Field Intelligence Inc v. Xylem Dewatering Solutions Inc ( 2022 )


Menu:
  •                                 PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    No. 21-2087
    FIELD INTELLIGENCE INC
    v.
    XYLEM DEWATERING SOLUTIONS INC,
    Appellant
    Appeal from the United States District Court
    for the District of New Jersey
    (D.C. Civil Action No. 1-19-cv-20590)
    District Judge: Honorable Joseph H. Rodriguez
    Argued on January 11, 2022
    Before: AMBRO, BIBAS, and ROTH, Circuit Judges
    (Opinion filed: September 13, 2022)
    Christopher Larus
    Benjamen C. Linden
    Rajin S. Olson
    David A. Prange (Argued)
    Robins Kaplan
    800 LaSalle Avenue
    2800 LaSalle Plaza
    Minneapolis, MN 55402
    Counsel for Appellant
    Aaron M. Frankel (Argued)
    Kramer Levin Naftalis & Frankel
    1177 Avenue of the Americas
    New York, NY 10036
    Counsel for Appellee
    _________
    OPINION OF THE COURT
    ____________
    AMBRO, Circuit Judge
    Two companies, Xylem Dewatering Solutions and Field
    Intelligence, entered into two contracts. The first contained an
    arbitration provision; the second required the parties to litigate
    their disputes. As sure as Camille coughing in the first scene
    and dying of consumption in the last, a conflict arose between
    the businesses. Field Intelligence filed suit in federal court
    alleging a breach of their second agreement. Xylem,
    2
    unconvinced that Field Intelligence’s lawsuit did not implicate
    the parties’ first contract, filed an arbitration demand and
    moved to stay the federal litigation pending the outcome of the
    arbitration.
    Field Intelligence protested. It asked the District Court
    to hold that the parties’ second contract superseded the first
    such that the arbitration provision contained in that earlier
    agreement was no longer in effect. While disputing this
    interpretation of the contracts, Xylem responded that Field
    Intelligence’s supersession challenge could, per the first
    contract’s arbitration provision, only be decided by an
    arbitrator. The Court disagreed. It held, first, that it had
    authority to decide the supersession issue and, second, that the
    parties’ later agreement did supersede their earlier contract,
    thereby eliminating any duty to arbitrate. Xylem appeals both
    rulings.
    We agree with the District Court that it was authorized
    to determine whether the parties’ second agreement
    superseded, and hence replaced, their first. But we disagree
    that the first agreement was superseded. We therefore reverse
    in part, vacate in part, and remand for further proceedings.
    I. Background
    Xylem is a water technology company that
    manufactures and sells large-capacity water pumps. It wanted
    a better way for its customers to monitor those pumps
    remotely. In 2012 it called on Field Intelligence to develop a
    custom telematics solution that would consist of hardware built
    to interface with the pumps (“Hardware Units” or “Units”), and
    3
    computer software and support services for monitoring and
    controlling the equipment.
    Two contracts followed. The first, in 2013, was a “Non-
    Disclosure Agreement.” It governed the disclosure and
    protection of “certain information and related materials” that
    the parties considered to be “confidential and secret and in
    which each has a proprietary interest” in connection with their
    “development of a custom telematics solution.” Appx. 531.
    Significantly, the agreement contained an arbitration provision
    requiring that any “dispute, controversy or claim arising out of
    or in connection with this Agreement, or the breach,
    termination or invalidity thereof,” be “settled by arbitration in
    accordance with the Rules of the American Arbitration
    Association.” Id. at 533.
    The parties launched the first-generation Hardware
    Units shortly thereafter. Second-generation Units became
    available around December 2014. Xylem purchased them
    from Field Intelligence via written Purchase Orders. It also
    purchased monthly subscriptions that permitted Xylem’s
    customers to access and use Field Intelligence’s software via
    satellite or cellular networks, thereby allowing them to monitor
    and control their Xylem pumps using the Hardware Units.
    There was no written agreement governing Xylem’s
    software subscription purchases until 2017, when the parties
    signed the second contract relevant to this dispute: the
    “Software Subscription Service Agreement.” It states that
    Field Intelligence is “the owner of certain proprietary computer
    software” and “sells subscriptions for subscribers to access and
    use” that software. Id. at 535. The contract allowed Xylem to
    access the software via a Field Intelligence-hosted website and
    4
    provided subscription terms and monthly fees based on the
    number of Hardware Units actively deployed in the field.
    The 2017 agreement also contained an “integration
    clause” (known also as a “merger clause”) stating that “[t]his
    Agreement constitutes the entire agreement between the parties
    with respect to its subject matter, and supersedes any and all
    prior or contemporaneous understandings or agreements
    whether written or oral.” Id. at 540. And, unlike its
    predecessor, the 2017 contract contained no arbitration
    provision, instead requiring any “action under or concerning”
    that contract to be litigated in a state or federal court in New
    Jersey. Id. at 539.
    Eventually, Xylem began building its own hardware.
    Suspecting Xylem had developed its product by reverse-
    engineering the Units, Field Intelligence sued it for breach of
    the 2017 contract, among other things. Per that contract’s
    forum-selection provision, Field Intelligence filed its action in
    the U.S. District Court for the District of New Jersey. Its
    complaint did not mention the 2013 contract, let alone allege
    any breach of that first agreement.
    Xylem moved to dismiss on the following rationale:
    Field Intelligence could not maintain its breach-of-contract
    claim because, even if Xylem had reverse-engineered the
    Hardware Units, the 2017 agreement did not bar it from doing
    so. The District Court rejected that interpretation of the
    contract and denied Xylem’s motion to dismiss in part.
    The parties then moved to discovery. Xylem sent Field
    Intelligence an interrogatory request asking if it intended to
    5
    rely on the parties’ 2013 contract to support any of its claims.
    Field Intelligence responded that
    Xylem breached the provisions [of the 2013
    contract] by copying the design and functionality
    of the [Hardware Units], modifying [them],
    using [them] to test and develop Xylem’s knock
    off designs, sending [them] to APD&M for
    purposes of developing Xylem’s knock off
    designs, and not taking reasonable precautions to
    protect the[ir] confidentiality . . . .
    Id. at 827.
    A month later, Xylem filed an arbitration demand with
    the American Arbitration Association seeking various forms of
    declaratory relief, including a determination that it did not
    breach the 2013 contract. It then moved to stay the federal
    litigation pending resolution of the arbitration. It argued that
    Field Intelligence’s interrogatory response revealed for the first
    time its intent to rely on the 2013 agreement as requiring
    Xylem to maintain the confidentiality of the Hardware Units.
    Xylem disputed this interpretation, as it maintained that these
    questions of contract scope and meaning were not for the
    District Court to decide but instead delegated to an arbitrator
    under the 2013 contract’s arbitration provision.
    Field Intelligence opposed and cross-moved to enjoin
    the arbitration. Its claim was that the 2017 agreement
    superseded the 2013 contract such that the earlier agreement to
    arbitrate ceased. The District Court agreed. It held first that
    it—rather than an arbitrator—needed to determine whether the
    2013 contract was still in effect. Second, it ruled that the 2017
    6
    agreement did replace the parties’ 2013 contract, thereby
    eliminating any arbitration obligation contained in the prior
    agreement. The Court enjoined the arbitration and denied as
    moot Xylem’s motion to stay the federal litigation. This appeal
    followed.
    II. Jurisdiction and Standard of Review
    The District Court had jurisdiction under 
    28 U.S.C. §§ 1331
     and 1332.         Our jurisdiction is under 
    9 U.S.C. § 16
    (a)(1)(A), which allows us to consider an order refusing a
    stay pending arbitration. We review anew (or de novo) the
    District Court’s denial of Xylem’s motion to stay proceedings
    pending arbitration. MZM Constr. Co. v. N.J. Bldg. Laborers
    Statewide Benefit Funds, 
    974 F.3d 386
    , 395 (3d Cir. 2020)
    (fresh review where district court has denied a party’s “asserted
    right to have [an] issue submitted to arbitration”).
    III. Discussion
    Congress enacted the Federal Arbitration Act, 
    9 U.S.C. § 1
     et seq., “to reverse the longstanding judicial hostility to
    arbitration agreements” and place them on “the same footing
    as other contracts,” Spinetti v. Serv. Corp. Int’l, 
    324 F.3d 212
    ,
    218 (3d Cir. 2003) (quoting Gilmer v. Interstate/Johnson Lane
    Corp., 
    500 U.S. 20
    , 24 (1991)). It “reflects the fundamental
    principle that arbitration is a matter of contract.” Rent-A-Ctr.,
    W., Inc. v. Jackson, 
    561 U.S. 63
    , 67 (2010). Arbitration
    agreements are thus “valid, irrevocable, and enforceable, save
    upon such grounds as exist at law or in equity for the revocation
    of any contract.” 
    9 U.S.C. § 2
    . If a court is “satisfied that the
    making of the agreement for arbitration . . . is not in issue,” it
    must send the parties to an arbitrator. 
    Id.
     § 4.
    7
    Parties may refer more than the merits of their disputes
    to arbitration. They may also agree to delegate to an arbitrator
    “‘gateway’ questions of ‘arbitrability,’ such as whether the
    parties have agreed to arbitrate or whether their agreement
    covers a particular controversy.” Henry Schein, Inc. v. Archer
    & White Sales, Inc., 
    139 S. Ct. 524
    , 529 (2019) (quoting Rent-
    A-Ctr., 561 U.S. at 68–69). This appeal involves such a
    threshold question: whether Field Intelligence is bound by the
    arbitration provision in the parties’ 2013 contract, or whether
    the 2017 agreement superseded that contract completely,
    thereby eliminating its duty to arbitrate.
    Two issues stem from this gateway concern. First, who
    should decide whether the second contract replaced the first, a
    court or an arbitrator? Second, if a court, rather than an
    arbitrator, should decide, does the parties’ 2017 contract in fact
    supersede their earlier agreement? Field Intelligence also asks
    us to consider a third issue: whether Xylem waived any right
    to seek arbitration under the 2013 contract by participating in
    this federal litigation. We address each in turn.
    A.
    To the first issue, we hold that the parties’ supersession
    dispute is for a court, not an arbitrator, to decide. That
    conclusion flows necessarily from a first principle of
    arbitration law: that “arbitration is strictly a matter of consent.”
    Lamps Plus, Inc. v. Varela, 
    139 S. Ct. 1407
    , 1415 (2019)
    (alteration adopted) (quoting Granite Rock Co. v. Teamsters,
    
    561 U.S. 287
    , 299 (2010)). An arbitrator’s authority is limited
    to those claims that “the parties have agreed to submit to
    arbitration.” First Options of Chi., Inc. v. Kaplan, 
    514 U.S.
                                    8
    938, 943 (1995); AT&T Techs., Inc. v. Commc’ns Workers of
    Am., 
    475 U.S. 643
    , 648–49 (1986). So before sending parties
    to an arbitrator, a court must decide whether they agreed to
    resolve their dispute in that forum, First Options, 514 U.S. at
    943, which in turn requires it to determine “whether an
    arbitration agreement exists at all,” Williams v. Medley Opp.
    Fund II, LP, 
    965 F.3d 229
    , 237 n.7 (3d Cir. 2020) (quoting
    Lloyd’s Syndicate 457 v. FloaTEC, L.L.C., 
    921 F.3d 508
    , 515
    n.4 (5th Cir. 2019)); Henry Schein, 
    139 S. Ct. at 530
     (“[B]efore
    referring a dispute to an arbitrator, the court determines
    whether a valid arbitration agreement exists.”). Because the
    substance of the parties’ supersession dispute is “whether there
    is an agreement to arbitrate,” Jaludi v. Citigroup, 
    933 F.3d 246
    ,
    255 (3d Cir. 2019), the District Court rightly declined to send
    it to an arbitrator.
    Xylem asks us to view this case differently. It points to
    the general rule, referenced above, that parties may delegate
    threshold arbitrability issues to an arbitrator provided there is
    “clear and unmistakable” evidence they agreed to do so. First
    Options, 514 U.S. at 944 (alterations adopted) (internal
    quotation marks omitted). The 2013 contract’s arbitration
    provision, it says, contains such clear and unmistakable
    evidence, as it expressly delegates arguments over its
    “termination or invalidity” to an arbitrator. Appx. 533. Hence
    that person, not a court, must decide the supersession dispute.
    Were this fight simply about whether the 2013
    agreement had terminated or was invalid, we might agree. But
    the question here is whether, by the later contract, the parties
    intended to extinguish their prior agreement and litigate any
    disputes between them moving forward. Put another way, if
    9
    Field Intelligence is correct that the 2017 contract superseded
    the 2013 agreement, then there is no arbitration agreement for
    us to enforce. And “it can hardly be said that contracting
    parties clearly and unmistakably agreed to have an arbitrator
    decide the existence of an arbitration agreement when one of
    the parties has put the existence of that very agreement in
    dispute.” 1 MZM, 974 F.3d at 401; see also McKenzie v.
    Brannan, 
    19 F.4th 8
    , 18–20 (1st Cir. 2021) (contract delegating
    arbitrability issues to an arbitrator cannot provide “clear and
    unmistakable” evidence of the parties’ intent if alleged to be
    superseded by a later agreement).
    Xylem’s arguments to the contrary are unpersuasive. It
    alludes to the so-called “severability” doctrine, under which an
    arbitration provision (including a provision delegating
    arbitrability issues to an arbitrator) is severable from the
    contract in which it is contained and may be enforced despite
    an assertion that the container contract is invalid. Prima Paint
    1
    Xylem argues that the 2013 agreement’s incorporation of
    American Arbitration Association rules further indicates an
    intent to arbitrate gateway arbitrability issues. Although
    “virtually every circuit to have considered the issue has
    determined that incorporation of the AAA arbitration rules
    constitutes clear and unmistakable evidence that the parties
    agreed to arbitrate arbitrability,” we have yet to decide it in this
    context. Chesapeake Appalachia, LLC v. Scout Petroleum,
    LLC, 
    809 F.3d 746
    , 763 (3d Cir. 2016) (alterations adopted)
    (quoting Oracle Am., Inc. v. Myriad Grp. A.G., 
    724 F.3d 1069
    ,
    1074 (9th Cir. 2013)). We save it again for another day
    because, as we explain below, even assuming the 2013
    contract’s arbitration provision delegates arbitrability issues to
    an arbitrator, it does not govern this dispute.
    10
    Corp. v. Flood & Conklin Mfg. Co., 
    388 U.S. 395
    , 403–04
    (1967); Rent-a-Ctr., 
    561 U.S. at
    70–71. But we have held that
    this doctrine “presumes an underlying, existent[] agreement.”
    Sandvik AB v. Advent Int’l Corp., 
    220 F.3d 99
    , 106 (3d Cir.
    2000). It does not apply where, as here, the existence of the
    parties’ arbitration agreement has been challenged.
    We recently reaffirmed this holding in MZM, a case
    that, like this one, involved a contractual provision purporting
    to delegate arbitrability issues to an arbitrator. The dispute
    there arose from a one-page, short-form agreement hurriedly
    signed between MZM Construction Co. and a local labor
    union. 974 F.3d at 392. The short-form agreement
    incorporated a separate agreement requiring MZM to make
    contributions to the New Jersey Building Laborers’ Statewide
    Benefit Funds (the “Funds”). Id. That incorporated agreement
    contained an arbitration provision. Id. at 393. When the Funds
    learned years later that MZM likely was not contributing the
    required amount (which MZM denied), they indicated they
    would be submitting the dispute to an arbitrator per that
    provision. Id.
    MZM sued to enjoin the arbitration. Id. Its claim was
    fraud in the execution—that the union misrepresented the
    substance of the short-form agreement to obtain MZM’s
    consent. Id. at 393–94. Because of this misrepresentation,
    MZM argued that agreement was void. Id. The Funds
    countered that the Court lacked authority to decide the fraud-
    in-the-execution claim under the incorporated agreement’s
    arbitration provision, which entitled an arbitrator “to decide
    whether an Agreement exists, where that is in dispute.” Id.
    11
    We disagreed. Because the Federal Arbitration Act
    requires courts to compel arbitration only when “satisfied that
    the making of the agreement for arbitration . . . is not in issue,”
    id. at 397 (alteration in original) (quoting 
    9 U.S.C. § 4
    ), they—
    rather than arbitrators—must “decide questions about the
    formation or existence of an arbitration agreement, namely the
    element of mutual assent,” 
    id.
     at 397–98. No doubt parties
    may, as a general matter, delegate arbitrability questions to an
    arbitrator. But “the legal effect of the delegation must come
    from an ‘independent source’ outside the contract whose
    formation or existence is being disputed.” 
    Id. at 402
     (quoting
    Sandvik, 
    220 F.3d at 108
    ). “[C]ourts retain the primary power
    to decide questions of whether the parties mutually assented to
    a contract containing or incorporating a[n arbitration]
    delegation provision.” 
    Id.
    Granted, MZM dealt with issues of contract formation
    rather than contract supersession. Our parties, by contrast, do
    not dispute that the 2013 agreement was valid when executed.
    But we think the distinction deserves little weight in this
    context. Like a formation dispute, Field Intelligence’s
    supersession challenge places the parties’ mutual assent
    directly at issue. Its contention is that the parties agreed, by
    their 2017 contract, not to submit the dispute before us to an
    arbitrator. A court should rule on that issue before referring a
    case to arbitration.
    To hold otherwise would foster passing strange results.
    Xylem asks us to enforce the arbitration provision contained in
    the parties’ 2013 contract despite the assertion that it was
    extinguished and that the parties instead redefined their
    relationship in the 2017 agreement not to include an arbitration
    12
    obligation. Were we to do so, parties would never be able to
    execute a superseding agreement to rid themselves of a prior
    agreement to arbitrate arbitrability. They would forever be
    bound by that agreement even if their later dealings show an
    intent to avoid it. That in turn would undermine our guiding
    principle in the arbitration context: that “no arbitration may be
    compelled in the absence of an agreement to arbitrate.”
    Sandvik, 
    220 F.3d at
    107–08. We decline to reach such an odd
    outcome and instead conclude that the District Court was right
    to resolve the supersession issue itself rather than send it to an
    arbitrator.
    B.
    Because a court, rather than an arbitrator, must decide
    whether the parties’ 2017 contract superseded their 2013
    agreement, we move now to that issue. They agree that New
    Jersey law governs our analysis. Under that law, supersession
    is a question of the parties’ intent as discerned “from the
    contracts themselves.” Rosenberg v. D. Kaltman & Co., 
    101 A.2d 94
    , 96 (N.J. Super. Ct. Ch. Div. 1953). A later contract
    does not supersede an earlier one unless both concern “the
    same subject matter” and the later agreement is so
    “inconsistent” with the former “that the two cannot stand
    together.” Id.; accord Doyle v. Northrop Corp., 
    455 F. Supp. 1318
    , 1332 (D.N.J. 1978).
    According to Field Intelligence, the parties intended the
    2017 contract to replace completely their prior agreement, such
    that the arbitration obligation imposed by that earlier contract
    no longer exists. It relies primarily on the 2017 contract’s
    merger provision, which (to repeat) states: “This Agreement
    constitutes the entire agreement between the parties with
    respect to its subject matter, and supersedes any and all prior
    13
    or contemporaneous understandings or agreements whether
    written or oral.” Appx. 540. But that statement expressly
    limits its effect to prior agreements concerning the same
    subject matter as the 2017 contract. So it alone cannot resolve
    the parties’ supersession dispute; rather, we must first
    determine whether the 2013 and 2017 agreements involve
    identical subject matter.
    We cannot say they do. The 2013 contract is a “Non-
    Disclosure Agreement” that applies to the parties’ exchange of
    confidential and proprietary information during their
    “development of a custom telematics solution.” Appx. 531.
    The 2017 contract, by contrast, is a “Software Subscription
    Service Agreement,” entered after the telematics solution was
    developed, to provide Xylem and its customers access to Field
    Intelligence’s software for “monitor[ing] the status and
    operation of remotely located machinery.” Appx. 535. And
    while that later agreement, like the 2013 one, includes
    protections for Field Intelligence’s confidential information,
    those protections do not extend to information exchanged
    between the parties prior to their execution of the 2017
    contract.
    Neither are the two agreements so “inconsistent” that
    they “cannot stand together.” See Rosenberg, 
    101 A.2d at 96
    .
    The only potential inconsistency between these documents is
    their differing dispute-resolution provisions, one of which
    provides for arbitration while the other provides for litigation.
    But those provisions are reconcilable. Each is expressly
    limited to the subject matter of its agreement: the 2013 contract
    requires arbitration of disputes “arising out of or in connection
    with this Agreement,” Appx. 533 (emphasis added), whereas
    the 2017 contract requires litigation of disputes arising “under
    14
    or concerning this Agreement,” Appx. 539 (emphasis added).
    The result: claims involving the first agreement are heard by
    an arbitrator, while claims involving the second are heard in
    court.
    One last note. The 2013 contract states that it “may be
    modified or waived only by an express amendment and waiver
    in writing signed by the Parties.” Appx. 533. Thus, if they
    meant to supersede that contract and its arbitration obligation,
    we would expect to see some specific language to that effect in
    the 2017 agreement. But there is none. The 2017 contract does
    not even mention its predecessor, let alone expressly indicate
    any intent to replace that earlier agreement. And with no
    indication in the 2017 agreement that the parties intended to
    replace the 2013 contract, we cannot say it was superseded.
    Accordingly, the 2013 contract’s arbitration provision is still
    in effect, and Xylem was entitled to arbitrate claims tied to that
    agreement.
    C.
    In a final effort to avoid arbitration, Field Intelligence
    submits Xylem lost its right to seek such relief by engaging in
    the federal litigation. We disagree.
    A party can waive its ability to arbitrate a claim by
    litigating it in court. 2 Gray Holdco, Inc. v. Cassady, 
    654 F.3d 2
     There is a distinction between waiver and forfeiture.
    “Whereas forfeiture is the failure to make the timely assertion
    of a right, waiver is the intentional relinquishment or
    abandonment of a known right.” United States v. Brito, 
    979 F.3d 185
    , 189 (3d Cir. 2020) (internal quotation marks
    omitted) (quoting United States v. Olano, 
    507 U.S. 725
    , 733
    (1993)). We note that this may well be a forfeiture dispute, as
    15
    444, 451 (3d Cir. 2011). But, given the “strong preference” for
    “enforc[ing] private arbitration agreements,” waiver is not
    lightly inferred. 
    Id.
     The “touchstone” of the inquiry is
    prejudice, Ehleiter v. Grapetree Shores, Inc., 
    482 F.3d 207
    ,
    222 (3d Cir. 2007) (quoting Hoxworth v. Blinder, Robinson &
    Co., 
    980 F.2d 912
    , 925 (3d Cir. 1992)), which we assess using
    several factors, including the timeliness of the party’s
    arbitration demand and the extent to which it has contested the
    merits of (and engaged in discovery with respect to) its
    arbitrable claims, see Gray Holdco, 654 F.3d at 451;
    Hoxworth, 
    980 F.2d at
    926–27 (detailing prejudice inquiry).
    There was no prejudice here. Field Intelligence brought
    its claims under the 2017, not the 2013, agreement. It did not
    indicate any intent to raise claims under the earlier contract
    until responding to Xylem’s discovery requests. When Xylem
    asked if Field Intelligence planned to rely on the parties’ 2013
    agreement to support any of its claims, the latter responded by
    citing several sections of the 2013 agreement which, in its
    view, required Xylem to keep confidential and not copy the
    Hardware Units’ design. Following this admission, Xylem did
    not delay in asserting its rights under that prior agreement: it
    filed its arbitration demand the next month.
    Given that Field Intelligence framed its suit around the
    2017 agreement, Xylem did not waive its right to pursue
    arbitration for claims arising under the 2013 contract merely
    by engaging in this litigation. See Forby v. One Techs., L.P.,
    we have no evidence Xylem intentionally abandoned its
    arbitration rights. Still, because the distinction does not bear
    on our analysis, we proceed based on how the parties have
    framed the issue.
    16
    
    13 F.4th 460
    , 465 (5th Cir. 2021) (“For waiver purposes, ‘a
    party only invokes the judicial process to the extent it litigates
    a specific claim it subsequently seeks to arbitrate.’” (emphasis
    in original) (quoting Subway Equip. Leasing Corp. v. Forte,
    
    169 F.3d 324
    , 328 (5th Cir. 1999))). Field Intelligence asserts
    harm caused by Xylem’s belated arbitration demand, but as its
    lawsuit focuses on an entirely different contract, it can hardly
    claim prejudice as to any claims Xylem may bring under the
    2013 agreement.
    *     *      *
    In sum, while we agree with the District Court that it,
    and not an arbitrator, was required to determine whether the
    parties’ first agreement was superseded by their second, we do
    not agree that the earlier agreement was in fact superseded.
    Because the 2013 agreement still exists, Xylem was entitled to
    enforce its arbitration provision as to what that contract covers.
    We therefore reverse the Court’s judgment enjoining the
    arbitration proceedings. We vacate its judgment as to Xylem’s
    motion to stay the federal litigation while arbitration is pending
    and remand for it to consider the merits of that motion in light
    of our opinion.
    17