Hunger U.S.Special v. Hardie-Tynes Manuf. ( 2000 )


Menu:
  •                                                                           F I L E D
    United States Court of Appeals
    Tenth Circuit
    UNITED STATES COURT OF APPEALS
    FEB 4 2000
    FOR THE TENTH CIRCUIT
    PATRICK FISHER
    Clerk
    HUNGER UNITED STATES
    SPECIAL HYDRAULICS
    CYLINDERS CORP., an Ohio
    corporation,
    Defendant-Appellant,
    v.                                                   No. 99-4042
    (D.C. No. 94-CV-83)
    HARDIE-TYNES                                           (D. Utah)
    MANUFACTURING COMPANY,
    a Delaware corporation,
    Defendant-Appellee.
    ORDER AND JUDGMENT            *
    Before BALDOCK , HENRY , and MURPHY , Circuit Judges.
    After examining the briefs and appellate record, this panel has determined
    unanimously that oral argument would not materially assist the determination
    *
    This order and judgment is not binding precedent, except under the
    doctrines of law of the case, res judicata, and collateral estoppel. The court
    generally disfavors the citation of orders and judgments; nevertheless, an order
    and judgment may be cited under the terms and conditions of 10th Cir. R. 36.3.
    of this appeal.   See Fed. R. App. P. 34(a)(2); 10th Cir. R. 34.1(G). The case is
    therefore ordered submitted without oral argument.
    GENERAL BACKGROUND
    This dispute arises out of the construction of the Jordanelle Dam near
    Heber City, Utah, a project of the United States Bureau of Reclamation (BOR).
    The general contractor, Granite Construction Company, subcontracted with
    appellee Hardie-Tynes Manufacturing Company (Hardie-Tynes) to supply two
    hydraulic cylinders for installation in the dam outlet lift gates. In turn,
    Hardie-Tynes subcontracted with appellant Hunger United States Special
    Hydraulic Cylinders Corporation (Hunger), an Ohio corporation with a German
    parent corporation, to manufacture the cylinders.
    All aspects of construction were to meet BOR specifications and standards.
    After an inspection of the cylinders at Hunger’s Ohio plant, the BOR notified
    Hardie-Tynes that the cylinders did not resemble those it normally ordered and
    asked for Hunger’s assurance that the cylinders complied with its requirements.
    Hunger certified that they did and contract performance continued.
    Upon completion of the cylinders, Hardie-Tynes incorporated them into the
    gates and shipped the gates to the dam site in Utah. There, another subcontractor,
    Murphy Company Mechanical Contractors & Engineers (Murphy, the original
    -2-
    plaintiff in this action) installed them into the dam. During testing, Murphy
    overpressurized one of the cylinders and damaged it.
    The incident triggered new questions about the cylinders’ compliance with
    BOR requirements. At first, Hunger claimed that they did comply, but eventually
    admitted that it could not provide calculations proving that the German materials
    used in the cylinders met the applicable American standards. As a consequence,
    the BOR demanded replacement of both the damaged and intact cylinders.
    Murphy replaced the damaged cylinder and Hardie-Tynes replaced the other one.
    Murphy brought suit in Utah state court against Hardie-Tynes, Hunger, and
    a number of other parties. Hunger removed the action to federal district court.
    Except for cross-claims between Hardie-Tynes and Hunger, the parties settled the
    lawsuit. The district court then entered judgment on the settled claims and turned
    to Hardie-Tynes’ motion for partial summary judgment on Hunger’s liability for
    breach of contract. After the court granted the motion, Hardie-Tynes and Hunger
    stipulated as to the amount of damages and attorneys’ fees incurred by
    Hardie-Tynes. Based on the stipulation, judgment was entered in favor of
    Hardie-Tynes. Within ten days of entry of judgment, Hunger filed a motion to
    alter or amend judgment pursuant to Rule 59(e) of the Federal Rules of Civil
    Procedure. The district court denied the post-judgment motion.
    -3-
    In this appeal, Hunger argues that (1) the district court lacked jurisdiction
    over its person, (2) factual disputes preclude summary judgment on Hardie-Tynes’
    breach of contract claim, and (3) Hardie-Tynes is not entitled to an award of
    attorneys’ fees and indemnity amounts. We conclude that the district court
    properly exercised jurisdiction over Hunger. We also affirm the entry of summary
    judgment and the inclusion of indemnity amounts in the damage calculation.
    Concerning the award of attorneys’ fees, however, we reverse and remand for
    further proceedings consistent with this order and judgment..
    DISCUSSION
    I.    Personal Jurisdiction
    Hunger contends that its contacts with Utah do not satisfy either the
    constitutional minimum contacts standard or the Utah long-arm statute,      see 
    Utah Code Ann. § 78-27-24
    , and therefore it is not subject to personal jurisdiction in
    the State of Utah. We review the district court’s ruling on the jurisdictional
    issue de novo.   See, e.g. , Far West Capital, Inc. v. Towne   , 
    46 F.3d 1071
    , 1075
    (10th Cir. 1995).
    Normally,
    [t]o obtain personal jurisdiction over a nonresident defendant in a
    diversity action, a plaintiff must show that jurisdiction is legitimate
    under the laws of the forum state   and that the exercise of jurisdiction
    does not offend the due process clause of the Fourteenth Amendment.
    -4-
    In Utah, jurisdiction is appropriate only if plaintiff establishes that:
    (1) the defendant conducted certain enumerated activities in Utah,
    and (2) there is a nexus between plaintiff’s claim and defendant’s
    conduct. See 
    Utah Code Ann. § 78-27-24
    .
    
    Id. at 1074
     (citation omitted). Nevertheless, in this case we need not evaluate the
    extent of Hunger’s contacts with Utah.
    “Because the requirement of personal jurisdiction represents first of all an
    individual right, it can, like other such rights, be waived.”      Insurance Corp. of
    Ireland, Ltd., v. Compagnie des Bauxites de Guinee         , 
    456 U.S. 694
    , 703 (1982).
    Rule 12(h)(1) of the Federal Rules of Civil Procedure provides that a defense
    based on lack of personal jurisdiction is waived if not made by motion or included
    in a responsive pleading. The rule, however,
    sets only the outer limits of waiver; it does not preclude waiver by
    implication. Asserting a jurisdictional defect in the answer [does]
    not preserve the defense in perpetuity. This defense may be lost by
    failure to assert it seasonably, by formal submission in a cause, or by
    submission through conduct.
    Yeldell v. Tutt , 
    913 F.2d 533
    , 539 (8th Cir. 1990) (citations and quotations
    omitted).
    In the absence of a motion to dismiss, a party’s continued participation in
    litigation is inconsistent with an assertion of lack of personal jurisdiction.    See
    Hamilton v. Atlas Turner, Inc.    , 
    197 F.3d 58
    , 59 (2d Cir. 1999) (concluding that
    defendant “forfeited its defense of lack of personal jurisdiction by participating in
    -5-
    extensive pretrial proceedings and forgoing numerous opportunities to move to
    dismiss during the four-year interval that followed its inclusion of the defense
    in its answer”); Bel-Ray Co. v. Chemrite (Pty) Ltd.     , 
    181 F.3d 435
    , 443 (3d Cir.
    1999) (stating that “where a party seeks affirmative relief from a court, it
    normally submits itself to the jurisdiction of the court with respect to the
    adjudication of claims arising from the same subject matter”);       Peterson v.
    Highland Music, Inc. , 
    140 F.3d 1313
    , 1318 (9th Cir.) (stating that “a party’s
    failure to satisfy th[e] minimum steps” specified in Rule 12(h)(1) is not the only
    way to waive the defense of lack of personal jurisdiction),      cert. denied , 
    119 S. Ct. 446
     (1998); Continental Bank, N.A. v. Meyer       , 
    10 F.3d 1293
    , 1296-97 (7th Cir.
    1993) (determining that defendants’ conduct constituted waiver of personal
    jurisdiction defense);   cf. Thompson v. United States , 
    312 F.2d 516
    , 519-20
    (10th Cir. 1962) (holding that an objection to venue is waived by the filing of
    a motion for summary judgment).
    Hunger removed the case to federal court on January 25, 1994, and,
    shortly afterwards, filed a cross-claim against Hardie-Tynes. Subsequently,
    Hardie-Tynes asserted a cross-claim against Hunger. In answering that
    cross-claim, on May 25, 1994, Hunger alleged that the court lacked jurisdiction
    over its person. It then engaged in settlement negotiations and entered into a
    stipulation to dismiss all claims except for the cross-claims between itself and
    -6-
    Hardie-Tynes. On March 10, 1997, the district court dismissed the settled claims
    with prejudice.
    Hunger then sought a prejudgment writ of attachment in connection with its
    cross-claim and responded to a similar request from Hardie-Tynes. On July 10,
    1997, more than three years after commencement of the action, Hunger attempted
    to revive its personal jurisdiction defense by filing a motion to dismiss
    Hardie-Tynes’s cross-claim.
    While Hunger timely raised the defense in its answer, as required by the
    Federal Rules, it did not request a ruling on the issue until most of the claims in
    the case were resolved and dismissed. Instead, Hunger actively participated in the
    litigation and sought affirmative relief from the court.
    We have no difficulty in determining that Hunger’s actions “amount[ed]
    to a legal submission to the jurisdiction of the court.”      Compagnie des Bauxites
    de Guinee , 456 U.S at 704-05. After its lengthy participation in this litigation,
    efforts to seek affirmative relief, and settlement of claims, Hunger may not pull
    its personal jurisdiction defense “‘out of the hat like a rabbit.’”    Federal Deposit
    Ins. Corp. v. Oaklawn Apartments       , 
    959 F.2d 170
    , 176 (10th Cir.1992) (quoting
    Broadcast Music, Inc. v. MTS Enters., Inc.       , 
    811 F.2d 278
    , 281 (5th Cir.1987))
    -7-
    (rejecting a belated personal jurisdiction defense backed on lack of service of
    process).   1
    The district court properly denied Hunger’s motion to dismiss.
    II.    Breach of Contract Issues
    A resolution of the remaining issues in this case depends upon an
    interpretation of the Hardie-Tynes/Hunger contract, which consists of several
    documents exchanged by the parties. The interpretation is a matter for our
    de novo review.       See Moncrief v. Williston Basin Interstate Pipeline Co.   ,
    
    174 F.3d 1150
    , 1163 (10th Cir. 1999). Our task begins with sorting through the
    documents exchanged by the parties and setting out a framework for determining
    their legal effect.   2
    1
    Hunger’s assertion that there was “little activity by the parties” during the
    three-year period after removal and before Hunger’s dismissal motion does not
    jibe with the record. Appellant’s Br. at 26. We note that the district court’s
    docket sheet reflects thirty-six entries between those two case events and that, in
    spite of an alleged lack of formal discovery, the parties appeared to have access to
    all necessary documents.
    We also note that Hunger continued to prosecute its cross-claim until it
    stipulated to an amount as an offset to Hardie-Tynes’ damages.   Cf. Neifeld v.
    Steinberg , 
    438 F.2d 423
    , 427 (3d Cir. 1971) (holding that the assertion of a
    permissive counterclaim does not constitute a waiver of a personal jurisdiction
    defense “where the defendant later validly withdraws the counterclaim without
    leave of court”).
    2
    Because this is a diversity action filed in Utah, we apply Utah’s
    substantive law, including choice of law rules.    See Bancoklahoma Mortgage
    Corp. v. Capital Title Co ., 
    194 F.3d 1089
    , 1103 (10th Cir.1994). In its appellate
    briefs, Hunger cites primarily to the statutory and judicial law of Ohio, where
    (continued...)
    -8-
    A.     Contract Formation
    1.     Contract Documents
    Hardie-Tynes opened contract negotiations by sending a request for
    quotations, dated October 26, 1988, asking for Hunger’s best price for two
    cylinders “PER [attached BOR] DRAWINGS . . . AND SPECIFICATIONS . . .
    AND BUREAU OF RECLAMATION ACCEPTED PRACTICES. MATERIAL IS
    TO BE AMERICAN, CERTIFICATION PAPERS ARE REQUIRED.” Joint App.
    at 365. On December 21, 1988, Hunger responded with a letter stating it was
    “pleased to quote your requirements as follows” and providing specific quantity,
    price, delivery, and payment terms.   Id. at 367.
    The parties agree that the quotation constituted an offer to contract.
    See, e.g., Rochester Plumbing Supply Co. v. A. Burgart, Inc.   , 
    370 N.Y.S.2d 716
    ,
    719 (1975) (determining that a price quotation for fabricated materials to be used
    in a construction bid amounts to an offer). A copy of Hunger’s “standard terms
    2
    (...continued)
    Hunger is headquartered. It does not argue, however, that Utah choice of law
    rules dictate application of Ohio law. Furthermore, we note that both Ohio and
    Utah have adopted the Article 2 of the Uniform Commercial Code (U.C.C.),
    which governs sales of goods. See 
    Ohio Rev. Code Ann. §§1302.01
     to 1302.98;
    Utah Code Ann. §§ 70A-2-201 to -725. In this order and judgment, we use
    citations to the Uniform Commercial Code.
    -9-
    and conditions applicable to all sales” may have accompanied the offer.        3
    These
    standard terms included a provision attempting to specify a mode of acceptance
    and limiting acceptance to Hunger’s terms. None of the terms related to payment
    of attorneys’ fees in the event of a contract dispute.
    Hardie-Tynes accepted Hunger’s offer by sending a purchase order, dated
    June 20, 1988. A provision on the face of the order released Hunger to make
    drawings in accordance with referenced BOR drawings and specifications, but not
    to begin manufacturing.      See Joint App. at 370-71. It also stated that “ALL
    ASPECTS OF PROPER WORKMANSHIP, TESTING, PREPARATION FOR
    SHIPMENT ALONG WITH PROPER PAPER WORK [ARE] MOST
    IMPORTANT, AS FINAL OWNERSHIP WILL BE U.S. BUREAU OF
    RECLAMATION. . . . FURNISH CERTIFICATE OF COMPLIANCE ON
    LABOR AND TEST REPORTS ON MATERIAL.”                        Id. at 371.
    The printed portion of Hardie-Tynes’ purchase order form states, on its
    face, that the conditions listed on the back are part of the order.       Id. Except for
    a provision requiring payment of attorneys’ fees “[i]n the event that Buyer
    commences litigation . . . upon Seller’s default,”       id. at 372, the terms were similar
    3
    There is a factual dispute about whether a copy of the standard terms were
    enclosed with the letter. There is no dispute that the terms were printed on the
    reverse side of another contract document, Hunger’s acknowledgment form.
    Accordingly, a finding on the issue is immaterial to our analysis.
    -10-
    to Hunger’s. Like Hunger, Hardie-Tynes attempted to limit the agreement to its
    own terms. Although the contract had already been formed, Hunger sent a written
    acknowledgment of the purchase order. The face of the acknowledgment did not
    call attention to them, but Hunger’s standard conditions were printed on the
    reverse side.
    The contract was not yet in its final form, however. As required by the
    purchase order, Hunger prepared drawings for approval. With the drawing, it
    proposed an alternative design for the cylinders’ piston rings and seals. Because
    this design deviated from the solicitation drawings and specifications, the BOR’s
    review and approval was necessary. While this review was being conducted,
    Hardie-Tynes issued Amendment No. 1 on its form purchase order, releasing
    Hunger to begin construction of the cylinders except for the piston rings and
    seals. The amendment, dated October 31, 1989, stated that “THE CYLINDERS
    AND PARTS [were] TO BE PER HUNGER DRAWINGS AND H-T DRAWINGS
    . . . . ALL OTHER CONDITIONS AND STIPULATIONS OF THE ORIGINAL
    PURCHASE ORDER ARE TO REMAIN THE SAME.”                  Id. at 382. Hunger sent
    another acknowledgment form.    See id. at 383.
    After further discussion, the BOR approved the design for the piston rings
    and seals. With Amendment No. 2 to the purchase order, dated December 14,
    1989, Hardie-Tynes notified Hunger of the approval and again stated that all other
    -11-
    provisions of the original order remained in effect.       See id. at 386. Hunger sent
    an acknowledgment form.       See id. at 391.
    To the extent the two amendments conflicted with the earlier documents,
    they amounted to modifications of the parties’ contract.       See Caven v. American
    Fed. Sav. & Loan Ass’n , 
    837 F.2d 427
    , 430-31 (10th Cir. 1988) (citing        Rapp v.
    Mountain States Tel. & Tel. Co.    , 
    606 P.2d 1189
    , 1191 (Utah 1980)).
    Thus, the relevant contract documents are: Hunger’s quotation, sent in
    response to Hardie-Tynes’ request; Hardie-Tynes’ purchase order and amended
    purchase orders; and Hunger’s acknowledgments.         4
    The boilerplate language
    contained in the parties’ forms, however, did not change during the contracting
    process. As a consequence, there are only two sets of standard terms.
    2.     Framework for Analysis of Contract Documents
    Where “parties use[] prefabricated forms to evidence their deal,       they are
    not generally aware of a disparity between the standard terms printed on their
    forms.” Murray , supra note 4 at 1466. Usually, the parties “concentrate[]
    exclusively on the ‘dickered’ terms of the deal, i.e., those terms which they
    consciously adverted, such as the description of the goods, the quantity, the price
    4
    See John E. Murray, Jr., The Revision of Article 2: Romancing the Prism ,
    
    35 Wm. & Mary L. Rev. 1447
    , 1479 (1994) (noting that a “confirmation cannot be
    an acceptance because the acceptance has already occurred and a contract was
    formed. Section 2-207(1) [of the U.C.C], however, would have us pretend that
    the confirmation is an acceptance”).
    -12-
    and other terms which the decent merchant consciously would consider.”            
    Id.
    The purpose of U.C.C. § 2-207, often called the “Battle of the Forms” provision,
    is “to discover the genuine factual bargain of the parties.”       Id. at 1464, 1466.
    Under § 2-207, “additional terms inserted unilaterally in [an acceptance or]
    a confirmation form become part of a contract between merchants unless: an
    offer is made expressly conditional to its terms, § 2-207(2)(a); the additional
    terms are expressly objected to, § 2-207(2)(c); or     the terms cause a material
    alteration to the contract , § 2-207(2)(b).”    Avedon Eng’g, Inc. v. Seatex ,
    
    126 F.3d 1279
    , 1283 (10th Cir. 1997) (footnote omitted).       5
    5
    Section 2-207 provides, in pertinent part:
    Additional Terms in Acceptance or Confirmation.
    (1) A definite and seasonable expression of acceptance or a written
    confirmation which is sent within a reasonable time operates as an
    acceptance even though it states terms additional to or different from
    those offered or agreed upon, unless acceptance is expressly made
    conditional on assent to the additional or different terms.
    (2) The additional terms are to be construed as proposals for
    addition to the contract. Between merchants such terms become part
    of the contract unless:
    (a) the offer expressly limits acceptance to the terms of the offer;
    (b) they materially alter it; or
    (c) notification of objection to them has already been given or is
    given within a reasonable time after notice of them is received.
    -13-
    In this case, Hardie-Tynes and Hunger, who are both merchants, each argue
    that its own terms should control and the other’s should be completely
    disregarded. Hardie-Tynes’ “ all or nothing” theory was accepted by the district
    court.
    Hardie-Tynes makes a two-part argument: (1) Hunger’s conditions should
    be excluded because the face of its form does not call attention to the presence of
    terms on the reverse side and (2) its own conditions should control because it
    made acceptance conditional on assent to its terms. The first part of the argument
    is loosely based on case law reflecting the frequent use of forms which contain
    a provision on their face referring to terms on the reverse.   See, e.g. , Avila Group,
    Inc. v. Norma J. of Cal. , 
    426 F. Supp. 537
    , 541 (D.N.Y. 1977) (enforcing terms
    on reverse side which were referenced near the signature line on face of form);
    H.D. Fowler Co. v. Warren , 
    562 P.2d 646
    , 648 (Wash. App. 1977) (same).
    It does not necessarily follow, however, that this body of case law stands for the
    proposition that terms on the reverse side of a form are automatically excluded
    unless there is a reference to them on the face of the form.
    The per se rule suggested by Hardie-Tynes has no foundation in the
    language of U.C.C. § 2-207. Moreover, the application of such an artificial and
    technical rule would shed no light on the true factual bargain of the parties.
    Where, as here, the terms on the reverse side of a form are provided to the other
    -14-
    contracting party, not contradicted on the face of the form, and not concealed in
    some way, they may not be discounted simply because they are not referenced on
    the front of the form. Instead, the terms should be evaluated to determine
    whether they are “additional to or different from those offered or agreed upon,”
    U.C.C. § 2-207(1), and whether they “become part of the contract,” § 2-207(2).
    For purposes of a § 2-207 analysis, Hunger’s terms are on equal footing with
    those of Hardie-Tynes.   6
    The second part of Hardie-Tynes’ argument is that all of its own terms are
    included in the contract. To support this claim, Hardie-Tynes quotes the
    following language from its purchase order: “This Order constitutes Buyer’s
    offer to purchase and forms a binding contract on the terms set forth herein when
    accepted by Seller. . . . No modification of this Order . . . shall be binding upon
    Buyer if in conflict with or inconsistent with these terms and conditions, unless
    accepted in writing by Buyer.” Joint App. at 372.
    It is apparent that this language contemplates a transaction in which the
    “Buyer’s” purchase order constituted an offer which ripened into a contract only
    when the “Seller” accepted it.   Id. Here, however, Hunger (the seller) made the
    offer and Hardie-Tynes (the buyer) accepted with its purchase order. As a
    6
    We note that the U.C.C. does not require any of the terms at issue in this
    case to be conspicuous. See § 2-316(2) (requiring conspicuous exclusion or
    modification of implied warranties).
    -15-
    consequence, “the boilerplate provision does not directly address the instant
    case.” Daitom, Inc. v. Pennwalt Corp.    , 
    741 F.2d 1569
    , 1576 (10th Cir. 1984).
    The language cannot be understood to mean that, under § 2-207(2)(a),
    Hardie-Tynes made an offer expressly limiting acceptance to its terms; or, under §
    2-207(1), made its acceptance “expressly . . . conditional on assent to
    the additional or different terms.” This “imprecision of language, ”     Daitom ,
    
    741 F.2d at 1576
    , does not render Hunger’s terms completely controlling.
    Hunger’s competing argument suffers from the identical flaw. Paragraph
    one of Hunger’s standard terms and conditions states: “[o]rders placed by Buyer
    may be accepted by Seller only by executing Seller’s own acknowledgment form
    and returning it to the Buyer. It is the specific intent of the parties that the only
    contract between them is set forth in the terms and conditions herein stated.”
    Joint App. at 369, ¶ 1.
    This provision, like Hardie-Tynes’, was meant for use in a transaction in
    which the buyer’s offer was to be “accepted by Seller.”      
    Id.
     Hunger, however,
    included the provision in its offer and acknowledgment. As we have stated
    above, the boilerplate language does not serve to limit the Hardie-Tynes’
    contracting rights under these circumstances.
    Because neither Hardie-Tynes’ nor Hunger’s terms are in sole control of the
    agreement, their contract consists of: (1) terms on which their writings agree; and
    -16-
    (2) additional terms, proposed by either party, which are not material alterations
    of the agreement, see U.C.C. § 2-207(2)(b).
    B.     Summary Judgment on Breach of Contract Claim
    The district court granted Hardie-Tynes’ motion for partial summary
    judgment based on a determination that Hunger’s cylinders failed to meet the
    negotiated terms of the parties’ contract.
    Summary judgment is appropriate if the pleadings, depositions,
    answers to interrogatories, and admissions on file, together with the
    affidavits, if any, show that there is no genuine issue as to any
    material fact and that the moving party is entitled to judgment as
    a matter of law. In determining whether the evidence presents a
    genuine issue of material fact, we view it in the light most favorable
    to the party against whom summary judgment was entered.
    Anaya v. Crossroads Managed Care Sys., Inc.       , 
    195 F.3d 584
    , 589-90 (10th Cir.
    1999) (quotations and citation omitted). “The interpretation of an unambiguous
    contract is a question of law to be determined by the court and may be decided on
    summary judgment.”     Public Serv. Co. v. Burlington N. R.R.      , 
    53 F.3d 1090
    , 1096
    (10th Cir. 1995) (citation omitted).
    The intent of the parties governs contract interpretation.     See Willard Pease
    Oil & Gas Co. v. Pioneer Oil & Gas Co.      , 
    899 P.2d 766
    , 770 (Utah 1995). To
    determine intent, we examine the contract documents in light of the surrounding
    circumstances: “[R]ational interpretation requires at least a preliminary
    consideration of all credible evidence offered to prove the intention of the parties
    -17-
    . . . so that the court can place itself in the same situation in which the parties
    found themselves at the time of contracting.”     Ward v. Intermountain Farmers
    Ass’n , 
    907 P.2d 264
    , 268 (Utah 1995) (quotations omitted).
    Hunger does not maintain that it supplied cylinders meeting BOR standards.
    Instead, it insists that there are questions of fact as to whether it was under a
    contractual obligation to do so. First, Hunger asserts that it never agreed to
    accept the BOR specifications because paragraph one of its standard terms and
    conditions limited the contract to products depicted in Hunger’s own drawings.
    We have previously rejected the argument that this paragraph “limit[s] acceptance
    to the terms of the offer,” U.C.C. § 2-207(1), to the exclusion of the BOR
    specifications explicitly and repeatedly referenced in Hardie-Tynes’ documents.
    Hunger’s next argument also relates to its drawings. It claims that the
    drawing submitted to illustrate the proposed design for the piston seals and rings
    clearly shows that the Hunger cylinders differed in fundamental ways from the
    BOR drawings and specifications. Pointing out that the purchase order
    amendments and acknowledgments referred to this drawing, Hunger contends
    that the parties’ agreement was modified to require the production of only the
    cylinders depicted in that drawing.
    “It is well-settled law that the parties to a contract may, by
    mutual consent, alter all or any portion of that contract by agreeing
    upon a modification thereof. Where such a modification is agreed
    -18-
    upon, the terms thereof govern the rights and obligations of the
    parties under the contract, and any pre-modification contractual
    rights which conflict with the terms of the contract as modified
    must be deemed waived or excused.”
    Caven , 
    837 F.2d at 430
     (quoting   Rapp v. Mountain States Tel. & Tel. Co.   ,
    
    606 P.2d 1189
    , 1191 (Utah 1980) (footnotes omitted).
    A comparison of the original contract documents with the later amendments
    reveals that the only conflicting provisions relate to the design of the rings and
    seals. Moreover, at the time these documents were sent, the parties were focusing
    on this aspect of the design, and were not reopening contract negotiations.
    Hunger’s modification argument finds absolutely no support in the law or the
    record.
    Finally, Hunger argues that the district court failed to recognize the
    ambiguity of the contract. “The dispositive factor” in an ambiguity analysis
    is “whether an examination of the entire agreement reveals more than one
    reasonable interpretation.”   Gamble, Simmons & Co. v. Kerr-McGee Corp.          ,
    
    175 F.3d 762
    , 767 (10th Cir. 1999).
    As the basis for its alternative interpretation, Hunger observes that, in
    responding to Hardie-Tynes’s request for quotation, it stated only that the
    proposed cylinders would “meet your requirements,” and did not specifically
    incorporate the drawings and specifications which accompanied the request.
    -19-
    Although its conduct demonstrated a belief that BOR standards were applicable,
    Hunger now claims that this phrase created an ambiguity. The claim is that
    intended the phrase to mean an offer of cylinders that were capable of performing
    the required functions, but not necessarily complying with the specifications.
    In context, the phrase “meet your requirements” is unambiguous, readily
    understood to mean that the proposed cylinders must meet the detailed BOR
    drawings and specifications, and not susceptible to Hunger’s proposed
    interpretation. This court declines to “create and then construe an ambiguity.”
    
    Id. at 768
     (quotation omitted).
    We conclude, as did the trial court, that Hunger breached the unambiguous,
    unconflicting terms of the documents exchanged by Hardie-Tynes and Hunger.
    The disparity between the negotiated terms of the parties’ agreement and
    Hunger’s performance establishes Hunger’s liability for breach of contract.
    Summary judgment was the appropriate disposition of the breach of contract
    claim. 7
    7
    In its appellate brief, Hunger claims that Hardie-Tynes is not entitled
    to recover for breach of contract even if the cylinders were out of compliance
    with the terms of the contract. Citing U.C.C. § 2-607(2), Hunger argues that
    Hardie-Tynes waived the right to enforce the contract by accepting the cylinders
    with knowledge of their nonconformity. Hunger makes this argument for the first
    time on appeal, and we do not consider claims not first presented to the district
    court. See Walker v. Mather (In re Walker) , 
    959 F.2d 894
    , 896 (10th Cir. 1992)
    (continued...)
    -20-
    C.        Amount of Judgment
    Hunger also appeals the amount of assessed damages and the award of
    attorneys’ fees. The negotiated terms of the parties’ writings do not address
    these issues.
    1.   Damage Award
    Generally, “[t]he methodology a district court uses in calculating a damage
    award, such as determining the proper elements of the award or the proper scope
    of recovery, is a question of law” which we review de novo.    Southern Colo.
    MRI, Ltd. v. Med-Alliance, Inc.   , 
    166 F.3d 1094
    , 1100 (10th Cir. 1999). In this
    case, however, the parties stipulated that they “intended to resolve issues of
    damages” after the district court entered partial summary judgment on issues of
    liability, Joint App. at 272, and requested the court to “award and enter judgment
    7
    (...continued)
    We note in passing, however, that the argument appears to have no merit.
    Hunger twice gave false assurances that the cylinders complied with BOR
    requirements. Section 2-608 of the U.C.C. provides that a buyer
    may revoke his acceptance of a lot . . .whose non-conformity
    substantially impairs its value to him if he has accepted it
    (a) on the reasonable assumption that its non-conformity would be
    cured and it has not been seasonably cured; or
    (b) without discovery of such non-conformity if his acceptance was
    reasonably induced either by the difficulty of discovery before
    acceptance or by the seller’s assurances.
    -21-
    for damages in favor of Hardie-Tynes and against Hunger,”    id. at 71. The district
    court entered judgment based on the stipulation.
    Later, Hunger filed a motion asserting that $19,262 was improperly
    included in the damage calculation. Hunger argued that this amount is
    recoverable only as an indemnity, not an element of compensatory damages,
    because it represents Hardie-Tynes’ settlement payment to Murphy for
    replacement of the damaged cylinder. The district court refused to alter or
    amend the judgment amount. We review this post-judgment ruling under an abuse
    of discretion standard.   See Phelps v. Hamilton , 
    122 F.3d 1309
    , 1324
    (10th Cir.1997).
    The plain language of the parties’ stipulation establishes the amount of
    damages: it set out a lump sum for “compensatory damages,” without any
    separate provision or reservation regarding amounts paid to Murphy. In entering
    into the stipulation, Hunger waived the right to attack the amount of the damage
    award. See O’Rourke v. City of Norman , 
    875 F.2d 1465
    , 1475 (10th Cir. 1989);
    see also Mock v. T.G. & Y. Stores Co. , 
    971 F.2d 522
    , 526 (10th Cir. 1992) (“It is
    uncontested that a party to a consent judgment is thereby deemed to waive any
    objections it has to matters within the scope of the judgment.”) (quotation
    omitted). Accordingly, the district court did not abuse its discretion in denying
    Hunger’s post-judgment motion.
    -22-
    2.     Award of Attorneys’ Fees
    We review de novo the legal analysis underlying the district court’s
    decision concerning attorney fees.       See Chesapeake Operating, Inc. v. Valence
    Operating Co. , 
    193 F.3d 1153
    , 1157 (10th Cir. 1999). Here, the district court
    based its award of fees on a boilerplate provision of Hardie-Tynes’ purchase order
    form. 8 Under the terms of U.C.C. § 2-207(2)(b), this is an additional term
    inserted in an acceptance which may become part of the Hardie-Tynes/Hunger
    contract unless it constitutes a material alteration.   9
    “Terms which ‘materially
    alter’ a contract include those which result in surprise or hardship to the parties.”
    Seatex , 
    126 F.3d at
    1284 n.12 (quoting U.C.C. § 2-207 cmt. 4).
    Because of its blanket determination that all terms of the Hardie-Tynes’
    contract controlled the parties’ transaction, the district court did not conduct
    an analysis of whether the attorneys’ fees term constituted a material alteration
    8
    The provision states that “[i]n the event that Buyer commences litigation or
    arbitration upon Seller’s default to enforce the terms hereof, Seller shall be liable
    for the reasonable costs and attorney’s fees incurred by Buyer in pursuing such
    action or proceeding.” Joint App. at 372, ¶16.
    9
    As discussed above, Hardie-Tynes’ acceptance did not serve as an express
    limitation of acceptance to the terms of the offer, see U.C.C. § 2-207(2)(a), and
    Hunger’s confirmation did not amount to an express objection to Hardie-Tynes’
    term, see § 2-207(2)(c).
    -23-
    of the parties’ agreement. Accordingly, we remand this issue for the district
    court’s consideration.   10
    10
    We note that, under conventional U.C.C. analysis, “whether an addition
    to a contract constitutes a material alteration . . . depends on the unique facts
    of every case. Determining whether a term results in surprise or hardship
    requires the trial court to make a factual evaluation of the parties’ position in
    each case.” American Ins. Co. v. El Paso Pipe & Supply Co.       , 
    978 F.2d 1185
    ,
    1190 (10th Cir. 1992) (citations and quotation omitted). The Utah Supreme
    Court, however, has held that “[t]he addition of a provision for attorneys’ fees
    alters the offer materially and thus does not fall within the ‘additional or different
    terms’ which the statute renders acceptable by mere silence on the part of the
    offeror.” Johnson Tire Serv., Inc. v. Thorn, Inc.    , 
    613 P.2d 521
    , 523 (Utah 1980)
    (quoting Utah Code Ann. § 70A-2-207(1).
    The record before us provides no information on the issue of “what
    state’s law controlled the formation of the contract.” Seatex , 
    126 F.3d at 1284
    .
    We leave the matter to the district court on remand.
    -24-
    CONCLUSION
    We AFFIRM the district court’s entry of summary judgment on liability
    issues and its award of damages. We REVERSE the award of attorneys’ fees and
    remand the case for further proceedings consistent with this order and judgment.
    Entered for the Court
    Robert H. Henry
    Circuit Judge
    -25-
    

Document Info

Docket Number: 99-4042

Filed Date: 2/4/2000

Precedential Status: Non-Precedential

Modified Date: 4/18/2021

Authorities (25)

fred-w-phelps-sr-jonathan-b-phelps-karl-d-hockenbarger-charles-f , 122 F.3d 1309 ( 1997 )

the-american-insurance-company-a-new-jersey-corporation-v-el-paso-pipe , 978 F.2d 1185 ( 1992 )

Avedon Engineering, Inc. v. Seatex , 126 F.3d 1279 ( 1997 )

Moncrief v. Williston Basin Interstate Pipeline Co. , 174 F.3d 1150 ( 1999 )

Chesapeake Operating, Inc. v. Valence Operating Co. , 193 F.3d 1153 ( 1999 )

Anaya v. Crossroads Managed Care Systems, Inc. , 195 F.3d 584 ( 1999 )

In Re Donald Dean Walker, Debtor. Donald Dean Walker v. ... , 959 F.2d 894 ( 1992 )

Bancoklahoma Mortgage Corp. v. Capital Title Co. , 194 F.3d 1089 ( 1999 )

Daitom, Inc. v. Pennwalt Corporation , 741 F.2d 1569 ( 1984 )

southern-colorado-mri-ltd-a-colorado-limited-partnership , 166 F.3d 1094 ( 1999 )

jerry-l-caven-and-thomas-odonnell-dba-states-investment-a-partnership , 837 F.2d 427 ( 1988 )

charles-mock-v-tg-y-stores-co-an-oklahoma-corporation-household , 971 F.2d 522 ( 1992 )

Gamble, Simmons & Company v. Kerr-Mcgee Corporation , 175 F.3d 762 ( 1999 )

John N. Thompson v. United States , 312 F.2d 516 ( 1962 )

David Neifeld v. Meyer Steinberg. David Neifeld v. Meyer ... , 438 F.2d 423 ( 1971 )

Linda Hamilton, Individually and as of the Estate of George ... , 197 F.3d 58 ( 1999 )

Far West Capital, Inc. And Steamboat Development Corp. v. ... , 46 F.3d 1071 ( 1995 )

Public Service Company of Oklahoma v. Burlington Northern ... , 53 F.3d 1090 ( 1995 )

bel-ray-company-inc-v-chemrite-pty-ltd-lubritene-pty-ltd-ivor-h , 181 F.3d 435 ( 1999 )

michael-w-orourke-shirley-m-orourke-and-kathleen-orourke-v-the-city , 875 F.2d 1465 ( 1989 )

View All Authorities »