Saudi Amer Bank v. Shaw Grp Inc ( 2009 )


Menu:
  •                                                                                                                            Opinions of the United
    2009 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    2-24-2009
    Saudi Amer Bank v. Shaw Grp Inc
    Precedential or Non-Precedential: Precedential
    Docket No. 05-2717
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2009
    Recommended Citation
    "Saudi Amer Bank v. Shaw Grp Inc" (2009). 2009 Decisions. Paper 1797.
    http://digitalcommons.law.villanova.edu/thirdcircuit_2009/1797
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 2009 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    Nos. 05-2717 & 07-1772
    IN RE: STONE & WEBSTER, INCORPORATED, ET AL.,
    Debtors
    SAUDI AMERICAN BANK
    v.
    SHAW GROUP, INC.;
    SWINC ACQUISITION THREE, INC.;
    SWE&C LIQUIDATING TRUSTEE,
    successor to Stone & Webster Engineering Corporation, et al.
    Shaw Group, Inc.,
    Appellant
    Appeal from the United States District Court
    for the District of Delaware
    (D.C. Civil Action No. 04-cv-00834)
    District Judge: Honorable Sue L. Robinson
    Argued April 18, 2008
    Before: SCIRICA, Chief Judge, AMBRO
    and FISHER, Circuit Judges
    (Opinion filed: February 24, 2009)
    Stephen E. Jenkins, Esquire (Argued)
    Catherine A. Strickler, Esquire
    Ashby & Geddes
    500 Delaware Avenue, 8th Floor
    Wilmington, DE 19899
    Counsel for Appellant
    Amy B. Abbott, Esquire
    Kirkpatrick & Lockhart Preston Gates Ellis
    One Lincoln Street
    State Street Financial Center
    Boston, MA 02111-0000
    Bruce S. Barnett, Esquire
    Daniel E. Rosenfeld, Esquire (Argued)
    DLA Piper
    33 Arch Street
    Boston, MA 02110
    Francis A. Monaco, Jr., Esquire
    Kevin J. Mangan, Esquire
    Womble, Carlyle, Sandridge & Rice
    222 Delaware Avenue, Suite 1501
    Wilmington, DE 19810-0000
    Counsel for Appellee
    2
    OPINION OF THE COURT
    AMBRO, Circuit Judge
    Stone & Webster, Incorporated (“Stone & Webster”) and
    its subsidiaries—including Stone & Webster Engineering
    Corporation (“SW Engineering”)—filed for Chapter 11
    bankruptcy protection in the District of Delaware. Shortly
    thereafter, Stone & Webster and its subsidiaries entered into an
    asset purchase agreement (“Purchase Agreement”) with the
    Shaw Group, Inc. (“Shaw”) to sell substantially all of their
    assets. The District Court approved the Purchase Agreement in
    a Sale and Assumption Order (“Sale Order”).
    At issue is whether by this transaction Shaw assumed a
    guaranty obligation of SW Engineering to Saudi American Bank
    (“SAMBA”). In that rare case where the seller and purchaser
    agree, SW Engineering and Shaw have argued that the latter did
    not assume the guaranty.1 SAMBA contends otherwise.
    1
    While SW Engineering is not a party to this appeal (even
    though it is listed in the case caption), it previously argued
    before the Bankruptcy Court that Shaw did not assume liability
    for the guaranty obligation or a related “Payment Letter.” See
    SW Engineering’s Answer, Affirmative Defenses, and
    Counterclaims, Saudi American Bank v. Shaw Group, Inc. (In re
    3
    The District Court, through a different Judge than the one
    who entered the Sale Order, agreed with SAMBA’s view and
    granted summary judgment in its favor.              In separate
    proceedings, the Court also awarded SAMBA pre- and post-
    judgment interest on the guaranteed debt, as well as attorneys’
    fees and other litigation costs.
    Stone & Webster, Inc.), Ch. 11 Case No. 00-02142, Adv. No.
    01-07766, at 10–11, 15–16 (Bankr. D. Del. Oct. 29, 2001)
    (“[T]he [Payment] Letter and the 1994 Guarantee are not
    Assumed Liabilities within the meaning of the [Purchase
    Agreement] and were not assumed by the Shaw Parties
    thereunder.”). The SWE&C Liquidating Trustee, the post-
    confirmation successor to SW Engineering, also agreed to terms
    in a Settlement Agreement with SAMBA that stated with regard
    to this case: “Nothing in this Agreement shall obligate the
    debtors [including SW Engineering and Stone & Webster] to
    alter their position that SAMBA does not have a valid claim
    against Shaw . . . .” Stipulation and Agreed Order Dismissing
    Adversary Proceeding, Appendix at A508, Saudi American
    Bank v. Saudi Arabian Oil Co. (In re Stone & Webster, Inc.),
    No. 07-3891 (3d Cir. pending).
    Shaw additionally has emphasized SW Engineering’s
    agreement with its position throughout its brief. See, e.g.,
    Shaw’s Br. at 21 (“There are only two parties to the [Purchase
    Agreement]—[the Stone & Webster entities] and Shaw—and
    they both agree that Shaw did not assume any liability to
    SAMBA.”).
    4
    Because we believe the Court misinterpreted the
    Purchase Agreement and Sale Order, we reverse its grant of
    summary judgment. While this decision further requires us to
    vacate the award of pre- and post-judgment interest, attorneys’
    fees and other litigation costs, we note our agreement with the
    Court’s analysis of those issues.
    I.     Factual and Procedural Background
    In 1980, SW Engineering formed a joint venture with
    Abdullah Said Bugshan & Bros. (“Bugshan”), a Saudi Arabian
    company. The joint venture obtained a contract with the Saudi
    Arabian American Oil Company (“Aramco”) to upgrade an oil
    refinery at Ras Tanura in Saudi Arabia (known as the “in-
    kingdom project” or “project number 65004/00”). In a separate
    contract, SW Engineering agreed to provide manufactured
    goods to Aramco for use at Ras Tanura (called the “out-of-
    kingdom project” or “project number 05062011”).
    To fund the in-kingdom project, the joint venture
    borrowed $35,000,000 from SAMBA. Bugshan and SW
    Engineering facilitated the granting of this loan by individually
    guarantying 50% of the amount owed by the joint venture to
    SAMBA (in the case of SW Engineering, the “Guaranty”). See
    Saudi American Bank v. Shaw Group, Inc. (“Saudi American
    Bank I”), No. 00-2142, 
    2005 WL 1036556
    , at *1 (D. Del. May
    3, 2005). Following completion of the in-kingdom project, the
    joint venture was unable to repay the loan and SW Engineering
    5
    and Bugshan began making payments pursuant to their
    guaranties. SW Engineering confirmed its obligation to pay this
    debt in a 1998 payment letter to SAMBA (the “Payment
    Letter”).
    When Stone & Webster and its subsidiaries filed their
    bankruptcy petitions in 2000, SW Engineering owed SAMBA
    $6,728,549 on the Guaranty. Shortly after those filings, Shaw
    purchased substantially all of the Stone & Webster entities’
    assets through an auction sale. The companies stated the terms
    of this sale in the Purchase Agreement.
    That document, which states that it is governed by
    Delaware law, labels the assets and liabilities of the sellers as
    either “assumed” by Shaw or “excluded” from the deal. As is
    typical, assumed assets and liabilities are those not excluded
    from the Purchase Agreement. Thus the definitions of Excluded
    Assets and Excluded Liabilities have controlling importance.
    Section 2.02 of the Purchase Agreement defines
    “Excluded Assets” as all Rejected Contracts, Completed
    Contracts, and Special Project Claims.
    •      “Rejected Contracts” are any contracts or related
    obligations listed by Stone & Webster on Schedule
    5.16(b). That schedule lists fifteen projects, none of
    which relates to SW Engineering’s work at the Ras
    Tanura facility.
    6
    •     “Completed Contracts” and their related receivables and
    drawings are “those specifically set forth on Schedule
    2.02(b), under which substantially all of the contractual
    work effort of Sellers has been completed.” Included
    within Schedule 2.02(b) is a notation of the in-kingdom
    project name, Aramco Ras Tanura (Bugshan), but with
    the out-of-kingdom project number, 05062011.
    •     “Special Project Claims” are “any and all claims under
    the project agreements set forth on Schedule 2.02(e).”
    That schedule lists the “Ras Tanura, Saudi Arabia,
    Refinery Upgrade Project,” specifically noting the in-
    kingdom project number (65004/00) and the presence of
    “one or more potential claims for payment under a series
    of Letters of Credit issued by [SAMBA].”
    The Purchase Agreement defines “Excluded Liabilities” in
    § 1.01 as
    any and all liabilities or obligations of [Stone &
    Webster and its subsidiaries] of any kind or
    nature, other than the Assumed Liabilities,
    including those liabilities or obligations described
    in Section 2.04, whether known or unknown,
    fixed or contingent, recorded or unrecorded, and
    whether arising before or after the Closing,
    including . . . surety or other bonds relating to
    Completed Contracts or Rejected Contracts.
    7
    App. at A118. In addition, § 2.04 notes that “Excluded
    Liabilities” are “liabilities or obligations associated with any
    Excluded Assets” or “associated with any and all indebtedness
    of [Stone & Webster and its subsidiaries] for borrowed money
    not included in the Assumed Liabilities.” The phrase “liabilities
    or obligations” is not defined, but provisions of the Purchase
    Agreement indicate, as one would expect, that guaranties are
    liabilities.2
    Perhaps because the parties were unsure which assets and
    liabilities were being transferred to Shaw, Sections 2.07 and
    5.17 of the Purchase Agreement permit Stone & Webster and its
    subsidiaries to amend schedules “to reflect any changes required
    as a result of the addition of applicable Subsidiaries” and to
    execute any new documents “that may be reasonably necessary
    or desirable.” Id. at A133, A158. Section 7.01(a) further
    explains that any added or amended schedule is “deemed to have
    been made and delivered as of the Effective Date [of the
    Purchase Agreement].” Id. at A163.
    After reviewing the Purchase Agreement, the District
    2
    For instance, Schedule 2.03, which describes liabilities, lists
    a guaranty given by Stone & Webster to Enron Power
    Corporation and includes a reference to “outstanding bank
    indebtedness.” App. at A199. A note at the end of Schedule
    3.17(a)(ix) also labels responsibilities from a guaranty as a
    “liability.” Id. at A283-84.
    8
    Court approved the sale of Stone & Webster’s assets in the Sale
    Order.3 The Order adopts “all of the terms and conditions” of
    the Purchase Agreement, but it adds protections for third parties
    claiming repayment rights under a contract or asset assumed by
    Shaw. For example, it states that Shaw “will cure . . . any
    default existing prior to the date hereof under any of the
    Assumed Contracts.” Id. at A432 (Paragraph S of the Order).
    It also states that “all rights and remedies of any non-debtor
    party or Shaw under any of the Assumed Contracts . . . are fully
    preserved and shall be fully enforceable after the Closing against
    Shaw or the non-debtor party . . . .” Id. at A437 (Paragraph 12
    of the Order). No party objected to the addition of these terms.
    Following conclusion of the asset sale, SAMBA filed a
    cure claim against SW Engineering for payment of $6,728,549
    pursuant to the Guaranty.4 Shaw did not contest this claim until
    3
    At the time of the sale hearing, the District Court was
    hearing bankruptcy cases pursuant to 
    28 U.S.C. § 1334
    (a).
    4
    SAMBA’s Statement of Cure Claim also sought $144,430
    from SW Engineering on an unrelated letter of credit issued by
    SAMBA to the joint venture’s account. SAMBA had received
    a demand for payment on the letter of credit from the second
    advising bank, MISR Romanian Bank of Bucharest, but this
    payment was stayed by an injunction obtained by SW
    Engineering. See App. at A457–58, A475–89. SAMBA did not
    request payment from Shaw of the $144,430 in the complaint
    that began the case before us. See Saudi American Bank I, 2005
    9
    it filed its Second Omnibus Objection to Claims in April 2001.
    See 
    id.
     at A1078–90. SAMBA thereafter filed suit against Shaw
    and SW Engineering in the Bankruptcy Court for the District of
    Delaware. SAMBA asked the Court to determine that the
    Guaranty and Payment Letter were Assumed Liabilities for
    which Shaw was responsible, or, in the alternative, to allow
    SAMBA’s cure claim as an unsecured claim against SW
    Engineering. After successfully moving for a withdrawal of the
    proceeding to the District Court, Shaw answered SAMBA’s
    claim with a motion for summary judgment.5 Shaw alleged that
    SAMBA lacked standing to sue under the Purchase Agreement
    and claimed that SW Engineering’s Guaranty and Payment
    WL 1036556, at *4.
    5
    The docket sheet and District Court opinions indicate that
    SW Engineering joined Shaw’s motion for summary judgment.
    See App. at A56–61 (“Motion for Summary Judgment Filed by
    The Shaw Group, Inc. and SWINC Acquisition Three, Inc., and
    Stone & Webster Engineering Corporation . . . (Entered:
    08/13/2002).”); Saudi American Bank I, 
    2005 WL 1036556
    , at
    *1 (identifying SW Engineering as a defendant and stating that
    “[p]resently before the court are plaintiff’s and defendants’
    motions for summary judgment”); Saudi American Bank v. Shaw
    Group, Inc., 
    354 B.R. 686
    , 687 (D. Del. 2006) (describing SW
    Engineering as a defendant and recounting that “[p]laintiffs and
    defendants filed motions for summary judgment”). SW
    Engineering, however, was not a party to the cross-motions for
    summary judgment.
    10
    Letter were Excluded Liabilities for which Shaw was not
    responsible.6 SAMBA counterclaimed with its own motion for
    summary judgment.
    The District Court granted SAMBA’s summary judgment
    motion and denied that of Shaw. In reaching its decision, the
    Court made two principal rulings. First, it held that SAMBA
    had standing to bring its suit. See Saudi American Bank I, 
    2005 WL 1036556
    , at *5 n.11. Second, it determined that “the
    Guaranty and Payment Letter are contracts that were assumed by
    defendant Shaw by operation of the [Purchase Agreement] and
    [Sale Order].” Id. at *7. The Court believed the Guaranty and
    Payment Letter were “separate contract[s]” that were not
    “unambiguously” listed as Excluded Assets or Excluded
    6
    SAMBA now asserts that Shaw was equitably estopped
    from asserting that it did not assume SW Engineering’s liability
    to SAMBA because Shaw failed timely to contest SAMBA’s
    cure claim. As SAMBA did not present this equitable estoppel
    argument to the District Court, it is waived. See Union Pac.
    R.R. Co. v. Greentree Transp. Trucking Co., 
    293 F.3d 120
    , 126
    (3d Cir. 2002). The failure to present this argument is easily
    understood, as equitable estoppel would need to involve
    misleading conduct by Shaw and detrimental reliance by
    SAMBA, not simply a failure timely to contest the cure claim.
    See Bechtel v. Robinson, 
    886 F.2d 644
    , 650 (3d Cir. 1989)
    (explaining that, under Delaware law, equitable “estoppel may
    arise when a party by his conduct . . . leads another, in reliance
    upon that conduct, to change position to his detriment”).
    11
    Liabilities under the Purchase Agreement. 
    Id.
     at *6–7. In so
    reasoning, it rejected Shaw’s argument that the Guaranty and
    Payment Letter were excluded by association with the in-
    kingdom project’s listing as a Completed Contract or a Special
    Project Claim. The Court considered only the Purchase
    Agreement and Sale Order in reaching its decision. Among the
    evidence it did not consider was the declaration of James P.
    Carroll, the President and Chief Restructuring Officer for Stone
    & Webster, who supported Shaw’s claim that the Guaranty and
    Payment Letter were Excluded Liabilities.7 See 
    id.
     at *5 n.10.
    In separate, but related, adversary proceedings, the
    District Court considered whether Shaw, as the party the Court
    ruled to have assumed the Guaranty, owed SAMBA pre- and
    post-judgment interest, attorneys’ fees and related costs under
    the terms of the Guaranty. See Saudi American Bank v. Shaw
    Group, Inc. (“Saudi American Bank II”), 
    354 B.R. 686
    , 688–93
    (D. Del. 2006). On the matter of pre-judgment interest, the
    Court applied New York law and held that the Guaranty set an
    7
    Although it is not relevant to our determination of this case,
    we note that the District Court properly excluded Carroll’s
    declaration at summary judgment review. See MBIA Ins. Corp.
    v. Royal Indem. Co., 
    426 F.3d 204
    , 214 n.4 (3d Cir. 2005) (“[I]n
    determining whether an ambiguity exists a court may consider
    only undisputed background facts . . . . ‘[U]ndisputed
    background facts’ do not include the self-serving parol evidence
    submitted by the parties . . . .”).
    12
    interest rate of 9%. See 
    id.
     at 690–91. It also awarded SAMBA
    $345,714.50 in attorneys’ fees along with $20,750.00 in costs.
    See id. at 692; Saudi American Bank v. Shaw Group, Inc.
    (“Saudi American Bank III”), 
    360 B.R. 64
    , 67 (D. Del. 2007).
    Lastly, the Court awarded SAMBA post-judgment interest at a
    rate of 3.33%. See Saudi American Bank II, 
    354 B.R. at 693
    .
    Shaw appealed the decisions of the District Court. We
    consolidated the cases for review.
    II.    Jurisdiction and Standard of Review
    The District Court had jurisdiction under 
    28 U.S.C. §§ 157
     and 1334. We have jurisdiction under 
    28 U.S.C. § 1291
    .
    We exercise plenary review over the District Court’s
    grant of summary judgment. Atkinson v. Lafayette Coll., 
    460 F.3d 447
    , 451 (3d Cir. 2006). Summary judgment is appropriate
    if there is “no genuine issue as to any material fact” and the
    party making the motion “is entitled to judgment as a matter of
    law.” Fed. R. Civ. P. 56(c); see also Celotex Corp. v. Catrett,
    
    477 U.S. 317
    , 322–23 (1986). “In determining whether a
    genuine issue of fact exists, we resolve all factual doubts and
    draw all reasonable inferences in favor of the nonmoving party.”
    Conoshenti v. Pub. Serv. Elec. & Gas Co., 
    364 F.3d 135
    , 140
    (3d Cir. 2004). We may affirm or vacate the District Court’s
    judgment on any grounds supported by the record. In re
    Teleglobe Commc’ns Corp., 
    493 F.3d 345
    , 385 (3d Cir. 2007).
    13
    We engage in plenary review of questions of contract
    interpretation. See Jumara v. State Farm Ins. Co., 
    55 F.3d 873
    ,
    880–81 (3d Cir. 1995).
    As different District Judges were involved in approving
    the Purchase Agreement by the Sale Order and in interpreting
    that Order, this is not a case where the District Judge is afforded
    special deference in interpreting her own order.
    III.   Discussion
    We review three issues: (1) whether the District Court
    erred in holding that SAMBA had standing to bring a claim
    against Shaw; (2) whether summary judgment in favor of
    SAMBA was proper; and (3) whether the Court correctly
    awarded SAMBA pre- and post-judgment interest, attorneys’
    fees and other costs of litigation.
    A.     Standing
    In determining whether SAMBA has standing to sue
    under the Purchase Agreement for payment of SW
    Engineering’s guaranty of the in-kingdom project loan, Shaw
    focuses on § 10.08 of the Purchase Agreement. It states:
    No Third Party Beneficiary. The terms and
    provisions of this Agreement . . . are intended
    solely for the benefit of the parties . . . and their
    14
    respective successors and permitted assigns, and
    are not intended to confer third-party beneficiary
    rights upon any other Person.
    Shaw argues that this provision, typical in sale-of-asset
    agreements, denies SAMBA standing as a third-party
    beneficiary by stating that only the debtors (i.e., the Stone &
    Webster entities) have standing to sue Shaw under the Purchase
    Agreement. According to this argument, SAMBA should have
    brought its claim for payment of the Guaranty and Payment
    Letter only against SW Engineering, which could then have
    sought indemnification from Shaw if it paid SAMBA and
    believed that the Guaranty and Payment Letter were assumed by
    Shaw.8
    Shaw’s argument is no doubt plausible. “Ordinarily, a
    stranger to a contract acquires no rights thereunder.” Guardian
    Constr. Co. v. Tetra Tech Richardson, Inc., 
    583 A.2d 1378
    ,
    8
    Shaw presents two other arguments for consideration in its
    brief. First, it asserts that the Guaranty and Payment Letter were
    not “Contracts” that granted SAMBA enforcement rights under
    the Sale Order’s third-party beneficiary provisions. Second,
    Shaw claims that the Guaranty and Payment Letter are non-
    executory contracts incapable of being assigned to it. As Shaw
    failed to present either of these arguments to the District Court,
    they are waived on appeal. See Pension Benefit Guar. v. White
    Consol. Indus., Inc., 
    215 F.3d 407
    , 418–19 (3d Cir. 2000).
    15
    1386 (Del. Super. Ct. 1990). According to Delaware law, which
    governs the Purchase Agreement, “to qualify as a third party
    beneficiary of a contract, (a) the contracting parties must have
    intended that the third party beneficiary benefit from the
    contract, (b) the benefit must have been intended as a gift or in
    satisfaction of a pre-existing obligation to that person, and (c)
    the intent to benefit the third party must be a material part of the
    parties’ purpose in entering into the contract.” E.I. DuPont de
    Nemours & Co. v. Rhone Poulenc Fiber & Resin Intermediates,
    S.A.S., 
    269 F.3d 187
    , 196 (3d Cir. 2001). In this case, we are
    not aware of evidence that Shaw intended to confer direct
    benefits to SAMBA through the Purchase Agreement; in fact,
    § 10.08 makes clear that Shaw did not intend to give enforceable
    rights to any third party. Thus, on the basis of the Purchase
    Agreement alone, SAMBA arguably does not have standing.
    The Purchase Agreement, however, is not the only
    document relevant to determining SAMBA’s rights. The Sale
    Order approving the Purchase Agreement includes language
    protecting the rights of third parties. Paragraph 12 of the Order
    states that “all rights and remedies of any non-debtor party or
    Shaw under any of the Assumed Contracts . . . are fully
    preserved and shall be fully enforceable after the Closing against
    Shaw or the non-debtor party . . . .” App. at A437. This
    language supersedes § 10.08 of the Purchase Agreement. See
    Caldwell Trucking PRP v. Rexon Tech. Corp., 
    421 F.3d 234
    ,
    245 (3d Cir. 2005) (explaining that “general, boilerplate
    language” prohibiting third-party actions “must yield to the
    16
    specific direction” of separate contractual provisions granting
    third parties enforceable rights in assumed liabilities); see also
    In re Safety-Kleen Corp., 
    380 B.R. 716
    , 740 (D. Del. 2008)
    (“When a buyer expressly assumes liabilities of a seller, it
    becomes directly liable therefore, regardless of any language in
    the sale agreement otherwise purporting generally to disclaim
    third-party beneficiary rights.”).
    In this context, SAMBA, a non-debtor, has standing to
    claim that Shaw has assumed SW Engineering’s guaranty of the
    in-kingdom project loan. We therefore affirm the District
    Court’s determination of this issue.9
    B.     Summary Judgment
    Based on the standard already noted, summary judgment
    is appropriate if no genuine issue of material fact exists over
    whether Shaw assumed SW Engineering’s guaranty of the in-
    kingdom project loan. Settling this issue requires us to ascertain
    the intentions of Shaw and the Stone & Webster entities as set
    out in the Purchase Agreement and Sale Order. See Eagle
    9
    Shaw claims that by this conclusion “every . . . part[y] who
    d[oes] not like the status it was assigned under the Purchase
    Agreement ha[s] standing to sue Shaw.” Shaw’s Br. at 33.
    Shaw, however, agreed to the Sale Order, and we are simply
    following what it states. See Saudi American Bank I, 
    2005 WL 1036556
    , at *7.
    17
    Indus., Inc. v. DeVilbiss Health Care, Inc., 
    702 A.2d 1228
    , 1232
    (Del. 1997).      The District Court determined that these
    documents unambiguously proved that “the Guaranty and
    Payment Letter are contracts that were assumed by defendant
    Shaw.” Saudi American Bank I, 
    2005 WL 1036556
    , at *7. We
    reach the opposite conclusion.
    In its review of the Purchase Agreement and Sale Order,
    the District Court considered only whether the Guaranty and
    Payment Letter were specifically listed as Excluded Liabilities.
    It did not question whether they were excluded by way of
    association with the excluded in-kingdom project. The Court
    decided not to consider this possibility based on its application
    of the “fundamental premise that a guaranty ‘is a separate
    contract . . . from the basic contract to which it is collateral.’”
    Id. at *6 (quoting FinanceAmerica Private Brands, Inc. v.
    Harvey E. Hall, Inc., 
    380 A.2d 1377
    , 1379 (Del. Super. Ct.
    1977)). This premise, it concluded, controlled interpretation of
    the parties’ agreements.
    We disagree with the Court’s premise that the Guaranty
    and Payment Letter’s association with the in-kingdom project is
    irrelevant to their classification as assumed or excluded
    liabilities. To be sure, case law establishes that “a guaranty and
    the underlying contract are separate contracts.” Saudi American
    Bank I, 
    2005 WL 1036556
    , at *6 n.12. But that law does not
    answer whether the parties intended to include the Guaranty and
    Payment Letter under a listing of the in-kingdom project.
    18
    Instead, the general law of contract, that agreements are
    enforced “in accord with their makers’ intent,” must control.
    MBIA Ins. Corp. v. Royal Indem. Co., 
    426 F.3d 204
    , 210 (3d
    Cir. 2005). In this case, the parties expressed a clear intent to
    associate guaranties and other liabilities or obligations with their
    underlying contracts.
    As discussed, the Purchase Agreement contains several
    sections that define liabilities as excluded based on their
    association with excluded contracts. Section 2.04, as noted
    above in part, describes “Excluded Liabilities” as
    (a) liabilities . . . other than Assumed Liabilities;
    . . . (c) liabilities or obligations associated with
    any Excluded Assets; (d) liabilities or obligations
    associated with any and all indebtedness of [Stone
    & Webster and its subsidiaries] for borrowed
    money not included in the Assumed Liabilities;
    [and] (e) liabilities or obligations under the
    Assumed Contracts that are not Assumed
    Liabilities and liabilities or obligations arising
    under the Rejected Contracts or the Completed
    Contracts.
    App. at A129. Under clauses (c), (d), or (e), a liability need only
    be “associated with” an Excluded Asset or a debt not an
    Assumed Liability, or “aris[e] under” a Rejected or Completed
    Contract, to qualify as an “Excluded Liability.” Excerpts from
    19
    the transcript of the Sale Order hearing further indicate that the
    parties and the Court understood that a listing of an excluded
    contract also included “all liabilities arising under th[at] . . .
    contract.” 
    Id.
     at A792; see also 
    id.
     at A762, A767–75, A789.
    Thus, the Guaranty and Payment Letter may be Excluded
    Liabilities if the in-kingdom project with which they are
    associated is listed as an Excluded Asset.10
    Recognizing the importance of whether the in-kingdom
    10
    SAMBA argues against associating the Guaranty and
    Payment Letter with the in-kingdom project because neither SW
    Engineering nor Stone & Webster had “any involvement
    whatsoever in [the project’s] execution and performance.”
    SAMBA’s Br. at 4. It also claims that use of the loan secured by
    the Guaranty was not limited to the in-kingdom project. 
    Id.
     at
    5–7. It is evident, however, that SW Engineering had an equity
    stake in the joint venture, see App. at A516, and that SW
    Engineering included contracts related to the in-kingdom project
    in its bankruptcy estate. See 
    id.
     at A212. Furthermore, internal
    SAMBA documents and the deposition transcript of Sheheryar
    Ali, SAMBA’s Assistant General Manager, indicate that the
    Guaranty was linked exclusively to the loan given by SAMBA
    to the joint venture to finance the in-kingdom project. See 
    id.
     at
    A77–96, A294; see also SAMBA’s Br. at 5 (“SAMBA has
    never denied that its initial loan to [the joint venture] was for the
    stated purpose of providing working capital that could be used
    for the In-Kingdom Contract and that Contract was, initially, the
    primary source of payment of the loan.”).
    20
    project is an assumed or excluded liability, our review turns to
    the schedules that identify the three types of Excluded Assets:
    Rejected Contracts, Completed Contracts, and Special Project
    Claims.
    First, all parties agree that the in-kingdom project is not
    a Rejected Contract. Schedule 5.16(b) of the Purchase
    Agreement lists the Rejected Contracts and contains no mention
    of the in-kingdom project.
    Second, the in-kingdom project’s status as a Completed
    Contract is ambiguous. Completed Contracts, to repeat, are
    “those specifically set forth on Schedule 2.02(b), under which
    substantially all of the contractual work effort of [the Stone &
    Webster entities] has been completed.” 
    Id.
     at A117. To repeat,
    Schedule 2.02(b) references the in-kingdom project name,
    Aramco Ras Tanura (Bugshan)/Refinery Upgrade, but does so
    in conjunction with the out-of-kingdom project number,
    05062011. See 
    id.
     at A196. Shaw argues that this reference
    proves that the parties meant to exclude both contracts. See
    Shaw’s Br. at 15–16. SAMBA asserts that the project number
    should control and faults Shaw and SW Engineering for not
    clarifying the schedule. See SAMBA’s Br. at 18–19, 53–54; Or.
    Arg. Tr. at 17. We are not convinced either way. The listing of
    the in-kingdom project name is significant, but the record does
    not show conclusively what the parties to the Purchase
    Agreement intended it to mean.
    21
    Third, the schedule of Special Project Claims
    unambiguously lists the in-kingdom project as an Excluded
    Asset. Schedule 2.02(e) excludes “any and all claims and
    liabilities” related to the “Ras Tanura, Saudi Arabia, Refinery
    Upgrade Project,” and specifies the in-kingdom project. App.
    at A212. In particular, the schedule lists:
    Contract for Construction dates as of June
    28, 1994 by and between Saudi Arabian Oil
    Company (“Saudi Aramco”) and BS&W [the joint
    venture] (designated by Saudi Aramco as Contract
    No. 65004/00).
    ...
    Contract retainage due to BS&W [the joint
    venture] in the amount of $5,757,000 on Contract
    No. 65004/00 . . . .
    ...
    One or more potential claims for payment
    under a series of Letters of Credit issued by Saudi
    American Bank . . . .
    
    Id.
     This listing is decisive. It excludes the in-kingdom project
    by name and number, and it makes clear that the Stone &
    Webster entities retain the claims and liabilities of the Ras
    Tanura Upgrade Project. The in-kingdom project is thus an
    Excluded Asset under the Purchase Agreement, and the
    Guaranty and Payment Letter are Excluded Liabilities because
    22
    they are associated with that Excluded Asset.11
    11
    The District Court did not consider this reasoning because
    “Schedule 2.02(e) was added to the [Purchase Agreement] by
    debtor and defendant Shaw subsequent to [the District Court]’s
    approval of the Execution Copy of the [Purchase Agreement].”
    Saudi American Bank I, 
    2005 WL 1036556
    , at *3 n.6. But the
    Court did consider as relevant other schedules added to the
    Purchase Agreement on the same day as Schedule 2.02(e). See,
    e.g., 
    id.
     at *3 & *7 (reviewing the contents of Schedule
    3.17(a)(ix)). And, as mentioned, Sections 2.07 and 5.17 of the
    Purchase Agreement permit the Stone & Webster entities to
    amend and add schedules, see App. at A133 & A158, and
    § 7.01(a) explains that any added schedule is “deemed to have
    been made and delivered as of the Effective Date [of the
    Purchase Agreement].” Id. at A163.
    SAMBA also argues that we should not consider the
    relevance of Schedule 2.02(e) because (1) paragraph 31 of the
    Sale Order provides that the Purchase Agreement “could not be
    modified without an order of the Court, unless the modification
    would not have a material adverse effect on Debtors’ estates,”
    and (2) Shaw’s counsel stated at the sale hearing in July 2000
    that “the contracts that are in [the Purchase Agreement] are now
    fixed.” SAMBA’s Br. at 55. We reject both arguments.
    First, the sections of the Purchase Agreement permitting
    amendment of schedules were not modified or added to the
    Agreement after the issuance of the Sale Order. Also, as noted
    by SAMBA’s counsel at oral argument, it is “uncontested” that
    Stone & Webster was the party that filed Schedule 2.02(e). Or.
    Arg. Tr. at 21. Adding the schedule was thus sanctioned by the
    23
    The conclusion that the Guaranty and Payment Letter are
    Excluded Liabilities by way of association with an excluded
    Special Project Claim is further supported by SW Engineering’s
    stated Answer, Affirmative Defenses, and Counterclaims to
    SAMBA’s initial complaint. Denying that the Guaranty and
    Payment letter were assumed by Shaw, SW Engineering
    asserted:
    Both the [Payment] Letter and the 1994
    Guarantee are Special Project Claims (as defined
    in section 1.01 and on schedule 2.02(e) of the
    [Purchase Agreement]), defined as “[a]ny and all
    claims or liabilities available at law or in equity,
    or arising under the project agreements in Saudi
    Arabia for the Ras Tanura Refinery Upgrade
    Project (“RTRUP”)—Package 2—Utilities . . . .”
    District Court and was not materially adverse to Stone &
    Webster’s interests.
    Second, counsel’s remark about the contracts being
    “fixed” says nothing about the parties’ ability to add contracts
    or adjust the schedules.        In fact, counsel’s statements
    immediately following the “fixed” remark focus on “preserving
    the right for [Stone & Webster] to say . . . [a contract]’s in, and
    Shaw to say . . . it’s out,” and discuss the parties’ belief that
    further negotiations would be necessary to clarify “material
    misunderstandings about what the effect of this contract on the
    estate is.” App. at A736–43.
    24
    [Purchase Agreement] at schedule 2.02(e). . . .
    Under the specific terms of the [Purchase
    Agreement], the Special Project Claims are
    Excluded Assets (as defined therein) and were not
    assumed by the Shaw Parties . . . . Additionally,
    any liabilities or obligations associated with any
    Excluded Assets (including the Special Project
    Claims) are Excluded Liabilities (as defined in the
    [Purchase Agreement]) and were not assumed by
    the Shaw Parties.
    SW Engineering’s Answer, Affirmative Defenses, and
    Counterclaims, Saudi American Bank v. Shaw Group, Inc. (In re
    Stone & Webster, Inc.), Ch. 11 Case No. 00-02142, Adv. No.
    01-07766, at 10–11 (Bankr. D. Del. Oct. 29, 2001) (emphasis
    added). Rarely is such a clear statement offered by a debtor
    against its interests. By refusing to claim that Shaw was
    obligated to pay the balance of SAMBA’s loan, SW Engineering
    eliminated its surest avenue to avoiding liability for the debt and
    reinforced the status of the Guaranty and Payment Letter as
    Excluded Liabilities.
    In concluding that Shaw did not assume liability for SW
    Engineering’s guaranty of the in-kingdom project loan, we
    additionally reject SAMBA’s assertions that the Guaranty and
    Payment Letter are Assumed Liabilities or Assumed Contracts.
    These assertions rely on unreasonable interpretations that do not
    overcome the unambiguous language of the Purchase
    25
    Agreement and Sale Order.
    To begin, SAMBA’s attempt to label the Guaranty and
    Payment Letter as Assumed Liabilities under Schedules 2.03
    and 3.17(a)(ix) is misleading. Schedule 2.03 states that
    Assumed Liabilities include “[l]iabilities under [the Stone &
    Webster entities’] outstanding bank indebtedness” and “other
    liabilities related to the . . . Assumed Contracts.” App. at A199.
    Schedule 3.17(a)(ix) lists all of the Stone & Webster entities’
    indebtedness “relating to the borrowing of money or indirect
    guarantee[s].” Id. at A139. Included within Schedule
    3.17(a)(ix) is a listing for a letter of guaranty dated September
    1, 1992 from SW Engineering to SAMBA for $5,000,000, and
    a letter of guaranty dated October 19, 1992 from SW
    Engineering to SAMBA for repayment of 40,000,000 Saudi
    Riyals. Id. at A282–83.
    Reading these schedules somehow to include the
    Guaranty, SAMBA asserts that they provide “undisputed
    evidence . . . that [SW Engineering]’s obligation to SAMBA
    constitutes [an Assumed Liability] under [SW Engineering]’s
    outstanding bank indebtedness.” SAMBA’s Br. at 21. This
    overstatement underwhelms, as neither of the guaranties
    referenced in Schedule 3.17(a)(ix) is related to the Guaranty,
    which was issued October 11, 1994, for $35,000,000—not
    September 1992 for $5,000,000 or October 1992 for 40,000,000
    Saudi Riyals (as noted, the dates and amounts of the guaranties
    listed in Schedule 3.17(a)(ix)). See App. at A73–76, A92–93.
    26
    SAMBA claims that this discrepancy is unimportant
    because “Shaw has admitted that it assumes that the guaranty
    listed on Schedule 3.17(a)(ix) incorporates the Guaranty.”
    SAMBA’s Br. at 22. This statement misrepresents Shaw’s
    actual response that it “currently assumes that this is the same
    guaranty (and it knows of no other), but there appears to be no
    direct way to confirm (or deny) this point.” App. at A496.12
    SAMBA is also incorrect in labeling the Guaranty and
    Payment Letter as Assumed Contracts.           The Purchase
    Agreement defines “Assumed Contracts” as “all Contracts of
    Sellers (including the Employee Agreements) other than the
    Rejected Contracts and the Completed Contracts.” Id. at A114.
    SAMBA claims that the Guaranty and Payment Letter fall
    within this definition because they are “Contracts” under the
    12
    Even if the Guaranty and Payment Letter were included
    within the guaranties listed in Schedule 3.17(a)(ix), their
    placement there would not be conclusive of their assumed
    status. The Purchase Agreement anticipates in Sections 1.01
    and 3.17 that there are liabilities and obligations listed in
    Schedule 3.17(a)(ix) that are elsewhere excluded through
    specific mention or association with an Excluded Asset. There
    is no reason why the Guaranty and Payment Letter at issue here
    would not be such liabilities if, in fact, they were listed in
    Schedule 3.17(a)(ix).
    27
    Purchase Agreement,13 and they are not specifically listed in the
    schedules of Rejected or Completed Contracts.14 We dismiss
    this claim as an illogical interpretation of the Purchase
    Agreement and Sale Order.
    “It is a general rule of contract construction to ‘consider
    the entire instrument and attempt to reconcile all of its
    provisions in order to determine the meaning intended to be
    given to any portion of it.’” In re IAC/Interactive Corp., 
    948 A.2d 471
    , 497 (Del. Ch. 2008) (quoting Wood v. Coastal States
    Gas Corp., 
    401 A.2d 932
    , 937 (Del. 1979)). “Moreover, the
    meaning which arises from a particular portion of an agreement
    cannot control the meaning of the entire agreement where such
    inference runs counter to the agreement’s overall scheme or
    13
    As defined in § 1.01 of the Purchase Agreement,
    “Contracts” are “all commitments, contracts, leases, licenses,
    agreements and understandings, written or oral, relating to the
    Assets or the operation of the Business to which any [Stone &
    Webster entity] is a party or by which it or any of its Assets are
    bound.” Id. at A117.
    14
    In its brief, SAMBA also cites page A882 of the Appendix
    to support an assertion that the “Guaranty and Payment Letter
    were listed on the Second Amended Assumed Contract List.”
    SAMBA’s Br. at 23. Page A882 is merely a title page for the
    Amended Assumed Contracts Lists, and a search of the
    preceding and following pages reveals no specific mention of
    the Guaranty or Payment Letter.
    28
    plan.” E.I. du Pont Nemours & Co., Inc. v. Shell Oil Co., 
    498 A.2d 1108
    , 1113 (Del. 1985).
    The overall scheme of the Purchase Agreement and Sale
    Order, as noted above, is for Shaw to assume all assets and
    obligations of the Stone & Webster entities except for those
    listed as Excluded Assets or Excluded Liabilities. SAMBA’s
    labeling of the Guaranty and Payment Letter as “Assumed
    Contracts” turns that scheme on its head by making Shaw liable
    for what are Excluded Liabilities via their association with an
    excluded Special Project Claim (the in-kingdom project).15
    15
    At oral argument, SAMBA asserted that paragraphs 12
    and 22 of the Sale Order reversed the Purchase Agreement’s
    general rule that Excluded Liabilities cannot create liabilities
    assumed by Shaw. See Or. Arg. Tr. at 22-28, 36, 39-43. This
    claim is waived because SAMBA raised it for the first time at
    oral argument. See Montrose Med. Group Participating Sav.
    Plan v. Bulger, 
    243 F.3d 773
    , 783 (3d Cir. 2001).
    Even were the claim not waived, it misses on the merits.
    Paragraph 12 of the Sale Order states, in part, that “Shaw is
    assuming all liabilities arising under the Assumed Contracts.”
    App. at A437. Paragraph 22 reads: “Under no circumstances
    shall any holder of an Excluded Liability be able to commence,
    continue or otherwise pursue or enforce any remedy, claim or
    cause of action against Shaw . . . except with respect to the
    liabilities assumed under an Assumed Contract by Shaw
    pursuant to paragraph 12 of this Sale Order.” 
    Id.
     at A442.
    Contrary to SAMBA’s claim, these provisions—like similar
    29
    Furthermore, were we to extend SAMBA’s logic to other
    Excluded Assets and Excluded Liabilities, we would in effect be
    reading entire sections and schedules out of the Purchase
    Agreement. All items only listed as, or associated with, Special
    Project Claims, for example, would no longer be distinctly
    excluded because they too would be “Contracts . . . other than
    the Rejected Contracts and the Completed Contracts.” App. at
    A114 (defining “Assumed Contracts”). To adopt such a far-
    reaching interpretation would violate “the cardinal rule of
    contract construction that, where possible, a court should give
    effect to all contract provisions.” E.I. du Pont, 
    498 A.2d at 1114
    ; see also New Castle County, Del. v. Nat’l Union Fire Ins.
    Co. of Pittsburgh, 
    174 F.3d 338
    , 350 (3d Cir. 1999).
    Lastly, we disagree with SAMBA’s assertion that the
    transcripts of the sale hearings show that the Guaranty and
    Payment Letter are Assumed Liabilities or Assumed Contracts
    clauses in paragraphs 7, 10, 17, 21, and 25 of the Sale
    Order—merely preserve the ability of non-debtor parties to
    assert their rights under an Assumed Contract. Paragraph 9 of
    the Sale Order confirms that paragraphs 12 and 22 do not alter
    the Purchase Agreement’s distinction between Excluded
    Liabilities and liabilities under Assumed Contracts, stating
    “[SW Engineering]’s assumption and assignment to Shaw, and
    Shaw’s assumption on the terms set forth in the [Purchase]
    Agreement, of the Assumed Contracts [are] hereby approved
    . . . .” 
    Id.
     at A435 (emphasis added).
    30
    because they were not identified as Rejected or Completed
    Contracts before entry of the Sale Order. SAMBA assigns
    particular significance to the representations made by counsel
    for the Committee of Unsecured Creditors at the sale hearing in
    July 2000 that
    [t]his agreement revolves, in terms of its
    economics, around three schedules, or let’s say
    two schedules, and whether or not your contract is
    on one of those two schedules. And those two
    schedules are the schedule for rejected contracts
    and the schedule for completed contracts. If they
    are not on those schedules, in essence, your
    contract is an assumed contract, and the economic
    impact to you as a stakeholder is dependent upon
    whether you are on those two lists . . . .
    Saudi American Bank I, 
    2005 WL 1036556
    , at *2.
    We do not see how this statement establishes with
    certainty that the Guaranty and Payment Letter are Assumed
    Contracts or Assumed Liabilities. The statement oversimplifies
    the terms of the Purchase Agreement, does not discuss the
    relevance of the “liabilities and obligations” associated with
    Excluded Assets, and fails to mention the importance of the
    Special Project Claims. Other statements from the sale hearing
    transcript, moreover, show that the District Court did not think
    that the provisions of the Purchase Agreement were settled when
    31
    it issued the Sale Order. See, e.g., App. at A788 (“I will allow
    [the parties to adjust the schedules after approval of the
    Purchase Agreement], with the understanding that we may end
    up having to deal with adjustments and the economic impact of
    adjustments.”); A798 (“I would rather leave Shaw and the
    debtor as much flexibility as they can to try and make
    adjustments, because I understand it is going to be
    complicated.”).
    The record is clear: the Guaranty and Payment Letter are
    Excluded Liabilities because they are associated with the in-
    kingdom project, which is an excluded Special Project Claim.
    We therefore reverse the District Court’s grant of summary
    judgment.16
    16
    Because we hold that the Guaranty was not assumed by
    Shaw, SAMBA’s claim for repayment should now be treated as
    a Proof of Claim against SW Engineering, as expressly reserved
    in SAMBA’s Statement of Cure Claim. See App. at A458 (“In
    the event it is determined that the Guaranty is not a contract
    assumed by Shaw, . . . [SAMBA] hereby claims the right to have
    such portion of its claim treated as a Proof of Claim, rather than
    a Statement of Cure Claim.”). SAMBA’s ability to recover
    payment under a Proof of Claim, however, is limited by the
    terms of its May 2003 Settlement Agreement with SW
    Engineering and the other Stone & Webster entities. See
    Stipulation and Agreed Order Dismissing Adversary
    Proceeding, Appendix at A500–10, Saudi American Bank v.
    Saudi Arabian Oil Co. (In re Stone & Webster, Inc.), No. 07-
    32
    3891 (3d Cir. pending). That Agreement resolved all disputes
    related to a preference action filed by SW Engineering against
    SAMBA and SAMBA’s claims under the Guaranty and
    Payment Letter. The specific terms of the Agreement state:
    WHEREAS the Parties have agreed to
    settle the disputes involved in the Preference
    Action and SAMBA’s contingent claims against
    [SW Engineering] as set forth herein;
    NOW, THEREFORE, . . . the Parties agree
    as follows:
    1.      [SW Engineering] shall make a one-time
    cash payment of One Million Dollars
    ($1,000,000) to SAMBA . . . .
    2.      SAMBA will have an allowed general,
    unsecured claim in the amount of Two
    M illion Five H undred Thousa nd
    ($2,500,000) against [SW Engineering].
    ....
    5.      Except for the rights and obligations
    e x p r e s s l y p r o v i d e d o r re s e r v e d
    hereunder[,] SAMBA . . . hereby releases,
    remises and forever discharges the [Stone
    & Webster entities] . . . from any and all
    claims and causes of action . . . that
    SAMBA ever had, now has or may have,
    for acts, events or occurrences . . . based
    upon the Proof of Claim, the Cure Claim,
    the Payment Letter, or the Guarantee, or
    33
    C.     Interest, Attorneys’ Fees and Other Litigation
    Costs
    Because we reverse the District Court’s grant of summary
    judgment, we must also vacate its subsequent awards to
    SAMBA, and against Shaw, of pre- and post-judgment interest,
    attorneys’ fees and other litigation costs. We nonetheless agree
    with the Court’s analysis of these issues had they applied to SW
    Engineering.
    With respect to the award of pre-judgment interest, we
    specifically agree with the District Court’s reliance on the
    Guaranty’s choice of New York law and its assignment of a 9%
    interest rate running from May 31, 2000.17 We likewise concur
    that were or could have been asserted by
    SAMBA in the Proof of Claim or the Cure
    Claim.
    
    Id.
     at A506–07; see also Saudi American Bank III, 360 B.R. at
    66 (discussing the Settlement Agreement).      Accordingly,
    SAMBA may recover no more than $2.5 million from SW
    Engineering through a Proof of Claim.
    17
    Despite the Guaranty’s statement that it “shall be governed
    by the laws of the State of New York,” SAMBA sought
    application of Delaware’s legal interest rate of 11%. See Saudi
    American Bank II, 
    354 B.R. at
    689–91. Shaw argued in
    response that SAMBA was not entitled to receive interest on the
    34
    in the Court’s application of 
    28 U.S.C. § 1961
     to establish a
    3.33% post-judgment interest rate. See Saudi American Bank II,
    
    354 B.R. at 693
    .18
    sum because the joint venture’s “obligation to SAMBA
    ultimately arose under and is determined by the Credit
    Agreement, and . . . Payment Letter,” which are controlled by
    Saudi law that forbids the collection of interest. 
    Id. at 690
    . The
    District Court concluded that the terms of the Guaranty
    controlled in all respects, granting SAMBA pre-judgment
    interest at New York’s interest rate of 9%. See 
    id.
     at 690–91;
    
    N.Y. C.P.L.R. §§ 5001
    (a) & 5004. The Court distinguished the
    Guaranty from the Credit Agreement by reiterating that a
    guaranty “is a separate contract involving duties and
    responsibilities which are different from the basic contract to
    which it is collateral.” Saudi American Bank II, 
    354 B.R. at 690
    (quoting FinanceAmerica, 
    380 A.2d at 1379
    ). It applied New
    York’s interest rate because it determined that Delaware, whose
    law would control in the absence of the parties’ choice of law,
    did not have a “materially greater” interest in the subject matter
    than New York. Id. at 691 (quoting Hionis Int’l Enters., Inc. v.
    Tandy Corp., 
    867 F.Supp. 268
    , 271 (D. Del. 1994)).
    18
    
    28 U.S.C. § 1961
    (a) states in part: “Interest shall be
    allowed on any money judgment in a civil case recovered in a
    district court. . . . Such interest shall be calculated from the date
    of the entry of the judgment, at a rate equal to the weekly
    average 1-year constant maturity Treasury yield . . . for the
    calendar week preceding the date of the judgment.”
    35
    Regarding litigation expenses, we approve the Court’s
    determination that the Guaranty’s promise of reimbursement for
    “any and all expenses incurred [by SAMBA] in enforcing [its]
    rights under this Guaranty” entitles SAMBA to reasonable
    attorneys’ fees and other costs of litigation. Saudi American
    Bank II, 
    354 B.R. at
    691–3. Any reward recovered under the
    language of the Guaranty, however, must be limited to the fees
    and costs directly incurred in enforcing rights against SW
    Engineering under that instrument. See 
    id. at 692
    .
    IV.    Conclusion
    We affirm the conclusion of the District Court that
    SAMBA has standing to challenge the status of its claim under
    the Purchase Agreement. We reverse the Court’s grant of
    summary judgment to SAMBA, and we vacate its orders
    requiring Shaw to pay pre- and post-judgment interest,
    attorneys’ fees and other litigation costs. We further remand the
    matter to the District Court for proceedings consistent with this
    opinion.
    36
    

Document Info

Docket Number: 05-2717

Filed Date: 2/24/2009

Precedential Status: Precedential

Modified Date: 10/14/2015

Authorities (19)

In Re Teleglobe Communications Corp. , 493 F.3d 345 ( 2007 )

ei-dupont-de-nemours-and-company-a-delaware-corporation-v-rhone-poulenc , 269 F.3d 187 ( 2001 )

Union Pacific Railroad Company v. Greentree Transportation ... , 293 F.3d 120 ( 2002 )

montrose-medical-group-participating-savings-plan-montrose-general , 243 F.3d 773 ( 2001 )

Mbia Insurance Corporation Wells Fargo Bank Minnesota, N.A.,... , 426 F.3d 204 ( 2005 )

Eve Atkinson v. Lafayette College Arthur J. Rothkopf, ... , 460 F.3d 447 ( 2006 )

Eagle Industries, Inc. v. DeVilbiss Health Care, Inc. , 702 A.2d 1228 ( 1997 )

George Jumara and Evangelina Jumara, H/w v. State Farm ... , 55 F.3d 873 ( 1995 )

paul-bechtel-wanda-elaine-greene-co-executors-of-estate-of-edward-g , 886 F.2d 644 ( 1989 )

Richard Conoshenti v. Public Service Electric & Gas Company , 364 F.3d 135 ( 2004 )

New Castle County, Delaware v. National Union Fire ... , 174 F.3d 338 ( 1999 )

Pension Benefit Guaranty Corporation v. White Consolidated ... , 215 F.3d 407 ( 2000 )

Hionis International Enterprises, Inc. v. Tandy Corp. , 867 F. Supp. 268 ( 1994 )

Saudi American Bank v. Shaw Group, Inc. (In Re Stone & ... , 354 B.R. 686 ( 2006 )

In Re IAC/InterActive Corp. , 948 A.2d 471 ( 2008 )

FinanceAmerica Private Brands, Inc. v. Harvey E. Hall, Inc. , 380 A.2d 1377 ( 1977 )

Wood v. Coastal States Gas Corp. , 401 A.2d 932 ( 1979 )

E.I. Du Pont De Nemours & Co. v. Shell Oil Co. , 498 A.2d 1108 ( 1985 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

View All Authorities »