Paraflon Investments, Ltd. v. Fullbridge, Inc. ( 2020 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 19-1913
    PARAFLON INVESTMENTS, LTD.,
    Plaintiff, Appellant,
    v.
    FULLBRIDGE, INC., ET AL.,
    Defendants, Appellees.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Richard G. Stearns, U.S. District Judge]
    Before
    Kayatta, Circuit Judge,
    Souter,* Associate Justice,
    and Selya, Circuit Judge.
    Nicholas D. Stellakis, with whom Michael R. Perry, Anna
    Baitchenko, and Hunton Andrews Kurth LLP were on brief, for
    appellant.
    Lawrence G. Green, with whom Susan E. Stenger, Kelly K.
    Ballentine, and Burns & Levinson LLP were on brief, for appellees.
    * Hon. David H. Souter, Associate Justice (Ret.) of the
    Supreme Court of the United States, sitting by designation.
    May 26, 2020
    SELYA,   Circuit       Judge.        When   a   seemingly     delicious
    investment    opportunity       turned     rancid    and     left   a   foul   taste,
    plaintiff-appellant Paraflon Investments, Ltd. (Paraflon) went on
    the   offensive:      it     sued    the   once    and    former    object     of   its
    affections,       Fullbridge,       Inc.   (Fullbridge),        and     Fullbridge's
    principals, Peter Olson and Candice Olson, claiming fraud and
    misrepresentation.      Following a five-day bench trial, the district
    court turned Paraflon away empty-handed.                 See Paraflon Invs., Ltd.
    v. Fullbridge, Inc., No. 16-12436, 
    2019 WL 3759522
    , at *12 (D.
    Mass. Aug. 9, 2019).         Paraflon now seeks appellate review.               After
    rounding off some ragged edges, we affirm.
    I. BACKGROUND
    We   rehearse    the    relevant      facts     consistent    with     the
    district court's supportable factual findings.                        See Dudley v.
    Hannaford Bros., 
    333 F.3d 299
    , 301 (1st Cir. 2003).                          Our tale
    begins with an introduction to the protagonists and other leading
    players.
    Paraflon is a private limited company, principally based
    in the British Virgin Islands and wholly owned by a family trust.
    The trust's main beneficiary, Michael Sarkesian, scouts investment
    opportunities for Paraflon.            Founded in 2010 by the Olsons and
    based in Massachusetts, Fullbridge develops training courses for
    students   to     facilitate     their     successful        transition    into     the
    - 3 -
    workforce.1     The Olsons served jointly as Fullbridge's chief
    executive officers until August of 2015.           Thereafter, Peter Olson
    alone acted in that capacity.        He resigned in May of 2016.
    This case has its genesis in Fullbridge's relationship
    with Takamol, a subsidiary of the Kingdom of Saudi Arabia's
    Ministry of Labor. The Ministry created Takamol with a view toward
    bolstering    the    Saudi   labor     market   through    private      sector
    partnerships.       In May of 2014, Takamol issued a Request for
    Proposal (RFP) seeking bidders for "Wave 1" of a project involving
    the production of online training courses.           Fullbridge submitted
    a bid and was subsequently notified by Takamol, both verbally and
    (at some point) in writing, that it was the winning bidder.
    In August of 2014 (after Fullbridge had been selected as
    the winning bidder for Wave 1), Takamol and Fullbridge executed a
    project   agreement,     sometimes      referred    to    as   the     "Master
    Agreement."     This Agreement provided that it would "serve as a
    framework for the terms" governing Fullbridge's work, which would
    occur incrementally in line with discrete work orders.               Each work
    order would function "as a separate contract and [would] adopt the
    terms of" the Master Agreement.          In turn, the Master Agreement
    disclaimed any commitment "that a Work Order will be offered,
    1 Where the context admits, we use either the shorthand
    "Fullbridge" or the term "the defendants" to refer to Fullbridge
    and the Olsons, collectively.
    - 4 -
    awarded or entered into," and declared that no "binding agreement"
    would exist "until the relevant Work Order is formally executed."
    In the fall of 2014, Takamol issued a second RFP for
    "Wave 2" of the project.   Fullbridge again submitted a bid and was
    awarded a portion of the Wave 2 project.       After Fullbridge was
    notified of the award, the parties spent weeks negotiating final
    pricing, eventually reaching an accord through an exchange of
    e-mails.
    Although the Master Agreement referenced the Wave 1 RFP,
    its application was not expressly confined to Wave 1.    And at the
    time the Master Agreement was executed, Takamol informed Peter
    Olson that it would cover all of Fullbridge's future work for
    Takamol, including any projects associated with Waves 2 and 3.
    Consistent with this representation, work orders subsequently
    issued to Fullbridge for both Wave 1 and Wave 2 incorporated by
    reference the terms of the Master Agreement.
    Throughout Fullbridge's work on Waves 1 and 2, Takamol
    maintained a practice of "perform[] now, paper[] later."    Relying
    on this practice, Fullbridge began work on Wave 1 before the Master
    Agreement had been executed, proceeding on the basis of verbal
    assurances from Takamol that it had received the Wave 1 award.
    Similarly, Fullbridge began multiple projects months before any
    work orders for those projects were executed.
    - 5 -
    As    Fullbridge's     relationship       with    Takamol    matured,
    Fullbridge found itself undercapitalized and went hunting for
    investors.        In the spring of 2015, Paraflon paid $500,000 to
    purchase shares of Fullbridge's convertible preferred stock during
    the company's Series D financing round.                At that time, Paraflon
    had made only a handful of other investments (none of which had
    been in the education sector).
    In April — from this point forward all dates are in 2015
    unless otherwise expressly denominated — Takamol issued a third
    RFP seeking course developers for Wave 3.                     This RFP included
    provisions requiring successful bidders to enter into three-year
    "Framework Agreements" with Takamol. It also required all bidders,
    "including those who ha[d] previously entered into an agreement
    with Takamol," to complete a "Legal Requirements attachment" since
    the standard terms employed in previous RFPs had been updated.
    Any successful bidder would be "expected to enter into a Framework
    Agreement with Takamol on the basis" of these legal requirements.
    Additionally, the RFP stated that "Preferred Bidder[s]" would be
    notified of that status in writing.
    Fullbridge submitted a bid for Wave 3 in late May.                 In
    August,   Takamol           requested    a   meeting     with     a      Fullbridge
    decisionmaker to commence negotiations regarding Wave 3. On August
    17,   three       Takamol    representatives    met     with    two   Fullbridge
    representatives in Saudi Arabia, with Peter Olson and two other
    - 6 -
    Fullbridge employees participating by telephone.                   At this meeting,
    a   Takamol        representative    stated       that    Fullbridge         had    won   a
    substantial share of the Wave 3 project, to include the development
    of approximately 8,000 learning hours over the course of three
    years,      with    the   price   per     learning    hour      capped       at    $4,800.2
    Fullbridge estimated that, under this arrangement, it would earn
    approximately $40 million in revenue.
    In the aftermath of the August 17 meeting, Fullbridge
    understood that the parties had reached a high-level agreement on
    the approximate number of learning hours, the maximum price per
    learning hour, and the overall duration of the work.                          Fullbridge
    also understood, though, that the parties still needed to negotiate
    a "second layer" of more granular details.                 These details included
    the "families" of course topics that Fullbridge would produce, the
    number of courses to be developed within each family, and the exact
    price       associated    with    each    family.         But   based    on        previous
    statements         that   the    Master    Agreement       would    govern         all    of
    Fullbridge's work for Takamol, Fullbridge did not believe that it
    would be required to execute a new Framework Agreement for Wave 3.
    Shortly    after    the    August     17   meeting,       a    Fullbridge
    employee e-mailed Takamol a "pricing offer" containing a proposed
    2
    At trial, Paraflon objected on hearsay grounds to the
    admission of testimony about Takamol's statements at the August 17
    meeting. The district court overruled this objection. On appeal,
    Paraflon does not argue that this evidence was improperly admitted.
    - 7 -
    breakdown    of   course   families,    the        price    per    learning    hour
    associated with each family, and the average course length per
    family. The next day, Abeer AlHashimi (a Fullbridge representative
    based in Saudi Arabia) reported that Takamol's "initial feedback"
    on   Fullbridge's    proposed   pricing      had    been    positive     and   that
    Fullbridge should expect to hear back from Takamol within two days
    "on the exact volume and families awarded."
    Fullbridge quickly commenced logistical planning for its
    work on Wave 3, remaining in regular contact with Takamol along
    the way.    Starting in September, Peter Olson checked weekly with
    AlHashimi, inquiring whether it would be accurate to tell investors
    that Fullbridge's Wave 3 "deal" was "still on."                    AlHashimi (who
    had contact with Takamol's upper echelon) repeatedly confirmed the
    deal's   continued    viability.       Apparently          still    strapped    for
    capital, Fullbridge sought loans from two venture capital firms.
    Both firms requested documentation of the Wave 3 award, sparking
    a series of communications between Fullbridge and Takamol about
    Wave 3's status.       Although we need not recite book and verse,
    several data points bear mention.
    To    begin,   Takamol   declined        to    sign    a   non-binding
    statement, drafted by Fullbridge, confirming the Wave 3 award.
    Then — in an e-mail to Takamol in late October — Peter Olson
    indicated that Fullbridge was ready to begin work in earnest on
    Wave 3 "pending the actual award of courses and a clear timetable
    - 8 -
    for delivery."3    He requested "a sense of the exact timing and
    courses designated."     Takamol responded that although it had been
    "delayed by issues outside of [its] control," matters seemed to be
    "moving in the right direction."       Emphasizing that it valued its
    "partnership" with Fullbridge, Takamol stated that although it
    could not give "a date now," all partners could expect to receive
    "a better outlook" the following week.
    In an e-mail to AlHashimi a few days later, Takamol
    indicated that it was "still waiting for the management approval
    in   this   particular   RFP"   and    proposed   that    an   alternative
    arrangement be implemented "to expedite the approval."                  This
    alternative   arrangement   entailed     the   issuance   of   a   so-called
    buffer order for "a certain number of learning [h]ours" on a
    "letter of intent basis" and a fixed price agreement that would
    set the "price and the demand for [the] long period agreement."
    Takamol's representative noted that although he did not know "how
    much" would ultimately be agreed to (an apparent reference to the
    volume and/or price of courses), Fullbridge's original pricing
    offer was "acceptable" to him. AlHashimi responded that Fullbridge
    would accept this arrangement if Takamol confirmed the full scope
    3  In this e-mail, Peter Olson described Fullbridge as
    "delighted to have been shortlisted as a course developer" for
    Wave 3.   He testified at trial that by "shortlisted," he meant
    that Fullbridge was "honored to be part of a very short list" of
    successful bidders.
    - 9 -
    of the Wave 3 project (specifically, a minimum of 7,200 learning
    hours    with   an   average   production   of   600   learning   hours   per
    quarter).       Takamol replied that it could not "accept a minimum
    scale" for Wave 3.       Fullbridge subsequently agreed to the buffer
    order "with no conditions," but Takamol never issued it.
    Around this time, Fullbridge opened its D-1 financing
    round.    On October 30, Fullbridge sought a second investment from
    Paraflon, e-mailing Sarkesian a copy of an investor presentation
    made earlier that month.         This presentation included statements
    that Fullbridge had won a "$40mm share of Wave 3" and had a "$40mm
    3 year contract with Takamol." On November 16, Fullbridge followed
    up with a "Qualitative High Level Summary" stating that it had
    "recently won a large flywheel contract/award from [the Kingdom of
    Saudi Arabia], signaling [a] large new pipeline fueling top-line
    growth over [the] next 2-3 years."4
    Sarkesian reviewed these documents and decided to invest
    in the D-1 round chiefly because of Fullbridge's representations
    about the $40 million Wave 3 award.              He never asked to review
    documentation relating to the Wave 3 award.              Nor did he visit
    Fullbridge's "data room," where important documents were made
    4 From time to time, Fullbridge referred to both a Wave 3
    "contract" and a Wave 3 "contract/award." Since nothing turns on
    this nomenclature, we use the terms interchangeably.
    - 10 -
    available to investors (but he testified that he was unaware of
    the data room's existence at the time).
    On November 20, Sarkesian made the purchase that gave
    rise to this litigation:     acting for Paraflon, he agreed to buy
    $750,000 worth of Series D-1 convertible preferred stock.                He
    approved the executed purchase documents, dated November 20, on
    November 23.    The signed documents were forwarded to Fullbridge
    that day.    And on December 1, Paraflon wired the purchase money.
    Meanwhile, Takamol had continued to delay finalizing the
    details of Fullbridge's Wave 3 work.           In a November 11 e-mail,
    Takamol stated that it was "on the final stages to finalize wave
    III awarding," which it expected "to be completed by [the] end of
    next week."     Roughly two weeks later (on November 26), Takamol
    informed Fullbridge that it had "reached the final stage for the
    issuance of the letter of award and subsequent agreement" but
    Fullbridge would need to accept a maximum of 3,000 learning hours.
    Fullbridge estimated that this decreased the value of the award
    from approximately $40 million to approximately $14 million.             In
    addition,    Fullbridge   interpreted    the    November   26   e-mail   as
    requiring it to sign a new Framework Agreement.
    Fullbridge had little time to dwell on the downside of
    these developments.    Within a matter of months, the Wave 3 project
    collapsed.    In February of 2016, Takamol put the entire project on
    hold.   The death knell was sounded when Takamol later decided to
    - 11 -
    develop its own courses internally.                By April of 2016, Candice
    Olson was openly bemoaning the "loss of [the] $40mm award."
    The parting of the ways between Fullbridge and Takamol
    did not end the matter.                Stung by the deterioration of its
    investment, Paraflon brought suit against, among other parties,
    Fullbridge and the Olsons in the United States District Court for
    the Southern District of New York.              It pressed federal securities
    fraud claims, as well as common law claims for breach of contract,
    negligent misrepresentation, and fraudulent misrepresentation and
    concealment.        By agreement, the case was transferred to the
    District of Massachusetts.         See 28 U.S.C. § 1404(a).
    After the close of discovery, a five-day bench trial
    ensued.       The   district    court    granted     Fullbridge's     motion   for
    judgment as a matter of law on Paraflon's breach of contract claim,
    and Paraflon has not appealed this ruling.                    After trial, the
    district court took the matter under advisement.                 In due course,
    it issued an exegetic rescript, ruling against Paraflon on both
    its       federal    securities        law   claims     and     its     state-law
    misrepresentation claims.5        See Paraflon, 
    2019 WL 3759522
    , at *12.
    Pertinently, the court found that Fullbridge "did not knowingly or
    intentionally       make   a   false    statement"    and     that   Fullbridge's
    5For ease in exposition, we sometimes refer to Paraflon's
    negligent misrepresentation and fraudulent misrepresentation and
    concealment claims collectively as the "misrepresentation claims."
    - 12 -
    representation of a $40 million award from Takamol "was not false
    nor should defendants have known it to be inaccurate at the time
    it was made."
    Id. This timely
    appeal followed.       In it, Paraflon
    challenges only the district court's disposition of the state-law
    misrepresentation claims against Fullbridge and the Olsons.
    II. ANALYSIS
    Following a bench trial, we review the trial court's
    legal conclusions de novo.     See Calandro v. Sedgwick Claims Mgmt.
    Servs., Inc., 
    919 F.3d 26
    , 33 (1st Cir. 2019).              We assay the
    court's factual findings for clear error, deferring to those
    findings unless careful consideration of the record leaves us with
    a firm conviction that they "are simply wrong."
    Id. (quoting State
    Police Ass'n v. Comm'r, 
    125 F.3d 1
    , 5 (1st Cir. 1997)).                   In
    undertaking this tamisage, we remain mindful that the trial court
    "sees and hears the witnesses at first hand and comes to appreciate
    the nuances of the litigation in a way which appellate courts
    cannot   hope   to   replicate."
    Id. (quoting Cumpiano
      v.   Banco
    Santander P.R., 
    902 F.2d 148
    , 152 (1st Cir. 1990)).
    In this instance, the district court determined that New
    York law supplies the substantive rules of decision.         Neither side
    challenges that determination.       When a federal court must make a
    choice of state substantive law, it is at liberty to accept,
    without particularized inquiry, the parties' reasonable consensus
    as to which state supplies the substantive rules of decision.            See
    - 13 -
    e.g., Borden v. Paul Revere Life Ins. Co., 
    935 F.2d 370
    , 375 (1st
    Cir. 1991).       Thus, we too apply New York law.
    Under       New   York     law,   a   plaintiff    alleging     negligent
    misrepresentation must prove by preponderant evidence that the
    defendant    had     a    duty    to    impart     accurate    information      to   the
    plaintiff by virtue of a special relationship; that the defendant
    breached this duty by carelessly imparting false information that
    he   ought   to    have        known    was    inaccurate;     that   the    defendant
    understood that the plaintiff would use the information for a
    particular purpose; and that the plaintiff reasonably relied on
    this information to his detriment.                 See Anschutz Corp. v. Merrill
    Lynch & Co., 
    690 F.3d 98
    , 114 (2d Cir. 2012); Mandarin Trading
    Ltd. v. Wildenstein, 
    944 N.E.2d 1104
    , 1109 (N.Y. 2011); White v.
    Guarente, 
    372 N.E.2d 315
    , 319 (N.Y. 1977); Wrynn v. Subaru Town
    Motors, Inc., 
    487 N.Y.S.2d 247
    , 247 (App. Term 1984).                       For a claim
    of fraudulent misrepresentation, New York law provides a somewhat
    different framework.            With respect to such a claim, the plaintiff
    must prove by clear and convincing evidence that the defendant
    knowingly or recklessly made a false representation of material
    fact; that the defendant made the misrepresentation with the intent
    of inducing the counter-party's reliance; and that the counter-
    party   justifiably            relied    on    the   misrepresentation         to    his
    detriment.    See Merrill Lynch & Co. v. Allegheny Energy, Inc., 
    500 F.3d 171
    , 181 (2d Cir. 2007); Mandarin 
    Trading, 944 N.E.2d at 1108
    .
    - 14 -
    The first of these elements may also be satisfied by showing an
    omission of material information "that the opposing party had a
    duty to disclose."        Ahern v. Scholz, 
    85 F.3d 774
    , 793 (1st Cir.
    1996); see Merrill 
    Lynch, 500 F.3d at 181
    ; P.T. Bank Cent. Asia v.
    ABN AMRO Bank N.V., 
    754 N.Y.S.2d 245
    , 250 (App. Div. 2003).                The
    parties appear to agree that such omissions also can give rise to
    negligent misrepresentation claims.            See Creative Waste Mgmt.,
    Inc. v. Capitol Envtl. Servs., Inc., 
    429 F. Supp. 2d 582
    , 609
    (S.D.N.Y. 2006).    A duty to disclose may attach if the parties are
    "in a fiduciary or confidential relationship"; if disclosure is
    necessary to correct or complete an earlier "partial or ambiguous
    statement"; or if one party enjoys an informational advantage and
    knows another party is acting on the basis of bad information.
    Brass v. Am. Film Techs., Inc., 
    987 F.2d 142
    , 150 (2d Cir. 1993).
    We pause to note an important doctrinal wrinkle.             Under
    New York law, an investor's claim that a defendant fraudulently
    induced its investment generally cannot rest on misrepresentations
    or omissions that postdate the investment because the element of
    detrimental reliance is "necessarily absent."           High Tides, LLC v.
    DeMichele, 
    931 N.Y.S.2d 377
    , 381 (App. Div. 2011); see RKA Film
    Fin., LLC v. Kavanaugh, 
    99 N.Y.S.3d 267
    , 270 (App. Div. 2019).
    This   principle    has     equal    bite    with   respect   to   negligent
    misrepresentation    claims,        which    likewise   require    proof    of
    reasonable reliance.       See Mandarin 
    Trading, 944 N.E.2d at 1109
    .
    - 15 -
    Against this backdrop, Paraflon marshals three separate
    lines of attack.6     Each line of attack centers on the district
    court's   findings   about    Fullbridge's        state   of    mind.7      First,
    Paraflon argues that the district court misidentified the correct
    cut-off date for Fullbridge's duty to disclose and, by extension,
    assessed Fullbridge's state of mind at the wrong temporal moment.
    Second,   Paraflon   argues   that    the    district       court   cabined   its
    assessment   of   Fullbridge's       state    of     mind      to   Fullbridge's
    subjective belief in a Wave 3 contract, failing to evaluate whether
    that belief was objectively reasonable.              Third, Paraflon argues
    that any finding that Fullbridge reasonably believed it had a $40
    million   contract   was   erroneous.        We    address     these     arguments
    sequentially.
    We start with Paraflon's contention that the district
    court botched its assessment of the misrepresentation claims by
    6 To the extent that Paraflon has attempted to raise other
    arguments along the way, those arguments are undeveloped,
    meritless, or both. Thus, we reject them out of hand.
    7 The parties use the phrase "state of mind" to refer to the
    element of negligent misrepresentation requiring proof that the
    defendant "should have known" that its representation was
    inaccurate. 
    Anschutz, 690 F.3d at 114
    (quoting Hydro Inv'rs, Inc.
    v. Trafalgar Power Inc., 
    227 F.3d 8
    , 20 (2d Cir. 2000)). They use
    the   same  term   to  refer   to   the   element  of   fraudulent
    misrepresentation requiring proof that the defendant knowingly or
    recklessly made a false statement with the intent to induce
    reliance by the counter-party (scienter). See Merrill 
    Lynch, 500 F.3d at 181
    ; Mandarin 
    Trading, 944 N.E.2d at 1108
    .        To avoid
    confusion, we follow the parties' lead and employ the same
    terminology where appropriate.
    - 16 -
    treating the date of Fullbridge's initial representation that it
    had a $40 million contract (October 30), rather than the date of
    Paraflon's     D-1    investment,   as   the   end   point   for   evaluating
    Fullbridge's state of mind and the fulfillment of its disclosure
    duties.      By misapprehending this pivotal date, Paraflon's thesis
    runs, the district court excluded from its decisional calculus
    various pre-investment events that Fullbridge either should have
    disclosed or that bore on its state of mind at the time of
    Paraflon's investment.       Before embarking on this circuitous path,
    we offer a brief primer on pertinent New York precedent and note
    the applicable standards of review.
    When — as in this case — a plaintiff alleges that the
    defendant's      misrepresentations       or    omissions      induced    its
    investment, New York law indicates that the defendant's state of
    mind and satisfaction of its disclosure duties should be assessed
    up until the date of the plaintiff's investment.             Cf. High 
    Tides, 931 N.Y.S.2d at 381
    (framing plaintiff's investment as temporal
    touchstone for determining whether misrepresentations or omissions
    can   form    basis   for   fraud   claims).     Even   if   post-investment
    developments might be said to trigger some disclosure duty on the
    defendant's part, see 
    Brass, 987 F.2d at 150
    , misrepresentations
    or omissions about such events are generally of no consequence in
    an action premised on fraudulent inducement of an investment.            See
    - 17 -
    High   
    Tides, 931 N.Y.S.2d at 381
       (explaining   that   in    such   a
    situation, detrimental reliance is "necessarily absent").
    New York courts have not been crystal clear about when
    an investment should be deemed to have occurred for purposes of
    misrepresentation claims.        This question becomes especially thorny
    where, as here, the plaintiff arguably bound itself to participate
    in the transaction as an investor before the transaction was
    formally consummated in all respects.           What little precedent there
    is, though, suggests that, in this context, an investment should
    be deemed to have occurred once the plaintiff has decided to invest
    and bound himself to the transaction sufficiently that subsequent
    developments    cannot   be   said     to    have   influenced   his    already-
    solidified investment decision.              Cf.
    id. (holding that
    post-
    investment misrepresentations and omissions cannot form basis for
    fraud claims).    Contrary to Paraflon's importunings, we think this
    pivotal date may, under the right factual circumstances, occur
    earlier than the technical consummation of all aspects of the
    transaction.
    Turning to the applicable standards of review, we review
    de novo whether the district court, as a matter of law, apprehended
    that the date of Paraflon's investment was the relevant cut-off
    date for assessing Fullbridge's state of mind.              See 
    Calandro, 919 F.3d at 33
    ; see also United States v. 15 Bosworth St., 
    236 F.3d 50
    , 54 (1st Cir. 2001) ("[W]hen a trial court bases its findings
    - 18 -
    of fact on an inaccurate appraisal of controlling legal principles,
    the   rationale    for     deference     [to    those   findings]   evaporates
    entirely.").     If so, we then must determine what finding, if any,
    the district court made about the date of Paraflon's investment
    decision.     Because the precise timing of a particular investment
    is a factbound determination that can only be made after a holistic
    assessment of the specific purchase documents and the attendant
    circumstances, cf. Crellin Techs., Inc. v. Equipmentlease Corp.,
    
    18 F.3d 1
    , 7 (1st Cir. 1994) ("[S]o long as the evidence does not
    point unerringly in a single direction . . . the question of
    whether a contract has been formed between two parties is a
    question of fact to be determined by the factfinder."), we review
    any factual finding about the timing of Paraflon's investment only
    for clear error, see 
    Calandro, 919 F.3d at 35
    .
    We begin with a de novo inquiry into whether the district
    court, as a matter of law, grasped the pivotal cut-off date for
    appraising Fullbridge's state of mind.            In mounting this inquiry,
    we are quick to acknowledge that the district court was not
    altogether    clear   as    to   its   temporal    focal   point.    Taken   in
    isolation, a few of the court's findings may be read to suggest
    that the court confined its conclusions to the period demarcated
    by Fullbridge's October 30 representations.             See, e.g., Paraflon,
    
    2019 WL 3759522
    , at *10-12.            This suggestion is given a boost by
    the court's citation to an unpublished decision that may be read
    - 19 -
    to suggest that a defendant's state of mind need only be evaluated
    as of the time of the alleged misrepresentation.                See
    id. at *10,
    *12 (citing IP Cube Partners Co. v. Telecomm. Sys., Inc., No. 15
    CV 6334, 
    2016 WL 3248500
    , at *2 (S.D.N.Y. June 13, 2016) ("An
    essential element of both fraud and negligent misrepresentation is
    that the defendant knew or should have known that its statements
    were false at the time they were made.")).
    But elsewhere in its rescript, the court clarified its
    thinking.       Citing pertinent New York precedent, it twice singled
    out the date of investment as the pivotal moment.                See
    id. at *10-
    11 (citing High 
    Tides, 931 N.Y.S.2d at 381
    ).                 Take, for instance,
    its extended discussion of Takamol's November 26 e-mail reducing
    the size of the Wave 3 award to approximately $14 million.                 Noting
    that    "Paraflon    had   purchased      the   stock   on    November   20"   and
    "executed the purchase agreement on November 23," the court held
    that "even assuming that [Fullbridge] had a duty to disclose the
    reduction in the award after the purchase," that disclosure would
    have "had no bearing on Paraflon's initial decision to invest in
    Fullbridge."
    Id. at *11
    (citing High 
    Tides, 931 N.Y.S.2d at 381
    ).
    Although the court mentioned in passing that Paraflon's
    "decision to invest" had occurred "a month prior to the [November
    26] e-mail," the surrounding context makes reasonably clear that
    the    court    viewed   that   initial    investment    decision     as   merely
    tentative and the final (analytically significant) investment
    - 20 -
    decision as having occurred in November.8          Id.; see
    id. at *6-7.
    This sequencing is consistent with real-world business practices:
    prospective investors typically make a preliminary decision to go
    forward because a given investment looks promising but withhold
    their final decision — usually evidenced by signing on the dotted
    line — until the details of the investment are in place.               Given
    the realities of the marketplace, the court's invocation of the
    November   purchase     dates   and   its   apparent   understanding   that
    Paraflon's     actual   investment     decision   occurred   in   November
    persuade us that it deemed the November 26 e-mail inconsequential
    because that e-mail was transmitted after Paraflon had already
    committed itself to the investment.
    In all events, any lingering concern that the district
    court froze its analysis at October 30 is dispelled by the court's
    factual findings anent November events and its reliance on a number
    of those findings in reaching its conclusions.          See, e.g.,
    id. at *4-7,
    *11.      Taking the court's rescript as a whole, it makes
    8 For example, as we read its rescript, the district court
    made a finding that Sarkesian reviewed both the October 30 investor
    presentation and the summary chart that Fullbridge provided on
    November 16 before deciding to invest in the D-1 round of
    financing. See Paraflon, 
    2019 WL 3759522
    , at *6. In addition,
    the court sandwiched its suggestion that Paraflon had made some
    sort of decision to invest in October between a citation to this
    finding and a reference to another finding that Paraflon had
    purchased the D-1 stock on November 20. See
    id. at *11
    . 
    Taken
    together, these findings and surrounding statements help to refute
    any suggestion that the court treated Paraflon's actual investment
    decision as having occurred in October.
    - 21 -
    reasonably evident that the court did not mean to limit the
    temporal parameters of its conclusions to October 30.
    We add a coda.   When a district court presides over a
    bench trial in a complex case and makes lengthy findings, some
    imprecision is not uncommon.        Where such imprecision exists, a
    reviewing    court   ordinarily    should     attempt   to    resolve   any
    uncertainty by construing that court's findings and conclusions as
    a whole.    Cf. 
    Calandro, 919 F.3d at 31
    ("Bench trials evoke a
    deferential standard of review.").         Here, a careful review of the
    totality of the district court's findings and conclusions makes
    manifest that the court did not stop the analytical clock at
    October 30 but, rather, treated the time of Paraflon's actual
    investment decision (November 20-23) as the cut-off for assessing
    Fullbridge's state of mind.
    As we read its rescript, the district court unarguably
    found that Paraflon purchased the D-1 stock on November 20 and
    executed the purchase agreement on November 23.              See Paraflon,
    
    2019 WL 3759522
    , at *7, *11.       Additionally, the court indicated
    that those November dates were more significant than December 1
    (when Paraflon wired its D-1 purchase money).            See
    id. at *11
    ("While the funds were wired on December 1, 2015, Paraflon had
    purchased the stock on November 20, 2015, and had executed the
    purchase agreement on November 23, 2015.").        And because there is
    no material difference between the November 20 date and the
    - 22 -
    November 23 date with respect to either Fullbridge's state of mind
    or its disclosure duties, we will assume, favorably to Paraflon,
    that the court found the later date to be the date of Paraflon's
    D-1 investment.
    The next question, of course, is whether this finding is
    supportable as a matter of fact.     As we have said, findings about
    when particular investments occur are "ineluctably factbound" and,
    thus, reviewable only for clear error.     
    Calandro, 919 F.3d at 35
    .
    We discern nothing resembling clear error here.
    To begin, by "execut[ing] and deliveri[ng]" the investor
    signature page in the D-1 stock purchase agreement on November 23,
    Paraflon "agree[d] to be bound by and be a party to" the agreement
    as an investor "as of the date set forth" on the signature page
    (November 20).    While the agreement specifies elsewhere that sales
    of   securities    can   only   be   "consummated"   by   Fullbridge's
    "acceptance of offers to purchase" stock, the undisputed evidence
    of Fullbridge's earnest solicitation of Paraflon's investment
    supports an inference that Fullbridge's acceptance was a foregone
    conclusion.    And even though Paraflon did not wire the purchase
    money until December 1, its counsel essentially conceded at oral
    argument that, absent fraud or misrepresentation prior to the
    execution of the agreement, it had no ability to renege on the
    transaction once it forwarded the investor signature page on
    November 23.
    - 23 -
    We add, moreover, that the district court premised its
    finding    about   the   date   of   Paraflon's   investment   in   part    on
    Paraflon's own pretrial stipulation that it "purchased" the D-1
    stock on November 20 and in part on undisputed evidence showing
    that Sarkesian directed the transmittal of the executed purchasing
    documents to Fullbridge on November 23. Paraflon, 
    2019 WL 3759522
    ,
    at *7.    The district court was free to factor these considerations
    into its decisional calculus.         See Chao v. Hotel Oasis, Inc., 
    493 F.3d 26
    , 32 (1st Cir. 2007); T I Fed. Credit Union v. DelBonis, 
    72 F.3d 921
    , 928 (1st Cir. 1995).
    To cap the matter, Paraflon itself suggested in its
    opening brief that November 23 was the date on which a "meeting of
    [the] minds on all essential terms" occurred between Paraflon and
    Fullbridge.     We conclude, therefore, that the district court's
    finding that Paraflon made its actual investment decision and bound
    itself to the transaction as of November 23 was not clearly
    erroneous.     It follows that any subsequent misrepresentations or
    omissions could not be said to have induced its investment.                See
    RKA Film 
    Fin., 99 N.Y.S.3d at 270
    ; High 
    Tides, 931 N.Y.S.2d at 381
    .
    Paraflon resists this conclusion, seizing on the stock
    purchase agreement's provision that sales of D-1 stock could not
    be "consummated" until Fullbridge accepted Paraflon's purchase
    offer.    With this in mind, Paraflon contends that Fullbridge did
    - 24 -
    not accept its investment until the D-1 round officially closed on
    January 22, 2016.   The rub, though, is that Paraflon never argued
    below that January 22 should be deemed the pivotal date on which
    its D-1 investment occurred.    "If any principle is settled in this
    circuit, it is that, absent the most extraordinary circumstances,
    legal theories not raised squarely in the lower court cannot be
    broached for the first time on appeal.”        Teamsters Union, Local
    No. 59 v. Superline Transp. Co., 
    953 F.2d 17
    , 21 (1st Cir. 1992).
    The circumstances here are not extraordinary and, thus, Paraflon's
    belated argument is foreclosed.
    In an effort to pull a large rabbit out of a small hat,
    Paraflon launches an alternative argument.       It presents December
    1 (when it wired its D-1 purchase funds) as the next most plausible
    date on which its investment should be deemed to have occurred.
    The   district   court   rejected   this   alternative   argument,   see
    Paraflon, 
    2019 WL 3759522
    , at *11, and so do we.          Paraflon has
    failed to offer any persuasive reasoning as to why the factfinder
    was obliged to privilege the date on which Paraflon wired its
    purchase funds over the dates on which it effectively bound itself
    to participate in the transaction.
    This brings us to Paraflon's complaint that the district
    court mistakenly evaluated Fullbridge's state of mind as of October
    30, instead of evaluating it as of November 23.          As we explain
    below, this complaint is unavailing.
    - 25 -
    To be sure, the district court — in elaborating upon its
    conclusion that the "[d]efendants did not act with the intent to
    deceive or with reckless disregard for the truth" — found that "in
    October of 2015, [the] defendants reasonably believed, and had a
    good faith basis for representing, that Fullbridge had been awarded
    $40 million of business over three years from Takamol."
    Id. But rejecting
      any    inference     that   Fullbridge's    financial   troubles
    prompted    it    to   mislead    investors    either    "purposefully       or
    recklessly," the court went on to find that Fullbridge "acted from
    August through November of 2015 consistently with the belief that
    it would receive the $40 million award from Takamol."
    Id. We think
    it apparent that the "belief" found by the court was a
    reasonable, good-faith belief in the $40 million award.
    Id. What is
    more, the court found that this belief persisted notwithstanding
    Fullbridge's difficulties in securing written confirmation from
    Takamol — difficulties that (as the court's accompanying citation
    to an earlier factual finding made clear) continued into November.
    See
    id. Taking these
    state-of-mind findings in the aggregate, we
    are satisfied that the district court intended those findings to
    capture more than the period ending October 30.           In our view, the
    totality of the court's statements on the subject amount to an
    implicit finding that Fullbridge reasonably believed it had been
    awarded a $40 million portion of Wave 3 and that such a belief
    - 26 -
    persisted through November 23.          It was not until November 26 (when
    Takamol reduced the Wave 3 award and made clear that Fullbridge
    would be required to sign a Framework Agreement) that Fullbridge's
    hopes were dashed.     See
    id. We recognize,
      of   course,     that   the   district     court's
    decision is not a model of clarity.            But "[b]ench trials evoke a
    deferential standard of review," 
    Calandro, 919 F.3d at 31
    , and
    wherever possible, we afford the district court's findings a
    generous reading.      Employing "this respectful standard," we are
    satisfied that the court below made at least an implicit finding
    about   Fullbridge's   state     of    mind    at   the   time   of   Paraflon's
    investment.
    Id. Battling on,
    Paraflon contends that the district court
    failed to consider certain events, postdating October 30, that
    bore upon Fullbridge's state of mind and duty to disclose.                  This
    contention is woven out of whole cloth.
    At least three of the items on Paraflon's list of
    "omitted" events — the November 26 e-mail, Takamol's subsequent
    failure to make any "commitments to Fullbridge," and Fullbridge's
    use of Paraflon's investment to defray basic operating expenses —
    occurred after Paraflon's investment on November 23.                  Thus, none
    of these developments could have influenced Paraflon's investment
    decision.   See RKA Film 
    Fin., 99 N.Y.S.3d at 270
    ; High 
    Tides, 931 N.Y.S.2d at 381
    ; see also Paraflon, 
    2019 WL 3759522
    , at *11
    - 27 -
    (recognizing this reality with respect to the November 26 e-mail).
    And since Paraflon has not advanced a plausible claim that any of
    these       events    evinced   pre-investment      misrepresentation    or
    concealment,         they   cannot    breathe     life   into    Paraflon's
    misrepresentation claims.
    We also give no weight to Paraflon's allusion to a
    conversation "[s]ometime before November 26" in which Takamol
    supposedly informed Fullbridge "that the scope of Wave 3 was being
    reduced" by some unspecified amount.            For one thing, there is no
    evidence establishing that this conversation, if it occurred at
    all, took place before the November 23 cut-off date.            For another
    thing, the allusion is untimely:        Paraflon never argued below that
    this conversation either should have been disclosed or was in some
    way revelatory of Fullbridge's state of mind.9              Arguments not
    raised below are typically deemed abandoned, see Teamsters 
    Union, 953 F.2d at 21
    , and so it is here.
    9
    In a post-argument letter purporting to pinpoint a place in
    the record where such an argument was raised below, Paraflon
    gestured only to a trial exhibit — buried in a voluminous record
    — which references this conversation. That unelaborated reference
    does not advance Paraflon's cause. To preserve an argument "for
    appeal, some developed argumentation must be put forward in the
    nisi prius court." B & T Masonry Constr. Co. v. Pub. Serv. Mut.
    Ins. Co., 
    382 F.3d 36
    , 40 (1st Cir. 2004). The obligation to spell
    out an argument clearly and distinctly is not satisfied by inviting
    the trial court "to ferret out an evanescent needle from an
    outsized paper haystack."    Rivera-Gomez v. de Castro, 
    843 F.2d 631
    , 635 (1st Cir. 1988).
    - 28 -
    This leaves two other events that Paraflon suggests the
    district court may have overlooked.          The first such event is a
    November 9 e-mail from Ramón Rivera, Fullbridge's chief financial
    officer, acknowledging that Fullbridge had been unable to secure
    confirmation of the Wave 3 award from Takamol.             The second is
    Takamol's November 11 e-mail telling Fullbridge that it was "on
    the final stages to finalize wave III awarding," which it expected
    to be completed shortly.      Despite Paraflon's self-serving attempt
    to characterize these events as missing pieces of the puzzle, the
    record reflects that they were part and parcel of the district
    court's decisional calculus.
    With respect to the November 9 e-mail, the district court
    made a specific factual finding and cited that finding twice when
    rendering its conclusions.      See Paraflon, 
    2019 WL 3759522
    , at *4,
    *11.    And even though the district court did not make a specific
    finding concerning the November 11 e-mail, it heard testimony that
    Fullbridge understood Takamol's statement about "finaliz[ing] wave
    III awarding" as a reference only to the finalization of the second
    layer of Wave 3 details.       We do not assume "that the trial judge
    slept through the trial" simply because his opinion does not
    explicitly address every scintilla of evidence.          Richard v. Reg'l
    Sch. Unit 57, 
    901 F.3d 52
    , 59 (1st Cir. 2018).            As long as the
    trial   court   makes   the   basis   for   its   disposition   of   a   case
    reasonably clear, it is not obliged to respond, piece by piece, to
    - 29 -
    each evidentiary fragment.           See Nevor v. Moneypenny Holdings, LLC,
    
    842 F.3d 113
    , 119 (1st Cir. 2016).                We think that this tenet
    effectively disposes of any contention that the district court
    committed reversible error by failing to comment specifically on
    the November 11 e-mail.          See 
    Richard, 901 F.3d at 59
    (observing
    that trial court need not "expressly respond like a debate champion
    to every evidentiary or factual contention made by the losing
    side").
    Next, Paraflon challenges the scope of the district
    court's state-of-mind findings.            Paraflon insists that the court
    only made findings about Fullbridge's subjective belief in a $40
    million     contract,        without     inquiring     into     the     objective
    reasonableness of that belief.          Specifically, Paraflon argues that
    for purposes of its negligent misrepresentation claims, the court
    ought to have inquired into what Fullbridge "should have known."
    
    Anschutz, 690 F.3d at 114
    (quoting Hydro Inv'rs, Inc. v. Trafalgar
    Power, Inc., 
    227 F.3d 8
    , 20 (2d Cir. 2000)).
    This argument is fruitless:              it ignores the district
    court's unequivocal finding that there was insufficient proof that
    Fullbridge "should . . . have known" that its representation about
    the contract was "inaccurate at the time it was made."                  Paraflon,
    
    2019 WL 3759522
    ,    at    *12.     Here,    moreover,     that    finding   was
    buttressed by other findings that Fullbridge "reasonably believed"
    that it had received the award and that it had "a good faith basis
    - 30 -
    for representing . . . [it] had been awarded $40 million of
    business over three years."
    Id. at *11
    .      And as we have explained,
    a    holistic     evaluation     of   the   court's      state-of-mind      findings
    reveals an implicit finding that Fullbridge maintained this good-
    faith belief through November 23.                See
    id. Seen in
    this light,
    the futility of Paraflon's plaint that the district court failed
    to     evaluate    the    objective       reasonableness        component   of    its
    negligent misrepresentation claims becomes starkly apparent.
    Paraflon also asserts that the district court dispensed
    with    its   fraud      claim   "based     on   a    cramped     understanding   of
    scienter," accusing the court of focusing exclusively on whether
    Fullbridge        intentionally       induced        Paraflon's     investment     by
    knowingly misrepresenting the existence of a $40 million contract.
    In Paraflon's estimation, the court utterly failed to assess
    whether Fullbridge acted with reckless disregard for the truth.
    See Bd. of Educ. v. Sargent, Webster, Crenshaw & Folley, 
    539 N.Y.S.2d 814
    , 820 (App. Div. 1989); Burgundy Basin Inn, Ltd. v.
    Watkins Glen Grand Prix Corp., 
    379 N.Y.S.2d 873
    , 879 (App. Div.
    1976). Once again, the district court's findings refute Paraflon's
    assertions.
    Most importantly, the district court twice rebuffed the
    notion that Fullbridge acted recklessly by representing that it
    had a $40 million contract with Takamol.                   See Paraflon, 
    2019 WL 3759522
    , at *11.         Although the court did not use the buzz words
    - 31 -
    that Paraflon touts — in particular, it did not comment upon
    whether Fullbridge made only a "pretense of knowledge," DiRose v.
    PK   Mgmt.   Corp.,   
    691 F.2d 628
    ,   632     (2d    Cir.    1982)   (quoting
    Ultramares Corp. v. Touche, 
    174 N.E. 441
    , 444 (N.Y. 1931)); Bd. of
    
    Educ., 539 N.Y.S.2d at 820
        —    its    findings       that   Fullbridge
    "reasonably believed" that it had received the award and "had a
    good    faith    basis"   for    its    representation         to    Paraflon    fairly
    encompass this point, Paraflon, 
    2019 WL 3759522
    , at *11.                        While a
    trial    court    sitting   without       a    jury    must    make    its    findings
    reasonably clear, there is no general requirement that it use
    particular words or pet phrases in performing such a task.                          Cf.
    Valsamis v. González-Romero, 
    748 F.3d 61
    , 63 (1st Cir. 2014)
    (observing, in context of a Federal Rule of Civil Procedure
    52(a)(1) challenge, that "substance trumps form").
    Endeavoring to change the trajectory of the debate,
    Paraflon submits that to the extent the district court reached
    "bare    conclusion[s]"         about     objective       reasonableness,         those
    conclusions are so tersely stated and thinly supported that they
    frustrate meaningful judicial review.                 We do not agree:        the basis
    for the challenged findings is readily apparent from context.                      For
    example, the court discussed, in close proximity to its findings
    about objective reasonableness, Takamol's statements in the August
    17 meeting, Takamol's averment that the Master Agreement would
    govern Fullbridge's work on Wave 3, Takamol's "performance first
    - 32 -
    and paper later" philosophy, and what it found to be the "credible
    testimony"        of   Fullbridge     representatives.          Paraflon,       
    2019 WL 3759522
    , at *11. The court also made pellucid that it had factored
    into the mix Fullbridge's struggle to secure written confirmation
    of the Wave 3 award, Fullbridge's activities from and after August,
    and AlHashimi's repeated assurances that the Wave 3 deal remained
    viable.        See
    id. No more
    was exigible.               Following a bench trial, a
    district court "need only make brief, definite, pertinent findings
    and conclusions."              Fed. R. Civ. P. 52(a), advisory committee's
    note to 1946 amendment.                   "[T]here is no necessity for over-
    elaboration of detail or particularization of facts."
    Id. Where, as
      here,      "'the    district     court's       decision   contains   sufficient
    findings and reasoning to make plain the basis for its disposition
    of the case,' we pay little heed to claims that it should have
    done more."        
    Richard, 901 F.3d at 59
    (quoting 
    Valsamis, 748 F.3d at 63
    ).        We are especially reluctant to entertain such claims when
    —    as   in    this    case    —   the   complaining     party   never    moved       for
    additional findings under Federal Rule of Civil Procedure 52(b).
    See Irving Tanning Co. v. Kaplan, 
    876 F.3d 384
    , 390 (1st Cir.
    2017).
    The upshot is that the court below made its findings
    reasonably clear — certainly clear enough to permit meaningful
    appellate review.          No useful purpose would be served by requiring
    - 33 -
    it to add hues to a sufficiently vivid rainbow.                We do pause,
    however, to address Paraflon's repeated references to the district
    court's suggestion that Fullbridge "may have" engaged in "a heaping
    ration of wishful thinking" when forming its belief that it had
    landed the $40 million contract.         Paraflon, 
    2019 WL 3759522
    , at
    *11.   This remark simply cannot bear the analytical import that
    Paraflon attempts to attribute to it.              In fairness, the remark
    must   be   read   in   conjunction   with   the    court's   findings   that
    throughout the relevant period, Fullbridge maintained a sincere
    and objectively reasonable belief in the $40 million award.               See
    id. at *11
    -12.     Such an integrated reading makes luminously clear
    the court's view that although Fullbridge may have indulged some
    wishful thinking, it nonetheless operated under a reasonable,
    good-faith belief in its securing of the $40 million award.               See
    id. The last
    leg of our journey takes us to Paraflon's
    asseveration that no objectively reasonable person could have
    thought, as late as November 23, that Fullbridge had a $40 million
    award from Takamol. We review factual findings related to scienter
    and objective reasonableness for clear error.            See 
    Calandro, 919 F.3d at 36
    ; Brotherston v. Putnam Invs., LLC, 
    907 F.3d 17
    , 27 (1st
    Cir. 2018), cert. denied, 
    140 S. Ct. 911
    (2020); Healey v. Chelsea
    Res., Ltd., 
    947 F.2d 611
    , 618 (2d Cir. 1991); ACA Fin. Guar. Corp.
    v. Goldman, Sachs & Co., 
    15 N.Y.S.3d 764
    , 766 (App. Div. 2015).
    - 34 -
    We conclude that the court below did not clearly err in finding
    that Fullbridge reasonably believed it had been awarded a $40
    million slice of Wave 3.       Nor did the court commit clear error in
    finding that Fullbridge did not act recklessly by representing to
    investors that it had received a $40 million award.                    We explain
    briefly.
    The   district     court's   state-of-mind      findings,       fairly
    construed, rest largely on its decision to credit the trial
    testimony of the Olsons and other Fullbridge witnesses. Of central
    importance, the court gave credence to the Olsons' testimony that
    Takamol informed Fullbridge it had been awarded a sizable portion
    of the Wave 3 project, agreed to the broad terms of a deal
    (amounting to a projected $40 million in revenue), and left open
    for negotiation a second layer of more granular details within
    that broad framework.       So, too, the court credited testimony that
    Fullbridge's     past   working     relationship      with        Takamol      was
    characterized    by   Takamol's   "perform    now,   paper    later"       ethos,
    resulting in Fullbridge's commencement of work on Wave 1 before
    the execution of the Master Agreement and on other projects months
    before the issuance of formal work orders.                Finally, the court
    credited testimony that Takamol had informed Fullbridge that the
    Master   Agreement    would   govern    its   work   on    Wave    3    and   that
    Fullbridge believed it would not be required to negotiate a new
    Framework Agreement.
    - 35 -
    Paraflon views much of this testimony with a jaundiced
    eye, regarding it as suspect and in tension with its interpretation
    of the documentary evidence.              But credibility determinations are,
    within   wide       limits,    grist     for   the   trial       court's    mill.     See
    
    Calandro, 919 F.3d at 35
    .              As we repeatedly have said, "weighing
    the evidence and assessing the witnesses' credibility is uniquely
    the province of the district court."                 Fed. Refinance Co. v. Klock,
    
    352 F.3d 16
    , 29 (1st Cir. 2003).
    Nor       does     Paraflon's       reliance     on     various    items    of
    documentary evidence get it very far.                      Much of the documentary
    evidence   to       which     Paraflon    points      is    capable    of    supporting
    competing inferences relating to Fullbridge's state of mind at the
    time of Paraflon's November 23 investment. A few examples suffice:
        Fullbridge's internal minutes from the August 17
    meeting and associated e-mails could support an
    inference that Fullbridge understood (or should
    have     understood)       that       the    parties     had     only
    discussed a tentative pricing benchmark that was
    entirely dependent on further negotiations.                    But by
    the same token, these minutes could be viewed as
    consistent with the Olsons' testimony that the
    parties had reached a firm agreement on broad terms
    and left open only a second layer of granular
    details within that framework.
    - 36 -
        Takamol's      evasion       of    Fullbridge's      requests     for
    written confirmation of the Wave 3 award could be
    viewed as foreboding signs that its representations
    on    August    17     had    been    far     from    ironclad        or
    conversely      (as     the       Olsons    testified      and    the
    district court apparently found) could be viewed as
    altogether      typical       manifestations         of   Takamol's
    modus operandi (perform now, paper later).
        Competing inferences could also be gleaned from
    Peter Olson's October 20 e-mail seeking "a sense of
    the   exact     timing       and    courses     designated"       and
    Takamol's October 22 response stating that although
    "things [were] moving in the right direction," it
    could not give a specific timetable for Wave 3; the
    e-mails surrounding Takamol's October 24 proposal
    for a buffer order and fixed price agreement; and
    Takamol's November 11 e-mail stating that it was
    "on    the     final     stages      to     finalize      wave    III
    awarding."
    The short of it is that, on this scumbled record,
    rational factfinders could have reached different conclusions
    about whether it was objectively reasonable for Fullbridge to
    believe (and, thus, represent) that it had a $40 million award for
    Wave   3   as   of   November       23.      Which      conclusion     appealed       to    a
    - 37 -
    particular factfinder would depend largely on how the factfinder
    viewed    not   only   Fullbridge's      explanation       of   the   documentary
    evidence but also the credibility of various witnesses.                    Thus, the
    case at hand falls squarely within the maxim that when a factfinder
    is confronted by "two permissible views of the evidence," the
    "choice    between     those      competing   views        cannot     be    clearly
    erroneous."
    Id. It was
    for the district court to weigh the
    evidence and decide whether Fullbridge should have realized, on or
    before November 23, that its representations about a $40 million
    award were overly optimistic.            So, too, it was for the district
    court to decide whether Fullbridge acted with fraudulent intent,
    a   reckless    disregard   for    the   truth,   or   a    false     pretense   of
    knowledge by making these representations.                  The district court
    acquitted its responsibilities adequately, and its findings pass
    muster under clear-error review.
    III. CONCLUSION
    We need go no further.          The decisive question here is
    not whether we, if writing on a pristine page, would have resolved
    this dispute in the same way as the district court.                 What matters,
    we think, is that we discern no clear error in the district court's
    determination that, as of November 23, Fullbridge had a good-faith
    belief that it had received the lucrative award from Takamol.                    Of
    equal significance, we discern no clear error in the district
    court's determination that Fullbridge's good-faith belief was
    - 38 -
    objectively reasonable based on its experience with Takamol and
    what it knew at the time of Paraflon's investment.   Given these
    determinations and the impotence of Paraflon's various claims of
    error, the judgment of the district court must be
    Affirmed.
    - 39 -
    

Document Info

Docket Number: 19-1913P

Filed Date: 5/26/2020

Precedential Status: Precedential

Modified Date: 5/26/2020

Authorities (19)

Dudley v. Hannaford Bros , 333 F.3d 299 ( 2003 )

United States v. 15 Bosworth Street , 236 F.3d 50 ( 2001 )

Federal Refinance Co. v. Klock , 352 F.3d 16 ( 2003 )

Crellin Technologies, Inc. v. Equipmentlease Corp. , 18 F.3d 1 ( 1994 )

T I Federal Credit Union v. DelBonis , 72 F.3d 921 ( 1995 )

Wilma Cumpiano A/K/A Wilma Cumpiano Sanchez v. Banco ... , 902 F.2d 148 ( 1990 )

B & T Masonry Construction Co. v. Public Service Mutual ... , 382 F.3d 36 ( 2004 )

Ahern v. Scholz , 85 F.3d 774 ( 1996 )

John A. Healey, Michael S. Press v. Chelsea Resources, Ltd.,... , 947 F.2d 611 ( 1991 )

Teamsters, Chauffeurs, Warehousemen and Helpers Union, ... , 953 F.2d 17 ( 1992 )

State Police Association of Massachusetts v. Commissioner ... , 125 F.3d 1 ( 1997 )

Ronald Borden v. The Paul Revere Life Insurance Company, ... , 935 F.2d 370 ( 1991 )

Martin Rivera-Gomez v. Rafael Adolfo De Castro , 843 F.2d 631 ( 1988 )

Chao v. Hotel Oasis, Inc. , 493 F.3d 26 ( 2007 )

J. Richard Dirose v. Pk Management Corp., Nicholas A. ... , 691 F.2d 628 ( 1982 )

Merrill Lynch & Co. Inc. v. Allegheny Energy, Inc. , 500 F.3d 171 ( 2007 )

hydro-investors-inc-plaintiff-counter-defendant-appellant-lawrence , 227 F.3d 8 ( 2000 )

sanford-brass-joyce-mericle-brass-gustave-e-chew-fred-suther-john , 987 F.2d 142 ( 1993 )

Creative Waste Management, Inc. v. Capitol Environmental ... , 429 F. Supp. 2d 582 ( 2006 )

View All Authorities »