United Steelworkers v. PPG Ind Inc , 154 F. App'x 288 ( 2005 )


Menu:
  •                                                                                                                            Opinions of the United
    2005 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    11-8-2005
    United Steelworkers v. PPG Ind Inc
    Precedential or Non-Precedential: Non-Precedential
    Docket No. 04-4363
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2005
    Recommended Citation
    "United Steelworkers v. PPG Ind Inc" (2005). 2005 Decisions. Paper 251.
    http://digitalcommons.law.villanova.edu/thirdcircuit_2005/251
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 2005 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    NOT PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    Case No: 04-4363
    UNITED STEELWORKERS OF AMERICA, AFL-CIO-CLC,
    a labor organization
    v.
    PPG INDUSTRIES, INC.,
    Appellant
    On Appeal from the United States District Court
    for the Western District of Pennsylvania
    District Court No.: 03-cv-00513
    District Judge: The Honorable Joy F. Conti
    Argued September 15, 2005
    Before: SLOVITER, BARRY, and SMITH, Circuit Judges
    (Filed: November 8, 2005)
    Counsel:      William T. Payne (Argued)
    Schwartz, Steinsapir, Dohrmann & Summers
    1007 Mount Royal Boulevard
    Pittsburgh, PA 15223
    Melvin P. Stein
    Daniel M. Kovalik
    United Steelworkers of America
    Five Gateway Center
    Pittsburgh, PA 15222
    Counsel for Appellee
    Richard J. Antonelli (Argued)
    Joseph Mack, III
    Rebecca J. Dick-Hurwitz
    Spilman, Thomas & Battle
    301 Grant Street
    One Oxford Centre, Suite 3440
    Pittsburgh, PA 15219
    Counsel for Appellant
    OPINION
    SMITH, Circuit Judge.
    PPG Industries, Inc. (“PPG”) appeals from the order of the District Court granting
    summary judgment to United Steelworkers of America, AFL-CIO-CLC (“USWA”) in an
    action arising from an ongoing labor dispute.1 This appeal requires us to decide whether
    the doctrine of res judicata bars USWA from bringing the current suit after a previous suit
    between these parties, involving part of the same overall labor dispute, was decided in
    favor of PPG. The District Court concluded that USWA’s second suit presented a
    different cause of action from its first suit against PPG and, therefore, was not barred by
    res judicata. For the reasons that follow, we will affirm the judgment of the District
    Court.
    1
    The District Court exercised jurisdiction over the case pursuant to 
    29 U.S.C. § 185
    ,
    which establishes jurisdiction over actions against labor organizations in the district in
    which such organizations maintain their principal offices. We have jurisdiction to review
    the District Court’s entry of summary judgment under 
    28 U.S.C. § 1291
    , and we review
    such decisions de novo. See, e.g., Vitalo v. Cabot Corp., 
    399 F.3d 536
    , 542 (3d Cir.
    2005).
    2
    USWA first sued PPG seeking specific performance of an alleged agreement to
    arbitrate the claims of employees of multiple PPG plants. USWA asserted that in October
    of 2000, PPG agreed to engage in expedited, multi-plant arbitration of particular transfer-
    right related grievances of its employees. When USWA filed a formal grievance seeking
    multi-plant arbitration of the transfer-right claims, however, PPG rejected it as non-
    arbitrable. In July, 2001, PPG wrote a letter withdrawing what it described as its
    conditional October 2000 agreement to multi-plant arbitration on the ground that USWA
    failed to file a proper grievance over the relevant dispute and also failed to meet the
    conditions of PPG’s prior proposal to submit the multi-plant claims to a single arbitrator.
    USWA filed suit in August, 2001. In August, 2002, District Judge Robert J. Cindrich
    adopted the Report and Recommendation of Magistrate Judge Robert Mitchell that
    summary judgment be granted to PPG on the ground that no multi-plant arbitration
    agreement existed.
    Later in 2002, USWA sent a letter to PPG requesting arbitration of several single-
    plant claims, pursuant to a single-plant arbitration agreement (“the Greensburg
    agreement”), and on behalf only of those employees covered by that agreement. In
    addition to raising other single-plant issues, the letter referenced a grievance included in
    the earlier, multi-plant dispute seeking to recover back-pay and resolve seniority issues
    under the Greensburg agreement. PPG refused to arbitrate all claims by an October, 2002
    letter, and USWA filed a second suit in April of 2003 to compel arbitration. In the
    3
    second action, the District Court (per Conti, J.) granted USWA’s motion for summary
    judgment, rejecting PPG’s arguments that the action was barred under the doctrine of res
    judicata.
    In ruling for USWA, the District Court found that only one prong of the three-
    prong test for res judicata 2 was at issue – whether USWA’s cause of action was the same
    in both suits. PPG argues on appeal that USWA’s current suit should be barred either
    because it presents the same cause of action as did the first suit between the parties, or
    because, at the least, USWA had a reasonable opportunity to sue on the Greensburg
    agreement in the first action. USWA counters that not only were the causes of action in
    the two suits analytically distinct, but also that, at the time of the first suit, the factual
    predicate required to compel arbitration under the Greensburg agreement did not exist
    because PPG had not yet refused to arbitrate under that specific, single-plant agreement.
    In U.S. v. Athlone Industries, Inc., 
    746 F.2d 977
    , 984 (3d Cir. 1984), this Court
    articulated a multi-factor test3 to determine whether two causes of action are identical for
    2
    An action will be barred if: (1) there has been a final judgment on the merits in the
    first of the two actions; (2) the two actions involve the same parties or their privies; and
    (3) both suits involve the same cause of action. See, e.g., General Elec. Co. v. Deutz AG,
    
    270 F.3d 144
    , 158 (3d Cir. 2001).
    3
    The elements of the original Athlone test are:
    (1) whether the acts complained of and the demand for relief are the same
    (that is, whether the wrong for which redress is sought is the same in both
    actions); (2) whether the theory of recovery is the same; (3) whether the
    witnesses and documents at trial are the same (that is, whether the same
    evidence necessary to maintain the second action would have been
    4
    res judicata purposes. We most recently reiterated that test in the bankruptcy case of In re
    Eastern Minerals & Chemical Co. v. Mahan, 
    225 F.3d 330
    , 337-38 (3d Cir. 2000).
    Although we acknowledged in Eastern Minerals that the bankruptcy context presented
    some unique issues in applying the res judicata doctrine, we expressly reiterated and
    applied the Athlone test, holding that “a claim should not be barred unless the factual
    underpinnings, theory of the case, and relief sought against the parties to the proceeding
    are so close to a claim actually litigated . . . that it would be unreasonable not to have
    brought them both at the same time . . . .” 
    Id. at 337-38
    .
    Applying the Athlone test, as clarified in Eastern Minerals, we agree with the
    District Court that the facts of this case require the conclusion that the causes of action in
    the two suits are distinct. As the District Court found, the factual underpinnings of the
    first action primarily involved the negotiations leading up to the putative multi-plant
    agreement, not the arbitration clause in the Greensburg agreement.4 Nor did USWA
    sufficient to support the first); and (4) whether the material facts alleged are
    the same.
    U.S. v. Athlone Industries, Inc., 
    746 F.2d 977
    , 984 (3d Cir. 1984).
    4
    We note that although USWA raised arbitration under the Greensburg agreement as
    possible alternative relief in the first suit, that prayer for relief was not addressed in the
    first action and is not significant for purposes of our “same cause of action” analysis here.
    USWA built no argumentative predicate in its complaint for the alternative relief it
    requested, neither party dealt with the substance of the request for single-plant arbitration
    in the first action, and the ruling of the district court in the first action made no mention
    whatever of USWA’s request for alternative relief. What is more, PPG itself argued
    before the District Court in the instant action that USWA unreasonably failed to raise the
    single-plant claim in the first action – a proposition the District Court accepted in ruling
    5
    complain of the same acts in both suits. USWA’s complaint in the first action clearly
    indicates that its theory of the case was that PPG breached the ad hoc multi-plant
    arbitration agreement. In the second suit, the complaint alleges specifically that PPG
    breached the arbitration clause of the single-plant Greensburg agreement. The documents
    and evidence at issue in the two actions also differ. The letters and other evidence
    suggesting a temporary or ongoing offer on the part of PPG to arbitrate multi-plant
    grievances were critical in the first action and irrelevant to USWA’s claims in the second.
    Finally, and although USWA’s first complaint does make the aforementioned request for
    alternative relief under the Greensburg agreement, it is clear that USWA primarily sought
    specific performance of the supposed multi-plant agreement in the first suit, and it sought
    specific performance of the single-plant Greensburg agreement as its primary relief in the
    second. In short, the two causes of action are distinct in every material respect.
    PPG nonetheless argues that USWA acted unreasonably by not pressing its claim
    under the Greensburg agreement in the first action. This argument is unavailing. Res
    judicata does not punish a litigant for failing to prosecute a claim in an earlier suit if that
    claim had not yet accrued at the time of the initial action. See CoreStates Bank, N.A. v.
    Huls America, Inc., 
    176 F.3d 187
    , 203 (3d Cir. 1999). Further, the parties agree with the
    District Court that an arbitration claim does not accrue until the employer issues an
    unequivocal refusal to arbitrate. Applying that standard, we conclude that USWA’s
    that the causes of action in the two suits were distinct.
    6
    Greensburg claim had not accrued as of the first suit.
    PPG argues that it issued an unequivocal refusal to arbitrate under the Greensburg
    agreement in its July 11, 2001 letter written in advance of the first suit, but the context of
    that letter does not admit of such a reading. The letter stated PPG’s position that USWA
    “has not met” and “has no intention of accepting all the terms and conditions of PPG’s
    prior offer to arbitrate these matters before a single arbitrator.” The letter also indicated a
    withdrawal of the offer to arbitrate the matters at hand before a single arbitrator. Having
    said that, the District Court correctly found that, taken in context, the 2001 letter rejected
    merely multi-plant, multi-party arbitration. Nothing in the 2001 letter speaks to a single-
    plant arbitration under the Greensburg agreement, let alone rejects such an arbitration.
    The request for single-plant arbitration under the Greensburg agreement alone arose for
    the first time in USWA’s letter to PPG dated October 10, 2002. Therefore, PPG’s
    October 15, 2002 letter, taken in its context, unequivocally rejected arbitration under the
    Greensburg agreement by flatly stating “PPG is under no duty to arbitrate.” USWA’s
    Greensburg claim accrued on October 15, 2002.5 Thus, USWA acted reasonably in
    failing to fully litigate that claim as part of the 2001 suit.
    Accordingly, we will affirm the judgment of the District Court.
    5
    As the District Court held, the finding that USWA’s Greensburg claim did not accrue
    until October 15, 2002 also disposes of PPG’s argument before the District Court that
    USWA’s second suit was barred by the six-month statute of limitations governing claims
    under the Labor Management Relations Act. USWA timely filed its second action.