State Corp. Commission of KS v. FERC , 876 F.3d 332 ( 2017 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 11, 2017           Decided November 28, 2017
    No. 15-1447
    STATE CORPORATION COMMISSION OF THE STATE OF KANSAS,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC., ET
    AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    John P. Coyle argued the cause for petitioner. With him
    on the briefs was Amy E. McDonnell.
    Beth G. Pacella, Deputy Solicitor, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were Robert H. Solomon, Solicitor, and
    Lona T. Perry, Deputy Solicitor.
    Benjamin C. Mizer, Principal Deputy Assistant Attorney
    General at the time the brief was filed, U.S. Department of
    Justice, Charles W. Scarborough, and Mark W. Pennak,
    2
    Attorneys, were on the brief for intervenor Western Area Power
    Administration in support of respondent. Jeffrey A. Clair,
    Attorney, U.S. Department of Justice, entered an appearance.
    Jeffrey C. Genzer, Eli D. Eilbott, William D. Booth,
    Valerie L. Green, and Thomas L. Blackburn were on the joint
    brief of intervenors Southwest Power Pool, Inc., et al. in
    support of respondent.     Natalie M. Karas entered an
    appearance.
    Before: KAVANAUGH and MILLETT, Circuit Judges, and
    WILLIAMS, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    WILLIAMS.
    WILLIAMS, Senior Circuit Judge: In 1996, to facilitate the
    unbundling of wholesale power generation from power
    transmission and thus the development of competitive
    wholesale power markets, the Federal Energy Regulatory
    Commission required that power utilities under its jurisdiction
    adopt open access transmission tariffs. Promoting Wholesale
    Competition Through Open Access Non-Discriminatory
    Transmission Services by Public Utilities, 
    61 Fed. Reg. 21,540
    ,
    21,541 (1996). FERC also encouraged these utilities to create
    regional transmission organizations (“RTOs”) to operate
    transmission facilities on behalf of their members. Braintree
    Elec. Light Dep’t v. FERC, 
    550 F.3d 6
    , 8 (D.C. Cir. 2008).
    This case involves the terms on which an RTO and a set of
    utilities joined forces. The Southwest Power Pool (“SPP”) is
    an RTO that at the time of the proposed integration operated
    facilities in eight states encompassing nearly 50,000 miles of
    transmission lines. Its members included Kansas utilities. The
    State Corporation Commission of the State of Kansas
    (“Kansas”) is the petitioner here, representing Kansas power
    3
    consumers. During the period in question, the Integrated
    System was an adjacent, 9,500-mile transmission system in the
    Upper Great Plains Region. SPP and three of the Integrated
    System entities, known here as the IS Parties, negotiated an
    integration of their facilities to take effect on October 1, 2015.
    Pursuant to § 205 of the Federal Power Act, 16 U.S.C.
    § 824d, SPP filed with FERC revisions to its tariff that reflected
    the parties’ agreement. Over the objections of Kansas, FERC
    approved the revisions as just, reasonable, and not unduly
    discriminatory, Sw. Power Pool, Inc., 
    149 FERC ¶ 61,113
    (2014) (“Order”), and affirmed the Order on rehearing, Sw.
    Power Pool, Inc., 
    153 FERC ¶ 61,051
     (2015) (“Rehearing
    Order”).
    Kansas’s objections are in substance twofold. First, it
    claims that the Commission wrongly accepted a rate structure
    that disadvantaged the SPP participants. Second, it claims that
    in accepting SPP’s calculation of the benefits that the merger
    afforded SPP, the Commission unreasonably accepted data
    challenged by Kansas. Thus FERC’s decision was not
    supported by substantial evidence, 16 U.S.C. § 825l (b), or
    reasoned decision-making, 
    5 U.S.C. § 706
    (2), see also Motor
    Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983), and was further marred by FERC’s failure to
    conduct an evidentiary hearing in the face of factual disputes
    that Kansas claims to have required one. We deny the petition
    for review.
    * * *
    Cost allocation. Kansas objects to the way the parties
    agreed to allocate the costs of “legacy” facilities. Here these
    are facilities with a “need by” date before October 1, 2015, or,
    approximately, facilities planned and constructed by the
    proposed time of the SPP-IS Parties’ joinder. The tariff
    4
    approved by FERC, reflecting the agreement of the two groups,
    provided that these facilities would continue to be paid for by
    the utilities in whichever pre-integration entity—SPP or the IS
    Parties—had planned and constructed them.
    Kansas argues, in effect, that by accepting these provisions
    SPP got taken for a ride. It forewent the benefits potentially
    afforded by an alternative allocation system, which would have
    charged legacy costs in the SPP region to the IS Parties as well.
    By Kansas’s expert’s calculations, these foregone benefits
    swamped SPP’s estimate of the transaction’s benefits to SPP—
    $334 million over ten years. Joint Appendix (“J.A.”) 341-43,
    360-61. Kansas’s expert estimates that SPP would have
    received another $475 million in revenue under a system in
    which the IS Parties were required to pay for use of SPP legacy
    facilities. 
    Id.
     Kansas thus argues that SPP’s choice and the
    Commission’s approval make the deal a loser for SPP, and also
    violate controlling norms of ratemaking.
    In upholding the tariff, FERC characterized the integrating
    parties’ plan as “a practical, reciprocal cost allocation approach
    for facilities in service before the integration date. . . . [C]osts
    for such legacy facilities in the Integrated System region will
    be allocated to the Integrated System Parties; likewise, costs for
    legacy facilities in the pre-integration SPP region will be
    allocated to the pre-integration SPP membership.” Rehearing
    Order at P 41. It reasoned that such allocation methods were
    just and reasonable because they “reflect prior investment
    decisions and the fact that existing facilities were built
    principally to support load within the sub-region.” 
    Id.
     FERC’s
    decision to approve similar arrangements has withstood
    judicial review in analogous circumstances. See Illinois
    Commerce Comm’n v. FERC, 
    576 F.3d 470
    , 474 (7th Cir.
    2009).
    5
    FERC accurately described the agreement as reciprocal. It
    would be difficult to label it otherwise, as the agreement and
    FERC’s approval assigned each side’s legacy costs to the
    power consumers in that side. The reciprocity of the
    arrangement alone undermines Kansas’s expert’s idea that SPP
    left $475 million lying on the table—a point FERC emphasized
    in favoring SPP’s expert testimony on this point over that of
    Kansas’s expert. Rehearing Order P 41. Kansas never suggests
    any reason to believe that the IS Parties would have agreed to
    share SPP members’ legacy costs without demanding that SPP
    members share the IS Parties’ legacy costs, and perhaps give
    other concessions as well.
    We note for purposes of clarity that even if we assumed (as
    Kansas does) that an arrangement giving SPP the extra $475
    million was available, SPP’s failure to achieve that
    arrangement would not make the actual transaction a negative
    for SPP—only less positive than it might have been. Kansas’s
    hypothetical $475 million is an opportunity cost, not an out-of-
    pocket cost.
    Of course, an arrangement could be reciprocal and yet
    violate critical norms of ratemaking. So Kansas contends, in a
    series of attacks that have in common a reliance on Kansas’s
    misreading of various precedents. First, it points to our
    decision in FirstEnergy Serv. Co. v. FERC, 
    758 F.3d 346
    , 355
    (D.C. Cir. 2014), characterizing it as a FERC (and Circuit)
    precedent “requiring allocation of transmission costs based on
    benefits where a utility joins a regional transmission
    organization.” But FirstEnergy provides no basis for saying
    that FERC imposed any such requirement or that we endorsed
    its doing so. The complaining energy system had entered an
    RTO (PJM) without challenge to the latter’s pre-existing
    provision allocating certain costs to a new entrant, including
    facilities based on investment decisions made before the
    joinder. 
    Id. at 351, 355
    . It then sought a finding from the
    6
    Commission that PJM’s rate structure would be unjust and
    unreasonable unless the entrant were exempted from that
    provision. In a decision applying § 206, 16 U.S.C. § 824e,
    under which the complaining party has the burden to show that
    the rates challenged are unjust and unreasonable, 758 F.3d at
    353, FERC rejected FirstEnergy’s position, finding that the
    costs in question “related to the benefits” of joinder, and that,
    having elected to proceed in the face of those costs, FirstEnergy
    could not now claim that the cost allocation methodology
    “created a barrier to entry,” id. at 351 (internal quotation marks
    omitted). Indeed, more generally, FERC had urged upon the
    merging parties the desirability of a negotiated cost allocation
    made in light of what each party had to offer. Am. Transmission
    Sys., Inc. FirstEnergy Serv. Co., 
    129 FERC ¶ 61,249
    , P 114
    (2009). FERC ultimately accepted the outcome resulting from
    whatever negotiations occurred, exactly as it did here, and later
    refused to upset that outcome in the § 206 proceeding reviewed
    in FirstEnergy, a refusal that we affirmed.
    Kansas also claims that SPP-specific precedent calls for
    requiring a new entrant to share the costs of SPP’s legacy
    facilities and that failure to follow that precedent here renders
    the resulting rate unduly discriminatory. Of course, a
    difference in rate design can be discriminatory only if the
    contested design “has different effects on similarly situated
    customers,” and even then only if the differences cannot be
    justified. Transmission Agency of N. Cal. v. FERC, 
    628 F.3d 538
    , 549 (D.C. Cir. 2010); Ark. Elec. Energy Consumers v.
    FERC, 
    290 F.3d 362
    , 367 (D.C. Cir. 2002).
    The precedent invoked is SPP’s apparent former practice
    of requiring new entrants to pay a share of SPP’s legacy costs
    on entry. But here the Commission pointed not only to its
    general expectation that a “new entrant proposal will be the
    result of a collaborative effort,” Rehearing Order at P 40, but
    also to characteristics of this merger that Kansas does not claim
    7
    to have been matched in the prior entries to SPP: increased
    efficiency and reliability, improvement in SPP’s dispatch of
    power on its western edge (the part most directly affected by
    inclusion of the IS Parties), and a lower price of energy by
    virtue of reduced needs for generation curtailment. 
    Id.
     at P 21.
    We see no basis for a claim of undue discrimination.
    Assessment of benefits from the merger. Apart from
    mistakenly trying to reevaluate the merger transaction on the
    basis of an alternative rate allocation that it has not shown to
    have been plausible, Kansas claims a quite independent flaw in
    the Commission’s estimate of a $334 million benefit to SPP.
    As its expert did before the Commission, J.A. 357-60, Kansas
    protests SPP’s reliance on a study commissioned by the IS
    Parties and performed by the Brattle Group. Kansas appears to
    assert two objections: that SPP didn’t perform the study itself
    and that Kansas never had an opportunity to verify its accuracy.
    As to the first, it is enough that, although SPP lacked direct
    access to the entire study, its staff had reviewed the study’s
    “input assumptions and the results for reasonability,” J.A. 87,
    and after conversations with Brattle “was confident relying on
    the information provided by Brattle and using [its data] for its
    calculation” of the probable benefits, 
    id. 389
    .
    Kansas’s claim of lack of access to the study is somewhat
    exaggerated. Kansas in fact had access to a redacted, electronic
    version even before the start of the FERC proceedings involved
    here. See Respondent’s Br. at 24 n.5 (giving the URL). And it
    had access to some publicly unavailable confidential data. J.A.
    389 (alluding to data in confidential attachment). At no point
    does Kansas pinpoint either a special reason to question the
    Brattle Group study, or some debilitating feature of the
    redaction.
    In any event, even if one omitted the SPP benefits that were
    substantiated by the Brattle study, the integration would result
    8
    in a substantial net benefit for SPP members—over $61 million
    over ten years.
    Evidentiary hearing. Finally, Kansas challenges FERC’s
    decision not to hold an evidentiary hearing on the disputed
    features of the record underlying its approval of the merger.
    But the presence of disputed factual issues does not ipso facto
    require an evidentiary hearing where the Commission can
    adequately resolve the issues without such a hearing.
    Blumenthal v. FERC, 
    613 F.3d 1142
    , 1144 (D.C. Cir. 2010).
    We review FERC’s decision not to hold an evidentiary hearing
    only for abuse of discretion. Minisink Residents for Envtl. Pres.
    & Safety v. FERC, 
    762 F.3d 97
    , 114 (D.C. Cir. 2014).
    FERC did order a “trial-type” hearing for issues that it
    believed it could not resolve in the absence of a hearing. Order
    at P 17; Respondent’s Br. at 27. But, for the challenges at issue
    here, FERC concluded that a hearing was unwarranted.
    Rehearing Order at P 20-21.
    In disputing the benefits of the integration proposal and
    the validity of SPP’s cost/benefit analysis, Kansas had an
    opportunity to present its contrary expert testimony as part of
    the written record. Kansas asserts that its expert’s testimony
    was “simply ignored” by FERC. Not true. As the above
    discussion demonstrates, the testimony was considered, but
    rejected on the merits.
    And while Kansas takes issue with SPP’s results, it points
    to no vulnerability in the testimony of SPP’s expert witness that
    could be better resolved with cross-examination than with
    analysis of the written testimony itself in light of all the
    information before the Commission. We therefore find no
    abuse of FERC’s discretion. See Blumenthal, 
    613 F.3d at 1145
    .
    9
    * * *
    The petition for review is
    Denied.