National Fire Insurance v. Fortune Construction Co. , 320 F.3d 1260 ( 2003 )


Menu:
  •                                                               [PUBLISH]
    IN THE UNITED STATES COURT OF APPEALS
    FILED
    FOR THE ELEVENTH CIRCUIT          U.S. COURT OF APPEALS
    ELEVENTH CIRCUIT
    _________________________             February 07, 2003
    THOMAS K. KAHN
    No. 01-15124                       CLERK
    _________________________
    D.C. Docket No. 97-02439-CV-JLK
    NATIONAL FIRE INSURANCE COMPANY OF HARTFORD,
    Plaintiff-Counter-
    Defendant-Appellee,
    versus
    FORTUNE CONSTRUCTION COMPANY,
    Defendant-Counter-
    Claimant-Third-Party-
    Plaintiff-Appellant,
    ARKIN CONSTRUCTION COMPANY, INC.,
    Third-Party-Defendant.
    _________________________
    Appeal from the United States District Court
    for the Southern District of Florida
    _________________________
    (February 7, 2003)
    Before TJOFLAT and KRAVITCH, Circuit Judges, and VINSON*, District Judge.
    VINSON, District Judge:
    The primary issue presented by this appeal is whether a surety on construction
    contract performance and payment bonds issued on behalf of a subcontractor has
    superior rights to retained contract balances in the possession of the general contractor
    when the general contractor completed the performance and has unsatisfied claims
    against the defaulting subcontractor.
    I.    BACKGROUND
    This case arises out of two construction projects - - - the Winston Park project
    in Coconut Creek, Florida, and the West Brickell project in Miami, Florida. As
    general contractor on the projects, Fortune Construction Company (“Fortune”) entered
    into two separate subcontracts with Arkin Construction Company (“Arkin”) to build
    the two apartment complexes, the Winston Park Subcontract and the West Brickell
    Subcontract. National Fire Insurance Company (“National Fire”), as surety, issued
    on behalf of Arkin, as principal, performance and payment bonds for the two
    construction projects. The performance bond and payment bond documents for the
    Winston Park project were standard forms issued by the American Institute of
    *
    Honorable Roger Vinson, United States District Judge for the Northern
    District of Florida, sitting by designation.
    2
    Architects.1 The performance bond and payment bond documents for the West
    Brickell project were drafted by National Fire with language that materially differed
    from the Winston Park bonds. Each of the performance bonds and each of the
    payment bonds incorporated the appropriate subcontract between Fortune and Arkin
    by reference.
    During construction of the two projects, Arkin began experiencing financial
    difficulty. National Fire provided financing to Arkin for a short time, but later refused
    to continue to finance Arkin. Both projects were behind schedule by this time.
    Arkin’s financial difficulties prompted Fortune and National Fire to enter into
    negotiations about what to do when Arkin defaulted. There was some discussion
    about National Fire procuring a completion contractor and about the possibility that
    Fortune could complete construction. The West Brickell project was near completion,
    but a substantial amount of work still needed to be done on the Winston Park project.
    Negotiations were still ongoing when, on May 29, 1997, Arkin abandoned both
    construction projects. On June 12, 1997, Fortune declared Arkin in default and
    notified National Fire accordingly.
    A flurry of letters between the attorneys for Fortune and National Fire ensued.
    During this increasingly acrimonious exchange, National Fire contends that it
    1
    AIA Document A311.
    3
    tendered, or offered to tender, a completion contractor. While National Fire asserts
    that Fortune rejected this tender because Fortune wanted to complete construction
    itself, Fortune maintains that the tender was never made. Fortune demanded that
    National Fire perform its obligations under both performance bonds by completing the
    subcontracts. National Fire did not do so. While National Fire made payments to
    payment bond claimants on both projects, both of the construction projects were
    actually completed by Fortune as the general contractor, and Arkin is now a dissolved
    corporation.
    The construction subcontracts between Fortune and Arkin each contained a
    clause obligating Arkin to pay liquidated damages for delays in completing the
    projects. The Winston Park Subcontract provided for liquidated damages of $35 per
    day per incomplete apartment and $1,000 per day for incomplete common areas. The
    West Brickell Subcontract provided for liquidated damages after a specified date of
    $30 per day per incomplete apartment. Due to Arkin’s dilatory performance during
    the Winston Park and West Brickell construction, Fortune invoked these liquidated
    delay damages clauses before Arkin abandoned the projects. By the time Arkin
    defaulted, Arkin owed $1,693,500 in liquidated delay damages on the Winston Park
    project and $93,600 in liquidated delay damages on the West Brickell project. The
    subcontracts also made Arkin responsible for the acts and omissions of its own sub-
    4
    subcontractors. Allied Fire Protection Systems (“Allied”), one of Arkin’s sub-
    subcontractors, failed to pay Davis-Bacon Act wages to its laborers for work
    performed on the West Brickell project, which apparently involved federally
    subsidized housing. Consequently, the Department of Labor jointly charged Fortune,
    Arkin, and Allied a total of $71,126 in back wages attributable to Allied’s improper
    payments, which Fortune paid.
    In addition to the West Brickell Subcontract between Fortune and Arkin, the
    parties entered into a letter agreement dated January 15, 1996 (the same date as the
    West Brickell Subcontract). This letter agreement recognized that the electrical work
    had been excluded from Arkin’s subcontract on the West Brickell project, but that
    Arkin had full responsibility for cost overages if the cost of the electrical work
    exceeded $669,000.      Arkin’s responsibility was “either finding a replacement
    subcontractor” for the electrical work at $669,000 or “issuing a credit change order
    to Fortune” for any amount incurred over and above $669,000.2 However, this letter
    2
    The typed letter, dated January 15, 1996, signed by both Fortune and Arkin,
    stated in pertinent part:
    RE: Construction Contract dated January 15, 1996 for
    West Brickell Apartments
    Dear Mr. Arkin:
    The Schedule of Values attached to the . . .
    contract . . . states that the electrical, elevator and cabinet
    5
    agreement was not listed as part of the contract documents in the West Brickell
    Subcontract, which contained two merger and integration clauses. During the West
    Brickell construction, Fortune’s original electrical subcontractor, Monohan’s Electric
    Co., defaulted and did not complete the electrical work. Arkin failed to provide
    another electrical contractor to complete the project within the fixed $669,000 price.
    In hiring another electrical contractor, Fortune incurred additional costs amounting to
    $404,118.81 in excess of $669,000,3 for which Fortune claims a credit against Arkin.
    trades have been excluded from said contract. The
    agreement between Fortune and Arkin is that even though
    these items have been excluded from said Contract, and
    despite the fact that the contracts with these trades are to be
    signed by Fortune (not Arkin), Arkin takes full
    responsibility for cost overages should the contract amounts
    for each of these trades exceed the following figures: (a)
    electrical – $669,000, (b) elevator – $185,000 and (c)
    cabinets – $110,916.
    This responsibility on the part of Arkin includes, but is not
    limited to, either Arkin finding a replacement subcontractor
    to contract for the specific trade at the above referenced
    amounts, or Arkin issuing a credit change order to Fortune
    for any amounts over and above the above referenced
    figures. . . .
    (R.85, Ex. C.)
    3
    The affidavits of Michael Spetko, the Project Manager for the West Brickell
    project, and Ernesto Gordo, an employee of Fortune who participated in negotiating
    the West Brickell Subcontract with Arkin are in the record. (R.89.) In these affidavits,
    Spetko and Gordo assert that they were involved in negotiating the subcontract and
    that the letter agreement was intended by both Arkin and Fortune to be an integral part
    6
    After Fortune completed the two construction projects, Fortune presented
    National Fire with an accounting of its “performance” costs to complete the Arkin
    subcontracts. National Fire then prepared an accounting of the net remaining contract
    proceeds.4 According to National Fire, the remaining contract proceeds exceeded
    Fortune’s costs of completion. National Fire requested that, according to the terms
    of the bonds, the unpaid contract balances be credited to the respective subcontracts
    and paid to National Fire, as the subrogee of Arkin. Fortune refused to pay National
    Fire the contract balances, claiming that it had superior right to the contract balances
    due to National Fire’s failure to perform on its performance bonds and because of
    Fortune’s right to set off the remaining contract claims Fortune had against Arkin.
    National Fire initiated this civil action against Fortune alleging assignment of Arkin’s
    rights under the subcontracts, equitable subrogation, and breach of the bond contracts.
    Fortune filed a counterclaim against National Fire for failure to perform under the
    performance bonds and failure to make the required payments under the payment
    of the subcontract on the West Brickell project. Gordo added that the letter agreement
    was made an addendum to the subcontract. There is nothing in writing evidencing
    incorporation of the letter agreement.
    4
    Fortune retained possession of certain proceeds from the two subcontracts
    pursuant to retainage and progress-payment provisions of the subcontracts. However,
    the exact amount of contract balances remaining is a matter of dispute between the
    parties.
    7
    bonds with respect to payments for Davis-Bacon Act violations, electrical overages,
    and the liquidated delay damages. Fortune also joined Arkin as a third party
    defendant responsible for the same damages, due to its breach of the two subcontracts.
    Before trial, National Fire filed seven different motions for partial summary
    judgment.5 The district court entered three separate orders granting partial summary
    judgment with respect to several of National Fire’s motions and granted the remainder
    in a pretrial conference order. In its first partial summary judgment order, the district
    court pointed to the language of the “Performance Bond Contract,” although the court
    did not specify which performance bond,6 and held that National Fire had a right to
    equitable subrogation “under the payment and performance bonds.” Thus, the district
    court held that National Fire’s equitable subrogation right to the contract balances was
    superior to Fortune’s right to set off its claims against Arkin under both the payment
    5
    Each motion addressed a discrete legal issue, and five of the motions were
    simultaneously filed. We discourage this practice of unnecessarily filing multiple
    motions for partial summary judgment. While the legal issues in this case are
    complex, combining the various legal issues into a single motion would have helped
    the trial court achieve a broader understanding of the entire case. National Fire’s
    attempt to break this case into little pieces seems to have contributed to the confusion
    below. See also S.D. Fla. Loc. R. 7.1(C)(2).
    6
    As noted earlier, the documents were different for each project. From
    examining the language quoted by the district court, we determine that the court cited
    the Winston Park performance bond. The district court made reference to neither the
    language of the West Brickell performance bond nor either of the two payment bonds.
    8
    and the performance bonds. In its pretrial conference order, the district court
    characterized this ruling as establishing that, to the extent the contract balances
    exceeded Fortune’s reasonable costs to complete construction after Arkin’s default,
    “the excess is to be paid to National Fire up to the amount of National Fire’s payment
    bond expenditures.” (R.67 at 2.) In that same order, the district court held that
    “National Fire had no obligation to complete [construction itself] or to tender [a
    completion contractor], but rather its obligation was to pay the excess of the costs to
    complete the contract over the contract balance, if any.”7 (R.67 at 3.) According to
    the district court, as a matter of law, National Fire’s failure to complete construction
    or to arrange for the completion of construction was not a breach of National Fire’s
    performance bond obligations, and thus Fortune was not entitled to consequential
    damages from National Fire for the costs that Fortune incurred due to Arkin’s default
    under the subject subcontracts.
    In its second order granting National Fire partial summary judgment, the district
    court held that the letter agreement between Fortune and Arkin concerning liability
    for electrical overages was a separate agreement that had not been integrated into the
    contracts on which the bonds had been issued. In its third order granting National Fire
    7
    Again, in making this determination, the district court did not cite any of the
    operative language from any of the bonds in support of its ruling. National Fire’s
    performance obligations materially differed under the two performance bonds.
    9
    partial summary judgment, the district court summarily dismissed with prejudice
    Fortune’s Davis-Bacon wage claim against National Fire, without explanation.
    At trial, the district court directed judgment as a matter of law in favor of
    Fortune on its third party claim against Arkin in the amount of $1,748,150 as to the
    Winston Park project and $432,000 as to the West Brickell project. These amounts
    included the Davis-Bacon wage claim, the electrical overage costs, and the liquidated
    delay damages.8 After this ruling, the only issues that remained for the jury at trial
    were: a determination of the reasonable costs Fortune incurred in completing
    construction,9 the amount of unpaid contract balances at the time of Arkin’s default,
    and the amount of payment bond claims paid by National Fire. The district court
    instructed the jury to this effect, incorporating several of the court’s prior rulings.10
    8
    Because National Fire did not pursue its assignment claim, the district court
    granted Fortune judgment as a matter of law as to that claim.
    9
    The district court instructed the jury that, in making this determination, the jury
    was not to include unreasonable costs Fortune could have avoided, costs related to
    correcting design defects, the liquidated delay damages, costs for electrical overages,
    and the Davis-Bacon wage claims. (R.133 at 9, 10, 12.)
    10
    Specifically, the district court instructed the jury:
    The Court has found, as a matter of law, that National Fire has a right to
    recoup payments it made under the payment bonds from the unpaid
    balance of the subcontract. This right is superior to Fortune’s right to
    apply the unpaid balance of the subcontract to claims that it might have
    against Arkin. The Court having so determined, this issue is not for your
    consideration.
    10
    The jury returned a verdict in favor of National Fire, finding that contract balances
    remained on both projects after the deduction of Fortune’s reasonable costs to
    complete construction,11 and awarded National Fire $255,774 as to the West Brickell
    The Court has also previously determined that, at this juncture, the
    reasonable costs of completing construction are to be credited against
    the contract balance....[T]o the extent the contract balance exceeds the
    reasonable costs of completing construction, the excess is to be paid to
    National Fire up to the amount of National Fire’s payment bond
    expenditures.
    ***
    In determining the reasonable cost to complete the projects, the Court
    has previously determined that certain damages and consequential post
    default costs that may have been incurred by Fortune must not be
    considered part of the reasonable cost to complete the projects and may
    not be assessed against National Fire. These include: (1) delay damages,
    including liquidated damages specified in the Arkin subcontracts; (2)
    damages relating to Fortune’s electrical overage claim; (3) damages
    relating to Fortune’s Davis-Bacon Act claim. While these items may
    constitute proper claims against Arkin, they are not to be considered part
    of the reasonable cost to complete the projects and may not be applied
    against National Fire.
    ***
    In determining whether National Fire breached the performance bond,
    you must accept that the Court has previously determined that National
    Fire had no obligation to complete the project itself or to tender a
    completion contractor. Rather, National Fire’s only performance bond
    obligation is to pay any excess, should it exist, of the reasonable cost to
    complete by Fortune over the contract balance at the time of default by
    Arkin.
    (R.133 at 7, 12, 20).
    11
    Part of the jury’s consideration in awarding National Fire damages was the
    determination of the reasonable costs of completion. However, the verdict form did
    not require the jury to make a specific finding as to the reasonable completion costs
    11
    project and $336,896.28 as to the Winston Park project, to which the district court
    added prejudgment interest. This appeal followed.
    II.   STANDARD OF REVIEW
    The standard of review for a district court’s rulings on motions for summary
    judgment is de novo, and an appellate court is to apply the same legal standards that
    bound the district court. See Sarfati v. Wood Holly Assocs., 
    874 F.2d 1523
    , 1525
    (11th Cir. 1989); Carlin Communication Inc. v. Southern Bell Tel. & Tel. Co., 
    802 F.2d 1352
    , 1356 (11th Cir. 1986). Likewise, de novo review is appropriate when
    addressing the construction of written contracts. See Securities & Exchange Comm’n
    v. Elliott, 
    953 F.2d 1560
    , 1582 (11th Cir. 1992). A jury’s verdict is reviewed for
    sufficiency of the evidence and will not be overturned unless no rational trier of fact
    could have reached the same conclusion based upon the evidence in the record. See
    Quick v. Peoples Bank of Cullman County, 
    993 F.2d 793
    , 798 (11th Cir. 1993).
    A motion for summary judgment should be granted when “the pleadings,
    depositions, answers to interrogatories, and admissions on file, together with the
    affidavits, if any, show that there is no genuine issue as to any material fact and that
    or as to the contract balances remaining before deductions. Instead, the jury merely
    calculated the remaining contract balances after reasonable completion costs and other
    costs were deducted. We have labored to try to infer the completion costs and
    remaining balances in light of the jury’s verdict, but we have been unable to do so.
    12
    the moving party is entitled to judgment as a matter of law.” FED. R. CIV. P. 56(c).
    “[T]he plain language of Rule 56(c) mandates the entry of summary judgment, after
    adequate time for discovery and upon motion, against a party who fails to make a
    showing sufficient to establish the existence of an element essential to that party's
    case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v.
    Catrett, 
    477 U.S. 317
    , 322, 
    106 S. Ct. 2548
    , 2552, 
    91 L. Ed. 2d 265
    , 273 (1986); see
    also Morisky v. Broward County, 
    80 F.3d 445
    , 447 (11th Cir. 1996). On a summary
    judgment motion, the record and all reasonable inferences that can be drawn from it
    must be viewed in the light most favorable to the non-moving party. See Whatley v.
    CNA Ins. Cos., 
    189 F.3d 1310
    , 1313 (11th Cir. 1999).
    We review a district court’s grant of judgment as a matter of law de novo,
    evaluating “whether such sufficient conflicts exist in the evidence to necessitate
    submitting the matter to the jury or whether the evidence is so weighted in favor of
    one side that one party must prevail as a matter of law.” Thosteson v. United States,
    
    304 F.3d 1312
    , 1316 (11th Cir. 2002). The evidence is evaluated in the light most
    favorable to the non-moving party. 
    Id.
    III.   DISCUSSION
    A.    Equitable Subrogation and Entitlement to Set-Off
    13
    The major issue raised in this appeal is National Fire’s equitable subrogation
    rights under the two performance bonds and the two payment bonds. National Fire
    asserts that it possesses a superior right to the unpaid contract balances in light of a
    surety’s recognized right to equitable subrogation.12 The District Court agreed and
    ruled below that National Fire had superior equitable subrogation rights under both
    its payment and its performance bonds. However, Fortune argues that the liquidated
    delay damages, Davis-Bacon Act violations, and the electrical overage costs incurred
    by Arkin should be set off against any unpaid contract balances that National Fire is
    claiming through equitable subrogation.
    Fortune relies primarily upon United States v. Munsey Trust Co., 
    332 U.S. 234
    ,
    236, 
    67 S. Ct. 1599
    , 1600, 
    91 L. Ed. 2022
    , 2023 (1947), in which the Supreme Court
    of the United States addressed the issue of “whether percentages retained pursuant to
    contract by the United States may be subjected to its set-off claims despite the claims
    12
    Fortune contends that equitable subrogation is not appropriate because
    National Fire did not complete, pursuant to its performance bonds, either the West
    Brickell or the Winston Park projects, and issues of fact exist concerning whether
    National Fire paid all of its payment bond obligations. See Affidavit of Michael J.
    Getz (listing unpaid subcontractors, laborers, and materialmen) (R.44.) From the
    record, it appears that one sub-subcontractor, Aurora Plumbing Corp., was pursuing
    a payment claim in state court at the time of trial. (R.149 at 55-59.) National Fire,
    however, represents that it fully satisfied its payment obligations by paying over $1.4
    million in payment bond claims, which amounted to every claim timely submitted.
    For purposes of this appeal, we have assumed that the district court has resolved all
    factual issues with respect to the payment bond claims.
    14
    of a surety who has paid laborers and materialmen.”            In Munsey Trust, the
    Government had entered into six contracts with a contractor to paint and repair certain
    federal buildings. Each contract was subject to both a performance bond and a
    payment bond. Although the contractor completed the work on the contracts so that
    the surety did not have to perform under the performance bond, the surety did pay
    $13,065.93 on payment bond claims made by laborers and materialmen. Under the
    terms of the contracts, the Government had retained percentages of the progress
    payments due to the contractor, amounting to $12,445.03. Subsequently, the same
    contractor submitted a bid to the Government for another project, which the
    Government accepted. However, the contractor failed to enter into a contract for the
    work, and another contractor performed the job at a price considerably higher than the
    bid price accepted by the Government, which resulted in damages to the Government
    in the amount of $6,731.50. In paying over the contract amount that it had retained
    on the other six contracts to the surety, the Government set off the $6,731.50 it
    claimed. The surety protested the set-off and asserted its right to an additional
    $3,568.23. See 
    id.
     at 
    332 U.S. 237
    -39, 
    67 S. Ct. at 1600-01
    .
    With respect to any claims that may have been asserted by the contractor
    against the Government, the Supreme Court recognized that “[t]he government has the
    same right ‘which belongs to every creditor, to apply the unappropriated moneys of
    15
    his debtor, in his hands, in extinguishment of the debts due to him.’” 
    Id. at 239
    , 
    67 S. Ct. at 1602
     (quoting Gratiot v. United States, 
    40 U.S. 336
    , 370, 
    10 L. Ed. 759
     (1841)).
    However, the surety argued that it had subrogation rights superior to both the laborers
    and materialmen to whom the surety had paid and to the Government, the bond
    obligee. In response to this argument, the Supreme Court observed that:
    [O]ne whose own appropriation and payment of money is
    necessary to create a fund for general creditors is not a
    general creditor. He is not compelled to lessen his own
    chance of recovering what is due him by setting up a fund
    undiminished by his claim, so that others may share it with
    him. In fact, he is the best of secured creditors; his security
    is his own justified refusal to pay what he owes until he is
    paid what is due him.
    
    Id.
     at 
    332 U.S. 240
    , 
    67 S. Ct. at 1602
     (emphasis added). Therefore, the Court held that
    the Government could set off the amount it claimed. See also United States ex rel. P.J.
    Keating Co. v. Warren Corp., 
    805 F.2d 449
    , 452 (1st Cir. 1986) (recognizing that
    “Government’s set off right is superior to a claim by a Miller Act surety under its
    payment bond to the same contract earnings”); Marriott Corp. v. Dasto Constr. Co.,
    
    26 F.3d 1057
    , 1070-71 (11th Cir. 1994) (recognizing owner’s right to set-off against
    unpaid contract balance).
    National Fire relies on the subsequent Supreme Court decision in Pearlman v.
    Reliance Ins. Co., 
    371 U.S. 132
    , 
    83 S. Ct. 232
    , 
    9 L. Ed. 2d 190
     (1962), in which the
    Court addressed the issue of whether a government contractor’s trustee in bankruptcy
    16
    or the contractor’s payment bond surety had the superior right to a fund withheld by
    the Government out of earnings due to the contractor. The Court recognized the
    clearly established right of subrogation, which provides that “a surety who pays the
    debt of another is entitled to all the rights of the person he paid to enforce his right to
    be reimbursed,” and held for the surety. 
    Id.,
     
    371 U.S. at 137
    , 
    83 S. Ct. at 235
    . The
    Supreme Court also noted that the Munsey Trust decision had no effect upon its prior
    holdings in Prairie State Bank v. United States, 
    164 U.S. 227
    , 
    17 S. Ct. 142
    , 
    41 L. Ed. 412
     (1896), and Henningsen v. United States Fid. & Guar. Co., 
    208 U.S. 404
    , 
    28 S. Ct. 389
    , 
    52 L. Ed. 547
     (1908), that “there is a security interest in a withheld fund . .
    . to which the surety is subrogated.” Pearlman, 
    supra,
     
    371 U.S. at 137
    , 
    83 S. Ct. at 235
    . The Supreme Court construed Munsey Trust as limited to the narrow proposition
    that “the Government could exercise the well-established common-law right of
    debtors to offset claims of their own against their creditors.” 
    Id. at 140
    , 
    83 S. Ct. at 237
    . Otherwise, the equitable rights of a surety to subrogation were left undisturbed.
    See 
    id.
     Therefore, the surety had a superior right, vis-a-vis the principal’s trustee in
    bankruptcy, to funds held by the Government. Pearlman did not involve the priority
    of rights between a surety and the obligee.
    We note that neither Munsey Trust nor Pearlman attempted to differentiate the
    surety’s equitable subrogation rights on the basis of whether a payment or a
    17
    performance bond obligation had been fulfilled. Under Florida law, which applies
    here, a performance and payment bond surety’s rights to equitable subrogation depend
    upon the nature of the obligation fulfilled by the surety under the terms of the bonds.
    In Transamerica Ins. Co. v. Barnett Bank of Marion County, 
    540 So. 2d 113
    , 115 (Fla.
    1989), the Supreme Court of Florida addressed the issue of “whether a surety’s
    equitable subrogation rights are limited to rights it obtains by standing in the shoes of
    the defaulting contractor. ” In considering this issue, the court observed:
    [T]he surety in cases like this undertakes duties which
    entitle it to step into three sets of shoes. When, on default
    of the contractor, it pays all the bills of the job to date and
    completes the job, it stands in the shoes of the contractor
    insofar as there are receivables due it; in the shoes of
    laborers and material men who have been paid by the surety
    – who may have had liens; and, not least, in the shoes of the
    [obligee], for whom the job was completed.
    
    Id. at 115-16
     (quoting National Shawmut Bank v. New Amsterdam Cas. Co., 
    411 F.2d 843
    , 844-45 (1st Cir. 1969)). Therefore, “[a] surety who performs or pays on behalf
    of a [sic] obligee steps into the shoes of the obligee to the extent of performance or
    payment.” Id. at 116 (emphasis added). Thus, only a performance and payment bond
    surety who pays all of the bills of the job to date and completes the job is entitled to
    stand in the contractor-principal’s shoes and demand payment of unpaid balances from
    the obligee. The surety’s rights, “as subrogee, are not inferior even to the rights of the
    obligee and may be asserted against the obligee.” Id. The Transamerica opinion of
    18
    the Supreme Court of Florida recognizes that a performing surety may assert a right
    to contract proceeds superior to the obligee because, by completing the project, the
    surety conferred a benefit on the obligee and, therefore, stepped into the shoes of the
    obligee. See id. at 115-16. Where a surety pays the claims of laborers and
    materialmen, the surety is only entitled to stand in the shoes of those laborers and
    materialmen who might have had liens, “but for” the surety’s payment. Of course, in
    both cases, the surety’s subrogation rights exist only to the extent of the surety’s
    performance. The fact that the surety in this case, National Fire, did not complete
    performance distinguishes this case from Transamerica.13
    We conclude that National Fire’s right to subrogation is controlled by the
    rationale of the former Fifth Circuit’s decision in Trinity Universal Ins. Co. v. United
    States, 
    382 F.2d 317
     (5th Cir. 1967).14 In Trinity Universal, the former Fifth Circuit
    addressed “whether, when a Miller Act surety completes a defaulted contract pursuant
    13
    “‘Subrogation rights place a party . . . in the legal position of one who has
    been paid money because of the acts of a third party. Thus, the subrogee ‘stands in
    the shoes’ of the subrogor and is entitled to all of the rights of its subrogor, but also
    suffers all of the liabilities to which the subrogor would be subject.’” Cleary Bros.
    Constr. Co. v. Upper Keys Marine Constr., Inc., 
    526 So. 2d 116
    , 117 (Fla. 3d DCA
    1988) (quoting Allstate Ins. Co. v. Metropolitan Dade County, 
    436 So. 2d 976
    , 978
    (Fla. 3d DCA 1983)).
    14
    The Eleventh Circuit has adopted as precedent decisions of the former Fifth
    Circuit rendered prior to October 1, 1981. See Bonner v. Prichard, 
    661 F.2d 1206
    (11th Cir.1981).
    19
    to its performance bond, the government may set off taxes owed by the contractor
    against the surety’s claim to the fund retained by the government to insure
    performance.” Id. at 318. Finding that there was no right to set-off, the former Fifth
    Circuit recognized that, in Munsey Trust, the rights of the surety were limited to those
    of subrogee of the contractor because the surety had only performed under a payment
    bond. Id. at 319. Having made payments pursuant to its payment bond, the surety in
    Munsey Trust became a creditor of the Government with respect to the funds retained
    by the Government, and the Government could exercise the well-established common
    law right to set-off claims against its creditors. Id. at 319-20.
    However, the former Fifth Circuit noted that, “[a] different situation occurs
    when the surety completes the performance of a contract. The surety is not only a
    subrogee of the contractor, and therefore a creditor, but also a subrogee of the
    government and entitled to any rights the government has to the retained funds.” Id.
    at 320. The distinction between a surety’s rights when performing under a payment
    bond or a performance bond is important. When a surety completes the project itself
    or pays the excess completion costs pursuant to the performance bond, the surety
    confers a benefit upon the obligee, whether the obligee is the Government or a private
    entity. That benefit relieves the obligee of the burden of completing the construction.
    In such circumstances, an implicit agreement exists that the surety has a right to all
    20
    retained funds and any remaining progress sums, and the obligee does not possess a
    right to set-off.15 See id. at 320-21; see also Aetna Cas. & Surety Co. v. United States,
    
    435 F.2d 1082
    , 1083-84 (5th Cir. 1970) (finding that surety’s payments made under
    performance bond were not subject to set-off).
    Courts often fail to address the distinction between a surety’s right to
    subrogation when the surety makes payments under a payment bond, as compared to
    the surety’s rights when it performs its performance bond obligations. The payment
    bond surety, who stands in the shoes of laborers and materialmen, normally has
    priority with respect to remaining contract balances because those laborers and
    materialmen would have high priority liens against the property under state law.
    15
    In Dependable Ins. Co. v. United States, 
    846 F.2d 65
     (Fed. Cir. 1988), the
    Federal Circuit also recognized that a surety’s subrogation rights, with respect to set-
    offs asserted by the Government, vary depending upon whether the surety performed
    under a performance bond or a payment bond. In that case, the surety acknowledged
    that, under Munsey Trust, “the government’s right to retained contract proceeds are
    generally superior to those of a payment bond surety.” 
    Id. at 67
    . The Federal Circuit
    further explained why performing performance bond sureties have superior rights to
    the obligee, while payment bond sureties do not:
    [W]hen a surety finances completion of a project, it confers
    a benefit upon the government by relieving it of the task of
    completing performance itself. It therefore becomes
    subrogated not only to the rights of the prime contractor but
    to those of the government. Accordingly, a completing
    performance bond surety has the right to accumulated
    contract proceeds free from setoff by the government.
    
    Id. at 67
    .
    21
    Under Florida law, construction liens of laborers and materialmen have priority over
    all subsequently recorded encumbrances on the owner’s property. 
    Fla. Stat. § 713.07
    (3) (1997). Of course, the payment bond surety’s subrogation is limited to
    proper payments made to valid lien claimants. Likewise, the performance bond surety
    who actually performs stands in the principal’s shoes and can demand payment of the
    remaining contract balances. Further, such a performance bond surety’s rights to
    contract balances are superior to the obligee’s and any claims the obligee may have
    against the principal. Where, as in this case, the surety makes payments under the
    payment bonds, but does not fulfill its performance bond obligations, this distinction
    is critical to an equitable prioritization of rights, particularly where it is the obligee
    who performs in the face of the surety’s possible breach of the performance bond.
    The rationale of Trinity Universal controls the respective rights of National Fire
    and Fortune to any retained contract balances in Fortune’s possession. To further
    analyze the surety’s subrogation rights, it is necessary to differentiate between what
    claims are covered by each of the respective bonds. Since National Fire did not
    complete construction under its performance bonds, it has acquired equitable
    subrogation rights only with respect to its payment bonds. The district court erred to
    the extent that it granted summary judgment for National Fire on its claim of equitable
    subrogation arising out of the performance bonds. Further, the extent of National
    22
    Fire’s subrogation under the payment bonds to Fortune is limited to the amount of the
    valid claims National Fire properly paid on a particular project after Fortune’s
    reasonable costs to complete construction on the project are deducted from the
    remaining contract balances.
    Our holding that National Fire is not entitled to equitable subrogation for any
    performance bond related claims is also based upon our conclusion that the district
    court erred in its partial summary judgment ruling that National Fire had no obligation
    under the performance bonds for either project to complete construction itself or to
    arrange for the completion of construction.16 Such a ruling would have been correct
    if the bonds were indemnity-type, but it is undisputed in the record that the
    performance bonds in this case were not merely indemnity bonds. The touchstone of
    any right to subrogation under a performance bond is actual and full performance of
    16
    National Fire could not, as the district court ruled, simply “do nothing” and
    pay for any excess construction costs. As noted in one treatise:
    The seductive enticement of the ‘do nothing’ option to the
    surety is avoiding the immediate cost of completion, but
    this course of action remains advantageous only if the
    surety is correct in its analysis that it has no liability to the
    obligee....Some bond forms remove the surety’s ‘do
    nothing’ option. These instruments require the surety to
    act. If the surety believes it has a defense, it may reserve its
    rights and litigate -- but it must perform.
    Phil Bruner & Patrick O’Connor, 4 BRUNER & O’CONNOR ON CONSTRUCTION LAW
    § 12:82 n.5 (2002), WL BOCL § 12:82.
    23
    the bond’s obligations. RESTATEMENT (THIRD) OF SURETYSHIP & GUARANTY § 27
    (1995). The language of the two performance bonds plainly contravenes the district
    court’s ruling. The Winston Park performance bond provided that:
    Whenever [Arkin] shall be, and declared by [Fortune] to be
    in default under the [Winston Park Subcontract], [Fortune]
    having performed [Fortune’s] obligations thereunder,
    [National Fire] may promptly remedy the default, or shall
    promptly
    1) Complete the [Winston Park Subcontract] in accordance
    with its terms and conditions, or
    2) Obtain a bid or bids for completing the [Winston Park
    Subcontract] in accordance with its terms and conditions,
    and upon determination by [National Fire] of the lowest
    responsible bidder, or if [Fortune] elects, upon
    determination by [Fortune] and [National Fire] jointly of
    the lowest responsible bidder, arrange for a contract
    between such bidder and [Fortune], and make available as
    Work progresses...sufficient funds to pay the cost of
    completion less the balance of the contract price; but not
    exceeding, including other costs and damages for which
    [National Fire] may be liable hereunder, the amount [of the
    bond].
    Under the terms of this bond, when Arkin was declared in default, National Fire had
    three options: (1) it could remedy the default; (2) it could complete construction itself;
    or (3) it could arrange for the completion of construction by selecting, either by itself
    or jointly with Fortune, a completion contractor and by making funds available to the
    completion contractor for completion costs in excess of the contract price. National
    24
    Fire could not, as the district court held, merely ignore Fortune’s demands that
    National Fire perform, force Fortune to complete construction, and then pay Fortune
    for reasonable costs in excess of the contract price. The express terms of the Winston
    Park performance bond placed the burden of performance on National Fire. Because
    National Fire did not perform, it is not entitled to subrogation with respect to the
    Winston Park performance bond.
    The district court also erred in applying the same analysis to National Fire’s
    West Brickell performance bond obligation as to the Winston Park performance bond
    obligation.    Unlike the Winston Park performance bond, the West Brickell
    performance bond’s terms potentially contemplated completion of construction by
    Fortune. The West Brickell performance bond stated:
    Whenever [Arkin] shall be, and be declared by [Fortune] to
    be in default under the subcontract, [Fortune] having
    performed [Fortune’s] obligations thereunder:
    (1) [National Fire] may promptly remedy the default
    subject to the provisions of paragraph 3 herein; or
    (2) [Fortune] after reasonable notice to [National Fire] may,
    or [National Fire] upon demand of [Fortune] may arrange
    for the performance of [Arkin’s] obligation under the
    subcontract subject to the provisions of paragraph 3 herein;
    (3) The balance of the subcontract price ... shall be credited
    against the reasonable cost of completing performance of
    the subcontract. If completed by [Fortune], and the
    reasonable cost exceeds the balance of the subcontract
    25
    price, [National Fire] shall pay to [Fortune] such excess,
    but in no event shall the aggregate liability of [National
    Fire] exceed the amount of this bond.
    (Emphasis added).
    Under this provision, National Fire also had three alternatives: (1) it could remedy the
    default; (2) if Fortune provided National Fire reasonable notice that Fortune wished
    to arrange for completion, it could allow Fortune to arrange for the completion of
    construction; or (3) if Fortune demanded that National Fire arrange for completion of
    construction, it could arrange for completion of construction itself. According to the
    evidence in the record (and construing the record in the light most favorable to
    Fortune since it appears to be a genuine factual dispute), Fortune did not wish to
    complete construction of the West Brickell project itself after Arkin defaulted.
    Instead, Fortune demanded that National Fire arrange for completion of construction
    of the West Brickell project, and National Fire refused to do so. Paragraph three of
    the West Brickell performance bond does contemplate the possibility that Fortune
    could have completed the subcontract itself. However, this contingency would only
    occur if, under the second alternative, Fortune sought to complete construction itself
    or, under the third alternative, National Fire arranged for Fortune to complete
    construction. In either of these cases, Fortune (not National Fire) could choose
    whether Fortune would voluntarily complete construction. Because it appears
    National Fire did not perform, it is not entitled to subrogation with respect to the West
    26
    Brickell performance bond.
    We also find that disputed issues of material fact exist in the record about
    whether National Fire’s failure to perform amounted to a breach of its performance
    bond obligations, as described above. National Fire claims it appropriately tendered
    a completion contractor and that Fortune refused this tender. (Aff. of Raymond
    Lemming, R.27 at 4-5.) Fortune claims a completion contractor was never tendered
    despite its demands. (Aff. of Michael Getz, R.44 at 2.) This obvious factual conflict
    was presented to the district court in the parties’ arguments on National Fire’s motions
    for partial summary judgment. The only way the district court avoided confronting
    this conflict was by erroneously ruling that, as a matter of law and without reference
    to the language of the performance bonds, National Fire had no obligation to tender
    a completion contractor or to complete performance itself. Summary judgment on
    Fortune’s breach of contract claim against National Fire was improper and we remand
    for further proceedings on this issue.17
    B.     Fortune’s Setoff Claims
    Having concluded that National Fire is only entitled to equitable subrogation
    17
    Determination of the factual dispute about whether National Fire actually
    breached the performance bonds is unnecessary to our ruling on National Fire’s claim
    of equitable subrogation. It is undisputed that National Fire did not, in fact, complete
    construction, and for that reason National Fire cannot claim subrogation under the
    performance bonds.
    27
    with respect to valid payments made under its payment bonds, and that Fortune is
    entitled to a setoff for all items encompassed within the scope of the performance
    bonds, we now must consider the specific claims for which Fortune seeks setoff.
    1.     Liquidated Delay Damages
    Fortune contends that National Fire is responsible for liquidated delay damages
    that had accrued prior to Arkin’s default due to Arkin’s failure to timely perform on
    both projects. Although Fortune obtained judgment as a matter of law against Arkin
    for these damages, Fortune seeks to set these damages off against the retained contract
    balances. Fortune also argues that National Fire is contractually liable for these
    damages because the bonds incorporated by reference the underlying subcontracts
    which expressly provided for delay damages. However, National Fire denies any
    responsibility for delay damages, arguing that such damages are unrelated to the
    completion of the bonded construction projects and that the performance bonds do not
    expressly recognize liability for delay damages.
    We look to Florida law to see what a surety’s obligations are in the
    circumstances of this case. As a general proposition, the true performance bond
    requires a surety to guarantee the performance through completion of the underlying
    contract. See Federal Ins. Co. v. Southwest Fla. Retirement Ctr., Inc., 
    707 So. 2d 1119
    , 1121 (Fla. 1998). However, in American Home Assurance Co. v. Larkin
    28
    General Hospital, Ltd., 
    593 So. 2d 195
     (Fla. 1992), the Supreme Court of Florida held
    that “a surety cannot be held liable for delay damages due to the contractor’s default
    unless the bond specifically provides coverage for delay damages.” 
    Id.
     
    593 So. 2d at 196
     (footnote omitted).      In Larkin General Hospital, the contractor had not
    substantially completed the project by the target date, but the owner did not declare
    the contractor in default. Nearly eighteen months later, after a dispute arose between
    the owner and contractor, the owner declared the contractor in default and notified the
    surety. The surety elected not to complete performance and the owner used another
    contractor to complete the job. In the owner’s action against the surety for breach of
    the performance bond, the trial court included in its damage award the owner’s
    consequential delay damages for the contractor’s tardy performance. Importantly for
    purposes of our analysis, there was no liquidated or other type of damages provision
    in the underlying contract. The Larkin General Hospital court noted:
    [t]he purpose of a performance bond is to guarantee the
    completion of the contract upon default by the contractor.
    Ordinarily a performance bond only ensures the completion
    of the contract. The surety agrees to complete the
    construction or to pay the obligee the reasonable costs of
    completion if the contractor defaults.
    
    Id. at 198
     (citations omitted). Although a surety’s liability is coextensive with that of
    the principal, “the surety’s liability for damages is limited by the terms of the bond.”
    
    Id.
     Therefore, the Supreme Court of Florida found that “[t]he language in the
    29
    performance bond, construed together with the purpose of the bond, clearly explains
    that the performance bond merely guaranteed the completion of the construction
    contract and nothing more.” 
    Id.
     (emphasis added); see also Mycon Constr. Corp. v.
    Board of Regents, 
    755 So. 2d 154
    , 155 (4th DCA 2000) (“Because the performance
    bond contains no provision for damages for delay, the surety cannot be held liable for
    such damages.”). However, unlike the performance bond in Larkin General Hospital,
    the bonds at issue in this case expressly incorporated the subcontracts, which, in turn,
    do expressly provide for liquidated delay damages.
    Larkin General Hospital could possibly be interpreted to mean that a
    performance bond surety cannot be held liable for, or denied subrogation for, delay
    damages, whether liquidated or unliquidated, unless the responsibility for delay
    damages is specified on the face of the performance bond. However, we do not read
    the decision that broadly.18 The “purpose of the bond” must be considered, which
    requires reference to the contract secured by the bond. Where a provision for
    liquidated delay damages is clearly delineated in the underlying contract and
    incorporated by reference into the bond, the surety is on notice of the time element of
    performance and the contractual consequences of failure to timely perform in
    18
    The Supreme Court of Florida has since declined to extend Larkin General
    Hospital beyond delay damages. Federal Ins. Co. v. Southwest Fla. Retirement Ctr.,
    
    707 So. 2d 1119
    , 1121 (Fla. 1998).
    30
    accordance with the contract. Once the liquidated damages accrue, the contractor-
    principal owes a debt to the obligee which is, in effect, a reduction of (or contractual
    off-set to) the contract price. In such event, the obligee becomes the creditor of the
    principal and the performance bond surety should not have superior rights to the
    obligee in the remaining contract balances where liquidated damages have been
    suffered. This is especially true where, as here, the surety does not remedy the
    principal’s delay by performing the surety’s obligations under the performance bond.
    While it is true that the terms of the bonds in this case do not expressly require
    the surety to assume responsibility for delay, “[i]t is the general rule of contract law
    that where a writing expressly refers to and sufficiently describes another document,
    the other document is to be interpreted as part of the writing.” Lord & Son Constr.,
    Inc. v. Roberts Electrical Contractors, Inc., 
    624 So. 2d 376
    , 377 n.2 (Fla. 1st DCA
    1993). Even after Larkin General Hospital, Florida courts have continued to utilize
    the well-established doctrine of incorporation by reference to impose liability on a
    performance bond surety. See DCC Constructors, Inc. v. Randall Mech. Inc., 
    791 So. 2d 575
    , 576-77 (Fla. 5th DCA 2001); Southwest Fla. Retirement Ctr. v. Fed Ins. Co.,
    
    682 So. 2d 1132
    -33 (Fla. 2d DCA 1996), aff’d, 
    707 So. 2d 1119
     (Fla. 1998). The
    “purpose” of the performance bonds was to insure performance in accordance with the
    terms of the respective subcontracts, and those terms plainly include adverse direct
    31
    consequences for delay. Therefore, under the particular facts of this case, the
    unequivocal delay damages provisions of the subcontracts are properly considered
    part of the bonds issued by National Fire because of the incorporation by reference.
    Moreover, the liquidated delay damages are properly considered part of the
    performance of the subcontracts, and it is undisputed that Fortune completed the
    projects, with no performance-related costs being incurred or paid by National Fire.
    Accordingly, Fortune’s claim for set-off of the delay damages is entitled to priority
    over National Fire with respect to any of National Fire’s claims related to the
    performance bonds.
    However, Fortune’s claim for delay damage set-off is not entitled to priority
    over National Fire’s valid payment bond claims. A performing payment bond surety
    stands in the shoes of the laborers and materialmen who might have had liens on the
    property. That right is generally superior to the rights of either the principal or the
    obligee. To the extent of the payment bond claims actually and properly paid,
    National Fire’s right to any unpaid contract balances is superior to Fortune’s
    liquidated delay damages claim.19 We express no opinion about whether National Fire
    may be responsible for delay damages related to Fortune’s breach of contract claims
    19
    It is not clear from the record, but it appears that National Fire’s payment bond
    equitable subrogation claims may exhaust the contract balances retained by Fortune.
    32
    on the performance bonds.
    2.     Davis-Bacon Wages
    The district court granted National Fire partial summary judgment on Fortune’s
    counterclaim for set-off of the amount of back wages Fortune paid due to violations
    of the Davis-Bacon Act by one of Arkin’s subcontractors on the West Brickell Project.
    The Davis-Bacon Act requires laborers on federally funded projects to be paid not less
    than the “prevailing” wages in the locale. See 40 U.S.C. § 276a(a); Walsh v. Schlecht,
    
    429 U.S. 401
    , 411, 
    97 S. Ct. 679
    , 686, 
    50 L. Ed. 2d 641
     (1977). The Act requires that
    “every contract based upon these specifications shall contain a stipulation that the
    contractor or his subcontractor shall pay all mechanics and laborers” the federally
    mandated wages. 40 U.S.C. § 276a(a) (emphasis added). Federal regulations
    applicable to contracts and subcontracts under the Davis-Bacon Act provide, “The
    prime contractor shall be responsible for the compliance by any subcontractor or
    lower tier subcontractor....” 
    29 C.F.R. § 5.5
    (a)(6) (1999).
    We conclude that the Davis-Bacon wages paid by Fortune are part of Fortune’s
    reasonable cost of completion of construction.20 The Davis-Bacon wage claims paid
    20
    One could evaluate Fortune’s Davis-Bacon Act claim, as Fortune suggests, as
    part of National Fire’s performance bond obligation because the West Brickell
    performance bond specifically incorporated by reference the West Brickell
    Subcontract which imposed on Arkin the responsibility for Arkin’s subcontractors’
    acts and omissions. However, we think the Davis-Bacon Act wages are properly
    33
    by Fortune represent wages of laborers on the West Brickell project that should have
    properly been paid as part of the costs of construction. Because of Arkin’s failure to
    properly supervise Allied’s compliance with the Davis-Bacon Act, as Arkin was
    required to do under the West Brickell Subcontract, federal funds payable to Fortune,
    as general contractor, for the West Brickell project sufficient to pay Allied’s
    employees could have been withheld. 40 U.S.C. § 276a-2(a). If the remaining federal
    funds were insufficient to repay the employees, the Davis-Bacon Act gave Allied’s
    employees the right to file a lien on the West Brickell property for the difference. 40
    U.S.C. § 276a-2(b); 
    Fla. Stat. § 713.03
    . We reverse the district court’s grant of partial
    summary judgment to National Fire on this issue and hold that Fortune has a right to
    set off its $71,126.00 Davis-Bacon Act claim against the remaining contract balances
    considered costs of construction because they represent wages that should have
    properly been paid, and were paid, through enforcement by the Department of Labor,
    to the laborers on the West Brickell project. Such wages were a part of the cost of
    completion.
    These wages could also be considered as being within National Fire’s payment
    bond obligation, but because of unique language in the West Brickell payment bond,
    the Davis-Bacon wage claims escape coverage under the bond. National Fire was
    only obligated under the West Brickell payment bond to make payments to valid
    “claimants”, defined as those persons having a “direct contract” with Arkin. The
    Davis-Bacon wage claimants were employees of Allied who did not technically have
    a “direct contract” with Arkin.
    34
    as part of Fortune’s reasonable costs of completion.21
    3.     Electrical Overages
    Fortune also claims the Fortune-Arkin letter agreement gives Fortune a right to
    payment from National Fire for the electrical overages Fortune paid on the West
    Brickell project. However, the West Brickell performance bond cannot be construed
    to cover an agreement that was not identified in the West Brickell Subcontract.22 The
    21
    The parties also have raised an issue concerning whether public policy favors
    holding either the principal contractor or a subcontractor’s surety responsible for
    ensuring payment of Davis-Bacon wages. As discussed earlier, Fortune is required
    by law, as well as by public policy, to ensure compliance by its subcontractors with
    the Davis-Bacon Act. See 40 U.S.C. §276a; 
    29 C.F.R. §5.5
    (a)(6). Fortune satisfied
    this responsibility in the West Brickell Subcontract, which was incorporated by
    National Fire’s performance bond, by requiring Arkin to be responsible for the acts
    and omissions of its subcontractors. We first note that Fortune actually paid the
    Department of Labor’s Davis-Bacon Act claim for restitution. Fortune only seeks
    reimbursement from Arkin and National Fire for their failure to pay the claim when
    requested to do so. Moreover, in the West Brickell performance bond, National Fire
    necessarily accepted the risk that its principal, Arkin, would not fulfill these
    obligations imposed upon it by the Act and its subcontracts. As a result, we conclude
    that the policy behind the Davis-Bacon Act will not be frustrated by allowing Fortune
    to recover this amount as a part of its reasonable costs of completion.
    22
    According to Fortune, the letter agreement dated January 15, 1996, is included
    in the bonded West Brickell Subcontract as evidenced by the fact that National Fire
    admitted its inclusion in its Answer to Fortune’s counterclaim. At oral argument,
    counsel for Fortune indicated that this admission by National Fire had not been
    brought to the trial judge’s attention prior to the granting of summary judgment
    against Fortune. Counsel for National Fire indicated that the admission was
    inadvertent. It appears that National Fire did erroneously admit that this agreement
    was part of the bonded subcontract, but we do not believe that this inadvertent
    admission should control liability for these overage costs when it was not considered
    35
    West Brickell performance bond specifically incorporated the West Brickell
    Subcontract by reference. The list of “Contract Documents” identified in the West
    Brickell Subcontract, which sets forth the documents that are part of the bonded
    subcontract, does not include the letter agreement. The subcontract made no other
    reference to the letter agreement, even though the parties made several other
    handwritten alterations to the subcontract. Merger and integration provisions in both
    the “Contract Documents” section and in Article 17 of the subcontract provide that the
    referenced documents are the entire and complete agreement of the parties. Since the
    bond was issued on the subcontract without reference to the letter agreement, the letter
    agreement is not within the scope of contract work that National Fire agreed to insure
    when it issued the bond. Further, the district court properly rejected Fortune’s offer
    of parol evidence that the letter agreement was part of the subcontract because Fortune
    produced no evidence that National Fire knew of the letter agreement at the time it
    issued the bond. Therefore, Fortune has no right to payment for electrical overages
    from National Fire and the district court properly granted summary judgment in favor
    of National Fire on this issue.
    C.     Remaining Issues
    1.     National Fire’s Breach of Contract Claim
    by the district court.
    36
    Fortune argues that National Fire’s breach of contract claim should not have
    been submitted to the jury because Fortune was not a signatory to the performance
    bonds on which the claim was based. National Fire asserts that the terms of the bond
    obligated Fortune to pay National Fire the balance of the proceeds of the Fortune-
    Arkin subcontract after Fortune completed construction. The terms of the bonds
    plainly contradict National Fire’s argument. Normally, bond agreements create duties
    that run from the surety to the obligee. The obligee is a beneficiary of the agreement
    between surety and principal. While there may possibly be some circumstances under
    which a bond’s terms might impose duties on the obligee, Fortune was merely a
    beneficiary of the performance bonds here.23 As discussed above, bonds are to be
    interpreted according to ordinary principles of contract construction. American Home
    Assurance Co. v. Larkin Gen. Hosp., Ltd., 
    593 So. 2d at 195, 197
     (Fla. 1992);
    Restatement (Third) of Suretyship & Guaranty §§ 17(2), 32(1) (1995).
    In the event that Arkin defaulted, under the terms of both performance bonds
    National Fire could complete construction itself or agree with Fortune to jointly select
    another contractor to finish construction, which could possibly be Fortune if the
    parties so agreed. If the latter occurred, the performance bonds obligated National
    23
    Even if the agreement imposed duties on Fortune, we find it difficult to
    understand how a principal and surety could bind an obligee to perform those duties
    without expressly obtaining the obligee’s consent.
    37
    Fire to make available funds for the completion of construction to the extent the costs
    exceeded the balance of the contract price. This provision does not require Fortune
    to tender to National Fire the remaining contract price if Fortune completed
    construction at a cost less than the contract price. Our interpretation of the bonds’
    terms is consistent with the surety’s traditional duty to complete construction in the
    event of the principal’s default. The purpose of a performance bond is to assure the
    obligee that construction will be completed and that it will not be liable for
    construction costs in excess of the contract price in the event the contractor defaults.
    If National Fire had completed construction, it would have been entitled to payment
    of the contract price, or under equitable subrogation, entitled to the remaining contract
    balances held by Fortune. However, National Fire did not complete construction
    under the bond’s terms. Instead, Fortune completed construction and, luckily for
    National Fire, at a cost less than the contract price. Under no reasonable construction
    of the performance bonds’ terms can a contractual duty be found for Fortune to pay
    National Fire the remaining balance after Fortune completed construction. Therefore,
    the district court erred in allowing National Fire’s breach of contract claim to be
    submitted to the jury. Further, even if (as National Fire claims) Fortune did prevent
    National Fire from completing construction by refusing to accept National Fire’s
    tender of a completion contractor, National Fire could only assert this fact as an
    38
    affirmative defense that its liability under the performance bonds was discharged, not
    as a breach of contract claim against Fortune. See Ins. Co. N. Amer. v. Metro. Dade
    County, 
    705 So. 2d 22
    , 34-35 (Fla. 3d DCA 1997)(obligee’s failure to timely notify
    surety of latent defects discharged surety). See also St. Paul Fire & Marine Ins. Co.
    v. City of Green River, 
    93 F. Supp. 2d 1170
     (D. Wyo. 2000), aff’d, 
    2001 WL 369831
    (10th Cir. 2001).
    2.     Prejudgment Interest
    Finally, we consider the district court’s award of prejudgment interest on the
    jury’s damages verdict in favor of National Fire, retroactive to January 30, 1998.
    Fortune notes that National Fire did not pay one payment bond claimant on the West
    Brickell project until March 19, 2001, and last paid a like claimant on the Winston
    Park project on May 15, 2001. Fortune argues that any equitable subrogation rights
    did not accrue until those dates, when performance under the bonds was complete.
    Therefore, Fortune contends that prejudgment interest should have been calculated
    from those dates on the respective projects, and not over three years earlier.
    We agree. Prejudgment interest in an action for breach of contract is allowable
    from the date the debt is due. See, e.g., Paoli v. Natherson, 
    732 So. 2d 486
    , 488 (Fla.
    2d DCA 1999). Where the judgment liquidates the plaintiff’s damages, the plaintiff
    is entitled, as a matter of law, to prejudgment interest from the date of that loss.
    Argonaut Ins. Co. v. May Plumbing Co., 
    474 So. 2d 212
    , 215 (Fla. 1985). However,
    39
    in this case, National Fire’s right to equitable subrogation under its payment bonds
    with respect to the remaining contract balances did not arise until all of its payment
    bond obligations had been performed. RESTATEMENT (THIRD)           OF   SURETYSHIP &
    GUARANTY § 27 (1995). Further, any entitlement to equitable subrogation on the
    remaining contract balances could not be determined until after Fortune had
    completed the construction. If, as is usually the case, the cost of completion by
    Fortune had equaled or exceeded the contract price, there would have been no
    remaining balances and National Fire would not have been entitled to any equitable
    subrogation with respect to them.       The district court erred when it awarded
    prejudgment interest on National Fire’s equitable subrogation claim prior to the
    completion of its payment bond obligations.
    IV.    CONCLUSION
    For the above reasons, the judgment of the district court is AFFIRMED IN
    PART and REVERSED IN PART and this case is REMANDED for further
    proceedings consistent with this opinion.
    40
    

Document Info

Docket Number: 01-15124

Citation Numbers: 320 F.3d 1260

Judges: Kravitch, Tjoflat, Vinson

Filed Date: 2/7/2003

Precedential Status: Precedential

Modified Date: 8/2/2023

Authorities (28)

The National Shawmut Bank of Boston v. New Amsterdam ... , 411 F.2d 843 ( 1969 )

United States of America, for the Use and Benefit of P.J. ... , 805 F.2d 449 ( 1986 )

Carlin Communication, Inc., Etc. v. Southern Bell Telephone ... , 802 F.2d 1352 ( 1986 )

Peter Thosteson v. United States , 304 F.3d 1312 ( 2002 )

Roger Whatley, Sr. v. Cna Insurance Companies, Baker ... , 189 F.3d 1310 ( 1999 )

Marriott Corporation, Plaintiff-Counter-Defendant-Appellee ... , 26 F.3d 1057 ( 1994 )

Argonaut Ins. Co. v. May Plumbing Co. , 474 So. 2d 212 ( 1985 )

The Aetna Casualty and Surety Company v. United States of ... , 435 F.2d 1082 ( 1970 )

Dependable Insurance Company, Inc. v. The United States , 846 F.2d 65 ( 1988 )

Morisky v. Broward County , 80 F.3d 445 ( 1996 )

Federal Ins. v. SOUTHWEST FLORIDA , 707 So. 2d 1119 ( 1998 )

Transamerica Ins. Co. v. Barnett Bank of Marion County, NA , 540 So. 2d 113 ( 1989 )

fed-sec-l-rep-p-96549-18-ucc-repserv2d-588-securities-and-exchange , 953 F.2d 1560 ( 1992 )

alberto-sarfati-v-wood-holly-associates-a-florida-general-partnership-and , 874 F.2d 1523 ( 1989 )

Lord & Son Const. v. Roberts Elec. Contractors , 624 So. 2d 376 ( 1993 )

DCC CONSTRUCTORS v. Randall Mech., Inc. , 791 So. 2d 575 ( 2001 )

Cleary Brothers Const. Co. v. Upper Keys Marine Const., Inc. , 526 So. 2d 116 ( 1988 )

Allstate Ins. Co. v. Metropolitan Dade County , 436 So. 2d 976 ( 1983 )

Paoli v. Natherson , 732 So. 2d 486 ( 1999 )

American Home Assur. Co. v. Larkin Gen. Hosp., Ltd. , 593 So. 2d 195 ( 1992 )

View All Authorities »