Atterbury v. U.S. Marshals Service ( 2015 )


Menu:
  • 14‐2805
    Atterbury v. U.S. Marshals Service
    UNITED STATES COURT OF APPEALS
    FOR THE SECOND CIRCUIT
    August Term, 2015
    (Argued: September 10, 2015       Decided: November 3, 2015)
    Docket No. 14‐2805‐cv
    STEPHEN L. ATTERBURY,
    Plaintiff‐Appellant,
    — v. —
    UNITED STATES MARSHALS SERVICE, GARY INSLEY, Contracting Officer, Office of
    Security Contracts, Judicial Division, United States Marshals Service, in his
    individual capacity, and JOHN DOE, in his individual capacity,
    Defendants‐Appellees.
    B e f o r e:
    LYNCH, LOHIER, and CARNEY, Circuit Judges.
    __________________
    1
    Plaintiff‐Appellant Stephen L. Atterbury appeals from a judgment of the
    United States District Court for the Western District of New York (Richard J.
    Arcara, Judge) dismissing his complaint for failure to state a claim and for lack of
    subject‐matter jurisdiction.  He alleges that Defendants‐Appellees the United
    States Marshals Service and Gary Insley violated his rights under the Due Process
    Clause and acted arbitrarily and capriciously by terminating his employment as a
    Court Security Officer.  We agree with the district court that Atterbury does not
    have a private right of action under the Due Process Clause of the sort recognized
    in Bivens v. Six Unknown Named Agents of Federal Bureau of Narcotics, 403
    U.S. 388 (1971), and accordingly that claim was properly dismissed.  We find,
    however, that the district court erred in determining that it lacked subject‐matter
    jurisdiction over Atterbury’s claim under the Administrative Procedure Act.
    AFFIRMED IN PART, VACATED IN PART, AND REMANDED.
    THOMAS N. CIANTRA (Kate M. Swearengen, on the brief), Cohen, Weiss
    and Simon LLP, New York, New York, for Plaintiff‐Appellant.
    MICHAEL  S.  CERRONE,  Assistant  United  States  Attorney,  on  behalf  of
    William J. Hochul, Jr., United States Attorney for the Western
    District  of  New  York,  Buffalo,  New  York,  for  Defendants‐
    Appellees.
    GERARD E. LYNCH, Circuit Judge:
    Plaintiff‐Appellant Stephen L. Atterbury’s employment as a Court Security
    Officer (“CSO”) was terminated when Defendants‐Appellees the United States
    Marshals Service (“USMS”) and Gary Insley determined that he had violated
    2
    USMS’s performance standards.  Because Atterbury was employed by a federal
    contractor, rather than directly by USMS, he could not challenge his dismissal
    under the administrative scheme that regulates the federal civil service.  Nor
    could he avail himself of the remedial scheme that governs disputes between
    contractors and the federal government.  He instead brought this action, alleging
    that the defendants violated his rights under the Due Process Clause and acted
    arbitrarily and capriciously by terminating his employment.  The United States
    District Court for the Western District of New York (Richard J. Arcara, Judge)
    dismissed his complaint for failure to state a claim and for lack of subject‐matter
    jurisdiction.
    We agree with the district court that Atterbury does not have a private
    right of action under the Due Process Clause of the sort recognized in Bivens v.
    Six Unknown Named Agents of Federal Bureau of Narcotics, 403 U.S. 388 (1971),
    and accordingly that claim was properly dismissed.  We find, however, that the
    district court erred in determining that it lacked subject‐matter jurisdiction over
    Atterbury’s claim under the Administrative Procedure Act (“APA”).
    Accordingly, the judgment of the district court is AFFIRMED IN PART and
    VACATED IN PART, and the case is REMANDED for further proceedings
    consistent with this opinion.
    3
    BACKGROUND
    Because Atterbury appeals from the grant of a motion to dismiss under
    Fed. R. Civ. P. 12(b)(1) and (b)(6), we draw the following facts from the complaint
    and accept them as true for the purposes of this appeal.1  Loginovskaya v.
    Batratchenko, 764 F.3d 266, 268 n.2 (2d Cir. 2014).
    USMS provides security services for United States courts and judicial
    officers, and contracts with private security companies that recruit and employ
    persons with law enforcement experience to participate in USMS’s Court Security
    Program as CSOs.  Atterbury was employed by one such contractor, Akal
    Security, Inc. (“Akal”), as a CSO for the Kenneth B. Keating Federal Building in
    Rochester, New York.  Under the terms of the contract between USMS and Akal,
    USMS retained the sole discretion to remove a CSO from the Court Security
    Program.  Further, the Akal–USMS contract incorporated fifty‐eight “CSO
    1
    In dismissing the APA claim under Rule 12(b)(1), the district court was
    permitted to rely, in addition to the complaint, on non‐conclusory, non‐hearsay
    portions of declarations submitted by the parties as part of their briefing.  M.E.S.,
    Inc. v. Snell, 712 F.3d 666, 671 (2d Cir. 2013).  The declarations submitted by the
    defendants in particular present a significantly different version of the facts from
    what is alleged in the complaint.  For the purposes of Atterbury’s appeal from the
    dismissal of his Bivens claim under Rule 12(b)(6), however, we are required to
    accept as true the complaint’s factual allegations.  In any event, the factual
    disputes surrounding the events that led to Atterbury’s dismissal are not material
    to the resolution of the purely legal questions at issue here.  See 
    id. 4 Performance
     Standards” promulgated by USMS, which set forth a detailed code
    of conduct for CSOs.  As a condition of his participation in the Court Security
    Program, Atterbury was required to acknowledge that he had reviewed the
    Performance Standards and was subject to them.  USMS was empowered to
    request that Akal investigate suspected violations of the Performance Standards,
    but it reserved the authority to remove CSOs from the Court Security Program
    even when Akal determined that no violation had occurred.
    The conditions of Atterbury’s employment with Akal were governed by a
    collective bargaining agreement (“CBA”), which provided that no employee
    having completed his probationary period would be disciplined or terminated
    without just cause.  The CBA also provided, however, that if a CSO was removed
    from the Court Security Program by USMS, his employment with Akal could be
    terminated “without recourse to the procedures under [the CBA].”  J.A. 11.
    On February 24, 2011, Atterbury was assigned to a “roving post” where he
    was responsible for the security of courtrooms and adjacent areas.  In the
    complaint’s version of the events, Atterbury had been suffering from a cold for
    several days, and at 1:30 p.m., feeling “febrile and nauseous,” J.A. 13, he advised
    Acting Lead CSO Jerry Risley, who was the highest‐ranking Akal employee on
    5
    duty at that time, that he was going home.  Risley responded, “See ya,” id., and
    Atterbury left for the day.  News of this incident made its way to USMS, which
    requested that Akal investigate whether Atterbury’s departure violated CSO
    Performance Standard 31, which provides that a CSO must not leave his assigned
    post until relieved or directed to do so by a supervisor.
    On May 3, following an investigation during which several witnesses were
    interviewed, Akal submitted a report to USMS that concluded that Atterbury had
    not violated the Performance Standards and recommended that he not face
    discipline.  USMS disagreed, and directed Akal to reinterview one witness.  Akal
    complied, and then advised USMS that its conclusion had not changed.  On May
    5, Defendant‐Appellee Gary Insley, the USMS Contracting Officer assigned to the
    Akal–USMS contract, sent Akal a letter stating that Atterbury’s actions “ha[d]
    undermined the District’s confidence and trust in [his] ability to effectively
    perform his duties,” J.A. 16, and permanently removing him from the Court
    Security Program.  Akal then informed Atterbury that, under the terms of the
    contract, he was entitled to respond in writing to USMS’s decision.  Atterbury,
    however, was not told what conduct had led to his removal.  He submitted a one‐
    page statement, but on June 24, Insley notified Akal that Atterbury’s “appeal of
    6
    removal” had been denied.  Akal then terminated Atterbury’s employment.
    Atterbury brought this action, asserting one cause of action under the Due
    Process Clause of the Fifth Amendment to the U.S. Constitution, and one cause of
    action under the APA.  The defendants moved for dismissal under Fed. R. Civ. P.
    12(b)(6) “and/or” Fed. R. Civ. P. 56.  J.A. 21.  The case was referred to Magistrate
    Judge Leslie G. Foschio, who issued a Report and Recommendation (“R&R”)
    advising that the district court dismiss the Due Process claim and the APA claim,
    the latter for lack of subject‐matter jurisdiction.  The district court, over
    Atterbury’s objections, adopted the R&R.  This appeal followed.
    DISCUSSION
    We review the district court’s dismissal of the complaint under Rules
    12(b)(1) and 12(b)(6) de novo, accepting as true the allegations in the complaint
    and drawing all reasonable inferences in favor of the plaintiff.  Town of Babylon
    v. Fed. Hous. Fin. Agency, 699 F.3d 221, 227 (2d Cir. 2012).
    I.    Bivens Claim
    Atterbury asserts his first cause of action directly under the Fifth
    Amendment’s Due Process Clause.    The Supreme Court first recognized an
    implied cause of action for damages under the Constitution in Bivens, in which
    7
    the plaintiff alleged that federal narcotics agents had entered and searched his
    apartment and arrested him in violation of the Fourth Amendment.  That
    decision “established that a citizen suffering a compensable injury to a
    constitutionally protected interest could . . . obtain an award of monetary
    damages against the responsible federal official,” Butz v. Economou, 438 U.S.
    478, 504 (1978), even in the absence of a federal statutory cause of action.
    More recently, however, the Supreme Court has narrowed the reach of that
    principle, explaining that the recognition of such a cause of action “is not an
    automatic entitlement,” but must instead “represent a judgment about the best
    way to implement a constitutional guarantee.”  Wilkie v. Robbins, 551 U.S. 537,
    550 (2007).  The analysis of whether to extend Bivens to a new context proceeds in
    two steps.  First, a court must determine “whether any alternative, existing
    process for protecting the interest amounts to a convincing reason for the Judicial
    Branch to refrain from providing a new and freestanding remedy in damages.”
    Id.  Second, even in the absence of such an alternative process, a court “must
    make the kind of remedial determination that is appropriate for a common‐law
    tribunal, paying particular heed, however, to any special factors counselling
    hesitation before authorizing a new kind of federal litigation.”  Id., quoting Bush
    8
    v. Lucas, 462 U.S. 367, 378 (1983).  This two‐part test has only rarely yielded a
    new Bivens remedy; indeed, the Supreme Court has extended Bivens to contexts
    other than unreasonable searches and seizures only twice, most recently thirty‐
    five years ago in Carlson v. Green, 446 U.S. 14 (1980).
    The defendants urge us to affirm the district court on the grounds that the
    Contract Disputes Act of 1978 (“CDA”), 41 U.S.C. § 7101 et seq., affords Atterbury
    an alternative process for protecting his rights that precludes the recognition of a
    Bivens claim at the first step of the Wilkie test.  The CDA provides a
    comprehensive procedural framework for the resolution of disputes arising from
    contracts with the federal government.  In M.E.S., Inc. v. Snell, we characterized
    the CDA’s “remedial scheme as ‘the paradigm of a precisely drawn, detailed
    statute,’ which ‘purports to provide final and exclusive resolution of all disputes
    arising from government contracts’ that fall within its ambit,” 712 F.3d 666, 673
    (2d Cir. 2013), quoting A & S Council Oil Co. v. Lader, 56 F.3d 234, 241 (D.C. Cir.
    1995), and held that the CDA precluded us from devising a Bivens remedy for a
    contractor that alleged that its contracts had been unlawfully terminated.  Id. at
    676.
    9
    Unlike the contractor in M.E.S., however, Atterbury is not in privity with
    the United States and – the parties agree – has no standing to bring a claim under
    the CDA.2  The defendants nevertheless argue that the CDA provides Atterbury
    with an alternative process for protecting his interests because Akal could have
    brought a CDA claim on his behalf.  We disagree.  While it is true that courts will
    not imply a new Bivens right of action simply because “existing remedies do not
    provide complete relief for the plaintiff,” Bush, 462 U.S. at 388, we decline to hold
    that a Bivens right of action is categorically barred whenever a third party could
    bring suit on the plaintiff’s behalf.  The facts before us illustrate the undesirability
    of such a rule.  Akal is under no obligation to defend Atterbury’s rights, and
    indeed may prefer to acquiesce in Atterbury’s dismissal rather than damage its
    relationship with the federal government by bringing suit against it.  The
    alternative process available to Atterbury under the CDA is thus much too
    contingent automatically to preclude a Bivens remedy.
    We nonetheless conclude that the existence of the CDA’s remedial scheme
    is a special factor counseling hesitation at the second step of the Wilkie test.  As
    2
    “[T]he provisions of the CDA apply only to ‘contractors,’” Winter v. FloorPro,
    Inc., 570 F.3d 1367, 1370 (Fed. Cir. 2009), and “contractor” is defined as “a party
    to a Federal Government contract other than the Federal Government,” 41 U.S.C.
    § 7101(7).
    10
    noted above, that scheme, while purporting to be comprehensive, does not
    provide a remedy for subcontractors or employees of contractors.  Under the
    Supreme Court’s more recent Bivens jurisprudence, courts generally assume that
    the omission of particular relief from a comprehensive congressional scheme
    “has not been inadvertent.”  Schweiker v. Chilicky, 487 U.S. 412, 423 (1988); see
    also M.E.S., 712 F.3d at 672.  In this case, that assumption finds additional
    support in the CDA’s legislative history.  The Senate Report lays out the
    justifications for Congress’s decision to adopt a “single point of contact
    approach,” that is, to deny to anyone but prime contractors access to the CDA’s
    administrative remedies.  S. Rep. No. 95‐1118, at 16–17 (1978).  It explains that
    such an approach “helps suppress frivolous claims,” id. at 16, and “forc[es] the
    prime contractor and the subcontractor to negotiate their disputes,” thereby
    preventing “additional time‐consuming and expensive litigation.”  Id. at 17.  It
    recognizes the “inequities” flowing from that approach, but concludes that they
    “are best handled by improved subcontract administration by the prime
    contractor,” and that the “additional problems” of bringing subcontractors
    within the scope of the CDA “outweigh the benefit to be gained.”  Id.  While the
    Senate Report explicitly addresses only the exclusion of subcontractors, the
    11
    “single point of contact approach” would also require the exclusion of employees
    of contractors like Atterbury.  We would be encroaching upon Congress’s
    authority were we to create a remedy for Atterbury where Congress intentionally
    withheld one, M.E.S., 712 F.3d at 672; Dotson v. Griesa, 398 F.3d 156, 169 (2d Cir.
    2005) – particularly where, as here, the decision to withhold the remedy was
    motivated in large part by a desire to curb litigation against the government.
    Another factor counseling hesitation is the fact that extending a Bivens
    remedy to Atterbury would paradoxically put him in a better situation than two
    similar classes of plaintiffs for whom Congress did create a remedy.  Atterbury is
    situated in what the district court termed a “remedy‐less ‘gap,’” J.A. 332, between
    the CDA and a second comprehensive remedial scheme: the Civil Service Reform
    Act (“CSRA”), which “represents Congress’s comprehensive identification of the
    employment rights and remedies available to federal civil service personnel.”
    Dotson, 398 F.3d at 160.   If Atterbury had been directly employed by the federal
    government, his exclusive remedy would lie under the CSRA, and he would be
    precluded from bringing a Bivens claim.  Bush, 462 U.S. at 368; Dotson, 398 F.3d
    at 160.  Alternatively, if he were a federal contractor, he would be limited to the
    remedies provided by the CDA and his Bivens claim would similarly be barred.
    12
    M.E.S., 712 F.3d at 668–69.  Neither the CDA nor the CSRA allows an aggrieved
    party to bring a plenary action for damages in federal court, with the attendant
    right to a jury trial and the ability to recover punitive damages, nor does either
    permit damages to be sought against individual federal officers.  See 41 U.S.C.
    § 7103(a)(1) (requiring aggrieved contractors to submit claims to a contracting
    officer for a decision); 5 U.S.C. § 7513(d) (providing that a federal employee
    against whom an adverse action is taken may appeal to the Merit Systems
    Protection Board).  It would be incongruous if Atterbury, whom Congress
    excluded from both of these carefully drawn administrative schemes, were
    afforded access to a more liberal procedure for vindicating his rights than people
    or entities who, unlike Atterbury, are in privity with the United States, and to
    whom Congress has explicitly extended rights to challenge federal government
    action.
    Atterbury responds that it would be equally, if not more, incongruous to
    leave employees of contractors without a remedy at all.  But that argument is
    overstated.  As we explain below, the APA provides Atterbury with an avenue
    for challenging his dismissal.  And in any event, courts are not required to
    recognize a Bivens remedy even when a plaintiff would otherwise be completely
    13
    remediless.  In Dotson, for example, we held that the CSRA barred a federal
    judicial branch employee’s Bivens claim, despite the fact that the employee was
    otherwise entitled to no administrative or judicial review of the termination of his
    employment.  Dotson, 398 F.3d at 168–69.  Accordingly, the district court
    properly dismissed Atterbury’s Bivens claim.
    II.   Claim Under the APA
    Atterbury brings his second claim under § 702 of the APA, which “permits
    a party to bring an equitable claim challenging arbitrary and capricious action of
    an administrative agency in federal district court and waives the government’s
    sovereign immunity with respect to such claims in that forum.”  Up State Fed.
    Credit Union v. Walker, 198 F.3d 372, 375 (2d Cir. 1999).  As a person alleging
    that he “suffer[ed] legal wrong because of agency action,” 5 U.S.C. § 702,
    Atterbury was thus presumptively entitled to challenge USMS’s decision to
    remove him from the Court Security Program.
    But § 702 further specifies that “[n]othing herein . . . confers authority to
    grant relief if any other statute that grants consent to suit expressly or impliedly
    forbids the relief which is sought.”  Id.  The government argues that the Tucker
    Act, 28 U.S.C. § 1491, which waives sovereign immunity with respect to “any
    14
    claim against the United States founded . . . upon any express or implied contract
    with the United States,” and grants the Court of Federal Claims exclusive
    jurisdiction over such claims, is such a statute.  “The Tucker Act impliedly
    forbids relief other than remedies provided by the Court of Federal Claims for
    actions that arise out of a contract with the United States.”  Up State, 198 F.3d at
    375 (alteration and internal quotation marks omitted).  The defendants argue, and
    the court below agreed, that Atterbury’s APA claim in fact arises out of Akal’s
    contract with USMS and is thus “impliedly forbid[den]” by the Tucker Act.
    Whether a claim is in essence a contract claim over which the Court of
    Federal Claims has exclusive jurisdiction depends on a two‐pronged analysis: a
    court must examine both “the source of the rights upon which the plaintiff bases
    [his] claims, and . . . the type of relief sought.”  Up State, 198 F.3d at 375, quoting
    Megapulse, Inc. v. Lewis, 672 F.2d 959, 968 (D.C. Cir. 1982).  With respect to the
    first prong, the district court concluded that the source of the rights at issue was
    the Akal–USMS contract, reasoning that only that contract gave USMS the power
    to remove Atterbury from CSO duty.  The right asserted by Atterbury here,
    however, is not USMS’s right to dismiss Atterbury, but instead Atterbury’s right
    to continued employment as a CSO.  That right plainly does not arise from the
    15
    Akal–USMS contract, which instead provides that “[USMS] reserves the right at
    all times to determine the suitability of any Contractor employee to serve as a
    CSO,” and that “[a]ny decision to continue a Contractor employee in a CSO
    capacity will be made solely by the Office of Court Security on a case‐by‐case
    basis.”  J.A. 42.
    Atterbury does not ground his claim in any provision of Akal’s contract
    with USMS.  Instead, he grounds his alleged right to continued employment as a
    CSO in the CBA between Akal and its employees and in the Due Process Clause
    of the Fifth Amendment.3  In Stein v. Board of the City of New York, 792 F.2d 13
    (2d Cir. 1986), we recognized that an employee of a government contractor may
    under certain circumstances have a constitutionally protected property interest in
    continued employment.  The plaintiff in that case was employed as a bus driver
    by a company that provided bus transportation for handicapped schoolchildren
    in New York City.  Id. at 14.  The company’s agreement with the city required it
    3
    It is true that the CBA allowed Akal to terminate an employee “without
    recourse” if USMS removed the employee from the Court Security Program.  J.A.
    11.  In his R&R, the Magistrate Judge relied on this fact to conclude that
    Atterbury did not have a property interest in his continued employment.  J.A.
    284–89.  But the district court did not adopt this reasoning from the R&R, and the
    defendants did not argue on appeal that this language eliminated the property
    interest otherwise created by the CBA’s “just cause” provision.  We therefore do
    not address the impact of this language, if any, on Atterbury’s APA claim.
    16
    to employ only “persons of good moral character,” while the plaintiff’s contract
    with the company provided that he would not be discharged except for “just
    cause.”  Id.  The plaintiff was terminated for falling below the standards of “good
    moral character,” and brought a claim under 42 U.S.C. § 1983, alleging that he
    was not given adequate notice or a fair hearing.  Id. at 15.  We concluded that the
    “just cause” provision in the plaintiff’s employment contract created a protected
    property interest or “claim of entitlement,” and that the city had transgressed on
    that claim of entitlement by disqualifying the plaintiff under the “good moral
    character” provision.  Id. at 16–17.
    Atterbury’s circumstances parallel those of the plaintiff in Stein.  His
    complaint can fairly be read to allege that the CBA’s just cause provision gave
    him a protected property interest in continued employment, see Ciambriello v.
    Cty. of Nassau, 292 F.3d 307, 314 (2d Cir. 2002) (“We have repeatedly recognized
    that a collective bargaining agreement may give rise to a property interest in
    continued employment.”), and that USMS deprived him of that property interest
    without due process by unfairly determining that he had violated its
    performance standards.4  Atterbury’s insistence that he did not in fact violate the
    4
    Unlike the employer in Stein, Akal’s business does not flow exclusively from its
    contract with the government.  But the defendants have not argued, nor is there
    17
    performance standards simply raises factual questions going to the merits of his
    claim.  It does not suggest that the performance standards, and thus the
    Akal–USMS contract, are themselves the source of the rights he is asserting.
    Our conclusion is not altered by the fact that Akal’s contract with USMS
    gives a CSO who is subject to removal fifteen days from the initial removal notice
    to respond in writing.  The defendants argue that the procedural rights Atterbury
    seeks to assert are thus derived from the contract.  As an initial matter, however,
    Atterbury is not a party to the Akal–USMS contract and has no standing to assert
    that it was breached.  More importantly, the question of APA jurisdiction does
    not turn on whether the plaintiff could conceivably have based his claim on a
    government contract.  Instead, the appropriate inquiry is whether the claim “is
    validly based on grounds other than a contractual relationship with the
    government.”  Megapulse, 672 F.2d at 968.  Far from basing his claim on the
    procedural protections provided in the contract, Atterbury argues that those
    protections were inadequate to constitute due process, since he claims that he
    was denied due process despite having been accorded the contractual
    procedures.  The Due Process Clause thus provides Atterbury with a basis for his
    any basis in the record for us to infer, that Akal had any non‐CSO positions open
    to which Atterbury could have been reassigned.
    18
    claim that is independent of the Akal–USMS contract.5
    In that respect, this case is similar to Megapulse, in which the D.C. Circuit
    first devised the two‐pronged test for distinguishing APA claims from
    “disguised” Tucker Act claims.  The court in Megapulse held that the district
    court had APA subject‐matter jurisdiction over a claim by a contractor that
    sought to enjoin the government from releasing certain confidential technical
    data.  Id. at 969–70.  Although a series of agreements between the government
    and the plaintiff placed limits on the government’s use of those data, the court
    concluded that the claim was ultimately based “on an alleged governmental
    infringement of property rights and violation of the Trade Secrets Act.”  Id. at
    969.  In Up State, which involved a real estate dispute between a credit union and
    the Army, we distinguished Megapulse, on the grounds that the credit union’s
    right “stem[med] from no independent, non‐contractual source.”  Up State, 198
    F.3d at 376.  The credit union alleged only a vague “‘failure of integrity and
    regularity of process’ under the APA,” id. at 375, but as the district court here
    correctly observed, “the APA is not itself a free‐standing source of rights.”  J.A.
    344.  The Due Process Clause supplies Atterbury with the independent source of
    5
    We express no view on the merits of that claim, which the district court did not
    reach, since it held that it lacked jurisdiction under the APA even to consider it.
    19
    rights that was missing from the credit union’s claim in Up State.
    “[S]o long as an action brought against the United States or an agency
    thereof is not one that should be classified from the outset as a ‘contract action’
    for Tucker Act purposes, its remedies are also not contract‐related . . . .”
    Megapulse, 672 F.2d at 971.  Because Atterbury’s claim is not based on rights
    derived from a contract with the United States, the first prong of the Megapulse
    test is determinative in this case.  But we further note that the second prong,
    under which courts examine whether the remedies sought by the plaintiff are
    fundamentally contractual in nature, also supports our conclusion that the claim
    is not barred by the Tucker Act.  The complaint seeks money damages for lost
    wages, loss of employment opportunities, and mental anguish and emotional
    distress, as well as declaratory relief and equitable relief in the form of
    reinstatement.  With the exception of compensation for lost wages – Atterbury’s
    possible entitlement to which does not derive from the Akal–USMS contract in
    any event – none of these remedies are generally available in contract actions.
    Relying on the rule that actions seeking specific performance of a contract
    with the United States are barred by the Tucker Act, see Presidential Gardens
    Assocs. v. United States ex rel. Sec’y of Hous. & Urban Dev., 175 F.3d 132, 143 (2d
    20
    Cir. 1999), USMS suggests that Atterbury’s request for reinstatement should be
    interpreted as in essence seeking specific performance of the Akal–USMS
    contract.  That argument fails, however, because, as we have discussed, the
    Akal–USMS contract reserved to USMS’s discretion the decision whether to
    continue to employ Atterbury as a CSO.6
    In sum, because Atterbury’s second claim has a basis independent of any
    contract with the United States, it does not fall within the scope of the Tucker Act.
    Accordingly, the district court had subject‐matter jurisdiction under the APA to
    consider it.  We do not reach the merits of Atterbury’s APA claim, however, and
    leave it to the district court to determine, in the first instance, whether Atterbury
    has properly alleged that USMS acted arbitrarily and capriciously, or in a manner
    “contrary to constitutional right, power, privilege, or immunity,” 5 U.S.C.
    § 706(2)(A), (B), in removing him from the Court Security Program.
    6
    Further, although reinstatement is usually available as a remedy in statutory
    employment cases, the common‐law rule is that employment contracts will not
    be specifically enforced.  See Am. Law Inst., Restatement of Employment Law
    § 9.04(a) & cmts. b, c (2015).  Thus, reinstatement cannot be construed as a
    contractual remedy that the Tucker Act makes unavailable in the federal district
    courts.
    21
    CONCLUSION
    For the foregoing reasons, we affirm the district court’s dismissal of
    Atterbury’s Bivens claim, vacate its dismissal for lack of subject‐matter
    jurisdiction of his claim under the APA, and remand the case for further
    proceedings consistent with this opinion.