LaFarge Building Materials, Inc. v. Federal Insurance Company , 510 F. App'x 884 ( 2013 )


Menu:
  •            Case: 12-14396    Date Filed: 02/27/2013   Page: 1 of 10
    [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________
    No. 12-14396
    Non-Argument Calendar
    ________________________
    D.C. Docket No. 1:09-cv-03249-RWS
    LAFARGE BUILDING MATERIALS, INC.,
    Plaintiff-Appellee,
    versus
    FEDERAL INSURANCE COMPANY,
    CLEVELAND CONSTRUCTION, INC.,
    Defendants -Third Party Plaintiffs-
    Appellants,
    THE PEOPLES BANK, et. al.,
    Third Party Defendants.
    Case: 12-14396     Date Filed: 02/27/2013   Page: 2 of 10
    ________________________
    Appeal from the United States District Court
    for the Northern District of Georgia
    ________________________
    (February 27, 2013)
    Before TJOFLAT, HULL and PRYOR, Circuit Judges.
    PER CURIAM:
    Defendants Cleveland Construction, Inc. (“CCI”), a general contractor, and
    Federal Insurance Company (“Federal Insurance”), its surety, appeal the district
    court’s final judgment of $87,855.64 in favor of Plaintiff Lafarge Building
    Materials, Inc. (“Lafarge”), a supplier of rock and concrete. After review, we
    affirm.
    Defendant CCI was the general contractor on two construction projects, a
    Wal-Mart store and the Chamblee Village Retail Shops (“the property”). Plaintiff
    Lafarge furnished materials, such as rock and concrete mix, to Michael B. Cline
    d/b/a/ Clinecrete (“Clinecrete”), a concrete subcontractor. When Clinecrete failed
    and refused to pay, Plaintiff Lafarge filed two materialman’s liens against the
    property. Defendant Federal Insurance, as surety, issued two bonds which released
    and bonded off Lefarge’s liens. Specifically, Defendant Federal Insurance’s bonds
    provided that (1) Defendants CCI and Federal Insurance “are held firmly bound
    unto Lefarge Building Materials, Inc., herein after known as Claimant in the sum”
    2
    Case: 12-14396     Date Filed: 02/27/2013    Page: 3 of 10
    of $134,999.02 and $51,439.02; (2) that CCI entered into a contract with
    Clinecrete and Clinecrete entered into a contract with Claimant Lafarge; (3) that
    “Claimant has filed a mechanics’ lien in the amount of $67,499.51” and another
    mechanic’s lien for $25,719.51 against certain property; (4) that the correctness of
    these claims is disputed; (5) the liens are released in accordance with Georgia law;
    and (6) that if CCI pays or causes to be paid the sums which the Claimant may
    recover on these claims, together with the cost of suit in a timely filed action, then
    this obligation to pay “shall be voided; otherwise it shall remain in full force and
    effect.” In other words, Claimant Lefarge’s liens were released on the express
    condition that CCI and Federal Insurance would pay the sums Lefarge recovered in
    a timely filed lawsuit on these claims against Clinecrete if those sums were not
    paid by Clinecrete.
    I. STATE COURT LAWSUIT
    In March 2007, before the present federal lawsuit commenced, Plaintiff
    Lafarge, as the materialman, timely filed a lawsuit against Clinecrete, the
    subcontractor, in state court to recover the unpaid amounts and perfect its claims of
    lien. After Clinecrete failed to respond to Plaintiffs Lafarge’s motion for summary
    judgment, the state court entered final judgment against Clinecrete on March 23,
    2009. Among other things, the state court’s judgment awarded Plaintiff Lafarge
    the principal sums of $67,189.51 and $25,719.51 (totaling $92,909.20) “for
    3
    Case: 12-14396        Date Filed: 02/27/2013        Page: 4 of 10
    building materials purchased on open account by Defendant [Clinecrete] from
    Plaintiff [Lafarge] and incorporated into improvements constructed on the property
    commonly known as Chamblee Village Shops/Chamblee Tucker Road, Dekalb
    County, Georgia.”
    After the final judgment against Clinecrete (which included the sums
    totaling $92,909.02), Plaintiff Lafarge made claims for payment of those sums
    under the bonds, but Defendants refused payment.
    II. FEDERAL COURT LAWSUIT
    Plaintiff Lafarge then filed this federal civil action against Defendants CCI
    and Federal Insurance. 1 Plaintiff Lafarge seeks to recover under the bonds for the
    unpaid sums totaling $92,909.02 awarded by the state court’s final judgment, plus
    attorney’s fees and costs.
    On June 29, 2012, the district court entered an order ruling on Plaintiff
    Lafarge’s motion for partial summary judgment. The district court first concluded,
    as a matter of law, that the state court’s final judgment of $92,909.02 against
    subcontractor Clinecrete “conclusively establishes the value of materials that
    Plaintiff [Lafarge] delivered to the Property and that the materials were
    incorporated into the improvements thereon.”
    1
    Plaintiff Lafarge originally filed this action in Fulton County Superior Court, but the
    Defendants CCI and Federal Insurance removed the action to federal court on the basis of
    diversity of citizenship.
    4
    Case: 12-14396       Date Filed: 02/27/2013      Page: 5 of 10
    The district court, however, found there was a genuine issue of material fact
    as to whether the full amount of $92,909.02 should be offset by two waivers of the
    rights to lien executed by Plaintiff Lafarge. After mediation, the parties reached an
    agreement as to the offset amount, and Plaintiff Lafarge dismissed its remaining
    claim (for bad faith). The district court then entered an order incorporating its June
    29, 2012 summary judgment order and entering final judgment for Plaintiff
    Lafarge in the amount of $87,855.64 after the offset. This appeal challenging the
    district court’s June 29, 2012 summary judgment order followed. 2
    III. DISCUSSION
    A.     Materialman’s Liens
    Under Georgia law, materialmen who furnish material to a subcontractor
    have a “special lien” on the property “for which they furnish labor, services, or
    materials.” O.C.G.A. § 44-14-361(a)(2). When a property owner obtains a release
    bond for a materialman’s lien, “the bond stands in the place of the real property as
    security for the lien claimant.” Few v. Capitol Materials, Inc., 
    274 Ga. 784
    , 786,
    
    559 S.E.2d 429
    , 430 (2002). In these circumstances, the materialman “must still
    comply with the statutory requirements for perfecting the lien,” except for the
    2
    The Defendants appeal the district court’s June 29, 2012 interlocutory order denying
    summary judgment, which “merged into the final judgment and is open to review on appeal from
    that judgment.” Aaro, Inc. v. Daewoo Int’l (America) Corp., 
    755 F.2d 1398
    , 1400 (11th Cir.
    1985). We review a district court’s summary judgment ruling de novo, drawing all inferences
    and construing the evidence in the light most favorable to the non-moving party. Craig v. Floyd
    County, Ga., 
    643 F.3d 1306
    , 1309 (11th Cir. 2011).
    5
    Case: 12-14396       Date Filed: 02/27/2013        Page: 6 of 10
    notice of suit requirement, and “the principal and the surety on the bond are
    entitled to raise any defense that would have been available as a defense to the lien
    foreclosure.” 
    Id.,
     
    559 S.E.2d at 430-31
    .3
    Additionally, the materialman “must first seek to recover monies owed from
    the contractor, the party with whom it has a contract, before seeking to recover
    from the property owner, with whom the supplier has no contractual relationship.”
    
    Id.
     “It is in [this] antecedent suit against the contractor that the adjudication is
    made as to items furnished and the amount due with respect to a particular
    contract.” Tri-State Culvert Mfg., Inc. v. Crum, 
    139 Ga. App. 448
    , 449, 
    228 S.E.2d 403
    , 405-06 (1976) (quotation marks omitted). More importantly, the
    judgment the materialman obtains against the contractor “is not conclusive against
    the (property owner), but it does establish prima facie that the (materialman) has a
    valid claim against the (contractor) for the amount of the judgment.” 
    Id. at 450
    ,
    
    228 S.E.2d at 406
    . Thus, if there is proof of a judgment against the contractor,
    “[t]he burden is upon the (owner) to introduce evidence sufficient to rebut the
    correctness of the judgment.” 
    Id.
     Moreover, “[t]his rule applies to litigated cases
    against the (contractor) and . . . to judgments rendered against him by default.” 
    Id.
    (quotation marks omitted).
    B.     Analysis of this Case
    3
    The parties do not dispute that Plaintiff Lafarge complied with the statutory lien
    requirements.
    6
    Case: 12-14396       Date Filed: 02/27/2013        Page: 7 of 10
    Here, Plaintiff Lafarge first obtained a state court judgment for $92,909.02
    against the party with whom it had a contract—subcontractor, Clinecrete. Plaintiff
    Lefarge then submitted that state court judgment to the district court. And, the
    district court properly applied the rebuttable presumption in Tri-State Culvert to
    conclude that Plaintiff Lafarge’s judgment was prima facie evidence that Plaintiff
    Lafarge furnished materials in the amount of $67,189.51 and $25,719.51 (totaling
    $92,909.02) that were “incorporated into improvements constructed on the
    property.” 4 Further, the Defendants CCI and Federal Insurance did not present any
    evidence to rebut the correctness of Plaintiff Lafarge’s state court judgment against
    Clinecrete.
    Contrary to the Defendants’ contention, Plaintiff Lafarge did not rely on the
    affidavit of Linda Bobo, Lafarge’s Lien and Legal Manager, to show it supplied
    over $92,000 in materials that were incorporated into the property. Further, as the
    district court explained, any alleged infirmities in Bobo’s testimony about the
    materials supplied or the amounts due are immaterial in light of the undisputed
    4
    In the district court, the Defendants agreed with Plaintiff Lafarge that Tri-State Culvert
    is “analogous to the facts of this case,” and that under Tri-State Culvert, “the judgment creates
    this prima facie case and then the burden is on us to rebut the presumption.” Accordingly, we do
    not address the Defendants’ argument, raised for the first time on appeal, that Tri-State Culvert’s
    rebuttable presumption does not apply. See Ramirez v. Sec’y, U.S. Dep’t of Transp., 
    686 F.3d 1239
    , 1249-50 (11th Cir. 2012) (“It is well-settled that we will generally refuse to consider
    arguments raised for the first time on appeal.”).
    7
    Case: 12-14396        Date Filed: 02/27/2013       Page: 8 of 10
    state court final judgment against Clinecrete. 5 Once Plaintiff Lafarge produced
    that state court judgment, the burden shifted to the Defendants to produce some
    evidence from which a jury could conclude that the judgment was incorrect, such
    as, for example, evidence that Lafarge’s materials were not in fact delivered to the
    construction site or were not actually incorporated into the property. Compare Tri-
    State Culvert, 
    139 Ga. App. at 450
    , 
    228 S.E.2d at 450
     (concluding that owner’s
    cross-examination of materialman’s general manager established that the
    underlying judgment against the subcontractor corporation was incorrect because
    the account was opened in the name of two individuals rather than the
    subcontractor corporation); see also Kelly v. Pierce Roofing Co., 
    220 Ga. App. 391
    , 393, 
    469 S.E.2d 469
    , 472 (1996) (concluding that, under Tri-State Culvert,
    materialman’s default judgment operated as an admission of the truth of the
    allegation that the materialman completed the work and therefore the materialman
    was entitled to summary judgment because the property owner failed “to come
    forward and point to specific evidence” to defeat summary judgment).
    5
    The Defendants argue that Bobo’s affidavit is insufficient as a matter of law because she
    had no personal knowledge of the amounts Clinecrete owed Lafarge or whether the materials
    associated with Clinecrete’s open account were delivered to or incorporated into the property.
    The Defendants contend that Plaintiff Lafarge needed to produce testimony from workers who
    loaded the materials, the driver who delivered them to the site, and Clinecrete’s agent who
    received them. As discussed above, under the rule in Tri-State Culvert, once Plaintiff Lafarge
    produced the state court judgment against Clinecrete, it was the Defendants’ burden to produce
    this sort of evidence. Moreover, given Bobo’s tacit admission that she had no personal
    knowledge of whether Lafarge’s materials actually were delivered to the construction site and
    incorporated into the property, the Defendants cannot use her deposition testimony to rebut the
    presumption that the state court judgment is correct.
    8
    Case: 12-14396        Date Filed: 02/27/2013      Page: 9 of 10
    Because the Defendants did not present the requisite type of evidence, the
    presumption of correctness remained unrebutted. Thus, as the district court
    concluded, Plaintiff Lafarge’s state court judgment “conclusively establishe[d] the
    value of materials that Plaintiff delivered to the Property and that the materials
    were incorporated into the improvements thereon.”
    The Defendants point to a joint check in the amount of $65,556.84 that
    Defendant CCI issued payable jointly to subcontractor Clinecrete and Plaintiff
    Lafarge. A CCI employee, David Sawicki, testified that after he sent the joint
    check to Lafarge, one of Lafarge’s employees told him that she had learned that
    “the check was turned back over to the subcontractors.” However, as the district
    court noted, the check is virtually illegible, and the Defendants do not dispute that
    Plaintiff Lafarge did not endorse or deposit the check. 6 Further, the Defendants
    did not present any evidence that Plaintiff Lafarge received any of the joint check’s
    proceeds. Under these circumstances here, the joint check and Sawicki’s
    testimony do not rebut the correctness of the state court judgment against
    Clinecrete or create a jury question as to the amount the Defendants owed to
    Plaintiff Lefarge under the plain language of the bonds. Thus, this evidence did
    6
    Indeed, the Defendants asserted in a third-party complaint against the FDIC that the joint
    check was deposited into Clinecrete’s bank account without Plaintiff Lafarge’s endorsement.
    The Defendants later dismissed this third-party complaint.
    9
    Case: 12-14396     Date Filed: 02/27/2013    Page: 10 of 10
    not create a genuine issue of material fact as to the amount Plaintiff Lafarge has
    already been paid pursuant to its claims.
    For all these reasons, we find no reversible error in the district court’s June
    29, 2012 summary judgment order and affirm the district court’s final judgment in
    favor of Plaintiff Lafarge in the amount of $87,855.64 and against the Defendants.
    AFFIRMED.
    10