Digital Ally, Inc. v. Z3 Technology, LLC , 754 F.3d 802 ( 2014 )


Menu:
  •                                                                               FILED
    United States Court of Appeals
    Tenth Circuit
    May 16, 2014
    PUBLISH                      Elisabeth A. Shumaker
    Clerk of Court
    UNITED STATES COURT OF APPEALS
    TENTH CIRCUIT
    DIGITAL ALLY, INC.,
    Plaintiff-Counter
    Defendant-Cross Defendant -
    Appellant/Cross-Appellee,
    v.                                                     Nos. 12-3258 & 12-3268
    Z3 TECHNOLOGY, LLC,
    Defendant-Counterclaimant-Third
    Party Plaintiff - Appellee/Cross-
    Appellant.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF KANSAS
    (D.C. No. 2:09–CV–02292–KGS)
    James F.B. Daniels of McDowell, Rice, Smith & Buchanan, Kansas City, Missouri, for
    Appellant/Cross-Appellee.
    Mark E. Wilson (Meghan A. Welch and Jeremy D. Kerman with him on the briefs) of
    Kerns, Frost & Pearlman, LLC, Chicago, Illinois, for Appellee/Cross-Appellant.
    Before MATHESON, McKAY, and EBEL, Circuit Judges.
    McKAY, Circuit Judge.
    This diversity case arises out of two contracts between the parties to this litigation.
    Both parties have filed appeals, in which Appellant–Cross-Appellee Digital Ally mainly
    challenges the validity and enforceability of one of the contracts, while Appellee–Cross-
    Appellant Z3 Technology challenges certain elements of the damages award.
    I. Background
    The contracts at issue in this case related to Z3’s design and manufacturing of
    circuit board modules for use in Digital’s products. The first contract, signed in
    November 2008, called for Z3 to design, manufacture, and deliver to Digital 1,000
    modules incorporating Texas Instruments’ DM355 computer chip. The second contract,
    signed on January 2, 2009, involved a larger quantity of modules that would use Texas
    Instruments’ next-generation DM365 chip. Both contracts were signed by Robert Haler,
    who was then Digital’s Executive Vice President of Engineering and Production. The
    contracts were described as “Production License Agreement[s],” and they expressly
    provided that the modules would be licensed, not sold, to Digital. (Appellant’s App. at
    39, 52.) The contracts both stated they would “be governed by and interpreted in
    accordance with the laws of the State of Nebraska, without reference to conflict of laws
    principles.” (Id. at 43, 58.)
    The 2008 contract called for Digital to make a total payment of $155,000 in
    exchange for Z3’s design and delivery of the 1,000 DM355-based modules. Digital paid
    the first $140,000 required by the contract, but it refused to make the final $15,000
    payment. Digital claimed that the DM355 modules provided by Z3 had hardware and/or
    -2-
    software design flaws that resulted in “pink noise” and other problems.1 The jury
    ultimately found that both parties had breached the contract, Digital by failing to pay the
    final $15,000, and Z3 by failing to satisfy the contract’s hardware warranties. The jury
    awarded $15,000 to Z3 for Digital’s breach of its payment obligations, while it awarded
    $30,000 to Digital for Z3’s failure to satisfy the contract’s hardware warranties. On
    appeal, the only issue we must consider regarding the 2008 contract is Z3’s argument that
    it was entitled to prejudgment interest on the $15,000 award.
    The 2009 contract, which is the main subject of this appeal, was a somewhat more
    complex contract than the 2008 contract. Unlike the 2008 contract, this contract did not
    simply call for a specific total payment in exchange for a specific number of modules.
    Rather, the contract included various types of payments Digital would be required to
    make at different points of the process. First, after setting out a twenty-eight-week design
    schedule, the contract listed a payment schedule for $300,000 in fees that were payable
    during the design period. Next, ¶ 14 of the contract—entitled “Guaranteed Minimum
    Purchase Quantity or Minimum Royalty”—required Digital to fulfill several purchase
    and/or royalty obligations at various times during the contract period. (Id. at 62 (bolding
    omitted).) Specifically, the first subsection of ¶ 14 obligated Digital to make a minimum
    purchase of fifty pre-production samples at a cost of $200 per unit. Subsection (b)(ii) of ¶
    14 then provided for an “initial production order (guaranteed) of 3,000 units @
    1
    “Pink noise” refers here to a problem that “manifest[ed] as an intermittent
    colored spot on a video screen” during video playback. (Appellant’s App. at 1109.)
    -3-
    $100/unit.” (Id. at 63 (capitalization omitted).) Finally, subsection (b) of ¶ 14 included
    the following terms:
    iii)    Minimum 12,000 units or equivalent Royalty PER YEAR for 3
    years.
    (1)     LICENSEE [Digital] will provide LICENSOR [Z3] 1st opportunity to
    manufacture modules given LICENSOR’s per module pricing,
    quality, and delivery are competitive with alternative manufacturers,
    including consideration of royalty cost for non-Z3 manufactured
    modules.
    (2)     Module price ESTIMATED TARGET is $100/module assuming
    similar [printed circuit board] layer, component, and architecture to
    [the modules manufactured pursuant to the 2008 contract]. FINAL
    PER/MODULE PRICE WILL BE AGREED AFTER
    COMPLETION OF FINAL HARDWARE DESIGN AND
    SUBMISSION OF FINAL BOM [(BILL OF MATERIALS)] TO
    LICENSEE. Specialized components may affect this pricing.
    Pricing is reviewed between LICENSOR and LICENSEE every 90
    days. LICENSOR will provide LICENSEE 100% complete BOM
    for LICENSEE’s use in cost analysis. BOM must include all
    manufacturer names and manufacturer part numbers.
    (3)     Production Payment Terms: Net 30 days[.]
    (4)     Production Lead Time: estimated 10 weeks[.]
    iv)     If LICENSOR cannot provide on-time delivery, a price and quality
    acceptable to LICENSEE, or is not willing to produce [the DM365-based
    module], then LICENSEE has the right to use alternative manufacturing.
    LICENSEE is liable for royalty of $7.50 per unit on modules actually
    SOLD BY LICENSEE on all modules not manufactured by Z3. []If
    LICEN[S]EE does not order 36,000 units at 12,000 units per year,
    LICENSEE is [to] pay a minimum royalty to LICENSOR equivalent to
    12,000*$7.500 = $90,000 royalty per calendar year or the pro-rated balance
    if at least some units have been purchased within the fiscal year in question.
    ...
    (Id. at 63.)
    Initially, both parties began performing their various obligations under the
    contract. Digital paid the first two payments required under the payment schedule,
    -4-
    $75,000 in January 2009 and $50,000 in February 2009, and both sides spent time
    working on the module’s design. However, in April 2009, Digital sent Z3 a letter
    purporting to terminate the contract. It is undisputed that this letter did not comply with
    the contractual termination requirements, which included a notice-and-cure period.
    However, in accordance with Digital’s letter, Z3 stopped its design work on the DM365-
    based module. Accordingly, no DM365 modules were ever completed by Z3.
    After repudiating the 2009 contract, Digital filed a lawsuit in the Kansas district
    court seeking a declaration that the 2009 contract was validly rescinded or void because
    Executive Vice President Haler, the Digital officer who signed this contract, lacked the
    authority to do so as a result of a change in Digital’s internal signature policies in
    December 2008. Digital also raised a claim based on the 2008 contract, alleging that Z3
    breached this contract by delivering faulty modules that did not satisfy the contractual
    warranties. Z3 filed a counterclaim in which it alleged, among other things, that Digital
    breached both contracts by failing to pay the final $15,000 due on the 2008 contract and
    by repudiating and failing to fulfill its performance obligations under the 2009 contract.2
    The district court resolved several legal issues relating to the 2009 contract in
    various summary judgment rulings. The district court concluded that the undisputed facts
    showed that (1) Vice President Haler had at least apparent authority to sign the contract,
    2
    Z3 also filed a third-party complaint against Vice President Haler. Z3’s claims
    against Vice President Haler were ultimately settled outside of court, and they are not
    pertinent to this appeal.
    -5-
    (2) any failure on Z3’s part to satisfy any conditions precedent was excused because
    Digital prevented Z3’s performance, and (3) Digital breached the contract by its
    anticipatory repudiation. The district court then concluded that Z3 was entitled as a matter
    of law to the remaining $175,000 of design fees that Digital had failed to pay under the
    payment schedule. As for the three-year minimum purchase or equivalent royalty
    provisions of ¶ 14(b)(iii) and (iv) of the contract, the district court rejected Z3’s argument
    that it was entitled to lost profits for the minimum production orders of 12,000 units per
    year. The court concluded that this portion of the contract created an alternative contract
    under which Digital could perform its contractual obligations by either purchasing 12,000
    units per year for three years or by paying the equivalent royalty of $90,000 per year.
    The court then concluded that Z3’s damages were limited to the alternative that resulted in
    the lesser recovery—the $270,000 total royalty payment. The court thus concluded Z3
    was entitled as a matter of law to recover $270,000 for Digital’s failure to comply with
    the purchase-or-royalty provisions of ¶ 14(b)(iii) and (iv). As for the earlier contractual
    provisions requiring Digital to purchase a minimum pre-production order of 50 units and
    an initial production order of 3,000 units, these provisions lacked a similar royalty
    alternative. Moreover, disputed facts regarding Z3’s costs and overhead prevented the
    district court from resolving the question of Z3’s lost profits for these 3,050 units as a
    matter of law. The district court accordingly denied summary judgment as to this element
    of damages, although it granted summary judgment on the question of breach.
    Following a lengthy jury trial, the jury found Z3 was entitled to an additional
    -6-
    $100,000 in damages for Digital’s breach of the 2009 contract. The jury also found both
    parties had breached the 2008 contract, and it awarded $15,000 in damages to Z3 and
    $30,000 in damages to Digital on their respective claims based on this contract.
    Z3 subsequently filed a motion asking the district court to award Z3 prejudgment
    interest for its $15,000 award on the 2008 contract and for the $175,000 in design fees
    and $270,000 in royalties that the district court had concluded Z3 was entitled to as a
    matter of law for Digital’s breach of the 2009 contract. The district court denied this
    motion.
    Digital then appealed, and Z3 filed a cross-appeal. On appeal, Digital challenges
    the district court’s summary judgment rulings regarding the validity and enforceability of
    the 2009 contract. Digital also argues the district court erred in allowing Z3 to recover
    $100,000 in lost profits based on Digital’s failure to purchase the minimum pre-
    production and initial production orders. In its cross-appeal, Z3 argues the district court
    erred by interpreting ¶ 14(b)(iii) and (iv) as setting forth alternative performance
    obligations and by holding that Z3 was only entitled to recover the $270,000 royalty and
    not its lost profits as damages for Digital’s breach of these provisions. Z3 further argues
    the district court erred in denying Z3’s request for prejudgment interest.
    II. Digital’s appeal
    We first consider Digital’s challenge to the district court’s summary judgment
    rulings regarding the validity and enforceability of the 2009 contract. We review the
    district court’s summary judgment decisions de novo, applying the same standard as the
    -7-
    district court. Ribeau v. Katt, 
    681 F.3d 1190
    , 1194 (10th Cir. 2012). Under this standard,
    “[t]he court shall grant summary judgment if the movant shows that there is no genuine
    dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
    Fed. R. Civ. P. 56(a). The parties agree the substantive issues in this case are governed
    by Nebraska law based on the contracts’ choice-of-law provisions.
    Digital argues there are three reasons why the district court should have granted
    Digital’s motion for summary judgment and denied Z3’s motion for summary judgment
    on the parties’ claims relating to the 2009 contract. First, Digital argues the contract is
    totally or at least partially unenforceable based on several unfulfilled conditions
    precedent. Second, Digital contends the contract was not binding on Digital because Vice
    President Haler lacked the authority to unilaterally sign contracts of this nature, due to a
    recently approved change in Digital’s internal policies regarding its officers’ authority to
    sign certain types of documents on behalf of the company. Third, Digital argues that Z3
    could not successfully bring an action on the 2009 contract because Z3 failed to
    substantially perform its own obligations under the contract. We consider each of these
    arguments in turn.
    A. Purported Conditions Precedent
    Digital argues the district court should have granted summary judgment in favor of
    Digital based on various unfulfilled conditions precedent. “The law of Nebraska is
    consistent with the recognized definitions which hold that a condition precedent is either
    a condition which must be performed before a contract becomes binding upon the parties
    -8-
    to it or must be fulfilled before a duty arises to perform the obligations of an already
    existing contract.” Omaha Pub. Power Dist. v. Emp’rs’ Fire Ins. Co., 
    327 F.2d 912
    , 915
    (8th Cir. 1964). Therefore, “[u]nder Nebraska law, ‘where a contract is executed but its
    effectiveness or fulfillment is dependent upon the doing of an agreed-upon condition
    before it shall become a binding contract, such contract cannot be enforced unless the
    condition is performed.’” AMISUB, Inc. v. Shalala, 
    12 F.3d 840
    , 844 (8th Cir. 1994)
    (quoting Metschke v. Marxsen, 
    125 N.W.2d 684
    , 687 (Neb. 1964)). “However, it is
    equally true that a condition is excused if the occurrence of the condition is prevented by
    the party whose [contractual obligations are] dependent upon the condition.” Chadd v.
    Midwest Franchise Corp., 
    412 N.W.2d 453
    , 457 (Neb. 1987). In other words, “if a
    promisor prevents or hinders the occurrence of a condition precedent, the condition is
    excused.” 
    Id. In Chadd,
    as in this case, the breaching party in a contract case claimed the other
    party could not succeed on its breach of contract claim because of unfulfilled conditions
    precedent. The defendant in Chadd, Midwest Franchise Corp., argued the plaintiffs failed
    to fulfill several conditions precedent, since they “never submitted a bid as required,
    could not keep construction costs within the stated cost estimate, never attached a
    required addendum setting forth exact rental costs, and did not complete the building or
    deliver possession of such to Midwest for its acceptance.” 
    Id. at 458.
    Midwest argued
    that because its own duties to perform were premised on these conditions precedent, the
    nonoccurence of these conditions prevented the plaintiffs from succeeding on a breach of
    -9-
    contract claim against Midwest. In turn, the plaintiffs argued in part “that they were
    unable to ever satisfy these conditions precedent due to the appellee’s repudiation of the
    contract.” 
    Id. While the
    Nebraska Supreme Court noted there was a factual dispute as to
    whether an anticipatory repudiation had occurred, it agreed with the plaintiffs’ legal
    argument that the nonoccurrence of the conditions precedent would not bar their contract
    claim if Midwest had prevented the occurrence of these conditions by repudiating the
    contract. “In a case such as this where one party (Chadds) has not fulfilled certain
    conditions precedent to the other party’s (Midwest’s) duty to perform, a special rule of
    law applies. Where a party’s repudiation contributes materially to the nonoccurrence of a
    condition of one of his duties, the nonoccurence is excused.” 
    Id. On appeal,
    Digital suggests that Chadd has been limited by the Nebraska Supreme
    Court’s subsequent statement in Lee Sapp Leasing, Inc. v. Catholic Archbishop of
    Omaha, 
    540 N.W.2d 101
    , 105 (Neb. 1995), that “[t]he nonoccurrence of a condition
    precedent cannot be excused if occurrence of the condition was a material part of the
    agreed exchange.” However, the Nebraska Supreme Court made this statement in
    discussing a different rule under which a court may excuse the nonoccurrence of a
    condition to avoid a disproportionate forfeiture. Nothing about the court’s discussion in
    Lee Sapp suggests that it was intended to affect the Chadd rule’s reach, limiting Chadd to
    non-material conditions and thus allowing breaching parties to escape liability for their
    breach so long as they successfully prevented or hindered material conditions from
    occurring. We conclude that Nebraska courts would continue to apply the reasoning from
    -10-
    Chadd to hold that the nonoccurence of a condition precedent is excused when the
    occurrence of the condition was prevented or hindered by the breaching party, regardless
    of whether this condition was material or not. After thoroughly reviewing the record and
    Digital’s arguments on appeal, we also conclude that the nonoccurrence of any of the
    conditions precedent identified by Digital in this case resulted from Digital’s unequivocal
    repudiation of the contract. Thus, the nonoccurence of any of these purported conditions
    precedent is excused and does not bar Z3 from successfully pursuing a breach of contract
    claim against Digital.
    Digital also raises the related argument that the purchase-or-royalty provisions in ¶
    14(b)(iii) and (iv) are unenforceable because these provisions gave only an estimated
    purchase price for the production modules and stated that the final price would not be
    agreed upon until after the final hardware design had been completed. Digital argues that
    the failure to state a specific price renders this provision unenforceable as a matter of law.
    For support, Digital cites to a case in which a Nebraska appellate court held that a
    contract was not enforceable at the time it was executed because it failed to define the
    quantity of goods to be sold under the contract, the price any goods would be sold for, or
    any type of method for determining the price. MBH, Inc. v. John Otte Oil & Propane,
    Inc., 
    727 N.W.2d 238
    , 248 (Neb. App. 2007). We are not persuaded that this case bars
    Z3’s recovery under ¶ 14(b)(iii) and (iv). In contrast to the contract at issue in MBH, the
    contract at issue in this case contained both a quantity and an estimated price for the
    goods. A purported contract will usually be considered “too indefinite to form a contract
    -11-
    if the essential terms are left open or are so indefinite that a court could not determine
    whether a breach had occurred or provide a remedy,” Stitch Ranch, LLC v. Double BJ
    Farms, 
    837 N.W.2d 870
    , 883 (Neb. App. 2013), but “‘the actions of the parties may show
    conclusively that they have intended to conclude a binding agreement, even though one or
    more terms are missing or are left to be agreed upon,’” City of Scottsbluff v. Waste
    Connections of Neb., 
    809 N.W.2d 725
    , 740 (Neb. 2011) (quoting Restatement (Second)
    of Contracts § 33, cmt. a). Where a purported contract provides neither a quantity nor a
    price for the goods to be sold, as in MBH, the agreement is too indefinite to bind the
    parties absent other indications of the parties’ intent. See 
    MBH, 727 N.W.2d at 249
    (noting that an unenforceable agreement “may become enforceable when the missing
    term is subsequently supplied by the parties”). In this case, however, the 2009 contract
    and the parties’ actions demonstrated an intent to be bound, and the terms of the contract
    were sufficiently definite for a court both to determine whether a breach had occurred and
    to provide a remedy for the breach. Moreover, as we discuss in further detail below, we
    agree with the district court that the contract specified an alternative performance
    option—a minimum royalty of $7.50 per unit for the 36,000 modules Digital was
    otherwise obligated to purchase—that was not based in any way on the as-yet-unfinalized
    price for the modules, and we affirm the district court’s decision to award damages based
    on this alternative. For both of these reasons, we reject Digital’s argument that ¶
    14(b)(iii) and (iv) are too uncertain and indefinite to be enforced.
    -12-
    B. Vice President Haler’s Authority to Sign the Contract
    Next, Digital contends the 2009 contract was not binding on Digital because Vice
    President Haler’s authority to enter into this type of contract had been limited by an
    internal change to Digital’s policies in December 2008. However, we conclude that Vice
    President Haler clearly had at least apparent authority to sign the 2009 contract, and we
    thus need not resolve the dispute over whether Vice President Haler had actual authority
    to sign the contract on behalf of Digital.
    The parties assume that Nevada law applies to the question of apparent authority,
    due to the fact that Digital is incorporated under the laws of Nevada, and we will
    accordingly proceed under the same assumption. See Grynberg v. Total SA, 
    538 F.3d 1336
    , 1346 (10th Cir. 2008) (applying Colorado law because the parties assumed
    Colorado law applied). Under Nevada law, “[a] party claiming apparent authority of an
    agent as a basis for contract formation must prove (1) that he subjectively believed that
    the agent had authority to act for the principal and (2) that his subjective belief in the
    agent’s authority was objectively reasonable.” Great Am. Ins. Co. v. Gen. Builders, 
    934 P.2d 257
    , 261 (Nev. 1997). In this case, Digital contests only the second prong of this
    test, arguing that Z3’s subjective belief in Vice President Haler’s authority to sign the
    2009 contract was not objectively reasonable because it was not based upon anything
    Digital had done.
    As Digital notes, the Nevada Supreme Court “has repeatedly ruled that apparent
    authority (when in excess of actual authority) proceeds on the theory of equitable
    -13-
    estoppel; it is in effect an estoppel against the alleged principal to deny agency when by
    his conduct he has clothed the agent with apparent authority to act.” Tsouras v. Sw.
    Plumbing & Heating, 
    587 P.2d 1321
    , 1323 (Nev. 1978) (internal quotation marks and
    brackets omitted). Accordingly, “‘[i]t is indispensable to keep in mind here that, as
    against the principal, there can be reliance only upon what the principal himself has said
    or done, or at least said or done through some other and authorized agent.’” 
    Id. (quoting Ellis
    v. Nelson, 
    233 P.2d 1072
    , 1076 (Nev. 1951)). The agent’s acts alone are not
    sufficient to establish apparent authority; rather, if the agent’s acts, rather than the
    principal’s acts, are relied upon, there must be “‘evidence of the principal’s knowledge
    and acquiescence in them.’” 
    Id. (quoting Ellis
    , 233 P.2d at 1076).
    Digital argues there is no evidence in this case that Digital or one of its other
    agents did or said anything which would suggest that Vice President Haler had the
    authority to enter into the 2009 contract. Digital contends the only actions suggestive of
    authority were taken by Vice President Haler himself, and Digital argues that this was
    insufficient as a matter of law to establish apparent authority. However, we are persuaded
    that Digital’s own actions established apparent authority. First, Digital took the action of
    bestowing upon Vice President Haler the title of Executive Vice President of Engineering
    and Production. This action in itself suggested that Vice President Haler might have the
    authority to enter into engineering and production contracts like the contracts at issue
    here. See Bucher & Willis Consulting Eng’rs v. Smith, 
    643 P.2d 1156
    , 1159 (Kan. App.
    1982) (noting that a principal’s words or actions suggesting that an agent has authority are
    -14-
    sometimes “overt and explicit,” but that “[i]n other cases, the mere relationship between
    the agent and principal or the title conferred upon the agent by the principal is sufficient
    to constitute a representation of some authority”). Indeed, Digital’s corporate bylaws
    explicitly stated: “Except as otherwise required by law or by these Bylaws, any contract
    or other instrument may be executed and delivered in the name of the Corporation and on
    its behalf by . . . any Vice President.” (Appellant’s App. at 1464.) Thus, under Digital’s
    own bylaws, Vice President Haler was explicitly vested with authority to execute
    contracts. Second, Digital indicated by both word and deed that Vice President Haler had
    validly exercised his contract-signing authority in November 2008 when he signed the
    2008 contract on behalf of Digital. Digital has never contested the fact that Vice
    President Haler was fully authorized to enter into this contract, and its actions following
    the signing of the 2008 contract clearly signaled to Z3 that Vice President Haler was
    authorized to enter into this type of contract for the design, manufacture, and delivery of
    circuit board modules.
    Despite all of this undisputed evidence, Digital contends Vice President Haler
    lacked even apparent authority to enter into the 2009 contract because of an internal
    change to Digital’s signature policies (but not the company bylaws) in the intervening
    month between the signing of the two contracts. However, there is no evidence that Z3
    was ever informed of this internal policy change, and we therefore conclude that this
    change did not affect Vice President Haler’s apparent authority to enter into this type of
    contract. Cf. Homes Sav. Ass’n v. Gen. Electric Credit Corp., 
    708 P.2d 280
    , 283 (Nev.
    -15-
    1985) (“HSA, as principal, may be bound by the acts of its agent as to third parties who
    have no reason to know of the agent’s improper conduct.”). Digital also argues that a
    finding of apparent authority could only be premised on evidence that Digital made
    specific representations to Z3 regarding Vice President Haler’s authority to enter into this
    specific contract. Digital points to no cases suggesting that an objectively reasonable
    belief in an agent’s authority will only arise where the principal makes specific
    representations about the precise act in question in that case. Indeed, such a rule would
    vitiate the doctrine of apparent authority. In light of the undisputed evidence regarding
    Vice President Haler’s title, Digital’s bylaws, Digital’s prior dealings with Z3, and the
    substantial similarity between the valid 2008 contract and the contested 2009 contract, we
    are persuaded that Z3’s belief in Vice President Haler’s authority to enter into the 2009
    contract was objectively reasonable. Nevada law does not require more.
    C. Substantial Performance
    Digital next argues that Z3’s breach of contract claim on the 2009 contract is
    barred by Z3’s failure to substantially perform its own obligations under the contract.
    Nebraska law generally holds that “[t]o successfully bring an action on a contract, a
    plaintiff must first establish that the plaintiff substantially performed the plaintiff’s
    obligations under the contract.” VRT, Inc. v. Dutton-Lainson Co., 
    530 N.W.2d 619
    , 623
    (Neb. 1995). “Substantial performance is shown when the following circumstances are
    established by the evidence: (1) The party made an honest endeavor in good faith to
    perform its part of the contract, (2) the results of the endeavor are beneficial to the other
    -16-
    party, and (3) such benefits are retained by the other party.” 
    Id. Here, because
    Digital
    repudiated the contract during the design period, Z3 never completed the modules, and
    thus Digital did not receive beneficial performance or retain any such benefits. Digital
    accordingly argues that Z3 cannot recover any damages for Digital’s breach. However,
    the Nebraska Supreme Court has made clear that a party’s failure to substantially perform
    its obligations under the contract will be excused if the party attempted to perform in
    good faith but was “substantially hindered and obstructed” by the other party. Brown v.
    Alron, Inc., 
    388 N.W.2d 67
    , 71 (Neb. 1986); see also In re Estate of Weinberger, 
    279 N.W.2d 849
    , 854 (Neb. 1979) (“Where a party bound by an executory contract repudiates
    his obligation before the time for performance, the promisee has an option to treat the
    contract as ended so far as further performance is concerned, and to maintain an action at
    once for the damages occasioned by such anticipatory breach.”). The undisputed
    evidence in this case demonstrates that Z3 attempted to perform its contractual obligations
    in good faith but was substantially hindered and obstructed by Digital’s anticipatory
    repudiation of the contract. We therefore reject this argument.
    D. Z3’s Lost-Profit Damages under ¶ 14(a) and (b)(i)
    Digital’s final argument on appeal is that the district court erred in concluding Z3
    could recover lost profits for Digital’s failure to make the minimum pre-production and
    initial production orders under ¶ 14(a) and (b)(i) of the 2009 contract. Specifically,
    Digital contends Z3 could not recover lost profits because this contract was governed by
    the Nebraska Uniform Commercial Code, which does not provide for lost profits as a
    -17-
    remedy for breach of a contract for the sale of goods. The fundamental problem with this
    argument is that the 2009 contract was not a contract for the sale of goods. The 2009
    contract explicitly stated it was a licensing agreement under which the modules would be
    “licensed, not sold to [Digital],” with Z3 retaining “title and ownership.” (Appellant’s
    App. at 52.) Accordingly, this contract was not governed by provisions regarding
    contracts for the sale of goods, and Digital has presented no convincing reason why the
    district court erred in permitting Z3 to recover lost-profit damages for Digital’s failure to
    purchase the pre-production and initial production orders.
    III. Z3’s cross-appeal
    In its cross-appeal, Z3 raises two main issues. First, Z3 contends the district court
    erred by interpreting ¶ 14(b)(iii) and (iv) as an alternative contract under which Digital
    could either order a minimum of 36,000 units or pay a minimum total royalty of
    $270,000. Additionally, Z3 contends that, if these provisions are interpreted as an
    alternative contract, the district court erred in awarding Z3 the smaller alternative of
    $270,000 rather than permitting it to recover its lost profits for Digital’s alternative
    obligation to purchase a minimum of 36,000 units. Second, Z3 contends the district court
    erred in denying its request for prejudgment interest for the $15,000 awarded by the jury
    on the 2008 contract and for the 2009 contract’s $175,000 design fee and $270,000
    royalty payment that the district court held Z3 was entitled to on summary judgment. We
    first consider Z3’s argument regarding the district court’s interpretation of ¶ 14(b)(iii) and
    (iv), then turn to the prejudgment interest issue.
    -18-
    A. Interpretation of ¶ 14(b)(iii) and (iv)
    We review de novo the district court’s interpretation of the 2009 contract and its
    legal conclusions regarding the applicable state law. See State Farm Mut. Auto. Ins. Co.
    v. Dyer, 
    19 F.3d 514
    , 521 (10th Cir. 1994). The dispute in this case centers around
    ¶ 14(b)(iv), which follows ¶ 14(b)(iii)’s provisions regarding the 36,000 minimum
    purchase requirement and provides in part: “If LICEN[S]EE does not order 36,000 units
    at 12,000 units per year, LICENSEE is [to] pay a minimum royalty to LICENSOR
    equivalent to 12,000*$7.500 = $90,000 royalty per calendar year or the pro-rated balance
    if at least some units have been purchased within the fiscal year in question.”
    (Appellant’s App. at 63.) The district court concluded this provision established an
    alternative contract, under which Digital could satisfy its performance obligations by
    either ordering a total of 36,000 units or paying a total royalty of $270,000. Z3 argues this
    conclusion was an incorrect interpretation of the contractual provisions.
    We have not found any applicable Nebraska cases dealing with alternative
    contracts, so we assume Nebraska would follow the general law on this issue. As other
    authorities have stated, an alternative contract provides that “either one of two
    performances may be given by the promisor and received by the promisee as the agreed
    exchange for a return performance by the promisee.” In re Cmty. Med. Ctr., 
    623 F.2d 864
    , 867 (3d Cir. 1980). One type of alternative contract is a “take-or-pay” contract,
    under which the buyer can perform its obligations under the contract by either taking the
    minimum purchase obligation (and paying for the purchase) or instead paying a specified
    -19-
    amount without taking the product. Prenalta Corp. v. Colo. Interstate Gas Co., 
    944 F.2d 677
    , 689 (10th Cir. 1991). A take-or-pay provision is thus different from an obligation
    combined with a liquidated damages provision: the “pay” option of a take-or-pay
    contract is a valid alternative for the buyer to perform under the contract, rather than a
    measure of damages for breach of a purchase obligation. See 
    id. However, where
    a
    buyer breaches a take-or-pay contract, the “pay” option will frequently serve as an
    appropriate measure of damages, particularly where the contract provides for expiration
    of the “take” option after a period of time. 
    Id. In determining
    whether a contract is a true alternative contract, we look not to the
    form of the transaction but to its substance, and a contract will be construed as an
    alternative contract if “it appears that it was intended to give a real option, that is, that it
    was conceived possible that at the time fixed for performance, either alternative might
    prove the more desirable.” 14 Williston on Contracts § 42:10 (4th ed. 2010). Thus, an
    alternative contract is one in which “either alternative may prove the more advantageous
    and is as open to the promisor as the other.” 
    Id. Based on
    these authorities, we agree with the district court that ¶ 14(b)(iii) and (iv)
    set forth an alternative contract which Digital could satisfy either by taking a minimum of
    12,000 modules per year or by paying a minimum royalty of $90,000 per year for three
    years. The surrounding contractual language indicates that the reason for the royalty
    option was that the parties did not know at the time of contract formation whether Z3
    would remain willing to produce the modules or whether Digital would find the price and
    -20-
    quality of Z3’s modules acceptable on an ongoing basis. Our review of the contract thus
    persuades us that “it was conceived possible that . . . either alternative m[ight] prove the
    more advantageous.” 
    Id. As for
    whether the royalty option was “as open to [Digital] as
    the [purchase obligation],” 
    id., Z3 contends
    that ¶ 14(b)(iii) in fact set forth a mandatory
    purchase obligation, while ¶ 14(b)(iv) only described a consequence of nonperformance
    of this obligation. However, we are persuaded these provisions in fact gave Digital a
    choice between alternative performances. While Digital’s pre-production and initial
    production purchase obligations under ¶ 14(a) and ¶ 14(b)(i) were unequivocal in their
    requirement that Digital purchase a minimum number of pre-production and initial
    production units, ¶ 14(b)(iii) was entitled “Minimum 12,000 units or equivalent Royalty
    PER YEAR for 3 years,” and ¶ 14(b)(iv) set forth the royalty Digital would be required to
    pay if it chose not to purchase the minimum number of units. (Appellant’s App. at 63
    (emphasis added).) Indeed, the contract permitted Digital to take some combination of
    the two performance options, since Digital could purchase some units during a particular
    year and then pay the prorated balance of the royalty for the units it did not purchase.
    The pertinent provisions did not indicate that Digital would be found in breach of the
    contract if it paid the full or prorated royalty in lieu of purchasing modules; rather these
    provisions simply described the minimum purchase requirement “or equivalent Royalty”
    to which Digital was obligated. (Id. (emphasis added).) We agree with the district court
    that ¶ 14(b)(iii) and (iv) set forth a valid take-or-pay contract under which Digital had the
    choice of alternatives to fulfill its contractual obligations.
    -21-
    B. Appropriate Measure of Damages under ¶ 14(b)(iii) and (iv)
    Having so concluded, we must next consider whether the district court erred in
    limiting Z3’s damages for Digital’s breach of these provisions to $270,000 in royalties
    rather than the larger amount of Z3’s lost profits for Digital’s failure to purchase the
    36,000 units. Because there is no Nebraska law on point, we must attempt to predict what
    the Nebraska Supreme Court would do if faced with this issue. See Wade v. EMCASCO
    Ins. Co., 
    483 F.3d 657
    , 666 (10th Cir. 2007).
    There is no universal consensus on the question of appropriate damages for breach
    of an alternative contract. In 1934, a panel of this court held as a matter of federal
    common law that damages could be based on the alternative that would result in the
    largest recovery. Prudential Ins. Co. v. Faulkner, 
    68 F.2d 676
    (10th Cir. 1934).3 In
    reaching this conclusion, the panel majority reasoned that “[o]ne who repudiates his
    obligation under a contract cannot thereafter exercise an election contained in its
    provisions.” 
    Id. at 679.
    A few cases have followed this rule. See, e.g., Anderson v.
    Rexroad, 
    306 P.2d 137
    , 142 (Kan. 1957). However, most cases have instead followed the
    rule set forth in the First Restatement of Contracts, which provides: “The damages for
    breach of an alternative contract are determined in accordance with that one of the
    alternatives that is chosen by the party having an election, or, in case of breach without an
    election, in accordance with the alternative that will result in the smallest recovery.”
    3
    Of course, in the case before us we are applying Nebraska law, and thus our prior
    opinion bears only persuasive and not precedential weight.
    -22-
    Restatement (First) of Contracts § 344 (1932); see In re Cmty. Med. 
    Ctr., 623 F.2d at 868
    (describing the First Restatement rule as the “general rule” and stating that the Prudential
    approach “has garnered scholarly approval in only one situation—where the contract
    itself contains language granting the promisee the right to elect remedies”); see also 25
    Williston on Contracts § 66:106 (4th Ed. 2010) (collecting cases and describing the
    Prudential approach as “an inconsistent and, it seems, erroneous rule . . . laid down in a
    few cases”). The majority of courts have reasoned, like the dissent in Prudential, that the
    Prudential approach “results in the imposing upon the promisor, as a penalty for the
    breach, a greater obligation or duty than does the contract itself; its effect is to increase
    the contractual rights of the promisee upon a breach by the promisor when the contract
    does not so provide, and to make a new contract for the parties.” 
    Prudential, 68 F.2d at 684
    (Phillips, J., dissenting).
    In recent years, a few courts have questioned in dicta whether the rule set forth in
    Section 344 of the First Restatement is still the current rule, in light of the omission of
    this provision from the Second Restatement. See, e.g., Schwan-Stabilo Cosmetics GmbH
    & Co.v. PacificLink Int’l Corp., 
    401 F.3d 28
    , 34 (2d Cir. 2005) (“Even if this is currently
    the rule—and its absence from the Second Restatement of Contracts suggests that it is
    not—it does not appear to apply in a case such as this one.”); Minnick v. Clearwire US
    LLC, 
    275 P.3d 1127
    (Wash. 2012) (same). However, these courts have not expressly
    rejected the First Restatement rule, but have instead premised their holdings on what
    Williston describes as “[a]n exception to the general rule,” which “is made if one of the
    -23-
    alternatives is to pay a certain sum of money.” 25 Williston on Contracts § 66:106 (4th
    Ed. 2010); see 
    Schwan-Stabilo, 401 F.3d at 34
    (holding that the First Restatement rule
    was inapplicable based on the exception for cases “where an alternative contract provides
    as one alternative the payment of a sum of money”); 
    Minnick, 275 P.3d at 1135
    (same).
    This exception provides that “[i]n an alternative contract where one of the alternatives is a
    sum of money, the promisee is entitled to the sum of money even though the other
    alternative may be less onerous to the promisor.” 
    Minnick, 275 P.3d at 1135
    . Thus,
    courts which have applied this exception have not needed to determine the continued
    viability of the general First Restatement rule.
    We conclude the Nebraska Supreme Court would be most likely to follow the
    majority approach and award damages based on the alternative that would result in the
    smaller recovery. This conclusion is bolstered by the fact that the lesser alternative in this
    case—the $270,000 total royalty payment—is a fixed sum of money under the “pay”
    alternative of the take-or-pay contract. An award of damages based on this monetary
    alternative accordingly complies with the approach taken by several courts, including
    those which have called the First Restatement rule into question, for an alternative
    contract that provides as one alternative the payment of a fixed sum of money. We
    therefore affirm the district court’s holding that Z3 was only entitled to $270,000 in
    damages for Digital’s breach of its obligation to either purchase 12,000 units or pay a
    $90,000 royalty each year for three years.
    C. Prejudgment Interest
    -24-
    We turn then to the final issue we must resolve in these cross-appeals—Z3’s
    argument that the district court erred in denying its request for prejudgment interest for
    the $15,000 awarded by the jury on the 2008 contract and for the $175,000 in unpaid
    design fees and $270,000 in royalties that the district court awarded to Z3 on summary
    judgment on the 2009 contract.
    Before resolving this issue, we must first determine the standard of review that
    governs our review of the district court’s denial of prejudgment interest. Z3 argues we
    must review this decision under a state de novo standard of review, while Digital argues
    our review is instead governed by a federal abuse of discretion standard. We note there is
    some conflict in the cases over whether the appellate standard of review in a federal
    diversity case is governed by state or by federal law. Compare Freund v. Nycomed
    Amersham, 
    347 F.3d 752
    , 762 (9th Cir. 2003) (“Yet it is well established that rules
    regarding the appropriate standard of review, or even the availability of review at all, to
    be applied by a federal court sitting in diversity, are questions of federal law.”), and Atlas
    Food Sys. & Servs. v. Crane Nat’l Vendors, Inc., 
    99 F.3d 587
    , 596 (4th Cir. 1996)
    (“While state law governs the substantive right to setoff, federal law dictates our standard
    of review. And, under federal law, a district court’s decision to set off a damage award is
    reviewed for clear error.”), with United Int’l Holdings, Inc. v. Wharf (Holdings) Ltd., 
    210 F.3d 1207
    , 1233 (10th Cir. 2000) (citing a Colorado case in support of reviewing de novo
    the district court’s conclusion that the facts of a case fell within the terms of Colorado’s
    prejudgment interest statute”), and Brocklehurst v. PPG Indus., Inc., 
    123 F.3d 890
    , 894
    -25-
    (6th Cir. 1997) (“[B]ecause this is a diversity case, we apply the standard of review used
    by the courts of the state whose substantive law governs the actions.”). However, we
    need not resolve this issue in the case before us because we conclude that a de novo
    standard of review is appropriate whether we label it a federal or a state standard.
    As Digital notes, several Tenth Circuit cases have indicated that the district court’s
    denial of prejudgment interest is reviewed for abuse of discretion. However, we have
    elsewhere more aptly stated that “[a]n award of prejudgment interest ‘is generally subject
    to an abuse of discretion standard of review on appeal.’” Atl. Richfield v. Farm Credit
    Bank of Wichita, 
    226 F.3d 1138
    , 1156 (10th Cir. 2000) (quoting Driver Music Co. v.
    Commercial Union Ins. Cos., 
    94 F.3d 1428
    , 1433 (10th Cir. 1996)) (emphasis added). A
    closer examination of our cases reveals that the abuse of discretion standard is generally
    appropriate because the decision whether to award prejudgment interest is generally
    committed to the district court’s discretion. Under federal law, an award of prejudgment
    interest is generally equitable; accordingly, in the “absence of a statutory provision to the
    contrary, the district court has broad discretion in deciding whether to grant prejudgment
    interest.” FDIC v. Rocket Oil Co., 
    865 F.2d 1158
    , 1160 (10th Cir. 1989). When, as is
    usually the case, the district court has broad discretion on the question of prejudgment
    interest, the abuse of discretion standard will govern. 
    Id. However, we
    are not persuaded
    that this general rule requires us to apply an abuse of discretion standard even in cases
    where a statute—whether federal or state—makes an award of prejudgment interest
    mandatory rather than discretionary. In such cases, it is appropriate to instead apply a de
    -26-
    novo review, since the pertinent inquiry in such a case will not involve the district court’s
    exercise of discretion, but will instead involve only the court’s legal determination as to
    whether the facts of the case fall within the terms of the statutory mandate.
    The Second Circuit reached the same conclusion in a case involving an award of
    post-judgment interest. In Westinghouse Credit Corp. v. D’Urso, 
    371 F.3d 96
    , 100 (2d
    Cir. 2004), the Second Circuit applied a de novo standard of review to review the district
    court’s award of post-judgment interest under 28 U.S.C. § 1961. The court explained:
    We recognize that interest awards are ordinarily said to be subject to an
    abuse of discretion standard. But such language appears only in cases
    where the statute commits those awards to the district court’s discretion. In
    contrast, we have not limited review to the abuse of discretion standard in
    cases where the governing law made an award of interest mandatory.
    
    Id. (citations omitted).
    Our own circuit at least implicitly reached the same conclusion in
    United International Holdings, in which we applied a de novo standard of review to
    determine whether the facts of the case before us fell within the terms of Colorado’s non-
    discretionary prejudgment interest 
    statute. 210 F.3d at 1233
    .
    The applicable state statute in this case commits no discretion in the district court,
    providing instead that prejudgment interest “shall accrue on the unpaid balance of
    liquidated claims from the date the cause of action arose until the entry of judgment.”
    Neb. Rev. Stat. § 45-103.02(2) (emphasis added). Because an award of prejudgment
    interest is mandatory under Nebraska law if the statutory terms are met, we review the
    district court’s denial of prejudgment interest under a de novo standard.
    Turning then to the merits of this issue, we note that Nebraska Revised Statutes
    -27-
    Section 45-103.02(2) provides for prejudgment interest only for “liquidated claims.” The
    Nebraska Supreme Court has explained: “Liquidated claims are those where there is no
    reasonable controversy as to the plaintiff’s right to recover or as to the amount of such
    recovery.” Blue Valley Coop. v. Nat. Farmers Org., 
    600 N.W.2d 786
    , 796 (Neb. 1999).
    Thus, to determine whether an award of prejudgement interest should be made, “[a] two-
    pronged inquiry is required,” under which there can be no reasonable controversy “either
    as to the amount due or as to the plaintiff’s right to recover, or both.” Countryside Coop.
    v. Harry A. Koch, Co., 
    790 N.W.2d 873
    , 889 (Neb. 2010). We apply this two-pronged
    inquiry to each of the three sums of money for which Z3 seeks prejudgment interest: (1)
    the $15,000 awarded by the jury on the 2008 contract; (2) the unpaid $175,000 in design
    fees the district court held Z3 was entitled to on summary judgment; and (3) the $270,000
    royalty payment the district court held Z3 was entitled to based on ¶ 14(b)(iii) and (iv) of
    the contract.
    Z3 contends it is entitled to prejudgment interest on the $15,000 awarded by the
    jury on the 2008 contract because there was no dispute that Digital breached the contract
    by failing to make the final, indisputable $15,000 payment due under the contract.
    However, this argument ignores the controversy in this litigation as to whether Z3 had
    “substantially performed so that it could . . . recover the balance due” on the 2008
    contract. Lange Indus., Inc. v. Hallam Grain Co., 
    507 N.W.2d 465
    , 477 (Neb. 1993).
    Digital contended throughout the proceedings below that the pink noise and other
    hardware issues with the modules delivered by Z3 demonstrated that Z3 had failed to
    -28-
    substantially perform its obligations under the contract. Indeed, the jury ultimately
    agreed with Digital that Z3 had breached the contract by failing to satisfy the hardware
    warranties, although the jury implicitly found that both sides had substantially performed
    under the contract such that they were each entitled to recover for the other’s breach.
    The pertinent facts regarding the $15,000 award in this case are very close to the
    facts at issue in the controlling Nebraska case of Church of the Holy Spirit v. Bevco, Inc.
    
    338 N.W.2d 601
    (Neb. 1983). In that case, a church hired a contractor, Bevco, to
    construct a parish center, and Bevco hired a subcontractor which did a very poor job of
    painting the parish center’s exterior walls. The church sued Bevco for breach of contract
    based on the “improper exterior wall coating and caulking resulting in lack of uniformity
    in color, thickness and texture, discoloration, cracking, [and] peeling.” 
    Id. at 604
    (internal quotation marks omitted). In response, Bevco filed a counterclaim against the
    church seeking the unpaid balance of $16,750 that was due under the contract. The jury
    ultimately found that both parties had breached the contract, and it awarded $29,117 to
    the church and $16,750 to Bevco. 
    Id. at 605.
    On appeal, Bevco claimed the trial court
    erred in denying its request for prejudgment interest on its $16,750 counterclaim. The
    Nebraska Supreme Court affirmed the trial court’s decision. The court explained:
    The poor quality of the painting raised the question whether Bevco could
    recover any amount from the Church. In view of the faulty painting—a
    breach of contract—Bevco requested and received an instruction on
    substantial performance in order to prevail on its counterclaim against the
    Church. Any possibility of recovery by Bevco depended on the jury’s
    answer to the question, Had Bevco substantially performed its contract with
    the Church? A reasonable controversy existed regarding the nature and
    -29-
    degree of performance by Bevco, and, therefore, the claim was not
    liquidated. The trial court was correct in denying prejudgment interest on
    Bevco’s counterclaim.
    
    Id. at 607.
    The Bevco case is on all fours with the case before us. Consequently, Z3’s
    argument that it is entitled to prejudgment interest for its award of $15,000 on the 2008
    contract lacks merit.
    We turn then to Z3’s argument that it is entitled to prejudgment interest for the
    $175,000 in unpaid design fees that the district court held it was entitled to on summary
    judgment. First, we must decide whether there was a reasonable controversy as to Z3’s
    right to recover for Digital’s breach of the 2009 contract. Digital contends there was a
    reasonable controversy based on its arguments regarding Vice President Haler’s lack of
    authority to enter into the 2009 contract on behalf of Digital. For the reasons discussed
    above, we find this argument to be without merit, and we are persuaded the principle of
    apparent authority was sufficiently settled that there could be no reasonable controversy
    as to whether Digital was bound by the contract. Moreover, the undisputed facts clearly
    established that Digital breached the contract through its unequivocal anticipatory
    repudiation. We accordingly conclude there was no reasonable controversy as to Z3’s
    right to recover for Digital’s breach of the 2009 contract.
    The second prong of the inquiry for determining whether a claim is
    liquidated—whether there is “no reasonable controversy as to . . . the amount of such
    recovery,” Blue Valley 
    Coop., 600 N.W.2d at 796
    —requires a somewhat lengthier
    analysis in this case. To make this determination, the critical question we must resolve is
    -30-
    whether the “no reasonable controversy” requirement applies to the entire amount of
    damages due for Digital’s breach of the 2009 contract, or whether Z3 can instead recover
    prejudgment interest for those specific portions of damages (i.e., the unpaid $175,000 in
    design fees) as to which the amount of recovery was undisputed, even if other elements of
    damages remained in dispute. Digital contends the total sum of damages recoverable for
    Z3’s single claim of breach of the 2009 contract needed to be liquidated in order for Z3 to
    be entitled to prejudgment interest under Nebraska law for any portion of damages. Z3
    argues in response that Nebraska law entitles it to recover prejudgment interest for those
    portions of the damage award where there was no reasonable controversy as to either its
    right to recover or the amount of such recovery, regardless of whether the entire amount
    of damages was settled.
    After reviewing the pertinent Nebraska cases, we agree with Z3 that it is entitled to
    recover prejudgment interest for those portions of the damage award as to which both
    Z3’s right of recovery and the amount to be recovered were not reasonably controverted.
    The Nebraska Supreme Court has indicated that a single claim of breach can give rise to
    disparate elements of damages, not all of which need to be liquidated in order for the
    undisputed amounts to give rise to an award of prejudgment interest. For instance, in
    Classen v. Becton, Dickinson & Co., 
    334 N.W.2d 644
    (Neb. 1983), the plaintiff agreed to
    supply steel to the defendant for its construction work, and the defendant agreed to pay a
    total of approximately $118,500 in return. The plaintiff supplied steel to the defendant,
    and the defendant paid invoices amounting to $98,094.38. However, the defendant
    -31-
    refused to pay the final invoice for $20,350.74. When the plaintiff sued to recover this
    unpaid amount, the defendant filed an answer and a setoff, in which it sought to reduce
    the plaintiff’s recovery by the amount the defendant was allegedly damaged as a result of
    the plaintiff’s late delivery and misfabrication of steel. Because the defendant’s alleged
    damages were smaller than the amount due on the unpaid invoice, “[t]he trial court found
    that it was agreed by all parties that there was $17,723.94 due the plaintiff.” 
    Id. at 645.
    However, based on the defendant’s disputed setoff claim, there was a dispute as to
    whether the plaintiff could recover the remainder of the unpaid invoice amount. The
    defendant ultimately succeeded in part on its setoff claim, and the plaintiff was awarded a
    total judgment of $18,973.94. On appeal, the plaintiff contended it was entitled to
    prejudgment interest on this award based on the defendant’s failure to pay the final
    invoice. The Nebraska Supreme Court agreed with this argument, but only as to the
    undisputed amount of the award: “The record shows that $17,723.94 of the amount due
    the plaintiff was not disputed and therefore was a liquidated claim. The plaintiff was
    entitled to interest on that amount . . . .” 
    Id. However, because
    there was a dispute as to
    whether the plaintiff could recover the remaining portion of the unpaid invoice, the
    plaintiff was not entitled to prejudgment interest on the $1,250 it recovered after
    resolution of the defendant’s setoff claim. 
    Id. Likewise, in
    a recent case where the “sole
    cause of action was essentially an action for conversion,” Brook Valley Ltd. P’ship v.
    Mut. of Omaha Bank, 
    825 N.W.2d 779
    , 785 (Neb. 2013), the Nebraska Supreme Court
    similarly upheld an award of prejudgment interest on one portion of the award of
    -32-
    damages despite the fact that there was a reasonable controversy as to the amount due and
    the right of recovery on another element of damages. 
    Id. at 792;
    see also Cheloha v.
    Cheloha, 
    582 N.W.2d 291
    , 295-97, 301 (Neb. 1998) (holding in an action for an
    accounting that the plaintiff was entitled to prejudgment interest for those elements of
    damages as to which there was no reasonable controversy, while reversing the trial
    court’s award of prejudgment interest for those elements of damages as to which there
    was a reasonable controversy).
    In this case, there was no reasonable controversy as to whether Digital breached
    the 2009 contract, nor was there any reasonable dispute that Z3 was entitled to $175,000
    in damages based on Digital’s failure to pay the remaining $175,000 in fees that were due
    during the design period. We accordingly hold that Z3 was entitled to prejudgment
    interest on this $175,000 award.
    Finally, we turn to Z3’s argument that it is similarly entitled to prejudgment
    interest on the $270,000 award the district court held it was entitled to for Digital’s breach
    of ¶ 14(b)(iii) and (iv). Again, as with the $175,000 design-fee award, there was no
    reasonable controversy that Z3 had a right to recover for Digital’s breach of the 2009
    contract. Unlike the uncontroverted $175,000 design-fee award, however, Z3’s right to
    recover a specific amount of damages under ¶ 14(b)(iii) and (iv) was the subject of
    reasonable controversy. Whereas Z3’s entitlement to the $175,000 award flowed
    automatically from Digital’s repudiation of the valid 2009 contract, Z3’s entitlement to the
    $270,000 in minimum royalty fees turned on the resolution of the parties’ alternative-
    -33-
    contract arguments.
    Specifically, the parties have disputed throughout this case both (1) whether ¶
    14(b)(iii) and (iv) created an alternative take-or-pay contract and, if so, (2) which
    alternative—lost profits or $270,000 in minimum royalties—was the appropriate remedy
    in the event of breach. Resolving these two questions could yield three possible
    outcomes under this provision of the contract. First, if ¶ 14 did not create an alternative
    contract, then Digital would owe Z3 both lost profits and $270,000 in minimum royalty
    fees. Second, if ¶ 14 created an alternative contract and if Z3 was entitled to the greater
    alternative, then Digital would owe Z3 lost-profit damages, but not the $270,000 in
    minimum royalties. Third, if ¶ 14 created an alternative contract and Z3 was only entitled
    to the smaller alternative, then Digital would owe Z3 the $270,000 in minimum royalties,
    but not lost profits.4
    4
    Z3 contends on appeal that its entitlement to $270,000 has always been
    uncontested because Z3 has consistently maintained that it is entitled to recover both lost
    profits and the $270,000 in minimum royalty fees, while Digital has consistently
    maintained that Z3’s potential recovery is limited to the smaller alternative of $270,000.
    However, Z3’s own arguments on appeal belie this contention. While Z3 mainly focuses
    on its argument that ¶ 14(b)(iii) and (iv) did not create an alternative contract, it also
    argues that if we do find an alternative contract, we must permit Z3 to recover the greater
    alternative of lost profits instead of the lesser alternative of $270,000 in royalties. Z3’s
    filings to the district court also demonstrate continued controversy as to whether Z3 was
    entitled to recover lost profits, minimum royalties, or both. While Z3 sometimes sought
    both lost profits and minimum royalties, it sometimes sought only the greater alternative
    of lost profits. For instance, in its Rule 26(a)(1) disclosures, Z3 disclosed as its damages
    only the $15,000 non-payment for the 2008 contract, the $175,000 balance due for design
    fees under the 2009 contract, and $2.3 million in “lost profits on 39,050 DM365 units @
    average profit per unit of $60.” (Appellant’s App. at 361.) Likewise, the district court’s
    pretrial order noted that Z3 sought $4.05 million in damages as detailed in its expert’s
    -34-
    As discussed above, we conclude the third possible outcome applies here.
    However, this conclusion does not remove the issue from the realm of reasonable
    controversy. Our resolution of this issue depended on our resolution of two legal
    questions of first impression in Nebraska. If we had resolved these two contested issues
    by holding that ¶ 14 created an alternative contract and that Z3 was entitled to recover the
    greater alternative of lost profits, Z3 could not have recovered prejudgment interest under
    ¶ 14(b)(iii) and (iv), since Z3’s lost profits could not be calculated “without reliance upon
    opinion or discretion.” Hill v. City of Lincoln, 
    380 N.W.2d 296
    , 299 (Neb. 1986).
    Because a reasonable controversy existed as to whether Z3 might be entitled to recover
    only its lost profits and not the minimum royalty fees under ¶ 14(b)(iii) and (iv), it
    follows that Z3 was not entitled to prejudgment interest on the $270,000 award it
    ultimately received. Even though the minimum royalty amount itself was specified in the
    contract and calculable without “reliance upon opinion or discretion,” 
    id., the alternative-
    contracts dispute meant that Z3’s right to recover this amount was not a foregone
    conclusion. “[N]ot only was the amount technically unliquidated, but owing to the
    unsettled state of the law, it was uncertain.” 
    Id. report (id.
    at 1043), and this report based the $4.05 million damage calculation only on
    the design fees and lost profits, not the $270,000 royalty payment (id. at 1591.) We
    accordingly agree with Digital that “[t]he $270,000 component of Z3’s damages was in
    ‘controversy’ at all times[,] and it is Z3 itself that created that controversy.” (Appellant’s
    Resp. and Reply Br. at 17.) See also Ferer v. Aaron & Sons Co., 
    725 N.W.2d 168
    , 174-
    75 (Neb. 2006) (“By electing to pursue their litigation for dissenters’ rights and refusing
    to receive the payment of their pro rata share of the sale proceeds, appellants in this case
    created a reasonable controversy with regard to their right to receive the sale proceeds.”).
    -35-
    Based on the continuing controversy over the amount Z3 was entitled to recover in
    damages for Digital’s breach of ¶ 14(b)(iii) and (iv), we conclude that this damage claim
    was not liquidated. We therefore hold that Z3 is entitled to prejudgment interest only as to
    the $175,000 award, since this was the only element of damages for which there was no
    reasonable controversy either as to Z3’s right to recovery or as to the amount to which Z3
    was entitled.
    IV. Conclusion
    For the foregoing reasons, we REVERSE and REMAND for the district court to
    award prejudgment interest to Z3 on the $175,000 award of damages for the unpaid design
    fees. All other portions of the district court’s judgment are AFFIRMED. We DENY
    Z3’s motion to strike portions of Digital’s opening brief.
    -36-
    

Document Info

Docket Number: 12-3258, 12-3268

Citation Numbers: 754 F.3d 802

Judges: Ebel, Matheson, McKAY

Filed Date: 5/16/2014

Precedential Status: Precedential

Modified Date: 8/31/2023

Authorities (38)

Prudential Ins. Co. of America v. Faulkner , 68 F.2d 676 ( 1934 )

Grynberg v. Total S.A. , 538 F.3d 1336 ( 2008 )

united-international-holdings-inc-a-delaware-corporation-and-uih-asia , 210 F.3d 1207 ( 2000 )

Driver Music Co. v. Commercial Union Insurance , 94 F.3d 1428 ( 1996 )

Wade v. Emcasco Insurance , 483 F.3d 657 ( 2007 )

Atlantic Richfield Co. v. Farm Credit Bank of Wichita , 226 F.3d 1138 ( 2000 )

atlas-food-systems-and-services-incorporated-v-crane-national-vendors , 99 F.3d 587 ( 1996 )

westinghouse-credit-corporation-nka-cbs-corporation-westinghouse , 371 F.3d 96 ( 2004 )

In the Matter of the Community Medical Center A/K/A All ... , 623 F.2d 864 ( 1980 )

Schwan-Stabilo Cosmetics Gmbh & Co. v. Pacificlink ... , 401 F.3d 28 ( 2005 )

Federal Deposit Insurance Corporation Deposit Insurance ... , 865 F.2d 1158 ( 1989 )

state-farm-mutual-automobile-insurance-company-v-teddy-ray-dyer-city-of , 19 F.3d 514 ( 1994 )

74-fair-emplpraccas-bna-984-72-empl-prac-dec-p-45149-karl-d , 123 F.3d 890 ( 1997 )

prenalta-corporation-a-florida-corporation-spelman-prentice-an-individual , 944 F.2d 677 ( 1991 )

Omaha Public Power District, a Corporation v. The Employers'... , 327 F.2d 912 ( 1964 )

VRT, INC. v. Dutton-Lainson Co. , 247 Neb. 845 ( 1995 )

Bucher & Willis Consulting Engineers v. Smith , 7 Kan. App. 2d 467 ( 1982 )

Anderson v. Rexroad , 180 Kan. 505 ( 1957 )

Amisub, Inc., (St. Joseph Hospital) v. Donna E. Shalala, ... , 12 F.3d 840 ( 1994 )

jeffrey-r-freund-plaintiff-appellee-cross-appellant-v-nycomed-amersham , 347 F.3d 752 ( 2003 )

View All Authorities »