Sanford Inv. Co. Inc. v. Ahlstrom Machinery ( 1999 )


Menu:
  •                                                                                                                            Opinions of the United
    1999 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    12-10-1999
    Sanford Inv. Co. Inc. v. Ahlstrom Machinery
    Precedential or Non-Precedential:
    Docket 98-2036
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_1999
    Recommended Citation
    "Sanford Inv. Co. Inc. v. Ahlstrom Machinery" (1999). 1999 Decisions. Paper 321.
    http://digitalcommons.law.villanova.edu/thirdcircuit_1999/321
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 1999 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    Filed December 10, 1999
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    No. 98-2036
    SANFORD INVESTMENT COMPANY, INC.,
    Appellant
    v.
    AHLSTROM MACHINERY HOLDINGS, INC.
    On Appeal from the United States District Court
    for the Eastern District of Pennsylvania
    (D.C. Civ. No. 97-07978)
    District Judge: Honorable Edmund V. Ludwig
    Argued November 5, 1999
    BEFORE: BECKER, Chief Judge, and GREENBERG
    and CUDAHY,* Circuit Judges
    (Filed: December 10, 1999)
    Peter F. Marvin (argued)
    Justin K. Miller
    Toll, Ebby, Langer & Marvin
    Two Logan Square
    18th Floor
    Philadelphia, Pa. 19103
    Attorneys for Appellant
    _________________________________________________________________
    * Honorable Richard D. Cudahy, Senior Judge of the United States Court
    of Appeals for the Seventh Circuit, sitting by designation.
    Jeffrey G. Weil (argued)
    Michael S. Doluisio
    Dechert, Price & Rhoads
    1717 Arch Street
    4000 Bell Atlantic Tower
    Philadelphia, Pa. 19103
    Attorney for Appellee
    OPINION OF THE COURT
    GREENBERG, Circuit Judge.
    I. INTRODUCTION
    This matter is before this court on an appeal from an
    order for summary judgment in this diversity of citizenship
    commercial litigation dispute. The litigation stems from a
    series of business relationships formed to finance,
    construct and operate a waste paper recycling facility in
    Sanford, West Virginia (the "Project"). The owner/developer
    of the project was American Power Recyclers, L.P., later
    known as American Fiber Resources, Limited Partnership
    (the "Partnership"). The Partnership included two general
    partners and two limited partners. The general partners
    were American Power Corporation ("APC"), the predecessor-
    in-interest to the plaintiff, Sanford Investment Company,
    Inc., and Adirondack G.P. Inc. ("AGP"). AGP is related to
    Ahlstrom Kamyr, Inc., the predecessor-in-interest to
    defendant Ahlstrom Machinery Holdings, Inc. We refer to
    the Ahlstrom entitites simply as "Ahlstrom" although the
    contracting party was Ahlstrom Kamyr, Inc. and the party
    to the litigation is Ahlstrom Machinery Holdings, Inc. The
    limited partners were Adirondack Recycle, L.P. ("ARLP"), a
    company related to Ahlstrom, and American Power
    Investors ("API"), a company related to APC. We will refer to
    the appellant Sanford and its predecessor-in-interest APC
    as "American" but it should not be confused with American
    Fiber Resources, i.e., the Partnership.
    On November 2, 1993, the Partnership entered into a
    contract with Ahlstrom referred to as the "EPC/Initial
    2
    Operation and Performance Testing Agreement" ("EPC
    contract"). The EPC contract provided that Ahlstrom would
    develop, construct and initially operate the Project. In
    return, the Partnership agreed to pay Ahlstrom an amount
    designated as the "Base Fee" during the initial operation of
    the Project. A different paragraph of the EPC contract
    provided that the Partnership would pay Ahlstrom a"Bonus
    Fee" under certain conditions. The Base Fee and the Bonus
    Fee were distinct payments under the EPC contract
    calculated in different ways. Moreover, the Bonus Fee,
    unlike the Base Fee, was conditional. The EPC contract
    provided the circumstances in which Ahlstrom was to
    receive the Base Fee, which is at issue in this lawsuit.
    After the execution of the EPC contract, Ahlstrom and
    American negotiated a division of the Base Fee that they
    memorialized in a Letter Agreement dated December 29,
    1993 (the "1993 Letter Agreement"). The 1993 Letter
    Agreement provides that
    25% of the base fee payable to [Ahlstrom] under Phase
    II of the EPC/Initial Operation and Performance
    Testing Agreement shall be payable by [Ahlstrom] to
    [American].
    American predicates this action on Ahlstrom's purported
    obligation to remit this 25% payment as set forth in the
    1993 Letter Agreement. American contends that Ahlstrom
    breached the contract as of January 31, 1996, by failing to
    remit payments of that portion of the Base Fee due under
    the 1993 Letter Agreement.
    The background surrounding this breach of contract case
    was complicated by three agreements entered into following
    the execution of the foregoing basic agreements. In 1995,
    the Partnership sought additional funding from the County
    Commission of Marion County, West Virginia ("Marion
    County"). Marion County contemplated obtaining the
    additional funding through the issuance of tax-free
    industrial development bonds.
    A problem with the funding arose, however, because
    American was in default of its obligation under a Cash
    Shortfall Funding Agreement (the "CSF Agreement") dated
    February 13, 1995. Apparently, Marion County would not
    3
    approve the additional funding unless American satisfied its
    obligations under the CSF Agreement.
    To cure its default under the CSF Agreement and clear
    the way for the additional funding, American sought a loan
    from one of its affiliates, the Conduit and Foundation
    Corporation ("Conduit" or "C&F "). It was contemplated that
    the loan would be funded by monies due and owing to
    Conduit from Kamtech, Inc. ("Kamtech"), an affiliate of
    Ahlstrom that Ahlstrom hired to construct the Project.
    The plan called for Conduit to loan American the funds
    owed to it by Kamtech so that American could meet its
    obligation under the CSF Agreement and thus permit the
    Partnership to receive additional funds from Marion
    County. In order for Conduit to loan the funds due from
    Kamtech to American the approval of Conduit's surety,
    National Union Fire Insurance Company of Pittsburgh,
    Pennsylvania, was required.
    The arrangements among the parties arising from these
    circumstances were evidenced in three documents executed
    in December 1995. The parties refer to the first document
    as the "Bonus Fee Agreement" and the second document
    which accompanied the first as the "Bonus Fee
    Assignment." The final agreement was the "Surety Loan
    Agreement." The Bonus Fee Agreement and Bonus Fee
    Assignment were executed on December 20, 1995, and the
    Surety Loan Agreement was executed on December 26,
    1995. The parties to this litigation dispute the legal effect of
    these agreements, in particular language found in the
    Surety Loan Agreement. Because the terms of the three
    contracts are central to the outcome of the appeal, we set
    forth their relevant provisions in some detail.
    Each member of the Partnership signed the Bonus Fee
    Agreement: (1) AGP (Ahlstrom's affiliate); (2) American; (3)
    ARLP (Ahlstrom's affiliate); and (4) API (American's affiliate).
    Among other things, the Bonus Fee Agreement provided for
    an "assignment" of 24% of the Bonus Fee due to Ahlstrom
    under the EPC contract to American or its affiliate.
    Paragraph 4 states in pertinent part:
    Assignment of 24% of the Bonus Fee to APC. AGP shall
    cause its Affiliate, [Ahlstrom], to deliver to [American]
    4
    or its designee upon the closing of the Bond Offering
    an Assignment . . . through which [Ahlstrom] assigns,
    sells and transfers to [American] or its designee, the
    right to receive twenty-four percent (24%) of
    [Ahlstrom's] Bonus Fee under paragraph 13.3 of the
    EPC Contract, as amended (the `Bonus Fee'), when
    earned. . . . AGP acknowledges that APC has
    designated The Conduit and Foundation Corporation
    (`C&F ') [an affiliate of American] as its designee under
    this paragraph 4.
    . . . .
    [O]nce the amount of the Bonus Fee has been finally
    determined in accordance with the EPC Contract,
    [American] shall have the right thereafter to assert a
    claim for its 24% of such Bonus Fee directly against
    [the Partnership and original signatory to the EPC
    Contract] and the payment of such amount to C&F or
    National Union (as defined below) shall not be subject
    to offset against the obligations of [American]. Nothing
    in this Agreement is intended to, nor shall, give
    [American] or its designee or any of their Affiliates any
    additional rights or obligations under the EPC
    Contract, including, but not limited to, any rights as a
    third party beneficiary to the EPC Contract, except as
    they may currently possess as a General or Limited
    Partner and except for the right to enforce payment of
    the 24% of the Bonus Fee assigned to [American] as
    hereinabove provided.
    App. at 112-13 (second emphasis added). With respect to
    National Union's rights under the Bonus Fee Agreement,
    section 8(k) provides:
    Limitation on Rights of Others. No person or entity other
    that the parties hereto shall have any legal or equitable
    right or interest, remedy or claim under or in respect of
    this Agreement; provided, however, that it is
    acknowledged that C&F and its surety, National Union
    . . . are creditor and/or donee third party beneficiaries
    in respect of the rights of [American] to receive the 24%
    of the Bonus Fee assigned to it pursuant to paragraph
    4 hereof and to enforce the payment of said amount
    against [the Partnership] as hereinabove provided.
    5
    App. at 115.
    The second agreement, the Bonus Fee Assignment, was
    executed by Ahlstrom as assignor and Conduit as assignee
    and designee of American in the form that accompanied the
    Bonus Fee Agreement. The Bonus Fee Assignment
    effectuates the assignment of Ahlstrom's interest in 24% of
    the Bonus Fee provided under the EPC contract to Conduit
    as American's designee. The Assignment provides in
    relevant part:
    1. Assignor [Ahlstrom] hereby assigns, sells and
    transfers to Assignee [Conduit], and Assignee hereby
    accepts the assignment of, the right to receive . . .
    twenty-four percent (24%) of Assignor's Bonus Fee
    under . . . the EPC Contract, . . . when earned.
    App. at 120. The provisions in the Bonus Fee Assignment
    that follow the foregoing quoted language reiterate again
    American's right (as Conduit's affiliate) to assert a claim
    against the Partnership to collect its portion of the Bonus
    Fee provided in the EPC Contract assigned to it under this
    assignment. The next paragraph then provides the
    following:
    4. Assignee [Conduit] hereby irrevocably dir ects that
    any amounts otherwise payable to it with respect to the
    24% of the Bonus Fee assigned to it hereby shall be
    paid directly to [National Union], and Assignor
    [Ahlstrom] hereby agrees to so pay any such amounts
    that it shall receive from AFR. . . . It is acknowledged
    that [National Union] is a creditor and/or donee third
    party beneficiary in respect of the right to receive and
    enforce payment of the 24% Bonus Fee assigned to
    Assignee as provided herein.
    App. at 115 (emphasis added). Thus, under the Bonus Fee
    Agreement and Assignment, Ahlstrom assigned its right to
    receive 24% of the Bonus Fee to Conduit, which was the
    designee of American (as set forth in the Bonus Fee
    Agreement). By the assignment, Conduit, as assignee,
    received the right to enforce payment of 24% of the Bonus
    Fee from the Partnership, and National Union was deemed
    the third-party beneficiary of the assignment. Moreover,
    6
    Ahlstrom was to pay Conduit's portion of the Bonus Fee by
    sending it directly to National Union.
    As we have indicated, the third and final agreement
    evidencing the parties' arrangement is the Surety Loan
    Agreement, which the following parties executed: (1)
    American; (2) API (American's affiliate); (3) Conduit
    (American's affiliate); (4) Richard Halloran (Conduit's
    indemnitor under prior March 1995 Surety Agreement); and
    (5) National Union (the Surety). In the Surety Loan
    Agreement, National Union agreed to defer receipt of funds
    Conduit owed to it, and permitted the funds to be used by
    American to satisfy its obligations under the CSF. In
    return, American and its affiliates agreed to the following
    provision:
    4. In further consideration of the Surety's consen t to
    the deferral by Conduit of the receipt of the Loaned
    Funds [i.e., the monies due from Kamtech],[American
    and its affiliates]:
    A. hereby transfer, assign, convey, gr ant a security
    interest in, pledge and mortgage to [National Union] all
    income, dividends, distributions, loan repayments,
    proceeds . . . related in any way to the Project, or any
    other payments of any kind payable to [American or its
    affiliates] or any of their designees from[the
    Partnership], [Ahlstrom], AGP, ARLP, Kamtech or any
    of their designees . . . (including but not limited to the
    Bonus Fees . . .) coupled with the rights to enforce the
    payments of same . . . as further collateral security and
    as a source for the repayment of all indebtedness of
    [the signatories] under the Contractor/Surety
    Agreement and this Surety Loan Agreement.
    App. at 85 (emphasis added). Unlike the Bonus Fee
    Agreement and Bonus Fee Assignment, Ahlstrom was not a
    signatory to the Surety Loan Agreement. To implement the
    Surety Loan Agreement, American sent Ahlstrom a letter
    dated March 27, 1996, directing that all payments related
    to the recycling facility be paid directly to National Union.
    II. PROCEDURAL HISTORY
    Notwithstanding its assignment to National Union,
    American filed this action in December 1997, to recover
    7
    from Ahlstrom $324,470, together with interest, an amount
    allegedly representing that portion of the Base Fee, i.e.,
    25% owed to it under the 1993 Letter Agreement. According
    to the complaint, American had received payments under
    the 1993 Letter Agreement through January 31, 1996, but
    not thereafter. Ahlstrom filed a motion for summary
    judgment on July 8, 1998, contending that American did
    not have standing to sue Ahlstrom for its percentage of the
    Base Fee due under the 1993 Letter Agreement because it
    had assigned its right to enforce that agreement to National
    Union in the Surety Loan Agreement.
    The district court heard oral argument on the matter on
    October 8, 1998, and on October 16, 1998, entered an
    order granting Ahlstrom's motion. Then on October 29,
    1998, the court entered a memorandum in support of its
    order.
    The district court determined that American lacked
    standing to sue Ahlstrom for the Base Fee payments under
    the 1993 Letter Agreement because of its complete
    assignment of that right to National Union pursuant to the
    Surety Loan Agreement. Under Pennsylvania law, which the
    parties treat as applicable, a contracting party that has
    assigned its contract rights to a third party does not have
    standing to enforce that contract. See West Penn Admin.,
    Inc. v. Pittsburgh Nat'l Bank, 
    433 A.2d 896
    , 902 (Pa. Super.
    Ct. 1981). While the district court accepted American's
    argument that the Surety Loan Agreement should be read
    together with the Bonus Fee Agreement and Bonus Fee
    Assignment because the three agreements were part of a
    larger transaction, the court nonetheless determined that
    nothing in the prior agreements rendered ambiguous the
    unequivocal language of the assignment in the Surety Loan
    Agreement.
    American appeals from the district court's order granting
    Ahlstrom's motion. We have jurisdiction under 28 U.S.C.
    S 1291 and exercise plenary review. See Nelson v. Upsala
    College, 
    51 F.3d 383
    , 385 (3d Cir. 1995); Allegheny Int'l,
    Inc. v. Allegheny Ludlum Steel Corp., 
    40 F.3d 1416
    , 1423
    (3d Cir. 1994).
    8
    III. DISCUSSION
    American contends that the district court's interpretation
    of the Bonus Fee Agreement, Bonus Fee Assignment, and
    Surety Loan Agreement was erroneous. It maintains that it
    has offered an interpretation of the Surety Loan Agreement
    which is reasonable given the language used and the
    circumstances surrounding the series of transactions.
    Accordingly, it contends that summary judgment was
    inappropriate because the relevant provision in the Surety
    Loan Agreement was ambiguous. American further
    contends that the district court erred in not construing the
    three contracts together, by not considering the commercial
    context in which the agreements were executed, and by not
    addressing Ahlstrom's subsequent performance under the
    1993 Letter Agreement even though its conduct was
    consistent with American's construction of the agreements.
    This reference to subsequent performance related to
    Ahlstrom's payment in January 1996, after the execution of
    the Surety Loan Agreement, of a portion of the Base Fee
    directly to American. Finally, citing Fed. R. Civ. P. 17,
    American contends that the district court failed to weigh
    the fact that American was the real party in interest to the
    Surety Loan Agreement.
    "To affirm a grant of summary judgment on an issue of
    contract interpretation, we must conclude that the
    contractual language is subject to only one reasonable
    interpretation." Arnold M. Diamond, Inc. v. Gulf Coast
    Trailing Co., 
    180 F.3d 518
    , 521 (3d Cir. 1999). Thus, the
    overarching question on appeal is whether American has
    provided a reasonable alternative reading of the assignment
    clause in the Surety Loan Agreement under which Ahlstrom
    would not be entitled to judgment as a matter of law.
    A court's purpose in examining a contract is to interpret
    the intent of the contracting parties, as they objectively
    manifest it. See Duquesne Light Co. v. Westinghouse Elec.
    Corp., 
    66 F.3d 604
    , 613 (3d Cir. 1995); Mellon Bank, N.A.
    v. Aetna Business Credit, Inc., 
    619 F.2d 1001
    , 1009 (3d Cir.
    1980). The process of interpreting a contract proceeds in
    two steps. First, the court must make a preliminary inquiry
    as to whether the contract before it is ambiguous. See
    Duquesne, 66 F.3d at 613; Allegheny, 40 F.3d at 1424. This
    9
    question is an issue of law for the court to resolve. A term
    is ambiguous if it is susceptible to reasonable alternative
    interpretations. See Duquesne, 66 F.3d at 614; Mellon
    Bank, 619 F.2d at 1011 (defining ambiguity as an
    "[i]ntellectual uncertainty [or] the condition of admitting two
    or more meanings, of being understood in more than one
    way, or referring to two or more things at the same time
    . . . ."). If the court determines that a given term in a
    contract is ambiguous, then the interpretation of that term
    is a question of fact for the trier of fact to resolve in light
    of the extrinsic evidence offered by the parties in support of
    their respective interpretations. See Hullett v. Towers,
    Perrin, Forster & Crosby, Inc., 
    38 F.3d 107
    , 111 (3d Cir.
    1994).
    "In determining whether a contract is ambiguous, the
    court assumes the intent of the parties to an instrument is
    embodied in the writing itself, and when the words are clear
    and unambiguous the intent is to be discovered only from
    the express language of the agreement." Pacitti v. Macy's,
    
    193 F.3d 766
    , 773 (3d Cir. 1999) (citing and quoting
    Hullett, 38 F.3d at 111) (quotation marks omitted);
    Allegheny, 40 F.3d at 1424. Nevertheless, in that
    undertaking a court is not always confined to the four
    corners of a document. Rather, it may not be apparent
    whether a contract is ambiguous without an examination of
    the context in which the contract was made. See Hullett, 38
    F.3d at 111; see also Pacitti, 193 F.3d at 773 (noting that
    in determining if a contract is ambiguous, court is not
    confined to its four corners and may read the contract in
    the context in which it was made). Therefore, to determine
    the parties' intentions, the court may consider, among
    other things, "the words of the contract, the alternative
    meaning suggested by counsel, and the nature of the
    objective evidence to be offered in support of that meaning."
    Hullett, 38 F.3d at 111 (quoting Mellon Bank , 619 F.2d at
    1011).
    Under Pennsylvania law, "when two or more writings are
    executed at the same time and involve the same
    transaction, they should be construed as a whole." Western
    United Assurance Co. v. Hayden, 
    64 F.3d 833
    , 842 (3d Cir.
    1995) (citations omitted). If the court finds that the
    10
    contracts pertain to the same transaction, the fact that the
    signatories are different does not mean that this rule does
    not apply. See id. This rule applies equally where several
    agreements are made as part of one transaction even
    though they are executed at different times. See id.
    In this case, the district court concluded that the Surety
    Loan Agreement was unambiguous and capable of only one
    reasonable interpretation -- i.e., American assigned
    National Union the right to enforce the Base Fee
    arrangement set forth in the 1993 Letter Agreement. Thus,
    because the Surety Loan Agreement effectuated a complete
    assignment to National Union, American, as the assignor of
    the right to receipt of the Base Fee, did not retain the right
    to sue Ahlstrom for its portion of the Base Fee as provided
    under the 1993 Letter Agreement.
    American contends, however, that there is a reasonable
    alternative interpretation of the assignment of rights
    embodied in the Surety Loan Agreement when it is
    considered together with the Bonus Fee Agreement and
    Bonus Fee Assignment as a unified transaction. Its
    interpretation begins with the language of the Surety Loan
    Agreement, recognizing that by its terms, American and its
    affiliates assigned to the Surety "all income .. . related in
    any way to the Project . . . (including but not limited to the
    Bonus Fees . . .) coupled with the rights to enforce the
    payments of same. . . ." American states that while this
    language makes it clear that American and Conduit
    assigned to National Union certain rights with respect to
    the Base Fee and the Bonus Fee, "the nature and extent of
    the rights assigned are less than clear." It then turns to the
    language in the Bonus Fee Agreement and Bonus Fee
    Assignment which designates National Union as a"third-
    party beneficiary" of Conduit's right to receive the Bonus
    Fee from Ahlstrom as effectuated by the assignment.
    Pointing to that language, it claims that "[c]onstruing these
    documents together . . . the Surety's right to receive `all
    income' from the Project and to `enforce payments' of the
    income [quoting from the Surety Loan Agreement], are the
    rights of a third-party beneficiary, not a promisee."
    Thus, by a "parity of reasoning," it concludes that if the
    surety was assigned a third-party beneficiary interest in the
    11
    Bonus Fee, National Union also was assigned a third-party
    beneficiary interest with respect to Ahlstrom's payment of
    the Base Fee and any other income from the Project. Of
    course, interpreting the assignment in the Surety Loan
    Agreement in this manner would inure to American's
    benefit, as "both a promisee and an intended third party
    beneficiary may sue to enforce a contract." See In re
    Kaplan, 
    143 F.3d 807
    , 813 (3d Cir. 1998) (applying Illinois
    law); see also Restatement (Second) of Contracts S 305
    (1981) (describing promisor's overlapping duties to
    beneficiary and promisee).
    Applying the standards of contract interpretation
    discussed above, we reject American's alternate
    interpretation which would compel the conclusion that the
    relevant provision in the Surety Loan Agreement is
    ambiguous. The plain language of the assignment found in
    paragraph four of the Surety Loan Agreement, states that
    American and its affiliates hereby "transfer, assign, convey
    . . . to [National Union] all income . . . related in any way
    to the Project, or any other payments of any kind payable
    to [American and its affiliates] . . . (including but not
    limited to the Bonus Fees) . . . coupled with the rights to
    enforce the payments of the same." This language
    inescapably and unambiguously expresses an intent to
    assign to National Union all of the assignors' rights to
    income or payments of any kind, along with the rights to
    enforce the same. See Western United, 64 F.3d at 838.
    There is no language in this paragraph limiting in any way
    National Union's interest in the assigned property; nor is
    there any language which indicates that the assignment
    should be construed as partial rather than complete. See
    Gordon v. Hartford Sterling Co., 
    179 A. 234
    , 236 (Pa. 1935)
    ("Where part of a chose in action has been assigned, the
    assignor and the assignee may unite in a suit for the
    enforcement of the chose; the assignor may sue alone, but
    the assignee may not sue on it in his own name."); see also
    6A Charles Allan Wright et al., Federal Practice and
    Procedure S 1545, at 351-53 (2d ed. 1990).
    While, as we have indicated, the plain language of the
    assignment informs our result, we also observe that an
    examination of the Bonus Fee Agreement, Bonus Fee
    12
    Assignment, and Surety Loan Agreement demonstrates that
    the three agreements are complementary rather than
    contradictory and are consistent with the plain language of
    the Surety Loan Agreement. Clearly, the Bonus Fee
    Agreement, Bonus Fee Assignment, and Surety Loan
    Agreement each represent distinct aspects of the overall
    transaction among the parties and accomplish different
    results. Because each document sets forth different aspects
    of the overall transaction, the provisions of each must be
    understood in that context and applied so as to recognize
    their distinct purpose. See Shehadi v. Northeastern Nat'l
    Bank, 
    378 A.2d 304
    , 306 (Pa. 1977); Flatley v. Penman, 
    632 A.2d 1342
    , 1344 (Pa. Super. Ct. 1993). Thus, we consider
    the documents together.
    The first document is the Bonus Fee Agreement, entered
    into by the four members of the Partnership, AGP, ARLP,
    API and American. The only relevant aspect of the Bonus
    Fee Agreement for purposes of this analysis is its provision
    which states that AGP (Ahlstrom's affiliate) agrees to cause
    Ahlstrom to effectuate an assignment of its right to 24% of
    the Bonus Fee to American's designee Conduit. The second
    document, the Bonus Fee Assignment, in turn, is an
    assignment between Ahlstrom (as assignor) and Conduit (as
    assignee and the designee of American). Its purpose was to
    assign or transfer Ahlstrom's right to 24% of the Bonus Fee
    under the EPC contract to Conduit. National Union was not
    a signatory to either the Bonus Fee Agreement or the
    Bonus Fee Assignment.
    The third document, the Surety Loan Agreement,
    effectuated an assignment from American and its affiliates
    (as assignors) to National Union (as assignee). We repeat
    that the document assigned to National Union "all income
    . . . related in any way to the Project . . . or any other
    payments of any kind payable to [American and its
    affiliates] . . . from [Ahlstrom and its affiliates] (including
    but not limited to the Bonus Fees) . . . coupled with the
    rights to enforce the payments of same. . . ." Ahlstrom was
    not a signatory to the Surety Loan Agreement. The Surety
    Loan Agreement, with its broad-based assignment of all of
    American's and its affiliates' rights to any income or
    payments received from the Project, by its very terms had
    13
    to occur subsequently to Ahlstrom's assignment to Conduit.
    After all, prior to the execution of the Bonus Fee Agreement
    and Bonus Fee Assignment, Conduit had no right or
    interest in the Bonus Fee to assign to National Union.
    Moreover, the assignment in the Surety Loan Agreement
    was central to completion of the overall transaction, as it
    was bargained for in exchange for National Union's
    agreement to permit Conduit to loan the funds to American
    so that American could meet its obligations under the CSF
    Agreement.
    As the foregoing analysis demonstrates, there is nothing
    in the Bonus Fee Agreement or Bonus fee Assignment
    which is inconsistent with the assignment in the Surety
    Loan Agreement. The only assignment in the Bonus Fee
    Assignment was from Ahlstrom (assignor) to Conduit
    (assignee) of Ahlstrom's right to receive 24% of Ahlstrom's
    Bonus Fee as set forth in the EPC contract. ("Assignor
    hereby assigns . . . to Assignee . . . the right to receive . . .
    twenty-four percent (24%) of Assignor's Bonus Fee under
    paragraph 13.3 of the EPC Contract."). Thus, the Bonus
    Fee Assignment did not effectuate an "assignment" from
    Conduit to National Union of Conduit's right to a portion of
    the Bonus Fee. To be sure, the agreement directed that any
    amounts otherwise payable to Conduit with respect to 24%
    of the Bonus Fee assigned to it by Ahlstrom should be paid
    directly to National Union as Surety. However, that
    arrangement is not the legal equivalent of an express
    assignment of rights. See 3 E. Allan Farnsworth,
    Farnsworth on Contracts S 11.3, at 69 (2d ed. 1998)
    (discussing transactions which would not qualify as
    assignments, and providing the following example:
    "Sometimes an obligee (B) orders the obligor (A) to pay a
    debt to a third person (C), rather than the obligee. If the
    order is given directly to the obligor (A), courts have little
    difficulty in concluding that the obligee did not intend to
    make an assignment. . . .").
    Moreover, the designation in the Bonus Fee Agreement
    and Bonus Fee Assignment of National Union as the third-
    party beneficiary is entirely consistent with American's and
    its affiliates' subsequent complete assignment to National
    Union of the rights to any income or payments related to
    14
    the Project. National Union's designation as a third-party
    beneficiary in the Bonus Fee Assignment and subsequent
    status as an assignee which received not only an
    unencumbered right to the Bonus Fee but also the right to
    "any income" or "any other payments of any kind" owed to
    American and its affiliates, does not render the third-party
    beneficiary provision in the Bonus Fee Assignment
    inconsistent with the assignment in the Surety Loan
    Agreement.
    We acknowledge that the assignment in the Surety Loan
    Agreement elevated National Union's rights from the status
    of a third-party beneficiary (as articulated in the Bonus Fee
    Assignment) to that of an assignee. In that regard, however,
    the assignment in the Surety Loan Agreement cannot be
    viewed as irreconcilable with the third-party beneficiary
    designation in the Bonus Fee Assignment. Cf. Flatley, 632
    A.2d at 1344 (where appellee sought construction of one
    paragraph of release which flatly conflicted with next
    paragraph of release, court invoked rule of construction
    that terms in contract should be read as consistent with
    one another, and one part should not be construed so as to
    nullify other terms). Indeed, for National Union to have any
    interest in the Bonus Fee Assignment, it had to be
    designated as a third-party beneficiary in that agreement,
    or at the very least clearly have been intended by the
    parties to the agreement to be its intended beneficiary, as
    it was not a party to that agreement. See Visor Builders,
    Inc. v. Devon E. Tranter, Inc., 
    470 F. Supp. 911
    , 923 (M.D.
    Pa. 1978) (noting that a third-party beneficiary is "one who,
    although not a party to the contract, and hence, not in
    privity with the promisor . . . is permitted to enforce the
    contract between the promisor and the promisee for its (the
    third-party beneficiary's) benefit").
    As we set forth above, assignments in the Bonus Fee
    Assignment and the Surety Loan Agreement occurred
    sequentially and involved different assignors and assignees.
    Accordingly, the provisions of each assignment must be
    interpreted with that reality in mind. When viewed in that
    light, it is clear that the parties' designation of National
    Union as a third-party beneficiary in the Bonus Fee
    Assignment is wholly consistent with its later status as an
    15
    assignee in the Surety Loan Agreement, given the sequence
    of events and the contemplated structure of the overall
    transaction. Thus, we reject American's contention that the
    Surety Loan Agreement, if read as a complete assignment,
    is inconsistent with the third-party beneficiary designation
    in the Bonus Fee Agreement and Assignment.
    Finally, there is nothing in the Surety Loan Agreement
    indicating that the parties intended that American's right to
    collect any delinquent payments owed to it, i.e. , 25% of the
    Base Fee, would be preserved. In any event, the Bonus Fee
    Assignment does not include a "reservation of rights" clause
    that theoretically could be imported into the Surety Loan
    Agreement so that the latter document could be interpreted
    as having reserved in American a right to sue Ahlstrom for
    25% of the Base Fee. Paragraph three of the Bonus Fee
    Assignment merely declares Conduit's right (as assignee) to
    enforce payment of 24% of the Bonus Fee. Because Conduit
    assigned that right to National Union by virtue of the
    Surety Loan Agreement, the rights declared in paragraph
    three of the Bonus Fee Assignment cannot be imported into
    the Surety Loan Agreement. As previously mentioned, the
    Bonus Fee Assignment and the Surety Loan Agreement
    were two distinct documents with two distinct purposes.
    Thus, a clause in the former document cannot be imported
    wholesale into the latter so as to create an ambiguity where
    none exists on the face of the Surety Loan Agreement. In
    this regard we point out that even when several
    instruments pertaining to one transaction are considered
    together, the instruments do not become a single document
    for all purposes. See USX Corp. v. Prime Leasing Inc., 
    988 F.2d 433
    , 437-38 (3d Cir. 1993).
    Additionally, as Ahlstrom correctly observes, American's
    right as a promisee under the Bonus Fee Agreement to sue
    the Partnership for unpaid Bonus Fees is unhelpful in
    determining whether the Surety Loan Agreement similarly
    preserves American's right to sue Ahlstrom for unpaid Base
    Fees. As our emphasis indicates, there is language in the
    Bonus Fee Agreement that sets forth with particularity
    American's right to sue the Partnership, not Ahlstrom,
    should American not receive any portion of the Bonus Fee
    due under that agreement. Moreover, the right to sue,
    16
    which the Bonus Fee Agreement provides, is for the Bonus
    Fees, not the Base Fee. Accordingly, if we were to adopt
    American's "reasonable alternative interpretation" of these
    agreements, not only would we have to import language
    from the Bonus Fee Agreement to the Surety Loan
    Agreement, after we imported it we next would have to
    stretch and mangle the language to reach the conclusion
    that the Surety Loan Agreement's broad assignment also
    was intended to preserve American's right to sue Ahlstrom
    for the Base Fee. The parties are highly sophisticated and
    have demonstrated their ability to create third-party
    beneficiary rights when they saw fit, and to create an
    assignment where they deemed one appropriate. They will
    get no help from us in rewriting the plain terms of their
    agreements.
    For each of these reasons, we find that these agreements,
    while part of the same transaction, clearly and purposefully
    accomplished distinct results. This conclusion renders the
    Bonus Fee Agreement, Bonus Fee Assignment and Surety
    Loan Agreement entirely consistent, and confirms our
    determination that the assignment in the Surety Loan
    Agreement unambiguously conveyed American's right to
    sue for 25% of the Base Fee to National Union.
    Finally, we reject American's subsequent performance
    argument. While it does appear that Ahlstrom made a Base
    Fee payment to American in January 1996 after the
    execution of the Surety Loan Agreement, we see no
    significance to that payment as Ahlstrom was not a party to
    the agreement and it made the payment before the
    execution of the March 27, 1996 letter directing it to make
    payments to National Union.
    IV. CONCLUSION
    For the foregoing reasons we will affirm the district
    court's order of summary judgment entered October 16,
    1998, to Ahlstrom. Plainly American does not have standing
    as the real party in interest under Fed. R. Civ. P. 17.
    American completely assigned its right to enforce payment
    under the 1993 Letter Agreement to National, and
    consequently, American lacks standing to sue Ahlstrom.
    17
    A True Copy:
    Teste:
    Clerk of the United States Court of Appeals
    for the Third Circuit
    18