Axia NetMedia Corporation v. Mass. Technology Park Corp. ( 2020 )


Menu:
  •             United States Court of Appeals
    For the First Circuit
    No. 19-1649
    AXIA NETMEDIA CORPORATION,
    Plaintiff, Appellant,
    KCST USA, INC.,
    Plaintiff,
    v.
    MASSACHUSETTS TECHNOLOGY PARK CORPORATION,
    d/b/a Massachusetts Technology Collaborative,
    Defendant, Appellee.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Timothy S. Hillman, U.S. District Judge]
    Before
    Howard, Chief Judge,
    Lipez, Circuit Judge,
    and Saris, U.S. District Judge.*
    Brian P. Voke, with whom Adam A. Larson and Campbell Conroy
    & O'Neil, P.C. were on brief, for appellant.
    Robert J. Kaler, with whom Edwin L. Hall and Holland & Knight
    LLP were on brief, for appellee.
    *   Of the District of Massachusetts, sitting by designation.
    August 31, 2020
    - 2 -
    LIPEZ,   Circuit    Judge.      Massachusetts        Technology          Park
    Corporation,     an    independent      public        instrumentality        of       the
    Commonwealth     of     Massachusetts          operating         under     the        name
    Massachusetts Technology Collaborative ("MTC"), owns a fiber-optic
    network in western Massachusetts known as the Massbroadband123
    Network.     Before the network was built, MTC contracted with Axia
    NGNetworks USA, Inc. -- now called KCST USA, Inc. ("KCST") -- to
    operate and market the network.              MTC also secured a guaranty of
    KCST's obligations under the contract from KCST's parent company,
    Axia NetMedia Corporation ("Axia").
    The relationship between MTC and Axia deteriorated after
    the network was built.           Axia ultimately sued MTC in federal
    district court over the guaranty agreement and MTC procured an
    order   compelling     arbitration      of     the    parties'     dispute.           The
    arbitrator found that MTC had materially breached the underlying
    contract with KCST, and, accordingly, that the guaranty agreement
    was void for failure of consideration.                Axia sought confirmation
    of   the   arbitration     award    while      MTC,       dissatisfied     with       the
    arbitrator's    decision,    sought      vacatur      or    modification         of   the
    arbitration award under section 10 of the Federal Arbitration Act
    ("FAA"), 9 U.S.C. § 10(a).         The district court concluded that the
    arbitrator     had    exceeded   the    scope        of    his   powers,    see
    id. § 10(a)(4), and
    vacated the portion of the arbitration award that
    voided the guaranty.      Axia has appealed that decision.
    - 3 -
    Concluding that the arbitrator acted within the scope of
    his powers, we reverse and remand with instructions to enter an
    order confirming the arbitration award.
    I.
    We begin by providing background about the relevant
    provisions of the contracts between MTC and KCST and between MTC
    and Axia, the breakdown of the relationship among MTC, KCST, and
    Axia, and the arbitrator's and district court's decisions.            This
    is not the first time that the dispute between MTC and Axia has
    come before us.   See Axia NetMedia Corp. v. Mass. Tech. Park Corp.
    (hereinafter   Axia I), 
    889 F.3d 1
    (1st Cir. 2018) (affirming
    preliminary injunction as modified); see also Axia NetMedia Corp.
    v. Mass. Tech. Park Corp., Nos. 18-2180, 18-2192, 
    2019 WL 2273650
    (1st Cir. Apr. 9, 2019) (dismissing appeals from district court
    orders denying Axia's motion to execute on preliminary injunction
    bond).   We draw background facts from our prior published opinion
    where appropriate.
    A.    The Contracts
    In 2010, MTC received state and federal funding to build
    the   Massbroadband123   Network    to   provide   high   speed   broadband
    service to underserved communities in western and north central
    Massachusetts.    Shortly before the funding was approved, MTC
    solicited proposals from telecommunications companies to operate
    and market the soon-to-be-built network.       Axia, a Canadian company
    - 4 -
    seeking to expand into the United States market, submitted a bid
    on behalf of its newly created United States subsidiary, KCST.
    MTC selected KCST to be the network operator.              On February 25,
    2011, MTC and KCST entered into the Agreement for Network Operator
    Services (the "Network Operator Agreement" or "NOA"), and MTC and
    Axia entered into the Guaranty Agreement (the "Guaranty") that is
    at issue in this appeal.
    Under the terms of the NOA, MTC was responsible for
    constructing the network1 and turning it over to KCST in segments.
    The planned network, as described in the NOA, would be "a 1,338-
    mile fiber-optic network with new fiber running through or near
    124 communities in western and north central Massachusetts" that
    connected to 1,392 Community Anchor Institutions ("CAIs").             CAIs
    are   state    or   community   facilities,   like    schools,   libraries,
    hospitals and police departments.       These facilities "are directly
    connected to the network[ and] serve as hubs of connectivity for
    extending the network to other customers."           Axia 
    I, 889 F.3d at 5
    .
    The NOA defines a CAI as "any one of the organizations and agencies
    identified in" a list that was appended to the NOA, which was
    subject to revision by MTC "from time to time in MTC's sole
    discretion."
    1MTC contracted with another company, G4S Technology LLC, to
    design and construct the network.
    - 5 -
    The NOA details the many responsibilities that KCST
    agreed to assume as the "Network Operator."              In short, KCST was
    "responsible for all aspects of the management, sales, monitoring,
    operations, support, and maintenance of" the Massbroadband123
    Network.      Also, it was responsible for "pay[ing] for all ongoing
    costs of operating" the network "and all costs of compliance with
    the terms of" the NOA.            KCST, additionally, paid an annual fee to
    MTC.     "In return, KCST retained the network's revenue up to a
    defined threshold, above which it agreed to share the revenue with
    MTC."      Axia 
    I, 889 F.3d at 4
    .
    By its express terms, the NOA would not take effect until
    Axia signed the Guaranty:
    12.14     Parent Guaranty.    This Agreement
    [the NOA] shall become binding only upon
    condition that Network Operator's parent
    company, Axia NetMedia Corporation, executes
    and delivers to MTC a guaranty of obligations
    of Network Operator hereunder in a form
    acceptable to MTC, with a limit of liability
    no less than four million ($4,000,000) U.S.
    dollars.
    In the Guaranty, Axia promised that, should KCST "default in any
    of   its    payment    or    performance   obligations   under   the    Network
    Operator Agreement," Axia would "make all such payments and perform
    all such obligations of the Network Operator" under the NOA, and
    would "fully and punctually pay and discharge . . . any and all
    costs,      expenses        and    liabilities"   associated     with     those
    obligations. The Guaranty was "limited to and capped at the amount
    - 6 -
    of" $4 million and it provided that, should Axia "advance to MTC
    funds up to said amount, [Axia] shall have no further obligation
    or liability under this Agreement."
    The Guaranty also provided that its validity would be
    unaffected by potential breaches of the NOA by KCST:
    2.3 This    Agreement    and   the   liability
    hereunder shall not be affected or impaired by
    any compromise, settlement, release, renewal,
    extension,    indulgence,    change    in   or
    modification of any of the obligations and
    liabilities of Network Operator under the
    Network Operator Agreement, or by any failure
    on the part of MTC, its successors or assigns,
    to realize upon any obligations or liabilities
    of Network Operator.
    The Guaranty said nothing about what effect, if any, potential
    breaches of the NOA by MTC would have on its continuing validity.
    Finally, both the NOA and the Guaranty address dispute
    resolution.      The NOA provides that any dispute between MTC and
    KCST that cannot be resolved through informal dispute resolution
    procedures      "will   be    finally    settled      by    binding   arbitration
    conducted     in    accordance      with        the    [American      Arbitration
    Association] Rules."         Under the Guaranty, all disputes between MTC
    and Axia that could not be resolved in mediation would "be resolved
    by litigation in a court serving Middlesex County, Massachusetts,"
    unless   "MTC    elect[ed]      arbitration      as   the    method   of   dispute
    resolution for a given dispute."           The Guaranty provides that, "at
    MTC's sole election, MTC may file a demand for arbitration by the
    - 7 -
    American Arbitration Association in its office serving Boston,
    Massachusetts."       (Emphasis added.)
    B.    Factual and Procedural Background2
    The construction of the network did not go as planned.
    The NOA required MTC to deliver the network to KCST in segments,
    as it was completed, with all thirty-six segments being turned
    over to KCST no later than August 25, 2013.                 MTC delivered only
    one network segment to KCST by that date.              MTC then turned over
    more than half of the network at once in late December 2013 and
    the remaining segments in early 2014.               In addition, the network
    was smaller in size and scope than the NOA contemplated, with fewer
    than the anticipated 1,392 CAIs connected to it.3
    KCST   initially    responded     to   MTC's    delays   and   other
    shortfalls by asking MTC to renegotiate the commercial terms of
    the   NOA.     When    those    negotiations    proved      unsuccessful,   KCST
    threatened to withhold payments due MTC, which MTC relied upon to
    2We draw the background information primarily from the
    arbitration award, as the parties are bound by the arbitrator's
    view of the facts. See United Paperworkers Int'l Union v. Misco,
    Inc., 
    484 U.S. 29
    , 37-38 (1987).
    3The parties dispute the number of CAIs that were connected
    to the network at the time it was turned over to KCST, with
    estimates ranging from 901 on the low end to 1,225 on the high
    end. The arbitrator did not resolve this factual dispute but found
    that, "[a]ccepting any of the[] numbers from either side as
    accurate, it is plain that MTC had a material shortfall in its
    failure to deliver connected CAIs reasonably approaching" the
    promised 1,392 in total.
    - 8 -
    pay for overhead and other network-related costs.             MTC promptly
    sought and obtained a preliminary injunction in Massachusetts
    Superior    Court    in   mid-2014    requiring   KCST   to   perform   its
    obligations under the NOA, including making payments to MTC.
    For the next two years, KCST performed its obligations
    under the NOA, but it was losing money and required loans from
    Axia to meet the demand on its financial resources.            Then, "[i]n
    2016, a Swiss investment firm acquired a controlling position in
    Axia."     Axia 
    I, 889 F.3d at 5
    .        To facilitate approval of the
    acquisition by the Federal Communications Commission ("FCC") --
    required because the FCC had authorized KCST to operate the network
    -- Axia transferred all KCST shares into a trust, see
    id., of which Axia
    was the sole beneficiary.          KCST retained its original name
    -- Axia NGNetworks USA, Inc. -- at that time, but changed its name
    to KCST USA, Inc. in February 2017.
    On March 22, 2017, KCST filed a voluntary petition for
    Chapter 11 bankruptcy, an "Event of Default" that triggered Axia's
    obligations under the Guaranty. On the same day, Axia preemptively
    filed this lawsuit against MTC in federal district court, seeking
    a declaratory judgment that the Guaranty was unenforceable because
    MTC had materially breached the NOA.          MTC secured a preliminary
    injunction, which required Axia to perform its obligations under
    the Guaranty while the parties resolved their contract dispute.
    See
    id. at 4.
          And, as we noted at the outset, MTC successfully
    - 9 -
    moved to compel arbitration of the dispute with Axia pursuant to
    the dispute resolution provision in the Guaranty.
    Also, before the bankruptcy court, MTC filed a proof of
    claim against KCST's bankruptcy estate seeking damages for alleged
    breaches of the NOA by KCST. KCST, in turn, commenced an adversary
    proceeding against MTC, objecting to MTC's claim and asserting
    counterclaims against MTC for its alleged breaches of the NOA.
    MTC filed a motion to compel arbitration of the competing claims,
    which the bankruptcy court granted. The arbitration of the dispute
    between MTC and KCST was then consolidated with the arbitration
    proceedings between MTC and Axia, which were already underway.4
    The arbitration proceedings were conducted before a sole
    arbitrator, who received documentary evidence from the parties and
    heard twenty-seven days of live testimony.5   The arbitrator issued
    his decision in the fall of 2018 in three parts: the Partial Final
    Award ("PFA"), the Final Award and Modification of Partial Final
    Award, and the Modification of Final Award.
    4 Although the arbitration proceedings were consolidated, the
    two disputes arose from different contracts and originated in
    different fora. They retained their separate identities, and the
    arbitrator's resolution of each dispute thus needed to be confirmed
    in the forum where it originated after the arbitration proceedings
    concluded.
    5 MTC raises issues with the arbitrator selection process in
    the factual background section of its brief but does not later
    argue that those issues provide a basis to vacate the arbitrator's
    award. We therefore do not address them.
    - 10 -
    In the PFA, the arbitrator found that "MTC failed to
    deliver a network within a reasonable range of the 1,392 CAIs that
    it contracted to provide under the NOA," that it "failed to
    'connect' a significant number of CAIs" to the network, and that
    it "failed to comply with its obligations to deliver the Network
    in a timely manner and in segments to achieve a cost-effective
    rollout."    The arbitrator concluded that these failures amounted
    to a material breach of the NOA.6
    As to remedy, the relief granted to KCST "for MTC's
    breach [wa]s that of reformation of the NOA" to make the terms of
    the contract commercially reasonable in light of MTC's "failed
    Network delivery obligations."7 The arbitrator also granted relief
    6 The arbitrator also found misconduct on the part of KCST
    and Axia.   Most notably, during the time leading up to KCST's
    bankruptcy filing, the companies failed to disclose to MTC that
    KCST had stopped paying network vendors (to the tune of hundreds
    of thousands of dollars of unpaid obligations) and that it was in
    dire economic straits. As a result, "the surprise attack of the
    KCST    bankruptcy     filing    and    Axia     federal    court
    litigation . . . combined to achieve maximized impact, as they
    were surely calculated to do." But the arbitrator concluded that
    KCST and Axia "escape[d] the consequences of these wrongful
    actions" because MTC accepted "curing performance" by Axia and
    because MTC failed to prove any damage caused by the delay in
    disclosure of KCST's financial situation.
    7 The arbitrator explained that reformation of the NOA was an
    appropriate remedy based on both the language of the NOA and the
    record. Specifically, the arbitrator relied on section 5.2.7 of
    the NOA, in which MTC promised to cooperate with KCST to "effect
    the goals, objectives and purposes" of the contract "in a
    commercially reasonable manner."     The arbitrator also observed
    that "the record reflects that at the time of [MTC's] breach [KCST]
    did not seek to terminate and claim damages, but rather it . . .
    - 11 -
    to Axia, observing that "the underlying consideration for the Axia
    Guaranty was the NOA, and MTC materially breached it."             As a
    result, "MTC was not entitled to the benefits it secured" pursuant
    to the district court's preliminary injunction order requiring
    Axia's continued performance of its obligations under the Guaranty
    while the parties' dispute was ongoing.      Thus, Axia was "entitled
    to recoup" from MTC over $4 million in costs that it had incurred
    in connection with the preliminary injunction order.
    After the arbitrator issued the PFA, MTC asked the
    arbitrator to clarify "the meaning of the PFA as to the continued
    effectiveness of the Guaranty . . . going forward."        MTC explained
    that Axia understood the PFA to mean that the Guaranty was "'void'
    going forward," but that MTC disagreed with that interpretation.
    MTC insisted that the Guaranty remained valid, and that "the effect
    of MTC making the payments to Axia required by the PFA would be to
    reinstate the full value of the Guaranty."        In other words, MTC
    argued,   "the   $4   million   limitation   on   Axia's    performance
    obligations would be reset" when MTC made the required payments to
    Axia.
    In response to MTC's request for clarification, the
    arbitrator specified in the Final Award and Modification of Partial
    continued to seek financially adjusted terms for ongoing
    performance of the NOA." The arbitrator treated that choice by
    KCST as an "election of remedies."
    - 12 -
    Final Award that "MTC lost on its request for declaratory relief
    with respect to the continued validity of the Guarant[y], as
    reflected in . . . the PFA."                    The arbitrator explained that this
    result was justified under Massachusetts law because "the breach
    by     MTC    found    in    the    PFA    went       at   once    to    the   'essence'    or
    'foundation'          of    the    NOA    and    underlying       consideration     of     the
    Guarant[y]."          In addition, the arbitrator found that MTC had not
    met its burden to prove that, if the parties had independently
    renegotiated          the    contract,          MTC    would      have    conditioned      its
    acceptance of the reformed NOA on the execution of a new guaranty
    agreement by Axia. Since "the record was simply devoid of specific
    persuasive evidence in this regard," the arbitrator concluded, MTC
    could not prevail on the issue.
    MTC and Axia returned to the district court, where Axia
    moved for confirmation of the arbitration award and MTC moved to
    vacate it insofar as it voided the Guaranty, arguing that the
    arbitrator had acted outside the scope of his authority in doing
    so.8        As we recounted above, the district court agreed with MTC
    and granted MTC's motion to partially vacate the arbitration award.
    II.
    We apply de novo review to a district court's decision
    to confirm or vacate an arbitration award.                         Dialysis Access Ctr.,
    8
    KCST secured confirmation in the bankruptcy court of the
    portion of the arbitration award that reformed the NOA.
    - 13 -
    LLC v. RMS Lifeline, Inc., 
    932 F.3d 1
    , 7 (1st Cir. 2019).   In doing
    so, however, we are mindful that "[t]he authority of a federal
    court to disturb an arbitration award is tightly circumscribed."
    Cytyc Corp. v. DEKA Prods. Ltd. P'ship, 
    439 F.3d 27
    , 32 (1st Cir.
    2006).   After all, "the parties have contracted to have disputes
    settled by an arbitrator chosen by them rather than by a judge,"
    and thus "it is the arbitrator's view of the facts and of the
    meaning of the contract that they have agreed to accept."    United
    Paperworkers Int'l Union v. Misco, Inc., 
    484 U.S. 29
    , 37-38 (1987).
    Although our review is limited, "arbitration awards are
    not invincible, and there are 'a few exceptions to the general
    rule that arbitrators have the last word.'"       Hoolahan v. IBC
    Advanced Alloys Corp., 
    947 F.3d 101
    , 111 (1st Cir. 2020) (quoting
    Cytyc 
    Corp., 439 F.3d at 32-33
    ).   Under section 10(a) of the FAA,
    federal courts are authorized to vacate an arbitral award only
    when (1) "the award was procured by corruption, fraud, or undue
    means," (2) "there was evident partiality or corruption" on the
    part of the arbitrator, (3) the arbitrator is guilty of misconduct
    that prejudices the rights of a party, including refusing to
    postpone the hearing when sufficient cause has been shown and
    refusing to hear evidence that is "pertinent and material to the
    controversy," or (4) the arbitrator "exceeded [his] powers, or so
    imperfectly executed them that a mutual, final, and definite award
    - 14 -
    upon the subject matter submitted was not made." 9 U.S.C. § 10(a).9
    Only the claim that the arbitrator exceeded his powers is at issue
    in this appeal.
    An    arbitrator's   decision   may    be   vacated   when   the
    arbitrator "strays from interpretation and application of the
    agreement and effectively 'dispense[s] his own brand of industrial
    justice.'"        Stolt-Nielsen S.A. v. AnimalFeeds Int'l Corp., 
    559 U.S. 662
    , 671 (2010) (alteration in original) (quoting Major League
    Baseball Players Ass'n v. Garvey, 
    532 U.S. 504
    , 509 (2001) (per
    curiam)).     In so doing, an arbitrator acts outside the scope of
    his "contractually delineated powers."             First State Ins. Co. v.
    Nat'l Cas. Co., 
    781 F.3d 7
    , 11 (1st Cir. 2015).           If, however, the
    9 We have also recognized in earlier case law "a second set
    of exceptions [that] flows from the federal courts' inherent power
    to vacate arbitral awards." 
    Hoolahan, 947 F.3d at 111
    (quoting
    Cytyc 
    Corp., 439 F.3d at 33
    ). This "very narrow" authority, Cytyc
    
    Corp., 439 F.3d at 33
    , arises in cases where the arbitrator acted
    "in manifest disregard of the law," Advest, Inc. v. McCarthy, 
    914 F.2d 6
    , 9 n.6 (1st Cir. 1990); see also
    id. at 9-10;
    Hoolahan, 947
    F.3d at 111
    .      The Supreme Court's decision in Hall Street
    Associates, L.L.C. v. Mattel, Inc., 
    552 U.S. 576
    (2008), however,
    cast doubt on "[t]he availability of non-statutory grounds to
    vacate an arbitration award." 
    Hoolahan, 947 F.3d at 111
    n.14; see
    Hall 
    Street, 552 U.S. at 584-87
    ("[T]he text [of the FAA] compels
    a reading of the §§ 10 and 11 categories [for vacating and
    modifying arbitration awards] as exclusive.").       We "have not
    squarely determined whether our manifest disregard case law can be
    reconciled with Hall Street," Kashner Davidson Sec. Corp. v.
    Mscisz, 
    601 F.3d 19
    , 22 (1st Cir. 2010); see also 
    Hoolahan, 947 F.3d at 111
    n.14, and we need not do so here. The district court
    did not rely on the manifest disregard doctrine, see Axia NetMedia
    Corp. v. Mass. Tech. Park Corp., 381 F. Supp.3d 128, 134 n.4 (D.
    Mass. 2019), and MTC does not argue that the doctrine provides a
    distinct basis for affirming the district court's decision.
    - 15 -
    award "'draw[s] its essence from the contract' that underlies the
    arbitration proceeding" and the arbitrator was "even arguably
    construing or applying the contract and acting within the scope of
    [his] authority," the award must stand -- even if the arbitrator
    committed serious legal or factual error.         Cytyc 
    Corp., 439 F.3d at 32
    (quoting 
    Misco, 484 U.S. at 38
    ).          MTC bears the burden "to
    establish   that   the   arbitrator's   award    should   be   set   aside."
    
    Hoolahan, 947 F.3d at 110
    (quoting Dialysis Access 
    Ctr., 932 F.3d at 7
    ).
    We note the limited scope of MTC's claim.          The question
    of whether the arbitrator exceeded his powers by reforming the NOA
    is not before us, nor was it before the district court.              Just as
    the district court ordered MTC and Axia to resolve their contract
    dispute over the Guaranty through arbitration, the bankruptcy
    court ordered MTC and KCST to resolve their competing claims of
    breach of the NOA -- which were originally raised in an adversary
    proceeding in the bankruptcy court -- through arbitration.             Hence,
    the bankruptcy court was the proper forum for a challenge to the
    arbitrator's resolution of MTC and KCST's dispute over the NOA,
    including the relief awarded to KCST for MTC's material breach of
    the NOA.    But MTC chose not to pursue such a challenge.            Instead,
    it poses in this proceeding a more limited question -- whether the
    arbitrator acted outside the scope of his authority by determining
    - 16 -
    that the Guaranty agreement was void for failure of consideration
    as a result of MTC's material breach of the NOA.10
    The    district   court       concluded    that   "the     arbitrator
    exceeded his powers under the FAA by prospectively voiding the
    Guaranty while re-writing the terms of the NOA."                       Axia NetMedia
    Corp. v. Mass. Tech. Park Corp., 
    381 F. Supp. 3d 128
    , 138 (D. Mass.
    2019).        The court reasoned, first, that "there is evidence that
    the   parties        never   intended     to    bestow    this   power     upon   the
    arbitrator" because arbitrators do not have the power to rewrite
    contracts or stray from the scope of the parties' agreement.                      See
    id. Second, the court
    rejected the arbitrator's finding that "the
    record was simply devoid of specific persuasive evidence" that MTC
    would        have    insisted    upon    a     Guaranty    in    any     independent
    renegotiation of the NOA.
    Id. The court observed
    that section
    12.14 of the NOA, section 2.3 of the Guaranty, and testimony and
    circumstantial evidence presented to the arbitrator demonstrate
    the necessity of the Guaranty.
    Id. at 138-39. 10
           This decision of MTC to accept in the bankruptcy court
    proceedings the arbitrator's resolution of its dispute with KCST
    -- the reformation of the NOA -- while refusing to accept his
    resolution of the dispute with Axia -- invalidating the Guaranty
    because of the material breach of the NOA -- arguably could have
    precluded MTC from challenging that reformation decision here in
    the guise of challenging only the decision on the Guaranty.
    Indeed, Axia made preclusion arguments before the district court,
    which rejected them, and renews those arguments here.     Without
    making any judgments on these arguments, we choose to reject the
    district court's decision on a different basis.
    - 17 -
    The     district     court's    reasoning     is   incompatible    in
    several respects with the limited role of the courts in reviewing
    arbitration awards.           The question of the Guaranty's validity was
    squarely before the arbitrator as a result of MTC's strategic
    choices.     The dispute resolution provision of the Guaranty gave
    MTC the power to seek arbitration of disputes with Axia "at [its]
    sole election."          MTC elected to pursue arbitration and, as the
    arbitrator       noted   in   the   PFA,   sought   "a    declaration   in   th[e
    arbitration] proceeding that '[t]he Guaranty and NOA . . . are
    valid and enforceable contracts not subject to recession [sic] nor
    rendered null and void.'"           In addition, after the PFA was issued,
    MTC sought further clarification from the arbitrator as to the
    validity of the Guaranty.           MTC itself submitted the issue to the
    arbitrator and the arbitrator had the power to reach it.                      See
    DiRussa v. Dean Witter Reynolds, Inc., 
    121 F.3d 818
    , 824 (2d Cir.
    1997) ("Our inquiry under § 10(a)(4) . . . focuses on whether the
    arbitrator[] had the power, based on the parties' submissions or
    the arbitration agreement, to reach a certain issue, not whether
    the arbitrator[] correctly decided that issue." (emphasis added)).
    Moreover, it is clear from the text of the arbitral award
    that the arbitrator did not stray outside the scope of the parties'
    agreement with his decision.           See First State Ins. 
    Co., 781 F.3d at 11
      ("In    ascertaining      whether    [the]     arbitrator[]   arguably
    interpreted the underlying contract, an inquiring court must look
    - 18 -
    . . . to the text of the arbitral award.").           The consideration
    underlying the Guaranty was the NOA, and specifically MTC's promise
    to build the network as described in the NOA.           The arbitrator
    determined that MTC's failure to fulfill that promise constituted
    a material breach of the NOA, and that the material breach of the
    NOA constituted a failure of consideration for the Guaranty.
    Applying Massachusetts law, the arbitrator concluded that the
    failure of consideration rendered the Guaranty void.11       Thus, with
    its explicit reasoning, the arbitrator's decision "draw[s] its
    essence"   from      the   contracts    underlying    the   arbitration
    proceeding,12 
    Misco, 484 U.S. at 38
    , and the arbitrator acted within
    the scope of his authority in rendering it.
    In   an   effort   to   support   its   disapproval   of   the
    arbitrator's decision on the Guaranty, the district court observed
    that section 2.3 of the Guaranty supports MTC's view that the
    11 MTC argues that the arbitration award should be set aside
    because the arbitrator's application of Massachusetts law was "not
    even . . . colorable." Even if that were true, our limited review
    of the arbitrator's decision means that we must leave the award in
    place despite legal errors committed by the arbitrator, "[e]ven
    where such error is painfully clear." Dialysis Access 
    Ctr., 932 F.3d at 9
    (alteration in original) (quoting 
    Advest, 914 F.2d at 8
    ).
    12 The arbitrator's decision necessarily "draws its essence"
    from both the NOA and the Guaranty.        The two contracts are
    connected because the NOA served as consideration for the Guaranty.
    Thus, the arbitrator's resolution of MTC and KCST's competing
    breach of contract claims based on the NOA affected his resolution
    of MTC and Axia's dispute over the validity of the Guaranty.
    - 19 -
    Guaranty must remain in place as long as the NOA is operative.   We
    disagree.    As we described above, section 2.3 provides that the
    Guaranty will remain valid regardless of any breaches of the NOA
    by the "Network Operator," i.e., KCST.     The provision is silent,
    however, as to the effect (if any) of a material breach of the NOA
    by MTC on the validity of the Guaranty.      Thus, section 2.3 does
    not constrain the arbitrator's power to determine the effect of
    such a breach.13   And no other provision of the Guaranty limits the
    arbitrator's power to decide issues submitted to him by the
    parties, including the validity of the Guaranty itself.
    Nor does the Guaranty limit the arbitrator's power to
    award appropriate remedies.   The "Defaults and Remedies" provision
    of the Guaranty provides:
    No remedy herein conferred or reserved is
    intended to be exclusive of any other
    available remedy or remedies, if any, but each
    and every such remedy shall be cumulative and
    shall be in addition to every other remedy
    given under this Agreement or now or hereafter
    existing at law or in equity or by statute.
    The Guaranty also incorporates by reference the dispute resolution
    and arbitration provisions of the NOA, which likewise do not limit
    the arbitrator's choice of remedy.    Thus, the decision to void the
    13 The district court also highlighted section 12.14 of the
    NOA, which requires a Guaranty from Axia if the NOA is to take
    effect.    This provision does support an argument about the
    necessity of the Guaranty, but, as we explain below, we are not in
    a position to question the arbitrator's finding of fact on this
    score.
    - 20 -
    Guaranty prospectively as a choice of remedy was within the
    authority of the arbitrator.            Indeed, "where it is contemplated
    that    the     arbitrator     will    determine    remedies       for    contract
    violations that he finds, courts have no authority to disagree
    with his honest judgment in that respect."               
    Misco, 484 U.S. at 38
    .
    The district court's disagreement with the arbitrator's
    factual finding as to the necessity of the Guaranty was not an
    appropriate basis for vacating the award.            Federal courts "do not
    sit . . . to hear claims of factual or legal error by an arbitrator
    or to consider the merits of the award."            Asociación de Empleados
    del    Estado       Libre   Asociado    de   P.R.   v.     Local    1850,   Unión
    Internacional de Trabajadores de la Industria de Automóviles,
    Aeroespacio e Implementos Agrícolas, 
    559 F.3d 44
    , 47 (1st Cir.
    2009) (quoting Challenger Caribbean Corp. v. Union General de
    Trabajadores de P.R., 
    903 F.2d 857
    , 860 (1st Cir. 1990)).                   Thus,
    even   if     the    arbitrator   committed     serious     factual      error   by
    concluding that the record lacked "specific persuasive evidence"
    that MTC would insist upon a Guaranty as part of a renegotiation
    of the NOA, that would not "justify setting aside the arbitral
    decision."      Cytyc 
    Corp., 439 F.3d at 32
    .
    In short, this is not a case where the arbitrator
    "ignore[d] the contract and simply dispense[d] 'his own brand of
    industrial justice.'"         Kraft Foods, Inc. v. Local 1295, Office and
    Prof'l Emps. Int'l Union, 
    203 F.3d 98
    , 100 (1st Cir. 2000) (quoting
    - 21 -
    United Steelworkers of Am. v. Enter. Wheel & Car Corp., 
    363 U.S. 593
    , 597 (1960)).     To the contrary, the arbitration award is
    grounded in the record and the parties' agreement.   The arbitrator
    did not exceed the scope of his powers under section 10(a)(4) of
    the FAA.   Accordingly, we reverse the district court's ruling and
    remand the case with instructions to enter a judgment confirming
    the arbitration award.
    So ordered.
    - 22 -