Tri-Bullion Smelting & Development Co. v. Jacobsen , 233 F. 646 ( 1916 )


Menu:
  • MAYER, District Judge.

    The action was brought by Jacobsen against Tri-Bullion to recover damages in the sum of $25,000 for breach of contract by Tri-Bullion. The essential features of the written agreement, expressing the contract between the parties, were as follows:

    (1) Tri-Bullion was to sell and Jacobsen to buy the output of zinc concentrates produced at Tri-Bullion’s plant at Kelly, N. M., for a period of two years from November 22, 1911, to November 22, 1913, concentrates to be delivered in as nearly as possible equal monthly quantities, with the agreement by Tri-Bullion that the minimum should not be less than 600 tons per month.

    (2) The price was to be arrived at by a method carefully set forth in the agreement.

    (3) Delivery was to be made f. o. b. cars at different points.

    (4) Payment was to be made by Jacobsen as soon as weights and assays were agreed upon.

    (5) Average quotation of the Engineering and Mining Journal for spelter at East St. Louis during the month of arrival at buyer’s works was to be taken as basis of final settlement.

    *648The agreement also contained the following clause:

    “Force Majeure. — Sellers will be relieved from, delivering, and buyers from taking tlie concentrates in case of strikes, fires, wars, revolutions, accidents to machinery, etc., etc., and in case of events of superior force of nature over which they have no control. * * * ”

    After a year and a half Tri-Bullion closed its mine, ceased delivering, and notified Jacobsen that it would not make any further deliveries to him; its reasons for this course being that because of the fall in the market price of spelter it could no longer mine the ore at a profit. Prior to July 7, 1913, Jacobsen had heard rumors that TriBullion intended to cease producing and close its mine, and some time around June 20, 1913, Tri-Bullion, on a post card on which it gave advice of shipments of ore, wrote the words, “This is our final shipment.”

    Jacobsen, after some endeavor, succeeded in obtaining an interview on July 7, 1913, with Paschal, the president of Tri-Bullion, E. P. Earle, its agent (to whom under the contract all payments were to be made), and David Earle, another representative of Tri-Bullion. The position of the Tri-Bullion officials and representatives was that, as the contract had become unprofitable, the company was released from its obligations under the force majeure clause. None of the contingencies contemplated under that clause had happened. Jacobsen protested against this extraordinary attitude and stated that he would hold the company responsible for its breach.

    On July 8, 1913, Jacobsen addressed a letter to Tri-Bullion stating that, if it did not immediately resume shipment, he would enter the market for monthly tonnage, charging the defendant with whatever difference he might be compelled to pay as between the contract price and the market price. On the same day Jacobsen wrote E. P. Earle substantially to the same effect and demanding that Tri-Bullion fulfill its contract. On July 9, 1913, Earle wrote Jacobsen, still insisting on the efficacy of the force majeure clause. To this Jacobsen replied on July 10, 1913, repeating that he would enter the market for the quantities still due and charge Tri-Bullion with the difference in price, if any. Jacobsen again asserted that the force majeure clause was not applicable. On July 11, 1913, Earle wrote Jacobsen to the effect that Tri-Bullion did not agree with Jacobsen’s contention. Further correspondence ensued at a later date, which did not, however, change' the relations of the parties.

    The theory of Tri-Bullion seems to be that because, in the letter of July 8th, Jacobsen urged Tri-Bullion to proceed to fulfill the contract, he was thereby precluded from bringing action for an anticipatory breach, but must perform all of the provisions of the contract called for on his part; one of which was to pay the amount thereafter due for ore theretofore delivered and that Jacobsen could sue only for failure to deliver any installment as the installment became due month by month.

    [ 1 ] The question of fact in the trial court was whether Tri-Bullion had breached its contract. Both parties having moved for the direction of a verdict, and the court having directed a verdict in favor of *649plaintiff, that question is disposed of by the verdict, and what the verdict amounts to is a finding that Tri-Bullion broke its contract, and it matters not whether the breach was actual or anticipatory. Wilson v. Knowles, 213 Fed. 782, 130 C. C. A. 440; Reis v. Rosenfeld, 204 Fed. 282, 122 C. C. A. 480; United States v. Two Baskets, 205 Fed. 37, 123 C. C. A. 310; Alleghenv Valley Brick Co. v. C. W. Raymond Co., 219 Fed. 477, 135 C. C. A. 189.

    [2] Viewed, however, as an anticipatory breach, the action of Jacobsen in writing the letter of July 8, 1913, insisting that Tri-Bullion should carry out' his contract, did not, in any manner, cure such anticipatory breach by Tri-Bullion. The persistent position of TriBullion was that it was excused by tbe force majeure clause — an obvious pretense to avoid the obligations of a contract which had become unprofitable. Jacobsen’s letter of July 8th, as the District Judge said, “was an ordinary business letter in which the plaintiff said in substance: ‘You ought to perform your contract, and I request you to do so; but, if you do not, I will enter the market, buy zinc concentrates, and hold you for the difference between the cost to me and the contract price.’ ”

    Where a parly to a contract insists that he is not under legal obli gation to perform the contract, and that insistence is coupled with a continuance of his original stand and refusal to perform, the breach is plain, and he cannot successfully take refuge in the plea that he must be excused because the other party urges that the contract be carried out, failing which such other party states he will be compelled to purchase goods in a rising market. Roehm v. Horst, 178 U. S. 1, 20 Sup. Ct. 780, 44 L. Ed. 953; Marks v. Van Eeghen, 85 Fed. 853, 30 C. C. A. 208.

    [3] It is claimed by Tri-Bullion that Jacobsen was first in default, for the reason that, several days after July 7th, Jacobsen, in the ordinary conduct of the contract, would have been indebted to TriBullion in an amount of, in round numbers, less than $2,000 (or about $1,871.35), representing the price of five cars of zinc concentrates shipments. We think the question as to- who was first in default was settled by the verdict; hut, in any event, this claim was clearly an afterthought.

    Jacobsen’s responsibility was not questioned; he had already paid Tri-Bullion, over $250,000 under the contract during a period when it was unprofitable to him; no demand was ever made for this — -to them — trifling sum of less than $2,000, and the practice of the parties was that payment was made when convenient, and that was usually several days after the price had been fixed by the rather elaborate method for determining price provided for in the contract. If TriBullion was guilty of anticipatory breach on July 7th, there was no obligation on Jacobsen’s part to pay over this small amount of money to Tri-Bullion, and especially in the face of every reasonable expectation that Tri-Bullion would be called upon to respond in substantial damages to Jacobsen because of loss suffered by Jacobsen in a rising market. Sperry & Hutchinson Co. v. O’Neill-Adams Co., 185 Fed. *650231, 107 C. C. A. 337; Whitcomb v. Shultz, 215 Fed. 75, 131 C. C. A. 383.

    [4] The only other question in the case relates to the rule of damages which the District Judge applied. There was no market value for Kelly ore because the mine was closed, and the only substitute in the market was ore from the Joplin mines in Missouri. This ore was purchased by National Zinc Company under a business arrangement between it and Jacobsen. It is well settled that, where there is no market, the value may be otherwise determined by the price of the best substitute procurable. Benjamin on Sales (5th Ed.) page 987; Sedgwick on Damages (9th Ed.) § 734; Williston on Sales, § 599; Hinde v. Liddell, L. R. 10 Q. B. Div., 265; Gruen v. Ohl, 81 N. J. Law, 626, 80 Atl. 547; E. W. Bliss Co. v. Buffalo Tin Can Co., 131 Fed. 51, 65 C. C. A. 289. A proper rule of damages having been applied, the amount of the damages, was a question of fact, disposed of -by the verdict, and not reviewable in this court.

    The judgment is affirmed, with costs.

    <@=sFor other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes

    ©=^>For other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes

Document Info

Docket Number: No. 101

Citation Numbers: 233 F. 646

Judges: Mayer, Rogers, Ward

Filed Date: 5/9/1916

Precedential Status: Precedential

Modified Date: 11/26/2022