Carr Office Park, LLC v. Charles Schwab & Co., Inc. , 291 F. App'x 178 ( 2008 )


Menu:
  •                                                                            FILED
    United States Court of Appeals
    Tenth Circuit
    August 29, 2008
    UNITED STATES COURT OF APPEALS
    Elisabeth A. Shumaker
    TENTH CIRCUIT                         Clerk of Court
    CARR OFFICE PARK, LLC, a Delaware
    limited liability company,
    Plaintiff - Appellant,
    No. 07-1277
    v.                                              (D. Colorado)
    CHARLES SCHWAB & CO., INC., a                 (D.C. No. 05-CV-2572-EWN-BNB)
    California corporation,
    Defendant - Appellee.
    ORDER AND JUDGMENT *
    Before MURPHY, HARTZ, and GORSUCH, Circuit Judges.
    Plaintiff Carr Office Park, LLC (Carr) and defendant Charles Schwab &
    Co., Inc. (Schwab) are, respectively, landlord and tenant in a corporate center
    located in Colorado. Numerous leases and agreements regulate the relationship
    between the parties. This dispute arose out of an agreement that obligated Carr to
    build an office complex and associated parking garage, which Schwab was then
    *
    This order and judgment is not binding precedent except under the
    doctrines of law of the case, res judicata, and collateral estoppel. It may be cited,
    however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th
    Cir. R. 32.1.
    obligated to lease. Changed circumstances led the parties to alter the agreement
    so that it covered a multiple-tenant parking garage, rather than an single-tenant
    office complex. After completion of the parking garage, Carr and Schwab were
    unable to agree on the terms governing the lease of the garage. Carr filed this suit
    in Colorado state court, claiming Schwab was in breach of contract for its failure
    to pay rent for the garage. Schwab removed the action to the Federal District
    Court for the District of Colorado. The district court, with diversity jurisdiction
    pursuant to 
    28 U.S.C. §§ 1332
     and 1441, determined that essential elements of the
    parking garage lease were ambiguous and the agreements between the parties
    constituted only an unenforceable agreement to agree. The district court
    accordingly granted Schwab’s motion for summary judgment. This court has
    jurisdiction under 
    28 U.S.C. § 1291
     and AFFIRMS the judgment of the district
    court.
    I. Background
    Carr owns and operates an office park in Arapahoe County, Colorado
    known as Panorama Corporate Center. In 1997, Carr and Schwab entered into a
    lease (Building III Lease) for a building known as Panorama III in the Corporate
    Center. At the same time, Carr and Schwab entered into an Option Agreement.
    Under the Option Agreement, Schwab was entitled to exercise five Expansion
    Notices, which would trigger Carr’s obligation to construct a new building and
    Schwab’s obligation to lease the newly constructed premises. The Option
    -2-
    Agreement specified that after the exercise of an expansion option, Carr would
    deliver a lease for the new building (New Building Lease). The Option Agreement
    also specified that the failure of the parties to agree to a New Building Lease
    would not affect the validity of the Expansion Notice. Rather, absent an
    agreement to alternate terms, the New Building Lease would contain, as a default,
    the same terms and conditions expressed in the Building III Lease. In December
    of 2000, the parties entered into the Second Amendment to the Option Agreement.
    That Amendment replaced the default lease terms from the Building III Lease
    with the terms negotiated for a different, prior lease between the parties for the
    Panorama VIII development. This new default lease was termed the Lease Form
    for New Buildings (Lease Form).
    In June of 2000 Schwab exercised its expansion option, requiring Carr to
    build a new office site and parking garage known as Panorama IV. After the
    exercise of this option, Carr was approached by the Regional Transportation
    District (RTD) regarding the proposed construction of a light rail stop and
    parking facilities near the Panorama IV building site. Carr and RTD, with
    Schwab’s knowledge, entered into an agreement under which the Panorama IV
    parking garage (Shared Parking Facility) would be shared by RTD and Schwab.
    Carr and Schwab entered into the Third Amendment to the Option Agreement, by
    which Schwab formally approved the agreement between Carr and RTD and
    -3-
    agreed that Carr would not be in breach of the Option Agreement by performing
    its contractual obligations to RTD.
    Subsequently, Schwab determined that, due to current economic conditions,
    it no longer wished to go forward with the Panorama IV expansion. The parties
    agreed in the Fourth Amendment to the Option Agreement (Fourth Amendment)
    that Schwab could revoke its exercise of the expansion option with respect to the
    office building in exchange for payments in excess of seven million dollars. 1 The
    Fourth Amendment specified that the revocation did not apply to Schwab’s lease
    of the Shared Parking Facility. It stated, “[u]pon completion of the Shared
    Parking Facility, [Schwab] shall be required to lease from [Carr] the parking
    spaces which are contained in two lowest levels of the Shared Parking Facility
    (the ‘Parking Spaces’).” The Fourth Amendment further provided that,
    within [sixty] days after [Schwab’s] receipt of [Carr’s] notice of
    commencement of construction of the Shared Parking Facility, [Carr]
    and [Schwab] shall, in good faith, negotiate and finalize a lease
    document (the “Garage Structure Lease”) based on the Lease Form
    for New Buildings . . . concerning [Schwab’s] lease of the Parking
    Spaces which requires [Schwab] to pay to [Carr] an annual triple net
    rent for use of the Parking Spaces calculated as a product of the Total
    Project Costs (as such term is defined in the Lease Form) for [Carr’s]
    cost of the construction of [Schwab’s] portion of the Shared Parking
    Facility and the Return Rate for Panorama IV . . . . [Carr] estimates
    that such rent will equal $502,200.00 per annum (triple net) assuming
    a Total Project Cost of $5,400,000.00 for [Schwab’s] portion of the
    Shared Parking Facility.”
    1
    Schwab ultimately made a termination payment of $7,142,777 to Carr.
    -4-
    In addition, the Fourth Amendment dictated that “[i]n the event of any conflict
    between the terms and provisions of the Option Agreement, as it has previously
    been amended, and the terms and provisions of this Fourth Amendment, the terms
    and provisions of this Fourth Amendment shall control.”
    In January of 2004 Carr notified Schwab that it would commence
    construction of the Shared Parking Facility in February. As agreed to in the
    Fourth Amendment, this notification triggered negotiations between the parties
    for a Shared Parking Facility lease. On March 5, 2004, Carr representative Lisa
    Foyston sent Schwab a proposed lease (March 5 Draft). The March 5 Draft was
    redlined against a previously proposed draft lease for the entire Panorama IV
    complex, with changes intended to convert the lease into one for only the parking
    garage. Included in those changes were deletions of terms that would allow
    Schwab to purchase the premises (Article 33) and giving Schwab a right of first
    offer on the parking garage (Article 34). Schwab rejected the March 5 Draft and
    the parties continued their negotiations. The negotiations between the parties
    included discussions on issues such as the premises covered by the lease, which
    party bore the maintenance obligations for the structure, rental of excess space by
    Schwab, and whether an extension option would exist.
    The parties failed to resolve these issues. The Shared Parking Facility was
    completed and delivered on December 3, 2004, but Schwab has never occupied
    the Facility nor paid rent. Carr brought suit on November 29, 2005, alleging
    -5-
    Schwab was in breach of contract. In the district court, the parties filed cross
    motions for summary judgment. Carr argued the existing agreements obligated
    Schwab to pay rent on the Shared Parking Facility and its failure to do so
    constituted breach. Schwab claimed no such agreement existed because material
    elements, such as rent, remained unresolved. It further argued that the Fourth
    Amendment constituted an unenforceable “agreement to agree.” The district
    court agreed that unresolved material terms to the lease rendered any agreement
    unenforceable and granted summary judgment to Schwab on Carr’s breach of
    contract claim.
    II. Discussion
    This court reviews a district court’s grant of summary judgment de novo,
    applying the same legal standards as the district court. Jones v. Denver Post
    Corp., 
    203 F.3d 748
    , 751 (10th Cir. 2000). We examine the factual record and
    reasonable inferences therefrom in the light most favorable to the nonmoving
    party, in this case, Carr. Concrete Works of Colo., Inc. v. City & County of
    Denver, 
    36 F.3d 1513
    , 1517 (10th Cir. 1994). Summary judgment is appropriate
    only “if the pleadings, the discovery and disclosure materials on file, and any
    affidavits show that there is no genuine issue as to any material fact and that the
    movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(c). The
    moving party must show the absence of evidence supporting the nonmoving
    party’s case. Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 325 (1986). If this burden
    -6-
    is met, the nonmoving party must then show a genuine issue of material fact
    exists. Fed. R. Civ. P. 56(e)(2). In so doing, it may not rely solely on the
    allegations made in its pleadings, but must set out specific facts demonstrating a
    genuine issue for trial. 
    Id.
     When sitting in diversity, this court applies the law of
    the forum state, here Colorado. Woolard v. JLG Indus., Inc., 
    210 F.3d 1158
    , 1168
    (10th Cir. 2000).
    To create an enforceable and binding contract, all essential elements must
    be settled or a method of settlement must be agreed upon. Greater Serv.
    Homebuilders’ Inv. Ass’n v. Albright, 
    293 P. 345
    , 348 (Colo. 1930). “If the
    writing leaves the agreement of the parties vague and indefinite as to an essential
    element thereof, it is no contract and cannot be made one by parol.” 
    Id.
     at 348-
    49. “To have an enforceable contract it must appear that further negotiations are
    not required to work out important and essential terms.” New York Life Ins. Co.
    v. K N Energy, Inc., 
    80 F.3d 405
    , 409 (10th Cir. 1996) (applying American
    Mining Co. v. Himrod-Kimball Mines, Co., 
    235 P.2d 804
    , 807-08 (Colo. 1951) (en
    banc)). When parties have entered into an “agreement to agree,” the purported
    contract is unenforceable because the court cannot force parties to reach an
    agreement and therefore no remedy is available. Griffin v. Griffin, 
    699 P.2d 407
    ,
    409 (Colo. 1985) (holding that an agreement by two parents to “negotiate and
    reach agreement at some future time concerning their child’s education” was
    unenforceable). “[C]ontract interpretation is a question of law that is reviewed de
    -7-
    novo.” Ad Two, Inc. v. City & County of Denver, 
    9 P.3d 373
    , 376 (Colo. 2000)
    (en banc). Evidence beyond the language of the instrument itself is admissible
    only where there is an ambiguity in the terms of the contract. 
    Id.
    Carr argues the Option Agreement specified all essential terms of the lease
    and therefore was unambiguous and enforceable. Carr contends that Colorado
    law specifies only four essential elements of a valid lease: (1) the boundaries of
    the property to be leased, (2) the term of the lease, (3) the amount of rent to be
    paid, and (4) the rent commencement date. 2 Carlson v. Bain, 
    182 P.2d 909
    , 911
    (Colo. 1947). Because the agreements between the parties contained these
    essential term, Carr argues, an enforceable lease exists. Schwab maintains that
    the district court correctly determined that neither the Lease Form nor the Option
    Agreement contained a final accord concerning rent for the Shared Parking
    Facility and, as a result, no binding contract existed.
    We agree. The agreements between the parties constitute only an
    unenforceable “agreement to agree.” The Fourth Amendment unambiguously
    states that Schwab and Carr “shall, in good faith, negotiate and finalize a lease
    document . . . concerning [Schwab’s] lease of the Parking Spaces which requires
    2
    Schwab contests Carr’s assertion that any lease with these four elements is
    enforceable under Colorado law. Schwab argues that these elements are
    necessary, but not always sufficient. We find it unnecessary to resolve this
    dispute because Carr cannot show that all of the elements it acknowledges are
    necessary existed in its agreements with Schwab.
    -8-
    [Schwab] to pay [Carr] . . . rent” (emphasis added). The Fourth Amendment also
    provides “[t]he Garage Structure Lease will require [Schwab] to agree to an initial
    lease term of 15 years” (emphasis added). These provisions demonstrate that the
    Garage Structure Lease was a document to be negotiated and agreed to at a future
    date.
    Furthermore, unlike the previous agreement between the parties, the Fourth
    Amendment did not designate lease terms to be used in the event of a failure to
    reach an accord on a new lease. The Option Agreement explicitly states that, in
    the event a New Building Lease cannot be negotiated, “[t]he lease of the New
    Building shall be on (and the New Lease shall contain) the same terms and
    conditions of the [Lease Form].” In contrast, the Fourth Amendment requires
    only that the parties negotiate a Shared Parking Facility lease “based on the Lease
    Form for New Buildings.” Unlike the unamended Option Agreement, the Fourth
    Amendment does not provide a fully negotiated fallback lease. The Fourth
    Amendment specified that in the event of a conflict between the Option
    Agreement and the terms of the Fourth Amendment, the Fourth Amendment
    would control. As a result, the Fourth Amendment constitutes only an agreement
    to agree, which is “unenforceable because the court has no power to force the
    parties to reach agreement and cannot grant a remedy.” Griffin, 699 P.2d at 409.
    The ambiguities concerning the amount of rent to be paid on the Shared
    Parking Structure further supports this conclusion. Carr argues the Fourth
    -9-
    Amendment itself was a fully negotiated agreement specifying all essential
    elements of the lease for the Shared Parking Facility. In particular, it claims the
    Fourth Amendment provided a method for calculating the Shared Parking Facility
    rent. It points to the parties’ agreement that “an annual triple net rent for use of
    the Parking Spaces calculated as a product of the Total Project Costs (as such
    term is defined in the Lease Form) for [Carr’s] cost of the construction of
    [Schwab’s] portion of the Shared Parking Facility and the Return Rate for
    Panorama IV . . . .” Carr argues that this provision constitutes an enforceable
    agreement on rent. It acknowledges that “Total Project Costs” is defined by
    reference to the Lease Form, but maintains the Fourth Amendment’s definition is
    nevertheless unambiguous.
    The calculation of rent agreed to in the Fourth Amendment, however,
    leaves two ambiguities which render the formula for rent meaningless absent
    further negotiations. First, as defined in the Fourth Amendment, one element of
    the formula is “[Carr’s] cost of the construction of [Schwab’s] portion of the
    Shared Parking Facility.” Yet the Fourth Amendment provides no definition for
    Schwab’s portion of the Shared Parking Facility. It could arguably be defined as
    only the Parking Spaces themselves or include areas used for ingress and egress,
    land surrounding the garage, structural elements of the garage, and the land
    underneath the garage. Without an agreement between the parties as to how to
    determine Schwab’s portion of the Shared Parking Facility, rent cannot be
    -10-
    calculated. An agreement that is “vague and indefinite as to an essential element”
    cannot be enforced. Albright, 293 P. at 348-49.
    Second, Total Project Costs, an element of the rent calculation, is defined
    in the Lease Form. The definition includes land costs, construction hard and soft
    costs, construction of infrastructure on the land, and “the cost of operating and
    maintaining the Premises.” The definition of construction hard costs included
    “Building Cost,” “Parking Structure,” and “Site Costs for the Premises.” The
    Lease Form defines “Premises” as “the Land, the Building, the Parking Lot and
    the Parking Structure appurtenant thereto, and all other improvements on the
    Land.” All provisions, however, contemplate a single-owner office complex and
    do not address the allocation of costs for a parking structure with two tenants.
    Thus, the Fourth Amendment and the Option Agreement do not specify how much
    of the land originally allocated for the Panorama IV complex is properly included
    in the cost of constructing only the Shared Parking Facility. Nor do the
    documents explain how the construction and maintenance costs of shared portions
    of the garage should be allocated between the two tenants. Without these
    components, rent cannot be calculated and the agreements are ambiguous as to an
    essential element.
    Carr attempts to refute this conclusion by arguing that “both parties
    understood that the ‘Tenant’s portion of the Shared Parking Facility’ means all of
    the lowest two floors of the parking garage and the associated improvements” and
    -11-
    that this is also the definition of Premises that should be used to calculate rent.
    Carr does not point to anything in the record, however, to show this
    understanding existed. Rather, the record shows that Carr took the position in
    lease negotiations that the Premises meant “the Land (subject to the ‘RTD
    Easement’ as such term is defined in the RTD Agreement), the Parking Structure
    and those certain other improvements located on the Land which provide access
    (ingress and egress) to the Parking Structure.” Carr argues that it took this
    position only as a negotiating tactic and it has no bearing on the Fourth
    Amendment’s default definition of Schwab’s portion of the Shared Parking
    Facility. This assertion is belied, however, by Carr’s calculations of rent for its
    damages exhibit before the district court. Carr admitted before the district court
    that its calculation of rent relied on a definition of Premises that included the cost
    of the land upon which the Shared Parking Facility was situated, including
    “ingress and egress and anything that relates to the garage.” In earlier
    negotiations, Schwab had contested this characterization of “Premises.” Carr’s
    contention that the parties had a shared understanding of “Tenant’s portion of the
    Shared Parking Facility” or “Premises” is not supported by the record.
    Carr also argues that the Option Agreement, as amended, evinces the
    parties’ intent to bind themselves to a lease for the garage. It notes the parties’
    agreement in the Fourth Amendment that Schwab’s obligation to lease the Shared
    Parking Facility “cannot and shall not be revoked.” The district court’s decision,
    -12-
    Carr maintains, does not give effect to the intent of the parties as evidenced by
    the clear language of the agreement. While it is true the parties agreed Schwab
    had an obligation to lease a portion of the Shared Parking Facility from Carr
    pursuant to a yet to be negotiated Shared Parking Facility Lease, this court cannot
    force the parties to come to an accord on essential elements that are left
    ambiguous. See Griffin, 699 P.2d at 409.
    In the alternative, Carr argues that the district court erred by granting
    summary judgment because a genuine dispute of material fact existed regarding
    the parties’ agreement on what “Premises” were leased to Schwab. A dispute of
    material fact is genuine “if the evidence is such that a reasonable jury could
    return a verdict for the nonmoving party.” Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986). Carr maintains that a triable issue of fact exists concerning
    whether the parties agreed upon the Premises leased to Schwab. See United
    States v. Hess, 
    194 F.3d 1164
    , 1174 (10th Cir. 1999) (“[W]here interpretation of a
    contract requires examination of extrinsic evidence to determine intent, and where
    more than one inference may be drawn therefrom, a question of fact is
    presented.”).
    Here, however, Carr has not pointed to any extrinsic evidence that an
    agreement between the parties existed as to the bounds of the Premises in the
    Fourth Amendment. Rather, Carr relies only on the “plain language of the Fourth
    Amendment” as support for its position. Contract interpretation, however, is a
    -13-
    matter of law. Ad Two, Inc., 9 P.3d at 376. As explained above, this court holds
    that as a matter of law the Fourth Amendment is ambiguous with respect to the
    extent of the Premises and the only extrinsic evidence in the record indicates that
    an agreement on the meaning of the term did not exist. Absent any extrinsic
    evidence suggesting there was an agreement as to the Premises to be leased, there
    is no genuine issue of fact for trial.
    III. Conclusion
    For the foregoing reasons, the judgment of the district court is
    AFFIRMED.
    ENTERED FOR THE COURT
    Michael R. Murphy
    Circuit Judge
    -14-