J.A.M. Builders, Inc. v. Alexis Herman , 233 F.3d 1350 ( 2000 )


Menu:
  •                                                                                     [PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FILED
    FOR THE ELEVENTH CIRCUIT                  U.S. COURT OF APPEALS
    ELEVENTH CIRCUIT
    ________________________                      NOV 22 2000
    THOMAS K. KAHN
    CLERK
    No. 99-11917
    ________________________
    O.S.H.R.C. No. 98-00823
    J.A.M. BUILDERS, INC.,
    Petitioner,
    versus
    ALEXIS HERMAN, Secretary of Labor, and
    OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION,
    Respondents.
    __________________________
    Petition for Review of an Order of the Occupational Safety and
    Health Review Commission
    _________________________
    (November 22, 2000)
    Before CARNES and BARKETT, Circuit Judges, and POLLAK*, District Judge.
    _______________________
    *Honorable Louis H. Pollak, U.S. District Judge for the Eastern District of Pennsylvania, sitting
    by designation.
    BARKETT, Circuit Judge:
    J.A.M. Builders, Inc., (“J.A.M.”) petitions for review of a final decision of
    the Occupational Safety and Health Review Commission (the “Commission”)
    affirming the administrative law judge’s (“ALJ”) finding that it willfully violated a
    safety regulation promulgated pursuant to the Occupational Safety and Health Act
    (“OSHA”).
    J.A.M. was a subcontractor at a construction site in Miami Beach, Florida,
    where an ironworker was killed by electrocution. After an investigation into the
    fatality, the Secretary of the Department of Labor (the “Secretary”) issued a
    citation and notice of a proposed penalty against J.A.M., alleging various
    violations of OSHA safety standards. One of the charges alleged that J.A.M.
    willfully violated a construction industry safety standard that prohibits an employer
    from permitting its employees to work in such proximity to electrical power
    circuits that they could come into contact with them, without taking adequate
    precautions to protect employees from the risk of electric shock.
    On appeal, J.A.M. challenges the Commission’s decision that it willfully
    violated this standard, arguing that the Commission’s decision is not supported by
    substantial evidence and is not in accordance with the law. We review the
    Commission’s findings of fact to determine whether they are supported by
    substantial evidence on the record as a whole; if so, they are deemed conclusive.
    2
    See 
    29 U.S.C. § 660
    (a); Niemand Indus., Inc. v. Reich, 
    73 F.3d 1083
    , 1084 (11th
    Cir. 1996). “Substantial evidence is more than a scintilla and is such relevant
    evidence as a reasonable person would accept as adequate to support a
    conclusion.” Lewis v. Callahan, 
    125 F.3d 1436
    , 1440 (11th Cir. 1997). We also
    review whether the Commission’s order is “in accordance with the law.” Reich v.
    Trinity Indus., Inc., 
    16 F.3d 1149
    , 1152 (11th Cir. 1994).
    The safety standard at issue, 
    29 C.F.R. § 1926.416
    (a)(1), provides:
    No employer shall permit an employee to work in such proximity to
    any part of an electric power circuit that the employee could contact
    the electric power circuit in the course of work, unless the employee is
    protected against electric shock by de-energizing the circuit and
    grounding it or by guarding it effectively by insulation or other means.
    OSHA differentiates among violations of varying severity. J.A.M was charged
    with the most severe offense, to wit, a “willful” violation pursuant to 
    29 U.S.C. § 666
    (a), which is subject to the greatest penalties under the Act: a fine not less than
    $5,000 and up to $70,000, and the possibility of imprisonment if the willful
    violation causes an employee’s death. See 
    29 U.S.C. § 666
    (a), (e). See also
    United States v. Ladish Malting Co., 
    135 F.3d 484
    , 490 (7th Cir. 1998)
    (differentiating various offenses under 
    29 U.S.C. § 666
    ).
    The ALJ upheld the citation, finding that J.A.M. failed to adequately protect
    its employees working in proximity to energized electrical lines on November 5th
    3
    through the 7th. The administrative record upon which the ALJ based his decision
    reflects the following. J.A.M. Builders was hired by Brodson Construction
    Company, the general contractor, to construct the shell of a three-story building.
    The new structure, measuring 85 feet long by 17 feet wide, was an addition to an
    existing building. At the time of the fatality, the structure stood approximately 20
    feet tall.1 During the relevant time period, three energized, high-voltage electrical
    lines, or primary conductors, carrying 7,620 volts of electricity each, ran parallel to
    the building’s east side approximately 8-12 feet above the structure. These lines
    were not insulated and were held up by one pole located at the northeast corner of
    the building, 19 inches away from the east wall, and by another pole at the
    southeast corner.
    After J.A.M. began its work on the building, company employees orally
    informed Brodson that the high-voltage lines needed to be rerouted. Five days
    before J.A.M. began working with steel on the third floor, J.A.M.’s project
    manager additionally wrote Brodson that a Florida Power & Light Co. (“FP&L”)
    representative had instructed J.A.M. that work would not be allowed to continue in
    proximity to the lines unless they were moved, and requested Brodson to
    1
    The structure was located on a corner lot: the south side abutted the existing building,
    the west side abutted another building, the east side faced an alley (across from which were
    several buildings), and the north side faced the street.
    4
    “coordinate with [FP&L] to have these lines moved.” Before the ALJ, J.A.M.
    took the position that notwithstanding its letter to Brodson, J.A.M. had fabricated
    this story in order to shift blame to FP&L for any project delays.2 However,
    Canute Lobean, a compliance officer for the Secretary, and John Jacob, an FP&L
    claims agent, testified that the FP&L representative, Diego Borges, told them that
    he had warned J.A.M. about working in proximity to the energized lines.
    On November 5, 1997, when J.A.M. began working with steel on the third
    floor, the energized lines along the building’s east side had not been de-energized,
    rerouted, moved, or insulated. Nonetheless, ironworkers working for J.A.M. began
    hoisting narrow bars of reinforcing steel (“rebar”), measuring between 16-20 feet
    long, from the ground level to the third floor, passing it through a second-floor
    window and then through a four-foot by four-foot hole located between the second
    and the third floors. The rebar was passed up length-wise, and was angled at a
    forty-five degree angle opposite from the building’s east wall and away from the
    energized lines, although it was tall enough that it could have touched the
    energized lines had it been stood up and/or leaned toward the east wall. After the
    rebar was lifted through the hole in the third floor, it was tied together on a 16-inch
    2
    The Secretary’s compliance officer also testified that J.A.M.’s president, John Bullis,
    admitted that there were safety hazards at the construction site, but that it was Brodson’s
    responsibility, not J.A.M.’s, to contact FP&L to have the lines rerouted.
    5
    cinderblock, supported by a 4-inch piece of wood, to form an interlocking matting
    of steel, which was then placed over a wood frame to form the base of the floor, or
    deck, into which concrete would be poured. Rebar was also used by J.A.M. to
    build the frame for horizontal and vertical support beams on the third floor. The
    hole was closed on November 5 after J.A.M. thought it had finished its ironwork.
    On November 6, 1997, J.A.M. discovered that it needed more rebar and
    began raising rebar to the third floor along the outside of the east wall. Under the
    direction of Juan Carlos Diaz, J.A.M.’s foreman, the ironworkers passed rebar
    length-wise directly from the ground level to the third floor, sometimes with the
    assistance of a worker positioned at the second-floor window. However, all work
    was stopped later that day by James Stowe, the ironworkers’ union foreman, after
    he was informed by an electrician of the severe danger of working along the east
    wall close to the energized lines.
    After Stowe stopped the work, J.A.M. management officials and
    representatives for the ironworkers met. The J.A.M. officials testified that at this
    meeting the parties agreed that the remaining rebar would be passed to the third
    floor along the north wall, instead of the east wall above which the energized lines
    were located. The ironworkers who attended the meeting testified that J.A.M. had
    agreed to cut a new hole in the floor, so that the rebar could be passed through as it
    6
    had been on November 5. It is undisputed that a new hole was not cut into the
    floor.
    The next day, November 7, the ironworkers’ union substituted Larry
    Williams as foreman for Stowe, whom J.A.M. had fired.3 Williams was instructed
    by J.A.M. to pass the remaining rebar along the structure’s north side.
    Notwithstanding these instructions, Williams and several ironworkers passed rebar
    along the east side. Williams was standing on the third floor deck and was
    receiving rebar from below when a 16-foot, 9-inch long piece of rebar he was
    holding came into contact with one of the high-voltage lines. Williams was
    electrocuted and died. Foreman Diaz testified that he was on site in J.A.M.’s
    office when the accident occurred. Ironworker Miguel Doreus testified that Diaz
    was at the site that day and that Diaz saw them working along the structure’s east
    side.
    Based on evidence presented that J.A.M. knew of the hazard involved both
    before work began and during construction of the structure’s third floor, the ALJ
    3
    The testimony reflects that J.A.M. felt that Stowe should not have stopped work on the
    6th and attributed the work stoppage to “personality conflicts” between Stowe and J.A.M.’s
    foreman. Stowe testified that, after he ordered the work stoppage, J.A.M.’s foreman told him that
    “[he] had better look for [] a new job because [he] no longer [had] one.” Stowe testified that he
    was allowed to finish work that day, but that he was not to report to the jobsite on November 7.
    The union representative, David Gornewicz, and J.A.M.’s vice president, Bill Mack, also
    testified that J.A.M and the ironworkers agreed that Stowe would be replaced by another
    foreman on November 7.
    7
    found that J.A.M. had a “heightened awareness of the hazardous conditions,” and
    concluded that its violation over the three days was “willful.” The ALJ rejected
    J.A.M.’s affirmative defense that Williams had committed employee misconduct,
    reasoning that J.A.M. had not established work rules designed to prevent the
    violation and had no written safety program. The ALJ observed:
    The deck was only 17 feet wide. The rebar was up to 20 feet long.
    The high voltage lines were 10 feet above the deck. . . . Walls of
    adjacent buildings abutted the west and south sides of the deck. Rebar
    lifted to the deck would, of necessity, come close to the energized
    lines. [J.A.M.] knew this long before the period of November 5,
    1997, through November 7, 1997. It took no action to eliminate the
    hazard or guard the energized lines. It continued to allow its
    employees to work in close proximity to this hazardous condition
    throughout this three-day period until one employee finally contacted
    the high voltage lines with rebar in the course of his work. . . .
    Allowing employees to continue to work from November 5, 1997,
    through November 7, 1997, with [a] heightened awareness [of the
    hazardous conditions] clearly indicates [J.A.M.’s] conscious disregard
    for the requirements of the Act and plain indifference to the safety of
    its employees. . . .
    The ALJ assessed a $35,000 civil penalty for this violation. Because the
    Commission declined J.A.M.’s request to review the ALJ’s decision, the ALJ’s
    decision became the Commission’s final order. See 
    29 U.S.C. § 661
    (j).
    DISCUSSION
    J.A.M. preliminarily contends that the ALJ erred by admitting the out-of-
    court statement of FP&L representative Diego Borges, that he had previously
    8
    warned J.A.M. not to work in proximity to the energized lines running along the
    structure’s east side. “Hearsay is admissible in administrative hearings and may
    constitute substantial evidence if found reliable and credible.” Williams v. U.S.
    Dep’t of Transp., 
    781 F.2d 1573
    , 1578 n.7 (11th Cir. 1986). We have identified
    several factors that demonstrate hearsay’s probative value and reliability for
    purposes of its admissibility in an administrative proceeding: whether (1) the
    out-of-court declarant was not biased and had no interest in the result of the case;
    (2) the opposing party could have obtained the information contained in the
    hearsay before the hearing and could have subpoenaed the declarant; (3) the
    information was not inconsistent on its face; and (4) the information has been
    recognized by courts as inherently reliable. See U.S. Pipe & Foundry Co. v. Webb,
    
    595 F.2d 264
    , 270 (5th Cir. 1979)4 (citing Richardson v. Perales, 
    402 U.S. 389
    ,
    402-06, 
    91 S.Ct. 1420
    , 1428-30, 
    28 L.Ed.2d 842
     (1971)).
    Borges’ statement was recounted by Canute Lobean, the compliance officer,
    and John Jacob, the FP&L claims agent who was not affiliated or employed by a
    party to this case. Borges’ statement was not inconsistent on its face and was
    consistent with other evidence presented, including J.A.M.’s own letter to Brodson
    4
    This Court has adopted as binding precedent all Fifth Circuit decisions handed down
    prior to the close of business on September 30, 1981. See Bonner v. Prichard, 
    661 F.2d 1206
    ,
    1209 (11th Cir. 1981) (en banc).
    9
    requesting that it contact FP&L to move the energized lines before J.A.M. began
    using steel on the third floor. Because Borges’ out-of-court statement was
    sufficiently reliable, we conclude that the ALJ did not err by admitting it into
    evidence.
    J.A.M. next argues that substantial evidence does not support the
    Commission’s finding that its violation was “willful” because, on each of the three
    days in question, it used methods designed to adequately protect the ironworkers
    from coming into contact with the energized lines.
    Although the term “willful” is not defined in the Act, this Court has held that
    in its simplest form, a willful violation is “an intentional disregard of, or plain
    indifference to, OSHA requirements.” Reich v. Trinity Industries, Inc., 
    16 F.3d 1149
    , 1152 (11th Cir. 1994) (quoting Georgia Elec. Co. v. Marshall, 
    595 F.2d 309
    ,
    318 (5th Cir. 1979)). The Court in Trinity reiterated the former Fifth Circuit’s
    adoption of the Commission’s determination that a violation is “willful” if an
    employer commits an act in either “intentional disregard of, or plain indifference
    to, OSHA requirements.” Trinity Indus., 
    16 F.3d at 1152
     (quoting Georgia Elec.
    Co., 595 F.2d at 318). Under the Commission’s definition, to be deemed “willful,”
    proof must be adduced either that (1) “[the] employer knew of an applicable
    standard or provision prohibiting the conduct or condition and consciously
    10
    disregarded the standard,” or (2) that, if the employer did not know of an
    applicable standard or provision’s requirements, it exhibited such “reckless
    disregard for employee safety or the requirements of the law generally that one can
    infer that . . . the employer would not have cared that the conduct or conditions
    violated [the standard].” Secretary of Labor v. Williams Enter., Inc., 
    13 O.S.H. Cas. 1249
    , 1257 (BNA) (O.S.H.R.C. 1987). See also Trinity Indus., 
    16 F.3d at 1152-55
     (holding that employer committed willful violation because it knew of the
    standard but decided not to comply, despite employer’s good faith belief that its
    own approach provided protection at least equivalent to OSHA’s requirements);
    Valdak Corp. v. Occupational Safety & Health Review Comm’n, 
    73 F.3d 1466
    ,
    1469 (8th Cir. 1996) (holding that an employer who “substitutes his own judgment
    for the requirement of a standard or fails to correct a known hazard commits a
    willful violation even if the employer does so in good faith”); Brock v. Morello
    Bros. Constr., Inc., 
    809 F.2d 161
    , 164-66 (1st Cir. 1987) (holding that “an act may
    be willful if the offender shows indifference to the [law]; he need not be
    consciously aware that the conduct is forbidden . . ., but his state of mind must be
    such that, if he were informed of the rule, he would not care”). Cf. McLaughlin v.
    Union Oil Co. of California, 
    869 F.2d 1039
    , 1047 (7th Cir. 1989) (setting aside
    11
    willful violation because no evidence was presented that employer was “reckless,”
    “grossly negligent,” or “more than careless”).
    After closely reviewing the administrative record and the parties’ briefs, and
    after hearing oral argument, we conclude that substantial evidence supports the
    Commission’s determination that J.A.M. willfully violated the standard. The
    record reflects that J.A.M. required its employees to work in dangerous proximity
    to energized electrical lines. Although J.A.M. does not deny knowing that the
    working conditions were hazardous and that the safety standard at issue applied, it
    failed to have the live wires de-energized, rerouted, moved, or insulated, doing
    essentially nothing to eliminate the risk of electrical shock to its workers. J.A.M.’s
    attempt to minimize the hazard by directing that the rebar be raised on the 17-foot
    wide north side of the building, where the high voltage lines only crossed over one
    corner, and blaming Larry Williams for disregarding its directions, does not
    adequately refute the evidence that J.A.M. consciously disregarded the standard or
    exhibited such “reckless disregard for employee safety or the requirements of the
    law generally that one can infer that . . . the employer would not have cared that the
    conduct or conditions violated [the standard].” Williams Enter., 13 O.S.H. Cas. at
    1257.
    12
    Indeed, we find this case similar to Georgia Electric Co., 
    595 F.2d 309
     (5th
    Cir. 1979), where a utility company was cited for willfully violating a highway
    construction safety standard that prohibits the operation of a crane within ten feet
    of an energized electrical line. A worker was electrocuted when the steel light pole
    that he was attempting to erect came into contact with an energized line. The
    company’s foreman, knowing of the hazard involved, nonetheless allowed the
    worker’s crew to attempt to erect the pole. The Court, noting that the employer
    had failed to take steps to acquaint its supervisory personnel with the requirements
    of the standard, despite knowing of “its obligation to conform to the Act,” affirmed
    the citation, finding that the employer was indifferent to OSHA’s requirements and
    exhibited “disregard for the safety of its employees.” 
    Id. at 319-20
    . The Court
    rejected the employer’s argument that, by instructing its employees to use their
    “common sense” and not get “too close” to the energized lines, it established
    adequate work safety rules. 
    Id. at 320
    ; see Central Soya De Puerto Rico, Inc., v.
    Secretary of Labor, 
    653 F.2d 38
    , 39-40 (1st Cir. 1981) (holding that employer that
    failed to repair a highly corroded grain tower, from which an employee fell, a
    highly dangerous condition known to supervisory personnel, consciously
    disregarded OSHA’s requirements and showed “[a] degree of indifference to the
    requirements of the law” sufficient to establish a willful violation); Kent Nowlin
    13
    Constr. Co., Inc. v. Occupational Safety & Health Review Comm’n, 
    648 F.2d 1278
    , 1280-81 (10th Cir. 1981) (holding that, where employer’s supervisory
    personnel knew of hazard involved in using crane within ten feet of electrical lines,
    but nonetheless decided to proceed and subject its employees to danger of
    electrocution, employer acted with plain indifference to OSHA’s
    requirements); F.X. Messina Constr. Corp v. Occupational Safety & Health
    Review Comm’n, 
    505 F.2d 701
    , 702 (1st Cir. 1974) (holding that employer that
    had “obvious” knowledge of trenching standard’s requirements but failed to
    comply, making “private determination that . . . [failing to comply] would not be
    dangerous,” acted with intentional disregard of OSHA’s requirements). Cf.
    Morello Bros. Constr., 
    809 F.2d at 164
     (holding that employer’s failure to comply
    fully with applicable safety standards did not create such an “obviously unsafe”
    hazard to experienced employees working on roof within sight of a safety monitor
    as to constitute a willful violation).
    Substantial evidence supports the finding that raising the rebar to the north
    side of the building was not appreciably less dangerous than raising it to the east
    side. Indeed, as the ALJ noted, it was not particularly safe to use the hole in the
    floor method, as the 20-foot rebar could still have come in contact with the
    energized lines. Moreover, J.A.M., which had no written safety program and
    14
    initially required its employees to raise rebar on what it now recognizes as the
    more dangerous east side, did not make even a minimal effort to address the
    problem until ironworking foreman James Stowe refused to endanger the workers
    further and halted work on that side of the structure. Even at that point, J.A.M.
    expressed no concern about safety. Indeed, Diaz was so angry about the work
    stoppage that he threatened not to pay Stowe if he did not go back to work. Stowe
    was ultimately dismissed for his efforts.
    Furthermore, J.A.M.’s attempts to place the blame for its willfulness on the
    ironworkers, particularly on Larry Williams, is contrary both to the law and to the
    ALJ’s findings of fact. Even if J.A.M. believed, in good faith, that the ironworkers
    had the skill and the experience to avoid the electrical hazards, that would not
    excuse J.A.M.’s intentional disregard of and plain indifference to its own duties
    under OSHA. See Trinity Indus., 
    16 F.3d at 1153
    ; Georgia Elec. Co., 595 F.2d at
    320. See also Western Waterproofing Co., Inc. v. Marshall, 
    576 F.2d 139
    , 143
    (8th Cir. 1978) (rejecting employer’s argument that willfulness was negated
    because it unilaterally determined that compliance was not necessary). J.A.M.’s
    arguments about what the ironworkers themselves believed about the danger are
    simply irrelevant. As the ALJ pointed out, J.A.M.’s alleged reliance on the
    ironworkers’ “experience” was misplaced because “[w]hile these employees may
    15
    be experienced ironworkers, they are not necessarily experienced in work near
    power lines and electricity.” See Floyd S. Pike Elec. Contractor, Inc. v.
    Occupational Safety & Health Review Comm’n, 
    576 F.2d 72
    , 76-77 (5th Cir.
    1978) (holding that employer improperly relied on “inexperienced working
    foreman [] in charge of an inexperienced crew” to comply with trenching
    regulation, thus defeating employee misconduct defense); see also Mineral Indus.
    & Heavy Constr. Group v. Occupational Safety & Health Review Comm’n, 
    639 F.2d 1289
    , 1295 (5th Cir. Unit A March 1981) (rejecting employee misconduct
    defense based on employer’s “common sense” approach to safety); Georgia Elec.
    Co., 595 F.2d at 320 (same).
    In light of J.A.M.’s clear acknowledgment of the extreme danger posed by
    the exposed lines to its employees, evidence of its cavalier attitude to the
    possibility of serious injury, including death, and its failure to provide a safe
    method of delivering or handling rebar to avoid contact with the energized lines,
    we conclude that substantial evidence supports the conclusion of the ALJ that
    J.A.M. acted willfully under either the “intentional disregard” or “plain
    16
    indifference” prongs of the Georgia Electric Co. standard. Accordingly, we DENY
    J.A.M.’s petition for review and AFFIRM the Commission’s decision.5
    AFFIRMED.
    5
    Finally, J.A.M. argues that because the citation did not charge it with violating the
    standard on November 5th or 6th, and the Secretary was prohibited by the statute’s six-month
    statute of limitations from citing it for these days, the ALJ’s decision is not in accordance with
    the law. See 
    29 U.S.C. § 658
    (c) (“No citation may be issued under this section after the
    expiration of six months following the occurrence of any violation.”). These claims are without
    merit. The citation specifically alleged that “[o]n or about 11/07/97,” J.A.M. willfully violated
    the standard, and the record plainly reflects that OSHA’s citation was issued on April 29, 1998,
    well before the expiration of the limitations period.
    17
    POLLAK, District Judge, dissenting:
    I agree with the court’s careful legal analysis, and I substantially concur in
    the court’s narration of the facts. But I do not agree with the court’s application of
    the law to the facts. Therefore I respectfully dissent.
    The Occupational Safety and Health Act (OSHA) contemplates three grades
    of violations of the statute and its attendant regulations – “willful”; “serious”; and
    “not . . . of a serious nature.” 
    29 U.S.C. § 666
    . An employer who is found by the
    Occupational Safety and Health Review Commission (“the Commission”), after a
    hearing before an administrative law judge, to have committed a violation which is
    “not . . . of a serious nature” may be assessed a civil penalty in an amount not to
    exceed $7,000. 
    29 U.S.C. § 666
     (c). The maximum civil penalty for a “serious”
    violation is also $7,000, but assessment of a civil penalty of some amount is
    obligatory. 
    29 U.S.C. § 666
    (b). A “willful” violation calls for a civil penalty of
    from $5,000 to $70,000. 29 U.S. C. § 666(a). When a “willful” violation causes
    the death of an employee, the employer is subject to criminal prosecution, with a
    maximum sentence of six months’ incarceration and a fine of $10,000, or a
    maximum sentence of one year’s incarceration and a $20,000 fine for a subsequent
    conviction. 
    29 U.S.C. § 666
    (e).
    18
    OSHA defines a “serious” violation as one where “there is a substantial
    probability that death or serious physical harm could result . . . unless the employer
    did not, and could not with the exercise of reasonable diligence, know of the
    presence of the violation.” 
    29 U.S.C. § 666
    (k). The statute does not define the
    more flagrant “willful” violation. As the court points out, in this Circuit the
    governing case law definition of “willful” violation is that articulated for the Fifth
    Circuit by Judge Brown in Georgia Electric Co. v. Marshall, 
    595 F.2d 309
    , 318 (5th
    Cir. 1979) and carried forward in Reich v. Trinity Industries, Inc., 
    16 F.3d 1149
    ,
    1152 (11th Cir. 1994): – “intentional disregard of, or plain indifference to, OSHA
    requirements.”
    The court today sustains the conclusion of an administrative law judge,
    adopted by the Commission, that in the case at bar the employer, J.A.M.,
    committed a “willful” violation of OSHA. The record made before the
    administrative law judge establishes that J.A.M.’s supervision of the work site was
    bumbling and, at times, incoherent. The record unquestionably supports a
    determination that J.A.M. violated the applicable OSHA regulation – and would, in
    my judgment, support a characterization of the violation as “serious.” But I do not
    find in that record substantial evidence of “intentional disregard for, or plain
    19
    indifference to, OSHA requirements” – the hallmark of a “willful” violation. For
    this reason I part company with my colleagues.
    The OSHA regulation that J.A.M. was charged with violating is 
    29 C.F.R. § 1926.416
    (a)(1):
    No employer shall permit an employee to work in such
    proximity to any part of an electric power circuit that the
    employee could contact the electric power circuit in the
    course of work, unless the employee is protected against
    electric shock by deenergizing the circuit and grounding
    it or by guarding it effectively by insulation or other
    means.
    The regulation is one which calls on the employer to exercise judgment: – is
    the work site one in which an employee must “work in such proximity to any part
    of an electric power circuit that the employee could contact the electric power
    circuit in the course of work”?
    On November 5, 1997, J.A.M.’s ironworkers began moving bars of rebar
    from the first to the third story of the three-story structure. What made this a
    problematic enterprise was the presence, along the structure’s east wall, of
    energized power lines strung about ten feet above the third story. To avoid the
    power lines, the rebar was, as the court explains, “pass[ed] . . . through a second-
    floor window and then through a four-foot hole located between the second and
    third floor. The rebar was passed up length-wise, and was angled at a forty-five
    20
    degree angle opposite from the building’s east wall and away from the energized
    lines, although it was tall enough that it could have touched the energized lines had
    it been stood up and/or leaned toward the east wall.”
    The operation having apparently been completed on November 5, the hole
    was closed.
    The next day – November 6 – when it became apparent that more rebar was
    required on the third floor, the movement of rebar resumed. But this time, with the
    hole closed, the rebar was, as the court explains, “rais[ed] to the third floor along
    the outside of the east wall” – a very risky maneuver which, as the court notes,
    came to a halt when “the ironworkers’ union foreman . . . was informed by an
    electrician of the severe danger of working along the east wall close to the
    energized lines.” This precipitated a meeting of management officials and union
    representatives. There is, to be sure, disagreement as to what course of action was
    agreed upon – passing rebar up the north wall (the J.A.M. understanding) or
    cutting a new hole between the second and third floors (the union understanding).
    The one thing that the disagreement plainly establishes is that management and
    union alike recognized that the rebar which was still to be raised to the third floor
    should not be passed up the east wall. Carlos Diaz, J.A.M.’s job superintendent,
    then ordered a carpenter to take rebar that was stacked on the east side of the
    21
    structure and move it to the north side (presumably, in anticipation of its being
    raised to the third floor).
    On the following day – November 7 – the raising of rebar to the third floor
    was to resume. Diaz directed foreman Larry Williams to pass rebar up the north
    side. But Williams did not follow Diaz’s directions. Williams and his crew raised
    rebar up the east side. And Williams died.
    The court “find[s] this case similar to Georgia Electric Co.” – the case in
    which the Fifth Circuit defined OSHA willfulness as “intentional disregard of, or
    plain indifference to, OSHA requirements.” In arguing that the two cases are
    “similar” the court points out that in Georgia Electric:
    a utility company was cited for willfully violating a
    highway construction safety standard that prohibits the
    operation of a crane within ten feet of an energized
    electrical line. A worker was electrocuted when the steel
    light pole that he was attempting to erect came into
    contact with an energized line. The company’s foreman,
    knowing of the hazard involved, nonetheless allowed the
    worker’s crew to attempt to erect the pole. The Court,
    noting that the employer had failed to take steps to
    acquaint its supervisory personnel with the requirements
    of the standard, despite knowing of “its obligation to
    conform to the act,” affirmed the citation, finding that the
    employer was indifferent to OSHA’s requirements and
    exhibited “disregard for the safety of its employees.” 
    Id. at 319-20
    . The Court rejected the employer’s argument
    that, by instructing its employees to use their “common
    sense” and not get “too close” to the energized lines, it
    established adequate work safety rules.
    22
    Georgia Electric’s definition of willfulness is binding law for this court.
    And the finding of willfulness sustained by Judge Brown and his colleagues was,
    so it seems to me, a proper application of that binding legal rule to the facts of
    record in Georgia Electric. But, with all respect, I do not think the facts yielding a
    finding of willfulness in Georgia Electric are “similar” to the facts in the case at
    bar. In the case at bar the applicable OSHA regulation – 
    29 C.F.R. § 1926.416
    (a)(1) – is a generalized admonition:
    No employer shall permit an employee to work in such
    proximity to any part of an electric power circuit that the
    employee could contact the electric power circuit in the
    course of work . . .
    By contrast, the OSHA regulation at issue in Georgia Electric – 
    29 C.F.R. § 1926.550
    (a)(15) – was a flat directive as to the space to be maintained between
    power lines and machinery or equipment:
    For lines rated 50 kV. or below, minimum clearance
    between the lines and any part of the crane or load shall
    be 10 feet . . .
    There was no room for doubt as to the meaning, or the applicability to any given
    scenario, of the regulation. However, as Judge Brown explained, “[d]espite its
    awareness of its obligation to conform to the Act and regulations promulgated
    thereunder, the Company never made any effort to acquaint its supervisory
    personnel with the OSHA standards. Not one employee with responsibility for the
    23
    Highway No. 82 project was aware of the minimum distance requirements of §
    1926.550(a)(15).” 595 F.2d at 319. Given the substantial difference between the
    applicable regulations, together with the fact that in the case at bar the tragic death
    of Larry Williams resulted from his ignoring the employer’s express instructions, I
    suggest that what the court perceives as similarity between the willfulness issue in
    Georgia Electric and the willfulness issue in the case at bar is illusory. There is, in
    my judgment, less similarity here than meets the eye.
    However, there is another aspect of Georgia Electric which seems to me
    remarkably similar to the present case. In carefully detailing the events that
    preceded the fatal accident of July 10, 1974 at issue in Georgia Electric, Judge
    Brown pointed out that the OSHA regulation the company was found to have
    violated – 
    29 C.F.R. § 1926.550
    (a)(15) – was included in “a copy of the OSHA
    safety and health regulations for the construction industry,” 595 F.2d at 313, that
    had been furnished to the employer in April of 1974, approximately three months
    before the July 10, 1974 accident. Judge Brown explained:
    The material was supplied as part of an OSHA
    investigation of an electrocution that occurred on April 8,
    1974, at a Company work site in Albany, Georgia. As a
    result of that investigation, the Company was cited for
    allowing an employee to work too near an electric power
    circuit that had not been de-energized or otherwise
    guarded. The Company was charged with a serious
    24
    violation of [29] C.F.R. § 1926.400(c)(1). The charge
    was uncontested, and the Company paid a $500 fine.
    Id.
    
    29 C.F.R. § 1926.400
    (c)(1) was the lineal ancestor of 
    29 C.F.R. § 1926.416
    (a)(1), the regulation at issue in the present case.6 In the context of
    Georgia Pacific, the Commission adjudged the employer guilty of a “serious”
    violation for, as Judge Brown put it, “allowing an employee to work too near an
    electric power circuit” – a “serious” violation that led to an employee’s
    electrocution. In the case we are considering today, the record amply supports a
    finding that on November 6, 1997 (the second of the three days, when rebar was
    “rais[ed] to the third floor along the outside of the east wall”) the employer (to
    transpose to the present case Judge Brown’s words in Georgia Electric) “allow[ed
    employees] to work too near an electric power circuit” – a finding, which,
    compatibly with the Commission’s assessment of Georgia Pacific’s April 8, 1974
    misconduct, would surely warrant citation for a “serious” violation.7 On
    6
    In addition to the renumbering, there were certain non-substantive verbal changes. The
    former regulation directed that “[n]o employer shall permit an employee to work in such
    proximity to any part of an electric power circuit that he may contact the same in the course of
    his work unless the employee is protected against electric shock by deenergizing the circuit and
    grounding it or by guarding it by effective insulation or other means.” The present regulation
    has been rendered genderly neutral through (a) the substitution of “the employee” for “he” and
    (b) the deletion of “his;” in addition, “could” has replaced “may,” and “by effective insulation or
    other means” has become “effectively by insulation or other means.”
    7
    Lest there be any misunderstanding, I am not arguing that the Fifth Circuit endorsed the
    Commission’s determination that this earlier dereliction was a “serious” (rather than a “willful”)
    violation. As Judge Brown’s opinion makes plain, Georgia Electric did not challenge the
    25
    November 7, 1997 – the next day – foreman Larry Williams was electrocuted when
    he had his crew pass rebar up the east wall rather than the north wall – but this
    tragic event came about because Williams acted in direct contravention of his
    employer’s instructions. I suppose it is arguable that J.A.M.’s failure to monitor
    the November 7 conduct sufficiently to prevent the tragedy could be deemed a
    “serious” violation. But not a “willful” one.
    I conclude that the evidence before the administrative law judge does not
    support a finding that J.A.M.’s violation of 
    29 C.F.R. § 1926.416
    (a)(1) was
    “willful.” I am fortified in this conclusion by the fact that, pursuant to the statute, a
    “willful” OSHA violation that causes the death of an employee gives rise to
    criminal liability. 
    29 U.S.C. § 666
    (e). I am confident that the Congress which
    crafted OSHA would have viewed J.A.M.’s makeshift methods of raising the rebar
    with strong disapproval. But I see no reason to suppose that the OSHA Congress
    would have contemplated that its strong disapproval could be ratcheted up, via an
    administrative assessment affirmed by a federal court, to a level of malfeasance
    that constitutes a crime.
    Accordingly, I dissent.
    “serious” citation, so its correctness was not before the Fifth Circuit.
    26
    

Document Info

Docket Number: 99-11917

Citation Numbers: 233 F.3d 1350

Filed Date: 11/22/2000

Precedential Status: Precedential

Modified Date: 12/21/2014

Authorities (18)

F. X. Messina Construction Corp. v. Occupational Safety and ... , 505 F.2d 701 ( 1974 )

William E. Brock, Secretary of Labor v. Morello Brothers ... , 809 F.2d 161 ( 1987 )

9-osh-casbna-1709-1981-oshd-cch-p-25379-kent-nowlin , 648 F.2d 1278 ( 1981 )

Larry Bonner v. City of Prichard, Alabama , 661 F.2d 1206 ( 1981 )

Robert B. Reich, United States Secretary of Labor v. ... , 16 F.3d 1149 ( 1994 )

9-osh-casbna-1998-1981-oshd-cch-p-25522-central-soya-de , 653 F.2d 38 ( 1981 )

mineral-industries-heavy-construction-group-brown-root-inc-v , 639 F.2d 1289 ( 1981 )

ann-mclaughlin-secretary-of-labor-v-union-oil-company-of-california , 869 F.2d 1039 ( 1989 )

6-osh-casbna-1781-1978-oshd-cch-p-22855-floyd-s-pike , 576 F.2d 72 ( 1978 )

Niemand Industries, Inc. v. Reich , 73 F.3d 1083 ( 1996 )

7-osh-casbna-1343-1979-oshd-cch-p-23567-georgia-electric , 595 F.2d 309 ( 1979 )

54-socsecrepser-261-unemplinsrep-cch-p-15796b-11-fla-l-weekly , 125 F.3d 1436 ( 1997 )

Harry J. Williams v. United States Department of ... , 781 F.2d 1573 ( 1986 )

u-s-pipe-and-foundry-company-v-charles-webb-and-corda-webb-and , 595 F.2d 264 ( 1979 )

Valdak Corporation v. Occupational Safety and Health Review ... , 73 F.3d 1466 ( 1996 )

United States v. Ladish Malting Co. , 135 F.3d 484 ( 1998 )

6-osh-casbna-1550-1978-oshd-cch-p-22731-western-waterproofing , 576 F.2d 139 ( 1978 )

Richardson v. Perales , 91 S. Ct. 1420 ( 1971 )

View All Authorities »