In Re: George Washington Bridge ( 2023 )


Menu:
  •      21-2050-bk
    In re: George Washington Bridge
    1                                         In the
    2                            United States Court of Appeals
    3                                for the Second Circuit
    4
    5
    6                                     August Term, 2022
    7
    8                                      No. 21-2050-bk
    9
    10    IN RE: GEORGE WASHINGTON BRIDGE BUS STATION DEVELOPMENT VENTURE LLC,
    11
    12                                                                           Debtor.
    13
    14                             TUTOR PERINI BUILDING CORP.,
    15
    16                                                               Plaintiff-Appellant,
    17                                            v.
    18
    19    NEW YORK CITY REGIONAL CENTER GEORGE WASHINGTON BRIDGE BUS STATION
    20   AND INFRASTRUCTURE DEVELOPMENT FUND, LLC, PORT AUTHORITY OF NEW YORK
    21   AND NEW JERSEY, GSNMF SUBCDE 12 LLC, UPPER MANHATTAN EMPOWERMENT
    22    ZONE DEVELOPMENT CORPORATION, DVCI CDE XIII, LLC, LIIF SUBCDE XXVI,
    23    LLC, GEORGE WASHINGTON BRIDGE BUS STATION DEVELOPMENT VENTURE LLC,
    24
    25                                                             Defendants-Appellees,
    26
    27    KENNETH P. SILVERMAN, Chapter 7 Trustee of the Bankruptcy Estate of George
    28           Washington Bridge Bus Station Development Venture LLC,
    29
    30                                                                 Trustee-Appellee.
    31
    32
    1                     Appeal from the United States District Court
    2                       for the Southern District of New York
    3                                   No. 20-cv-7433
    4
    5                  (Argued October 27, 2022; Decided April 10, 2023)
    6
    7   Before:     WALKER, LEE, and ROBINSON, Circuit Judges.
    8
    9         Plaintiff-Appellant Tutor Perini Building Corp. appeals from an order of the
    10   United States District Court for the Southern District of New York (Rakoff, J.)
    11   affirming an order of the United States Bankruptcy Court for the Southern District
    12   of New York (Chapman, Bankr. J.), which held that Plaintiff-Appellant may not
    13   use 
    11 U.S.C. § 365
    (b)(1)(A) to assert a “cure claim” against the Trustee-Appellee
    14   for the Trustee-Appellee’s assumption of an unexpired lease to which Plaintiff-
    15   Appellant was neither a party nor a third-party beneficiary. We hold that a
    16   creditor who seeks to assert a “cure claim” under § 365(b)(1)(A) must have a
    17   contractual right to payment under the assumed executory contract or unexpired
    18   lease in question, and we agree that Plaintiff-Appellant is not a third-party
    19   beneficiary of the assumed lease. We therefore AFFIRM.
    20                                               JEFFREY K. GARFINKLE, Buchalter,
    21                                               P.C., Irvine, California (Robert Nida,
    22                                               Nida & Romyn, P.C., Los Angeles,
    23                                               California, on the brief), for Plaintiff-
    24                                               Appellant Tutor Perini Building Corp.
    25
    26                                               ANTHONY C. ACAMPORA, Silverman
    27                                               Acampora LLP, Jericho, New York,
    28                                               for Trustee-Appellee Kenneth P.
    29                                               Silverman.
    2
    1   EUNICE C. LEE, Circuit Judge:
    2         Generally, when a debtor declares bankruptcy, the debtor’s creditors line up
    3   to be paid in the order of priority provided by the Bankruptcy Code—for example,
    4   secured creditors are normally paid in full before unsecured creditors have any
    5   right to payment. See 
    11 U.S.C. § 1129
    (b). Thus, if a general contractor seeks
    6   unpaid fees from a bankrupt real estate developer, but his contract with the
    7   developer renders him an unsecured creditor, then the general contractor only gets
    8   paid to the extent that there is money left after all creditors with higher priority
    9   get paid. But the Bankruptcy Code contains exceptions to the normal rules of
    10   priority, and Plaintiff-Appellant Tutor Perini Building Corp. (“Tutor Perini”), a
    11   general contractor and would-be unsecured creditor of the debtor in this case,
    12   attempts to rely upon one of these exceptions to get priority on its claim: 11 U.S.C.
    13   § 365(b)(1)(A).
    14         Under § 365, a debtor undergoing reorganization may not assume “an
    15   executory contract or unexpired lease” in which there “has been a default” until
    16   the debtor “cures” the default. In other words, § 365 obligates the debtor to cure
    17   any existing defaults before the debtor can continue to benefit from the contract.
    18   If a default resulted from the debtor’s failure to pay money due under the contract,
    19   then curing the default means making payment. This is good for the creditor on
    3
    1   the other side of the contract in question, because the creditor’s claims get fully
    2   paid at the moment the debtor assumes the contract. This effectively lets the
    3   creditor cut to the front of the priority line, rather than waiting for payment
    4   according to the normal order of priority.
    5         In this action, Tutor Perini believes that § 365 applies to its claims for
    6   recovery against the debtor. As part of its bankruptcy proceeding, the debtor here
    7   assumed an unexpired lease it had entered into with the owner of a property to be
    8   developed. The debtor hired Tutor Perini to be the general contractor for the
    9   property. Tutor Perini now points to what it contends is a default in the lease
    10   between the debtor/developer and the property owner: The lease says that the
    11   debtor has to pay anyone hired to work on the development. Tutor Perini, whom
    12   the debtor hired, has not been paid in full under its own contract with the debtor—
    13   after all, that is why it is waiting in line to recover from the developer’s bankruptcy
    14   estate. Thus, Tutor Perini believes § 365(b) entitles it to immediate payment. Even
    15   though Tutor Perini is not a party to the lease, it argues that § 365 does not say one
    16   has to be a contracting party to identify a default and seek priority of payment.
    17         This appeal calls for us to decide whether Tutor Perini is right, i.e., whether,
    18   as a non-party to the lease, it can bring a “cure claim” under 
    11 U.S.C. § 4
    1   365(b)(1)(A). We hold that it cannot. More specifically, based on principles of
    2   Bankruptcy Code construction, we hold that § 365(b)(1)(A) does not provide a
    3   right of priority to a creditor who seeks payment from a debtor under one contract
    4   but whose assertion of uncured default arises from a separate contract in which
    5   the creditor has no contractual rights. Additionally, we hold that Tutor Perini is
    6   not a third-party beneficiary entitled to recover under the contract with the
    7   purported uncured default.
    8         Accordingly, we AFFIRM the judgment of the district court.
    9                                 I. BACKGROUND
    10         The bankrupt debtor in this action, George Washington Bridge Bus Station
    11   Development Venture LLC (“Debtor”), is the redeveloper of a bus station of the
    12   Port Authority of New York and New Jersey (the “Port Authority”) located at the
    13   Manhattan end of the George Washington Bridge. In July of 2011, Debtor and the
    14   Port Authority entered into an agreement (the “Ground Lease”) providing that
    15   Debtor was to manage and oversee the approximately $183 million redevelopment
    16   project, and that, in return, Debtor would receive a 99-year lease to operate and
    17   maintain the approximately 129,000 square foot retail mall that would be erected
    18   at the bus station site. The Port Authority was to contribute approximately $52
    5
    1   million of the project’s costs, made in monthly installments, and the remainder of
    2   the funds would come from pre-petition lenders who made loans to Debtor
    3   secured by Debtor’s interest in the Ground Lease.
    4         As relevant here, the Ground Lease provides that Debtor was to hire
    5   contractors and subcontractors, including a general contractor, subject to the Port
    6   Authority’s approval. Section 5.7(c) of the Ground Lease states:
    7         Except as provided in Section 5.4 hereof, the Port Authority shall have
    8         no obligations or liabilities in connection with the performance of any
    9         Construction Work or the contracts for the performance thereof
    10         entered into by [Debtor.] Provided that the Port Authority shall pay
    11         the amounts due and owing under Section 5.4 hereof, [Debtor] shall
    12         pay all claims lawfully made against it by its contractors,
    13         subcontractors, material-men and workmen and all claims lawfully
    14         made against it by other third persons arising out of or in connection
    15         with or because of the performance of the Construction Work and
    16         shall cause its contractors and subcontractors to pay all such claims
    17         lawfully made against them. The obligations assumed by [Debtor]
    18         . . . in this [Ground Lease] shall not be limited, affected, impaired or
    6
    1         in any manner modified by [among other things] contracts covering
    2         the Construction Work.
    3   App’x at 97. Section 5.4, in turn, provides that “the Port Authority shall pay to
    4   [Debtor] a fixed price,” id. at 89, of approximately $52 million towards project costs
    5   and sets forth procedures by which payments were to be made, id. at 89–93. 1
    6         In June of 2013, nearly two years after Debtor and the Port Authority entered
    7   into the Ground Lease, Debtor and Tutor Perini entered into an agreement for
    8   Tutor Perini to act as the general contractor for the redevelopment project (the
    9   “Construction Contract”). However, Debtor and Tutor Perini found themselves
    10   in various disputes over the bills Tutor Perini submitted for payment pursuant to
    11   the Construction Contract, and Tutor Perini missed the deadline for project
    12   completion.    Subsequently, in February of 2015, Debtor filed an arbitration
    13   proceeding against Tutor Perini with the American Arbitration Association over
    14   the disputed bills Tutor Perini submitted.        Tutor Perini counterclaimed and
    1Additionally, Section 5.1.2(b) of the Ground Lease states that, “All . . . Construction
    Work shall be performed at [Debtor’s] sole cost and expense, subject to Section 5.4
    hereof.” App’x at 87 (underlining removed).
    7
    1   presented evidence in support of approximately $113 million in damages for
    2   Debtor’s failure to pay. 2
    3         In October of 2019, Debtor filed for Chapter 11 bankruptcy, which stayed
    4   the arbitration with Tutor Perini. Through the bankruptcy process, Debtor sought
    5   to sell substantially all of its assets, which most notably meant selling its rights in
    6   the Ground Lease. This is where § 365 of the Bankruptcy Code comes into play.
    7   As will be explained in more detail below, before Debtor could sell the Ground
    2Separately, in July of 2018, Tutor Perini sued the Port Authority in New York State
    Supreme Court, alleging that it was in “the functional equivalent of privity” with the Port
    Authority, despite Tutor Perini’s not being a party to the Ground Lease. App’x at 569.
    On July 5, 2019, the New York Supreme Court denied the Port Authority’s motion to
    dismiss. On February 18, 2021, the Appellate Division unanimously reversed that
    decision and granted the Port Authority’s motion to dismiss Tutor Perini’s breach of
    contract claim brought under the Ground Lease, reasoning that Tutor Perini is not in
    privity with the Port Authority. Tutor Perini Bldg. Corp. v. Port Auth. of N.Y. & N.J., 
    191 A.D.3d 569
    , 569–71 (1st Dep’t 2021). Tutor Perini was allowed to proceed on its claim
    against the Port Authority for unjust enrichment. 
    Id. at 571
    .
    Additionally, in January of 2020, Tutor Perini filed a separate action in the Southern
    District of New York against various parties connected to the redevelopment project. See
    Tutor Perini Bldg. Corp. v. N.Y.C. Reg’l Ctr., LLC et al., 1:20-cv-00731-PAE, ECF No. 1
    (S.D.N.Y. Jan. 27, 2020). The action was dismissed without prejudice via stipulation and
    order on July 14, 2021. 
    Id.
     at ECF No. 137.
    8
    1   Lease, it needed to satisfy the Bankruptcy Code’s requirement that it “cure[]” any
    2   default in the Ground Lease. See 
    11 U.S.C. § 365
    (b)(1)(A).
    3         Accordingly, Tutor Perini objected to Debtor’s selling the Ground Lease. It
    4   argued to the bankruptcy court that, because Debtor had yet to pay Tutor Perini’s
    5   approximately $113 million claim under the Construction Contract, Debtor had
    6   failed to cure a default under Section 5.7(c) of the Ground Lease, and thus § 365
    7   did not allow Debtor to sell the Ground Lease until Tutor Perini’s “cure claim”
    8   was paid. Separately, the Port Authority asserted its own cure claim against the
    9   Debtor under Section 5.7(c) of the Ground Lease, but Debtor and Port Authority
    10   ultimately reached a settlement. This left only Tutor Perini’s purported cure claim
    11   under § 365(b).
    12         After briefing and oral argument, the bankruptcy court (Chapman, Bankr. J.)
    13   approved the settlement with the Port Authority on July 14, 2020, and held that
    14   Tutor Perini could not reframe Debtor’s alleged failure to pay it under the
    15   Construction Contract as a default under the Ground Lease that vested Tutor
    16   Perini with the right to pursue a cure claim under § 365(b). It rejected the two
    17   arguments that Tutor Perini made to it: first, that it did not need contractual rights
    18   in the Ground Lease because “Section 365(b)(1)(A) contains no textual limitation
    9
    1   on who may assert a cure claim,” App’x at 585; and second, in the alternative, that
    2   it was a third-party beneficiary of the Ground Lease entitled to sue under it. Id. at
    3   584–85.
    4            Tutor Perini appealed to the United States District Court for the Southern
    5   District of New York, and the district court affirmed the bankruptcy court’s order.
    6   Tutor Perini Building Corp. v. N.Y.C. Reg’l Ctr. George Washington Bridge Bus Station
    7   and Infrastructure Dev. Fund LLC (In re George Washington Bridge Bus Station Dev.
    8   Venture LLC) (“In re GWB”), 
    2021 WL 3403590
     (S.D.N.Y. Aug. 4, 2021) (Rakoff, J.).
    9   The district court reasoned that Tutor Perini could not be a third-party beneficiary
    10   of the Ground Lease because, among other things, the Ground Lease specifically
    11   named several third-party beneficiaries, and none of them were Tutor Perini. 
    Id.
    12   at *4.    As to Tutor Perini’s arguments about the lack of textual limits in §
    13   365(b)(1)(A), the district court held that it is generally “only the non-debtor party
    14   to an assumed executory contract”—in this case, the Port Authority—who can
    15   assert a “cure claim under § 365(b),” and that Tutor Perini’s position—that “an
    16   economic interest in the [G]round [L]ease short of” an actual contractual right can
    10
    1   justify a cure claim—would “turn the Bankruptcy Code’s priority scheme on its
    2   head.” Id. at *5–6 (internal quotation marks omitted).
    3         This appeal followed.
    4                              II. STANDARD OF REVIEW
    5         In an appeal from a district court’s review of a bankruptcy court decision,
    6   this Court will “independently review the bankruptcy court’s decision, ‘accepting
    7   the bankruptcy court’s factual findings unless they are clearly erroneous and
    8   reviewing its conclusions of law de novo.’” Law Offices of Francis J. O’Reilly, Esq. v.
    9   Selene Fin., L.P. (In re DiBattista), 
    33 F.4th 698
    , 702 (2d Cir. 2022) (alteration marks
    10   omitted) (quoting Jackson v. Novak (In re Jackson), 
    593 F.3d 171
    , 176 (2d Cir. 2010)).
    11                                    III. DISCUSSION
    12         The main issue in this appeal involves the bounds of 
    11 U.S.C. § 365
    (b)(1)(A),
    13   and specifically whether it allows a creditor in Tutor Perini’s position to assert a
    14   “cure claim,” which entitles a creditor to the highest priority of payment under the
    15   Bankruptcy Code, even if the creditor has no contractual rights in the contract or
    16   lease being assumed. We also resolve Tutor Perini’s alternative arguments that it
    17   does in fact have rights under the Ground Lease, including as a third-party
    18   beneficiary.
    11
    1   A. Assumption of Executory Contracts and Unexpired Leases and the Right of
    2      Cure
    3          To understand the main issue on appeal, one must first understand the
    4   Bankruptcy Code’s rules for assuming an “executory contract or unexpired lease,”
    5   § 365(a), 3 and how such assumption affects the priority of claims.
    6          “[C]ontract assumption is an important re-organizational tool under
    7   Chapter 11 because it allows a trustee, or a debtor in possession, ‘to go through the
    8   inventory of executory contracts and decide which ones it would be beneficial to
    9   adhere to and which ones it would be beneficial to reject.’” ReGen Capital I, Inc. v.
    10   Halperin (In re U.S. Wireless Data, Inc.), 
    547 F.3d 484
    , 488 (2d Cir. 2008) (alteration
    11   marks and internal citation omitted) (quoting Med. Malpractice Ins. Ass’n v. Hirsch
    12   (In re Lavigne), 
    114 F.3d 379
    , 386 (2d Cir. 1997)). When a debtor assumes an
    13   executory contract, it “effectively . . . compel[s] non-debtor parties to [such]
    14   contracts ‘to continue to do business’” with the debtor, even though the debtor’s
    15   having filed for bankruptcy “‘might otherwise make [non-debtor contracting
    3By an “executory contract,” we mean one where “the obligation of both the bankrupt
    and the other party to the contract are so far unperformed that the failure of either to
    complete performance would constitute a material breach excusing the performance of
    the other.” ReGen Capital I, Inc. v. Halperin (In re U.S. Wireless Data, Inc.), 
    547 F.3d 484
    , 488
    n.1 (2d Cir. 2008) (quoting Vern Countryman, Executory Contracts in Bankruptcy: Part I, 
    57 Minn. L. Rev. 439
    , 460 (1973)).
    12
    1   parties] reluctant to do so.’” 
    Id.
     (quoting Frito-Lay, Inc. v. LTV Steel Co. (In re
    2   Chateaugay Corp.), 
    10 F.3d 994
    , 955 (2d Cir. 1993)).
    3         However, “a debtor cannot assume [an executory] contract unless the debtor
    4   satisfies several statutory conditions designed to make the non-debtor contracting
    5   party whole.” 
    Id.
     at 489 (citing E. Air Lines, Inc. v. Ins. Co. of the State of Pa. (In re
    6   Ionosphere Clubs, Inc.), 
    85 F.3d 992
    , 999 (2d Cir. 1996)). “Specifically, a debtor must
    7   (1) cure the default, or provide adequate assurance that it will promptly cure it; (2)
    8   compensate, or provide adequate assurance that the trustee will promptly
    9   compensate, the non-debtor party to the contract for any actual monetary loss
    10   caused by the debtor’s default; and (3) provide adequate assurance of future
    11   performance under the contract.” 
    Id.
     (citing 
    11 U.S.C. § 365
    (b)(1)(A)-(C)).
    12         Importantly, because a debtor must “cure” a default under § 365(b)(1)(A)
    13   before assuming an executory contract, “[c]laims arising under contracts or leases
    14   so assumed are afforded administrative priority” under Sections 503 and 507 of
    15   the Bankruptcy Code. See In re Chateaugay Corp., 10 F.3d at 952, 954; see also
    16   American Anthrocite & Bituminous Coal Corp. v. Leonardo Arrivabene, S.A., 
    280 F.2d 17
       119, 124 (2d Cir. 1960) (explaining, in the era prior to § 365’s enactment, the
    18   “equitable right” to “first priority” that applied to claims under “an executory
    13
    1   contract” that “the trustee or debtor in possession elect[ed] to assume” (internal
    2   quotation marks omitted)). In other words, when a creditor of a debtor has a claim
    3   arising from a default in an executory contract the debtor wishes to assume, that
    4   creditor’s claim must be paid 100 cents on the dollar before the debtor may assume
    5   it, even if that creditor would otherwise “receive the priority provided [to] general
    6   unsecured creditors.” See N.L.R.B. v. Bildisco & Bildisco, 
    465 U.S. 513
    , 531 (1984)
    7   (citing 
    11 U.S.C. §§ 502
    (g) & 507).
    8   B. Requirements for Asserting a Section 365(b)(1) Cure Claim
    9         Tutor Perini argues that, although it is not a party to the Ground Lease, it
    10   may assert a cure claim via § 365(b)(1)(A) because the text of § 365(b)(1)(A) “does
    11   not limit who may assert a cure claim.” Appellant’s Br. at 23. Specifically, the text
    12   does not state that only a party to the assumed contract may do so. Thus, under
    13   Tutor Perini’s view, it is entitled to full recovery on its claims under the
    14   Construction Contract because Section 5.7(c) of the Ground Lease requires Debtor
    15   to pay the amounts due to all those hired to work on the redevelopment project.
    16         We disagree with Tutor Perini’s reading of the statute, and we hold that, to
    17   receive priority under § 365(b)(1)(A), a creditor asserting a default must have some
    18   right to pursue a breach of contract claim under the executory contract or
    14
    1   unexpired lease a debtor assumes under § 365(a). See In re Wireless Data, 
    547 F.3d 2
       at 495 (explaining that “a cure . . . is a claim against the [d]ebtor under an executory
    3   contract that arose prior to the commencement of the Chapter 11 case and that the
    4   [d]ebtor ha[s] in fact assumed” (emphasis added) (internal quotation marks,
    5   alteration marks, and citations omitted)). We reach this holding for two main
    6   reasons.
    7         First, although Tutor Perini is correct that § 365(b) does not spell out which
    8   parties may raise a default in an assumed contract or lease to seek priority on their
    9   claims, it is a well-established rule of Bankruptcy Code construction that,
    10   “[b]ecause the presumption in bankruptcy cases is that the debtor’s limited
    11   resources will be equally distributed among his creditors, statutory priorities are
    12   narrowly construed.” Supplee v. Bethlehem Steel Corp. (In re Bethlehem Steel Corp.),
    13   
    479 F.3d 167
    , 172 (2d Cir. 2007) (quoting Trs. of Amalgamated Ins. Fund v. McFarlin’s,
    14   Inc., 
    789 F.2d 98
    , 100 (2d Cir. 1986)). “[I]f one claimant is to be preferred over
    15   others, the purpose should be clear from the statute.” Nathanson v. N.L.R.B., 344
    
    16 U.S. 25
    , 29 (1952).
    17         As demonstrated from the above, reading § 365(b)’s grant of priority as
    18   cabined to non-debtors with rights under an assumed contract furthers a clear
    15
    1   statutory purpose:    It “make[s] the non-debtor contracting party whole” by
    2   guaranteeing that party the benefit of its bargain before it must continue to
    3   perform under the contract for the debtor’s benefit. In re Wireless Data, 
    547 F.3d at
    4   489. We have previously said that “Congress’s intent in imposing these conditions
    5   on the ability of the debtor to assume the contract was to insure that the contracting
    6   parties receive the full benefit of their bargain if they are forced to continue
    7   performance.” In re Ionosphere Clubs, 
    85 F.3d at 999
     (internal quotation marks
    8   omitted). Other Circuits have read § 365 as similarly premised on an intent to
    9   protect the non-debtor parties to contracts. See, e.g., Century Indemnity Co. v. Nat’l
    10   Gypsum Co. (In re Nat’l Gypsum Co.), 
    208 F.3d 498
    , 506 (5th Cir. 2000) (“[T]he debtor
    11   party must take full account of the cost to cure all existing defaults owed to the
    12   non-debtor party when assessing whether the contract is beneficial to the estate.”);
    13   In re Superior Toy & Mfg. Co., 
    78 F.3d 1169
    , 1174 (7th Cir. 1996) (“Section 365 was
    14   clearly intended to insure that the contracting parties receive the full benefit of
    15   their bargain if they are forced to continue performance.”). That intent is effected
    16   where an actual party to the Ground Lease—here, the Port Authority—seeks cure
    17   claim treatment before Debtor’s trustee assumes the Ground Lease.
    18         By contrast, we do not see how it furthers any statutory purpose to read
    16
    1   § 365(b) as granting administrative priority to someone whose claims against the
    2   debtor do not arise from a contract assumed under § 365(a). Tutor Perini argues
    3   that disallowing a non-party to a contract to assert a cure claim under
    4   § 365(b)(1)(A) would “provide the debtor with an unjustified windfall” since the
    5   debtor would assume the contract without “satisfy[ing] all defaulted obligations
    6   under the subject contract.” Appellant’s Br. at 23. But we think it is the non-party
    7   seeking payment under a contract who would receive an unjustified windfall. A
    8   non-party to a contract assumed under § 365(a) has no relevant bargain with the
    9   debtor and owes the debtor no performance under that contract. Affording that
    10   non-party administrative priority would let it cut the line and stand in front of
    11   even secured creditors in exchange for nothing. 4
    12         Second, by reading § 365(b) as providing priority only to those with claims
    13   under a contract assumed via § 365(a), we make the most sense of § 365 and the
    4This understanding—that the Bankruptcy Code generally grants administrative priority
    in exchange for something that benefits a debtor’s reorganization—is consistent with how
    we have construed a creditor’s entitlement to payment of an administrative expense
    under §§ 503(b)(1)(A) and 507(a)(1): “An expense is administrative only if it arises out of
    a transaction between the creditor and the bankrupt’s trustee or debtor in possession, and
    only to the extent that the consideration supporting the claimant’s right to payment was
    both supplied to and beneficial to the debtor-in-possession in the operation of the
    business.” In re Bethlehem Steel, 
    479 F.3d at 172
     (alteration marks omitted) (quoting
    McFarlin’s, 
    789 F.2d at 101
    ).
    17
    1   “Bankruptcy Code as a whole.” Smart World Techs., LLC v. Juno Online Servs., Inc.
    2   (In re Smart World Techs., LLC), 
    423 F.3d 166
    , 183 (2d Cir. 2005) (citing Off. Comm.
    3   of Unsecured Creditors of Cybergenics Corp. ex rel. Cybergenics Corp. v. Chinery, 330
    
    4 F.3d 548
    , 560 (3d Cir. 2003)); see also Pettus v. Morgenthau, 
    554 F.3d 293
    , 297 (2d Cir.
    5   2009) (“[W]hen construing the plain text of a statutory enactment[,] . . . . we
    6   attempt to ascertain how a reasonable reader would understand the statutory text,
    7   considered as a whole.” (citing Robinson v. Shell Oil Co., 
    519 U.S. 337
    , 341 (1997))).
    8         For one thing, Tutor Perini’s argument urges us to infer an expansive
    9   priority right under § 365(b)(1)(A) based on “the lack of a textual limitation,” i.e.,
    10   statutory silence. Appellant’s Br. at 25. But statutory silence in this context
    11   generally cuts the other way, for, as the Supreme Court has explained, “[t]he
    12   importance of the priority system leads us to expect more than simple statutory
    13   silence if, and when, Congress were to intend a major departure.” Czyzewski v.
    14   Jevic Holding Corp., 
    580 U.S. 451
    , 465 (2017).
    15         For another thing, other portions of § 365 strongly suggest that the statute
    16   provides rules of priority that govern the claims brought by creditors who seek to
    17   recover based on their rights in a contract that is assumed or rejected, and not as a
    18   means of modifying the rules of priority for anyone else. See CSX Transp., Inc. v.
    18
    1   Island Rail Terminal, Inc., 
    879 F.3d 462
    , 470–71 (2d Cir. 2018) (“The meaning of a
    2   statute can be understood ‘in context with and by reference to the whole statutory
    3   scheme by appreciating how sections relate to one another.’” (quoting Auburn
    4   Hous. Auth. v. Martinez, 
    277 F.3d 138
    , 144 (2d Cir. 2002))).            For example, §
    5   365(b)(1)(B), which details the trustee’s additional responsibilities with regard to
    6   assumed executory contracts, specifically speaks to the rights of creditors who are
    7   parties to a contract: It says that “a party other than the debtor to [the relevant]
    8   contract or lease” has a priority right to be “compensate[d] . . . for any actual
    9   pecuniary loss . . . resulting from [a] default.” See also In re GWB, 
    2021 WL 3403590
    ,
    10   at *6 (district court observing the same). Section 365(g), regarding the rejection of
    11   an executory contract, also speaks to the priority rights of creditors with claims
    12   actually arising under a contract: It provides that, absent exceptions not relevant
    13   here, “the rejection [by the debtor or trustee] of an executory contract or unexpired
    14   lease of the debtor constitutes a breach of such contract or lease.” 
    11 U.S.C. § 15
       365(g). The resulting “[breach of contract] claim [by the non-debtor party to the
    16   contract] is treated as a pre-petition unsecured claim.” In re Lavigne, 114 F.3d at
    17   389; see Adelphia Bus. Sols., Inc. v. Abnos, 
    482 F.3d 602
    , 606 (2d Cir. 2007) (“Rejection”
    18   allows a non-debtor contracting party to “seek allowance of its claims . . . with the
    19
    1   same priority as a general unsecured creditor.”). Thus, in both of these subsections
    2   of § 365, Congress clearly contemplated the rules of priority for creditors with
    3   claims actually arising under contracts, and not just for any party who claims some
    4   tangential interest in a contract short of a legal right to sue under it. It is thus hard
    5   to fathom that the same Congress that wrote these subsections would have
    6   intended a far broader view of priority in § 365(b)(1)(A) alone.
    7         Particularly in light of § 365(g)’s rule regarding the low-priority treatment
    8   of creditors alleging a breach of a rejected executory contract, Tutor Perini’s
    9   position regarding § 365(b)(1)(A) makes little sense when one considers a case, like
    10   this one, where a creditor who is not a party to an assumed contract has its own
    11   independent contract with a debtor.          Recall that Tutor Perini has its own
    12   Construction Contract with Debtor—indeed, Tutor Perini told the bankruptcy
    13   court that it had “claims” against Debtor “under the Construction Contract,”
    14   App’x at 12, and that the damages Tutor Perini seeks “aris[e] from the Debtor’s
    15   breach of its [C]onstruction [C]ontract with Tutor Perini,” App’x at 11. Assume,
    16   hypothetically, that the Construction Contract is an executory contract within the
    17   meaning of § 365(a). If Debtor were to reject the Construction Contract under §
    18   365(a), then § 365(g) would treat this as a breach of the Construction Contract and
    20
    1   provide Tutor Perini with “a pre-petition unsecured claim,” In re Lavigne, 
    114 F.3d 2
       at 389, meaning Tutor Perini would be disabled from bringing a cure claim based
    3   on the Construction Contract. And yet, if we were to accept Tutor Perini’s
    4   interpretation of § 365(b)(1)(A), § 365(g) would become irrelevant, as Debtor
    5   would still have to pay Tutor Perini’s Construction Contract claim as if it had
    6   administrative priority.       It is difficult to believe that this is what Congress
    7   intended. Cf. Czyzewski, 580 U.S. at 466 (“Congress does not, one might say, hide
    8   elephants in mouseholes.” (alteration marks omitted) (quoting Whitman v. Am.
    9   Trucking Assns., Inc., 
    531 U.S. 457
    , 468 (2001))). 5
    10          For the above reasons, we conclude that the Bankruptcy Code does not
    11   entitle Tutor Perini, a non-party to the Ground Lease, to assert a cure claim under
    12   § 365(b)(1)(A) based on a purported default under that lease.
    5
    The cases Tutor Perini relies on in suggesting that non-parties to a contract can assert
    cure claims under § 365(b)(1)(A) are readily distinguishable. Each of those cases involved
    a debtor’s former landlord who had transferred to a new landlord its interests in the lease
    while specifically retaining its cure rights against the debtor/(former) lessee. See ECPG
    (Peoria) Assocs. Ltd. P’shp. v. Bldg. Block Child Care Ctrs., Inc. (In re Bldg. Block Child Care
    Ctrs., Inc.), 
    234 B.R. 762
    , 766 (B.A.P. 9th Cir. 1999); In re USN Commc’ns, Inc., 
    1999 WL 33496079
    , at *3–4 (Bankr. D. Del. July 30, 1999). Thus, these cases do not support Tutor
    Perini’s assertion that an entity that was never party to a lease agreement and which has
    no contractual rights of its own under that lease may assert a cure claim based on the
    assumption of that lease.
    21
    1   C. Potential Third-Party Beneficiary Rights Under an Assumed Contract
    2         In the alternative, Tutor Perini argues that it does have contractual rights in
    3   the Ground Lease sufficient to pursue a cure claim, either by virtue of “Debtor’s
    4   delegation to and Tutor Perini’s assumption of [certain] Ground Lease
    5   obligations,” or by being “a third-party beneficiary.” Appellant’s Br. at 30, 34. We
    6   reject both claims.
    7         First, although Tutor Perini asserts rights by virtue of being an assumptor,
    8   assignee, and delegatee, it never raised these arguments below in either the
    9   bankruptcy court or the district court. Accordingly, these arguments are waived.
    10   In re Johns-Manville Corp., 
    759 F.3d 206
    , 219 (2d Cir. 2014).
    11         Second, as to Tutor Perini’s remaining claim that it has the status of a third-
    12   party beneficiary, it is worth noting, as an initial matter, that no party contests
    13   whether third-party beneficiary status is a sufficient contractual right to pursue a
    14   cure claim under § 365(b). Regardless of whether third-party beneficiaries have a
    22
    1   right to assert a cure claim, 6 Tutor Perini’s claim fails because it is not a third-party
    2   beneficiary.
    3         Whether Tutor Perini may sue as a “third-party beneficiary” of the Ground
    4   Lease is a matter controlled by “relevant state law.” Silverman v. Teamsters Loc. 210
    5   Affiliated Health & Ins. Fund, 
    761 F.3d 277
    , 286 (2d Cir. 2014). The Ground Lease
    6   states that it is governed by New York law. New York contract law distinguishes
    7   between an intended third-party beneficiary who “may sue . . . on a contract made
    8   for its benefit,” and “an incidental beneficiary with no right to enforce [a]
    9   particular contract[].” Dormitory Auth. of N.Y. v. Samson Constr. Co., 
    30 N.Y.3d 704
    ,
    10   710 (2018) (internal quotation and alteration marks omitted). In particular, New
    11   York law recognizes that “construction contracts . . . generally require[] express
    12   contractual language stating that the contracting parties intended to benefit a third
    13   party” in order for that third party to sue. Id.; see also India.Com, Inc. v. Dalal, 412
    
    14 F.3d 315
    , 321 (2d Cir. 2005) (clause “entitled ‘No Third Party Beneficiaries,’ clearly
    6Although we do not need to resolve in this case whether third-party beneficiaries of a
    contract assumed under § 365(a) can seek priority under § 365(b), there are sound reasons
    to think that Congress would have wanted third-party beneficiaries to be able to assert
    cure claims. After all, a third-party beneficiary is one who has a “right to performance”
    under a contract because “the intention of the parties” to that contract was to afford the
    third party such a right. Restatement (Second) of Contracts § 302 (1981). Thus, protecting
    the non-debtor contracting party’s bargain reasonably includes allowing the intended
    third-party beneficiary to be made whole as well.
    23
    1   provided” that contract was not “intended to create any right, claim or remedy in
    2   favor of any person or entity other than the parties hereto” and “foreclosed the
    3   [third-party beneficiary] theory of recovery on which Dalal and the District Court
    4   relied” (some internal quotation marks omitted)). Further, as New York courts
    5   have held, “in instances where the contract in issue makes clear that a third party
    6   will be retained to assist in the performance by the promisee[,] . . . such third
    7   parties are not intended beneficiaries of the main contract.” Subaru Distribs. Corp.
    8   v. Subaru of Am., Inc., 
    425 F.3d 119
    , 125 (2d Cir. 2005) (rejecting third-party
    9   beneficiary status) (quoting Artwear, Inc. v. Hughes, 
    202 A.D.2d 76
    , 83 (1st Dep’t
    10   1994)).
    11         Tutor Perini argues that it is an intended third-party beneficiary because the
    12   Ground Lease’s Section 5.7(c) states that Debtor was obligated to make payments
    13   to the redevelopment project’s various contractors, subcontractors, and other
    14   parties hired by Debtor. However, we think the district court correctly read this
    15   portion of the Ground Lease—in which Debtor agreed to “pay all claims lawfully
    16   made against it by its contractors,” App’x at 97—as “simply allocat[ing] payment
    17   responsibilities to [Debtor] rather than the Port Authority” and not as Debtor’s
    18   promise to perform obligations for the benefit of Tutor Perini or any other
    24
    1   contractor. In re GWB, 
    2021 WL 3403590
    , at *4. The rest of Section 5.7(c) confirms
    2   that this promise to pay was meant for Port Authority’s benefit, and not for any
    3   as-yet unhired contractors, as it states that “the Port Authority shall have no
    4   obligations or liabilities in connection with the performance of any Construction
    5   Work or the contracts for the performance thereof entered into by [Debtor],” App’x
    6   at 97. See Subaru Distributors Corp., 425 F.3d at 126 (holding that a contract’s
    7   requiring a party “to appoint sub-distributors does not, as a matter of law, make
    8   the sub-distributors intended beneficiaries”).     Moreover, the Ground Lease
    9   specifically names certain “third-party beneficiaries of this Agreement,” App’x at
    10   173, but nowhere does it name Tutor Perini or otherwise indicate that Tutor Perini
    11   was intended to be among them. This tells us that the “parties to [the] contract
    12   . . . intended the omission” of other third-party beneficiaries. Quadrant Structured
    13   Prods. Co. v. Vertin, 
    23 N.Y.3d 549
    , 560 (2014) (holding that textual omissions in a
    14   “no-action clause” placed limits on the situations in which certain parties could
    15   and could not bring suit to enforce a contract); see also India.Com, 412 F.3d at 321
    16   (holding that appellee was not a third-party beneficiary entitled to sue where a
    17   contract stated that a section was not “intended to create any right, claim or
    18   remedy in favor of any person or entity other than” specific, listed parties). Thus,
    25
    1   Tutor Perini is not a third-party beneficiary of the Ground Lease.
    2                                 IV.   CONCLUSION
    3         Tutor Perini’s expansive view of the priority rights conferred by 
    11 U.S.C. § 4
      365(b)(1)(A) is inconsistent with applicable principles of Bankruptcy Code
    5   interpretation, and its third-party beneficiary argument is inconsistent with
    6   controlling principles of New York contract law. Thus, for the foregoing reasons,
    7   we AFFIRM the district court’s judgment.
    26
    

Document Info

Docket Number: 21-2050

Filed Date: 4/10/2023

Precedential Status: Precedential

Modified Date: 4/10/2023

Authorities (19)

ECPG (Peoria) Associates Ltd. Partnership v. Building Block ... , 234 B.R. 762 ( 1999 )

Supplee v. Bethlehem Steel Corp. , 479 F.3d 167 ( 2007 )

CSX Transportation, Inc. v. Island Rail Terminal, Inc. , 879 F.3d 462 ( 2018 )

Auburn Housing Authority v. Martinez , 277 F.3d 138 ( 2002 )

Silverman v. Teamsters Local 210 Affiliated Health & ... , 761 F.3d 277 ( 2014 )

Common Law Settlement Counsel v. Travelers Indemnity Co. (... , 759 F.3d 206 ( 2014 )

Quadrant Structured Products Co. v. Vertin , 23 N.Y.3d 549 ( 2014 )

In re Superior Toy & Manufacturing Co. , 78 F.3d 1169 ( 1996 )

Trustees of the Amalgamated Insurance Fund v. McFarlin's, ... , 789 F.2d 98 ( 1986 )

in-re-ionosphere-clubs-inc-eastern-air-lines-inc-and-bar-harbor , 85 F.3d 992 ( 1996 )

Adelphia Business Solutions, Inc., Debtor-Appellee v. ... , 482 F.3d 602 ( 2007 )

Jackson v. Novak (In Re Jackson) , 593 F.3d 171 ( 2010 )

ReGen Capital I, Inc. v. Halperin (In Re U.S. Wireless Data,... , 547 F.3d 484 ( 2008 )

Pettus v. Morgenthau , 554 F.3d 293 ( 2009 )

Artwear, Inc. v. Hughes , 615 N.Y.S.2d 689 ( 1994 )

Dormitory Auth. of N.Y. v. Samson Constr. Co. , 30 N.Y.3d 704 ( 2018 )

Robinson v. Shell Oil Co. , 117 S. Ct. 843 ( 1997 )

Whitman v. American Trucking Assns., Inc. , 121 S. Ct. 903 ( 2001 )

National Labor Relations Board v. Bildisco & Bildisco , 104 S. Ct. 1188 ( 1984 )

View All Authorities »