Geosyntec Consultants, Inc. v. United States , 776 F.3d 1330 ( 2015 )


Menu:
  •                Case: 14-11107       Date Filed: 01/29/2015     Page: 1 of 29
    [PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 14-11107
    ________________________
    D.C. Docket No. 9:12-cv-80334-DLB
    GEOSYNTEC CONSULTANTS, INC.,
    Plaintiff - Appellant,
    versus
    UNITED STATES OF AMERICA,
    Defendant - Appellee.
    ________________________
    Appeal from the United States District Court
    for the Southern District of Florida
    ________________________
    (January 29, 2015)
    Before WILSON and ROSENBAUM, Circuit Judges, and CONWAY, ∗ District
    Judge.
    WILSON, Circuit Judge:
    ∗
    Honorable Anne C. Conway, Chief United States District Judge for the Middle District
    of Florida, sitting by designation.
    Case: 14-11107    Date Filed: 01/29/2015   Page: 2 of 29
    Plaintiff-appellant Geosyntec Consultants, Inc. (Geosyntec) appeals the
    district court’s grant of summary judgment in favor of defendant-appellee United
    States of America (United States) and against Geosyntec, in which the district
    court found that Geosyntec was not entitled to research tax credits pursuant to 26
    U.S.C. § 41 for research expenses incurred on certain client projects during tax
    years 2002 to 2005.
    Under § 41, a taxpayer may claim a tax credit for increased spending on
    qualified research. Certain categories of research are expressly excluded from the
    definition of “qualified research.” Specifically, under § 41(d)(4)(H), a taxpayer is
    precluded from claiming the research tax credit when otherwise qualifying
    research is “funded” by a third party. The district court found that research
    conducted by Geosyntec pursuant to two particular contracts was funded by
    Geosyntec’s clients, making Geosyntec ineligible for the research tax credit for
    those contracts. On appeal, Geosyntec challenges the district court’s
    categorization of those contracts as funded.
    We are thus asked to consider whether the research performed by Geosyntec
    pursuant to the two contracts was funded by Geosyntec’s clients (making
    Geosyntec ineligible for the research tax credit) or not funded (such that Geosyntec
    is entitled to claim the research tax credit). Although we have not previously had
    occasion to consider the applicability of § 41(d)(4)(H)’s funded research exclusion,
    2
    Case: 14-11107    Date Filed: 01/29/2015   Page: 3 of 29
    the Federal Circuit has, and the parties rely heavily on that court’s seminal opinion.
    See Fairchild Indus., Inc. v. United States, 
    71 F.3d 868
    (Fed. Cir. 1995), modified
    (Feb. 23, 1996). Upon review, we conclude that the district court was correct in its
    interpretation of § 41 and affirm its entry of summary judgment against Geosyntec.
    I.
    Geosyntec is a specialized consulting and engineering firm that contracts
    with clients, both public and private, to provide services on projects involving the
    environment, natural resources, and geological infrastructure. It specializes in
    environmental studies and cleanup, infrastructure design and engineering, and
    natural resources assessment and restoration. Geosyntec’s stated business model is
    the development of innovative and sustainable solutions to environmental issues
    facing its clients.
    In 2012, Geosyntec filed suit in the district court, seeking a federal income
    tax refund of $1,677,432 pursuant to 26 U.S.C. § 41—the research tax credit.
    Geosyntec alleged that it was entitled to research tax credits for qualified research
    expenses that it incurred on client projects in taxable years 2002, 2003, 2004, and
    2005. Geosyntec had previously sought a federal income tax refund from the
    Internal Revenue Service (IRS), which the IRS had disallowed. In response to
    Geosyntec’s district court action, the United States maintained its position that
    Geosyntec was not eligible for any tax refund under § 41.
    3
    Case: 14-11107     Date Filed: 01/29/2015     Page: 4 of 29
    Between 2002 and 2005, Geosyntec entered into hundreds of varied
    contracts with its clients. In the interest of efficiency, Geosyntec and the United
    States designated six representative contracts for the district court’s review. Three
    of the contracts were fixed-price contracts, under which Geosyntec was paid a
    fixed total price for its work. The other three contracts were cost-plus contracts
    subject to a maximum, also known as “capped contracts,” under which Geosyntec
    was paid for its labor and expenses, plus a mark-up, subject to an agreed-upon
    maximum price.
    The parties further agreed on three key issues: (1) Geosyntec could not claim
    the research tax credit if a third party had “funded” the otherwise qualified
    research; (2) Geosyntec’s existing client contracts governed determination of the
    funding issue and, there being no factual disputes as to those contracts, expert
    testimony would be unnecessary; and (3) if the district court determined
    Geosyntec’s research was funded, the United States was entitled to judgment in its
    favor. A finding that Geosyntec’s research was not funded, however, would
    necessitate further litigation on additional fact-intensive issues related to
    Geosyntec’s right to the research tax credit.
    Given the parties’ stipulations and on the parties’ joint motion, the district
    court authorized summary judgment briefing on the threshold matter of whether
    research performed by Geosyntec under the representative fixed-priced and capped
    4
    Case: 14-11107     Date Filed: 01/29/2015   Page: 5 of 29
    contracts was funded within the meaning of § 41. The parties filed cross-motions
    for summary judgment on the funding issue.
    On April 17, 2013, the district court entered an order granting each party’s
    motion for summary judgment in part and denying each in part. As to the three
    capped contracts, the district court agreed with the United States and found those
    contracts funded, making Geosyntec ineligible for the research tax credit for
    research expenses incurred under the capped contracts. As to the three fixed-price
    contracts, the district court agreed with Geosyntec and found that those contracts
    were not funded. Therefore, Geosyntec remained eligible for the research tax
    credit for qualifying research expenses it incurred under the fixed-price contracts.
    Because Geosyntec remained eligible for the research tax credit as to the
    fixed-price contracts, further litigation would be necessary to determine whether
    Geosyntec was, in fact, entitled to the research tax credit. However, in lieu of
    further litigation, the parties entered into a settlement agreement. Pursuant to the
    parties’ settlement, the district court entered an agreed-upon judgment that, among
    other things, (a) allowed Geosyntec a federal income tax refund totaling $255,575,
    plus statutory interest, for the unfunded fixed-price contracts; (b) denied a refund
    5
    Case: 14-11107         Date Filed: 01/29/2015        Page: 6 of 29
    for the funded capped contracts; and (c) preserved Geosyntec’s right to appeal the
    district court’s ruling as to the capped contracts. This appeal followed.1
    II.
    We review a district court’s order granting summary judgment de novo,
    applying the same legal standards as those applied by the district court.2 See
    Thrasher v. State Farm Fire & Cas. Co., 
    734 F.2d 637
    , 638 (11th Cir. 1984) (per
    curiam). To this end, we view the evidence and make all reasonable inferences in
    favor of the non-moving party. See Whatley v. CNA Ins. Cos., 
    189 F.3d 1310
    ,
    1313 (11th Cir. 1999) (per curiam). Summary judgment is properly granted only
    where there exists “no genuine issue of material fact and the moving party is
    entitled to judgment as a matter of law.” See Beal v. Paramount Pictures Corp., 
    20 F.3d 454
    , 458 (11th Cir. 1994) (citing Fed. R. Civ. P. 56(c)).
    III.
    Geosyntec contends that the district court erred in finding that the three
    capped contracts were funded and that Geosyntec was thus ineligible for the
    research tax credit as to research expenses incurred under those contracts. While
    1
    The United States did not appeal the district court’s partial denial of its motion for
    summary judgment.
    2
    To the extent that Geosyntec’s appeal is a more narrow challenge to the district court’s
    reading of the applicable statutes and regulations or its interpretation of the contracts at issue, our
    standard of review remains the same, as both statutory and contractual interpretation present
    questions of law that we review de novo. See Tobin v. Mich. Mut. Ins. Co., 
    398 F.3d 1267
    , 1274
    (11th Cir. 2005) (per curiam).
    6
    Case: 14-11107         Date Filed: 01/29/2015        Page: 7 of 29
    three capped contracts were before the district court, Geosyntec appeals the district
    court’s summary judgment ruling as to only two: (1) a contract with the Delaware
    Solid Waste Authority (DSWA) to expand the capacity of the Cherry Island
    Landfill in Wilmington, Delaware (the Cherry Island Contract); and (2) a contract
    with Waste Management, Inc. (WM) to evaluate technology for remediating
    groundwater beneath a warehouse in Niagara, New York (the WM Contract). 3
    After consideration of the applicable statute and regulations, the district
    court found that both the Cherry Island Contract and the WM Contract were
    funded within the meaning of § 41 and Geosyntec was therefore not entitled to
    claim the research tax credit for research conducted pursuant to those contracts.
    Geosyntec agrees with the district court’s invocation of the standard articulated in
    
    Fairchild, 71 F.3d at 873
    , that the funded research inquiry “turns on who bears the
    research costs upon failure” of the research; but it challenges the district court’s
    application of that standard to the Cherry Island and WM Contracts. According to
    Geosyntec, both of those contracts place the costs of research failure “squarely” on
    Geosyntec, and it is thus eligible for the research tax credit. The United States
    disagrees. On de novo review, we find that the district court correctly applied § 41
    3
    As set forth above, the district court found all three of the capped contracts before it
    funded for purposes of the research tax credit. However, on appeal, Geosyntec challenges the
    district court’s order as to only two of those contracts; it does not appeal the district court’s order
    as to the third capped contract between Geosyntec and Pneumo Abex Corporation. Any
    challenge to the district court’s characterization of that contract as funded is deemed abandoned.
    See Sapuppo v. Allstate Floridian Ins. Co., 
    739 F.3d 678
    , 680 (11th Cir. 2014) (issues not briefed
    on appeal are abandoned).
    7
    Case: 14-11107        Date Filed: 01/29/2015       Page: 8 of 29
    and its implementing regulations to the Cherry Island Contract and to the WM
    Contract.
    A.
    Our analysis begins with an examination of the language of the statute and
    its overarching purpose. The research tax credit was enacted as part of the
    Economic Recovery Tax Act of 1981 4 to incentivize American industry to invest in
    research. See 
    id. at 870,
    874. “[D]esigned to divert additional resources to
    research by reducing the cost of that additional research,” 
    id. at 874,
    its importance
    is evidenced by Congress’ repeated extension of the credit since its inception, see,
    e.g., H.R. Conf. Rep. No. 100-1104, pt. 2, at 78 (1988) (“[E]ffective tax incentives
    for research and development must be a fundamental element of America’s
    competitiveness strategy.”). Still, as with all tax credits, taxpayers who claim the
    research tax credit bear the burden of establishing their entitlement to it. See
    MedChem (P.R.), Inc. v. Comm’r, 
    295 F.3d 118
    , 123 (1st Cir. 2002).
    Under § 41, a taxpayer may claim a twenty-percent tax credit for the amount
    of “qualified research expenses” paid or incurred in the performance of “qualified
    research” that exceed a statutorily defined base amount. Qualified research
    expenses mean and refer to in-house and contract research expenses paid or
    4
    Pub. L. No. 97-34, § 221(a), 95 Stat. 241 (originally codified at 26 U.S.C. § 44F). The
    research tax credit was redesignated as § 30 by the Deficit Reduction Act of 1984, Pub. L. 98-
    369, §§ 471(c), 474(i)(1), 98 Stat. 826, 831, 912. The current version of the research tax credit is
    found at § 41. See Tax Reform Act of 1986, Pub. L. 99-514, § 231, 100 Stat. 2173–80, 2856
    (amending research tax credit and renumbering section as § 41).
    8
    Case: 14-11107   Date Filed: 01/29/2015     Page: 9 of 29
    incurred by the taxpayer during the taxable year. See § 41(b)(1). Research is
    qualified if: (a) it is an expenditure that may be treated as an expense under § 174; 5
    (b) it is undertaken to discover technological information “intended to be useful in
    the development of a new or improved business component of the taxpayer”; and
    (c) it includes activities that constitute elements of a process of experimentation for
    a statutorily defined purpose. See 
    id. § 41(d)(1).
    There are seven categories of research expressly excluded from the
    definition of “qualified research.” See 
    id. § 41(d)(4)(A)–(H).
    For purposes of this
    appeal, we are concerned only with the seventh category of exclusion—the funded
    research exclusion—which excludes “[a]ny research to the extent funded by any
    grant, contract, or otherwise by another person (or governmental entity).” 
    Id. § 41(d)(4)(H).
    The Code does not define “funded” as the term is used in § 41;
    however, the implementing regulations do set forth criteria as to what research
    qualifies as “funded” and who, if anyone, is eligible to claim the research tax credit
    for amounts paid or incurred pursuant to a contract for research (i.e., the researcher
    or the client).
    5
    Section 174 provides the standard by which “[a] taxpayer may treat research or
    experimental expenditures” as expenses. Whether the amounts incurred by Geosyntec under the
    Cherry Island and WM Contracts qualify as “expenses” is not at issue.
    9
    Case: 14-11107        Date Filed: 01/29/2015       Page: 10 of 29
    “To determine the extent to which research is funded,” we are directed to
    Treasury Regulation § 1.41-4A(d), 6 which provides, in relevant part:
    Research does not constitute qualified research to the extent it is
    funded by any grant, contract, or otherwise by another person
    (including any governmental entity). All agreements (not only
    research contracts) entered into between the taxpayer performing the
    research and other persons shall be considered in determining the
    extent to which the research is funded. Amounts payable under any
    agreement that are contingent on the success of the research and thus
    considered to be paid for the product or result of the research (see §
    1.41-2(e)(2)) are not treated as funding.
    26 C.F.R. § 1.41-4A(d) (emphasis added). 7 Referring to “the taxpayer performing
    the research,” § 1.41-4A(d) addresses eligibility for § 41’s research tax credit from
    the researcher’s perspective. Placing the emphasis on agreements between the
    researcher and its client, this regulation provides that research is not considered
    funded where an agreement makes payment to the researcher “contingent on the
    success of [its] research.” See 
    id. 6 See
    26 C.F.R. § 1.41-4(c)(9) (“Qualified research does not include any research to the
    extent funded by any grant, contract, or otherwise by another person (or governmental entity). To
    determine the extent to which research is so funded, § 1.41–4A(d) applies.”).
    7
    Section 1.41-4A(d) contemplates a second scenario in which research is funded; that is,
    where the researcher agrees to perform research for another person or entity without retaining
    “substantial rights” in the research. See § 1.41-4A(d)(2)–(3). By stipulation, the parties deferred
    the issue of whether Geosyntec retained substantial rights in its research at least in part because
    Geosyntec’s retained rights varied among its contracts and the issue did not lend itself to
    summary judgment. The parties further stipulated that, if the research was “funded,” as the term
    is defined at § 1.41-4A(d)(1), judgment would be entered in favor of the United States regardless
    of whether Geosyntec retained substantial rights in its research. As such, the district court did
    not address the matter in deciding on the cross-motions, and it is not at issue on appeal.
    10
    Case: 14-11107       Date Filed: 01/29/2015      Page: 11 of 29
    Treasury Regulation § 1.41-2(e), in turn, governs the client’s ability to claim
    funds expended on qualified research as credit-eligible research expenses under §
    41. To be an expense paid or incurred by the client, the research must be
    performed on behalf of the client and the client must “bear the expense [of the
    research] even if the research is not successful.” 
    Id. § 1.41-2(e)(2)(iii).
    The reason
    is clear: “If an expense is paid or incurred pursuant to an agreement under which
    payment is contingent on the success of the research, then the expense is
    considered paid for the product or result rather than the performance of the
    research,” and the tax credit is meant to incentivize research not production. Id.;
    see H.R. Rep. No. 100-1104, vol. 2, at 78. Therefore, the client cannot claim the
    payment as a credit-eligible contract research expense. 8 See § 1.41-2(e).
    Together, the regulations present “mirror image rules” for determining who
    is entitled to claim the research tax credit under § 41—the researcher or the
    researcher’s client. 
    Fairchild, 71 F.3d at 870
    (internal quotation marks omitted).
    The regulations allocate the research tax credit to the entity or person that bears
    “the financial risk of failure of the research to produce the desired product or
    result.” 
    Id. As such,
    the client “may claim the credit only if the agreement
    requires the [client] to pay for the research even if it is unsuccessful.” Id.; see §
    1.41-2(e)(2). If, on the other hand, the client “need not pay unless the research is
    8
    Under § 1.41-2(e), where only a portion of a payment is contingent on success, a client
    may claim the research tax credit as to those amounts that are not contingent on success.
    11
    Case: 14-11107      Date Filed: 01/29/2015    Page: 12 of 29
    successful,” the client is paying for a product or result rather than performance of
    the research, and the researcher is eligible to claim the research tax credit because
    the research is not funded. 
    Fairchild, 71 F.3d at 870
    ; see § 1.41-4A(d).
    Therefore, under § 41 and its implementing regulations, our inquiry turns on
    whether Geosyntec’s right to payment under its separate contracts with DSWA and
    with WM was “contingent on the success of the research” contemplated by those
    contracts. See § 1.41-4A(d); see also 
    Fairchild, 71 F.3d at 870
    , 872.
    B.
    Given the contract-centric nature of our review, we look next to the terms of
    the two contracts at issue, examining each in turn. See 
    Fairchild, 71 F.3d at 870
    (citing § 1.41-2(e)(2)) (“[T]he contractual arrangement is the factor that determines
    who is entitled to the tax benefit . . . .”); § 1.41-4A(d) (requiring consideration of
    all agreements between taxpayer performing research and other persons).
    1.     The Cherry Island Contract
    In 2001, Geosyntec contracted with DSWA to design a method for
    expanding the Cherry Island Landfill in Wilmington, Delaware. The goal was to
    increase the capacity of the landfill within its existing footprint. The landfill sat on
    a soft foundation, which limited its capacity for vertical expansion, but a
    previously-commissioned composite stability analysis of the landfill demonstrated
    12
    Case: 14-11107       Date Filed: 01/29/2015   Page: 13 of 29
    that expansion was possible. Geosyntec ultimately designed a berm wall and
    drainage system that allowed for the vertical expansion sought by DSWA.
    The Cherry Island Contract was composed of an engineering services
    agreement and five exhibits, including a detailed scope of work, a project schedule
    with a list of meetings and deliverables, a project budget, a statement of the
    manner and times of payment, and a hold-harmless agreement. Geosyntec’s work
    was separated into seven general tasks: (1) site studies; (2) design work, including
    site design; (3) general services, including permit applications and construction
    drawings; (4) preparation of an operation and maintenance manual; (5)
    construction-related services, including on-site supervision and quality assurance
    monitoring; (6) post-construction services, including as-built drawings and a
    project completion report; and (7) additional analyses, modeling, and testing. Each
    task included several subtasks.
    DSWA agreed to pay Geosyntec “on a cost reimbursement basis . . . in an
    amount not to exceed $9,991,578.” Each subtask was separately priced and
    payment to Geosyntec for each subtask was not to exceed the amount specified
    therefor. However, additional compensation was available to Geosyntec in stated
    circumstances. For example, where statutory or administrative requirements
    necessitated additional work by Geosyntec, it was entitled to “an equitable
    adjustment of its compensation.” Similarly, if the state’s environmental authorities
    13
    Case: 14-11107     Date Filed: 01/29/2015    Page: 14 of 29
    imposed “unreasonable demands” related to the issuance of any permit, which
    demands required Geosyntec to perform work that would not otherwise be
    required, Geosyntec was entitled to “extra compensation” for such work in an
    amount to be determined by the parties. Geosyntec was entitled to additional
    compensation where mandatory public hearings and meetings on the project
    resulted in costs above the applicable subtask total, and it also reserved the right to
    change the hourly rate for work performed during the construction and final phases
    of the project (Tasks 5 and 7) subject to certain conditions.
    Geosyntec was required to submit to DSWA one “approvable invoice” per
    month for services rendered under the Cherry Island Contract; prior to submission,
    the invoices were to be verified by project managers for both Geosyntec and
    DSWA. DSWA was obligated to pay “only those sums invoiced for Work that [it]
    approved for payment.” Where DSWA disputed any sums shown on the invoice, it
    could withhold payment of the disputed amount. Within three days of completion
    of all services required under the Cherry Island Contract, Geosyntec had to submit
    a notice of completion to DSWA, which, in turn, had thirty days to provide to
    Geosyntec a list of any incomplete services.
    All services to be provided by Geosyntec under the Cherry Island Contract
    were to be performed “in accordance with the standard of care applicable to such
    services on the type of Project” contemplated by the contract. Elsewhere in the
    14
    Case: 14-11107      Date Filed: 01/29/2015       Page: 15 of 29
    contract, Geosyntec warranted that it would perform in accordance with the
    standards applicable to similar engineering professionals performing services of a
    similar nature. Omissions and ambiguities in Geosyntec’s plans, specifications,
    and reports were to be corrected by Geosyntec at no additional cost to DSWA;
    Geosyntec was also permitted to remedy any errors or omissions in its work
    through “reperformance” of the work at its own expense in a timely fashion.
    The Cherry Island Contract affirmatively required that Geosyntec’s work
    comply with all current and future federal, state, and local laws and regulations as
    well as with DSWA’s existing permits for the landfill. Geosyntec was obligated to
    complete certain of its work to the satisfaction of Delaware’s Department of
    Natural Resources and Environmental Control (DNREC) 9 and to perform
    “whatever work” was required by DNREC’s “Regulations Governing Solid
    Waste.” Specified subtasks also required Geosyntec to provide its work to DSWA
    and/or DNREC for their review and for discussion and comment where necessary.
    DSWA could terminate the contract for default or for its own convenience.
    9
    Under the Cherry Island Contract, Geosyntec was tasked with obtaining the required
    construction and operation permits from DNREC and the City of Wilmington, and the parties
    acknowledged that “to obtain the permits [Geosyntec] must satisfy the [permit] requirements to
    the satisfaction of DNREC or the City of Wilmington.” In addition, the Cherry Island Contact
    required the “DSWA [to] maintain close contact with DNREC and [to] update DNREC on the
    design status to facilitate permit review and approval.”
    15
    Case: 14-11107      Date Filed: 01/29/2015    Page: 16 of 29
    2.     The WM Contract
    In 1997, WM and Geosyntec entered into a master services agreement
    whereby Geosyntec agreed to provide engineering consulting services on future
    projects as described in project-specific addenda. Each addendum would include a
    standard WM addendum form and a statement of work by Geosyntec. Pursuant to
    one such addendum, executed by the parties in 2003, Geosyntec was hired to
    evaluate a system for remediating contaminated groundwater beneath a warehouse
    site previously used to manufacture and store weapons and radioactive material.
    Pursuant to the WM Contract,10 Geosyntec was to (1) perform laboratory
    bench tests to evaluate the feasibility and performance of enhanced in situ
    bioremediation (EISB) for groundwater cleanup and (2) prepare a report describing
    its methodology, tabulating the results, interpreting the data collected, and
    discussing site conditions and potential pilot-test designs. The addendum capped
    the contract price at $18,781 in accordance with Geosyntec’s estimated budget for
    the project. A statement of work, with Geosyntec’s objectives, technical approach,
    and scope of work, as well as an estimated budget, including projected labor and
    material costs, were attached to the addendum. All necessary work and services
    were to be completed by October 31, 2003.
    10
    The WM Contract is comprised of both the master services agreement and the 2003
    addendum.
    16
    Case: 14-11107    Date Filed: 01/29/2015   Page: 17 of 29
    The WM Contract required payment to Geosyntec “upon proper
    performance of each task” at fixed unit prices as set forth in Geosyntec’s estimated
    budget. Geosyntec was required to submit monthly progress invoices, and WM
    had forty-five days within which to pay all undisputed amounts therein. WM
    could dispute any item in invoices submitted by Geosyntec for “any reason,
    including the lack of supporting documentation or suspected defective or
    negligently performed work.” In such an instance, WM was required to promptly
    notify Geosyntec of the dispute and to request clarification or remedial action as to
    the item; where disputes were settled in Geosyntec’s favor, WM was to include
    payment for the settled amount in a subsequent payment to Geosyntec.
    The contract gave WM the right to change, make additions to, or omit work
    required under the WM Contract by sending “a written change directive” to
    Geosyntec. Geosyntec was to perform or omit such changed work as directed;
    however, if any change necessitated an increase in the capped contract price,
    Geosyntec was to promptly notify WM of the increase. Geosyntec was not to
    proceed with the changed work unless and until the parties executed an addendum
    adjusting the contract price. The WM Contract also gave WM the right to
    terminate the contract for default or on five days’ notice for any reason.
    Geosyntec, in turn, could terminate the WM Contract on ninety days’ notice for
    any reason.
    17
    Case: 14-11107      Date Filed: 01/29/2015    Page: 18 of 29
    Geosyntec was responsible for performing its work “in accordance with the
    degree of professional care, prudence and skill of a nationally recognized, properly
    licensed, professional engineering firm in performing comparable services.” The
    WM Contract further required that Geosyntec’s work be free from negligence.
    WM had a right to review and approve, reject, or approve with comment any work
    provided by Geosyntec, and any remedial work deemed necessary by WM was to
    be performed in part or entirely by either Geosyntec or WM. Geosyntec was
    accountable for costs, damages, and expenses resulting from errors, defects, or
    negligent acts or omissions in its work.
    C.
    Applying the above-stated legal principles to the two contracts at issue, the
    matter to be determined is whether payment to Geosyntec under the Cherry Island
    Contract or under the WM Contract, or both, was contingent on Geosyntec’s
    performance. See 
    Fairchild, 71 F.3d at 872
    . If Geosyntec was entitled to payment
    under both or either contract regardless of the success of its research, it is not
    eligible to claim the research tax credit; conversely, if payment to Geosyntec under
    both or either contract was contingent on Geosyntec’s successful research or
    development of a product or process, Geosyntec is eligible to claim the research
    tax credit. See §§ 1.41-2(e), 1.41-4A(d). The parties’ benchmark is the fixed-price
    incentive contract discussed in Fairchild.
    18
    Case: 14-11107     Date Filed: 01/29/2015    Page: 19 of 29
    In Fairchild, an airplane manufacturer, Fairchild, contracted with the United
    States Air Force to design and produce the T-46A aircraft. See 
    Fairchild, 71 F.3d at 870
    . The contract included a full-scale development (FSD) phase and a
    production phase, but the case focused solely on the FSD phase. 
    Id. Fairchild’s work
    in the FSD phase was subdivided into eleven separately-priced contract line
    items, and each line item required “research, development, and testing, to meet
    complex contract specifications.” 
    Id. at 871,
    873. The Fairchild contract
    contained over 1,000 pages of technical specifications requiring Fairchild to meet
    specific design, construction, quality, and performance standards. 
    Id. at 870.
    Under the terms of the contract, the Air Force was obligated to pay Fairchild
    only if Fairchild produced results that met the contract’s specifications; equally,
    Fairchild was entitled to payment only for work delivered to and accepted by the
    Air Force. See 
    id. at 871.
    “Quality assurance procedures” required the Air Force
    to evaluate Fairchild’s work item-by-item. See 
    id. If Fairchild’s
    work was
    delivered and deemed unacceptable, the Air Force could reject the work, make
    Fairchild correct the work at its own expense, or accept the work and pay a
    reduced price. 
    Id. Examining the
    contract, the Federal Circuit concluded that
    “[w]hatever risk Fairchild was bearing, the Air Force bore none of it” because the
    Air Force only had to pay when the work, “line item by line item, succeeded and
    was accepted.” 
    Id. at 873.
    Since Fairchild bore the financial risk of failed
    19
    Case: 14-11107        Date Filed: 01/29/2015         Page: 20 of 29
    research, the contract was not funded, making Fairchild eligible for the research
    tax credit. 11 See 
    id. at 874.
    Here, Geosyntec avers that the Cherry Island Contract and the WM Contract
    fall squarely within the gambit of Fairchild. Geosyntec contends that it faced
    substantial financial risk under the capped contracts because it would only be paid
    for expenses incurred, eliminating an opportunity to make a profit on the research
    should it come in under budget, and it bore the risk that its expenses would exceed
    the ceiling price for each contract. Geosyntec further argues that the totality of the
    provisions contained in both the Cherry Island Contract and the WM Contract
    allocated to Geosyntec the financial risk of the failure of its research to produce the
    desired product or result—even if success was not expressly mandated by the
    terms of either contract. See 
    id. at 870.
    Despite Geosyntec’s arguments to the
    contrary, we find that both the Cherry Island Contract and the WM Contract were
    “funded” as that term is used in § 41 and Treasury Regulation § 1.41-4A(d).
    First, Geosyntec’s general economic risk arguments are misplaced.
    Geosyntec argues that it faced substantial financial risk under the capped contracts
    because its compensation was fixed. More specifically, Geosyntec avers that it ran
    the risk of not receiving the full ceiling price or, conversely, of exceeding its own
    11
    In Fairchild, the parties agreed that Fairchild retained substantial rights in its research.
    As such, the Federal Circuit was only concerned with “whether payment [to Fairchild] was
    contingent on success.” 
    Fairchild, 71 F.3d at 872
    .
    20
    Case: 14-11107     Date Filed: 01/29/2015    Page: 21 of 29
    budget. However, these cost-of-performance arguments focus on the amount
    Geosyntec would be paid and/or the likelihood that its contracts would be
    profitable, which is of no matter here. Cost-of-performance is not the financial risk
    with which we are concerned because “the only issue is whether payment was
    contingent on the success of the research”—that is, the financial risk of failure.
    See 
    id. at 872.
    Moreover, additional compensation was available in certain circumstances.
    Geosyntec could submit a claim for additional compensation for necessary work
    that fell outside the scope of the services contemplated by the Cherry Island
    Contract. Geosyntec was also entitled to extra compensation where Delaware’s
    environmental authorities imposed “unreasonable demands” that required
    additional work or services, and it reserved the right to change the hourly rate for
    work performed during two separate phases (subject to stated conditions). In the
    WM Contract, if WM changed the work required under the contract, the parties
    would agree on a price increase and/or time extension necessary for Geosyntec to
    complete the additional work. In short, contrary to Geosyntec’s arguments, the
    capped contracts’ not-to-exceed ceiling prices were not immovable.
    Second, neither the Cherry Island Contract nor the WM Contract expressly
    made payment to Geosyntec contingent on the success of Geosyntec’s research.
    Fairchild, for example, had to succeed at each step of the FSD phase in order to be
    21
    Case: 14-11107     Date Filed: 01/29/2015   Page: 22 of 29
    paid; those were the terms of Fairchild’s contract with the Air Force. 
    See 71 F.3d at 873
    . In fact, the Fairchild contract provided that Fairchild was without any right
    to retain progress payments made to Fairchild by the Air Force during the course
    of Fairchild’s performance if the contract line items to which the payments applied
    were not delivered and accepted. See 
    id. at 871.
    Here, DSWA and WM were
    contractually obligated to pay for Geosyntec’s research and work product even if it
    did not produce the desired outcome.
    Looking first at the WM Contract, it required Geosyntec to perform
    laboratory bench tests and to provide WM with a brief study report. Data from the
    study would be used to determine the cost-effectiveness and feasibility of
    implementing EISB, and, if appropriate, to design a field-scale implementation.
    However, if Geosyntec’s laboratory bench tests were performed in accordance with
    all applicable professional standards, but the tests established that EISB was not a
    feasible process for accelerating groundwater cleanup, WM remained contractually
    obligated to pay Geosyntec for the labor and material used in conducting the
    treatability test and preparing the report thereon. WM contracted for and agreed to
    pay Geosyntec for its research, not for a result.
    As to the Cherry Island Contract, Geosyntec was asked to design an
    expansion of the Cherry Island Landfill and provide support services during
    construction. Like the Fairchild contract, each of the tasks required research,
    22
    Case: 14-11107       Date Filed: 01/29/2015       Page: 23 of 29
    development, and testing. However, unlike the Fairchild contract, the project did
    not require installation and integration of specific elements; each task was not
    subject to complex contract specifications; and Geosyntec’s work was not subject
    to inspection and testing before acceptance. Cf. 
    id. at 871,
    873. Rather, the design
    was left almost entirely to Geosyntec’s professional expertise, informed by
    Geosyntec’s own research and subject to general (and, at times, passive)
    requirements. 12 Further, while DSWA had the right to review and comment on
    certain of Geosyntec’s design work, there was no method for its rejection.
    Third, the totality of the provisions in the Cherry Island Contract and in the
    WM Contract did not place the risk of failed research on Geosyntec. See 
    id. at 870
    (stating that tax credit is allocated to person that bears financial risk of failure of
    the research). Given that neither the Cherry Island Contract nor the WM Contract
    expressly mandates a successful outcome (either in total or in each phase of the
    particular projects), Geosyntec interprets the contracts’ provisions as collectively
    placing the risk of failure of the research on Geosyntec. To this end, Geosyntec
    12
    In discussing the performance requirements to which it was held, Geosyntec repeatedly
    refers to language in the Cherry Island Contract requiring that Geosyntec’s work be completed
    “to the satisfaction of DNREC.” For one thing, DNREC was not a party to the Cherry Island
    Contract. See 
    Fairchild, 71 F.3d at 870
    (stating the contractual arrangement between the
    researcher and the client determines who is entitled to the tax credit). Further, part of
    Geosyntec’s contractual obligation was to obtain the necessary permits from DNREC and the
    City of Wilmington. To this end, the Cherry Island Contract acknowledges “that DNREC and
    the City of Wilmington interpret their permit requirements, and that to obtain the permits
    [Geosyntec] must satisfy the requirements to the satisfaction of DNREC or the City of
    Wilmington.” The language to which Geosyntec refers does not evidence a quality assurance
    procedure akin to that in Fairchild; rather, it denotes which tasks had to be completed subject to
    DNREC’s or the City of Wilmington’s requirements in order to obtain the necessary permits.
    23
    Case: 14-11107       Date Filed: 01/29/2015      Page: 24 of 29
    contends it was subject to certain performance requirements and quality assurance
    procedures that allocated “unsatisfactory-performance risk” to Geosyntec.
    Geosyntec also relies heavily on the invoice procedures contained in each contract
    as evidence of the “strong client-rejection rights” to which it was subject.
    Geosyntec’s arguments are not persuasive.
    In the first place, Geosyntec’s argument that it was subject to performance
    requirements that allocated the risk of failure to Geosyntec is unavailing. Both the
    Cherry Island Contract and the WM Contract required Geosyntec to perform in
    accordance with the standard of care applicable to like professionals performing
    comparable services on the type of project contemplated by the each of the
    contracts; Geosyntec’s work was to be free from negligence, error, and defects.
    We are not concerned, however, with the general standard of care applicable to
    Geosyntec or Geosyntec’s uniform assurances that its performance would be free
    from negligence; those provisions do not mandate success. Indeed, neither
    contract equates “proper performance” with “successful performance.” 13
    Further, under neither contract was Geosyntec subject to quality assurance
    procedures akin to those in Fairchild. See, e.g., 
    id. at 873
    (noting contract made all
    work subject to inspection and testing prior to acceptance and provided that
    13
    See Key v. Allstate Ins. Co., 
    90 F.3d 1546
    , 1549 (11th Cir. 1996) (“[W]here the
    language is plain a court should not create confusion by adding hidden meanings, terms,
    conditions, or unexpressed intentions.” (citations omitted)).
    24
    Case: 14-11107       Date Filed: 01/29/2015      Page: 25 of 29
    payment would be made only after acceptance). Contrary to the Fairchild
    contract, the WM Contract did not have an extensive list of deliverables; it
    required only that all services be completed by a specified date. While the WM
    Contract granted to WM a general right to inspect any work provided by
    Geosyntec thereunder, WM’s approval and acceptance was not mandated. Cf. 
    id. at 871,
    873. The provision is passive, and WM’s “right of approval” is not
    informed by and does not inform Geosyntec’s right to payment. 14
    Under the Cherry Island Contract, Geosyntec was required to submit certain
    of its work to DSWA for review, comment, and discussion. In the design phase,
    design plans and specifications were submitted to DSWA for review at 30%, 65%,
    85%, 95%, and 100% completion; at 30% completion, the Cherry Island Contract
    required DSWA’s review and approval of the site design. Still, even in this
    instance, the WM Contract provided that Geosyntec need only incorporate
    DSWA’s “comments” to the extent deemed “desirable” by Geosyntec. The Cherry
    Island Contract provided no barometer by which Geosyntec’s performance could
    be considered “successful,” and there existed no mechanism for evaluation and
    acceptance or rejection of the delivered design. Cf. 
    id. at 871.
    Finally, Geosyntec’s argument that the two capped contracts provide for
    “strong client rejection rights” such that it was only entitled to payment for work
    14
    See Feaz v. Wells Fargo Bank, N.A., 
    745 F.3d 1098
    , 1104 (11th Cir. 2014) (noting the
    terms of a contract must be interpreted in the context of the entire contract).
    25
    Case: 14-11107    Date Filed: 01/29/2015    Page: 26 of 29
    delivered to and accepted by DSWA or by WM is similarly unpersuasive.
    According to Geosyntec, because DSWA and WM could dispute sums included on
    invoices submitted by Geosyntec, it had “no legal right” to payment unless it could
    demonstrate its work was satisfactory. Geosyntec likens its clients’ right to dispute
    invoiced sums to the Air Force’s right to inspect and reject Fairchild’s work
    product in Fairchild. A review of the invoice procedures in the Cherry Island and
    WM Contracts dampens Geosyntec’s comparison.
    In Fairchild, the contract between Fairchild and the Air Force included
    “quality assurance procedures” whereby the Air Force would inspect, test, and
    approve or reject Fairchild’s work product. See 
    id. at 871,
    873. Unless and until
    Fairchild “fully succeeded in each phase of the project,” it had no right to payment,
    and, if the Air Force deemed the work unacceptable, Fairchild ran the risk of
    nonpayment. 
    Id. Monthly invoices
    submitted by Geosyntec to DSWA and to
    WM, on the other hand, were payable upon submission unless an item or sum
    shown due on the invoice was in dispute.
    Under the WM Contract, for example, Geosyntec was required to submit
    monthly progress invoices for all work performed during the previous calendar
    month. The master agreement provided that payment was due upon “proper
    performance of each task.” WM could dispute items in submitted invoices for any
    reason, including Geosyntec’s failure to accurately account for its work or where
    26
    Case: 14-11107     Date Filed: 01/29/2015   Page: 27 of 29
    WM suspected the work was “defective or negligently performed.” However, the
    item was only temporarily deleted and, once the dispute was settled, WM was
    obligated to pay the invoiced amount.
    Similarly, the Cherry Island Contract required Geosyntec to submit monthly,
    “approvable” invoices for services rendered. Each invoice was to be verified by
    representatives of both DSWA and Geosyntec, and DSWA was required to pay
    Geosyntec “only those sums invoiced for Work that [was] approved for payment
    by DSWA.” All of the work contemplated under the Cherry Island Contract was
    set forth in the scope of work attached thereto, and the pay rate for each “item of
    work” was pre-determined by the project budget. The Cherry Island Contract did
    not provide for DSWA’s review and approval of Geosyntec’s work product prior
    to payment, but it did require Geosyntec to obtain DSWA’s written approval
    before performing any work outside the contemplated scope of services. As such,
    unless the work performed was set forth in the scope of work or DSWA gave
    written permission for performance of the work, DSWA was not required to pay
    Geosyntec therefor and could dispute the sum.
    Under neither contract does the right to dispute sums shown due on an
    invoice equate to a requirement that Geosyntec’s work product be evaluated and
    accepted prior to payment. While the Cherry Island Contract included a two-page
    list of deliverables, Geosyntec was not paid on delivery and acceptance of those
    27
    Case: 14-11107     Date Filed: 01/29/2015    Page: 28 of 29
    items and was not required to deliver results that met contract specifications prior
    to payment. Rather, Geosyntec was paid upon submission of an approvable
    invoice. Similarly, under the WM Contract, Geosyntec was not entitled to
    payment only if the study report was delivered and accepted. Instead, Geosyntec
    was paid for all work performed during the previous calendar month. Any risk of
    nonpayment borne by Geosyntec was unrelated to the outcome of its research.
    In sum, Geosyntec was entitled to payment under both the Cherry Island
    Contract and the WM Contract regardless of success. See 26 C.F.R. §§ 1.41-2(e),
    1.41-4A(d). Both DSWA and WM contracted with Geosyntec to reimburse
    Geosyntec for labor and costs for pre-defined tasks at pre-defined rates. Neither
    the Cherry Island Contract nor the WM Contract provided that DSWA or WM was
    obligated to reimburse Geosyntec only if Geosyntec produced results that met the
    contracts’ specifications. Cf. 
    Fairchild, 71 F.3d at 871
    . Similarly, Geosyntec was
    not “entitled to payment only for work product delivered [to] and accepted” by its
    clients. 
    Id. Because payment
    to Geosyntec was not contingent on the success of
    its research, Geosyntec did not bear the financial risk of its own failure, and the
    two capped contracts were funded by Geosyntec’s clients. See 
    id. at 872;
    see also
    § 1.41-4A(d).
    28
    Case: 14-11107      Date Filed: 01/29/2015     Page: 29 of 29
    IV.
    As Geosyntec acknowledged at oral argument, the success or failure of its
    appeal lay in the terms of the two capped contracts. Upon a careful review of both
    contracts, we agree with the district court that both the Cherry Island Contract and
    the WM Contract are funded, as that term is used in § 41 and the implementing
    regulations, and Geosyntec is not eligible for research tax credits for research
    expenses incurred under those contracts.15 Therefore, the district court’s grant of
    summary judgment is AFFIRMED.
    15
    See Burton v. Tampa Hous. Auth., 
    271 F.3d 1274
    , 1277 (11th Cir. 2001) (“A grant of
    summary judgment may be upheld on any basis supported by the record.”).
    29