Tri-State Commodities, Inc. v. GSO America, Inc. , 18 F. App'x 737 ( 2001 )


Menu:
  •                                                                        F I L E D
    United States Court of Appeals
    Tenth Circuit
    UNITED STATES COURT OF APPEALS                   SEP 5 2001
    TENTH CIRCUIT                 PATRICK FISHER
    Clerk
    TRI-STATE COMMODITIES, INC., a Kansas
    Corporation,
    Plaintiff-Appellant and Cross-Appellee,                No. 99-3117
    No. 99-3168
    v.                                             (D.C. No. 96-CV-1100-MLB)
    (District of Kansas)
    GSO AMERICA, INC.,
    Defendant-Appellee and Cross-Appellant.
    ORDER AND JUDGMENT*
    Before HENRY, PORFILIO, Circuit Judges, and WEINSHIENK, District Judge.**
    INTRODUCTION
    This diversity breach of contract case involves issues concerning the nature of a
    contract to supply mulch. Appellant Tri-State Commodities, Inc., (Tri-State) believed it
    had signed a minimum requirements contract with appellee GSO America, Inc., (GSO)
    *
    This order and judgment is not binding precedent, except under the doctrines of
    law of the case, res judicata, and collateral estoppel. This court generally disfavors the
    citation of orders and judgments; nevertheless, an order and judgment may be cited under
    the terms and conditions of 10th Cir. R. 36.3.
    **
    The Honorable Zita L. Weinshienk of the United States District Court for the
    District of Colorado, sitting by designation.
    guaranteeing that GSO would purchase all of its mulch from Tri-State over a five-year
    period. GSO believed that it merely was a one-year contract, renewable for additional
    one-year periods, that required GSO to purchase certain minimum amounts if the contract
    was to renew automatically for another year. GSO also came to believe that Tri-State
    fraudulently had induced it into signing a contract by misrepresenting Tri-State’s
    relationship with its suppliers.
    Tri-State brought suit in the District of Kansas for breach of contract. The district
    court granted partial summary judgment to GSO, finding that the contract was only for
    one year, and that GSO was required only to purchase certain limited amounts of mulch
    from Tri-State. The district court also granted GSO’s motion in limine to limit damages
    to lost profits. Finding for Tri-State on the breach of contract claim, the jury awarded Tri-
    State damages less than the maximum allowable lost profit figure. GSO then moved for a
    judgment as a matter of law, which was denied. Tri-State appeals from the district court’s
    partial summary judgment in favor of GSO, and from the ruling granting GSO’s motion
    in limine. GSO cross-appeals from the district court’s denial of its motion for judgment.
    We assert jurisdiction pursuant to 
    28 U.S.C. § 1291
    , and, for the reasons stated below,
    affirm the district court’s rulings.
    BACKGROUND
    Tri-State historically has been in the transportation business. In early 1995, Tri-State
    -2-
    became aware that Munson Trucking (Munson) had mulch for sale at its facilities in
    Washington State. Tri-State then approached GSO, a manufacturer of mulch and other
    gardening products, about supplying mulch to GSO. As GSO was concerned about a
    possible shortage of mulch, it expressed interest. Tri-State then contracted with Munson
    to purchase mulch, and, after exchanging a variety of oral and written proposals, signed a
    contract on May 4, 1995, to supply GSO with mulch.
    Initially, the contract between Tri-State and GSO functioned well. GSO set up a
    bagging facility at Tri-States’ depot in Nebraska and shipped the bagged mulch to GSO’s
    commercial facilities. However, in July, 1995, after a trip to Washington State where
    representatives met with Munson, GSO began to suspect that it had been fraudulently
    induced into signing the contract with Tri-State. Specifically, GSO claims that it had
    been led to believe that Tri-State had exclusive supply contracts with over forty lumber
    mills on the west coast.
    Relations between Tri-State and GSO went downhill rapidly, and GSO stopped
    purchasing mulch from Tri-State. On December 20, 1995, GSO removed its bagger from
    Tri-State’s facility, and on February 20, 1996, GSO sent a letter to Tri-State terminating
    their contract, claiming that Tri-State had misrepresented that it had exclusive supply
    contracts with over forty mills on the west coast, and characterizing Tri-State’s pricing as
    unreasonable and unconscionable. After the February 20, 1996, letter, GSO began
    purchasing mulch directly from Munson. Tri-State ceased purchasing mulch from
    Munson, and was sued for breach of contract by Munson. In turn, Tri-State sued GSO for
    -3-
    breach of contract.
    Tri-State’s amended complaint against GSO alleged, among other claims, that
    GSO had agreed to purchase all of its Grade A cedar bark mulch from Tri-State for a
    period of five years, in the following quantities: 10,000 cubic yards for inventory as well
    as a minimum of 70,000 cubic yards the first year, 140,000 cubic yards during the second
    year, and 190,000 cubic yards during the third, fourth and fifth years. GSO denied
    liability, and claimed the contract was procured by fraud. In GSO’s view, the contract
    required GSO to purchase only 10,000 cubic yards during the first year. After that point,
    the contract continued only if GSO satisfied a condition precedent, the minimum purchase
    of at least 70,000 additional cubic yards of mulch within the first year. Another provision
    of the contract gave either side the right to terminate the contract upon notice at least 90
    days in advance of the contract’s anniversary.
    The district court, in granting GSO’s motion for partial summary judgment, found
    that the contract required GSO to purchase unconditionally 10,000 cubic yards, and
    required GSO to purchase an additional 70,000 cubic yards only if it wished to renew the
    contract for another year. However, during the term of the contract, GSO was obligated
    to purchase all of its mulch requirements from Tri-State. GSO then filed a motion in
    limine, granted by the district court, which limited the measure of damages to lost profits
    of $6.20 per cubic yard, not the full contract price of $18.50 per cubic yard as sought by
    Tri-State.
    The jury found that GSO had breached the contract by purchasing mulch during
    -4-
    the first year directly from Munson, rather than through Tri-State, and awarded Tri-State
    $32,132.60 in damages, based on lost net profits of $4.03 per cubic yard for 7,973.35
    cubic yards of mulch purchased by GSO directly from Munson. Following the jury
    verdict, GSO moved for judgment as a matter of law under Fed. R. Civ. P. 50(b); the
    motion was denied. Tri-State appeals the district court’s partial summary judgment in
    favor of GSO concerning the interpretation of the contract, and the district court’s ruling
    granting GSO’s motion in limine with respect to contract damages. GSO cross-appeals
    the district court’s denial in part of its motion for summary judgment, arguing that Tri-
    State presented no evidence that GSO processed any mulch in violation of the contract
    during its term, and also arguing that the district court’s instruction to the jury during
    testimony of a GSO witness in effect granted Tri-State a directed verdict with respect to
    the volume of mulch at issue.
    DISCUSSION
    This Court reviews grants or denials of summary judgment de novo. Butler v. City
    of Prairie Village, Kansas, 
    172 F.3d 736
    , 745 (10th Cir. 1999). The methodology of
    calculating a damage award is a question of law, and thus reviewed de novo, while the
    amount of a damage reward is a question of fact, and thus is reviewed for clear error.
    Southern Colorado MRI, Ltd. v. Med-Alliance, Inc., 
    166 F.3d 1094
    , 1100 (10th Cir.
    1999). The standard of review for evidentiary rulings is abuse of discretion. Mitchell v.
    Gencorp, Inc., 
    165 F.3d 778
    , 780 (10th Cir. 1999).
    -5-
    I. The Contract:
    The May 4, 1995, signed contract between Tri-State and GSO contained, in part,
    the following language (Appendix to Appellant’s Brief at 439):
    2. Term. The Term of the contract shall be for a
    period of five years; provided however, that the term shall
    automatically be extended for one additional year on each
    anniversary date so as to create an ongoing five (5) year term,
    unless either party, at least ninety (90) days prior to the
    anniversary date, gives written notice to the other party
    canceling the contract or unless Buyer fails to purchase the
    minimum quantities of Mulch as described in Section 3 . . . .
    3. Quantity. Seller shall sell and Buyer shall buy a
    minimum of 10,000 cubic yards of the Mulch for Buyer’s
    inventory during the first year of the Term. As a condition to
    the annual continuation of this Agreement, Buyer must
    purchase minimum requirement of Grade “A” Cedar Mulch as
    follows: 70,000 cubic yards the first year; 140,000 cubic yards
    the second year; and 190,000 cubic yards for each of the third,
    fourth, and fifth years and each year thereafter. If Buyer does
    not purchase the minimum requirements for each year, Seller
    may, but is not required, to unilaterally terminate this contract,
    without penalty or claim to or by either party, and find a new
    market for the mulch. These are minimum requirements and
    the parties may agree to greater amounts for any one year.
    ....
    6. Supply. For each of the first six (6) months of this
    Agreement, Seller shall supply Buyer with 3,000 cubic yards
    of Mulch upon Buyer’s request. In the event Seller does not
    supply the Mulch as requested by Buyer, Seller shall
    reimburse Buyer the sum of a non-refundable, Five Thousand
    Dollar ($5,000.00) payment to offset Buyer’s lease costs for
    Buyer’s facility at its McCook, Nebraska facility, and the
    costs incurred by Buyer to disassemble, transport and
    reassemble its McCook, Nebraska facility’s equipment to its
    Nahunta, Georgia facility.
    ....
    8. Buyer’s Exclusive Marketing and Distribution
    -6-
    Rights. During the Term of this Agreement, including
    renewal terms, Seller grants to Buyer the exclusive right to
    market and distribute its bagged and bulk Mulch products for
    the United States east of the Rocky mountains . . . .
    ....
    10. Non-Competition. During the Term Buyer agrees
    not to compete with Seller by purchasing raw, all-bark, Grade
    “A” cedar mulch and processing it for resale, or selling all-
    bark, Grade “A” cedar mulch provided by someone other than
    Seller . . . .
    11. Miscellaneous. This Agreement contains the
    entire understanding of the parties with respect to the subject
    matter. There are no restrictions, agreements, promises,
    warranties, covenants of undertaking other than those
    expressly set forth herein. This Agreement supercedes all
    other prior agreements and understandings between the
    parties with respect to the subject matter. This Agreement
    may only be amended by written instrument executed by all
    the parties.
    ....
    The district court, relying on the parol evidence rule, found that the contract was
    unambiguous and contained a complete integration clause, and thus refused to consider
    extrinsic evidence interpreting the contract. Appellant objects to the district court’s
    interpretation of the contract, arguing: (1) under Kansas law, a contract may be
    supplemented by certain extrinsic evidence, and (2) that the provisions of the contract
    need to be harmonized.
    First, Tri-State argues that Kansas Statutes Annotated (K.S.A.) § 84-2-202
    provides that the terms of a contract may be supplemented by a course of dealings, trade
    usage, or a course of performance. Tri-State characterizes the contract as a minimum
    requirements contract. The contract, in Tri-State’s view, calls for increasing minimum
    -7-
    purchases, which indicates that the intent of the parties was for GSO to use its best efforts
    to expand the mulch market. As K.S.A. § 84-2-306, which governs requirements
    contracts, requires both parties to exercise their best efforts, Tri-State believes the
    contract best resembles a minimum requirements contract.
    Second, Tri-State claims that when the various sections of the contract are
    harmonized, GSO’s only option to terminate the contract is by notifying Tri-State in
    writing, while Tri-State had the option of terminating if the minimum purchase was not
    made. To read the contract any other way, according to Tri-State, is to render
    meaningless the language giving Tri-State the option of terminating the contract.
    Tri-State points to prior negotiations to show that the parties contemplated a
    70,000 cubic yard minimum purchase for the first year of the contract. To support this
    argument, Tri-State claims that the contract’s provisions for making appellee exclusive
    distributor east of the Rockies envisioned a strong commercial tie between the parties,
    consistent with a 70,000 cubic yard minimum purchase instead of a 10,000 cubic yard
    minimum purchase, and that the requirement that Tri-State supply 3,000 cubic yards a
    month or pay a penalty also is inconsistent with a 10,000 minimum purchase. Tri-State
    claims its own subsequent conduct, specifically Tri-State’s entering into a minimum
    requirements contract with Munson to purchase 100,000 cubic yards of mulch per year, is
    consistent with its interpretation of the contract. (See Appendix to Appellant’s Brief at
    439).
    -8-
    Tri-State points to its dealings with Munson as a “course of performance” intended
    to support its interpretation of the contract, arguing that it would not enter into a
    minimum requirements contract with Munson without being confident that it had a
    similar arrangement with its own customer, GSO. Despite this argument, the Court
    cannot reform contracts to match one party’s intent. It is clear from K.S.A. § 84-2-208
    that the course of performance mentioned in K.S.A. § 84-2-202 refers to the course of
    performance between the parties to the contract, not between one of the parties and a third
    party, in this case, Munson.
    The Kansas Supreme Court has interpreted K.S.A. § 84-2-202 as meaning that
    parol evidence is to be used only when the agreement is ambiguous, or silent on a matter.
    Barbara Oil Co. v. Kansas Gas Supply Co., 
    827 P.2d 24
    , 34 (Kan. 1992). As a general
    rule, if the language is clear, there is no room for rules of construction. Marquis v. State
    Farm Fire and Cas. Co., 
    961 P.2d 1213
    , 1219 (Kan. 1998). Analogizing to other states’
    interpretations of the Uniform Commercial Code, the Tenth Circuit has held that under 2-
    202 of Oklahoma’s Commercial Code, evidence of prior agreements, course of dealing,
    and course of performance cannot be used where they contradict the terms of the
    agreement. C.F.Braun & Co. v. Oklahoma Gas & Elec. Co., 
    603 F.2d 132
    , 133 (10th Cir.
    1979). In the instant case, where the terms of the contract are unambiguous and there is a
    complete integration clause, the district court was correct to reject intrinsic evidence as to
    the intent of the parties or the nature of the contract.
    Admittedly, this contract is not the finest example of draftsmanship. It appears to
    -9-
    reflect conflicting intentions of the parties. Tri-State claims that the district court’s
    reading of the contract would render its power of termination meaningless. However, the
    district court’s interpretation does not render the language granting Tri-State the right to
    terminate meaningless, it merely strips the language of the power that Tri-State apparently
    believes it was to hold: the unilateral right to determine whether the contract continues or
    terminates. To read the contract in that light, the district court would have to completely
    ignore the provision making the purchase of a certain quantity of mulch a condition
    precedent for the continuation of the contract. Under these circumstances, the district
    court’s interpretation of the contract was reasonable. When reading a contract, it is the
    intent expressed by the parties, not the actual intent of the parties, which controls.
    General Surgery, P.A. v. Suppes, 
    953 P.2d 1055
    , 1057 (Kan. 1998).
    II. Damages:
    Tri-State appeals the district court’s granting of GSO’s motion in limine which
    restricted Tri-State’s recovery of damages to net profits lost, rather than a full recovery of
    the contract price. Tri-State argues that a lack of a market for its mulch dictates that it
    should recover the entire contract price. Recovery of the contract price is possible under
    some circumstances under Kansas law; such recovery, however, only applies “[w]hen the
    buyer fails to pay the price as it becomes due.” K.S.A. § 84-2-709. In the instant case,
    GSO did not refuse to pay for mulch it purchased from Tri-State. After sending Tri-State
    the February 20, 1996, termination letter, GSO simply refused to purchase its mulch from
    -10-
    Tri-State as mandated by the non-compete provision of the contract. In essence, GSO
    either did not accept or repudiated its purchase requirement under the non-compete
    provision. Damages for repudiation are covered by K.S.A. § 84-2-708, which provides:
    “ . . . the measure of damages for nonacceptance or repudiation by the buyer is the
    difference between the market price at the time and place for tender and the unpaid
    contract price together with any incidental damages . . . .” K.S.A. § 84-2-708.
    It appears that Tri-State actually is seeking to recover the costs incurred by its
    entry into a true minimum requirements contract with Munson. Tri-State’s costs incurred
    as a result of its misconstruction of the contract are unfortunate, but are not incidental
    damages recoverable from GSO, and consequential damages are not recoverable under
    K.S.A. § 84-2-710. Tri-State’s losses attributable to GSO’s breach of contract consist
    solely of the lost net profit on the mulch purchased improperly from Munson. The district
    court found that as a matter of law, the maximum lost net profit was $6.40 per cubic yard.
    The jury found that the actual lost net profit was $4.03 per cubic yard. Under K.S.A. §
    84-2-708, that was the appropriate measure of Tri-State’s damages due to GSO’s breach.
    III. GSO’s Cross-Appeal:
    Tri-State objects to the cross-appeal, arguing that it is untimely. It argues that the
    claim properly is made under Fed. R. Civ. P. 50(b), which is timely made only at the close
    of evidence. Jackson v. City of Cookeville, 
    31 F.3d 1354
    , 1358 (6th Cir. 1994). GSO
    claims that the relief requested is available under Fed. R. Civ. P. 59 and at common law,
    -11-
    and thus is timely made. Furthermore, GSO points out that Tri-State failed to assert the
    timeliness defense at the district court level, nor did the trial court rely on such a bar in
    denying GSO’s motion, so such a defense should be considered waived. As a general
    rule, issues not raised before the lower court are waived on appeal. Yapp v. Excel Corp.,
    
    186 F.3d 1222
    , 1230 (10th Cir. 1999). As Tri-State failed to object to the timeliness of
    GSO’s Fed. R. Civ. P. 50 motion in the lower court, GSO’s cross-appeal may be
    considered.
    GSO appeals from the district court’s denial of its motion for judgment pursuant to
    Rule 50(b), arguing that the contract with Tri-State only prohibited it from purchasing
    AND processing mulch from another supplier. While it may have purchased mulch from
    Munson, GSO claims that no evidence was introduced that GSO processed the mulch.
    This argument is baseless. In the Revised Pretrial Order, GSO stipulated to purchasing
    and processing 3,693.34 cubic yards of mulch from Munson. In addition, there was
    evidence at trial that GSO moved its bagging equipment from Tri-State’s Nebraska
    facility to Munson’s Washington State facility in December, 1995. A representative of
    Munson testified at trial that he processed and bagged the mulch ordered by GSO using
    GSO’s equipment. The jury was charged with deciding at what point GSO had
    “purchased and processed” mulch, and decided the point against GSO. There was
    sufficient evidence introduced at trial to support the jury’s finding that GSO purchased
    and processed mulch in violation of the contract.
    GSO also appeals on the basis that the district court confused the jury by
    -12-
    instructing it to ignore certain evidence. During the testimony of Craig Lehmkuhl, GSO’s
    chief financial officer, evidence was presented to the jury demonstrating that GSO had
    purchased only 3,693.34 cubic yards of mulch from Munson. GSO claimed that credits
    received from Munson showed that several sales occurred after the term of the Tri-State
    contract ended. GSO also attempted to introduce additional documents showing that
    other mulch GSO allegedly purchased was not actually purchased or received until after
    the term of the contract had expired. Tri-State objected to the introduction of the latter
    documents, and the district court instructed the jury to disregard the testimony concerning
    “credits”. Although Jury Instruction 12 stated that GSO claimed to have purchased only
    3,693.34 cubic yards of mulch in violation of the contract, GSO believes that the jury may
    have been misled into believing that they were to ignore all evidence of credits. This
    confusion would have extended to the jury instructions, in GSO’s view, and thus the
    instructions were prejudicial and should be corrected. Royal College Shop v. Northern
    Ins. Co. of N.Y., 
    895 F.2d 670
    , 681 (10th Cir. 1984).
    The jury instructions themselves are clear and unambiguous. The only possibility
    of confusion arises from the admonishment to the jury to ignore the evidence concerning
    credits during Lehmkuhl’s testimony. GSO could have requested clarification from the
    trial judge, but chose not to do so. The jury was presented evidence supporting GSO’s
    claim and Tri-State’s claim concerning the amount of mulch purchased in violation of the
    contract. The jury apparently found Tri-State’s evidence more persuasive. The Court
    -13-
    finds no evidence of error or prejudice.
    AFFIRMED.
    ENTERED FOR THE COURT
    Zita L. Weinshienk
    Senior District Judge
    -14-