Newmont USA v. Insurance Co. of North America ( 2010 )


Menu:
  •                                                                   FILED
    United States Court of Appeals
    Tenth Circuit
    August 11, 2010
    PUBLISH                 Elisabeth A. Shumaker
    Clerk of Court
    UNITED STATES COURT OF APPEALS
    TENTH CIRCUIT
    NEWMONT U.S.A. LIMITED,
    formerly known as NEWMONT
    MINING CORPORATION, and
    N.I. LIMITED,
    Plaintiffs-Counter-Claim-
    Defendants-Appellants-
    Cross-Appellees,
    v.                                     Nos. 08-1347 and 08-1370
    INSURANCE COMPANY OF
    NORTH AMERICA,
    Defendant-Counter-
    Claimant-Appellee-
    Cross-Appellant.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLORADO
    (D.C. NO. 1:06-CV-1178-ZLW-BNB)
    Mark A. Wielga, Temkin Wielga Hardt & Longenecker LLP, Denver, Colorado
    (Nathan M. Longenecker and Jason B. Robinson, Temkin Wielga Hardt &
    Longenecker LLP, Denver, Colorado and Robert L. Tofel and Mark A. Lopeman,
    Tofel & Partners, LLP, New York, New York with him on the briefs) for
    Plaintiffs-Counter-Claim-Defendants-Appellants-Cross-Appellees.
    Lloyd A. Gura, Mound Cotton Wollan & Greengrass, New York, New York
    (Matthew J. Lasky, Mound Cotton Wollan & Greengrass, New York, New York
    and Andrew D. Ringel, Hall & Evans, Denver, Colorado with him on the briefs)
    for Defendant-Counter-Claimant-Appellee-Cross Appellant.
    Before TACHA, ALARCÓN *, and TYMKOVICH, Circuit Judges.
    TYMKOVICH, Circuit Judge.
    In this insurance matter, Newmont U.S.A. Limited (Newmont), f/k/a
    Newmont Mining Corporation, and N.I. Limited (NIL) brought suit against the
    Insurance Company of North America (INA). Newmont sought a declaratory
    judgment that NIL was no longer liable to INA for reinsurance arising out of
    policies INA had issued to Newmont, and an injunction barring INA from
    proceeding to arbitrate the companies’ disputes. The district court compelled
    arbitration and the arbitration panel found in INA’s favor, awarding money
    damages. The district court subsequently modified the portion of the arbitration
    panel’s award concerning post-judgment interest, and entered final judgment.
    On appeal, Newmont and NIL argue the district court erred by compelling
    arbitration. In a cross-appeal, INA contends the district court erred by altering
    the arbitration panel’s post-judgment interest rate determination and setting the
    post-judgment interest accrual date.
    Our jurisdiction arises under 28 U.S.C. § 1291. We find the district court
    properly compelled arbitration. We also conclude the district court should have
    applied the post-judgment interest rate set forth in the parties’ agreements and
    *
    The Honorable Arthur L. Alarcón, Senior Circuit Judge, United States
    Court of Appeals for the Ninth Circuit, sitting by designation.
    -2-
    incorrectly determined the start date for the accrual of post-judgment interest.
    Accordingly, we AFFIRM in part and REVERSE in part.
    I. Background
    During the early 1980s, INA issued general liability policies to Newmont,
    the parent corporation of NIL, 1 and certain of its subsidiaries and affiliates. INA
    and NIL, in turn, entered into three successive reinsurance agreements under
    which NIL committed to reinsure INA with respect to the policies INA had issued
    to Newmont. The last effective date of the applicable Reinsurance Agreements
    was July 18, 1985.
    For our purposes, the Reinsurance Agreements may be considered identical.
    Several provisions of the Agreements are relevant to our analysis of whether and
    when arbitration may be compelled. Article X of the Reinsurance Agreements
    provides: “As a condition precedent to any right of action hereunder, any dispute
    arising out of this Agreement shall be submitted to the decision of a board of
    arbitration . . . .” Aplt. App. at 22. And, Article XIII of the Reinsurance
    Agreements states: “Either party will pay to the other an interest charge at the
    monthly rate of . . . 1.5%[] on any amount that is not paid within the time
    required by this Agreement, said charge to commence at the time any such
    1
    At all times relevant to this case, Newmont was the parent corporation and
    owner of 100 percent of the stock in NIL.
    -3-
    payment is required by this Agreement.” 
    Id. at 23.
    Pennsylvania law governs the
    Reinsurance Agreements.
    In the early 1980s, the State of Colorado brought claims against two of
    Newmont’s subsidiaries, the Idarado Mining Company and the Resurrection
    Mining Company. In response, Newmont filed a declaratory judgment action
    against INA in state court, seeking defense coverage and indemnity from INA
    under the general liability policies.
    In 1997, INA and Newmont entered into a Settlement Agreement relating to
    the general liability policies. The Recitals section of the agreement states “this
    settlement resolves all claims of Newmont for insurance coverage for Idarado
    Environmental Claims” and “this settlement resolves only Newmont’s claims
    arising from the Idarado mining site and does not settle or resolve Newmont’s, or
    any other entity’s, claims arising from the Resurrection mining site or any other
    site . . . .” 
    Id. at 141S42.
    The 1997 Settlement Agreement also provides:
    INA . . . release[s] [NIL] from all claims . . . relating to the Declaratory
    Judgment Action . . . , which claims arise from any . . . reinsurance
    contract with [NIL]. The foregoing to the contrary notwithstanding,
    this release shall not apply to (I) claims by INA against [NIL] for
    reinsurance coverage . . . , which claims are based on alleged
    occurrences at the California Gulch Mining Site [(i.e., the Resurrection
    Site)] or any other site other than the Idarado Mining Site . . . .
    
    Id. at 147S48.
    In 2002, INA and Newmont entered into another Settlement Agreement.
    The Recitals section of that agreement states “this settlement resolves all claims
    -4-
    of Newmont for insurance coverage for Resurrection Environmental Claims” and
    “the [p]arties intend hereby to compromise, settle and finally resolve their
    disputes concerning the alleged application of the [general liability] [p]olicies to
    the Resurrection Environmental Claims . . . .” 
    Id. at 160.
    The 2002 Settlement
    Agreement also provides:
    INA . . . release[s] [NIL] . . . from all claims . . . relating to the
    Declaratory Judgment Action . . . , which arise . . . from any . . .
    reinsurance contract . . . of [NIL].
    The foregoing to the contrary notwithstanding, this release shall
    not apply to (I) claims by INA against [NIL] for reinsurance coverage
    . . . , on account of alleged occurrences at any site other than the
    California Gulch Mining Site or the Idarado Mining Site . . . . 2
    
    Id. at 165S66.
    Neither Settlement Agreement contains an arbitration provision. Both,
    however, contain merger clauses. And, both are to be construed according to
    Colorado law.
    In 2000, BHP Copper, Inc., a former Newmont subsidiary, sued INA in
    state court, seeking coverage under the general liability policies for
    environmental liabilities at BHP’s Pinal Creek Site (the BHP Litigation). INA
    drew upon a letter of credit from NIL in 2002 to reimburse itself for
    approximately $439,000 in costs it allegedly incurred defending the BHP
    Litigation. INA maintained it was due the money under the Reinsurance
    2
    The Resurrection Environmental Claims relate to the California Gulch
    Mining Site.
    -5-
    Agreements. In 2005, INA asserted another claim under the Reinsurance
    Agreements in the amount of approximately $517,000 for additional costs
    allegedly incurred defending the BHP Litigation. Newmont and NIL challenged
    INA’s draw on the letter of credit and claim for additional reimbursement.
    In 2006, INA demanded, under Article X of the Reinsurance Agreements,
    the parties’ dispute over reimbursement be arbitrated. Newmont and NIL
    responded by filing an action in state court, which was subsequently removed to
    federal district court, seeking a declaratory judgment that the Settlement
    Agreements released NIL from reinsurance liability with respect to the BHP
    Litigation, an injunction barring INA from proceeding to arbitration, and money
    damages. 3 The district court compelled arbitration. 4
    The arbitration panel issued a final award on December 21, 2007, finding
    for INA and against NIL in all material respects. The panel found in INA’s favor
    with regard to reimbursement under the Reinsurance Agreements and, based on
    3
    We note that, based on the terms of the 1997 and 2002 Settlement
    Agreements, Newmont has standing as the promisee to enforce those agreements
    on behalf of NIL, the third-party beneficiary of those agreements. See In re
    Kaplan, 
    143 F.3d 807
    , 813 (3d Cir. 1998) (noting that both a promisee and the
    third-party beneficiary may sue to enforce a contract); Cody Park Prop. Owners’
    Ass’n, Inc. v. Harder, --- P.3d ---, 
    2009 WL 4070874
    at *3 (Colo. App. 2009)
    (“The intent to benefit a third party need not be expressly referred to in the
    agreement, but must be apparent from the terms of the agreement or the
    surrounding circumstances.”).
    4
    The district court stayed Newmont and NIL’s action pending the
    completion of arbitration.
    -6-
    Article XIII of the Reinsurance Agreements, provided for pre- and post-judgment
    interest at the rate of 1.5 percent per month.
    The district court entered final judgment on September 19, 2008, nunc pro
    tunc June 5, 2008. Citing 9 U.S.C. § 11(b), the district court modified the
    arbitration panel’s award with respect to post-judgment interest, ordering that the
    post-judgment interest rate be set in accordance with 28 U.S.C. § 1961, rather
    than at the contract amount of 1.5 percent per month. In this instance, § 1961
    provided a lower interest rate than the contract. The district court also ordered
    that post-judgment interest begin to accrue after June 5, 2008.
    Newmont and NIL appeal the district court’s decision to compel arbitration,
    arguing that the Settlement Agreements released NIL from reinsurance and
    arbitration obligations existing under the Reinsurance Agreements. INA appeals
    the district court’s rulings setting the post-judgment interest rate in accordance
    with § 1961 and establishing June 5, 2008 as the post-judgment interest accrual
    date. INA contends the interest rate the arbitration award provided should be
    applied and that the accrual date should be the date judgment was entered,
    September 19, 2008.
    II. Discussion
    The district court’s granting of a motion to compel arbitration is reviewed
    de novo, see Riley Mfg. Co. v. Anchor Glass Container Corp., 
    157 F.3d 775
    , 779
    (10th Cir. 1998), as is the district court’s interpretation and application of § 1961,
    -7-
    see Soc’y of Lloyd’s v. Reinhart, 
    402 F.3d 982
    , 1003 (10th Cir. 2005). “In
    reviewing [the] district court’s confirmation of an arbitration award, we review
    factual findings for clear error and legal determinations de novo.” DMA Int’l,
    Inc. v. Qwest Commc’ns Int’l, Inc., 
    585 F.3d 1341
    , 1344 (10th Cir. 2009). With
    respect to the factual averments made in Newmont and NIL’s complaint, because
    the district court rendered its decision on the pleadings, we must accept them as
    true for purposes of this appeal. See 
    Riley, 157 F.3d at 779
    .
    A. Arbitration
    Newmont and NIL first challenge the district court’s decision to compel
    arbitration. They contend the district court improperly determined the
    reimbursement issue is within the scope of the arbitration clause contained in the
    Reinsurance Agreements and that the clause survived the expiration of those
    contracts and the entry into force of the Settlement Agreements. We disagree.
    Our cases hold unless the parties to an agreement “clearly and
    unmistakably” provide otherwise, “the question of arbitrability—whether a
    contract creates a duty for the parties to arbitrate the particular grievance—is
    undeniably an issue for judicial determination.” 
    Id. (internal punctuation
    omitted). Here, we cannot conclude INA and Newmont clearly and unmistakably
    provided that an arbitration panel, rather than a court, decide issues of
    arbitrability relating to the Reinsurance Agreements. The agreements are
    completely silent on the issue. Given the lack of contractual guidance, we look to
    -8-
    the district court to handle the question of whether the parties’ dispute concerning
    the BHP Litigation is arbitrable.
    Second, in deciding if a dispute is arbitrable, a court must initially
    determine whether the arbitration provision is broad or narrow. See Cummings v.
    FedEx Ground Package Sys., Inc., 
    404 F.3d 1258
    , 1261 (10th Cir. 2005). “Where
    the arbitration clause is broad, there arises a presumption of arbitrability and
    arbitration of even a collateral matter will be ordered if the claim alleged
    implicates issues of contract construction or the parties’ rights and obligations
    under it.” 
    Id. (internal quotation
    marks omitted). Looking to the plain language
    of the arbitration provision contained in the Reinsurance Agreements, including
    its use of the phrase “arising out of,” we have little trouble determining that it is a
    broad provision. 5 We find therefore the arbitration provision pertaining to the
    Reinsurance Agreements covers the parties’ dispute. In reaching this conclusion,
    we bear in mind that “any doubts concerning the scope of arbitrable issues should
    be resolved in favor of arbitration.” Moses H. Cone Mem’l Hosp. v. Mercury
    Const. Corp., 
    460 U.S. 1
    , 24S25 (1983).
    5
    Generally, when an arbitration provision provides for any dispute “arising
    out of” a particular contract, the provision is construed broadly to suggest that a
    given dispute is arbitrable. Miron v. BDO Seidman, LLP, 
    342 F. Supp. 2d 324
    ,
    330 (E.D. Pa. 2004) (addressing an agreement in accordance with the Federal
    Arbitration Act and Pennsylvania law); see also Williams v. Imhoff, 
    203 F.3d 758
    ,
    765S66 (10th Cir. 2000) (“[W]e believe [the phrase, ‘arising out of,’] must be
    broadly construed to mean ‘originating from,’ ‘growing out of,’ or ‘flowing
    from.’”).
    -9-
    Third, an arbitration clause in a contract is presumed to survive the
    expiration of that contract. This presumption might be overridden given some
    express or clearly implied evidence that the parties intended to override that
    presumption, or the relevant dispute cannot be said to have arisen under the
    previous contract. See 
    Riley, 157 F.3d at 781
    . A dispute “arises under” a
    previous contract if it involves rights that to some degree vested or accrued
    during the life of the contract and merely ripened after expiration, or relates to
    events that occurred at least in part while the contract was still in effect. See 
    id. Here, the
    Settlement Agreements do not evidence the parties’ express or
    clearly implied intent to repudiate post-expiration arbitrability. An examination
    of the Settlement Agreements in their entirety reveals that they were intended to
    resolve claims relating to the Idarado and Resurrection sites only—claims
    concerning reinsurance coverage for the BHP Litigation were not released. 6 Also,
    there can be no doubt that the parties’ dispute over the BHP Litigation “arose
    6
    Under Colorado law, in determining the meaning of a contract, courts
    must analyze the entire instrument and not view provisions or phrases in isolation.
    See Level 3 Commc’ns, LLC v. Liebert Corp., 
    535 F.3d 1146
    , 1154 (10th Cir.
    2008). “Recitals . . . cannot extend contractual stipulations, [but] they may have
    material influence on the construction of the instrument . . . .” Engineered Data
    Prods., Inc. v. Nova Office Furniture, Inc., 
    849 F. Supp. 1412
    , 1417 (D. Colo.
    1994) (discussing Colorado law). Also, “while every relevant provision must be
    considered and given effect, a more specific provision controls the effect of
    general provisions.” Level 
    3, 535 F.3d at 1154
    (internal quotation marks
    omitted). Further, absent indication by the parties to the contrary, a contract’s
    language must be construed in accordance with the plain meaning of the words
    used. See 
    id. -10- under”
    the Reinsurance Agreements. The BHP Litigation dispute concerns rights
    that vested and events that took place, at least in part, while the Reinsurance
    Agreements were in effect.
    The arbitration provision in the Reinsurance Agreements encompasses the
    parties’ dispute concerning the BHP Litigation and neither the Reinsurance
    Agreements’ expiration nor the Settlement Agreements extinguish arbitrability.
    Accordingly, the district court did not err in compelling arbitration.
    B. Post-Judgment Interest Rate
    INA contends the district court erred by altering the post-judgment interest
    rate provided in the arbitration panel’s final award. The district court replaced
    the post-judgment interest rate the arbitration panel established with the rate set
    forth in § 1961. In doing so, the district court modified the arbitration panel’s
    award pursuant to § 11(b) on the understanding that it could modify the
    arbitration award where the arbitration panel awarded upon matters not submitted
    for arbitration. See 9 U.S.C. § 11(b). INA argues the district court’s alteration of
    the arbitration award based on § 11(b) was in error because the arbitration panel
    had the authority to decide the post-judgment interest issue. We agree.
    As discussed above, a broad arbitration clause gives rise to the presumption
    of arbitrability and arbitration of a collateral matter will be ordered if it
    implicates issues of contract construction or the parties’ contractual rights and
    obligations. See 
    Cummings, 404 F.3d at 1261
    . Doubts about the arbitrability of
    -11-
    an issue should to be resolved in favor of arbitration. See Mem’l 
    Hosp., 460 U.S. at 25
    . In addition, we are reminded that, “[o]nce an arbitration award is entered,
    the finality of arbitration weighs heavily in its favor and cannot be upset except
    under exceptional circumstances.” 
    DMA, 585 F.3d at 1344
    (internal quotation
    marks omitted); see also LB&B Assocs., Inc. v. Int’l Bhd. of Elec. Workers, Local
    No. 113, 
    461 F.3d 1195
    , 1197 (10th Cir. 2006) (“Whether the arbitrator’s reading
    of the agreement was strained or even seriously flawed is irrelevant. As long as
    the arbitrator is even arguably construing . . . the contract and acting within the
    scope of his authority, that a court is convinced he committed serious error does
    not suffice to overturn his decision.”) (internal quotation marks, alterations, and
    citation omitted).
    Here, as we have already determined, the arbitration provision contained in
    the Reinsurance Agreements is a broad provision. Also, because parties may set
    their own rate of post-judgment interest through contract, see Westinghouse
    Credit Corp. v. D’Urso, 
    371 F.3d 96
    , 101 (2d Cir. 2004) (cited favorably in
    
    Reinhart, 402 F.3d at 1004
    ), determining the rate of post-judgment interest to be
    applied to the money damages the arbitration panel awarded implicates Article
    XIII of the Reinsurance Agreements. Article XIII provides for an interest rate of
    1.5 percent per month on any amount due under the Reinsurance Agreements. See
    3 T HOMAS H. O EHMKE , C OMMERCIAL A RBITRATION § 124:2 (2010) (“Parties may
    ‘contract out’ of statutory interest rates if their agreement expresses the parties’
    -12-
    intent to deviate from a post-judgment interest rate set by statute. Arbitrators
    must honor an agreement as to the amount of interest on an award . . . .”). And
    nothing in the Reinsurance Agreements purports to limit the arbitration panel’s
    authority to decide post-judgment interest issues. 7 Accordingly, we find that the
    matter of post-judgment interest was properly before the arbitration panel. See
    United Steelworkers of Am. v. Enter. Wheel & Car Corp., 
    363 U.S. 593
    , 599
    (1960) (“It is the arbitrator’s construction which was bargained for . . . .”); see
    also Tanoma Mining Co. v. Local Union No. 1269, United Mine Workers of Am.,
    
    896 F.2d 745
    , 747 (3d Cir. 1990) (“[Because] the parties have bargained for the
    arbitrator’s decision, it is the arbitrator’s view of the facts and of the meaning of
    the contract that they have agreed to accept.”) (internal quotation marks omitted).
    Neither § 1961 nor caselaw directs a different conclusion. An agreement to
    apply a post-judgment interest rate other than that § 1961 specifies is enforceable
    so long as the parties indicate their intent to override the statute using “clear,
    unambiguous and unequivocal language.” 
    Reinhart, 402 F.3d at 1004
    . The
    parties’ intent is a quintessential fact question, and we see no reason why an
    arbitration panel with authority to decide a contractual dispute cannot also
    7
    We also note the fact that the parties made arguments before the
    arbitration panel concerning Article XIII and the post-judgment interest issue
    further supports our conclusion the arbitration panel was authorized to address the
    issue. See, e.g., Carpenter Local No. 1027, Mill Cabinet-Indus. Div. v. Lee
    Lumber and Bldg. Material Corp., 
    2 F.3d 796
    , 799 (7th Cir. 1993) (“[T]he
    agreement to arbitrate a particular issue may be implied from the parties’ conduct,
    including their actual litigation of that issue.”).
    -13-
    determine whether the contract in question includes language clearly,
    unambiguously, and unequivocally stating the parties’ intent to bypass § 1961.
    See Ansari v. Qwest Commc’ns Corp., 
    414 F.3d 1214
    , 1220 (10th Cir. 2005)
    (quoting Ormsbee Dev. Co. v. Grace, 
    668 F.2d 1140
    , 1146 (10th Cir.1982), for
    the proposition that, when parties agree to submit a dispute to arbitration, it is
    presumed that the arbitrator is authorized to determine all issues of law and fact
    necessary to resolve the dispute). “While [§ 1961] employs mandatory
    language, . . . this is aimed mainly at precluding district courts from exercising
    discretion over the rate of interest or adopting an interest rate set by arbitrators,
    not at limiting the ability of private parties to set their own rates through
    contract.” See 
    D’Urso, 371 F.3d at 101
    . Consistent with § 1961, an arbitration
    panel may not establish a post-judgment interest rate itself, but it may determine
    whether the parties have sufficiently contracted for their own rate and, if they
    have, indicate that rate should be applied.
    Because the post-judgment interest issue was arbitrable under the
    Reinsurance Agreements, the arbitration panel had the authority to determine the
    issue. The district court therefore erred by modifying the final award based on
    § 11(b).
    -14-
    C. Interest Accrual Date
    The last issue involves the applicable date interest begins accruing. INA
    contends the district court erred by fixing June 5, 2008 as the date after which
    post-judgment interest should begin to accrue. We agree. In this case, § 1961
    mandates a post-judgment interest accrual date of September 19, 2008.
    Section 1961 provides the statutorily determined post-judgment interest rate
    goes into effect on the date of the entry of judgment. See 28 U.S.C. § 1961
    (“Such interest shall be calculated from the date of the entry of the
    judgment . . . .”). Judgment is entered when the district court files a separate
    document in accordance with Rule 58 of the Federal Rules of Civil Procedure.
    See Youngs v. Am. Nutrition, Inc., 
    537 F.3d 1135
    , 1146 (10th Cir. 2008); see also
    Hull v. United States, 
    971 F.2d 1499
    , 1507S09 (10th Cir. 1992) (holding the
    district court’s nunc pro tunc order establishing an earlier date as the relevant
    judgment date for purposes of § 1961 was invalid because the district court had
    not satisfied Rule 58 prior to issuing its nunc pro tunc order). Here, judgment
    was not entered in accordance with Rule 58 until September 19, 2008.
    Consequently, the district court’s Judgment, dated September 19, 2008, nunc pro
    tunc June 5, 2008, did not establish June 5, 2008 as the date of the entry of
    judgment for purposes of § 1961.
    The district court thus erred in identifying June 5, 2008 as the post-
    judgment interest accrual date. The district court should have identified
    -15-
    September 19, 2008—the date on which a valid judgment was entered—as the
    date of accrual.
    III. Conclusion
    For the foregoing reasons, we find the district court rightly compelled
    arbitration, but erred by modifying the post-judgment interest rate and in setting
    the post-judgment interest accrual date. We AFFIRM in part and REVERSE in
    part.
    -16-
    

Document Info

Docket Number: 08-1347

Filed Date: 8/11/2010

Precedential Status: Precedential

Modified Date: 10/14/2015

Authorities (19)

In Re Manuel Kaplan, Debtor. Manuel Kaplan Arthur ... , 143 F.3d 807 ( 1998 )

Dma Intern., Inc. v. Qwest Communications Intern. , 585 F.3d 1341 ( 2009 )

Level 3 Communications, LLC v. Liebert Corp. , 535 F.3d 1146 ( 2008 )

LB & B Associates, Inc. v. International Brotherhood of ... , 461 F.3d 1195 ( 2006 )

riley-manufacturing-company-inc-plaintiff-counter-defendant-appellee-v , 157 F.3d 775 ( 1998 )

Ansari v. Qwest Communications Corp. , 414 F.3d 1214 ( 2005 )

westinghouse-credit-corporation-nka-cbs-corporation-westinghouse , 371 F.3d 96 ( 2004 )

ormsbee-development-company-a-wyoming-corporation-v-corrine-grace-and , 668 F.2d 1140 ( 1982 )

Tanoma Mining Company, Inc. v. Local Union No. 1269, United ... , 896 F.2d 745 ( 1990 )

Cummings v. Fedex Ground Package System, Inc. , 404 F.3d 1258 ( 2005 )

Youngs v. American Nutrition, Inc. , 537 F.3d 1135 ( 2008 )

society-of-lloyds-v-richard-a-reinhart-society-of-lloyds-v-grant-r , 402 F.3d 982 ( 2005 )

phillip-lee-hull-a-minor-by-his-natural-parents-guardians-and-personal , 971 F.2d 1499 ( 1992 )

Williams v. Imhoff , 203 F.3d 758 ( 2000 )

carpenter-local-no-1027-mill-cabinet-industrial-division-affiliated-with , 2 F.3d 796 ( 1993 )

United Steelworkers v. Enterprise Wheel & Car Corp. , 80 S. Ct. 1358 ( 1960 )

Moses H. Cone Memorial Hospital v. Mercury Construction ... , 103 S. Ct. 927 ( 1983 )

Engineered Data Products, Inc. v. Nova Office Furniture, ... , 849 F. Supp. 1412 ( 1994 )

Miron v. BDO Seidman, LLP , 342 F. Supp. 2d 324 ( 2004 )

View All Authorities »