Fisher Sand & Gravel, Co. v. Girón , 465 F. App'x 774 ( 2012 )


Menu:
  •                                                                FILED
    United States Court of Appeals
    UNITED STATES COURT OF APPEALS         Tenth Circuit
    TENTH CIRCUIT                March 6, 2012
    Elisabeth A. Shumaker
    Clerk of Court
    FISHER SAND & GRAVEL, CO., d/b/a
    Southwest Asphalt Paving; FISHER
    SAND & GRAVEL - NEW MEXICO,
    INC.,
    Plaintiffs - Appellees,
    v.                                                   No. 11-2067
    (D.C. No. 1:10-CV-00635-RB-SMV)
    GARY GIRÓN, individually and as                      (D. N. Mex.)
    former Cabinet Secretary of the New
    Mexico Department of Transportation;
    MAX VALERIO, individually and as
    former Deputy Secretary of the New
    Mexico Department of Transportation,
    Defendants - Appellants,
    and
    FNF CONSTRUCTION, INC.; PULICE
    CONSTRUCTION, INC.; JED
    BILLINGS, Chief Executive Officer of
    FNF Construction, Inc.; STEPHEN
    BASILA, President of Pulice
    Construction, Inc.
    Defendants.
    ORDER AND JUDGMENT*
    Before BRISCOE, Chief Judge, GORSUCH, and MATHESON, Circuit Judges.
    MATHESON, Circuit Judge.
    Fisher Sand & Gravel-New Mexico (“FSG-NM”) submitted a bid to the New
    Mexico Department of Transportation (“NMDOT”) for a contract on the Las Cruces
    Highway Construction Project (the “Project” or the “Project Contract”). Although FSG-
    NM was the low bidder, NMDOT rejected all bids and eventually awarded the Project
    Contract to another company. Plaintiffs-Appellees Fisher Sand & Gravel, Co. and FSG-
    NM (collectively, “FSG”) sued Defendants-Appellants Gary Girón and Max Valerio,
    secretary and deputy secretary of NMDOT respectively, and other defendants not
    involved in this appeal.
    Among other things, FSG alleged under 
    42 U.S.C. § 1983
     that Mr. Girón and Mr.
    Valerio violated its right to procedural due process when NMDOT refused to award the
    Project Contract to FSG-NM. Mr. Girón and Mr. Valerio moved to dismiss this claim
    based on qualified immunity and insufficient notice pleading under Fed. R. Civ. P. 8(a).
    *This order and judgment is not binding precedent, except under the doctrines of
    law of the case, res judicata, and collateral estoppel. It may be cited, however, for its
    persuasive value consistent with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.
    -2-
    The district court denied their motion. Exercising jurisdiction under 
    28 U.S.C. § 1291
    ,
    we reverse and remand with directions to dismiss the §1983 claim brought against Mr.
    Girón and Mr. Valerio. We also deny FSG’s motion to dismiss this appeal for lack of
    jurisdiction.
    I.     BACKGROUND
    A. Factual Background1
    On May 1, 2009, NMDOT advertised the Project and issued Invitations for Bid.
    See NMDOT, Standard Specifications for Highway and Bridge Construction (“NMDOT
    Sp.”), § 102.1. NMDOT opened the bids on May 29, 2009, and determined that FSG-
    NM was the apparent lowest bidder. See NMDOT Sp. § 102.15. On June 18, 2009,
    NMDOT recommended to the Federal Highway Association (“FHWA”) that the Project
    Contract should be awarded to FSG-NM.2 FHWA responded on June 22, 2009,
    informing NMDOT that it would not be able to give final approval for at least 14 days.
    Under NMDOT Sp. § 103.2, NMDOT must award a contract to the lowest
    responsible bidder within 30 days after it opens the bids, unless it requests additional time
    from the bidder. On June 22, 2009, NMDOT contacted FSG-NM and requested
    1
    Our review of a motion to dismiss takes its facts from the complaint. Cnty. of
    Santa Fe, N.M. v. Pub. Serv. Co. of N.M., 
    311 F.3d 1031
    , 1035 (10th Cir. 2002) (“In
    deciding a Rule 12(b)(6) motion, a federal court may only consider facts alleged within
    the complaint.”).
    2
    NMDOT needed approval from FHWA because funding for the Project came
    from federal funds granted by the American Recovery and Reinvestment Act of 2009.
    -3-
    additional time to award the Project Contract.
    Around this time, the second-lowest bidder—FNF Construction (“FNF”)—began
    making disparaging comments about FSG-NM to induce NMDOT to award the Project
    Contract to FNF. This strategy proved successful. NMDOT changed course and decided
    to award the Project Contract to FNF. On July 10, 2009, NMDOT recommended to
    FHWA that the Project Contract be awarded to FNF rather than FSG-NM. FHWA
    responded on July 13, 2009, and refused to award the contract to FNF because FSG-NM
    was the lowest bidder.
    In response, NMDOT announced on July 28, 2009, that it was “reject[ing] all of
    the bids for the Project under [NMDOT Sp. §] 103.1 . . . as not promoting the best
    interests of the public.” Compl. ¶ 115 (quotations omitted). Three days later, NMDOT
    readvertised the Project and accepted new bids. On November 25, 2009, NMDOT
    awarded the Project Contract to the lowest responsible bidder, which was neither FSG-
    NM nor FNF.
    B. Procedural Background
    FSG filed a complaint against numerous defendants, including Mr. Girón, Mr.
    Valerio, and FNF. FSG brought 10 claims, most of which involved an alleged conspiracy
    among FNF, another construction company, and members of NMDOT to prevent FSG-
    NM from being awarded the Project Contract. FSG also sued Mr. Girón and Mr. Valerio
    under 42 U.S.C § 1983, alleging that they violated its procedural and substantive due
    process rights by not awarding the Project Contract to FSG-NM after the original bid
    -4-
    process.
    Mr. Girón and Mr. Valerio filed a motion to dismiss the § 1983 claim based on
    qualified immunity and improper notice pleading under Fed. R. Civ. P. 8(a). The district
    court granted their motion to dismiss in part and denied it in part. It dismissed without
    prejudice FSG’s claim against Mr. Girón and Mr. Valerio in their official capacities. It
    also granted their motion to dismiss FSG’s substantive due process claim based on
    qualified immunity.
    The district court denied Mr. Girón and Mr. Valerio’s motion to dismiss FSG’s
    procedural due process claim based on qualified immunity. It found that FSG had
    alleged sufficient facts to support a plausible claim that FSG-NM and NMDOT reached a
    “mutually explicit understanding,” or an “implied contract,” that NMDOT would award
    the Project Contract to FSG-NM. See Appx. at 175, 173 (“It would have been helpful if
    [FSG] had included more specific allegations in the Complaint; nonetheless, [FSG’s]
    allegations are sufficient, if only barely, to survive a Rule 12(b)(6) motion to dismiss.”).
    It further held that this “mutually explicit understanding” or “implied contract” was a
    clearly established constitutionally protected property interest. The district court also
    denied Mr. Girón and Mr. Valerio’s motion to dismiss this claim based on insufficient
    notice pleading under Fed. R. Civ. P. 8(a).
    Mr. Girón and Mr. Valerio now appeal the district court’s denial of their motion to
    dismiss FSG’s procedural due process claim based on qualified immunity and its refusal
    to dismiss this claim for insufficient notice pleading.
    -5-
    II.    DISCUSSION
    A. Qualified Immunity
    1. Jurisdiction
    Under 
    28 U.S.C. § 1291
    , we “have jurisdiction of appeals from all final decisions
    of the district courts” of this circuit. Based on this final judgment rule, “interlocutory
    appeals . . . are the exception, not the rule.” Johnson v. Jones, 
    515 U.S. 304
    , 309 (1995).
    Under the collateral order doctrine exception, an interlocutory order may qualify as a
    “final decision[]” under 
    28 U.S.C. § 1291
     even though it is not “the last order possible to
    be made in a case.” Mitchell v. Forsyth, 
    472 U.S. 511
    , 524 (1985); see also Johnson, 
    515 U.S. at 310
    .
    The collateral order doctrine permits a party to appeal a district court’s
    interlocutory ruling that “fall[s] in [the] small class which finally determine claims of
    right separable from, and collateral to, rights asserted in the action, too important to be
    denied review and too independent of the cause itself to require that appellate
    consideration be deferred until the whole case is adjudicated.” Cohen v. Beneficial Indus.
    Loan Corp., 
    337 U.S. 541
    , 546 (1949).
    “[T]he applicability of [the collateral order] doctrine in the context of qualified-
    immunity claims is well established . . . .” Ashcroft v. Iqbal, 
    129 S. Ct. 1937
    , 1946
    (2009). The doctrine applies to denials of qualified immunity because qualified
    immunity “is an immunity from suit rather than a mere defense to liability . . . [and] it is
    effectively lost if a case is erroneously permitted to go to trial.” Mitchell, 472 U.S. at
    -6-
    526; see also Iqbal, 
    129 S. Ct. at 1945-46
     (“[Q]ualified immunity . . . is both a defense to
    liability and a limited entitlement not to stand trial or face the other burdens of litigation.”
    (quotations omitted)).
    The collateral order doctrine applies only when qualified immunity turns on a
    purely legal issue. See Brown v. Montoya, 
    662 F.3d 1152
    , 1162 (10th Cir. 2011) (“[A]
    district court’s denial of a claim of qualified immunity, to the extent that it turns on an
    issue of law, is an appealable final decision within the meaning of 
    28 U.S.C. § 1291
    .”
    (emphasis added) (quotations omitted)); Gann v. Cline, 
    519 F.3d 1090
    , 1091 (10th Cir.
    2008) (“Our jurisdiction arises under 
    28 U.S.C. § 1291
     and the collateral order doctrine
    allowing an interlocutory appeal from the denial of qualified immunity that rests upon
    purely legal grounds.” (emphasis added)). A motion to dismiss based on qualified
    immunity requires a legal determination. In Iqbal, the Supreme Court explained that
    “[e]valuating the sufficiency of a complaint is not a ‘fact-based’ question of law” and the
    collateral order doctrine applies to the denial of a motion to dismiss for qualified
    immunity, including when qualified immunity turns on whether the “complaint
    sufficiently alleges a clearly established violation of law.” 
    129 S. Ct. at 1947
    .
    After Mr. Girón and Mr. Valerio filed their notice of appeal, FSG moved to
    dismiss the appeal for lack of jurisdiction. FSG argues that the district court’s order
    denying Mr. Girón and Mr. Valerio’s claim for qualified immunity turns on factual rather
    than legal matters and is thus unreviewable. We disagree. The district court’s order was
    a Fed. R. Civ. P. 12(b)(6) determination of the legal sufficiency of the complaint
    -7-
    regarding qualified immunity. Mr. Girón and Mr. Valerio assume for the purposes of this
    appeal that FSG has alleged sufficient facts to support a “mutually explicit
    understanding” or “implied contract” that NMDOT would award the Project Contract to
    FSG-NM. They challenge whether FSG-NM could have a due process property interest
    in receiving the Project Contract based on an implied contract with NMDOT—a purely
    legal question. Under Iqbal, we have jurisdiction over the qualified immunity issue.
    2. Standard of Review
    “We review the district court’s denial of a motion to dismiss based on qualified
    immunity de novo.” Brown, 
    662 F.3d at 1162
     (quotations omitted). “In reviewing a
    motion to dismiss, all well-pleaded factual allegations in the complaint are accepted as
    true and viewed in the light most favorable to the nonmoving party.” 
    Id.
     (quotations
    omitted).
    “[T]o withstand a motion to dismiss, a complaint must have enough allegations of
    fact, taken as true, ‘to state a claim to relief that is plausible on its face.’” Kan. Penn
    Gaming, LLC v. Collins, 
    656 F.3d 1210
    , 1214 (10th Cir. 2011) (quoting Bell Atl. Corp. v.
    Twombly, 
    550 U.S. 544
    , 570 (2007)). “‘[O]nly a complaint that states a plausible claim
    for relief [will] survive[] a motion to dismiss.’” 
    Id.
     (quoting Iqbal, 
    129 S. Ct. 1950
    ).
    3. Legal Background
    a.      The Qualified Immunity Framework
    Title 
    42 U.S.C. § 1983
     provides in part that “[e]very person who, under color of
    any statute, ordinance, [or] regulation . . . subjects . . . any citizen of the United States . . .
    -8-
    to the deprivation of any rights, privileges, or immunities secured by the Constitution and
    laws, shall be liable to the party injured.” See also Camreta v. Greene, 
    131 S. Ct. 2020
    ,
    2027 (2011) (“[Section 1983] authorizes suits against state officials for violations of
    constitutional rights.”).
    “[T]o ensure that fear of liability will not unduly inhibit officials in the discharge
    of their duties, the officials may claim qualified immunity . . . .” Camreta, 
    131 S. Ct. at 2030-31
     (citation omitted) (quotations omitted). Qualified immunity applies only when
    government defendants are sued in their individual capacities. Brown, 
    662 F.3d at 1164
    .
    Under this principle, “government officials are not subject to damages liability for the
    performance of their discretionary functions when their conduct does not violate clearly
    established statutory or constitutional rights of which a reasonable person would have
    known.” Buckley v. Fitzsimmons, 
    509 U.S. 259
    , 268 (1993) (quotations omitted).
    “Qualified immunity protects defendants not only from liability but also from suit.”
    Watson v. Univ. of Utah Med. Ctr., 
    75 F.3d 569
    , 577 (10th Cir. 1996).
    We employ a two-part test to evaluate a qualified immunity defense. “In resolving
    a motion to dismiss based on qualified immunity, a court must consider [1] ‘whether the
    facts that a plaintiff has alleged make out a violation of a constitutional right,’ and [2]
    ‘whether the right at issue was clearly established at the time of defendant’s alleged
    misconduct.’” Leverington v. City of Colorado Springs, 
    643 F.3d 719
    , 732 (10th Cir.
    2011) (quoting Pearson v. Callahan, 
    555 U.S. 223
    , 232 (2009)). The burden is on the
    plaintiff to prove both parts of this test. See Dodds v. Richardson, 
    614 F.3d 1185
    , 1191
    -9-
    (10th Cir. 2010). “If the plaintiff fails to satisfy either part of this two-part inquiry, the
    court must grant the defendant qualified immunity.” Hesse v. Town of Jackson, Wyo.,
    
    541 F.3d 1240
    , 1244 (10th Cir. 2008) (quotations omitted).
    We have discretion to “decid[e] which of the two prongs of the qualified immunity
    analysis should be addressed first in light of the circumstances in the particular case at
    hand.” Pearson, 
    555 U.S. at 236
    . And “[i]f the court concludes no constitutional right
    has been violated, no further inquiry is necessary and the defendant is entitled to qualified
    immunity.” Hesse, 
    541 F.3d at 1244
     (quotations omitted).
    b.     Procedural Due Process
    Mr. Girón and Mr. Valerio challenge the district court’s denial of their motion to
    dismiss FSG’s procedural due process claim based on qualified immunity.
    “Procedural due process imposes constraints on governmental decisions which
    deprive individuals of liberty or property interests within the meaning of the Due Process
    Clause of the . . . Fourteenth Amendment.” Mathews v. Eldridge, 
    424 U.S. 319
    , 332
    (1976) (quotations omitted). “The Fourteenth Amendment’s procedural protection of
    property is a safeguard of the security of interests that a person has already acquired in
    specific benefits.” Bd. of Regents of State Colls. v. Roth, 
    408 U.S. 564
    , 576 (1972).
    We engage in a two-step assessment of a procedural due process property claim:
    “(1) did the individual possess a protected interest such that the due process protections
    were applicable; and, if so, then (2) was the individual afforded an appropriate level of
    process.” Brown, 
    662 F.3d at 1167
     (quotations omitted). “[I]t is only after the plaintiff
    -10-
    first demonstrates the existence and deprivation of a protected property interest that the
    plaintiff is constitutionally entitled to an appropriate level of process.” Teigen v.
    Renfrow, 
    511 F.3d 1072
    , 1078 (10th Cir. 2007).
    In the procedural due process context, “[p]roperty interests . . . are not created by
    the Constitution [but] [r]ather . . . by existing rules or understandings that stem from an
    independent source such as state law.” Roth, 
    408 U.S. at 577
    . “Thus, constitutionally
    protected property interests are created and defined by statute, ordinance, contract,
    implied contract and rules and understandings developed by state officials.” Kirkland v.
    St. Vrain Valley Sch. Dist. No. Re-1J, 
    464 F.3d 1182
    , 1190 (10th Cir. 2006). “Valid
    contracts may constitute a property interest for purposes of due process.” S. Disposal,
    Inc. v. Tex. Waste Mgmt., 
    161 F.3d 1259
    , 1265 (10th Cir. 1998).
    4. Application
    The threshold issue is whether New Mexico law recognizes a property interest in
    an implied contract with a governmental agency. Based on 
    N.M. Stat. Ann. § 37-1
    -
    23(A), Mr. Girón and Mr. Valerio say the answer is no.
    a.      Forfeiture Issue
    FSG argues that we should not consider 
    N.M. Stat. Ann. § 37-1-23
    (A)’s effect on
    the existence of a due process property interest because Mr. Girón and Mr. Valerio did
    not raise this argument in the district court. Legal theories raised for the first time on
    appeal are either waived or forfeited. Richison v. Ernest Grp., Inc., 
    634 F.3d 1123
    , 1127-
    28 (10th Cir. 2011). If the theory is waived, meaning the party intentionally relinquished
    -11-
    or abandoned it in the district court, we refuse to consider it. 
    Id. at 1127
    . If it is
    forfeited, meaning a party’s failure to raise it was unintentional, we may consider it under
    a plain error standard of review. 
    Id. at 1128
    .
    Mr. Girón and Mr. Valerio did not waive their argument. On the motion to
    dismiss the procedural due process claim, neither party argued the implied contract
    theory on which the district court based its decision that FSG-NM possessed a property
    interest. In its response to Mr. Girón and Mr. Valerio’s motion to dismiss, FSG argued
    that its property interest was based on NMDOT’s implied obligation to follow its own
    policies and procedures. The district court rejected this argument. Appx. at 173.
    (“Plaintiffs confuse the issue of an implied contract by conflating the two distinct types of
    implied contracts—the one giving rise to a constitutionally protected property right and
    potential § 1983 claim and the other providing the disappointed bidder with nothing more
    than a state cause of action for its costs in preparing the bid.” (citations omitted)).
    Although FSG referred briefly to an implied understanding that NMDOT would award
    the Project Contract to FSG-NM, it did not develop this argument.
    Because the district court based its qualified immunity conclusion on a theory that
    neither party developed in the district court, we find it difficult to fault Mr. Girón and Mr.
    Valerio for not addressing a theory that first emerged in the district court’s decision. On
    appeal, they challenge that decision because 
    N.M. Stat. Ann. § 37-1-23
    (A) precludes a
    property interest based on an implied contract with a governmental entity. They did not
    intentionally relinquish or abandon this argument in district court and therefore did not
    -12-
    waive it.
    As for whether Mr. Girón and Mr. Valerio forfeited their argument, we need not
    decide that issue because, as explained below, they prevail even under plain error review.
    “[W]e will reverse a district court’s judgment on the basis of a forfeited theory only if
    failing to do so would entrench a plainly erroneous result.” Richison, 
    634 F.3d at 1128
    .
    To satisfy this standard, “a party must establish the presence of (1) error, (2) that is plain,
    which (3) affects substantial rights, and which (4) seriously affects the fairness, integrity,
    or public reputation of judicial proceedings.” Id.3
    3
    In Richison, we faulted the appellant for not attempting to show on appeal how
    his forfeited legal theory satisfied the plain error standard. 
    634 F.3d at 1130-31
     (“[T]he
    failure to argue for plain error and its application on appeal . . . surely marks the end of
    the road for an argument for reversal not first presented to the district court.”). Here, Mr.
    Girón and Mr. Valerio argue that we should consider their argument not only because it is
    a purely legal one but also because “failure to consider it would result in a miscarriage of
    justice.” Aplt. Reply Br. at 6. They further argue that the district court, once it elected to
    rely on an implied contract theory, failed to undertake a proper review of state law,
    leading to a clearly improper result. See Aplt. Br. at 9-10, 12-13 (“[U]nder New Mexico
    law, it is clear that [FSG] could not enforce an implied contract against NMDOT because
    state entities are immune from claims based on implied contract.”).
    In Richison, we explained the history and rationale behind applying plain error
    review to forfeited arguments:
    Long ago, this court held that we will reverse on the basis of a legal theory
    not previously presented to the district court when the correct resolution of
    that theory is beyond a reasonable doubt and the failure to intervene would
    result in a miscarriage of justice. More recently, we have stated this
    standard in slightly different terms, requiring a litigant to show the four
    elements of plain error. Linguistic packaging aside, the substantive
    analysis under either articulation of the standard is similar, and the
    litigant’s burden is the same: establishing a clear legal error that
    Continued . . .
    -13-
    b.     Plain Error Analysis
    Mr. Girón and Mr. Valerio’s argument that 
    N.M. Stat. Ann. § 37-1-23
    (A)
    precludes a property interest based on an implied contract with a governmental entity
    warrants reversal of the district court’s judgment under plain error review.
    i.     Error
    The district court erred by concluding that FSG-NM’s implied contract with
    NMDOT created a due process property interest.
    Although due process property interests may arise out of express or implied
    contracts, Pater v. City of Casper, 
    646 F.3d 1290
    , 1294 (10th Cir. 2011), such property
    interests arise only out of enforceable agreements, see Kirkland, 
    464 F.3d at 1190-91
    (“Because the resignation agreement . . . never became an enforceable contract, Kirkland
    never gained a property interest in that agreement such that it would be subject to due
    ______________________________________
    Cont.
    implicates a miscarriage of justice.
    Id. at 1128 (emphasis added) (citations omitted); see also Jordan v. U.S. Dep’t of Justice,
    —F.3d—, 
    2011 WL 6739410
    , at *9 (10th Cir. 2011) (“When a matter is forfeited, we
    may review for plain error, but that review is limited to whether there was a clear legal
    error that implicates a miscarriage of justice.” (quotations omitted)) .
    Because Mr. Girón and Mr. Valerio show there has been a “clear legal error that
    implicates a miscarriage of justice,” we may review their argument under the plain error
    standard.
    -14-
    process protections.” (emphasis added)); see also Stidham v. Tex. Comm’n on Private
    Sec., 
    418 F.3d 486
    , 492 n.9 (5th Cir. 2005) (“With respect to property rights relating to
    contracts, our precedent is clear that there must be an enforceable contract between the
    parties.” (emphasis added)); Drake v. Scott, 
    823 F.2d 239
    , 242 (8th Cir. 1987) (“[Under
    Arkansas law], [t]he promise must be express, or else there is no enforceable contract,
    and, hence, no property right for purposes of the Due Process Clause.” (emphasis
    added)). In Kirkland, we held that a plaintiff did not have a property interest in an
    agreement because that agreement was not enforceable under state law. 
    464 F.3d at 1190-91
    . In that case, the agreement required approval from the school board before it
    became binding. 
    Id. at 1190
    . Because the school board never gave such approval, there
    was never an enforceable agreement, and therefore no due process property interest. 
    Id. at 1190-91
    . We held that the individual defendants were entitled to qualified immunity
    on the procedural due process claim. 
    Id. at 1191
    .
    FSG must have an enforceable agreement with NMDOT to have a due process
    property interest. 
    N.M. Stat. Ann. § 37-1-23
    (A) states: “Governmental entities are
    granted immunity from actions based on contract, except actions based on a valid written
    contract.” Thus, for a contract with a governmental entity to be enforceable, it must be
    based on a “valid written contract.”4 See Eaton, Martinez & Hart, P.C. v. Univ. of N.M.
    4
    In Garcia v. Middle Rio Grande Conservancy District, 
    918 P.2d 7
     (N.M. 1996),
    the New Mexico Supreme Court held that 
    N.M. Stat. Ann. § 37-1-23
    (A) did not foreclose
    a suit against a governmental agency arising from an implied employment contract based
    Continued . . .
    -15-
    Hosp., 
    934 P.2d 270
    , 272 (N.M. 1997) (“The Legislature has imposed a statutory
    requirement that a contract claim must be supported by a writing in order for it to be
    enforceable against the State.”).
    Other circuits have refused to find a property interest based on a contract that is
    unenforceable under state law. 5 See Conner v. Lavaca Hosp. Dist., 
    267 F.3d 426
    , 437
    (5th Cir. 2001) (holding there was no property interest based on an “implied contract
    because a contract that fails the statute of frauds cannot be enforced as such a contract
    ______________________________________
    Cont.
    on an employee handbook. Id. at 11-13. The employee handbook provided the “valid
    written contract” required by 
    N.M. Stat. Ann. § 37-1-23
    (A). 
    Id. at 12-13
    . New Mexico
    courts, however, have not extended this exception beyond the employment context. See
    Campos de Suenos, Ltd. v. Cnty. of Bernalillo, 
    28 P.3d 1104
    , 1111-12 (N.M. Ct. App.
    2001); see also Whittington v. State Dep’t of Pub. Safety, 
    100 P.3d 209
    , 214-15 (N.M. Ct.
    App. 2004) (explaining that Campos de Suenos limited Garcia to the employment
    context).
    5
    In Luttrell v. Montoya, No. 94-2189, 
    1995 WL 350601
     (10th Cir. June 12, 1995)
    (unpublished) (cited for persuasive value pursuant to 10th Cir. R. 32.1(A)), we held that,
    based on 
    N.M. Stat. Ann. § 37-1-23
    (A), an employee did not have a property interest in
    continued employment because he did not have a written contract for employment. 
    Id. at *2
    . Because the “plaintiff had no enforceable contract right to employment under state
    law, he had no legitimate claim of entitlement to employment” and no property interest
    under state law. 
    Id.
     (quotations omitted). Therefore, we held that the plaintiff had not
    asserted the violation of a constitutional right, and the defendants were entitled to
    summary judgment based on qualified immunity. 
    Id. at *3
    .
    Luttrell is distinguishable from Garcia. Unlike Garcia, there is no indication in
    Luttrell that there was an employee handbook or any writing that the plaintiff could claim
    to support his implied contract. See 
    id. at *1
     (“Plaintiff maintains . . . that he had an
    implied contract of continued employment, based on representations made to him . . .
    [and] that the school district treated him as an employee while he was on leave of absence
    by continuing his benefits . . . .”).
    -16-
    under Texas law”); Woolsey v. Hunt, 
    932 F.2d 555
    , 564-65 (6th Cir. 1991) (“We are
    compelled to reverse because Tennessee does not recognize the enforcement of an
    implied contract against the state and has not done so since 1980. . . . Tennessee had
    waived its sovereign immunity only with respect to suits against the state based on an
    express contract or breach thereof.”).
    FSG-NM’s interest in the Project Contract was not based on a written agreement.
    It was based on an implied contract with NMDOT that arose from a mutual
    understanding that NMDOT would award the Project Contract to FSG-NM. Because
    there was no “valid written contract,” this mutual understanding was not enforceable.
    See 
    N.M. Stat. Ann. § 37-1-23
    (A).
    
    N.M. Stat. Ann. § 37-1-23
    (A) grants immunity to governmental entities. FSG
    brings this claim against Mr. Girón and Mr. Valerio in their individual capacities, but this
    does not alter our conclusion.6 The statute determines whether FSG-NM had a property
    interest in the Project Contract based on an implied contract with NMDOT. Without
    such an interest, FSG-NM had no due process right that the individual defendants could
    violate.
    Moreover, FSG does not allege that it had an implied contract with Mr. Girón or
    6
    In Luttrell, the plaintiff brought a § 1983 claim against the defendants in their
    individual capacities. Based on 
    N.M. Stat. Ann. § 37-1-23
    (A), we said “it [was] clear
    that plaintiff could not enforce an implied contract against the school district.” 
    1995 WL 350601
    , at *2 (emphasis added). We held that the individual defendants were entitled to
    qualified immunity. 
    Id. at *3
    .
    -17-
    Mr. Valerio. Instead, it alleges only that Mr. Girón and Mr. Valerio violated its
    constitutional rights when they determined not to award the Project to FSG-NM. See
    Compl. ¶¶ 239-254. Even if Mr. Girón and Mr. Valerio had made representations
    creating a “mutual, explicit, understanding that [FSG-NM’s] bid had been accepted . . .
    and [FSG-NM] would be awarded the contract . . . ,” Appx. at 173, this understanding
    would at most be an implied contract between FSG-NM and NMDOT, not between FSG-
    NM and Mr. Girón or Mr. Valerio. And, to repeat, such an implied contract is
    unenforceable under New Mexico law.
    Because FSG-NM did not have a protected property interest in the Project
    Contract, there could be no deprivation of due process. The district court erred by
    denying Mr. Girón and Mr. Valerio qualified immunity on FSG’s due process claim.
    ii.    Plain
    “An error is ‘plain’ if it is clear or obvious under current, well-settled law.”
    United States v. Weeks, 
    653 F.3d 1188
    , 1198 (10th Cir. 2011). “In general, for an error to
    be contrary to well-settled law, either the Supreme Court or this court must have
    addressed the issue.” United States v. Thornburgh, 
    645 F.3d 1197
    , 1208 (10th Cir.
    2011), cert. denied, 
    132 S. Ct. 214
     (2011) (quotations omitted). “The absence of such
    precedent will not, however, prevent a finding of plain error if the district court’s
    interpretation was clearly erroneous.” United States v. Ruiz-Gea, 
    340 F.3d 1181
    , 1187
    (10th Cir. 2003) (quotations omitted).
    Although we have no published case on point, our reasoning in Luttrell, as well as
    -18-
    the New Mexico cases cited above, clearly establish that 
    N.M. Stat. Ann. § 37-1-23
    (A)
    prevents a party from entering into an enforceable contract with a governmental entity
    unless that contract is in writing. We conclude that the district court’s analysis was
    clearly erroneous in holding that FSG-NM had a property interest in an implied contract
    with NMDOT.
    iii.   Affecting Substantial Rights
    “To satisfy the third prong of plain error review, the appellant must show a
    reasonable probability that, but for the error claimed, the result of the proceeding would
    have been different.” United States v. Cordery, 
    656 F.3d 1103
    , 1108 (10th Cir. 2011)
    (quotations omitted). This requirement is easily satisfied in this case. If the district court
    had properly considered the effect of 
    N.M. Stat. Ann. § 37-1-23
    (A), it would have
    granted Mr. Girón and Mr. Valerio’s motion to dismiss for qualified immunity. Thus, the
    district court’s error affected Mr. Girón’s and Mr. Valerio’s substantial rights.
    iv.    Seriously Affecting the Fairness, Integrity, or Public
    Reputation of Judicial Proceedings
    Failure to consider Mr. Girón and Mr. Valerio’s argument and affirming the
    district court’s denial of their motion to dismiss for qualified immunity would produce an
    outcome contrary to clearly established law. Permitting the district court’s plainly
    erroneous ruling to stand would “seriously affect[] the fairness, integrity, or public
    reputation of judicial proceedings,” Richison, 
    634 F.3d at 1128
    , because 
    N.M. Stat. Ann. § 37-1-23
    (A) requires that Mr. Girón and Mr. Valerio are entitled to qualified immunity.
    -19-
    See Cordery, 
    656 F.3d at 1108
     (holding that the fourth element of plain error review was
    satisfied when the district court’s error would result in a 10 percent longer sentence). We
    conclude that the fourth element of plain error is satisfied. Our conclusion comports with
    the principle that “qualified immunity . . . is both a defense to liability and a limited
    entitlement not to stand trial or face the other burdens of litigation,” Iqbal, 129 S. Ct. at
    1945-46 (quotations omitted), and the “importance of resolving immunity questions at the
    earliest possible stage in litigation.” Pearson, 
    555 U.S. at 232
     (quotations omitted).
    ***
    For these reasons, the district court committed plain error by concluding that FSG-
    NM’s implied contract with NMDOT was a property interest under the due process
    clause. Because FSG-NM did not have a protected property interest in the Project
    Contract, there could be no deprivation of due process. Mr. Girón and Mr. Valerio are
    therefore entitled to qualified immunity on FSG’s procedural due process claim.
    B. Sufficiency of the Pleadings Under Fed. R. Civ. P. 8(a)
    Mr. Girón and Mr. Valerio also argue that the district court erred in denying their
    motion to dismiss based on insufficient notice pleading under Fed. R. Civ. P. 8(a).
    Assuming we have jurisdiction over this issue, we need not decide it because we reverse
    the district court’s denial of Mr. Girón and Mr. Valerio’s qualified immunity defense.
    III.   CONCLUSION
    We deny FSG’s motion to dismiss this appeal for lack of jurisdiction. We reverse
    the district court’s judgment denying Mr. Girón and Mr. Valerio’s motion to dismiss
    -20-
    FSG’s procedural due process claim based on qualified immunity and remand with
    directions to dismiss the §1983 claim brought against Mr. Girón and Mr. Valerio.
    Entered for the Court
    Scott M. Matheson, Jr.
    Circuit Judge
    -21-
    

Document Info

Docket Number: 11-2067

Citation Numbers: 465 F. App'x 774

Judges: Briscoe, Gorsuch, Matheson

Filed Date: 3/6/2012

Precedential Status: Non-Precedential

Modified Date: 8/5/2023

Authorities (32)

United States v. Cordery , 656 F.3d 1103 ( 2011 )

Leverington v. City of Colorado Springs , 643 F.3d 719 ( 2011 )

United States v. Ruiz-Gea , 340 F.3d 1181 ( 2003 )

County of Santa Fe v. Public Service Co. , 311 F.3d 1031 ( 2002 )

Gann v. Cline , 519 F.3d 1090 ( 2008 )

Kirkland v. St. Vrain Valley School District No. Re-1J , 464 F.3d 1182 ( 2006 )

sharlene-k-watson-v-university-of-utah-medical-center-dale-gunnell , 75 F.3d 569 ( 1996 )

Teigen v. Renfrow , 511 F.3d 1072 ( 2007 )

Dodds v. Richardson , 614 F.3d 1185 ( 2010 )

Hesse v. Town of Jackson, Wyo. , 541 F.3d 1240 ( 2008 )

United States v. Weeks , 653 F.3d 1188 ( 2011 )

Kansas Penn Gaming, LLC v. Collins , 656 F.3d 1210 ( 2011 )

Brown v. Montoya , 662 F.3d 1152 ( 2011 )

Southern Disposal, Inc. v. Texas Waste Management , 161 F.3d 1259 ( 1998 )

Conner v. Lavaca Hospital District , 267 F.3d 426 ( 2001 )

telena-d-woolsey-v-james-c-hunt-chancellor-of-university-of-tennessee , 932 F.2d 555 ( 1991 )

Stidham v. Texas Commission on Private Security , 418 F.3d 486 ( 2005 )

Pater v. City of Casper , 646 F.3d 1290 ( 2011 )

Richison v. Ernest Group, Inc. , 634 F.3d 1123 ( 2011 )

don-g-drake-v-ray-scott-director-of-arkansas-dept-of-human-services-dr , 823 F.2d 239 ( 1987 )

View All Authorities »