United States Ex Rel. O.L.S., Inc. v. Southwind Construction Services, LLC , 510 F. App'x 688 ( 2013 )


Menu:
  •                                                               FILED
    United States Court of Appeals
    UNITED STATES COURT OF APPEALS       Tenth Circuit
    FOR THE TENTH CIRCUIT                       February 7, 2013
    Elisabeth A. Shumaker
    Clerk of Court
    THE UNITED STATES OF AMERICA
    (FOR THE USE AND BENEFIT OF
    O.L.S., INC., d/b/a OZARK LASER
    AND SHORING),
    Plaintiff-Appellant,
    v.
    No. 12-6132
    SOUTHWIND CONSTRUCTION                             (D.C. No. 5:11-CV-00195-R)
    SERVICES, LLC, an Oklahoma                                (W.D. Okla.)
    corporation; SOUTHWIND
    CONSTRUCTION COMPANY, INC.,
    an Oklahoma corporation; FIDELITY &
    DEPOSIT COMPANY OF
    MARYLAND, a Maryland corporation,
    Defendants-Appellees.
    ORDER AND JUDGMENT*
    Before ANDERSON and BALDOCK, Circuit Judges, and BRORBY, Senior Circuit
    Judge.
    *
    After examining the briefs and appellate record, this panel has determined
    unanimously to grant the parties’ request for a decision on the briefs without oral
    argument. See Fed. R. App. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore
    ordered submitted without oral argument. This order and judgment is not binding
    precedent, except under the doctrines of law of the case, res judicata, and collateral
    estoppel. It may be cited, however, for its persuasive value consistent with
    Fed. R. App. P. 32.1 and 10th Cir. R. 32.1.
    O.L.S., Inc. (“Ozark”) was a third-tier subcontractor on a federal construction
    project at Tinker Air Force Base in Oklahoma. When it did not get paid for the
    equipment it leased to a second-tier subcontractor, Ozark brought an action on the
    payment bond against the first-tier subcontractor, the prime contractor, and the surety
    under the Miller Act, 
    40 U.S.C. §§ 3131
    , 3133.1 The district court dismissed the suit
    for lack of jurisdiction, concluding that because Ozark was a third-tier subcontractor,
    it was not protected by the bond and could not sue under the Miller Act. Ozark
    appeals, arguing that the prime contractor and the first-tier subcontractor should be
    treated as a single, unitary prime contractor, thereby eliminating a tier of the
    contractual structure and making Ozark a second-tier subcontractor entitled to
    protection under the bond.
    In 2005, Southwind Construction Company, Inc. (“Southwind”) received a
    multi-year Indefinite Duration, Indefinite Quantity contract from the government
    known as a SABER contract. Over the course of five years, the government issued
    multiple delivery orders to Southwind for maintenance, repair, and construction
    services at Tinker Air Force Base. At issue here is an order issued to Southwind in
    September 2009 to perform a project known as “Repair RAC FirePond” (“RAC
    Project”). In connection with this project, Southwind, as principal, and Fidelity &
    Deposit Company of Maryland (“Fidelity”), as surety, executed a payment bond.
    1
    As required by the Miller Act, the suit was brought in the name of the United
    States for the benefit and use of Ozark. See 
    40 U.S.C. § 3133
    (b)(3)(A).
    -2-
    Southwind subcontracted the majority of the work on the RAC Project to
    Southwind Construction Services, LLC (“Services”), which then subcontracted part
    of that work to Johnson & Johnson Utility (“Johnson”). Johnson later entered into a
    contract with Ozark to lease equipment. The RAC Project had significant
    cost-overruns, and Johnson failed to pay Ozark $22,288.21. Ozark seeks to recover
    that amount from Southwind’s payment bond.
    The Miller Act requires every contractor who is awarded a government
    construction contract of $100,000 or more to furnish a payment bond “for the
    protection of all persons supplying labor and material in carrying out the work
    provided for in the contract for the use of each person.” 
    Id.
     § 3131(b)(2). The Act
    defines a “contractor” as “a person awarded a contract . . . for the construction,
    alteration, or repair of any public building or public work of the Federal
    Government.” Id. § 3131(a), (b). The Act further provides that a person who
    provides labor or material to the contractor may bring an action on the payment bond,
    id. § 3133(b)(1), as can “[a] person having a direct contractual relationship with a
    subcontractor but no contractual relationship, express or implied, with the contractor
    furnishing the payment bond,” id. § 3133(b)(2).
    Although the Miller Act defines the term “contractor,” it does not define the
    term “subcontractor.” The Supreme Court has held that Congress intended to give
    the term its “technical meaning, as established by usage in the building trades.”
    Clifford F. MacEvoy Co. v. U.S. ex rel. Calvin Tomkins Co., 
    322 U.S. 102
    , 108-109
    -3-
    (1944). Accordingly, a “subcontractor” is “one who performs for and takes from the
    prime contractor a specific part of the labor or material requirements of the original
    contract.” 
    Id. at 109
    . “[A] contract with the prime contractor is a prerequisite to
    being a ‘subcontractor.’” J.W. Bateson Co. v. U.S. ex rel. Bd. of Trs. of Nat’l
    Automatic Sprinkler Indus. Pension Fund, 
    434 U.S. 586
    , 590 (1978).
    Looking at the contractual scheme here, Southwind, as the company that had
    the contract with the government and posted the payment bond, was the prime
    contractor. Services, as a company who had a contract with Southwind to take from
    Southwind a part of the labor or material requirements of Southwind’s contract with
    the government, was a subcontractor (or first-tier subcontractor). And Johnson,
    which had a direct contract with Services but no contract with Southwind, was a
    sub-subcontractor (or second-tier subcontractor) entitled to make a claim against the
    payment bond. See 
    40 U.S.C. § 3133
    (b)(2). Ozark, which had no contract with
    either Southwind or Services, was a third-tier subcontractor and had no right to make
    a claim against the bond. See Bateson, 
    434 U.S. at 591-92
    .
    Ozark argues, however, that the court should look at the substance, rather than
    the form, of the parties’ respective contractual relationships and recognize that
    although Services was nominally a subcontractor, in reality, it was the de facto prime
    contractor. Accordingly, Ozark argues, the court should treat Southwind and
    Services as a unitary prime contractor and Johnson as a first-tier subcontractor, which
    would make Ozark a second-tier subcontractor entitled to protection under the Miller
    -4-
    Act. Ozark relies on this court’s decision in Glens Falls Insurance Co. v. Newton
    Lumber & Manufacturing Co., 
    388 F.2d 66
     (10th Cir. 1967), as authority for
    disregarding the parties’ formal contractual relationships.
    In Glens Falls, two third-tier subcontractors sought the protection of the prime
    contractor’s payment bond by arguing that the nominal first-tier subcontractor,
    Campbell, was a sham and that the nominal second-tier subcontractor, Whiteside,
    was the true first-tier subcontractor. Following a bench trial, the district court found
    that Campbell was a sham; that he permitted DMH, the prime contractor, to use his
    name in the contract with Whiteside in order to protect DMH; that DMH did not
    intend to impose any contractual obligation on Campbell despite its contract with
    him; that the purpose of executing a contract between DMH and Campbell and then a
    contract between Campbell and Whiteside was to insulate DMH from liability to
    Whiteside’s materialmen by making Campbell appear to be the subcontractor; and
    that Campbell’s true relationship with DMH was that of employee or agent. 
    Id. at 69
    .
    On appeal, this court concluded that the district court “properly regarded
    substance, rather than form,” in concluding that Whiteside was the true first-tier
    subcontractor, because “[o]therwise, the purpose of the remedial statute, to protect
    suppliers of materials to the actual subcontractors of the prime contractor, could be
    defeated by setting up by formal contract a straw man as a subcontractor between the
    prime contractor and one who in substance and intent is the actual subcontractor.”
    -5-
    
    Id. at 69-70
    . We therefore affirmed the district court’s judgments against DMH and
    its surety in favor of the plaintiffs who supplied materials to Whiteside.
    Ozark argues that we should take a similar “substance over form” approach
    here. But there are several impediments to doing so. First, it is not clear that this
    court’s focus on “substance and intent” to determine “the actual subcontractor,”
    
    id. at 70
    , is still proper after the Supreme Court’s decision in Bateson. The Court in
    Bateson acknowledged that, in earlier cases, it had taken a functional approach to
    determining who is a subcontractor for purposes of the Miller Act. 
    434 U.S. at
    593-
    94. But it explained that in those previous cases, notably, MacEvoy and F.D. Rich
    Co. v. U.S. ex rel. Industrial Lumber Co., 
    417 U.S. 116
     (1974), the party in question
    had a “direct contractual relationship with the prime contractor” and the question
    before the Court was whether that party qualified as a “subcontractor” or was merely
    a supplier. Bateson, 
    434 U.S. at 594
    . By contrast, in Bateson, where the employees
    of a second-tier subcontractor sought to make a claim on the bond, the Court said that
    a functional approach was improper because “the traditional tools of statutory
    construction provide a definitive answer to the question before us.” 
    Id. at 594
    .
    The Court held that “the word ‘subcontractor’ must be limited in meaning to
    one who contracts with a prime contractor.” 
    Id.
     And although the second-tier
    subcontractor did have a direct contractual relationship with the first-tier
    subcontractor, the second-tier subcontractor’s employees did not and were therefore
    not entitled to make a claim against the bond. 
    Id. at 591-92
    . “Congress . . . intended
    -6-
    the scope of protection of a payment bond to extend no further than to sub-
    subcontractors.” 
    Id. at 591
    . The Court was “not unmindful of [its] obligation to
    construe the highly remedial Miller Act liberal[ly] . . . in order properly to effectuate
    the Congressional intent to protect those whose labor and materials go into public
    projects.” 
    Id. at 594
     (second & third alterations in original) (internal quotation marks
    omitted). But “such a salutary policy does not justify ignoring plain words of
    limitation and imposing wholesale liability on payment bonds.” 
    Id.
     (internal
    quotation marks omitted). The Court recognized the “importance of certainty with
    regard to bonding practices on Government construction projects.” 
    Id. at 592
    .
    Following Bateson, it is not clear that anyone who does not have a direct
    contractual relationship with either the prime contractor or a first-tier subcontractor
    could legitimately make a claim against the payment bond, regardless of the actual
    functions carried out by the respective parties. See U.S. ex rel. K & M Corp. v.
    A & M Gregos, Inc., 
    607 F.2d 44
    , 47 (3d Cir. 1979) (“We agree that Bateson rules
    out a holding that the court may look to the functions carried out by contracting
    parties, rather than to the position they occupy in the contractual structure, to identify
    the first-tier subcontractor.”). But even if it may still be possible after Bateson to
    establish that a nominal first-tier subcontractor was merely a sham or alter ego of the
    prime contractor so that the second-tier subcontractor’s contract with the nominal
    first-tier subcontractor could be said, in reality, to have been with the prime
    contractor, such a theory would not benefit Ozark.
    -7-
    First and foremost, Ozark does not seek to show that Services was a sham
    subcontractor, so that Johnson’s subcontract should be deemed to have been directly
    with Southwind. Ozark concedes that Services actually performed for and took from
    Southwind a specific part of the labor or material requirements of Southwind’s
    contract with the government. See MacEvoy, 
    322 U.S. at 109
     (defining who is a
    “subcontractor”). In fact, Ozark’s complaint is that Services took on and performed
    too many of Southwind’s obligations and thus functioned more like a prime
    contractor than a subcontractor. But the Miller Act quite clearly defines the prime
    contractor as the person who is awarded the contract with the government and who
    posts the surety bond. 
    40 U.S.C. § 3131
     (a), (b). And Ozark does not dispute that
    Southwind is the only party to the SABER contract with the government2 and that
    Southwind is the only party to the bond agreement with Fidelity.
    The Fourth Circuit has held that it may be possible to treat the prime
    contractor and its subcontractor as a unitary prime contractor for the purposes of the
    Miller Act, but “only where ordinary principles of corporate law permit the courts to
    disregard corporate forms.” U.S. ex rel. Global Bldg. Supply, Inc. v. WNH Ltd.
    P’ship, 
    995 F.2d 515
    , 519 (4th Cir. 1993). The district court here held that, under
    Oklahoma law,
    to disregard the separate corporate existence of an entity, a party must
    show either 1) that the separate corporate existence of that entity is a
    2
    In fact, Services was not formed until 2007, well after Southwind entered into the
    SABER contract and performed substantial work under it.
    -8-
    design or scheme to perpetrate a fraud, defeat public convenience,
    justify a wrong or defend a crime; or 2) that one corporation is so
    organized and controlled and its affairs so conducted that it is merely an
    instrumentality or adjunct of another corporation, a dummy or a sham.
    Aplt. App., Vol. 3, at 935. It concluded that Ozark failed to establish a basis for
    disregarding the separate corporate existence of Southwind or Services, or even to
    create a genuine issue of fact on the matter.
    Ozark does not disagree with the district court’s statement of Oklahoma law or
    its conclusion that Ozark failed to meet this legal standard. Ozark argues only that it
    did not have to meet this standard, because, according to Glens Falls, it had only to
    show that Southwind and Services “act[ed] interchangeably” and that “[t]he
    substance of the parties[’] conduct was that of a unitary contractor rather than a
    prime contractor and a subcontractor.” Aplt. Br. at 21. But as we have already
    explained, the plain language of the Miller Act does not permit us to use a functional
    approach to determine the identity of the prime contractor, because the Act itself
    defines who is a prime contractor.3
    3
    Because Ozark does not dispute the district court’s conclusion that the evidence
    did not establish grounds for piercing the corporate veil, we need not decide whether
    the existence of such grounds would ever permit a court to treat a nominal
    second-tier subcontractor as a first-tier subcontractor or to treat a nominal first-tier
    subcontractor as a prime contractor under the Miller Act. Cf. A & M Gregos,
    
    607 F.2d at 48
     (declining to decide “whether Bateson ever permits an application of a
    sham rule or whether in the case of a truly illusory subcontractor this circuit should
    apply a sham rule” in light of its conclusion that contract between prime contractor
    and first-tier subcontractor was bona fide).
    -9-
    Finally, treating Services as the prime contractor in order to elevate Ozark
    from its position as a third-tier subcontractor to that of a second-tier contractor would
    not benefit Ozark, because Services--regardless of the role it may have played--is not
    a party to the bond agreement with Fidelity. Fidelity’s obligations on the bond
    extend only to the failure of Southwind to “promptly make[] payments.” Aplt. App.
    at 103. The court cannot unilaterally alter the terms of the bond agreement to extend
    Fidelity’s obligations to Services. See 15 Okla. Stat. § 373 (“A surety cannot be held
    beyond the express terms of its contract . . . .”). So treating Services as the de facto
    prime contractor would not permit Ozark to make a claim against the payment bond.
    As a third-tier subcontractor, Ozark is simply in too remote a relationship to
    Southwind to be protected by the payment bond. “It was Congress that drew a line
    between sub-subcontractors and those in more remote relationships to the prime
    contractor. If the scope of protection afforded by the Miller Act payment bond is to
    be extended, it is Congress that must make the change.” Bateson, 
    434 U.S. at 594
    (citations omitted) (internal quotation marks omitted).
    The judgment of the district court is affirmed.
    Entered for the Court
    Wade Brorby
    Senior Circuit Judge
    - 10 -