NDC Construction Company v. Secretary of Labor, United States Department of Labor ( 2022 )


Menu:
  • USCA11 Case: 20-14484       Date Filed: 06/30/2022   Page: 1 of 21
    [DO NOT PUBLISH]
    In the
    United States Court of Appeals
    For the Eleventh Circuit
    ____________________
    No. 20-14484
    ____________________
    NDC CONSTRUCTION COMPANY,
    Petitioner,
    versus
    SECRETARY OF LABOR, UNITED STATES DEPARTMENT OF
    LABOR,
    Respondent.
    ____________________
    Petition for Review of a Decision of the
    Occupational Safety and Health Review Commission
    Agency No. 17-1689
    ____________________
    USCA11 Case: 20-14484       Date Filed: 06/30/2022    Page: 2 of 21
    2                      Opinion of the Court               20-14484
    Before LAGOA, BRASHER, and TJOFLAT, Circuit Judges.
    PER CURIAM:
    NDC Construction Company (“NDC”) seeks review of an
    administrative law judge’s (“ALJ”) decision imposing a penalty for
    violations of 
    29 C.F.R. § 1926.501
    (b)(13), an Occupational Safety
    and Health Administration (“OSHA”) regulation concerning fall
    protection at construction worksites. Following a bench trial, the
    ALJ found that NDC failed to exercise reasonable diligence. The
    ALJ’s decision became a final order of the Occupational Safety and
    Health Review Commission (the “Commission”) when the Com-
    mission denied NDC’s petition for discretionary review. NDC
    now seeks review of the ALJ’s decision from this Court.
    In its petition for review of the final order, NDC primarily
    asserts two arguments. First, NDC contends that it cannot be held
    liable for violating § 1926.501(b)(13) because NDC was held liable
    under OSHA’s multi-employer citation policy, which, according to
    NDC, is an unpromulgated agency rule or the product of imper-
    missible agency policymaking, or both. Second, NDC asserts that
    the ALJ erred in finding that NDC did not exercise reasonable dili-
    gence.
    After careful review, and with the benefit of oral argument,
    we conclude that, under 
    29 U.S.C. § 660
    (a), NDC is barred from
    raising its arguments concerning the validity of OSHA’s multi-em-
    ployer citation policy and that the ALJ’s findings are supported by
    USCA11 Case: 20-14484       Date Filed: 06/30/2022   Page: 3 of 21
    20-14484              Opinion of the Court                       3
    substantial evidence. Accordingly, we deny NDC’s petition for re-
    view and affirm the ALJ’s decision.
    I.     FACTUAL BACKGROUND
    A. The Construction Worksite and NDC’s Role as General
    Contractor
    NDC was the general contractor for a multiacre residential
    construction project in Bradenton, Florida. The construction pro-
    ject involved building fourteen structures, including multifamily
    residential housing units.
    As the general contractor, NDC managed the construction
    worksite. While NDC had employees stationed at the worksite, its
    employees did not perform the construction work. Instead, NDC’s
    employees managed the construction process and oversaw various
    subcontractors who performed the construction work.
    NDC oversaw between thirty and forty subcontractors at
    the height of construction. NDC neither trained subcontractors in
    connection with worksite safety nor conducted its own safety-spe-
    cific inspections. But NDC’s onsite employees conducted daily
    worksite-walkthroughs and notified subcontractors, either by
    phone or in writing, of worksite safety violations they happened to
    observe.
    Under the agreements NDC had with its subcontractors, the
    subcontractors were required to provide NDC with a copy of their
    safety manuals and to provide documentation of weekly safety
    meetings. NDC also had the contractual authority to require
    USCA11 Case: 20-14484            Date Filed: 06/30/2022         Page: 4 of 21
    4                          Opinion of the Court                      20-14484
    subcontractors to abate safety violations within seventy-two hours
    and NDC could “make the necessary corrections” if a safety hazard
    was not abated by its subcontractors. And NDC could remove sub-
    contractors and sub-subcontractors, as well as the subcontractors’
    employees, from the worksite for safety violations.
    B. OSHA Inspections
    On April 5, 2017, two OSHA inspectors visited the worksite.
    Upon entering the worksite, the OSHA inspectors observed four
    fall-protection-related safety violations—i.e., violations of 
    29 C.F.R. § 1926.501
    (b)(13). 1 The OSHA inspectors later learned that
    these safety violations involved workers that were employed by
    NDC’s subcontractors or sub-subcontractors.
    The first safety violation involved a worker who was “doing
    sheeting work”—i.e., laying pieces of plywood—on the roof of a
    building without “any kind of protection against a fall.” The sec-
    ond safety violation involved a worker on a stepladder, on an open-
    sided balcony without safety railings, who was not wearing a “per-
    sonal fall arrest system.” The third safety violation involved two
    workers on a one-story building that were working without fall
    protection systems in place. And the fourth safety violation in-
    volved a worker, who was not wearing a harness and who was not
    1 As relevant to this case, under 
    29 C.F.R. § 1926.501
    (b)(13), “[e]ach employee
    engaged in residential construction activities 6 feet (1.8 m) or more above
    lower levels shall be protected by guardrail systems, safety net system, or per-
    sonal fall arrest system. . . .”
    USCA11 Case: 20-14484        Date Filed: 06/30/2022      Page: 5 of 21
    20-14484                Opinion of the Court                         5
    “tied off,” on a third-story balcony that did not have a safety railing
    or safety net.
    The OSHA inspectors reported these observations to NDC’s
    on-site superintendent and manager, and an NDC employee in-
    formed NDC’s subcontractors that OSHA was on-site. The OSHA
    inspectors then walked around the worksite a second time and
    spoke to various employees. During their second walkthrough, the
    OSHA inspectors did not observe any additional safety hazards.
    While many workers were no longer working during OSHA’s sub-
    sequent walkthrough, the workers the OSHA inspectors did ob-
    serve were either not working on elevated surfaces or were wear-
    ing personal fall protection equipment. But, in talking to workers
    at the worksite, the OSHA inspectors learned that workers “had
    been working all day without fall protection” and “at no time did
    they use fall protection.”
    The OSHA inspectors returned to the worksite on April 7,
    2017. They did not observe any safety violations during that in-
    spection.
    II.    PROCEDURAL BACKGROUND
    After further investigation, OSHA issued a citation and noti-
    fication of penalty to NDC for the four violations of 
    29 C.F.R. § 1926.501
    (b)(13) that the OSHA inspectors observed. The citation
    proposed a penalty of $8,873. Because NDC had failed to submit
    documents to demonstrate that the violations were abated, OSHA
    also requested proof of abatement. NDC contested the citation,
    USCA11 Case: 20-14484       Date Filed: 06/30/2022     Page: 6 of 21
    6                      Opinion of the Court                20-14484
    and the case proceeded to trial to determine whether NDC was li-
    able for the four safety violations.
    A. Trial
    At trial, NDC stated that “[u]nlike many, many contractors
    that have come before this Commission . . . , [NDC is] not asking
    you to destroy the multi-employer work site doctrine.” Instead,
    NDC asserted that it acted in a reasonably diligent manner and
    abated the relevant safety violations.
    NDC’s employees testified that they notified their subcon-
    tractors when they observed safety hazards at the worksite and
    held meetings with subcontractors to discuss “any safety issues that
    were brought up.” NDC’s employees further testified that all of
    the safety hazards that they observed were immediately abated by
    their subcontractors, including the safety violations OSHA identi-
    fied. But NDC’s employees also testified that they did not always
    follow up with subcontractors to ensure that safety hazards were,
    in fact, abated. And NDC did not maintain records indicating that
    the [s]afety violations were abated.
    Evidence admitted at trial suggested that the fall-protection-
    related safety violations arose before, and persisted after, the
    OSHA inspections. For example, on several occasions leading up
    to the OSHA inspections, NDC notified its subcontractors that bal-
    conies did not have safety rails. And at a meeting held on April 11,
    2017, approximately one week after the OSHA inspections, NDC
    USCA11 Case: 20-14484           Date Filed: 06/30/2022       Page: 7 of 21
    20-14484                  Opinion of the Court                             7
    notified its subcontractors that “[s]afety rails continue[d] to be in-
    sufficient.”
    B. The ALJ’s Decision
    Following trial, the ALJ issued its decision and held that
    NDC violated § 1926(b)(13) and that NDC could be held liable, as
    a controlling employer under OSHA’s multi-employer citation pol-
    icy, because NDC exercised supervisory control over the worksite
    and its subcontractors. In so doing, the ALJ held that NDC had, at
    least, constructive knowledge of the violations OSHA identified be-
    cause the violations were “open and obvious.” And the ALJ held
    that NDC did not exercise reasonable diligence. 2
    As relevant to this case, the ALJ found that NDC did not take
    reasonable measures to prevent safety violations at the worksite.
    The ALJ noted that NDC was aware that certain subcontractors
    frequently violated safety standards and that one of its subcontrac-
    tors committed “repeated fall protection violations.” The ALJ fur-
    ther found that NDC did not monitor or discipline these subcon-
    tractors to prevent additional fall protection violations. And the
    ALJ found that NDC never confirmed whether subcontractor em-
    ployees “received fall protection training, or whether they had fall
    2 NDC, in its petition for review, does not contest that it was a controlling
    employer or that it had knowledge of the safety violations OSHA cited. In-
    stead, NDC’s arguments pertain to whether it can be held liable as a control-
    ling employer, because controlling employer liability is a by-product of
    OSHA’s multi-employer citation policy, and whether NDC exercised reason-
    able diligence.
    USCA11 Case: 20-14484       Date Filed: 06/30/2022   Page: 8 of 21
    8                     Opinion of the Court                20-14484
    protection equipment” and that NDC largely relied on its subcon-
    tractors to comply with OSHA safety standards despite knowledge
    of their repeated violations.
    The ALJ also found that NDC could have detected the rele-
    vant safety violations, which were “open and obvious,” and that
    “NDC did not ensure that fall hazards were abated immediately or
    whether or not hazards were resolved at all.” While the ALJ
    acknowledged that NDC conducted walkthroughs and notified
    subcontractors of safety violations, the ALJ found that NDC did not
    “believe that looking for safety issues was its responsibility” and
    that, contrary to NDC’s assertions, certain fall hazards were not
    abated. The ALJ further found that NDC did not keep track of
    safety violations or abatement efforts.
    The ALJ concluded that NDC did not effectively monitor for
    safety violations and that NDC’s abatement efforts were ineffec-
    tive. Based on these findings, the ALJ imposed a penalty of $7,986.
    C. NDC’s Petition for Commission Review
    NDC filed a petition for discretionary review under 
    29 C.F.R. § 2200.91
    . Specifically, NDC asked the Commission to re-
    view five issues concerning whether the ALJ: (1) erred in finding
    that NDC did not exercise reasonable diligence; (2) disincentivized
    other general contractors from engaging in reasonable efforts to
    ensure worksite safety; (3) erred in concluding that NDC was re-
    quired to implement a “graduated system of enforcement” and dis-
    cipline its subcontractors; (4) impermissibly expanded the duty
    USCA11 Case: 20-14484          Date Filed: 06/30/2022    Page: 9 of 21
    20-14484                Opinion of the Court                         9
    owed by general contractors under OSHA’s multi-employer cita-
    tion policy; and (5) erred in holding that OSHA did not need to
    define “what would have constituted compliance for NDC.” But
    NDC did not challenge the validity of OSHA’s multi-employer
    worksite doctrine in its petition.
    The Commission declined to review the ALJ’s decision.
    Therefore, the ALJ’s decision became a final order of the Commis-
    sion. See 
    29 U.S.C. § 661
    (j). This timely appeal followed.
    III.   STANDARD OF REVIEW
    Commission “decisions are entitled to considerable defer-
    ence on appellate review.” Fluor Daniel v. Occupational Safety &
    Health Rev. Comm’n, 
    295 F.3d 1232
    , 1236 (11th Cir. 2002). “[T]he
    legal determinations of an agency . . . are to be overturned only if
    they are ‘arbitrary, capricious, an abuse of discretion, or otherwise
    not in accordance with [the] law.’” 
    Id.
     (alteration in original) (quot-
    ing 
    5 U.S.C. § 706
    (2)(A)). And, under 
    29 U.S.C. § 660
    (a), “[t]he find-
    ings of the Commission with respect to questions of fact, if sup-
    ported by substantial evidence on the record considered as a whole,
    shall be conclusive.” “Substantial evidence is more than a scintilla
    and is such relevant evidence as a reasonable person would accept
    as adequate to support a conclusion.” J.A.M. Builders, Inc. v. Her-
    man, 
    233 F.3d 1350
    , 1352 (11th Cir. 2000) (quoting Lewis v. Calla-
    han, 
    125 F.3d 1436
    , 1440 (11th Cir.1997)).
    IV.      ANALYSIS
    USCA11 Case: 20-14484          Date Filed: 06/30/2022       Page: 10 of 21
    10                       Opinion of the Court                    20-14484
    On appeal, NDC asserts two arguments. First, NDC asserts
    that it could not be held liable as a controlling employer under
    OSHA’s multi-employer citation policy because the policy is an un-
    promulgated agency rule or the product of impermissible agency
    policymaking, or both. Second, NDC asserts that it exercised rea-
    sonable diligence and that the ALJ failed to consider whether NDC
    reasonably abated the safety violations. We consider NDC’s argu-
    ments in turn.
    A. 
    29 U.S.C. § 660
    (a) and NDC’s Arguments Concerning
    OSHA’s Multi-Employer Citation Policy
    OSHA’s multi-employer citation policy “provides guidance
    to OSHA inspectors as to when it may be appropriate to cite a par-
    ticular employer” for a violation of an OSHA safety standard at a
    worksite with more than one employer. Acosta v. Hensel Phelps
    Constr. Co., 
    909 F.3d 723
    , 737 (5th Cir. 2018) (citing Occupational
    Safety & Health Admin., CPL 02-00-124, Multi-Employer Citation
    Policy (1999)). NDC asserts that the policy is an invalid interpreta-
    tion of 
    29 U.S.C. § 654
    (a)(2) and is the product of impermissible
    agency rulemaking or an unpromulgated legislative rule, or both. 3
    But under 
    29 U.S.C. § 660
    (a), “[n]o objection that has not
    been urged before the Commission shall be considered by the
    3 Under 
    29 U.S.C. § 654
    (a)(2), employers “shall comply with occupational
    safety and health standards promulgated under this chapter,” which include
    standards “reasonably necessary or appropriate to provide safe and healthful
    employment and places of employment.” 
    29 U.S.C. §§ 652
    (8), 654(a)(2).
    USCA11 Case: 20-14484            Date Filed: 06/30/2022          Page: 11 of 21
    20-14484                   Opinion of the Court                                11
    court, unless the failure or neglect to urge such objection shall be
    excused because of extraordinary circumstances.” Section 660(a)
    thereby prevents parties from raising arguments in federal court
    that were not raised before the Commission absent “extraordinary
    circumstances.” Power Plant Div., Brown & Root, Inc. v. Occupa-
    tional Safety & Health Rev. Comm’n, 
    659 F.2d 1291
    , 1295 (5th Cir.
    Unit B 1981) 4 (“[Under] 
    29 U.S.C. § 660
    (a)[,] . . . issues raised for
    the first time in the court of appeals shall not be considered.”), reh’g
    granted and opinion modified, 
    673 F.2d 111
     (5th Cir. Unit B 1982);
    see also Am. Airlines, Inc. v. Sec’y of Labor, 
    578 F.2d 38
    , 41 n.7 (2d
    Cir. 1978) (“The simple answer to the contention that the regula-
    tion was improperly promulgated is that the objection was not
    raised before the Commission. Accordingly, American has waived
    its right to raise it here.”). “[I]n cases where the Commission de-
    clines to review the ALJ decision,” appellate courts have “uni-
    formly held that [they] lack jurisdiction over objections not raised
    in the” petition for discretionary review. Frank Lill & Son, Inc. v.
    Sec’y of Lab., 
    362 F.3d 840
    , 844 (D.C. Cir. 2004) (quoting A.J.
    McNulty & Co. v. Sec’y of Lab., 
    283 F.3d 328
    , 332 (D.C. Cir. 2002)).
    Thus, before we can address the merits of NDC’s argu-
    ments, we must ensure that NDC either raised these arguments in
    4 Decisions issued by Unit B of the former Fifth Circuit are binding precedent
    in the Eleventh Circuit. Stein v. Reynolds Secs., Inc., 
    667 F.2d 33
    , 34 (11th Cir.
    1982).
    USCA11 Case: 20-14484        Date Filed: 06/30/2022     Page: 12 of 21
    12                      Opinion of the Court                 20-14484
    its petition for discretionary review or that NDC’s failure to do so
    was “excused because of extraordinary circumstances.” § 660(a).
    1. Whether NDC Raised its Arguments in its Petition for Dis-
    cretionary Review
    As noted, NDC raised five issues in its petition for discretion-
    ary review. The validity of OSHA’s multi-employer citation policy
    was not one of those five issues. NDC, however, asserts that the
    issue it raised concerning OSHA’s “failure to define what would
    have constituted compliance for NDC under the circumstances and
    how NDC’s conduct was deficient” sufficiently alerted the Com-
    mission that NDC was challenging the validity of the multi-em-
    ployer citation policy. But that argument was specific to the con-
    tours of the duty owed by general contractors—i.e., NDC argued
    that OSHA failed to identify “how often NDC should [have] in-
    sepct[ed] its subcontractors,” the “limits of NDC’s responsibility
    over its subcontractors,” and “what consequences a general con-
    tractor must hand down in order to entitle itself to a defense against
    multi-employer liability.” NDC did not assert that OSHA’s multi-
    employer citation policy was itself invalid or that NDC could not
    be held liable for violating an OSHA standard in its capacity as a
    controlling employer or general contractor.
    Indeed, NDC’s petition did not address OSHA’s interpreta-
    tion of § 654(a)(2) or the procedural validity of the multi-employer
    citation policy. And throughout the proceedings below, NDC
    maintained that it did “not desire to litigate the validity of the mul-
    tiemployer doctrine.” We cannot ignore these assertions and
    USCA11 Case: 20-14484        Date Filed: 06/30/2022     Page: 13 of 21
    20-14484                Opinion of the Court                        13
    interpret the five issues that NDC did raise in a manner that is not
    supported by NDC’s petition. See Power Plant Div., 
    659 F.2d at 1295
     (holding that the Court would not review “[f]undamental le-
    gal questions” not raised before the Commission “particularly . . .
    where, as here, a party has affirmatively misled the Commission as
    to its position on an issue”); see also United States v. Ross, 
    131 F.3d 970
    , 988 (11th Cir. 1997) (“It is ‘a cardinal rule of appellate review
    that a party may not challenge as error a ruling or other trial pro-
    ceeding invited by that party.’” (quoting Crockett v. Uniroyal, Inc.,
    
    772 F.2d 1524
    , 1530 n.4 (11th Cir. 1985))). Therefore, we conclude
    that NDC failed to raise its arguments concerning the validity of
    OSHA’s multi-employer citation policy in its petition for discre-
    tionary review.
    2. Whether NDC’s Failure to Raise its Arguments is Excused
    Because of Extraordinary Circumstances
    Because NDC failed to raise its arguments concerning the
    validity of OSHA’s multi-employer citation policy before the Com-
    mission, we can only review NDC’s arguments if “the failure or
    neglect” was “excused because of extraordinary circumstances.”
    § 660(a). NDC contends that it did not raise arguments concerning
    the validity of the multi-employer citation policy in its petition be-
    cause 
    29 C.F.R. § 2200.91
    (d)— the regulation concerning petitions
    for discretionary review—prevented it from raising these argu-
    ments. Specifically, NDC asserts that “the Commission’s own rules
    of procedure forbid the incorporation of legal memorandum or
    briefs into Petitions for Discretionary Review.”
    USCA11 Case: 20-14484            Date Filed: 06/30/2022          Page: 14 of 21
    14                         Opinion of the Court                        20-14484
    Resolution of this case does not require us to decide whether
    the Commission’s rules of procedure may constitute extraordinary
    circumstances because § 2200.91(d) did not prevent NDC from rais-
    ing its arguments. While NDC is correct that petitions should not
    “incorporate by reference a brief or legal memorandum,”
    § 2200.91(d) only prevents petitioners from relying on a separate
    “brief or legal memorandum” to support an issue or argument.
    NDC was not prohibited from objecting to the legal validity of
    OSHA’s multi-employer citation policy directly in its petition for
    discretionary review. Indeed, § 2200.91(d) directs petitioners to
    “state . . . [w]hether the [ALJ’s] decision raises an important ques-
    tion of law” or whether the “decision is contrary to law.”
    Because NDC has failed to satisfy its burden to show that
    extraordinary circumstances excused its failure to raise them, we
    cannot consider the arguments NDC has made with respect to the
    validity of OSHA’s multi-employer citation policy. 5 See § 660(a);
    see, e.g., L.R. Willson & Sons, Inc. v. Occupational Safety & Health
    5 The National Association of Home Builders and the    Associated General Con-
    tractors of America (together “NAHB”) filed an amicus brief in support of
    NDC. Together with NDC, they have raised strong arguments that OSHA’s
    multi-employer citation policy is invalid. But for the reasons stated in this sec-
    tion, § 660(a) prevents us from considering those arguments in this case.
    NAHB has also asserted that NDC made reasonable efforts, as a con-
    trolling employer, to comply with OSHA’s safety standards. But, as noted in
    the next section of this opinion, we conclude that the ALJ’s findings concern-
    ing reasonable diligence are supported by substantial evidence on the record
    as a whole.
    USCA11 Case: 20-14484       Date Filed: 06/30/2022    Page: 15 of 21
    20-14484               Opinion of the Court                       15
    Rev. Comm’n, 
    134 F.3d 1235
    , 1241 (4th Cir. 1998) (“[Section] 660(a)
    clearly states that, ‘[n]o objection that has not been urged before
    the Commission shall be considered . . . , unless the failure or ne-
    glect to urge such objection shall be excused because of extraordi-
    nary circumstances.’ . . . Therefore, having found no extraordinary
    circumstances to excuse this omission, we hold that the fine cannot
    properly be considered here.” (quoting § 660(a)).
    B. Reasonable Diligence
    Assuming a controlling employer can be held liable for vio-
    lating 
    29 C.F.R. § 1926.501
    (b)(13) under OSHA’s multi-employer
    citation policy—an issue we cannot address in this case pursuant to
    § 660(a)—the parties agree that a controlling employer is “reason-
    ably . . . expected to prevent or detect and abate the violations due
    to its supervisory authority and control over the worksite.” Cen-
    tex-Rooney Constr. Co., 16 OSHC 2127, 
    1994 WL 682931
    , at *2
    (No. 92-0851); accord Suncor Energy (U.S.A.) Inc., 2019
    OSHD 33705, 
    2019 WL 654129
    , at *4 (No. 13-0900) (same). In
    other words, the parties agree that, under the Commission’s prec-
    edents, a controlling employer must exercise reasonable care to ei-
    ther prevent or detect and abate safety violations.
    The ALJ found that NDC did not exercise reasonable care as
    a controlling employer. In this petition for review, NDC asserts
    that there is sufficient evidence of “NDC’s efforts to prevent viola-
    tions” and that its efforts “to abate violations committed by sub-
    tiers were ‘sufficiently persistent,’ realistic, practical and
    USCA11 Case: 20-14484            Date Filed: 06/30/2022          Page: 16 of 21
    16                         Opinion of the Court                        20-14484
    reasonable.” NDC further asserts that the ALJ did not consider
    “whether NDC took reasonable measures to obtain abatement.” 6
    Our analysis of whether the ALJ erred in finding that NDC
    failed to exercise reasonable care proceeds in two steps. First, we
    consider whether NDC exercised reasonable care to prevent the
    safety violations. Second, we consider whether NDC exercised rea-
    sonable care to detect and abate the safety violations. 7
    Under § 660(a), our analysis is specific to whether the ALJ’s
    factual findings, which were adopted by the Commission, “are sup-
    ported by substantial evidence on the record as a whole.” J.A.M.
    Builders, 233 F.3d at 1352 (applying this standard to an ALJ’s deci-
    sion, which became the Commission’s final order after the Com-
    mission declined the petitioner’s request to review); see Fla.
    Lemark Corp. v. Sec’y, U.S. Dep’t of Lab., 634 F. App’x 681, 685 n.
    3 (11th Cir. 2015) (“Because the Commission declined review, the
    6 NDC also asserts that the ALJ erred by transforming the duty NDC owed—
    i.e., NDC was reasonably expected to prevent or detect and abate the viola-
    tions—into a conjunctive obligation, such that NDC was required to prevent
    and detect and abate the violations. NDC further asserts that “[w]hen a con-
    trolling employer has knowledge of a subcontractor’s safety violations,” the
    analysis should focus only on whether the controlling employer took “reason-
    able measures to obtain abatement.” Like NDC’s argument with respect to
    the validity of OSHA’s multi-employer citation policy, NDC failed to raise
    these specific issues in its petition for discretionary review. Therefore, we will
    not address these specific arguments on appeal. See § 660(a).
    7 Contrary  to NDC’s assertion, the ALJ did consider whether NDC abated the
    safety violations.
    USCA11 Case: 20-14484      Date Filed: 06/30/2022     Page: 17 of 21
    20-14484               Opinion of the Court                      17
    ALJ’s order became the final order of the Commission. . . . There-
    fore, we review the ALJ’s decision under the same standards as we
    would a decision issued by the Commission.”). If so, we must af-
    firm the conclusions reached by the ALJ. See Fluor Daniel, 
    295 F.3d at
    1240–41.
    1. Whether NDC Exercised Reasonable Care to Prevent the
    Safety Violations
    The ALJ found that NDC did not exercise reasonable dili-
    gence in preventing safety hazards at the worksite. NDC asserts
    that the ALJ’s findings are not supported by substantial evidence
    because NDC sought to prevent safety violations by monitoring
    the worksite and by immediately “call[ing] . . . any offending sub-
    contractor whenever violations were discovered.”
    We find that the ALJ’s findings are supported by “substantial
    evidence on the record considered as a whole.” § 660(a). NDC’s
    employees testified that they did not specifically monitor for com-
    pliance with safety standards when they walked around the
    worksite. Moreover, the record suggests that NDC observed fall-
    protection-related safety violations “a couple times a week,” and
    the record is devoid of the measures NDC took to prevent those
    violations from occurring.
    While NDC notified subcontractors of the safety violations
    NDC observed, that was not a measure to prevent—i.e., “[t]o an-
    ticipate or act in advance,” Prevent, OXFORD ENGLISH DICTIONARY
    (3d ed. 2007)—a violation from occurring. The record also
    USCA11 Case: 20-14484       Date Filed: 06/30/2022    Page: 18 of 21
    18                     Opinion of the Court                20-14484
    suggests that NDC’s employees discussed safety issues at meetings
    with NDC’s subcontractors. But those discussions appear to have
    concerned safety issues that had already occurred or that were on-
    going, such as the lack of safety rails on balconies. The record does
    not suggest that NDC’s employees discussed preventing future
    safety violations at its meetings with subcontractors.
    Given the quantum of evidence, the ALJ reasonably con-
    cluded that NDC did not exercise reasonable diligence to prevent
    the safety violations before they occurred. See Fluor Daniel, 
    295 F.3d at 1241
     (holding that the Commission’s determination was
    supported by substantial evidence where the petitioner offered “no
    reason” for this Court to hold that the Commission erred and the
    testimony supported the Commission’s findings).
    2. Whether NDC Exercised Reasonable Care to Detect and
    Abate the Safety Violations
    The ALJ also found that NDC could have, but did not, detect
    the safety violations and that NDC “did not ensure that fall hazards
    were abated immediately or whether or not hazards were resolved
    at all.” NDC, however, contends that it acted reasonably because
    NDC’s employees walked around the worksite daily and notified
    its subcontractors of safety violations. NDC further contends that
    the subcontractors immediately abated those violations, including
    the violations the OSHA inspectors observed. But NDC’s argu-
    ments fail for two reasons.
    USCA11 Case: 20-14484       Date Filed: 06/30/2022     Page: 19 of 21
    20-14484               Opinion of the Court                        19
    First, “[t]he substantial evidence standard limits the review-
    ing court from ‘deciding the facts anew, making credibility deter-
    minations, or re-weighing the evidence.’” Stone & Webster Con-
    str., Inc. v. U.S. Dep’t of Lab., 
    684 F.3d 1127
    , 1133 (11th Cir. 2012)
    (quoting Moore v. Barnhart, 
    405 F.3d 1208
    , 1211 (11th Cir. 2005)).
    And here, the ALJ found that NDC’s assertion that the subcontrac-
    tors abated all safety violations immediately, including the cited
    safety violations, was not credible.
    The ALJ’s determination was based on testimony from
    NDC’s employees that, while the employees believed NDC’s sub-
    contractors abated the safety violations they observed, they did not
    confirm whether the subcontractors, in fact, abated the violations.
    Moreover, at trial, NDC did not present evidence to show that the
    safety violations were, in fact, abated, and the evidence that was
    presented showed that the types of fall protection safety violations
    OSHA observed occurred before, and persisted after, the OSHA in-
    spections. In light of this testimony and evidence, we conclude that
    substantial evidence—i.e., “such relevant evidence as a reasonable
    person would accept as adequate,” J.A.M. Builders, 233 F.3d at 1352
    (quoting Lewis, 
    125 F.3d at 1440
    )—supports the ALJ’s credibility
    determination, and we cannot make our own “credibility determi-
    nations, or re-weigh[] the evidence.” Stone & Webster Constr.,
    684 F.3d at 1133; see Fla. Lemark Corp., 634 F. App’x at 686 (“Sub-
    stantial evidence supports the ALJ’s determination that a hazard
    existed at the worksite. . . . The ALJ reasonably relied on Ayub’s
    testimony[, and] . . . “[i]n crediting Ayub’s testimony, the ALJ also
    USCA11 Case: 20-14484           Date Filed: 06/30/2022         Page: 20 of 21
    20                         Opinion of the Court                      20-14484
    reasonably relied on the lack of credible evidence contradicting
    it.”).
    Second, under Commission precedents NDC owed a duty
    to exercise reasonable care to detect and abate the violations under
    the circumstances. See, e.g., Centex-Rooney Constr., 16 OSHC
    2127, 
    1994 WL 682931
    , at *2; Suncor Energy, 2019 OSHD 33705,
    
    2019 WL 654129
    , at *4. Under the circumstances of this case, the
    ALJ found that it was not reasonable for NDC to solely rely on no-
    tifying subcontractors of safety violations in order to abate the vio-
    lations. And that finding is adequately supported by the record.
    The record shows that NDC repeatedly notified its subcon-
    tractors in connection with the same fall protection violations and
    that these violations occurred before, and persisted after, the
    OSHA inspections. The record also demonstrates that the relevant
    safety violations were in plain sight and that NDC had the contrac-
    tual authority to both compel its subcontractors to abate safety vi-
    olations and to abate the violations itself.
    Based on the record, NDC should have known that its sub-
    contractors were not abating the safety violations and that NDC
    reasonably could have, but did not, take any other measures to
    abate them. Cf. Cent. of Ga. R.R. Co. v. Occupational Safety &
    Health Rev. Comm’n, 
    576 F.2d 620
    , 625 (5th Cir. 1978) 8 (“An
    8 In Bonner v. City of Prichard, 
    661 F.2d 1206
    , 1209 (11th Cir. 1981) (en banc),
    we adopted as binding precedent all Fifth Circuit decisions issued before Oc-
    tober 1, 1981.
    USCA11 Case: 20-14484        Date Filed: 06/30/2022     Page: 21 of 21
    20-14484                Opinion of the Court                        21
    employer may carry out its statutory duties through its own private
    arrangements with third parties, but if it does so and if those duties
    are neglected, it is up to the employer to show why he cannot en-
    force the arrangements he has made. If he cannot make this show-
    ing, he must take the consequences. . . .”). Substantial evidence
    therefore supports the ALJ’s conclusion because “the violative con-
    ditions were in plain view, they had existed for a significant period
    of time before the . . . inspection[s], and [NDC] could have ascer-
    tained their existence” and abated them “through the exercise of
    reasonable diligence.” See Centex-Rooney, 16 OSHC 2127, 
    1994 WL 682931
    , at *2; cf. Edwin Taylor Corp. v. U.S. Dep’t of Lab., 814
    F. App’x 498, 502 (11th Cir. 2020) (“Given the quantum of evidence,
    the ALJ could reasonably conclude that [petitioner] willfully vio-
    lated the fall protection regulations[, where] the ALJ relied on tes-
    timony from [petitioner’s] employees showing that they knew of
    the fall protection regulations required for greater than six-foot fall
    risks yet disregarded that risk at its worksite.”). Because the ALJ’s
    findings are supported by substantial evidence, “we are bound by
    the [ALJ’s] determination[s].” See Fluor Daniel, 
    295 F.3d at 1240
    .
    V.     CONCLUSION
    For the reasons stated, we deny NDC’s petition for review
    and affirm the ALJ’s decision.
    PETITION DENIED, AFFIRMED.