Tulsa Airports Improv. Trust v. FAA , 839 F.3d 945 ( 2016 )


Menu:
  •                                                                     FILED
    United States Court of Appeals
    Tenth Circuit
    PUBLISH                    October 14, 2016
    Elisabeth A. Shumaker
    UNITED STATES COURT OF APPEALS             Clerk of Court
    TENTH CIRCUIT
    TULSA AIRPORTS IMPROVEMENT
    TRUST, for and on behalf of Cinnabar
    Service Company,
    Petitioner,
    v.                                                   No. 15-5009
    FEDERAL AVIATION
    ADMINISTRATION,
    Respondent.
    ON PETITION FOR REVIEW OF A FINAL ORDER
    OF THE FEDERAL AVIATION ADMINISTRATION
    (Court of Federal Claims No. 13-906-CFL)
    Roger M. Gassett, of Hall, Estill, Hardwick, Gable, Golden & Nelson, P.C.,
    Tulsa, Oklahoma, (John M. Hickey, of Hall, Estill, Hardwick, Gable, Golden &
    Nelson, P.C., and Steven K. Metcalf of McDonald, McCann, Metcalf & Carwile,
    L.L.P., Tulsa, Oklahoma, with him on the briefs), for Petitioner-Appellant.
    Edward Himmelfarb, Attorney, Appellate Staff, Civil Division, Department of
    Justice, Washington, D.C., (Benjamin C. Mizer, Principal Deputy Assistant
    Attorney General; and Michael S. Raab, Attorney, Appellant Staff, Civil Division,
    Department of Justice, Washington, D.C., with him on the brief), for Respondent-
    Appellee.
    Before BRISCOE, MURPHY and PHILLIPS, Circuit Judges.
    BRISCOE, Circuit Judge.
    Tulsa Airports Improvement Trust (TAIT) seeks reimbursement for
    amounts it paid to a third-party contractor in furtherance of a noise abatement
    program funded primarily by grants from the Federal Aviation Administration
    (FAA). Because its petition for review of agency action was not timely filed, we
    dismiss the action.
    I
    Since the mid-1990s, TAIT has been working to reduce noise caused by the
    Tulsa International Airport. Tulsa Airports Improvements Trust v. United States,
    
    120 Fed. Cl. 254
    , 256–57 (2015). TAIT’s efforts have largely been funded by
    grants from the FAA. 
    Id. at 257.
    In 2002, while awaiting the approval of
    additional grant funding, TAIT instructed its contractors to place some projects
    on hold until additional funds were approved. 
    Id. at 257–58.
    As a result of the
    delay, some contractors “demanded contract increases or terminated their
    contracts.” 
    Id. at 258.
    Consequently, TAIT paid $705,913.40 to its contractors
    and then sought reimbursement from the FAA. 
    Id. The FAA
    initially reimbursed
    TAIT for the costs, but subsequently demanded repayments totalling $656,574.37
    after determining that the payments were “contract delay/escalation costs,” which
    were “not allowable” costs under the grants. 
    Id. TAIT reimbursed
    the FAA for
    these amounts. 
    Id. In 2010,
    TAIT sought reconsideration and the FAA provided
    2
    reimbursements for supplemental allowable costs in the amount of $569,566.00.
    See Agency Record (AR) at 2187.
    On January 23, 2012, TAIT informed the FAA that it had reviewed the
    remaining unpaid expenses 1 and had “identified numerous cost categories which
    [were] eligible for reimbursement.” AR at 487. TAIT requested that the FAA
    review the attached documentation and approve the reimbursements. 
    Id. On October
    24, 2012, the FAA’s Southwest Region responded that it had “carefully
    examined the information” provided and “[could not] make a favorable
    determination of additional allowable costs.” AR at 1140. This letter stated that
    “additional reviews on the [grants] would not be considered an efficient use of
    resources.” 
    Id. TAIT responded
    by appealing to the FAA’s Associate
    Administrator for Airports on December 6, 2012. AR at 1141. On December 31,
    2012, the Associate Administrator for Airports issued a letter to TAIT stating
    that, because TAIT’s most recent request for reimbursement did not delineate
    costs that had been reimbursed as well as allowable costs that were outstanding,
    the FAA was “unable to find that there [were] potentially eligible costs that ha[d]
    not been reimbursed.” AR at 2190. The letter further stated that TAIT should
    1
    Although the parties do not specify the amount contested, we estimate
    from the record that TAIT is seeking reimbursement for a portion of
    approximately $87,000.00 in outstanding expenses.
    3
    resubmit any information that it believed had not been considered. 
    Id. TAIT submitted
    no further documentation to the FAA.
    Instead, on November 14, 2013, TAIT filed a breach of contract action in
    the Court of Federal Claims, invoking jurisdiction under the Tucker Act, 28
    U.S.C. § 1491(a)(1). Tulsa Airports Improvements 
    Trust, 120 Fed. Cl. at 256
    .
    TAIT alleged that the FAA had wrongfully determined that the payments in
    question were “not allowable grant costs.” 
    Id. at 256.
    The Court of Federal
    Claims determined that it did not have subject matter jurisdiction because either
    49 U.S.C. § 46110 or 49 U.S.C. § 47111 vested exclusive jurisdiction in the
    United States Court of Appeals. 
    Id. at 263.
    Accordingly, it transferred the case to
    this court. 
    Id. at 265–66.
    For procedural purposes, we now consider it as a
    petition for review of agency action.
    II
    TAIT asks us to compel the FAA “to conduct a hearing to formally consider
    TAIT’s request for reimbursement under the Grants” — the procedure required by section
    47111. Aplt. Br. at 9. TAIT argues that section 47111 applies; that under either section
    46110 or section 47111, the FAA did not issue a final order appropriate for judicial
    review; and that even if the FAA did issue a final order, its wording created confusion
    that caused TAIT’s delay in filing this petition. We disagree.
    First, we conclude that 49 U.S.C. § 46110 governs this action because 49 U.S.C
    § 47111 does not apply. Section 46110 is a general review provision that allows a person
    4
    to petition for review of an order in which the person has a substantial interest.2 49
    U.S.C. § 46110(a). Section 47111 specifically allows a person to petition for review of
    an agency’s decision to withhold a payment that is due under a grant agreement.3 49
    2
    Section 46110(a) provides:
    (a) Filing and Venue. — Except for an order related to a
    foreign air carrier subject to disapproval by the President
    under section 41307 or 41509(f) of this title, a person
    disclosing a substantial interest in an order issued by the
    Secretary of Transportation (or the Under Secretary of
    Transportation for Security with respect to security duties and
    powers designated to be carried out by the Under Secretary or
    the Administrator of the Federal Aviation Administration with
    respect to aviation duties and powers designated to be carried
    out by the Administrator) in whole or in part under this part,
    part B, or subsection (l) or (s) of section 114 may apply for
    review of the order by filing a petition for review in the United
    States Court of Appeals for the District of Columbia Circuit or
    in the court of appeals of the United States for the circuit in
    which the person resides or has its principal place of business.
    The petition must be filed not later than 60 days after the order
    is issued. The court may allow the petition to be filed after the
    60th day only if there are reasonable grounds for not filing by
    the 60th day.
    3
    Section 47111(d) provides:
    (d) Withholding Payments. — (1) The Secretary may withhold
    a payment under a grant agreement under this subchapter for
    more than 180 days after the payment is due only if the
    Secretary— (A) notifies the sponsor and provides an
    opportunity for a hearing; and (B) finds that the sponsor has
    violated the agreement. (2) The 180-day period may be
    extended by— (A) agreement of the Secretary and the sponsor;
    or (B) the hearing officer if the officer decides an extension is
    necessary because the sponsor did not follow the schedule the
    officer established. (3) A person adversely affected by an
    order of the Secretary withholding a payment may apply for
    review of the order by filing a petition in the United States
    (continued...)
    5
    U.S.C. § 47111(d). This section also sets forth procedures that must be followed before a
    payment may be withheld. See 49 U.S.C. § 47111(d)(1).
    Contrary to TAIT’s contention, section 47111 does not apply to a finding that
    certain costs are not allowable under a grant agreement. Before the United States may be
    obligated to make a payment under a grant agreement, the statutory scheme requires that
    the Secretary first decide that the cost is allowable. 49 U.S.C. § 47110. Until such a
    determination has been made, no payment can be due. Section 47111 only applies to the
    withholding of payments that are “due” under a grant agreement. 49 U.S.C.
    § 47111(d)(1) (emphasis added). A determination that a particular cost is not allowable is
    not a withholding of a payment that is due, but merely a determination that no payment
    was ever owed. Furthermore, section 47111 applies to situations in which the payment is
    withheld due to a violation of the grant agreement. See 49 U.S.C. § 47111(d)(1)(B). In
    order to withhold a payment under this section, the Secretary must notify the sponsor,
    provide an opportunity for a hearing, and make a finding that the sponsor has violated the
    grant agreement. 49 U.S.C. § 47111(d)(1). The FAA made no such finding because there
    is no allegation that TAIT violated the grant agreement. The payments were denied
    because the costs were not allowable, and not because of an independent violation of the
    (...continued)
    Court of Appeals for the District of Columbia Circuit or in the
    court of appeals of the United States for the circuit in which
    the project is located. The petition must be filed not later than
    60 days after the order is served on the petitioner.
    6
    grant agreement. Because section 47111 does not apply, TAIT must challenge the FAA’s
    action under the general judicial review provision, 49 U.S.C. § 46110.
    Second, we conclude that the December 31, 2012 letter is a final order issued
    by the FAA. We have not previously had the opportunity to address what
    constitutes an “order” under section 46110, but those circuits that have considered
    the meaning of “order” under this section or its predecessor, 49 U.S.C. § 1486,
    have concluded that an agency decision is an “order” only if it possesses “the
    quintessential feature of agency decisionmaking suitable for judicial review:
    finality.” Vill. of Bensenville v. FAA, 
    457 F.3d 52
    , 68 (D.C. Cir. 2006) (citing
    Aerosource, Inc. v. Slater, 
    142 F.3d 572
    , 577 (3d Cir. 1998) (collecting cases)).
    Accordingly, the agency action must “mark the consummation of the agency’s
    decisionmaking process,” and “be one by which rights or obligations have been
    determined, or from which legal consequences will flow.” Bennett v. Spear, 
    520 U.S. 154
    , 177–78 (1997) (quotations omitted); see also Vill. of 
    Bensenville, 457 F.3d at 68
    (applying Bennett in the context of 49 U.S.C. § 46110). In addition,
    most circuits require that the alleged order “be predicated on an administrative
    record sufficient to allow a court to engage in a meaningful review,” but this
    requirement is “not a demanding one.” Burdue v. FAA, 
    774 F.3d 1076
    , 1080 (6th
    Cir. 2014) (collecting cases).
    A communication need not be formal to constitute a final agency action.
    Numerous circuits have held that letters from the FAA, including those not issued
    7
    by the Administrator, constitute “orders” for purposes of 49 U.S.C. § 46110.
    Aerosource, 
    Inc., 142 F.3d at 577
    –78 (collecting cases). Further, under a similar
    statute, we have concluded that an informal agency communication may constitute
    an order suitable for judicial review. TransAm Trucking, Inc. v. Fed. Motor
    Carrier Safety Admin., 
    808 F.3d 1205
    , 1212 n.4 (10th Cir. 2015) (“[T]he informal
    nature of the email communication doesn’t necessarily determine whether it was a
    ‘final order’ within the meaning of [28 U.S.C.] § 2342(3)(A).”). In addition,
    “[t]he mere possibility that an agency might reconsider in light of ‘informal
    discussion’ and invited contentions of inaccuracy does not suffice to make an
    otherwise final agency action nonfinal.” Sackett v. E.P.A., 
    132 S. Ct. 1367
    , 1372
    (2012).
    The FAA’s December 31, 2012 letter is a final order. The letter marks the
    consummation of the FAA’s decisionmaking process. It details TAIT’s prior
    requests and the FAA’s responses thereto, including the various requests, reviews,
    grants, and denials over the preceding ten years. There is no indication in the
    letter or in the record that any additional process on the FAA’s part was to follow.
    Although the letter does provide TAIT an opportunity to resubmit any information
    the FAA had not yet considered, this invitation does not make an otherwise final
    decision nonfinal. Absent additional action from TAIT, the FAA made clear that
    it would not reconsider the request. Following the receipt of the December 31,
    2012 letter, TAIT took no further action. In addition, the letter determined rights
    8
    and obligations by concluding that TAIT had no right to reimbursement for the
    requested funds and that the FAA had no obligation to pay them. These are legal
    consequences sufficient to indicate finality. Further, the administrative record,
    which includes nearly 3000 pages of letters, agreements, and payment records
    from 2002 through 2012, is sufficient for review. The parties have provided us
    with relevant communications between themselves, as well as documentation
    supporting TAIT’s claim to reimbursement. Thus, the December 31, 2012 letter
    from the FAA is a final order suitable for judicial review under section 46110.
    Third, we conclude that the action was not timely filed. Section 46110 provides
    that a petition for review of an agency order generally must be filed not later than
    sixty days after the agency order is issued. 49 U.S.C. § 46110(a). A court does
    have discretion to allow a petition filed after the sixtieth day if there are
    reasonable grounds for the delay. 
    Id. Because the
    FAA’s letter on December 31,
    2012 was a final order, the sixty-day period expired on March 1, 2013. TAIT did
    not file its action in the Court of Claims until November 14, 2013 4 — more than
    eight months after the statutory period expired. Further, TAIT has not established
    any reasonable grounds to justify its delay.
    4
    We consider this petition for review as if it had been filed in this court on
    the date on which it was actually filed in the Court of Federal Claims. See 28
    U.S.C. § 1631.
    9
    Agency-created confusion has been recognized in some circuits as a basis
    for finding delay to be reasonable. See, e.g., Safe Extensions, Inc. v. FAA, 
    509 F.3d 593
    , 603–04 (D.C. Cir. 2007) (excusing delay when the FAA had stated that a
    revision was forthcoming but never issued one); Greater Orlando Aviation Auth.
    v. FAA, 
    939 F.2d 954
    , 960 (11th Cir. 1991) (excusing delay when the FAA’s
    inconsistent communications caused confusion), abrogated on other grounds by
    Henderson v. Shinseki, 
    562 U.S. 428
    , 438 (2011), as recognized in Corbett v.
    TSA, 
    767 F.3d 1171
    , 1174 (11th Cir. 2014). But we do not have such factual
    circumstances here. The D.C. Circuit has twice held this year that ambiguity in a
    letter issued by an agency does not excuse delay. See Nat’l Fed’n of the Blind v.
    DOT, 
    827 F.3d 51
    , 57 (D.C. Cir. 2016); Elec. Privacy Info. Ctr. v. FAA, 
    821 F.3d 39
    , 43 (D.C. Cir. 2016). We agree with the D.C. Circuit that parties should
    assume finality in the face of ambiguity and file protectively for judicial review.
    See 
    id. Thus, if
    there was any ambiguity in the December 31, 2012 letter, it does
    not excuse TAIT’s delay in filing a petition for review. Moreover, a plain reading
    of the December 31, 2012 letter makes clear that the FAA’s determination was
    final and no reimbursements would be issued unless TAIT took further action,
    either by resubmitting documentation in the format recommended by the FAA, or
    by appealing to this court within sixty days. TAIT did neither.
    III
    The petition for review of agency action is DISMISSED as not timely filed.
    10