DeFelice Corp. v. Department of Public Utilities , 88 Mass. App. Ct. 544 ( 2015 )


Menu:
  • NOTICE: All slip opinions and orders are subject to formal
    revision and are superseded by the advance sheets and bound
    volumes of the Official Reports. If you find a typographical
    error or other formal error, please notify the Reporter of
    Decisions, Supreme Judicial Court, John Adams Courthouse, 1
    Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
    1030; SJCReporter@sjc.state.ma.us
    14-P-1056                                             Appeals Court
    DeFELICE CORPORATION      vs.   DEPARTMENT OF PUBLIC UTILITIES.
    No. 14-P-1056.
    Suffolk.       May 6, 2015. - October 19, 2015.
    Present:   Berry, Kafker, & Cohen, JJ.
    Department of Public Utilities. "Dig Safe" Statute. Penalty.
    Administrative Law, Adjudicatory proceeding, Findings,
    Agency's interpretation of statute, Evidence, Substantial
    evidence. Evidence, Prima facie evidence.
    Civil action commenced in the Supreme Judicial Court for
    the county of Suffolk on June 18, 2013.
    The case was reported by Gants, J., and the appeal was
    transferred by him to the Appeals Court.
    Ben N. Dunlap (Patrick E. McDonough with him) for the
    plaintiff.
    Bryan F. Bertram, Assistant Attorney General, for the
    defendant.
    COHEN, J.     On November 3, 2010, DeFelice Corporation
    (DeFelice), a contractor engaged in removing and reinstalling
    water mains, struck an underground natural gas service line
    while excavating on Danny Road in the Hyde Park neighborhood of
    2
    Boston.   The ensuing explosion and fire destroyed a single
    family home at 17 Danny Road, and badly damaged other nearby
    residences.1
    The pipeline and engineering safety division (division) of
    the Department of Public Utilities (department) investigated
    DeFelice's operations on Danny Road, as well as its operations
    at a nearby site on Como Road.   As a result of the division's
    investigation, it issued notices of probable violations (NOPVs)
    of the "dig safe" law, G. L. c. 82, §§ 40-40E,2 and associated
    regulations, for each of the two sites.   DeFelice contested the
    NOPVs and, after receiving adverse informal review decisions as
    to both matters, requested a formal adjudicatory hearing.     The
    cases were consolidated, and a hearing was held before a three-
    member panel of department commissioners.   In a thirty-nine page
    decision and order, the department found DeFelice responsible
    for four violations of the dig safe law and imposed the maximum
    statutory penalty allowed for each violation, resulting in a
    total fine of $31,000.
    As to both the Como Road and Danny Road excavations, the
    department determined that DeFelice had violated G. L. c. 82,
    1
    While the property damage was extensive, it does not
    appear that anyone sustained personal injuries.
    2
    The Legislature rewrote the dig safe law in 1998. See St.
    1998, c. 332. Unless otherwise noted, we refer to this version
    of the statute.
    3
    § 40A, which requires an excavator to provide proper advance
    notice of its planned work to the telephone call center of Dig
    Safe System, Inc. (call center), an information clearinghouse
    and communications system statutorily required to be maintained
    by various utility companies.       See G. L. c. 164, § 76D.
    Specifically, the department found that DeFelice's notification
    to the call center failed to provide information needed to
    "accurately define the location" of the excavations as required
    by G. L. c. 82, § 40.       See G. L. c. 82, § 40A.   In addition, the
    department found that, at both sites, DeFelice had failed to use
    "reasonable precautions" while performing work in "close
    proximity" to existing underground utility facilities, as
    required by G. L. c. 82, § 40C.
    Before us is DeFelice's appeal, pursuant to G. L. c. 25,
    § 5.3       DeFelice challenges the department's findings of dig safe
    law violations, but only with respect to the excavation on Danny
    Road.4      DeFelice also challenges the four separate penalties as
    cumulative.       For the following reasons, we affirm.
    3
    In accordance with G. L. c. 25, § 5, DeFelice sought
    judicial review by filing a petition in the Supreme Judicial
    Court for the county of Suffolk. Thereafter, the single justice
    transferred the appeal to this court.
    4
    At the adjudicatory hearing, DeFelice did not contest the
    violations found by the division in connection with the
    excavation on Como Road; nor does DeFelice contest those
    findings on appeal.
    4
    Background.    1.   Regulatory scheme.   The dig safe law,
    G. L. c. 82, §§ 40-40E, and the regulations promulgated
    thereunder, 220 Code Mass. Regs. §§ 99.00-99.12 (2008), are
    designed to protect life and property by requiring excavators to
    comply with notification and safety procedures.     See generally
    Yukna v. Boston Gas Co., 
    1 Mass. App. Ct. 62
    , 66-67 (1973).        An
    excavator must "premark[]" the location of the intended work
    using white paint, stakes, or other suitable white markings.
    G. L. c. 82, § 40A.     See 220 Code Mass. Regs. § 99.02 (2008).
    The excavator then must notify the call center, "accurately"
    describing the excavation location, and indicating the date that
    excavation is expected to begin.    G. L. c. 82, § 40A.   220 Code
    Mass. Regs. § 99.04 (2008).    Except in the case of emergency,
    the excavator cannot proceed with the work until at least
    seventy-two hours after giving notice.    See G. L. c. 82, § 40A;
    220 Code Mass. Regs. § 99.04 (2008).     During this seventy-two
    hour period, the call center notifies the utility companies that
    have underground facilities where the excavation is to occur.
    Using standard, color-coded markings, each such company must
    mark the location of any of its facilities within the
    excavator's premarking zone and an additional fifteen-foot
    safety zone.   See G. L. c. 82, § 40B; 220 Code Mass. Regs.
    § 99.05 (2008).
    5
    At the conclusion of the seventy-two hour period, the
    excavator may begin work, but must use "reasonable precautions"
    when in close proximity to an underground facility in order to
    avoid damaging it.      G. L. c. 82, § 40C.   220 Code Mass. Regs.
    § 99.06(1) (2008).      "[R]easonable precautions" include using
    "non-mechanical means" when excavating near an underground
    facility.    G. L. c. 82, § 40C.    See 220 Code Mass. Regs.
    § 99.06(1) (2008).      Violation of any provision of the dig safe
    statute or regulations is subject to a penalty of $1,000 for a
    first offense, and between $5,000 and $10,000 for any subsequent
    offense within twelve consecutive months.      See G. L. c. 82,
    § 40E; 220 Code Mass. Regs. § 99.12(1) (2008).
    2.      Facts.   We summarize the essential facts established in
    the administrative record.      In 2010, DeFelice began work on a
    public works contract awarded to it by the Boston Water and
    Sewer Commission to replace and repair underground municipal
    water mains and sewer pipes in the Hyde Park, Roslindale, and
    West Roxbury neighborhoods of Boston.      Among other things, the
    project involved the "re-lay" of water mains on Reynold Road in
    Hyde Park, including the junctions where Reynold Road intersects
    with Danny Road and Como Road.
    On October 1, 2010, DeFelice notified the call center of
    its planned excavation work, reporting that it had done its
    premarking and giving the following description of the
    6
    excavation location:     "Starting at and including the
    intersection with Como Road, continuing approximately 500 feet
    north on Reynold Road to and including the intersection with
    Chesterfield Street."    DeFelice also stated that the work would
    be from "street to property lines."     Based upon this
    notification, the call center issued a dig safe ticket to
    DeFelice and relayed the information to NSTAR Gas Company
    (NSTAR), which, at the time, was the owner of the underground
    natural gas facilities in that area.
    DeFelice began working at the junction of Reynold Road and
    Como Road on or about October 22, 2010.     The department found
    that DeFelice excavated parts of Como Road that were sixty-five
    feet away from the intersection with Reynold Road and that,
    therefore, DeFelice had failed to provide the call center with
    an accurate description of the excavation location, in violation
    of G. L. c. 82, § 40A.    The department also found that DeFelice
    had used a jackhammer on Como Road in close proximity to
    unidentified underground gas facilities and, therefore, DeFelice
    had failed to use reasonable precautions in performing the
    excavation, in violation of G. L. c. 82, § 40C.
    DeFelice began working at the junction of Reynold Road and
    Danny Road on November 3, 2010.    This excavation was for a
    connection to a water main drain pipe starting at the corner of
    Reynold Road and Danny Road, and continuing down Danny Road.
    7
    While excavating on Danny Road seventeen feet beyond the
    property line running along the east side of Reynold Road, the
    work crew's backhoe machine struck and punctured a one-inch
    steel gas pipeline that serviced the home at 17 Danny Road.     Gas
    entered the home and ignited, causing the explosion.   At the
    time of the excavation, there were a few NSTAR markings on Danny
    Road beyond the immediate intersection with Reynold Road;
    however, the service pipeline to 17 Danny Road was not marked.
    Prior to the Danny Road gas explosion, DeFelice had
    encountered gas utility pipelines buried beneath Reynold Road
    that either had not been marked or had been improperly marked by
    NSTAR.   This had led DeFelice personnel in the field to make an
    oral request of an NSTAR employee to remark the gas facilities
    in the vicinity of Reynold and Danny Roads.   Also, on November
    2, 2010, DeFelice's general manager, Robert Savage, had
    telephoned the call center, requesting that NSTAR again mark the
    areas to be excavated.   Savage asked that the remarking include
    "all intersections," but did not mention Danny Road by name.      In
    addition, Savage confirmed with the call center operator that
    the excavation location would remain "street to property line";
    Savage did not inform the call center that the excavation would
    extend from any intersection beyond the Reynold Road property
    line.
    8
    The department found that DeFelice had failed to provide
    proper notification to the call center, as required by G. L.
    c. 82, § 40A.    Accordingly, the department also found that
    DeFelice became subject to the final sentence in G. L. c. 82,
    § 40C, which provides that excavating without first giving
    proper notice constitutes prima facie evidence that any
    resulting damage was caused by the excavator's negligence.5    The
    department's findings also rested on DeFelice's use of a
    mechanical excavator at the time it encountered the gas
    pipeline, thus implicating that portion of § 40C requiring that
    "[w]hen excavating in close proximity to the underground
    facilities of any company when such facilities are to be
    exposed, non-mechanical means shall be employed, as necessary,
    to avoid damage in locating such facility."
    Concluding that NSTAR's role, if any, in contributing to
    the explosion did not excuse DeFelice's noncompliance with the
    dig safe law, and that DeFelice had failed to refute the prima
    facie evidence of negligence arising from its notification
    5
    The last sentence of G. L. c. 82, § 40C, provides in full:
    "The making of an excavation without providing the notice
    required by section 40A with respect to any proposed
    excavation which results in any damage to a pipe, main,
    wire or conduit, or its protective coating, shall be prima
    facie evidence in any legal or administrative proceeding
    that such damage was caused by the negligence of such
    person."
    9
    violation, the department found DeFelice in violation of both
    § 40A and § 40C.
    Discussion.    1.    Standard of review.   DeFelice's appeal is
    pursuant to G. L. c. 25, § 5.    The standard of review under that
    statute is "well settled . . . [and the] burden [on an
    appellant] is heavy. . . .    [W]e give deference to the
    department's expertise and experience . . . [and] uphold [the
    department's] decision unless it is based on an error of law,
    unsupported by substantial evidence, unwarranted by facts found
    on the record as submitted, arbitrary and capricious, an abuse
    of discretion, or otherwise not in accordance with law."
    Massachusetts Elec. Co. v. Department of Pub. Util., 
    469 Mass. 553
    , 558-559 (2014), quoting from Bay State Gas Co. v.
    Department of Pub. Util., 
    459 Mass. 807
    , 813-814 (2011).
    2.   Notification.    Pursuant to G. L. c. 82, § 40A, an
    excavator is required to give initial notice setting forth a
    "description of the excavation location."      As defined in G. L.
    c. 82, § 40, such description
    "shall include the name of the city or town, street, way,
    or route number where appropriate, the name of the streets
    at the nearest intersection to the excavation, the number
    of the buildings closest to the excavation or any other
    description, including landmarks, utility pole numbers or
    other information which will accurately define the location
    of the excavation"6 (emphasis supplied).
    6
    The related regulation, 220 Code Mass. Regs. § 99.02
    (2008), is identical to the text of G. L. c. 82, § 40, except
    that the regulation contains the phrase "and/or any other
    10
    A prior version of G. L. c. 82, § 40, as appearing in St. 1983,
    c. 353, required the excavator to describe the location of the
    excavation "reasonably accurate[ly]."   However, in 1998, the
    word "reasonably" was deleted.   See St. 1998, c. 332.   As a
    result of this deletion, excavators became legally required to
    identify excavation locations with precision.
    DeFelice argues that its initial notice, combined with
    Savage's later confirmation that the excavation location would
    include "all intersections," sufficed to inform the call center
    of the location of the planned excavation on Danny Road.     The
    department was entitled to conclude otherwise.   In neither of
    its communications with the call center did DeFelice identify
    Danny Road by name or voice any intention to go beyond the
    property line running alongside Reynold Road as to any
    intersections.   Indeed, in the second communication, Savage
    reiterated that the excavation location was "street to property
    line."   The department's finding that DeFelice excavated on
    Danny Road in an area seventeen feet beyond the property line
    running alongside Reynold Road is supported by substantial
    evidence and forecloses any argument that the shorthand phrase
    "all intersections" sufficed as any "other information" that
    description which will accurately define the excavation
    location" (emphasis supplied). The addition of the conjunctive
    reinforces the need for a full and detailed description.
    11
    "accurately" described the excavation location.    G. L. c. 82,
    § 40.
    DeFelice also points to the premarking that it made at the
    intersection of Danny and Reynold Roads, consisting of painted
    arrows pointing down Danny Road in both directions with
    notations of "50'."   According to DeFelice, this indicated its
    intention to excavate outside the intersection and resulted in
    some markings by NSTAR, albeit ones that were incomplete.
    However, the dig safe statute and regulations place two separate
    requirements on an excavator -- premarking and providing an
    accurate description to the call center.    Satisfying one
    requirement does not excuse the failure to satisfy the other.
    Similarly, DeFelice's oral request to an NSTAR employee did not
    relieve it of its statutory duty to provide the call center with
    complete and accurate notice of the location of the excavation.
    It is a fundamental dictate of the dig safe law that any and all
    requests by an excavator for markings must be made through the
    call center and not by informal requests in the field.7
    3.   Reasonable precautions.   The department found that
    DeFelice failed to use reasonable precautions when it used a
    7
    This has long been the position of the department, see J.
    Derenzo Co., D.P.U. 94-DS-10, at 7 (1997), and the authorities
    cited therein. We accord substantial discretion to an agency
    interpreting the statute it is charged with enforcing. Alliance
    to Protect Nantucket Sound, Inc. v. Energy Facilities Siting
    Bd., 
    457 Mass. 663
    , 681 (2010).
    12
    mechanical excavator (a backhoe) near the gas line at 17 Danny
    Road, in violation of G. L. c. 82, § 40C.   DeFelice admits that
    it used a mechanical excavator, but claims that it relied on the
    fact that there were some NSTAR markings on Danny Road, but none
    in the vicinity of 17 Danny Road.   According to DeFelice, it did
    not know that it was excavating in close proximity to a facility
    and, hence, its use of a mechanical excavator was reasonable.
    DeFelice fails to take into account the provision in G. L.
    c. 82, § 40C, that the "making of an excavation" without proper
    notice constitutes prima facie evidence that any resulting
    damage was caused by the excavator's negligence.    See note 
    5, supra
    .   Because DeFelice failed to give notice that it would be
    excavating farther down Danny Road than just "street to property
    line" at the intersection with Reynold Road, and admittedly
    damaged the natural gas service line at 17 Danny Road, there was
    prima facie evidence of DeFelice's negligence.
    The department was well entitled to conclude in its
    discretion that DeFelice's reliance on NSTAR's markings did not
    refute the prima facie evidence against DeFelice.    DeFelice
    could not assume that markings made outside the dig safe system
    were complete and accurate, and acted at its peril in proceeding
    to work in an unmarked area using mechanical means of
    13
    excavation.8   In these circumstances, the department rationally
    could conclude that DeFelice was in violation of the dig safe
    law by failing to take reasonable precautions in excavating on
    Danny Road.
    4.   Fines.   The Legislature has authorized the department
    to impose a civil fine against any "person or company" found,
    after a hearing, "to have violated any provision" of the dig
    safe law (emphasis supplied).    G. L. c. 82, § 40E.   For a
    "first" offense, the offender shall be fined $1,000, and for
    "any subsequent" violation within twelve months, the offender
    shall be fined "not less than $5,000 nor more than $10,000."
    G. L. 82, § 40E, as amended by St. 2004, c. 149, §§ 133, 134.
    DeFelice takes the position that all violations stemming
    from its October 1, 2010, notification should be viewed as a
    single offense, subject to a single fine.    However, pursuant to
    the plain language of § 40A, a violation of that section arises
    when the excavator "make[s] an excavation" without complying
    with notice requirements.    See G. L. c. 82, § 40A ("No excavator
    . . . shall, except in an emergency, make an excavation . . .
    unless . . . such excavator has . . . given an initial notice to
    8
    There was no requirement that NSTAR mark the area at
    issue. As explained in the department's decision, in order to
    ensure the effectiveness of the dig safe system, the department
    takes the position that utility representatives should not mark
    sites without proper notice.
    14
    the system").   In other words, the failure to give accurate
    notice ripens into a violation when the excavation begins.9     A
    subsequent violation of G. L. c. 82, § 40C (e.g., by using
    mechanical means to excavate in proximity to natural gas
    facilities), will then subject the violator to an additional
    fine.
    Here, there is substantial evidence to support the
    department's finding that four separate, consecutive violations
    occurred.   DeFelice undertook excavation outside of the area
    described to the call center in two different locations, on two
    separate dates.   Thereafter, DeFelice failed to take reasonable
    precautions at each site -- using a jackhammer (at Como Road)
    and a backhoe (at Danny Road) in close proximity to natural gas
    facilities.
    A court will not disturb the sound exercise of discretion
    by an agency of the Commonwealth duly authorized to impose a
    civil penalty or fine except in the most "extraordinary of
    circumstances."   Levy v. Board of Registration & Discipline in
    Med., 
    378 Mass. 519
    , 529 (1979).   This case is not extraordinary
    or exceptional.   The department correctly ruled that each
    9
    DeFelice's reading of the statute would lead to
    nonsensical results. The excavator would be unable to cure an
    improper notification and could become subject to a fine even if
    digging never took place; or the excavator could notify the call
    center of intended work at a single location, dig outside the
    location on multiple occasions, but still be subject only to a
    single fine.
    15
    offense committed by DeFelice was subject to a separate civil
    penalty under G. L. c. 82, § 40E.
    Decision and order of
    Department of Public
    Utilities affirmed.
    

Document Info

Docket Number: AC 14-P-1056

Citation Numbers: 88 Mass. App. Ct. 544

Filed Date: 10/19/2015

Precedential Status: Precedential

Modified Date: 1/12/2023