Wadley Crushed Stone Company, LLC v. Positive Step, Inc. ( 2022 )


Menu:
  • USCA11 Case: 21-11002    Date Filed: 05/24/2022   Page: 1 of 17
    [PUBLISH]
    In the
    United States Court of Appeals
    For the Eleventh Circuit
    ____________________
    No. 21-11002
    ____________________
    WADLEY CRUSHED STONE COMPANY, LLC,
    an Alabama Limited Liability Company,
    Plaintiff-Counter Defendant-Appellant,
    versus
    POSITIVE STEP, INC.,
    a Georgia Corporation d.b.a.
    1st Quality Equipment Company,
    Defendant-Counter Claimant-Appellee,
    1ST QUALITY EQUIPMENT COMPANY, INC.,
    USCA11 Case: 21-11002       Date Filed: 05/24/2022    Page: 2 of 17
    2                      Opinion of the Court               21-11002
    Defendant-Counter Claimant,
    THOMAS W. CURLEY,
    Defendant.
    ____________________
    Appeal from the United States District Court
    for the Middle District of Alabama
    D.C. Docket No. 3:17-cv-00852-KFP
    ____________________
    Before NEWSOM, TJOFLAT, and HULL, Circuit Judges.
    TJOFLAT, Circuit Judge:
    This is a case about whether Wadley Crushed Stone Com-
    pany, LLC, (“Wadley”) has filed its breach of contract claim against
    1st Quality Equipment Company (“1st Quality”) within the appli-
    cable statute of limitations. And the applicable statute of limita-
    tions depends on whether the contract is for goods under the Uni-
    form Commercial Code (“UCC”) or for services under traditional
    contract law. Because we hold that the contract is for goods, and
    the applicable statute of limitations under the UCC has already run,
    we affirm the District Court’s ruling that Wadley’s claim was time-
    barred. We also affirm the District Court’s grant of summary
    USCA11 Case: 21-11002       Date Filed: 05/24/2022     Page: 3 of 17
    21-11002               Opinion of the Court                        3
    judgment and denial of reconsideration as to 1st Quality’s counter-
    claim for unpaid invoices.
    I.
    To sum up this case, it’s all fun and games until the granite
    plant turns out to be inefficient. Wadley is an Alabama corporation
    in the granite processing business. In 2009, Wadley wanted to build
    a granite plant in Alabama that, among other specifications, would
    process 500 tons of granite per hour. 1st Quality is a Georgia cor-
    poration that represents manufacturers in the sale of equipment
    used in the granite industry. 1st Quality sells equipment, provides
    customer support in connection with equipment sales, and supplies
    parts for some equipment from its warehouse. Based on prior busi-
    ness dealings between the executives of both companies, Wadley
    reached out to 1st Quality as it began the process of planning to
    build the granite plant.
    1st Quality worked with both Wadley and several third par-
    ties to figure out how big the equipment would have to be to sup-
    port the plant and sub-contracted with engineers, contractors, and
    other vendors to figure out how the plant would operate. In other
    words, 1st Quality was doing its due diligence to figure out what
    kind of equipment the new Wadley plant would need. After this
    investigation period, 1st Quality and Wadley entered into a con-
    tract worth $5,579,255, which allocated $4,140,255 for 27 line items
    of equipment, $1,384,000 for erection, installation, and electrical,
    and $55,000 for extra electrical. The parties expected that 1st Qual-
    ity would hire Gaston Construction Company to complete the line
    USCA11 Case: 21-11002            Date Filed: 05/24/2022        Page: 4 of 17
    4                         Opinion of the Court                      21-11002
    items for erection, installation, and electrical work for the plant
    (and 1st Quality would pay Gaston Construction Company accord-
    ingly).
    In February 2012, Wadley asked 1st Quality if Wadley could
    work directly with Gaston Construction Company on the erection,
    installation, and electrical work. 1 1st Quality agreed to that ar-
    rangement, and the parties signed a modified contract in May 2012,
    which subtracted out almost $1.5 million for the work Gaston Con-
    struction Company would do independently. 2 In the modified
    contract, worth $ 4,059,224.43, there were 27 line items. Twenty-
    five of the line items were for individual pieces of equipment, add-
    ing up to $3,887,274.43. The other two line items were for instal-
    lation, setup, and calibration of scales and for engineering, which
    combined, only added up to $171,950, less than five percent of the
    contract price. Both parties understood that the engineering line
    item would be done by a third party, whom 1st Quality would pay.
    Wadley received all the contracted-for equipment but did
    not pay the invoices for some of that equipment because Wadley
    was not satisfied with the functioning of the plant. On its own
    dime, 1st Quality visited the plant to try to figure out why the
    1 Apparently, this is because 1st Quality was not a licensed contractor in Ala-
    bama.
    2 Any further references to the “contract” refer to this modified contract,
    which omitted the erection, installation, and electrical work that would now
    be done by Gaston Construction Company.
    USCA11 Case: 21-11002             Date Filed: 05/24/2022          Page: 5 of 17
    21-11002                    Opinion of the Court                                 5
    equipment it sold Wadley did not meet the 500 ton-per-hour re-
    quirement. 1st Quality understood that the plant was supposed to
    process 500 tons of granite per hour when it sold the equipment to
    Wadley.
    About five years after the plant was completed, Wadley sued
    1st Quality in Alabama state court, arguing, among other things,
    that 1st Quality breached its contract with Wadley when the gran-
    ite plant did not meet the 500 ton-per-hour requirement. 3 1st Qual-
    ity removed that case to federal district court in the Middle District
    of Alabama. The procedural history of this case from there is con-
    voluted, and, frankly, irrelevant for our purposes until we get to
    Wadley’s Fourth Amended Complaint.4 In that complaint,
    Wadley alleged breach of contract as to the 500 ton-per-hour re-
    quirement and as to the loadout capacity and also alleged misrep-
    resentation by 1st Quality as to the specifications of the plant. 1st
    Quality moved to dismiss, arguing that both the breach of contract
    claims as well as the misrepresentation claim were barred by the
    applicable statute of limitations. Specifically, 1st Quality argued
    that the UCC’s four-year statute of limitations applied to the breach
    3 Wadley also alleged breach of contract as to the loadout capacity of the plant
    and misrepresentation as to the design of the granite plant. Wadley wanted a
    plant that had a “rail ballast load out system that could load out 2,000 ton[s] of
    granite per hour.”
    4 The short story is that the District Court afforded Wadley multiple opportu-
    nities to amend its complaint to allege facts establishing that it filed within the
    applicable statute of limitations.
    USCA11 Case: 21-11002           Date Filed: 05/24/2022        Page: 6 of 17
    6                         Opinion of the Court                     21-11002
    of contract claims because, 1st Quality said, the contract was for
    goods rather than services. And 1st Quality argued that a two-year
    statute of limitations applied to the misrepresentation claim. The
    District Court then dismissed the misrepresentation claim as
    barred by the two-year statute of limitations but allowed the
    breach-of-contract claims to proceed because Wadley had alleged
    enough facts to make it plausible that the contract was for services
    rather than goods, so that it was plausible the action was not time-
    barred. 5
    1st Quality then answered the Fourth Amended Complaint
    and counterclaimed against Wadley for breach of contract (and un-
    just enrichment) for failing to pay 1st Quality for some of the equip-
    ment at the granite plant. In the midst of both discovery and trial
    preparation, 1st Quality then filed two summary judgment mo-
    tions, one for Wadley’s claims and one for its own counterclaims
    against Wadley. The District Court then granted both motions for
    summary judgment. As to Wadley’s breach of contract claims, the
    District Court determined that the contract was for goods under
    the UCC, so the applicable statute of limitations had passed before
    Wadley filed suit. Thus, the District Court granted summary judg-
    ment on the breach of contract claims. As to 1st Quality’s counter-
    claim, the District Court determined Wadley had to pay the unpaid
    5 The District Court noted that “nothing in the contract specifically reflects
    the[] specific services” Wadley alleged that 1st Quality was supposed to pro-
    vide.
    USCA11 Case: 21-11002         Date Filed: 05/24/2022     Page: 7 of 17
    21-11002                Opinion of the Court                          7
    invoices, with interest and costs, and granted summary judgment
    on the counterclaim as well. After the District Court denied its
    motion to reconsider, Wadley timely appealed the District Court’s
    order granting summary judgment as to both claims, the District
    Court’s denial of the motion to reconsider its grant of summary
    judgment as to 1st Quality’s counterclaims, and the District Court’s
    order for Wadley to pay 1st Quality based on the counterclaim,
    with interests and costs.
    II.
    Now, we must determine whether the District Court erred
    in granting summary judgment for 1st Quality on both the breach
    of contract claims and the counterclaim for unpaid invoices and
    whether it erred in denying Wadley’s motion for reconsideration
    on the grant of summary judgment as to 1st Quality’s counter-
    claim.
    We review a district court’s grant of summary judgment de
    novo. Sierra Club, Inc. v. Leavitt, 
    488 F.3d 904
    , 911 (11th Cir.
    2007). We grant summary judgment “when viewing the evidence
    in the light most favorable to the non-moving party, there is no
    genuine issue of material fact and the moving party is entitled to
    judgment as a matter of law.” Id.; see Fed. R. Civ. P. 56(c). We
    review a District Court’s factual findings for clear error and its legal
    conclusions de novo. AcryliCon USA, LLC v. Silikal GmbH, 
    985 F.3d 1350
    , 1363 (11th Cir. 2021). Where there is no dispute over
    the contract terms themselves, we review de novo the
    USCA11 Case: 21-11002           Date Filed: 05/24/2022       Page: 8 of 17
    8                         Opinion of the Court                    21-11002
    determination of whether the contract is for goods or services.
    BMC Indus., Inc. v. Barth Indus., Inc., 
    160 F.3d 1322
    , 1331 (11th
    Cir. 1998).
    And, finally, we review a district court’s denial of a motion
    for reconsideration for abuse of discretion. Corley v. Long-Lewis,
    Inc., 
    965 F.3d 1222
    , 1234 (11th Cir. 2020).
    III.
    Let’s start with the governing law. Federal courts sitting in
    diversity apply the choice of law rules for the state in which they
    sit. Klaxon Co. v. Stentor Elec. Mfg. Co., 
    313 U.S. 487
    , 496, 
    61 S. Ct. 1020
    , 1021 (1941). So, Alabama choice of law rules apply in this
    case. Alabama’s choice of law rule states that the law of the state
    where the contract was signed governs the contract. See Cherokee
    Ins. Co., Inc. v. Sanches, 
    975 So. 2d 287
    , 292 (Ala. 2007). So, Geor-
    gia substantive law governs the contract at issue. But for proce-
    dural matters, generally Alabama applies its own law, and Alabama
    law considers the statute of limitations to be a procedural matter.6
    See Battles v. Pierson Chevrolet, Inc., 
    274 So.2d 281
    , 285 (Ala.
    1973). So, we are left with Georgia law governing the interpreta-
    tion of the contract—whether it is for goods or services in this
    case—and Alabama law governing whether Wadley filed a
    6 There are exceptions to this general rule. But the parties have agreed with
    the District Court’s holding that Alabama law governs the applicable statute
    of limitations, so we do not dive deeper into or disturb the District Court’s
    analysis of the applicable statute of limitations here.
    USCA11 Case: 21-11002        Date Filed: 05/24/2022     Page: 9 of 17
    21-11002               Opinion of the Court                         9
    counterclaim within the applicable statute of limitations. Alabama
    and Georgia have both adopted the UCC, and the applicable stat-
    ute of limitations under the UCC is four years. See 
    Ala. Code § 7
    -
    2-725(1); O.C.G.A. § 11-2-725.
    Starting with the substance of the contract, Georgia law says
    that when a contract is for both goods and services, the court must
    apply the predominant factor test to determine whether the con-
    tract is more for the sale of goods or for services. See J. Lee Greg-
    ory, Inc. v. Scandinavian House, L.P., 
    433 S.E.2d 687
    , 689 (Ga. Ct.
    App. 1993); S. Tank Equip. Co. v. Zartic, Inc., 
    471 S.E.2d 587
    , 589
    (Ga. Ct. App. 1986). “When the predominant element of a contract
    is the sale of goods, the contract is viewed as a sales contract and
    the UCC applies even though a substantial amount of service is to
    be rendered in installing the goods.” J. Lee Gregory, 
    433 S.E.2d at 689
     (internal citation and quotation marks omitted). We must de-
    termine whether the services 1st Quality provided were “inci-
    dental” to the sale of goods. 
    Id.
     If they were, then the sale of goods
    was the predominant purpose, but, if the sale of goods was only
    incidental to the provision of services, then services predominate.
    See 
    id.
    To apply the predominant factor test, we must evaluate
    three aspects of the contract to determine whether goods or ser-
    vices are predominant: 1) the language of the contract—looking at
    how the parties refer to each other and the labeling of the contract;
    2) the subject matter of the contract—looking to see if the contract
    is for a movable good; and 3) the billing of the contract—looking
    USCA11 Case: 21-11002        Date Filed: 05/24/2022     Page: 10 of 17
    10                      Opinion of the Court                 21-11002
    to see the proportion of the contract’s price dedicated to goods and
    services. See Suntrust Bank v. Venable, 
    791 S.E.2d 5
    , 7–8 (Ga.
    2016); see also BMC Indus., 
    160 F.3d at 1330
     (applying the same
    predominant factor test to a contract governed by Florida law). If,
    after applying the predominant factor test, it is still unclear whether
    the contract is for goods or for services, Georgia law says that the
    UCC should “be liberally construed and applied to promote its un-
    derlying purposes and policies.” Óle Mexican Foods, Inc. v. Han-
    son Staple Co., 
    676 S.E.2d 169
    , 171 (Ga. 2009).
    Under the first factor, we must look at the language of the
    contract. Wadley makes much of the fact that the modified con-
    tract is for a “500 TPH Portable Granite Plant.” The modified con-
    tract also has a reference to the “Total Plant Selling Price.” That
    makes it seem like the contract is for a working granite plant, a cus-
    tom-built operation, which could point in the direction of the con-
    tract being for the service of designing a plant rather than just the
    component parts themselves. See Heart of Tex. Dodge, Inc. v. Star
    Coach, LLC, 
    567 S.E.2d 61
    , 64 (Ga. Ct. App. 2002) (explaining that
    the contract was for services rather than goods when the purpose
    of the contract was to customize a vehicle and the parts purchased
    to do so were only incidental to the service). The contract ends
    with 1st Quality’s executive saying, “We thank you for giving us
    the opportunity to work with you on this plant.” That too seems
    to indicate that 1st Quality was providing the service of construct-
    ing a plant. See 
    id.
     (explaining that services were anything but inci-
    dental to customizing a vehicle).
    USCA11 Case: 21-11002        Date Filed: 05/24/2022     Page: 11 of 17
    21-11002                Opinion of the Court                        11
    On the flip side, the contract says that it is a “quotation,” a
    common word used in the sale of goods. See Paramount Contract-
    ing Co. v. DPS Indus., Inc., 
    709 S.E.2d 288
    , 291–92 (Ga. Ct. App.
    2011) (explaining that quote for selling dirt indicated a contract for
    goods rather than services). And the fact that the contract refers to
    the “Total Plant Selling Price” can cut in 1st Quality’s favor too be-
    cause usually in contractual language only goods are bought and
    sold, in contrast to services. See BMC Indus., 
    160 F.3d at 1330
     (ex-
    plaining that words like “purchase,” “customer,” and “seller,” indi-
    cate a transaction for the sale of goods). Further, the contract spe-
    cifically listed out 25 items of “equipment,” which suggests a goods
    contract. 
    Id.
     In BMC, we found that the contract’s language sug-
    gested a goods transaction when it stated that it was a “purchase
    order ‘for the fabrication and installation of automated equip-
    ment.’” 
    Id. at 1331
     (quoting parties’ contract). The Court so con-
    cluded despite language in the contract that one party had hired the
    other to “‘design, fabricate, debug/test and supervise field installa-
    tion and start up of equipment to automate the operations of
    [BMC’s production line for unfinished eyeglass lenses].’” 
    Id. at 1325
     (quoting parties’ contract). Here, any language that would
    suggest a services contract is not as robust as the language in BMC
    Industries. So, the first factor does not cut decisively in either
    party’s direction.
    Turning to the second factor, we must evaluate whether the
    contract is for a movable good. Under Georgia law, “goods” are
    defined by whether they are “movable at the time of identification
    USCA11 Case: 21-11002        Date Filed: 05/24/2022     Page: 12 of 17
    12                      Opinion of the Court                 21-11002
    to the contract for sale.” O.C.G.A. § 11-2-105(1). In the modified
    contract, 25 of the 27 line items are for movable goods. Each piece
    of equipment is a good that was movable when the contract was
    signed. 1st Quality is a sales representative for equipment. This
    factor clearly favors us holding that the UCC applies to the con-
    tract.
    Finally, we must evaluate how the contract was billed. See
    BMC Indus., 
    160 F.3d at 1330
    . “[W]hen the contract price does not
    include the cost of services, or the charge for goods exceeds that
    for services, the contract is more likely to be for goods.” Id.; see
    also J. Lee Gregory, 
    433 S.E.2d at 689
     (“Rather it would appear that
    the rendition of services was the incidental factor. After all, approx-
    imately two-thirds of the cost of the transaction was allocated to
    [goods].”). Looking at the contract itself, we know that there were
    27 line items, 25 of which were for individual pieces of equipment,
    totaling $3,887,274.43, over 95% of the contract price. The last two
    line items for the installation, setup, and calibration of the scales
    and engineering totaled $171,950, less than five percent of the con-
    tract price. And we know that both parties understood that the en-
    gineering included in the last line item would be done by a third
    party anyway, not by 1st Quality. If over 95% of the contract is for
    goods, then it seems pretty clear under Georgia case law, like J. Lee
    Gregory, that the contract is for goods and not services. J. Lee
    Gregory, 
    433 S.E.2d at
    688–89. But, Wadley argues, the numbers
    aren’t the whole story. The thrust of Wadley’s response to the 95%
    figure is that the price for each line item of equipment in the
    USCA11 Case: 21-11002       Date Filed: 05/24/2022     Page: 13 of 17
    21-11002               Opinion of the Court                        13
    contract included a mark-up—meaning that 1st Quality was baking
    its charge for services into the cost of each item of equipment so
    that there is a genuine issue of material fact on the costs allocable
    to goods and services sufficient to defeat summary judgment.
    At oral argument, 1st Quality pointed to Document 112 of
    the record and its exhibits to explain that 1) even accepting
    Wadley’s argument that markups constitute service charges and as-
    suming a 20% markup on all 25 equipment items and 2) counting
    the $91,000 commission payment that 1st Quality received from
    Gaston as a service charge, still 74% of the contract would be at-
    tributable to goods rather than services. So, 1st Quality explained,
    still no genuine dispute of material fact exists, even taking Wadley’s
    figures as the right ones, because the contract is still clearly for
    goods based on Georgia case law. See Zartic, 471 S.E.2d at 588; J.
    Lee Gregory, 
    433 S.E.2d at 688
    . 1st Quality’s colloquy with the
    Court on this issue was a surprise to Wadley, which explained that
    it was not aware of the figures 1st Quality was referring to. So, we
    asked for supplemental briefing to help us resolve the issue.
    Having reviewed the supplemental briefing, we do not
    think it sheds meaningful light on the issue. We simply cannot
    conclude, as a matter of either law or fact, that the markups repre-
    sent service charges. Wadley has cited no record document or case
    to suggest that the contracting parties agreed to the markups as dis-
    guised service charges, and it seems more logical to conclude that
    a sale of equipment will include a margin of profit for the seller.
    So, summary judgment is appropriate, because this is a contract for
    USCA11 Case: 21-11002           Date Filed: 05/24/2022         Page: 14 of 17
    14                         Opinion of the Court                      21-11002
    goods, and the UCC’s applicable four-year statute of limitations has
    passed. 7
    IV.
    Now, all we have left to do is decide whether the District
    Court properly granted summary judgment to 1st Quality and
    properly denied Wadley’s motion for reconsideration on its coun-
    terclaim for unpaid invoices. Wadley raises three defenses on ap-
    peal that, it says, foreclose summary judgment on the issue of un-
    paid invoices: 1) its setoff defense; 2) its implied warranty of fitness
    claim; and 3) its statute of limitations defense. None are persuasive.
    First, Wadley argues that it properly asserted a common-law
    setoff or recoupment defense below that should have foreclosed
    summary judgment and that the District Court’s reading of
    7 Wadley’s more global position that the contract is for services seems to be
    based in the outside conversations of the executives at Wadley and 1st Quality
    and 1st Quality’s role in consulting on the plant. The problem for Wadley is
    that Georgia law has recognized that services will often be a part of delivering
    goods, and the services involved in preparing to provide goods do not trans-
    form a contract from the sale of goods to the provision of services. See Para-
    mount, 
    709 S.E.2d at 290
     (“When the predominant element of a contract is the
    sale of goods, the contract is viewed as a sales contract and [the UCC] applies,
    even though a substantial amount of service is to be rendered in installing the
    goods.” (quoting Heart of Tex., 
    567 S.E.2d at 63
    )). On a separate note, we
    acknowledge that Wadley’s counsel on appeal did not represent Wadley when
    Wadley originally filed its complaint. Wadley has sued its original lawyers for
    malpractice in not filing the breach of contract claims earlier. Wadley Crushed
    Stone Co. LLC v. Rushton Stakely Johnston & Garrett, Case No. CV-2021-
    900252 (Cir. Ct. of Montgomery Cnty., Ala.).
    USCA11 Case: 21-11002        Date Filed: 05/24/2022      Page: 15 of 17
    21-11002                Opinion of the Court                        15
    Wadley’s defense as a statutory setoff defense under 
    Ala. Code § 6
    -
    8-80 was unjustifiably narrow. After review of Wadley’s response
    to 1st Quality’s motion for summary judgment on the unpaid in-
    voices, we think the District Court was exactly right. Wadley did
    not assert a common-law recoupment or setoff defense based on
    Finish Line v. J.F. Pate & Assocs. Contractors, 
    90 So. 3d 749
     (Ala.
    Civ. App. 2012) in its response to 1st Quality, like it does on appeal.
    In its brief opposing summary judgment, Wadley points to 
    Ala. Code § 6-8-80
     and then says the following:
    In the event the Court finds that 1st Quality’s motion
    for summary judgment on the unpaid invoices should
    be granted, while at the same time finding that WCS’s
    claims against 1st Quality can proceed to a jury, it
    should decline to certify a judgment in favor of 1st
    Quality on its counterclaims as final under Fed. R.
    Civ. P. 54(b) so that the issue of set-off can be resolved
    at trial.
    The only way to read Wadley’s argument in its opposition to 1st
    Quality’s motion for summary judgment is that Wadley wanted a
    setoff if it prevailed at trial. So, if the District Court determined
    that 1st Quality should not prevail on its summary judgment mo-
    tion on the statute of limitations issue, then, Wadley was saying,
    “We should be entitled to a setoff for the unpaid invoices based on
    whatever we get from the jury.” We agree with the District Court
    that Wadley did not sufficiently flesh out any other theory, such as
    to preserve it. Because Wadley cannot recover on its original claim
    USCA11 Case: 21-11002        Date Filed: 05/24/2022     Page: 16 of 17
    16                      Opinion of the Court                 21-11002
    because of the statute of limitations issue, its setoff defense is una-
    vailing.
    Next, as to the implied warranty of fitness defense, as the
    District Court explained, Wadley never raised implied warranty of
    fitness in its original pleadings. Nor did it raise an implied warranty
    defense in its answer to 1st Quality’s counterclaim. We do not typ-
    ically allow parties to raise new defenses in response to summary
    judgment motions that they did not already make in their answers
    unless there are exceptional circumstances, such as when “a pure
    question of law is involved” and a failure to address it would result
    in “a miscarriage of justice.” Easterwood v. CSX Transp., Inc., 
    933 F.2d 1548
    , 1551 (11th Cir. 1991), aff’d, 
    507 U.S. 658
    , 
    113 S. Ct. 1732
    (1993) (“If federal pre-emption is an affirmative defense, CSX’s fail-
    ure to specifically plead the defense in its answer or amended an-
    swer results in the waiver of this defense.”). Had Wadley asked to
    amend its answer under Fed. R. Civ. P. 15(a) to include an implied
    warranty defense, the District Court might have allowed Wadley
    to remedy the problem in its answer. See 
    id.
     It did not do so.
    The reason we require parties to raise their defenses in an-
    swering a complaint or counterclaim is that it helps trial prepara-
    tion as discovery is targeted toward the claims and defenses that
    are presented. See Hassan v. U.S. Postal Serv., 
    842 F.2d 260
    , 263
    (11th Cir. 1988). And here, Wadley and 1st Quality engaged in ex-
    tensive discovery before Wadley brought up this defense in its re-
    sponse to 1st Quality’s motion for summary judgment. It would
    thus be unfair to 1st Quality to allow Wadley to raise that defense
    USCA11 Case: 21-11002       Date Filed: 05/24/2022     Page: 17 of 17
    21-11002               Opinion of the Court                        17
    now. So, there is no miscarriage of justice in us denying Wadley
    consideration of the implied warranty of fitness claim, and we
    deem it forfeited.
    Finally, Wadley argues that if the UCC statute of limitations
    bars its claims, it should also bar 1st Quality’s claim for unpaid in-
    voices. The only problem is that Wadley forfeited that argument
    when it did not include it in its response to 1st Quality’s motion for
    summary judgment on the unpaid invoices. Again, we typically do
    not reach arguments forfeited by the parties and only do consider
    them in a very limited set of circumstances. See Access Now, Inc.
    v. Sw. Airlines Co., 
    385 F.3d 1324
    , 1331 (11th Cir. 2004). Wadley’s
    failure to raise the statute of limitations defense in its response to
    1st Quality’s motion for summary judgment is not an “exceptional
    condition[]” that merits us using our discretion to consider it now.
    
    Id. at 1332
    . Wadley’s argument on the statute of limitations de-
    fense is forfeited.
    Therefore, the District Court properly granted summary
    judgment to 1st Quality on the claim for unpaid invoices and
    properly denied Wadley’s motion for reconsideration, and the Dis-
    trict Court’s judgment is
    AFFIRMED.