Group Against Smog and Polluti v. Shenango Inc , 810 F.3d 116 ( 2016 )


Menu:
  •                                          PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    ______
    No. 15-2041
    ______
    GROUP AGAINST SMOG AND POLLUTION, INC.,
    Appellant
    v.
    SHENANGO INCORPORATED
    ______
    On Appeal from the United States District Court
    for the Western District of Pennsylvania
    (D.C. Civil No. 2:14-cv-00595)
    District Judge: Honorable Cathy Bissoon
    ______
    Submitted Pursuant to Third Circuit L.A.R. 34.1(a)
    December 7, 2015
    Before: FUENTES, SHWARTZ, and VAN ANTWERPEN,
    Circuit Judges
    (Opinion Filed: January 6, 2016)
    John K. Baillie, Esq.
    Group Against Smog and Pollution, Inc.
    5135 Penn Ave.
    Pittsburgh, PA 15221
    Counsel for Appellant
    Chester R. Babst III, Esq.
    James D. Miller, Esq.
    Varun Shekhar, Esq.
    Babst, Calland, Clements & Zomnir, P.C.
    Two Gateway Center, 6th Floor
    603 Stanwix Street
    Pittsburgh, PA 15222
    Counsel for Appellee
    Emily A. Collins, Esq.
    Fair Shake Environmental Legal Services
    3495 Butler Street, Suite 102
    Pittsburgh, PA 15201
    Counsel for Amici Curiae Sierra Club,
    Mountain Watershed Association, Clean Air
    Council, Three Rivers Waterkeeper, and Center
    for Coalfield Justice
    ______________
    OPINION OF THE COURT
    ______________
    VAN ANTWERPEN, Circuit Judge.
    Group Against Smog and Pollution, Incorporated
    (“GASP”) filed suit against Shenango, Incorporated
    (“Shenango”) in the U.S. District Court for the Western
    District of Pennsylvania pursuant to the citizen suit provision
    2
    of the Clean Air Act (“Act”), 
    42 U.S.C. § 7604
    (a)(1). The
    District Court granted Shenango’s motion to dismiss for lack
    of subject matter jurisdiction, filed pursuant to Federal Rule
    of Civil Procedure (“Rule”) 12(b)(1). The District Court
    found that the administrative agencies were already
    “diligently prosecuting” the Clean Air Act violations alleged
    by GASP, and therefore GASP’s action was prohibited by the
    diligent prosecution bar of the Act. 
    42 U.S.C. § 7604
    (b)(1)(B); (App. 13–14). We will affirm the judgment
    of the District Court on other grounds, concluding that GASP
    has failed to state a claim because administrative agencies
    were “diligently prosecuting” the Clean Air Act violations
    and that this prosecution “requires compliance” with the Act.
    In making this determination, we conclude that the diligent
    prosecution bar of the Clean Air Act is not a jurisdictional
    limitation and is therefore properly dismissed through a Rule
    12(b)(6) motion to dismiss for failure to state a claim upon
    which relief may be granted, rather than Rule 12(b)(1).
    I.
    INTRODUCTION
    Shenango operates the Neville Island Coke Plant, a
    coke manufacturing and by-products recovery facility in
    Allegheny County, Pennsylvania.1 (App. 3). The Neville
    1
    The Neville Island Coke Plant “performs destructive
    distillation of coal to produce metallurgical coke and by-
    products such as tar, light oil, sodium phenolate, and
    ammonium sulfate. Coke oven gas . . . fuel, which is used to
    underfire the coke battery and to fuel the boilers, is also
    produced.” (App. 90).
    3
    Island Coke Plant is subject to National Ambient Air Quality
    Standards (“NAAQS”) set by the United States
    Environmental Protection Agency (“EPA”) pursuant to the
    Clean Air Act. 
    42 U.S.C. §§ 7408
    –09; (App. 3–4). As part of
    the Act’s encouragement of federal cooperation with state and
    local governments, Pennsylvania is required to create a “state
    implementation plan,” (“SIP”) detailing how it will attain and
    maintain the NAAQS. 
    42 U.S.C. § 7410
    . Once the EPA
    approves the SIP, it becomes binding federal law. 
    Id.
     § 7413.
    In Allegheny County, the Commonwealth of Pennsylvania
    delegates the authority for enforcing air pollution laws to the
    Allegheny County Health Department (“ACHD”). (App. 4).
    The ACHD has promulgated emissions standards that are
    incorporated in the Pennsylvania SIP and are thereby binding
    federal law under the Clean Air Act. See ACHD Rules and
    Regulations Art. XXI. Three ACHD regulations are at issue
    in this case:
    First, Section 2105.21.b.1 restricts visible
    emissions from any battery of coke ovens to no
    more than five percent . . . of the door areas of
    the operating coke ovens (the “five percent door
    emissions     standard”).     Second,    Section
    2105.21.f.3     prohibits    combustion     stack
    emissions with opacity greater than 20 percent
    for three minutes over a 60 minute period (the
    “20 percent combustion stack opacity
    standard”). Finally, Section 2105.21.f.4
    prohibits combustion stack emissions with
    opacity greater than 60 percent (the “60 percent
    combustion stack opacity standard”).
    (App. 4).
    4
    In 2012, the EPA, the Pennsylvania Department of
    Environmental Protection (“DEP”), and the ACHD filed an
    action in the U.S. District Court for the Western District of
    Pennsylvania against Shenango claiming violations of these
    three standards. (App. 4–5). The parties entered into a
    Consent Decree to resolve these violations, specifically
    addressing the twenty and sixty percent combustion stack
    opacity standards. (Id.). The District Court entered final
    judgment on this action in 2012 but retained jurisdiction “for
    the purpose of modifying, construing and/or enforcing the
    rights and obligations of the Parties to this Consent Decree.”
    (Id. at 168–69, 174).
    In 2014, GASP sent Shenango a notice of intent to sue,
    claiming violations of the same three standards. (Id. at 5). The
    ACHD then filed an action against Shenango in the
    Allegheny County Pennsylvania Court of Common Pleas, and
    the parties entered into a Consent Order and Agreement. (Id.).
    This Agreement appears to address the five percent door
    emissions standard, as discussed infra, and reaffirms the 2012
    Consent Decree’s approach to the twenty and sixty percent
    combustion stack opacity standards. (Id.). The Court of
    Common Pleas entered final judgment on this action on April
    8, 2014. (Id. at 106). The ACHD retained authority with
    respect to future violations and “to seek further enforcement
    of this Agreement” if Shenango fails to comply. (Id. at 95).
    The Consent Order and Agreement was intended to be jointly
    terminated by the parties upon Shenango’s compliance with
    certain conditions. (Id. at 105–06).
    On May 8, 2014, GASP filed the instant citizen suit
    against Shenango in U.S. District Court, again claiming
    violations of the same three emissions standards. (Id. at 6, 19–
    5
    29). Shenango moved to dismiss for lack of subject matter
    jurisdiction and for failure to state a claim upon which relief
    may be granted, pursuant to Rules 12(b)(1) and 12(b)(6). (Id.
    at 109–10). The District Court found the issue presented to be
    jurisdictional. (Id. at 6). The Court granted Shenango’s
    motion to dismiss for lack of subject matter jurisdiction,
    finding that GASP could not bring an action because the
    ACHD was already “diligently prosecut[ing]” an action in
    court against Shenango to require compliance under the Act.
    (Id. at 12–14). The Court rejected two arguments raised by
    GASP in opposition to the motion to dismiss: (1) that the
    Consent Decrees2 do not actually require Shenango to comply
    with the standards set forth in the Act; and (2) that the 2014
    Consent Order and Agreement was deficient because the
    parties failed to provide an opportunity for the public to
    intervene or comment on the terms of the order. (Id. at 11–
    13). GASP timely appealed. (Id. at 1).
    II.3
    DISCUSSION
    GASP raises two arguments on appeal: (1) that the
    diligent prosecution bar4 should not apply because no state or
    2
    We refer to the 2012 Consent Decree and 2014 Consent
    Order and Agreement collectively as the “Consent Decrees.”
    3
    The District Court had federal question jurisdiction pursuant
    to 
    28 U.S.C. § 1331
     through application of the citizen suit
    provision in 
    42 U.S.C. § 7604
    (a)(1). We have jurisdiction to
    review the final decision of the District Court pursuant to 
    28 U.S.C. § 1291
    .
    6
    administrative agency was actively “prosecuting” a civil
    action in court at the time GASP filed its present citizen suit;
    and (2) that the Consent Decrees from 2012 and 2014 do not
    “require compliance” with the Act. (Appellant’s Br. 16–18).
    In dealing with these issues we must first determine whether
    the diligent prosecution bar is jurisdictional or only a claim-
    processing rule. The District Court proceeded assuming the
    bar was jurisdictional. (App. 6). We exercise plenary review
    over the District Court’s legal conclusions. CNA v. United
    States, 
    535 F.3d 132
    , 139 (3d Cir. 2008).
    A.     Nonjurisdictional Diligent Prosecution Bar
    Amici curiae raise the issue of whether the diligent
    prosecution bar is jurisdictional and appropriately decided
    through a Rule 12(b)(1) motion to dismiss for lack of subject
    matter jurisdiction, or whether the diligent prosecution bar is
    nonjurisdictional and should be decided through a Rule
    12(b)(6) motion to dismiss for failure to state a claim.5 This
    4
    The diligent prosecution bar, discussed infra, is a limitation
    on the Act’s citizen suit provision. It provides that a citizen
    suit may not be commenced “if the Administrator or State has
    commenced and is diligently prosecuting a civil action in a
    court of the United States or a State to require compliance
    with the standard, limitation, or order.” 
    42 U.S.C. § 7604
    (b)(1)(B).
    5
    While Appellant did not raise this argument and has
    consistently proceeded assuming the diligent prosecution bar
    is jurisdictional, “federal courts have an independent
    obligation to ensure that they do not exceed the scope of their
    jurisdiction, and therefore they must raise and decide
    7
    dichotomy is significant, “one of considerable practical
    importance for judges and litigants,” as “[b]randing a rule as
    going to a court’s subject-matter jurisdiction alters the normal
    operation of our adversarial system.” Henderson ex rel.
    Henderson v. Shinseki, 
    562 U.S. 428
    , 434 (2011).6
    The U.S. Supreme Court has noted, “[o]n the subject-
    matter jurisdiction/ingredient-of-claim-for-relief dichotomy,
    this Court and others have been less than meticulous.”
    Arbaugh v. Y & H Corp., 
    546 U.S. 500
    , 511 (2006). Arbaugh
    instructs us that “[i]f the Legislature clearly states that a
    threshold limitation on a statute’s scope shall count as
    jurisdictional, then courts and litigants will be duly
    instructed,” however “when Congress does not rank a
    statutory limitation on coverage as jurisdictional, courts
    should treat the restriction as nonjurisdictional in character.”
    
    546 U.S. at
    515–16 (footnote omitted). The Court has
    described this as a “readily administrable bright line rule.”
    jurisdictional questions that the parties either overlook or
    elect not to press.” Henderson ex rel. Henderson v. Shinseki,
    
    562 U.S. 428
    , 434 (2011) (citation omitted).
    6
    The differences between a motion to dismiss for lack of
    subject matter jurisdiction and a motion to dismiss for failure
    to state a claim include: an objection to subject matter
    jurisdiction may be raised at any time, a court may raise
    jurisdictional issues sua sponte, and a court may consider
    evidence beyond the pleadings such as testimony and
    depositions when considering a jurisdictional challenge.
    Henderson ex rel Henderson, 
    562 U.S. at
    434–35; Gotha v.
    United States, 
    115 F.3d 176
    , 179 (3d Cir. 1997).
    8
    Henderson ex rel. Henderson, 
    562 U.S. at 435
     (quoting
    Arbaugh, 
    546 U.S. at 516
    ) (internal quotation marks omitted).
    In Henderson, the Supreme Court distinguished claim-
    processing rules, which “seek to promote the orderly progress
    of litigation by requiring that the parties take certain
    procedural steps at certain specified times,” from
    jurisdictional rules, which “govern[] a court’s adjudicatory
    capacity, that is, its subject-matter or personal jurisdiction.”
    
    Id.
     To distinguish these rules, the pivotal question as it
    applies to this case “is whether Congress mandated” the
    diligent prosecution bar to be “jurisdictional.” 
    Id.
     There are
    no “magic words” Congress must use to express that a
    statutory requirement is jurisdictional. Id. at 436. Instead, we
    look “to the condition’s text, context, and relevant historical
    treatment” in determining whether the condition is
    jurisdictional. Reed Elsevier, Inc. v. Muchnick, 
    559 U.S. 154
    ,
    166 (2010); see also Henderson ex rel. Henderson, 
    562 U.S. at 436
     (stating the Court’s approach in Arbaugh “is suited to
    capture Congress’ likely intent and also provides helpful
    guidance for courts and litigants, who will be duly instructed
    regarding a rule’s nature”) (internal quotation marks omitted).
    Two circuit courts have interpreted Arbaugh in the
    context of a diligent prosecution bar in other acts7 and have
    7
    While we rely on cases interpreting other environmental
    statutes in our present analysis of the Clean Air Act, we note
    that the legislative history of these other statutes explains that
    their citizen suit provisions and diligent prosecution bars were
    “modeled on” the relevant provisions of the Clean Air Act.
    See Jeffrey G. Miller, Overlooked Issues in the “Diligent
    Prosecution” Citizen Suit Preclusion, 
    10 Widener L. Rev. 63
    ,
    9
    concluded the bar is nonjurisdictional. Louisiana Envtl.
    Action Network v. City of Baton Rouge, 
    677 F.3d 737
    , 745–49
    (5th Cir. 2012) (per curiam) (interpreting the diligent
    prosecution bar of the Clean Water Act, 
    33 U.S.C. § 1365
    (b)(1)(B)); Adkins v. VIM Recycling, Inc., 
    644 F.3d 483
    , 491–92 (7th Cir. 2011) (interpreting the diligent
    prosecution bar of the Resource Conservation and Recovery
    Act, 
    42 U.S.C. § 6972
    (b)(1)(B)).
    This Court has addressed questions regarding the
    diligent prosecution bar, not at issue here, in which the bar
    was referenced as jurisdictional. In these cases, we
    determined whether the administrative action in question was
    taken by a “court” for the purpose of applying the diligent
    prosecution bar. Student Pub. Interest Research Grp. of New
    Jersey, Inc. v. Fritzsche, Dodge & Olcott, Inc., 
    759 F.2d 1131
    , 1135 (3d Cir. 1985) (“Because we find that the EPA’s
    action is not a ‘court’ proceeding (and fails the first prong of
    [the citizen suit bar]), we need not address the second issue of
    whether      the    consent     order    constitutes    ‘diligent
    prosecution.’”); see also Baughman v. Bradford Coal Co.,
    Inc., 
    592 F.2d 215
    , 219 (3d Cir. 1979) (determining that the
    69 & n.31 (2003) (collecting cases); see, e.g., Gwaltney of
    Smithfield, Ltd. v. Chesapeake Bay Found., Inc., 
    484 U.S. 49
    ,
    62 (1987) (explaining that “both the Senate and House
    Reports explicitly connected [the citizen suit provision of the
    Clean Water Act] to the citizen suit provisions authorized by
    the Clean Air Act”). Because the provisions serve a similar
    purpose in their respective statutes, courts commonly
    consider the interpretation of citizen suit provisions and
    diligent prosecution bars in other statutes in deciding the case
    at hand. Miller, 
    supra,
     at 69 & n.32.
    10
    district court had subject matter jurisdiction because the
    administrative action in question was not taken by a “court”
    under the diligent prosecution bar of the Clean Air Act). We
    did not consider in either case whether Congress intended the
    bar to be jurisdictional.8
    We conclude that the diligent prosecution bar of the
    Clean Air Act is not a jurisdictional limitation. Beginning our
    analysis with the text of the statute, the language of the
    diligent prosecution bar does not “clearly state[] that a
    threshold limitation on [its] scope shall count as
    jurisdictional.” Arbaugh, 
    546 U.S. at 515
    . The language
    Congress used, “No action may be commenced,” is
    mandatory, but it is not stated in terms of the court’s
    adjudicatory capacity or jurisdiction. 
    42 U.S.C. § 7604
    (b); see
    Henderson ex rel. Henderson, 
    562 U.S. at 439
     (explaining
    that the Supreme Court has rejected the notion that all
    mandatory rules are jurisdictional). Congress could have
    expressly made the diligent prosecution bar jurisdictional by
    using the word “jurisdiction” or phrasing the language in
    terms of the court’s powers. See Arbaugh, 
    546 U.S. at 516
    (“[W]hen Congress does not rank a statutory limitation on
    coverage as jurisdictional, courts should treat the restriction
    as nonjurisdictional in character.”). Shenango has not
    identified any specific text in the Act that indicates the
    diligent prosecution        language should “count as
    jurisdictional.” Beazer E., Inc. v. Mead Corp., 
    525 F.3d 255
    ,
    8
    Appellee does not cite cases in which any federal court
    engaged in an analysis of the diligent prosecution bar and
    concluded that it is a jurisdictional limitation in the vein of
    Arbaugh.
    11
    261 (3d Cir. 2008) (quoting requirements of Arbaugh, 
    546 U.S. at
    515–16) (internal quotation marks omitted).
    In Henderson, the Supreme Court held that a 120-day
    notice requirement prior to filing an appeal to the Veterans
    Court was nonjurisdictional. 
    562 U.S. at 431
    . The Court
    interpreted the following statutory language: “In order to
    obtain review,” an appropriate person “shall file a notice of
    appeal with the Court within 120 days after the date on which
    notice of the decision is mailed.” 
    Id. at 438
     (quoting 
    38 U.S.C. § 7266
    (a)) (internal quotation marks omitted). The
    Court distinguished this from language governing Federal
    Circuit review of Veterans Court decisions: “Federal Circuit
    review must be obtained within the time and in the manner
    prescribed for appeal to United States court of appeals from
    United States district courts.” 
    Id.
     (quoting 
    38 U.S.C. § 7292
    (a)) (internal quotation marks omitted). Because timing
    requirements for taking an appeal from a district court have
    long been considered jurisdictional, this latter language
    clearly signaled congressional intent for Federal Circuit
    review requirements to be jurisdictional. 
    Id.
     at 438–39; see
    Bowles v. Russell, 
    551 U.S. 205
    , 209–14 (2007) (holding that
    statutory time limits for taking an appeal are jurisdictional
    based on their “longstanding treatment” as such by the
    Supreme Court). The former language, at issue in Henderson,
    is not framed in a manner that clearly states its intention to be
    jurisdictional or references similar treatment to a clearly
    jurisdictional limitation. 
    562 U.S. at 439
    . The Clean Air Act
    diligent prosecution bar, like the Henderson 120-day notice
    requirement, does not reference the court’s jurisdiction in any
    way nor is it phrased in a way that clearly suggests it is a
    jurisdictional requirement. We agree with the Seventh
    Circuit’s interpretation of the citizen suit provision in the
    12
    Resource Conservation and Recovery Act that the “limits on
    citizen suits appear in separate provisions that do not ‘speak
    in jurisdictional terms or refer in any way to the jurisdiction
    of the district courts.’” Adkins, 
    644 F.3d at 492
     (quoting Zipes
    v. Trans World Airlines, Inc., 
    455 U.S. 385
    , 394 (1982)).9
    The Henderson Court also discussed the placement of
    statutory provisions in determining that the notice
    requirement in question was nonjurisdictional. 
    562 U.S. at 439
    . The Clean Air Act title for 
    42 U.S.C. § 7604
    , “Citizen
    suits,” “can aid in resolving an ambiguity in the legislation’s
    text.” Immigration & Naturalization Serv. v. Nat’l Ctr. for
    Immigrants’ Rights, Inc., 
    502 U.S. 183
    , 189 (1991). Congress
    further titled § 7604(a): “Authority to bring civil action;
    jurisdiction,” and § 7604(b): “Notice.” That these subsections
    are separately titled suggests they should be considered
    separate provisions. Rather than including the diligent
    prosecution bar within the exact provision granting
    jurisdiction, the diligent prosecution bar is part of this
    separate “Notice” provision. The “Notice” provision also
    requires the citizen to notify the involved administrative
    agencies at least sixty days prior to filing the citizen suit. 
    42 U.S.C. § 7604
    (b)(1)(A). This procedural rule is similar to the
    claim-processing rule in Henderson. See 
    562 U.S. at 441
    (holding that the 120-day notice requirement for filing an
    appeal with the Veteran’s Court “does not have jurisdictional
    9
    While Appellee appears to object to the approach of
    interpreting Arbaugh in the context of an environmental case,
    we have already applied Arbaugh in concluding that the “civil
    action” requirement of the Comprehensive Environmental
    Response, Compensation, and Liability Act of 1980 is not a
    jurisdictional threshold. Beazer E., Inc., 
    525 F.3d at
    260–61.
    13
    attributes”).10 The placement of the diligent prosecution bar
    within the “Notice” subsection suggests the diligent
    prosecution bar is also a claim-processing rule. Louisiana
    Envtl. Action Network, 
    677 F.3d at 748
     (“The placement of
    the ‘diligent prosecution’ bar in the ‘Notice’ section,
    alongside a typical claim-processing rule, suggests that
    Congress intended the ‘diligent prosecution’ bar to be a
    claim-processing rule.”).
    Our language in Student Public Interest Research
    Group and Baughman does not control. Neither case
    specifically addresses the question of jurisdiction, but rather
    both cases held that the administrative agency involved was
    not a “court” for the purpose of applying the diligent
    prosecution bar. Student Pub. Interest Research Grp. of New
    Jersey, Inc., 
    759 F.2d at 1139
    ; Baughman, 
    592 F.2d at 219
    .
    10
    Appellee relies on Hallstrom v. Tillamook County for the
    proposition that “a plaintiff’s failure to abide by the identical
    notice requirements under the Resource Conservation and
    Recovery Act . . . warranted dismissal for lack of subject
    matter jurisdiction.” (Appellee’s Br. 48) (citing 
    493 U.S. 20
    ,
    23, 31 (1989)). We believe Appellee’s reliance on this case is
    misplaced, as the Hallstrom Court stated, “[t]he parties have
    framed the question presented in this case as whether the
    notice provision is jurisdictional or procedural. In light of our
    literal interpretation of the statutory requirement, we need not
    determine whether § 6972(b) is jurisdictional in the strict
    sense of the term.” 493 U.S. at 31. Therefore, the Court did
    not determine that this notice provision is jurisdictional. In
    fact, Hallstrom was decided before Arbaugh and Henderson,
    which themselves further defined the contours of
    jurisdictional provisions.
    14
    The approach taken in these cases predates the guidance set
    forth in Arbaugh. As the Supreme Court articulated, “the
    relevant question here is not” whether the diligent prosecution
    bar “itself has long been labeled jurisdictional, but whether
    the type of limitation that” the diligent prosecution bar
    “imposes is one that is properly ranked as jurisdictional
    absent an express designation.” Reed Elsevier, Inc., 
    559 U.S. at 168
    .
    In terms of the context of the diligent prosecution bar
    and the Supreme Court’s “interpretation of similar
    provisions,” the diligent prosecution bar is analogous to other
    mandatory, threshold requirements the Supreme Court has
    deemed nonjurisdictional in addition to the notice
    requirement in Henderson. See 
    id.
     at 168–69 (holding that the
    Copyright Act’s requirement that copyright holders register
    their work before suing for copyright infringement is not a
    jurisdictional requirement); 
    id.
     at 166 & n.6 (indicating that
    the Supreme Court in Jones v. Bock, 
    549 U.S. 199
    , 216–17
    (2007) treated the administrative exhaustion requirement of
    the Prison Litigation Reform Act of 1995 as
    nonjurisdictional); Zipes, 
    455 U.S. at 393
     (holding that “a
    timely charge of discrimination with the [Equal Employment
    Opportunity Commission] is not a jurisdictional prerequisite
    to suit in federal court”).
    Appellee presents legislative history in which the word
    “jurisdiction” was used in conjunction with the diligent
    prosecution bar. See S. Rep. No. 91-1196, at 37 (1970) (“[I]f
    the court viewed the agency action as inadequate, it would
    have jurisdiction to consider the citizen action
    notwithstanding any pending agency action.”). This language
    does not convince us that Congress intended the diligent
    15
    prosecution bar to be jurisdictional. It does appear that
    Congress intended the diligent prosecution bar to be a
    mandatory condition precedent to filing a citizen suit.
    Nevertheless as we have discussed, the actual text of the
    statute does not reference in any way or clearly suggest its
    intention to be jurisdictional, and its placement next to a
    claim-processing timing rule suggests it is a nonjurisdictional
    requirement. See Reed Elsevier, Inc., 
    559 U.S. at 166
     (stating
    that the Supreme Court has “treated as nonjurisdictional other
    types of threshold requirements that claimants must complete,
    or exhaust, before filing a lawsuit”).11
    Congress did not clearly state or mandate that the
    diligent prosecution bar of the Clean Air Act “shall count as
    jurisdictional.” Arbaugh, 
    546 U.S. at
    515–16. The text and
    placement of the specific provision reflect congressional
    intent that the limitation is a mandatory claim-processing rule
    designed “to promote the orderly progress of litigation” by
    ensuring the case is not already being diligently prosecuted.
    Henderson ex rel. Henderson, 
    562 U.S. at 435
    . It is
    particularly instructive that the Supreme Court has held
    similar mandatory threshold requirements are not
    jurisdictional limitations. We therefore conclude that the
    diligent prosecution bar of the Clean Air Act is
    nonjurisdictional.
    11
    There is no historical treatment of the diligent prosecution
    bar to discuss because the Supreme Court has not directly
    addressed the jurisdictional nature of § 7604(b)(1)(B). Thus,
    we lack “a long line of [the Supreme] Court’s decisions” to
    instruct our analysis. Henderson ex rel. Henderson, 
    562 U.S. at 436
     (citations omitted) (internal quotation marks omitted).
    16
    B.      Analysis
    The Clean Air Act provides that citizens may
    commence a civil action on their own behalf against a person
    or entity alleged to be in violation of an emission standard or
    limitation set forth under the Act. 
    42 U.S.C. § 7604
    (a)(1).
    This citizen suit provision is subject to an important
    limitation, at issue in the present case:
    No action may be commenced—
    ...
    if the Administrator or State has commenced
    and is diligently prosecuting a civil action in a
    court of the United States or a State to require
    compliance with the standard, limitation, or
    order, but in any such action in a court of the
    United States any person may intervene as a
    matter of right.
    
    Id.
     § 7604(b)(1)(B). We have commented that there is
    “extensive legislative history to establish that Congress
    intended citizen suits to both goad the responsible agencies to
    more vigorous enforcement of the anti-pollution standards
    and, if the agencies remained inert, to provide an alternate
    enforcement mechanism.” Baughman, 
    592 F.2d at 218
    .
    However, we have also noted that the “same legislative
    history also indicates ‘that Congress intended to provide for
    citizens’ suits in a manner that would be least likely to clog
    already burdened federal courts and most likely to trigger
    governmental action which would alleviate any need for
    judicial relief.’” 
    Id.
     (quoting City of Highland Park v. Train,
    
    519 F.2d 681
    , 690–91 (7th Cir. 1975)); see also Gwaltney of
    Smithfield, Ltd. v. Chesapeake Bay Found., Inc., 
    484 U.S. 49
    ,
    17
    60 (1987) (“The bar on citizen suits when governmental
    enforcement action is under way suggests that the citizen suit
    is meant to supplement rather than to supplant governmental
    action.”). We consider these policies in assessing the
    Appellant’s arguments.
    1.      Standard of Review
    We must decide whether the District Court correctly
    determined that GASP could not advance a citizen suit
    because of the diligent prosecution bar. We exercise plenary
    review over the District Court’s legal conclusions. CNA, 
    535 F.3d at 139
    . In so doing, we must ask whether GASP has
    failed to state a claim. To survive a 12(b)(6) motion to
    dismiss for failure to state a claim,12 “a complaint must
    contain sufficient factual matter, accepted as true, to ‘state a
    claim to relief that is plausible on its face.’” Ashcroft v. Iqbal,
    
    556 U.S. 662
    , 678 (2009) (quoting Bell Atl. Corp. v.
    Twombly, 
    550 U.S. 544
    , 570 (2007)). “In this review, courts
    accept all factual allegations as true, construe the complaint in
    the light most favorable to the plaintiff, and determine
    whether, under any reasonable reading of the complaint, the
    12
    Although this case was decided by the District Court as a
    12(b)(1) motion to dismiss for lack of subject matter
    jurisdiction, consistent with our discussion, supra, regarding
    the nonjurisdictional nature of § 7604(b), we will decide this
    case under 12(b)(6) standards. We note Shenango’s initial
    motion to dismiss was based on both 12(b)(1) and 12(b)(6),
    and the District Court should have used the 12(b)(6) standard.
    We may affirm the judgment of the District Court for any
    reason supported by the record. Brightwell v. Lehman, 
    637 F.3d 187
    , 191 (3d Cir. 2011).
    18
    plaintiff may be entitled to relief.” Eid v. Thompson, 
    740 F.3d 118
    , 122 (3d Cir. 2014) (quoting Phillips v. Cnty. of
    Allegheny, 
    515 F.3d 224
    , 233 (3d Cir. 2008)) (internal
    quotation marks omitted).
    We may review the 2012 Consent Decree and 2014
    Consent Order and Agreement in deciding a 12(b)(6) motion
    to dismiss for failure to state a claim, as “it is the usual
    practice for a court to consider only the allegations contained
    in the complaint, exhibits attached to the complaint and
    matters of public record.” City of Pittsburgh v. W. Penn
    Power Co., 
    147 F.3d 256
    , 259 (3d Cir. 1998) (citation
    omitted); accord Pension Benefit Guar. Corp. v. White
    Consol. Indus., Inc., 
    998 F.2d 1192
    , 1196 (3d Cir. 1993).
    “Courts have defined a public record, for purposes of what
    properly may be considered on a motion to dismiss, to include
    . . . letter decisions of government agencies . . . and published
    reports of administrative bodies.” Pension Benefit Guar.
    Corp., 
    998 F.2d at 1197
     (citations omitted); see also Schmidt
    v. Skolas, 
    770 F.3d 241
    , 249 (3d Cir. 2014) (determining that
    Securities and Exchange Commission filings are also matters
    of public record appropriately considered in reviewing a Rule
    12(b)(6) motion to dismiss). Further, courts may consider
    exhibits attached to a defendant’s motion to dismiss if it is
    “an undisputedly authentic document” and “plaintiff’s claims
    are based on the document.” Pension Benefit Guar. Corp.,
    
    998 F.2d at 1196
    .
    The 2012 Consent Decree and 2014 Consent Order
    and Agreement are public records as they are court decisions
    and final judgments. Further, the 2014 Consent Order and
    Agreement was an exhibit attached to the complaint. Portions
    of the 2012 Consent Decree were attached to the complaint,
    19
    but the full document was only attached to the defendant’s
    motion to dismiss. The 2012 Consent Decree is undisputedly
    authentic as neither party nor the District Court has
    questioned its authenticity. GASP’s claims were based on the
    Consent Decree, specifically GASP’s contention that the
    2012 Consent Decree does not require compliance with the
    Act. Our reliance on these Consent Decrees in the context of
    a Rule 12(b)(6) motion is appropriate.
    2.     Were the agencies “prosecuting” an
    action?
    Appellant argues that the term “prosecuting” in the
    diligent prosecution bar “requires an agency enforcement
    action to be pending in court if it is to bar a citizen suit.”
    (Appellant’s Br. 26). The argument follows that because the
    2012 and 2014 civil actions culminated in final judgments,
    they were not pending before a court when GASP filed its
    citizen suit, and therefore the Consent Decrees from these
    actions could not support a diligent prosecution bar. This
    issue is one of first impression in this Court. We have little
    difficulty in holding that when a state or federal agency
    diligently prosecutes an underlying action in court, the
    diligent prosecution bar will prohibit citizen suits during the
    actual litigation as well as after the litigation has been
    terminated by a final judgment, consent decree, or consent
    order and agreement. In addition, when a state or federal
    agency diligently pursues an ongoing consent decree that may
    be modified by the parties and enforced by the agency, the
    diligent prosecution bar will prohibit citizen suits. We note
    that the parties in the present case were still able to modify or
    enforce the 2012 Consent Decree and 2014 Consent Order
    and Agreement and the District Court correctly found that the
    20
    ACHD was “diligently prosecuting” the case by taking
    actions that furthered the goals of these Consent Decrees,
    which was compliance with the regulations.
    In addition, case law from other circuit courts supports
    the proposition that if the underlying case was diligently
    pursued, the diligent prosecution bar will apply even though
    an agency has entered into a consent decree with a polluter
    following a civil or administrative action. See N. & S. Rivers
    Watershed Ass’n, Inc. v. Town of Scituate, 
    949 F.2d 552
    , 556
    (1st Cir. 1991) (“The focus of the statutory bar to citizen’s
    suits is not on state statutory construction, but on whether
    corrective action already taken and diligently pursued by the
    government seeks to remedy the same violations as
    duplicative civilian action.”); see also Piney Run Pres. Ass’n
    v. Cnty. Comm’rs. of Carroll Cnty., Md., 
    523 F.3d 453
    , 459
    (4th Cir. 2008) (stating that “when presented with a consent
    decree” following a completed administrative agency
    proceeding, “we must be particularly deferential to the
    agency’s expertise”); Karr v. Hefner, 
    475 F.3d 1192
    , 1197–
    98 (10th Cir. 2007) (determining that a citizen suit was barred
    because “the EPA’s prosecution,” a consent decree previously
    entered into, “was diligent”); Supporters to Oppose Pollution,
    Inc. v. Heritage Grp., 
    973 F.2d 1320
    , 1324 (7th Cir. 1992)
    (stating that the diligent prosecution bar in the Resource
    Conservation and Recovery Act “permits a follow-on private
    suit if the public suit was not prosecuted diligently. But if the
    agency prevails in all respects, that is the end . . . .”). Courts
    have concluded, in cases similar to ours, that consent decrees
    already entered into by administrative agencies and polluting
    entities were capable of constituting diligent prosecutions.
    21
    Within this Circuit, we note that a district court has
    determined that the diligent prosecution bar applied to a
    consent order in Citizens for Clean Power v. Indian River
    Power, LLC, 
    636 F. Supp. 2d 351
    , 358 (D. Del. 2009). An
    environmental organization sent a notice of intent to sue to
    the defendant, prompting the administrative agencies to file
    suit against the defendant and propose a consent order. 
    Id. at 354
    . On February 13, 2009, the Delaware Superior Court
    entered the consent order, and on February 26, 2009, the
    organization filed its citizen suit against the same defendant.
    
    Id.
     at 354–55. The court found that the agency “diligently
    prosecuted its suit against defendant, which preclude[ed]
    plaintiff’s suit under 
    42 U.S.C. § 7604
    (b)(1)(B).” 
    Id. at 358
    .13
    Appellant relies on cases that “employ[] a literal,
    inflexible interpretation compelled by the clear and
    unambiguous language of the Act.” Friends of Milwaukee’s
    Rivers v. Milwaukee Metro. Sewerage Dist., 
    382 F.3d 743
    ,
    754 (7th Cir. 2004). The U.S. District Court for the Eastern
    District of Texas compared the date the plaintiffs’ complaint
    was filed with the date final judgment was entered in the
    pending case, finding it “clear the state of Texas was actually
    prosecuting [an applicable civil action] on the date the
    plaintiffs filed their original complaint.” Glazer v. Am.
    13
    In Citizens for Clean Power, the District Court did not
    squarely address the present argument of whether
    “prosecuting” includes consent decrees from civil actions that
    resulted in a final judgment. Just as the District Court in this
    case proceeded, the Citizens for Clean Power case impliedly
    answered this question affirmatively, evidenced by its
    analysis of whether the prosecution was “diligent.” 
    636 F. Supp. 2d at
    357–58.
    22
    Ecology Envtl. Servs. Corp., 
    894 F. Supp. 1029
    , 1035 (E.D.
    Tex. 1995). Appellant additionally relies on cases from within
    this Circuit where a district court applied a literal and
    grammatical analysis to conclude a diligent prosecution bar
    did not apply. United States v. Sunoco, Inc. 
    501 F. Supp. 2d 656
    , 665 (E.D. Pa. 2007) (“The statute speaks in the present
    and present perfect tense: it only applies if [the agency] ‘has
    commenced’ and ‘is diligently prosecuting’ a civil action in
    court; or if it ‘is in litigation’ . . . .”); Pub. Interest Research
    Grp. of New Jersey, Inc. v. GAF Corp., 
    770 F. Supp. 943
    , 949
    (D.N.J. 1991) (stating that the statute “speaks in the present
    tense” and it “does not state that a citizen suit is barred if a
    state has prosecuted an action with respect to such violations,
    although Congress could have easily so provided”).
    We reject cases cited by Appellant which rely on a
    literal, inflexible, or grammatical interpretation. We conclude
    instead that if a state or administrative agency diligently
    prosecuted a suit, the presence of a final judgment, consent
    decree, or consent order and agreement will not prevent
    application of the diligent prosecution bar.
    The circumstances of this case show ongoing diligent
    prosecution. The Consent Decrees provide a means to seek
    court intervention in the event of continuing violations. (App.
    105–06, 168–69). This provides a speedy and efficient means
    to enforce an order mandating compliance with the
    regulations without having to initiate a separate lawsuit.
    Moreover, the 2012 Consent Decree includes a “Continuing
    Jurisdiction” provision, providing that the District Court
    “shall retain jurisdiction from the date of entry of this
    Consent Decree through the date of termination of this Decree
    for the purpose of modifying, construing and/or enforcing the
    23
    rights and obligations of the Parties to this Consent Decree.”
    (App. 168). The Decree defines “termination” by requiring
    Shenango to file a motion with the Court demonstrating its
    compliance with the terms of the Decree. (Id. at 169–70). The
    2014 Consent Order and Agreement, in a section titled
    “Effective Date and Termination,” states that “[i]t is the
    intention of the parties that they will move jointly to
    terminate this Agreement” either three years from the
    effective date of the Agreement, or once Shenango
    demonstrates sufficient compliance with the terms of the
    Order and Agreement, whichever is sooner. (Id. at 105–06).
    No such motion was filed when GASP filed its citizen suit.
    The ACHD also retains its authority “to seek further
    enforcement of this Agreement in the event Shenango fails to
    successfully comply with its terms and conditions.” (Id. at
    95). Both the 2012 Consent Decree and 2014 Consent Order
    and Agreement utilize ongoing monitoring and recording of
    Shenango’s emissions, as well as allow ACHD the right to
    inspect Shenango’s facilities or record emissions. (Id. at 99–
    101) (2014 Consent Order and Agreement); (Id. at 130–33,
    145–46) (2012 Consent Decree).
    It is undisputed by their own terms that the 2012
    Consent Decree and 2014 Consent Order and Agreement
    were still in effect when GASP filed its citizen suit.
    Therefore, although the actions culminated in final
    judgments, the principal enforcement mechanism against
    Shenango for these Clean Air Act violations remained in
    place.
    We are reminded that the legislative history of the
    citizen suit provision of the Clean Water Act suggests that
    “the citizen suit is meant to supplement rather than to
    24
    supplant governmental action.” Gwaltney of Smithfield, Ltd.,
    
    484 U.S. at 60
    . Legislative history surrounding the citizen suit
    provision of the Clean Water Act provides that “[t]he
    Committee intends the great volume of enforcement actions
    be brought by the State” and that the citizen suit is
    appropriate only “if the Federal, State, and local agencies fail
    to exercise their enforcement responsibility.” S. Rep. No. 92-
    414, at 64 (1971); Gwaltney of Smithfield, Ltd., 
    484 U.S. at 60
    .
    Appellant is correct that no circuit court has squarely
    addressed whether the term “prosecuting” in the diligent
    prosecution bar of the Clean Air Act requires an agency
    enforcement action to be pending in court when the citizen
    suit is filed. Courts have impliedly answered this question
    through their decisions on whether to enforce a diligent
    prosecution bar when faced with a recent consent decree. Our
    decision hinges on the circumstances of this case and the
    ongoing vitality of these Consent Decrees, specifically the
    parties’ ability to modify or enforce the terms of the Consent
    Decrees.
    3.     Does       the     prosecution     “require
    compliance” with the Act?
    The Clean Air Act states that diligent prosecution must
    “require compliance with the standard, limitation, or order” of
    the Act. 
    42 U.S.C. § 7604
    (b)(1)(B). We note that the
    government’s prosecution is entitled to great deference. Karr,
    
    475 F.3d at 1198
     (quoting Williams Pipe Line Co. v. Bayer
    Corp., 
    964 F. Supp. 1300
    , 1324 (S.D. Iowa 1997)); Friends of
    Milwaukee’s Rivers, 
    382 F.3d at 760
    ; see also N. & S. Rivers
    Watershed Ass’n, Inc., 949 F.2d at 557 (“Where an agency
    25
    has specifically addressed the concerns of an analogous
    citizen’s suit, deference to the agency’s plan of attack should
    be particularly favored.”). The question of whether the
    prosecution is diligent is related to the question of whether
    the prosecution requires compliance with the Act, as both
    involve the merits of the alleged prosecution. Therefore, we
    are mindful that “when presented with a consent decree we
    must be particularly deferential to the agency’s expertise.”
    Piney Run Pres. Ass’n, 
    523 F.3d at 459
    .
    GASP alleges that the 2012 Consent Decree and 2014
    Consent Order and Agreement do not require compliance
    with the Act with respect to the twenty and sixty percent
    combustion stack opacity requirements and the five percent
    door emissions violations. GASP further argues that because
    Shenango has continued to violate these provisions since the
    effective date of the Consent Decree and Consent Order and
    Agreement the Consent Decrees do not require compliance
    with the Act. We agree with the District Court that “[o]n
    balance, the 2012 and 2014 [Consent Decrees] demonstrate
    that the ACHD is in the process of diligently prosecuting and
    enforcing the same violations alleged in the instant lawsuit.”
    (App. 9).
    We first consider the contention that the ACHD’s
    actions in 2012 and 2014 do not require compliance with the
    sixty percent and twenty percent combustion stack opacity
    requirements. The 2012 Consent Decree addresses these
    violations. In a section titled “Compliance With Applicable
    Laws,” the Decree states that “[n]othing contained in this
    Consent Decree shall be construed to relieve Defendant of
    obligations to comply with all applicable federal, state, and
    local regulations, statutes, and laws, including but not limited
    26
    to” the Clean Air Act, the Pennsylvania SIP, and the ACHD
    Rules and Regulations. (App. 164). This Consent Decree
    specifically requires compliance with both the twenty percent
    and sixty percent combustion stack opacity standards:
    Defendant shall not operate, or allow to be
    operated, any battery of coke ovens at the
    Facility in such manner that, at any time,
    emissions from any coke oven battery
    combustion stack at the Facility (including
    emissions from the COB S-1 combustion
    stack):
    ...
    b.      equal or exceed any opacity of 20% for a
    period or periods aggregating in excess of three
    (3) minutes in any 60 minute period; or
    c.      equal or exceed any opacity of 60% at
    any time.
    (App. 126–27). The Decree was still effective when GASP
    filed its citizen suit, as the District Court retained jurisdiction.
    (App. 168).
    We next consider GASP’s contention that the Consent
    Decrees do not require compliance with the five percent door
    emissions standard. The 2014 Consent Order and Agreement
    addresses the five percent door emissions violations. The
    Consent Order and Agreement states that “the ACHD has
    found and determined . . . . [e]xcess visible emissions from
    the door areas of Battery S-1 in violation of Section
    2105.21.b.1,” which is the five percent door emissions
    standard of the ACHD Rules and Regulations. (App. 4, 89–
    90). In addition to assessing a civil penalty for these
    27
    violations, the Agreement set forth measures to address the
    five percent door emissions violations, “to enhance the
    control of . . . coke oven door emissions” and implement
    “[d]oor inspection procedures [that] have been revised to
    include a door change-out program of 1 to 2 doors/week.”
    (App. 94, 102). This Agreement was still effective when
    GASP filed its citizen suit and the ACHD retained the
    authority “to seek further enforcement of this Agreement.”
    (App. 95, 105–06).
    The 2012 Consent Decree and 2014 Consent Order
    and Agreement adequately set forth ACHD’s approach with
    respect to these three Clean Air Act violations at issue with
    Shenango which include monitoring the violator, providing
    for penalties in the event of violations, and requiring the
    violator to bear the cost of improvement. Concluding that this
    approach does not require compliance with the Act when the
    Consent Decrees specifically reference and address these
    three violations would question the agency’s expertise and
    contradict the accepted practice of giving deference to the
    diligence of the agency’s prosecution. GASP’s apparent
    dissatisfaction with the 2012 Consent Decree led to a
    subsequent civil action and the 2014 Consent Order and
    Agreement. Taken together, these Consent Decrees address
    GASP’s contentions. “Merely because the State may not be
    taking the precise action Appellant wants it to or moving with
    the alacrity Appellant desires does not entitle Appellant to
    injunctive relief.” N. & S. Rivers Watershed Ass’n, Inc., 949
    F.2d at 558. Therefore, we will affirm the District Court’s
    finding that ACHD’s diligent prosecution “requires
    compliance” with the Act.
    III.
    28
    SUMMARY
    In deciding this case, we have determined that the
    diligent prosecution bar of the Clean Air Act is a claim-
    processing rule, not a jurisdictional limitation, and should
    have been dealt with under Rule 12(b)(6) rather than Rule
    12(b)(1). GASP has failed to state a cause of action in its
    citizen suit because of the diligent prosecution bar. The
    ACHD diligently prosecuted the same three Clean Air Act
    violations GASP now attempts to litigate. The ACHD entered
    into a Consent Decree and Consent Order and Agreement
    with Shenango which were still in effect when GASP filed its
    citizen suit. ACHD’s prosecution requires compliance with
    the Act. We hold that when a state or federal agency
    diligently prosecutes an underlying action in court, the
    diligent prosecution bar will prohibit citizen suits during the
    actual litigation as well as after the litigation has been
    terminated by a final judgment, consent decree, or consent
    order and agreement. In addition, when a state or federal
    agency diligently pursues an ongoing consent decree that may
    be modified by the parties and enforced by the agency, the
    diligent prosecution bar will prohibit citizen suits.
    Accordingly, we will affirm the District Court’s Order
    granting Shenango’s motion to dismiss, albeit for somewhat
    different reasons.
    29
    

Document Info

Docket Number: 15-2041

Citation Numbers: 810 F.3d 116

Filed Date: 1/6/2016

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (30)

Karr v. Hefner , 475 F.3d 1192 ( 2007 )

Student Public Interest Research Group of New Jersey, Inc. ... , 759 F.2d 1131 ( 1985 )

Sheila Gotha v. United States , 115 F.3d 176 ( 1997 )

City of Pittsburgh v. West Penn Power Comp., D/B/A ... , 147 F.3d 256 ( 1998 )

Beazer East, Inc. v. Mead Corporation , 525 F.3d 255 ( 2008 )

Cna v. United States , 535 F.3d 132 ( 2008 )

Adkins v. VIM Recycling, Inc. , 644 F.3d 483 ( 2011 )

Supporters to Oppose Pollution, Inc. v. The Heritage Group , 973 F.2d 1320 ( 1992 )

Pension Benefit Guaranty Corporation v. White Consolidated ... , 998 F.2d 1192 ( 1993 )

Friends of Milwaukee's Rivers and Lake Michigan Federation ... , 382 F.3d 743 ( 2004 )

Piney Run Preservation Ass'n v. County Commissioners of ... , 523 F.3d 453 ( 2008 )

Brightwell v. Lehman , 637 F.3d 187 ( 2011 )

LOUISIANA ENVIRONMENTAL ACTION v. Baton Rouge , 677 F.3d 737 ( 2012 )

lavere-c-and-doris-j-baughman-ernest-and-jessie-billotte-mabel-e-bock , 592 F.2d 215 ( 1979 )

Williams Pipe Line Co. v. Bayer Corp. , 964 F. Supp. 1300 ( 1997 )

the-city-of-highland-park-illinois-etc-v-russell-e-train-etc-the , 519 F.2d 681 ( 1975 )

Zipes v. Trans World Airlines, Inc. , 102 S. Ct. 1127 ( 1982 )

Public Interest Research Group v. GAF Corp. , 770 F. Supp. 943 ( 1991 )

United States v. Sunoco, Inc. , 501 F. Supp. 2d 656 ( 2007 )

Citizens for Clean Power v. Indian River Power, LLC , 636 F. Supp. 2d 351 ( 2009 )

View All Authorities »