H & R Yacht Service, Inc. v. 133' Broward Motor Vessel , 356 F. App'x 268 ( 2009 )


Menu:
  •                                                           [DO NOT PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE ELEVENTH CIRCUIT
    ________________________                  FILED
    U.S. COURT OF APPEALS
    No. 09-13415                ELEVENTH CIRCUIT
    DECEMBER 9, 2009
    Non-Argument Calendar
    THOMAS K. KAHN
    ________________________
    CLERK
    D. C. Docket No. 08-61450-CV-WPD
    H & R YACHT SERVICE, INC.,
    a Florida Corporation,
    Plaintiff-Appellee,
    versus
    133' BROWARD MOTOR VESSEL,
    "Serque" Ex "Providence" her
    engines tackle, appurtenances,
    spares and equipment appertaining
    whether onboard or not, In rem,
    Defendant-Appellant.
    ________________________
    Appeal from the United States District Court
    for the Southern District of Florida
    _________________________
    (December 9, 2009)
    Before BLACK, PRYOR and KRAVITCH, Circuit Judges.
    PER CURIAM:
    The 133-foot vessel Broward Motor Yacht “Serque” (“Serque”) appeals an
    in rem judgment against it on a claim brought by H&R Yacht Service (“H&R”), a
    boat repair company located in Fort Lauderdale, Florida. We affirm the district
    court’s judgment.
    I. Background
    In December 2007, H&R entered an oral contract with Elana Charters, LLC
    (“Elana”), the owner of the Serque, to fully service the Serque. Although the
    parties dispute the nature of the agreed-upon terms, the record indicates that H&R
    provided an estimate prior to the job and that Elana closely supervised H&R’s
    work. During the course of the job, H&R was forced to repeat some of its work.
    H&R claims that this additional work was necessary because of damage by other
    contractors on the job. The Serque claims these alterations were the result of
    H&R’s faulty work.
    At the conclusion of H&R’s work, H&R submitted a bill for $84,942.90.
    After Elana refused to pay, H&R brought an in rem claim against the Serque.
    H&R claimed that its repairs automatically entitled it to a maritime lien on the
    2
    Serque under 
    46 U.S.C. § 31342.1
     H&R’s action sought to foreclose on this lien to
    recover the cost of the repairs. After a bench trial, the district court entered a
    judgment in rem against the Serque and awarded H&R $88,153.74 in damages and
    prejudgment interest. The Serque appeals.
    II. Discussion
    We review the legal conclusions of a district court sitting in admiralty de
    novo and its findings of fact for clear error. Flagship Marine Services, Inc. v.
    Belcher Towing Co., 
    966 F.2d 602
    , 604 (11th Cir. 1992).
    The Serque argues that H&R is not entitled to a maritime lien on the Serque
    because H&R charged an unreasonable amount for its repairs. Sweet Pea Marine,
    Ltd. v. APJ Marine, Inc., 
    411 F.3d 1242
    , 1249 (11th Cir. 2005) (holding that, to
    establish a maritime lien, the plaintiff must prove that it charged a reasonable
    price). The Serque argues that H&R charged a flat rate of $75 per hour for each of
    its employees regardless of the nature of the work performed and level of skill
    required. The Serque also argues that H&R should not be entitled to be paid for
    work which had to be repeated. It argues that H&R is only entitled to recover
    under a theory of quantum meruit, entitling H&R to the reasonable amount for
    labor and materials furnished.
    1
    One who furnishes “necessaries” to a vessel on the order of the owner is automatically
    entitled to a maritime lien for such repairs. Necessaries include repairs. 
    46 U.S.C. § 31301
    (4).
    3
    For a maritime lien, a reasonable price is one that is “customary” and “in
    accord with prevailing charges for the work done and the materials furnished.”
    Sweet Pea, 
    411 F.3d at 1249
    . Here, the district court found that H&R quoted a rate
    of $75 per hour, even though the industry standard was $80-90 per hour, prior to
    the work. Furthermore, the district court also found that H&R billed the Serque for
    781 hours, even though it was later determined that H&R may have actually
    worked 808 hours. Finally, the district court found that H&R’s bill reflected a 25
    percent markup on parts, rather than the industry standard of 30 percent. The
    Serque has not disputed these findings, so we cannot say that they are clearly
    erroneous. Thus, we conclude that the price was reasonable and that the district
    court was correct in entering a judgment against the Serque.
    Finally, the Serque argues that H&R breached its warranty of workmanlike
    service because certain repairs had to be repeated. The district court found,
    however, that Elana requested some of this duplication and other work was
    complicated by Elana’s inadequate explanation of the blueprints to H&R. Because
    the Serque has not disputed these findings, we find no clear error and no breach of
    this warranty. Furthermore, even if H&R had breached this warranty, the Serque
    has cited no authority for the proposition that such a “breach” can defeat H&R’s
    4
    maritime lien.
    Accordingly, the judgment of the district court is
    AFFIRMED.
    5
    

Document Info

Docket Number: 09-13415

Citation Numbers: 356 F. App'x 268

Judges: Black, Kravttch, Per Curiam, Pryor

Filed Date: 12/9/2009

Precedential Status: Non-Precedential

Modified Date: 8/2/2023