Nussbaum v. United States ( 2019 )


Menu:
  •         3Jn tbe Wniteb ~tates C!Court of jfeberal C!Claims
    No. 19-376C
    (Filed: September 20, 2019)
    )
    THOMAS NUSSBAUM,                               )     Contract dispute subject to the Contract
    )     Disputes Act, 41 U.S.C. §§ 7101-7109;
    Plaintiff,              )     timeliness; equitable tolling
    )
    v.                                     )
    )
    UNITED STATES,                                 )
    )
    Defendant.              )
    --------------)
    Thomas Nussbaum, prose, Millbrae, California.
    Sonia Orfield, Trial Attorney, Commercial Litigation Branch, Civil Division, United
    States Department of Justice, Washington, D.C., for defendant. With her on the briefs were
    Joseph H. Hunt, Assistant Attorney General, Civil Division, Robert E. Kirschman, Jr., Director,
    and Deborah A. Bynum, Assistant Director, Commercial Litigation Branch, Civil Division,
    United States Department of Justice, Washington, D.C.
    OPINION AND ORDER
    LETTOW, Senior Judge.
    Plaintiff Thomas Nussbaum has brought suit against the United States acting through the
    Federal Bureau of Prisons ("Bureau" or "Bureau of Prisons"), alleging that the Bureau failed to
    pay him in full for work done to replace boilers at the Federal Correction Institution, Victorville,
    California ("Victorville"). Comp!. at 5. Mr. Nussbaum seeks $201,735 in damages and lost
    profits, plus interest and attorneys' fees and costs. Comp!. at 19-20.
    Mr. Nussbaum filed his complaint in March 2019. He alleges four counts against the
    Bureau of Prisons: (1) fraudulent and intentional misrepresentation when Victorville induced
    him to believe his bid was accepted or that he would be a sub-contractor on a bonded
    construction contract but was instead made a sub-supplier without a bond on an impermissible
    purchase order, Comp!. at 15-16; (2) negligent misrepresentation on the same premise, Comp!. at
    16; (3) a breach of the implied covenant of good faith and fair dealing for the misrepresentations
    and for engaging in improper procurement practices, Comp!. at 16; and (4) unjust enrichment for
    not paying for labor and parts supplied by Mr. Nussbaum, Comp!. at 17. Mr. Nussbaum's
    damages consist of $45,000 for being induced improperly by the Bureau and prime contractor,
    Cal Inc., to lower his bid, $62,113 for uncompensated work requested and performed by the
    Bureau that was outside the original contract, $80,375 for costs incurred due to actions of the
    prime contractor that necessitated Mr. Nussbaum to perform extra work and bring lawsuits
    against several subcontractors and the prime contractor, and $14,247 for lost profit at a rate of
    15% on the $63,133 in change orders and $37,806 in extra work necessitated by actions of the
    prime contractor. Comp!. at 17-19. Mr. Nussbaum provided 19 exhibits, which consisted of,
    among other things, the solicitation, the contract, various letters sent by Mr. Nussbaum to the
    contractor, Cal Inc., and the Bureau of Prisons disputing work performance or payments,
    invoices for Mr. Nussbaum's expenses for the project, and an investigation by the Bureau of
    Prisons into Mr. Nussbaum 's allegations of improper procurement practices by the Bureau
    relating to his work. Comp!. Exs. 1-19 .1
    Pending before the court is the government's motion to dismiss Mr. Nussbaum's
    complaint for lack of subject-matter jurisdiction. Def. 's Mot. to Dismiss ("Def. 's Mot."), ECF
    No. 12. The government contends that Mr. Nussbaum's complaint is barred by the six-year
    statute of limitations prescribed under 28 U.S.C. § 2501 and that Mr. Nussbaum, as a sub-
    supplier, lacks standing to sue the government. See generally Def. 's Mot. Mr. Nussbaum has
    responded in opposition, see Pl.'s Opp'n to Def.'s Mot. to Dismiss ("Pl.'s Opp'n."), ECF No. 15,
    and defendant has filed a reply, see Def.'s Reply to Pl.'s Response ("Def.'s Reply"), ECF No.
    17. A hearing was held on August 29, 2019. See Hr' g Tr. 3 :4 to 29:3 (Aug. 29, 2019). 2
    The court concludes that Mr. Nussbaum's complaint falls outside the statute of
    limitations imposed on claims arising under the Contract Disputes Act ("CDA''), 41 U.S.C. §§
    7101-7109. But because the statute of limitations under that Act does not go to jurisdiction and
    may be equitably tolled, the court addresses the standard for equitable tolling. In that respect, the
    court finds that Mr. Nussbaum has not satisfied the exacting standard for equitable tolling, and
    thus the court dismisses his suit for failure to state a claim upon which relief can be granted
    under the CDA.
    BACKGROUND 3
    A. Contract Solicitation Process
    Mr. Nussbaum supplied Victorville with two central plant boilers in 2000. Comp!. at 9.
    At that time, Mr. Nussbaum had quoted $200,000 to change the burners to comply with certain
    nitrogen oxide emission requirements, but Victorville opted instead to implement a Selective
    Catalytic Reduction ("SCR") system, which Mr. Nussbaum alleges cost over $1 million. Comp!.
    at 9. Despite its cost, the SCR system failed to meet the emission standards, requiring
    Victorville to implement upgrades that would. Comp!. at 9.
    Accordingly, during the fall of 2001, Victorville solicited bids for a construction project
    to upgrade the two existing boilers and install a new, third boiler. Comp!. Ex. 1 at 2. Mr.
    Nussbaum and two other companies submitted bids. See Comp!. Ex. 1 at 2. The lowest of the
    three, Mr. Nussbaum offered to complete the project for $320,000. Comp!. Ex. 12 at 2. The
    1
    Some of Mr. Nussbaum's exhibits are individually numbered, but because others are not
    individually paginated, citations to page numbers refer to the page markings as assigned by the
    court's Electronic Filing System.
    2
    The date will be omitted from further citations to the hearing transcript.
    3
    This background does not constitute findings of fact by the court. Rather, its sole
    purpose is to provide context for an analysis of the government's motion to dismiss.
    2
    other bidders were Southern California Boiler, Inc. and Automatic Boiler Company, which had
    bid $331,130 and $343,386, respectively. Comp!. Ex. 14 at 2-7.
    Mike Fief, Victorville's General Foreman, informed Mr. Nussbaum on November 21,
    2001 that he "would really like to see the bid go to Cal Inc." because he had an ongoing working
    relationship with them. Comp!. Ex. 11 at 2. Cal Inc. had not bid on the project but it did have a
    preexisting Schedule Contract with General Services Administration ("GSA") to provide
    environmental services. Comp!. at 6. Consequently, Mr. Nussbaum's quote was forwarded to
    Cal Inc., which, upon receipt of the bid, made some modifications to his proposals and requested
    that he re-quote his price based on those changes. See Comp!. at 17. Mr. Nussbaum did not
    think the alterations would meet the required emission standards, but he lowered his price from
    $320,000 to $275,000 on the understanding that Cal Inc. had Victorville's authority to make the
    changes. See Comp!. at 17.
    Victorville then arranged for Cal Inc. to "broker" the project under its Schedule Contract
    while Mr. Nussbaum supplied materials and performed the actual construction work. Comp!. at
    6. To that end, Victorville's Contracting Officer, Contigny Arakaki, issued a purchase order to
    Cal Inc. for a total price of$398,141. Comp!. at 6. The use ofa purchase order for this project
    was "improper," Mr. Nussbaum alleges, because purchase orders are disallowed for construction
    work. Comp!. at 6, 8. Moreover, the amount of the purchase order issued to Cal Inc. exceeded
    Mr. Nussbaum's original bid amount by $78,141, a difference he regards as Cal Inc.'s
    "commission" for Victorville's use of a Schedule Contract rather than directly issuing him a
    construction contract. Comp!. at 6. He maintains that Victorville designed this arrangement to
    circumvent GSA requirements for constrnction projects and to conceal the fact that Victorville
    had imprudently spent a significant amount of money on the unsuccessful SCR system when it
    could have implemented the necessary changes up front for only $200,000 based on the quote
    Mr. Nussbaum provided when he did the initial work. See Comp!. at 5-6, 14.
    B. Contract Performance and Disputes
    Work on the boiler project was well underway by May 2002, but disagreements soon
    emerged. Victorville requested a series of what Mr. Nussbaum characterizes as "change orders,"
    which involved work such as changing pipes, adding a flue stack, and pouring a new cement pad.
    Comp!. at 17. Mr. Nussbaum considered these to be change orders because he had not included
    them in his bid, but Victorville countered that the matters had been discussed in the original
    project walk-throughs and that Mr. Nussbaum was merely "trying to compensate for his losses"
    after underbidding the job. Comp!. Ex. 15 at 48. Nonetheless, reluctant to stop work and
    assuming the disagreements would be resolved, Mr. Nussbaum and his subcontractors continued
    to perform. See Comp!. Ex. 15 at 51. Victorville never paid for the disputed amounts.
    Then, Mr. Nussbaum asserts that in October 2002, Cal Inc. "interceded" with Mr.
    Nussbaum's subcontractors, Desert Boiler and Bay City, directly paying them more than they
    were entitled to receive before the work was finished and doing so out of funds he asserts Cal
    Inc. owed to him. See Comp!. at 18. Further complicating matters, after receiving payment from
    Cal Inc., Desert Boiler left the job unfinished, leaving Mr. Nussbaum to finish the work and later
    requiring him to incur $23,000 oflegal fees to obtain only a partial recovery from Desert Boiler.
    See Comp!. at 18.
    3
    C. Post-Completion Developments
    Mr. Nussbaum had completed the project by April 9, 2003, when Victorville issued final
    acceptance. Comp!. at 7. He then pursued two separate but simultaneous courses of action: he
    filed a complaint with the Office of the Inspector General and he brought a legal action in state
    court against Cal Inc. for the remaining amount due that it refused to pay him. See Comp!. at 7;
    see also Comp!. Ex. 7 at 4.
    Mr. Nussbaum's complaint with the Office of the Inspector General was filed in
    September 2004, and alleged that Victorville did not award the contract to the lowest bidder, that
    Cal Inc. was not qualified to do the work, that the use of a purchase order was inappropriate, and
    that the Contracting Officer, Contigny Arakaki, told him she did not sign the purchase order and
    that someone must have forged her signature. See Comp!. Ex. 7 at 4. The Inspector General
    investigated the matter and, in a redacted report issued by Special Agent Kenneth Strange in
    October 2004, concluded that "the funding mechanism for the conh·act was appropriate."
    Comp!. Ex. 7 at 4. Ms. Arakaki reportedly told Strange that she had signed the purchase order,
    that she did not accept any bribes relating to the contract, and that she found nothing "suspicious
    about the manner in which the purchase order was completed." Com pl. Ex. 7 at 6-7.
    Mr. Nussbaum's legal action against Cal Inc. was brought at some time before October
    2004, and a settlement eventually was reached by February 2010. See Comp!. at 12.4 The
    settlement included a recovery of $80,000 from Cal Inc. but that amount did not include any
    compensation for the disputed change orders, which Victorville had never paid to anyone. See
    Comp!. at 18. Therefore, Cal Inc. also agreed to issue a Form SF30 to Victorville requesting
    payment of expenses associated with the change orders, which it did effective January 5, 2010.
    See Comp!. at 18; see also Comp!. Ex. 6. Mr. Nussbaum sent the SF30 to Victorville and the
    Bureau offices in Grand Prairie, Texas and Dublin, California. Comp!. at 7. He received no
    response from Ms. Arakaki. Comp!. at 12. The only acknowledgement he received was from
    John Wenkman in Grand Prairie on March 10, 2010. Comp!. at 7; see also Comp!. Ex. 3. Mr.
    Wenkman denied the claim on grounds that Mr. Nussbaum was an improper party to make the
    submission, noting that "the formal request for payment of these services should be requested by
    Cal Inc." because the contract was with Cal Inc. Comp!. Ex. 3 at 2.
    What happened after Nussbaum received the denial from Mr. Wenkman is not entirely
    evident. Mr. Nussbaum provided the court no information concerning actions he took with
    respect to his claim during the nine-year period from when he received the denial in March 2010
    to the time he filed suit in this court in March 2019. In a hearing conducted by the court on
    August 29, 2019, Mr. Nussbaum suggested that he had taken actions with the Government
    Accountability Office ("GAO") related to his claims during this period, and the court requested
    that he produce information regarding those efforts. Hr'g Tr. 17:21 to 19:5, 25:4 to 26:15. Mr.
    Nussbaum subsequently submitted a chain of emails with the GAO that were sent in August
    2019, after he had filed this suit. See Scheduling Order, ECF No. 18; see also Pl.'s Resp. to
    Order, ECF No. 21. Those emails show that Mr. Nussbaum contacted Lacy Vong at the GAO on
    4
    None of the parties' filings specify exactly when this litigation occurred, but the
    Inspector General investigation report, dated October 2004, indicates that the Cal Inc. litigation
    had commenced by that time. Comp!. Ex. 7 at 5. Likewise, the SF30 that emerged from the
    settlement with Cal Inc. was signed in early January 2010, indicating that litigation had
    concluded around that time. Comp!. Ex. 6 at 2.
    4
    August 23, 2019 and again on August 27, 2019, alleging that Ms. Arakaki engaged in "unlawful"
    conduct and that the Inspector General investigator perpetrated a "cover up" of her behavior.
    PL 's Resp. to Order at 4, 6. Because Ms. Arakaki had "abandoned her duties as [Contracting
    Officer], Mr. Nussbaum requested that the GAO step in and review her actions. 
    Id. at 6.
    Ms.
    Vong replied on August 27, acknowledging the emails and informing him that she had forwarded
    the information on to GAO's fraud division for further investigation. Id at 4. Thus, none of the
    information Mr. Nussbaum produced in response to the court's order had any relation to his
    pursuit of his claims between March 2010 and March 2019. In short, there is no evidence in the
    record indicating Mr. Nussbaum's actions to further his claims during this nine-year period.
    STANDARDS FOR DECISION
    A. Rule I2(b)(l) -Lack of Subject-Matter Jurisdiction
    The Tucker Act provides this comt with jurisdiction over "any claim against the United
    States founded either upon the Constitution, or any Act of Congress or any regulation of an
    executive department, or upon any express or implied contract with the United States, or for
    liquidated or unliquidated damages in cases not sounding in tort." 28 U.S.C. § 149l(a)(l). The
    Tucker Act does not, however, provide substantive rights. See United States v. Testan, 
    424 U.S. 392
    , 398 (1976). To establish this court's jurisdiction under the Tucker Act, Mr. Nussbaum
    "must identify a substantive right for money damages against the United States separate from the
    Tucker Act." Todd v. United States, 
    386 F.3d 1091
    , 1094 (Fed. Cir. 2004). An express or
    implied contract creates such a right, 28 U.S.C. § 149l(a)(l), and the CDA confers jurisdiction
    on this court to hear disputes involving government contracts, 41 U.S.C § 7104(b).
    A claim in this court is "barred unless the petition thereon is filed within six years after
    such claim first accrues." 28 U.S.C. § 2501. The six-year statute of limitations specified in
    Section 2501 is jurisdictional and is thus not susceptible to equitable tolling or any of the other
    doctrines that would excuse an untimely claim. See John R. Sand & Gravel Co. v. United States,
    
    552 U.S. 130
    , 133-36 (2008). "Comts created by statute can have no jurisdiction but such as the
    statute confers." Christianson v. Colt Indus. Operating Corp., 486 U.S. 800,818 (1988) (quoting
    Sheldon v. Sill, 49 U.S. (8 How.) 441,449 (1850)).
    Claims that fall under the CDA, however, must proceed through a mandatory
    administrative process. 41 U.S.C. § 7103(a); see also Ace Constructors, Inc. v. United States, 
    70 Fed. Cl. 253
    , 265 (2006), ajf'd, 
    499 F.3d 1357
    (Fed. Cir. 2007). A contractor must first submit a
    written claim within six years of accrual to the contracting officer, who has 60 days in which to
    respond or, if no response is received, the claim is deemed denied by operation of law. 41
    U.S.C. § 7103(f)(5). Upon a decision or a denial by operation of law, the contractor has one year
    in which to bring an action in this court. 41 U.S.C. § 7104(b). It is an open question whether,
    unlike 28 U.S.C. § 2501, the one-year statute of limitations provided by the CDA is non-
    jurisdictional and subject to equitable tolling. See Guardian Angels Med. Serv. Dogs, Inc. v.
    United States, 809 FJd 1244, 1252-53 (Fed. Cir. 2016) (declining to decide whether the one-
    year filing period is jurisdictional). Assuming it is non-jurisdictional, equitable tolling requires
    the litigant to establish two elements: "(I) that he has been pursuing his rights diligently, and (2)
    that some extraordinary circumstance stood in his way and prevented timely filing." Menominee
    Indian Tribe of Wis. v. United States, _U.S._,_, 
    136 S. Ct. 750
    , 755 (2016) (quoting
    Hollandv. Florida, 560 U.S. 631,649 (2010)).
    5
    Mr. Nussbaum, as plaintiff, must establish jurisdiction by a preponderance of the
    evidence. See Trusted Integration, Inc. v. United States, 
    659 F.3d 1159
    , 1163 (Fed. Cir. 2011)
    (citing Reynolds v. Army & Air Force Exch. Serv., 
    846 F.2d 746
    , 748 (Fed. Cir. 1988)). 5 When
    ruling on the government's motion to dismiss for lack of jurisdiction, the court must "accept as
    true all undisputed facts asserted in the plaintiffs complaint and draw all reasonable inferences
    in favor of the plaintiff." Id (citing Henke v. United States, 
    60 F.3d 795
    , 797 (Fed. Cir. 1995)).
    Yet, "[i]f a court lacks jurisdiction to decide the merits of a case, dismissal is required as a matter
    of law." Gray v. United States, 
    69 Fed. Cl. 95
    , 98 (2005) (citing Exparte Mccardle, 74 U.S. (7
    Wall.) 506,514 (1868); Thoen v. United States, 
    765 F.2d 1110
    , 1116 (Fed. Cir. 1985)); RCFC
    12(h)(3) ("If the court determines at any time that it lacks subject-matter jurisdiction, the court
    must dismiss the action.").
    B. Rule 12(b)(6) - Failure to State a Claim
    A complaint will survive a motion to dismiss under RCFC 12(b)(6) ifit "contain[s] sufficient
    factual matter, accepted as true, to 'state a claim to relief that is plausible on its face."' Ashcroft
    v. Iqbal, 556 U.S. 662,678 (2009) (quoting Bell At/. Corp. v. Twombly, 550 U.S. 544,570
    (2007)). "A claim has facial plausibility when the plaintiff pleads factual content that allows the
    court to draw the reasonable inference that the defendant is liable for the misconduct alleged."
    
    Id. The factual
    matters alleged "must be enough to raise a right to relief above the speculative
    level on the assumption that all the allegations in the complaint are true (even if doubtful in
    fact)." 
    Twombly, 550 U.S. at 555-56
    (citations omitted).
    When reviewing the complaint, "the court must accept as true the complaint's undisputed
    factual allegations and should construe them in a light most favorable to the plaintiff."
    Cambridge v. United States, 
    558 F.3d 1331
    , 1335 (Fed. Cir. 2009) (citing Papasan v. Allain, 478
    U.S. 265,283 (1986)) (additional citation omitted). Conclusory statements of law and fact,
    however, "are not entitled to the assumption of truth" and "must be supported by factual
    allegations." 
    Iqbal, 556 U.S. at 679
    . "'[N]aked assertion[s]' devoid of 'further factual
    enhancement"' are insufficient to state a claim." 
    Id. at 678
    (quoting 
    Twombly, 550 U.S. at 557
    );
    accord Bradley v. Chiron Corp., 
    136 F.3d 1317
    , 1322 (Fed. Cir. 1998) ("Conclus01y allegations
    oflaw and unwairnnted inferences of fact do not suffice to support a claim.").
    ANALYSIS
    Mr. Nussbaum asserts that the statute of limitations should be equitably tolled because
    the contracting officer, Contigny Arakaki, "abandoned her duties" by refusing to hear or reply to
    his claims, requiring him "to find someone else to perform them." Pl.'s Opp'n. at 10. He
    contends that the GAO's Oversight Department is responsible for appointing someone to
    perform the contracting officer's duties and he is awaiting "commitment from GAO on that
    issue." 
    Id. He alleges
    that Ms. Arakaki engaged in "prosecutable acts" designed to deny him
    5
    A court may "grant the prose litigant leeway on procedural matters, such as pleading
    requirements." McZeal v. Sprint Nextel Corp., 
    501 F.3d 1354
    , 1356 (Fed. Cir. 2007) (citing
    Hughes v. Rowe, 
    449 U.S. 5
    , 9 (1980) ("An umepresented litigant should not be punished for his
    failure to recognize subtle factual or legal deficiencies in his claims.")). But this leniency cannot
    extend to lessening jurisdictional requirements. See Kelley v. Secreta,y, United States Dep 't of
    Labor, 
    812 F.2d 1378
    , 1380 (Fed. Cir. 1987) ("[A] court may not ... take a liberal view of ...
    jurisdictional requirement[s] and set a different rule for pro se litigants only.").
    6
    "due process" and that these actions made it "impossible to comply" with the statute of
    limitations. 
    Id. The government
    relies on Section 2501, arguing that this court lacks jurisdiction to
    consider Mr. Nussbaum' s complaint because it is untimely and, because Section 2501 is
    jurisdictional, the six-year statute oflimitations is not susceptible to equitable tolling. Def.'s
    Reply at 3. Alternatively, the government asserts that to the extent Mr. Nussbaum's claims are
    considered pass-through claims, and thus governed by the CDA, Mr. Nussbaum could only toll
    the statute of limitations by showing that he "timely sought reconsideration of the contracting
    officer's final decision." Def. 's Reply at 4. Because he did not file a motion for reconsideration,
    the government asserts, Mr. Nussbaum's equitable estoppel arguments should also be rejected
    under the CDA. 
    Id. A. Section
    2501
    A claim is barred in this court under Section 2501 "unless the petition thereon is filed
    within six years after such claim first accrues." 28 U.S.C. § 2501. A claim accrues "as soon as
    all events have occurred that are necessary to enable the plaintiff to bring suit, i.e., when 'all
    events have occurred to fix the Government's alleged liability, entitling the claimant to demand
    payment and sue here for his money."' Martinez v. United States, 
    333 F.3d 1295
    , 1303 (Fed.
    Cir. 2003) (en bane) (quoting Nager Elec. Co. v. United States, 
    368 F.2d 847
    , 851 (Ct. CL 1966))
    (other citations omitted).
    The Supreme Comt recognizes a distinction between jurisdictional and non-jurisdictional
    statutes of limitations. See John R. Sand & Gravel 
    Co., 552 U.S. at 133-34
    . Non-jurisdictional
    statutes of limitations permit courts to toll the time period in light of special equitable
    considerations, but jurisdictional statutes of limitations are more absolute. Designed to foster
    broad, systemic objectives of judicial efficiency, jurisdictional statutes forbid courts from
    considering equitable doctrines that might otherwise prevent the limitations period from running.
    
    Id. Section 2501
    is a jurisdictional statute and is thus "not susceptible to equitable tolling." 
    Id. at 136.
    If Mr. Nussbaum's claims are governed by Section 2501, then, as the government asse1ts,
    he could not bring his claim because the six-year period has run, and equitable tolling is not
    available to him. See Def.'s Mot. at 2-3. At the latest, Mr. Nussbaum's claims accrued around
    the time he received the denial from Mr. Wenkman in March 2010, meaning that he would have
    had to bring his claim in March 2016 for it to fall within the limitations period. Because no
    equitable tolling is available, the statute of limitations would categorically prevent this court
    from hearing Mr. Nussbaum's claims under Section 2501. But Section 2501 is not the pertinent
    statute of limitations here. Instead, this case is governed by the CD A.
    B. The Contract Disputes Act
    The CDA governs disputes involving "any express or implied contract ... made by an
    executive agency for ... the procurement of construction." 41 U.S.C. § 7102(a). Mr. Nussbaum
    maintains that he had a contractual management through Cal Inc. with the Bureau of Prisons to
    provide construction services, and therefore his claim falls within the ambit of the CD A.
    7
    The CDA establishes a mandatory administrative process that requires a contractor to
    submit a "claim" to the contracting officer before the contractor may file suit on that claim in this
    court. 41 U.S.C. § 7103(a)(l). Compliance with the dispute resolution procedures set forth in
    the CDA is a prerequisite to the court's exercise of jurisdiction over claims covered by that Act.
    See Englandv. The Swanson Group, Inc., 
    353 F.3d 1375
    , 1379 (Fed. Cir. 2004) (noting that
    'jurisdiction over an appeal of a contracting officer's decision is lacking unless" the
    administrative procedures are followed). The claim must be in writing and, if it exceeds
    $100,000, must certify that: (1) it is made in good faith; (2) the supporting data is accurate and
    complete; (3) the amount requested reflects the amount for which the contractor believes the
    government is liable; and (4) the certifier is authorized to certify the claim on behalf of the
    contractor. 41 U.S.C. § 7103(b)(l). After the claim is submitted, the contracting officer is
    required-within sixty days-to either issue a decision or notify the contractor of the time within
    which a decision will be issued. 41 U.S.C. § 7103(£)(2).
    Shorter than the general six-year statute of limitations applicable to claims under Section
    2501, the limitations period set forth in the CDA requires that suit be initiated in this court within
    one year of the contractor's receipt of the contracting officer's decision. 41 U.S.C. § 7104(b)(3).
    A contracting officer's failure to issue a decision within sixty days is "deemed to be a decision ..
    . denying the claim." 41 U.S.C. § 7103(£)(5). Thus, if a contractor receives no response from
    the contracting officer within sixty days of filing his complaint, the complaint is deemed denied
    and the contractor must file suit in this court within one year. See Baistar Mech., Inc. v. United
    States, 128 Fed. Cl. 504,515 (2016) ("When a contracting officer fails to issue a final decision
    within the allotted time under the CDA, the contractor's claim is 'deemed' denied and the
    contractor is permitted to seek relief in this court.").
    Here, the government does not appear to dispute that Mr. Nussbaum's claim submitted to
    the contracting officer satisfied the administrative procedural requirements of the CDA. As part
    of the settlement of state court litigation with Cal Inc., Cal Inc. agreed to sponsor Mr.
    Nussbaum's claim to the contracting officer. 
    See supra, at 4
    ; see also Hr' g Tr. 6: 5 to 7: 11. In
    pursuing dismissal on alternative grounds, the government focuses on the one-year statute of
    limitations for filing in this court. Even assuming Mr. Nussbaum's claim satisfies the procedural
    requirements, it is far outside the one-year statute of limitations. Mr. Nussbaum received the
    letter from Mr. Wenkman denying his claim in March 2010, and he never received any response
    from the contracting officer, Contigny Arakaki. Even if Mr. Wenkman's response does not
    constitute a denial given that he was not actually the contracting officer, the lack of response
    from Ms. Arakaki within sixty days is itself deemed a denial under the CDA. In any event, the
    one-year statute of limitations had run, by any measure, before Mr. Nussbaum filed his claim in
    this court approximately nine years later. Mr. Nussbaum's claim, therefore, falls outside the
    CDA' s statute of limitations unless he can establish that it should be equitably tolled.
    C. Equitable Tolling
    The CDA contains two separate filing deadlines. First, Section 7103 requires that a
    contractor submit his claim to the contracting officer within six years after accrual of the claim.
    41 U.S.C. § 7103(a)(4)(A). The government does not appear to dispute that Mr. Nussbaum met
    this deadline. Second, Section 7104 establishes a one-year period for suing in this comt based on
    a decision or deemed denial by the contracting officer. 41 U.S.C. § 7104(b)(3). The one-year
    deadline is the limitation at issue here. The Federal Circuit has explicitly held that the six-year
    limit in Section 7103 is not jurisdictional. See Sikorsky Aircraft Corp. v. United States, 
    773 F.3d 8
     1315, 1322 (Fed. Cir. 2014) (holding that Section 7103 is not jurisdictional because it "does not
    have any special characteristic that would warrant making an exception to the general rule that
    filing deadlines are not jurisdictional"). But the Federal Circuit has declined to decide whether
    the one-year filing deadline in Section 7104 is jurisdictional, while simultaneously emphasizing
    that the Supreme Court "in recent years has repeatedly emphasized that 'filing deadlines
    ordinarily are not jurisdictional."' Guardian 
    Angels, 809 F.3d at 1252-53
    (quoting Sebelius v.
    Auburn Reg'/ Med Ctr., 
    568 U.S. 145
    , 154 (2013)). Indeed, the Supreme Court has held that
    "quintessential claim-processing rules" should not be characterized as jurisdictional unless "there
    is any 'clear' indication that Congress wanted the rule to be 'jurisdictional."' Henderson ex rel.
    Henderson v. Shinseki, 
    562 U.S. 428
    , 435-36 (2011) (quoting Arbaugh v. Y&H Corp., 
    546 U.S. 500
    , 515-16 (2006)). Especially given that there are no special characteristics in Section 7103
    indicating that it should be jurisdictional, such factors do not appear to be present in the context
    of Section 7104 either. It is unnecessary, however, for the comt to decide whether Section 7104
    is jurisdictional because-even assuming it is not-Mr. Nussbaum cannot satisfy the standard
    for equitable tolling.
    Equitable tolling is a "nairnw doctrine." 
    Martinez, 333 F.3d at 1318
    . It requires the
    litigant to establish "(]) that he has been pursuing his rights diligently, and (2) that some
    extraordinary circumstance stood in his way and prevented timely filing." Menominee Indian
    
    Tribe, 136 S. Ct. at 755
    . Both prongs of this test must be met. 
    Id. at 756
    ("Equitable tolling's
    two components [are] 'elements,' not merely factors of indeterminate or commensurable
    weight.") (citation omitted). The second prong is met "only where the circumstances that caused
    a litigant's delay are both extraordinary and beyond its control." 
    Id. at 756
    (emphasis in
    original). Notably, the Supreme Court regards this high bar for equitable tolling, which is
    applied in the habeas context, as a minimum test and suggests that when applied in a civil
    proceeding the standai·d may be even higher. 
    Id. at n.2
    (noting that the equitable tolling test
    derives from a habeas case and does not necessarily apply outside of it, but declining "to decide
    whether an even stricter test might apply to a nonhabeas case"). Moreover, the Supreme Court
    has held that "mere excusable neglect is not enough to establish a basis for equitable tolling;
    there must be a compelling justification for delay, such as where the complainant has been
    induced or tricked by his adversary's misconduct into allowing the filing deadline to pass."
    
    Martinez, 333 F.3d at 1318
    (quoting Irwin v. Dep 't. of Veterans Affairs, 
    498 U.S. 89
    , 96 (1990)).
    Mr. Nussbaum fails to meet either prong of the test. Regarding the first prong, he has
    produced no evidence showing that he made efforts to pursue his case during the nine-year
    period from when he received the denial from Mr. Wenlanan until he filed suit in this court. The
    only documentation Mr. Nussbaum produced when the court inquired about his activities during
    this period was email correspondence with GAO, all of which occurred after he had commenced
    this litigation in March 2019. Given that Mr. Nussbaum was unable to produce any evidence
    about his actions regarding this matter during that time, the court has no basis for concluding that
    he pursued his claims diligently.
    Mr. Nussbaum also fails to satisfy the second prong. He argues that the period should be
    tolled because Ms. Arakaki's "prosecutable" actions-by which he presumably refers to her
    having "abandoned her duties"-made it "impossible to comply with" the statute of limitations,
    rising to the kind of"compelling" justification for the delay. Pl.'s Opp'n at 10. Yet, even if Ms.
    Arakaki's inaction respecting his complaint constitutes misconduct, that is insufficient to satisfy
    the kind of compelling justification required because the statute itself contemplates that
    contracting officers will sometimes fail to respond to claims. To that end, it authorizes plaintiffs
    9
    to pursue their claims in this court after sixty days without a decision from the contracting
    officer, meaning that Mr. Nussbaum's failure to file suit within the one-year time period was
    neither extraordinary nor outside his control. It was not extraordinary because the very text of
    the statute anticipates that contracting officers will occasionally ignore claims, and it was not
    outside his control because the lack of response was deemed a denial that authorized him to bring
    his claim as soon as sixty days had passed. Given that the statute explicitly makes allowance for
    such a scenario, a contracting officer's mere failure to respond to a claim cannot establish the
    kind of misrepresentation, inducement, or trickery that would create a compelling justification
    for tolling.
    While the court is not without sympathy for Mr. Nussbaum, it is bound by the
    jurisdictional limitations prescribed by Congress. Statutes of limitations are designed to ensure
    the prompt and just adjudication of disputes and to balance competing interests. See John R.
    Sand & Gravel 
    Co., 552 U.S. at 133
    . And although the application ofa statute of limitations
    may seem unfair on an individual level, these laws "seek ... to achieve [a] broader system [of]
    related goal [s], such as facilitating the administration of claims, limiting the scope of a
    governmental waiver of sovereign immunity, or promoting judicial efficiency." 
    Id. (citations omitted).
    CONCLUSION
    For the reasons stated, the court finds that Mr. Nussbaum's claim is untimely and cannot
    be equitably tolled. The government's motion to dismiss for lack of subject-matter jurisdiction is
    GRANTED in part and DENIED in part. Mr. Nussbaum's complaint is dismissed, but for failure
    to state a claim upon which relief can be granted and not for a lack of subject-matter jurisdiction.
    The Clerk shall enter judgment accordingly.
    No costs.
    It is so ORDERED.
    Charles F. Letlow
    Senior Judge
    10