was at fault for the delays.  Or it may have reduced the
    award because it did not agree that Lebrn was solely at fault for
    the collapse.  Or it may have reduced the award because it believed
    that the "better evidence" referred to by PRASA demonstrated that
    Lluch was not on the job as long as it claimed.  This is, of
    course, all speculation, but PRASA does not offer any argument as
    to why the amount actually awarded was against the weight of the
    evidence.  PRASA offers several arguments that demonstrate why
    Lluch should not have been granted all it requested, but the fact
    remains that Lluch was not granted all it requested.
    In the jury verdict form, the 1993 jury found: (1) that
    PRASA breached its contract with Lluch; (2) that this breach caused
    damages to Lluch in the amount of $138,758; and (3) that PRASA owed
    Lluch $617,713.59 for work performed on the contract.  PRASA does
    not offer any evidence or argument that Lluch did not in fact
    suffer damages in the amount of $138,758 or that Lluch was not in
    fact owed $617,713.59 for work performed on the contract.
    Consequently, we reject PRASA's claims that the verdict was against
    the weight of the evidence and leave undisturbed the judgment in
    favor of Lluch on its counterclaims.
    CONCLUSION
    Based on the foregoing, the judgment awarding PRASA no
    damages is VACATED, and this case is REMANDED for a new trial on
    the issue of damages.  The judgment awarding Lluch $756,471.59 on
    its counterclaims for breach of contract and amounts owed on the
    contract is AFFIRMED.
    

Document Info

Docket Number: 98-1331

Filed Date: 1/20/1999

Precedential Status: Precedential

Modified Date: 12/21/2014

Authorities (25)

Kersey v. Dennison Manufacturing Co. , 3 F.3d 482 ( 1993 )

Fernandez v. Corporacion Insular De Seguros , 79 F.3d 207 ( 1996 )

Acevedo Villalobos v. Hon. Hernandez , 22 F.3d 384 ( 1994 )

wang-laboratories-inc-v-applied-computer-sciences-inc-james-abbenhaus , 926 F.2d 92 ( 1991 )

Neftali Gonzalez-Marin v. The Equitable Life Assurance ... , 845 F.2d 1140 ( 1988 )

Agapita Rosa Velazquez v. Edna J. Figueroa-Gomez, (Two ... , 996 F.2d 425 ( 1993 )

Elizabeth v. Bogosian v. Mercedes-Benz of North America, ... , 104 F.3d 472 ( 1997 )

Jesse Forrestal, Etc. v. Henry G. Magendantz , 848 F.2d 303 ( 1988 )

Carlos Torres-Troche v. Municipality of Yauco , 873 F.2d 499 ( 1989 )

Chat Phav v. Trueblood, Inc. , 915 F.2d 764 ( 1990 )

Guy L. Smith, Jr. v. Massachusetts Department of Correction , 936 F.2d 1390 ( 1991 )

Michael Johnson v. National Sea Products, Ltd. , 35 F.3d 626 ( 1994 )

Richard C. Fiore v. Washington County Community Mental ... , 960 F.2d 229 ( 1992 )

Credit Francais International v. Bio-Vita, Ltd. , 78 F.3d 698 ( 1996 )

City of Cleveland v. Peter Kiewit Sons' Co. , 624 F.2d 749 ( 1980 )

Marian Hollywood v. City of Santa Maria Dorothy Lyman ... , 886 F.2d 1228 ( 1989 )

Jerry Baker, Jerry Baker v. Mercedes Benz of North America ... , 114 F.3d 57 ( 1997 )

Frankie L. Barber v. Whirlpool Corporation , 34 F.3d 1268 ( 1994 )

john-clough-md-v-dominica-rush-rueben-marchisano-md-pete-grenko-md , 959 F.2d 182 ( 1992 )

fed-sec-l-rep-p-99028-david-c-meyers-v-shearn-moody-jr-bernard , 693 F.2d 1196 ( 1982 )

View All Authorities »