Horsehead v. Paramont Comm Inc ( 2001 )


Menu:
  •                                                                                                                            Opinions of the United
    2001 Decisions                                                                                                             States Court of Appeals
    for the Third Circuit
    7-17-2001
    Horsehead v. Paramont Comm Inc
    Precedential or Non-Precedential:
    Docket 99-3865
    Follow this and additional works at: http://digitalcommons.law.villanova.edu/thirdcircuit_2001
    Recommended Citation
    "Horsehead v. Paramont Comm Inc" (2001). 2001 Decisions. Paper 156.
    http://digitalcommons.law.villanova.edu/thirdcircuit_2001/156
    This decision is brought to you for free and open access by the Opinions of the United States Court of Appeals for the Third Circuit at Villanova
    University School of Law Digital Repository. It has been accepted for inclusion in 2001 Decisions by an authorized administrator of Villanova
    University School of Law Digital Repository. For more information, please contact Benjamin.Carlson@law.villanova.edu.
    Filed July 17, 2001
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    NO. 99-3865
    HORSEHEAD INDUSTRIES, INC.,
    Appellant
    v.
    PARAMOUNT COMMUNICATIONS, INC.
    On Appeal From the United States District Court
    For the Middle District of Pennsylvania
    (D.C. Civil Action No. 3:CV-94-0298)
    District Judge: Honorable Edwin M. Kosik
    Submitted Under Third Circuit LAR 34.1(a)
    October 25, 2000
    Before: BARRY, AMBRO and GREENBERG,
    Circuit Judges*
    (Filed July 17, 2001)
    _________________________________________________________________
    *This matter was argued on June 22, 2000 befor e the panel of the
    Honorable Maryanne Trump Barry and Morton I. Greenberg, Circuit
    Judges, and the Honorable Louis F. Ober dorfer, Senior United States
    District Judge for the District of Columbia, sitting by designation. The
    case was reassigned on June 30, 2000 to the above panel due to the
    recusal of Judge Oberdorfer.
    OPINION OF THE COURT
    AMBRO, Circuit Judge.
    The issue presented in this appeal is whether a state
    court judgment, which requires Horsehead Industries, Inc.
    ("Horsehead") contractually to indemnify Paramount
    Communications, Inc. ("Paramount") for all environmental
    costs arising from Horsehead's purchase of certain
    Paramount operations, subsequently can be used by
    Paramount collaterally to estop Horsehead's federal
    CERCLA contribution claim. As a threshold matter, we
    conclude that, under New York law, the state court
    declaratory judgment requiring Horsehead to indemnify
    Paramount is sufficiently final to be given pr eclusive effect,
    despite the fact that damages have yet to be decided.
    Applying New York's principles of collateral estoppel, we
    find that the scope of the indemnity provision is sufficiently
    broad to encompass the identical issues in the federal
    CERCLA contribution case, and that the parties had a full
    and fair opportunity to litigate the issue befor e the New
    York courts. We therefore affirm the decision of the United
    States District Court for the Middle District of Pennsylvania
    ("District Court") granting preclusive ef fect to the judgment
    of the New York Supreme Court, Appellate Division.
    I. Background
    At the heart of this appeal is the interplay between two
    sources of liability for the cost to remedy environmental
    damage -- a contractual indemnification pr ovision and
    statutory liability under the Comprehensive Environmental
    Response, Compensation, and Liability Act of 1980
    ("CERCLA"), found at 42 U.S.C. SS 9601-9627, 9651-9675,
    6911a; and 26 U.S.C. SS 4611-12, 4661-62. W ith respect to
    the former, parties to a contract can indemnify each other
    for the costs stemming from environmental liabilities, and
    those clauses will be interpreted under traditional contract
    law principles. Where sufficient consideration exists --
    either as a benefit to the promisor, or a detriment to the
    promisee -- the indemnification clause is enforceable. See
    2
    Holt v. Feigenbaum, 
    419 N.E.2d 332
     (N.Y. 1981) (holding
    that a written promise to indemnify co-shar eholders against
    disproportionate loss was supported by legally sufficient
    consideration and therefore was enfor ceable).
    Parties may also be statutorily liable to the federal
    Government for cleanup costs under CERCLA, a
    determination made in a suit filed by the Government
    against potentially responsible parties. The purpose of
    CERCLA is "to assure that the current and future costs
    associated with hazardous waste facilities, including post-
    closure costs, will be adequately financed and, to the
    greatest extent possible, borne by the owners and operators
    of such facilities." See 42 U.S.C. S 9607; OHM Remediation
    Services v. Evans Cooperage Co., Inc., 116 F .3d 1574 (5th
    Cir. 1997) (noting CERCLA's broad, r emedial purpose to
    facilitate prompt cleanup of hazardous waste sites and to
    shift costs of environmental response fr om taxpayers to
    parties who benefitted from wastes that caused harm). To
    effect this purpose, Congress cast the liability net wide to
    capture all potentially responsible parties.1
    Under CERCLA, if a purchaser were found liable for
    cleanup costs, it could then seek cost recovery or
    _________________________________________________________________
    1. Section 107 of CERCLA creates four categories of potentially
    responsible defendants:
    1. The current owner and operator of a vessel or facility;
    2. Any person who at the time of disposal of any hazardous
    substance owned or operated any facility at which such hazardous
    substances were disposed of;
    3. Any person who by contract, agreement, or otherwise arranged
    for disposal or treatment, or arranged with a transporter for
    transport for disposal or treatment, of hazar dous substances owned
    or possessed by such person, by any other party or entity, at any
    facility or incineration vessel owned or operated by another party
    or
    entity and containing such hazardous substances;
    4. Any person who accepts or accepted any hazar dous substances
    for transport to disposal or treatment facilities, incineration
    vessels
    or sites selected by such person.
    Frank B. Cross, Federal Environmental Regulation of Real Estate, P 2.03
    (1993) (citations omitted); 42 U.S.C. S 9607(a)(1)-(4).
    3
    contribution from the seller absent an indemnification
    agreement to the contrary. See Nicholas A. Robinson,
    Environmental Regulation of Real PropertyS 22.03[2]
    (1998). Where such an indemnity agreement was entered
    into, contractual and statutory liability for r emediation co-
    exist. In this context, CERCLA recognizes the parties' right
    contractually to indemnify each other, although S 107(e)(1)
    does not permit the transfer of statutory liability vis a vis
    the Government:
    No indemnification, hold harmless, or similar
    agreement or conveyance shall be effective to transfer
    from the owner or operator of any vessel or facility or
    from any person who may be liable for a r elease or
    threat of release under this section, to any other
    person the liability under this section. Nothing in this
    subsection shall bar any agreement to insur e, hold
    harmless, or indemnify a party to such agr eement for
    any liability under this section.
    42 U.S.C. S 9607(e)(1). While the parties r emain jointly and
    severally liable for cleanup responsibility, the statute
    permits, inter alia, the allocation of the costs for cleanup
    via indemnification agreements. See SmithKline Beecham
    Corp., v. Rohm and Haas Co., et al., 89 F .3d 154, 158 (3d
    Cir. 1996) (citing Beazer East, Inc., v. Mead Corp., 
    34 F.3d 206
    , 211 (3d Cir. 1994)). Of course, "statutory liability
    under CERCLA endures even if contractual liability is later
    determined to be non-existent." GNB Battery Technologies,
    Inc., v. Gould, Inc., 
    65 F.3d 615
    , 621 (7th Cir. 1995).
    In this appeal, the contractual liability and statutory
    liability for the remediation of environmental damage are
    allegedly in conflict because the New York state courts
    determined the contractual liability, including CERCLA
    contribution claims, to flow one way -- to Horsehead --
    while the statutory liability is joint and several.
    II. Factual and Procedural History
    With this background, we turn to the facts before us.2
    _________________________________________________________________
    2. A thorough history is presented in the New York Supreme Court,
    Appellate Division case titled Paramount Communications, Inc. v.
    Horsehead Industries, Inc., 
    660 N.Y.S.2d 718
     (App. Div. 1997). It is this
    state court judgment that Paramount used collaterally to estop
    Horsehead's CERCLA contribution claim in the District Court.
    4
    Since the late 19th century, the New Jersey Zinc Company
    ("NJZ") conducted zinc ore smelting operations in the
    vicinity of Palmerton, Pennsylvania.3 These smelting
    operations did not employ air emissions contr ol equipment
    or devices to prevent the leaching of hazar dous wastes into
    the soil, groundwater or watercourses."As a result, the
    areas in which the smelting took place suf fered drastic on-
    site and off-site contamination and degradation, including
    the formation of slag heaps permeated with heavy metals,
    known as `cinder banks', which, at Palmerton alone,
    contained approximately 30 million tons of r esidue."
    Paramount Communications, Inc. v. Horsehead Industries,
    Inc., 
    660 N.Y.S.2d 718
    , 719 (App. Div. 1997).
    In the late 1970s, Gulf and Western Industries, Inc.
    (G&W), Paramount's predecessor in inter est, purchased
    NJZ. Shortly thereafter, Congress passed CERCLA. As a
    result, "the cinder banks became a r egulatory concern
    because heavy metals were leaching into the soil and into
    nearby waterways." 
    Id.
     The financial consequences of
    remediation were steep. For example, estimates for the
    encapsulation of the Palmerton cinder banks in cement to
    prevent further discharge exceeded $50,000,000. Although
    G&W permanently closed the zinc smelting operations in
    December of 1980, it still performed other manufacturing
    processes at Palmerton. Because CERCLA imposes joint
    and several liability on past as well as curr ent owners or
    operators, "simply selling [NJZ's] assets would not relieve
    [G&W] of these liabilities. Consequently, G&W's preferable
    course of action was to sell a still viable operation." 
    Id. at 722
    .4
    _________________________________________________________________
    3. NJZ also subsequently operated zinc smelting operations in the
    vicinity of DePue, Illinois. The appeal befor e us is limited to the
    Palmerton site.
    4. The Court in Paramount noted that
    while some regulatory compliance costs wer e immediate and
    ongoing, CERCLA permitted the bulk of expenditures at either of the
    sites, including Palmerton, to be postponed until NJZ closed down
    operations at the site completely, at which point full scale,
    sitewide
    remediation and satisfaction of statutory closure obligations would
    be required.
    Paramount, 
    660 N.Y.S.2d at 719
    .
    5
    Because of the difficulty in arranging financing for the
    transfer of such a huge environmental liability, former
    officials of G&W's Natural Resources Division formed
    Horsehead in 1981 to purchase certain assets at the
    Palmerton site.5 The Asset Pur chase Agreement ("APA")
    between G&W and Horsehead was entered on September
    15, 1981. Given the potential environmental cleanup costs
    at Palmerton, G&W included an indemnity provision, found
    at Paragraph I.F (2) of the APA, under the heading
    "Assumption of Liabilities."6 The indemnity provision
    specifically requires Horsehead to
    pay, perform and discharge only the following
    obligations of Seller: . . . [a]ll commitments, obligations
    and requirements imposed upon Seller by virtue of any
    environmental, safety and health, reclamation or other
    law, rule, regulation, action or proceeding by any
    governmental agency and any order emanating
    therefrom and all liabilities, damages, costs, obligations
    and requirements imposed upon Seller by virtue of any
    action or proceeding brought by any person, firm or
    corporation under any environmental, safety and
    health or reclamation law (statutory or common), rule
    or regulation relating to the maintenance or operation
    of the Purchased Assets or to the conduct of the
    Seller's Business7 at any time prior to or after the
    _________________________________________________________________
    5. The agreement of sale transferred"all of seller's right, title and
    interest
    in and to all real property located in the County of Carbon, Pennsylvania
    [where the Palmerton facility is located], the County of Sussex, New
    Jersey and the County of Bureau, Illinois [where the DePue site is
    located] . . . ." 
    Id. at 720
    . Again, this appeal is concerned with the
    transfer of assets at the Palmerton facility.
    6. In addition, G&W and Horsehead agreed that Horsehead would pay
    annual environmental compliance and maintenance costs of
    approximately $200,000. G&W also purchased insurance for any
    additional environmental cleanup costs. See Paramount, 
    660 N.Y.S.2d at 719-20
    .
    7. "Seller's Business" is described in the APA as
    the business of mining, manufacturing and selling zinc oxide, zinc
    powder, zinc dust, zamak and other alloys, secondary materials,
    special anodes, rolled zinc, copper-based and other metal powders,
    special oxides, zinstabe, cadmium, ammonia and carbon dioxide
    and . . . the operation of Palmer Water Company and Chestnut
    Ridge Railway Company and, through NJZ Alloys, partnership, . . .
    the manufacture and sale of indium metal . . . .
    6
    Transfer Date including, but not limited to, those
    matters disclosed in Schedule VIII.
    Schedule VIII, entitled "Defaults, Litigation, Claims,
    Environmental Matters, Etc.," contained a detailed listing of
    existing or potential legal obligations or liabilities for which
    some official action, investigation or study had already
    begun at the time of the APA, including those related to the
    discontinued operations of the metal circuits 8 purchased by
    Horsehead. See Paramount, 
    660 N.Y.S.2d at 720
    .
    The APA further provided that, except as identified in the
    indemnification provision, Horsehead would assume no
    other liability or obligation of the seller arising from the
    Seller's Business. See 
    id.
     In addition, Subparagraphs[a]-[f]
    of Paragraph I.F(2) in the APA (directly following the
    indemnification provision) listed those contingent liabilities
    that Horsehead expressly did not assume9 and those
    particular legal or enforcement actions under which (1)
    Paramount would reimburse Horsehead, (2) the parties
    would share the costs, or (3) Horsehead would assume the
    performance and all related costs.
    That the parties had contemplated CERCLA liability is
    evidenced by the reference in Schedule VIII to a
    memorandum attached thereto discussing CERCLA
    reporting requirements, which stated in part:
    _________________________________________________________________
    8. The APA transferred, among other things, the assets comprising the
    metal circuits, which included the property, plant and equipment used
    in the production of primary zinc metal at the Palmerton facility.
    9. Under Subparagraph I.F(2)[d], Horsehead expressly did not assume
    certain contingent liabilities in Schedule VIII. One such contingent
    liability is found in Schedule VIII-A2(a), which states:
    Because applicable law gives administrative agencies discretion to
    bring enforcement actions against closed facilities, and because
    the
    U.S. Environmental Protection Agency ("EPA") was, at the time of
    closing the primary zinc metal circuit at Palmerton, threatening to
    bring such an action against Seller to recover civil penalties for
    past
    alleged violations of applicable air-pollution control laws
    (primarily
    in respect of sulfur-oxide and particulate emissions), Seller
    recognizes this state of fact as repr esenting a contingent
    liability.
    . . .
    7
    "The Comprehensive Environmental Response,
    Compensation and Liability Act, 42 U.S.C. 9601 et
    seq., commonly known as the `Superfund' legislation,
    requires reporting of all unper mitted releases into the
    environment of hazardous substances fr om facilities
    (42 U.S.C. 9603[a]), and requires pr esent and past
    owners to report existing and abandoned hazar dous
    waste disposal facilities that do not have appr oval or
    interim status under [the Resource Conservation and
    Recovery Act] (42 U.S.C. 9603[c]). `Superfund' also
    establishes funding for cleanup of existing hazar dous
    waste facilities, imposes liability for hazar dous waste
    spills, and sets financial responsibility r equirements for
    operators of hazardous waste treatment, storage and
    disposal facilities (42 U.S.C. 9607, 9611).
    "If a hazardous waste site is subject to`Superfund', the
    obligation to report hazardous waste sites survives the
    transfer of the site. Both present and past pr operty
    owners who disposed of hazardous waste must r eport
    the existence of the site. 42 U.S.C. 9603(c). The former
    owner may be liable for cleanup and disposal costs
    under 42 U.S.C. 9607(a). The former owner may not
    use an indemnification agreement to shift liability to any
    other person, but may obtain insurance against his own
    liability."
    Paramount, 
    660 N.Y.S.2d at 721
     (quoting Memorandum
    dated September 22, 1981, attached to and made a part of
    the APA) (emphasis added in opinion).
    On September 8, 1983, the United States Envir onmental
    Protection Agency (the "EPA"), after an investigation begun
    in 1979, listed Palmerton on the CERCLA National Priority
    List. Since then, Horsehead claims to have incurr ed
    significant costs from studies and remediation of the
    environmental conditions at Palmerton. In September,
    1985, Horsehead entered into an Administrative Order by
    Consent (the "Consent Order") with the EP A wherein
    Horsehead agreed to fund a Remedial Investigation and
    Feasibility Study of the Palmerton site. In September, 1987,
    the EPA issued a Record of Decision ("ROD") for the Blue
    Mountain Operable Unit,10 which, according to the EPA,
    _________________________________________________________________
    10. Operable Unit 1 is an area of Blue Mountain located south of
    Horsehead's East Plant at Palmerton.
    8
    was denuded of vegetation as a result of years of smelting
    operations. Horsehead agreed to design and fund the re-
    vegetation of a portion of the Mountain. In June, 1988,
    after EPA issued a ROD for the Cinder Bank Operable Unit,11
    Horsehead agreed to perform five additional studies to
    identify alternate response actions. On February 11, 1992,
    in a second amendment to the Consent Order , Horsehead
    agreed to undertake additional response actions related to
    the removal of lead from homes in Palmerton. Id. at 11-12.
    Litigation of statutory liability under CERCLA began with
    regard to the Palmerton site in 1992, when the United
    States filed an action against Horsehead Resour ce
    Development Company, Inc.12 and Horsehead alleging
    violation of certain environmental laws. United States v.
    Horsehead Resource Dev. Co., et al., 92-CV -0008.13 On
    October 8, 1993, Horsehead filed a motion for leave to file
    a third-party complaint against Paramount to r ecover its
    remediation costs. Horsehead's motion to file its third-party
    complaint was subsequently denied.
    In light of the Government's CERCLA action, and
    pursuant to a choice of law clause in the AP A, Paramount
    filed a contract action for damages and for declaratory
    judgment in the Supreme Court of New York, Trial Division,
    on October 14, 1993, seeking an interpretation of the
    contractual indemnification provision as it applied to
    environmental claims. The New York trial court ruled on
    _________________________________________________________________
    11. The Cinder Bank Operable Unit (Operable Unit 2) consists of more
    than 30,000,000 tons of smelter residue deposited along the base of Blue
    Mountain. The cinder bank is approximately 2 miles long, 500 to 1,000
    feet wide, and 100 to 200 feet high. The remaining Operable Units have
    been designated by the EPA as Operable Unit 3, consisting of the surface
    soils in the Palmerton area, and Operable Unit 4, consisting of the
    groundwater in the same area.
    12. Horsehead Resource Development Company, Inc. ("HRDC") is a
    wholly-owned subsidiary of Horsehead Industries, Inc.
    13. Ultimately, the EPA's suit was settled by consent decree with
    Horsehead and HRDC. Subsequently, on April 17, 1998, the United
    States filed a CERCLA liability and cost r ecovery action in the Middle
    District of Pennsylvania against Horsehead, HRDC, Paramount and
    nearly 200 other parties. See United States v. Horsehead Industries, Inc.,
    et al., No. 3:CV 98-0654.
    9
    April 24, 1996 that the contractual indemnification
    provision obligated Horsehead to indemnify Paramount for
    certain environmental costs, but did not transfer CERCLA
    liability costs.
    Both parties appealed the New York trial court decision,
    and on July 10, 1997 the New York Supr eme Court,
    Appellate Division, agreed with the Trial Division's ruling
    that as a matter of law Horsehead is requir ed to indemnify
    Paramount pursuant to the indemnification pr ovision for
    certain environmental costs. But unlike the T rial Division,
    the Appellate Division held that the indemnification
    provision included those remediation costs that Horsehead
    is currently seeking under CERCLA. The Appellate Division
    refused re-argument and refused to grant Horsehead leave
    to appeal. Horsehead then filed a motion for leave to appeal
    directly in the New York Court of Appeals. The motion was
    dismissed on the ground that the order of the Appellate
    Division did not finally determine the action. Paramount
    Communications, Inc. v. Horsehead Industries Inc., 
    691 N.E.2d 634
     (Table, December 22, 1997).
    Notwithstanding the New York state court action,
    Horsehead filed a complaint in the United States District
    Court for the Middle District of Pennsylvania on Mar ch 1,
    1994 against Paramount for contribution under S 113(f) of
    CERCLA, which provides that "[a]ny person may seek
    contribution from any other person who is liable or
    potentially liable . . . . In resolving contribution claims, the
    court may allocate response costs among liable parties
    using such equitable factors as the court deter mines are
    appropriate." 42 U.S.C. S 9613(f). The amended complaint
    included four counts. Counts I and II sought r ecovery from
    Paramount pursuant to S 107(a)(4) of CERCLA, 42 U.S.C.
    S 9607(a)(4). Count III sought contribution fr om Paramount
    under S 113(f) of CERCLA, 42 U.S.C. S 9613(f). Count IV
    sought cost recovery and also alleged public nuisance
    under the Pennsylvania Hazardous Sites Cleanup Act
    ("HSCA"), 35 Pa. C.S.A. SS 6020.101-1305. Paramount
    moved for summary judgment on June 4, 1999, asking that
    the District Court, as an affirmative defense to Horsehead's
    claims, give full faith and credit to the decision of the New
    York Supreme Court, Appellate Division. The District Court
    10
    did so, and entered summary judgment in Paramount's
    favor on October 21, 1999. This appeal followed.
    Jurisdiction was proper in the District Court under 42
    U.S.C. S 9613(b), which vests exclusive jurisdiction of
    CERCLA claims in the federal courts, and under 28 U.S.C.
    SS 1331 and 1367. Appellate jurisdiction is proper in this
    Court pursuant to 28 U.S.C. S 1291.
    III. Legal Analysis
    As noted at the outset of this opinion, we must decide
    whether the District Court properly invoked New York's
    collateral estoppel law to give preclusive ef fect to the state
    court judgment rendering Horsehead contractually liable for
    the costs stemming from environmental damage at the
    Palmerton site, including CERCLA claims. If so, Horsehead
    may not proceed on its CERCLA contribution claim against
    Paramount in the District Court.
    We review the District Court's entry of summary
    judgment de novo. See Armbruster v. Unisys Corp., 
    32 F.3d 768
    , 777 (3d Cir. 1994). We also r eview the District Court's
    interpretation, application, and prediction of state law de
    novo. See InfoComp, Inc. v. Electra Pr oducts, Inc., 
    109 F.3d 902
    , 905 (3d Cir. 1997). Rule 56(c) of the Federal Rules of
    Civil Procedure "mandates the entry of summary judgment,
    after adequate time for discovery and upon motion, against
    a party who fails to make a showing sufficient to establish
    the existence of an element essential to that party's case,
    and on which that party will bear the burden of proof at
    trial." Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322 (1986).
    "Where the record taken as a whole could not lead a
    rational trier of fact to find for the non-moving party, there
    is no `genuine issue for trial.' " Matsushita Elec. Indus. Co.
    v. Zenith Radio Corp., 
    475 U.S. 574
    , 587 (1986) (citing First
    National Bank of Arizona v. Cities Serv. Co., 
    391 U.S. 253
    ,
    289 (1968)). We recognize that when considering a motion
    for summary judgment, all evidence submitted must be
    viewed in a light most favorable to the party opposing the
    motion. See Matsushita, 
    475 U.S. at 587
    .
    A. Collateral Estoppel Under New York Law
    The doctrine of collateral estoppel provides that "once a
    court has decided an issue of fact or law necessary to its
    11
    judgment, that decision may preclude relitigation of the
    issue in a suit on a different cause of action involving a
    party to the first case." Allen v. McCurry , 
    449 U.S. 90
    , 94
    (1980). By federal statute, "judicial proceedings . . . shall
    have the same full faith and credit in every court within the
    United States and its Territories and Possessions as they
    have by law or usage in the courts of such State . .. ." 28
    U.S.C. S 1738.
    The parties agree that New York law governs this issue.
    "In adjudicating a case under state law, we ar e not free to
    impose our own view of what state law should be; rather,
    we are to apply existing state law as interpr eted by the
    state's highest court in an effort to pr edict how that court
    would decide the precise legal issues befor e us." Koppers
    Co., Inc. v. Aetna Cas. and Sur. Co., 
    98 F.3d 1440
    , 1445 (3d
    Cir. 1996) (citing Kowalsky v. Long Beach Township, 
    72 F.3d 385
    , 388 (3d Cir. 1995)). Given that we are faced with
    an absence of guidance from New York's highest court, we
    must look to decisions of state intermediate appellate
    courts and of federal courts interpreting New Y ork law. 
    Id.
    Neither party disputes that 28 U.S.C. S 1738 r equires
    federal courts, in cases where state law applies, to give
    preclusive effect to state court judgments whenever courts
    of the state from which the judgment emanated would do
    so. What the parties dispute is whether the state court
    judgment in this case meets the New York collateral
    estoppel test such that the District Court can give it
    preclusive effect as a matter of law.
    The District Court cited to Hickerson v. City of New York,
    
    146 F.3d 99
     (2d Cir. 1998), for New Y ork's collateral
    estoppel principles. Although a federal court decision,
    Hickerson explained and applied New York collateral
    estoppel law, stating that "an issue may not be r elitigated
    if the identical issue was necessarily decided in a previous
    proceeding, provided that the party against whom collateral
    estoppel is being asserted had a full and fair opportunity to
    litigate the issue in the prior action." 146 F .3d at 104
    (relying on In re Sokol, 113 F .3d 303, 306 (2d Cir. 1997);
    Ryan v. New York Tel. Co., 
    467 N.E.2d 487
    , 490-91 (N.Y.
    1984)). As to these two elements -- the identical issue and
    a full and fair opportunity to litigate -- "[t]he party seeking
    12
    the benefit of collateral estoppel has the bur den of
    demonstrating the identity of the issues in the pr esent
    litigation and the prior determination, wher eas the party
    attempting to defeat its application has the bur den of
    establishing the absence of a full and fair opportunity to
    litigate the issue in the prior action." In r e Juan C. v.
    Cortines, 
    679 N.E.2d 1061
    , 1065 (N.Y. 1997) (citing
    Kaufman v. Lilly & Co., 
    482 N.E.2d 63
    , 66 (N.Y . 1985)). In
    addition to whether the issues are identical and whether a
    full and fair opportunity to litigate is affor ded, embodied in
    New York's collateral estoppel rule is the concept of finality
    of judgments, i.e., that the judgment in the prior
    proceeding, and on which the claim to collateral estoppel is
    based, is final. See In re Juan C., 679 N.E.2d at 1063. Each
    of these principles, beginning with finality, is discussed
    below.
    (1) Finality
    New York law incorporates the threshold concept of
    "finality" of judgments into its collateral estoppel standard.14
    The previous proceeding must result"in a final and valid
    judgment in which the party opposing estoppel had a full
    and fair opportunity to litigate." See In r e Juan C., 679
    N.E.2d at 1063. However, contrary to Horsehead's
    argument, finality does not requir e that all appeals be
    completed. "The finality of a judgment for the purposes of
    appealability is not the same as its finality for collateral
    estoppel purposes." State Bank of Albany v. McAuliffe, 
    485 N.Y.S.2d 139
    , 141 (App. Div. 1985); see also Matter of
    Amica Mut. Ins. Co., 
    445 N.Y.S.2d 820
    , 822 (App. Div. 1981)
    ("The rule in New York, unlike that in other jurisdictions, is
    that the mere pendency of an appeal does not pr event the
    use of the challenged judgment as the basis of collaterally
    estopping a party to that judgment in a second
    proceeding."). Accordingly, the possibility that this
    judgment may be overturned during the pr oper course of
    _________________________________________________________________
    14. Of course, a prerequisite to finding finality is that the judgment
    relied upon for collateral estoppel purposes be valid. Restatement
    (Second) of Judgments S 1 (1982). Neither party disputes the validity of
    the judgment of the New York Supreme Court, Appellate Division.
    13
    appellate review does not prohibit r esort to collateral
    estoppel.
    The District Court cited Lummus Co. v. Commonwealth
    Oil Refining Co., 
    297 F.2d 80
     (2d Cir . 1962), cert. denied
    sub nom. Dawson v. Lummus Co., 
    368 U.S. 986
     (1962), for
    the distinction between finality for purposes of appeal and
    finality for purposes of collateral estoppel. Judge Henry J.
    Friendly in Lummus was interpreting New York law when he
    stated:
    Whether a judgment, not "final" in the sense of 28
    U.S.C. S 1291, ought nevertheless be consider ed "final"
    in the sense of precluding further litigation of the same
    issue, turns upon such factors as the natur e of the
    decision (i.e., that it was not avowedly tentative), the
    adequacy of the hearing, and the opportunity for
    review. "Finality" in the context her e relevant may
    mean little more than that the litigation of a particular
    issue has reached such a stage that a court sees no
    really good reason for permitting it to be litigated
    again.
    
    297 F.2d at 89
     (internal citations omitted); accord, Sherman
    v. Jacobson, 
    247 F. Supp. 261
    , 268 (S.D.N.Y. 1965) (" `final'
    in the res judicata or collateral estoppel sense is not
    identical to `final' in the rule governing the jurisdiction of
    appellate courts"). In Sherman, as in this case, the decision
    on which collateral estoppel rested remained open for
    appeal. Significantly, as the District Court in our case
    pointed out, the court in Sherman concluded that a
    judgment may be final as to some matters, even though the
    litigation continues as to others, and "the decision may
    have adjudicated liability only, leaving the assessment of
    damages in abeyance." Sherman, 
    247 F. Supp. at 268
    ; see
    also Zdanok v. Glidden Co., Durkee Famous Foods Div. , 
    327 F.2d 944
    , 955 (2d Cir. 1964) ("The mere fact that the
    damages of the Zdanok plaintiffs have not yet been
    assessed should not deprive that ruling of any ef fect as
    collateral estoppel it would otherwise have."), cert. denied,
    
    377 U.S. 934
     (1964).
    The District Court noted that while the New Y ork
    approach outlined in Lummus departs fr om the traditional
    14
    view of finality, it continues to garner support. See
    Metromedia Co. v. Fugazy, 
    983 F.2d 350
    , 366 (2d Cir. 1992)
    ("The mere fact that the damages awar ded to the plaintiff
    have not been yet calculated, though normally precluding
    an immediate appeal, . . . does not prevent use of a final
    ruling on liability as collateral estoppel."); In re Brown, 
    951 F.2d 564
    , 569 (3d Cir. 1991) ("In this case, the order of the
    state court granting summary judgment on liability was not
    final for purposes of appeal, but that does not deny it
    preclusive effect in the bankruptcy court."); Hennessy v.
    Cement and Concrete Worker's Union, 
    963 F. Supp. 334
    ,
    339 (S.D.N.Y. 1997) ("The fact that Hennessy could have
    appealed the order but chose to await a decision on the
    damages on the counterclaim before appealing from the
    dismissal of his claim does not change the conclusive effect
    of the final disposition of the claim.").
    Applying the factors that Judge Friendly consider ed
    relevant, e.g., the nature of the decision, the adequacy of
    the hearing, and the opportunity for review, the District
    Court found that the New York indemnification order was
    sufficiently final. We agree. Horsehead fully litigated the
    indemnification agreement before both the New York trial
    court and the intermediate appellate court. Thus, the
    hearing and opportunity for review affor ded Horsehead were
    adequate. The decision rendered by the New York Supreme
    Court, Appellate Division, is binding on the T rial Division.
    Although not final for purposes of an appeal to the New
    York Court of Appeals given that damages r emain to be
    litigated, the nature of the New York Appellate Division
    decision as to liability is in no way tentative. Therefore, we
    conclude that, for purposes of collateral estoppel, the
    decision is final.
    (2) Identical Issues
    Under New York law, the burden r ests on Paramount to
    demonstrate that the issues litigated in the separate
    proceedings were identical. See Ryan, 467 N.E.2d at 490.
    For an issue to be identical, "it must be the point actually
    to be determined in the second action or pr oceeding such
    that `a different judgment in the second would destroy or
    impair rights or interests established by thefirst.' " Id. The
    15
    issue in the New York Supreme Court, Appellate Division,
    proceeding was whether Paramount was entitled to
    indemnification for liability for certain envir onmental claims
    pursuant to its indemnification agreement with Horsehead.
    The state appellate court made an express finding that the
    indemnification provision included CERCLA contribution
    claims. See Paramount, 
    660 N.Y.S.2d at 723
    . The threshold
    issue in the District Court proceeding seeking contribution
    from Paramount for response costs under CERCLA is
    whether the scope of the indemnification pr ovision covers
    CERCLA liability costs. If it does, then the issue in the state
    contract and federal CERCLA contribution proceedings is,
    for our purposes, identical.
    Courts that have considered the issue r ecognize that "the
    questions of CERCLA liability and the interpr etation of any
    indemnification agreement among the parties liable for the
    clean-up are inextricably related." GNB Battery
    Technologies, Inc. v. Gould, Inc., 65 F .3d 615, 621 (7th Cir
    1995) (citing Kerr-McGee Chem. Corp. v. Lefton Iron & Metal
    Co., 
    14 F.3d 321
     (7th Cir. 1994)). Moreover, in the context
    of asset purchase or transfer agreements, courts (including
    this Court) have held that CERCLA claims are subsumed
    within broad contractual indemnification pr ovisions. See,
    e.g., SmithKline Beecham Corp. v. Rohm and Haas Co., et
    al., 
    89 F.3d 154
    , 160 (3d Cir. 1996) (holding that the
    language in the Purchase Agreement indemnity provisions
    is general enough to evidence the parties' intent to include
    CERCLA response costs, even though not specifically
    enumerated); GNB Battery Technologies, 
    65 F.3d at 622
    (concluding that the plain language of the assumption
    agreement was sufficiently broad to encompass any
    CERCLA liabilities that may arise, even though no specific
    reference to CERCLA was made); Beazer East, Inc. v. Mead
    Corp., 
    34 F.3d 206
    , 211 (3d Cir. 1994) ("we must look to see
    whether an indemnification provision is either specific
    enough to include CERCLA liability or general enough to
    include any and all environmental liability which would,
    naturally, include subsequent CERCLA claims"). Applying
    New York law to indemnity and release pr ovisions, courts
    have reached similar conclusions. See Olin Corp. v.
    Consolidated Aluminum Corp., 
    5 F.3d 10
    , 14 (2d Cir. 1993)
    (concluding that an agreement transferring"all liability"
    16
    transfers responsibility for all CERCLA liability, even if it
    does not expressly reference CERCLA); see also Purolator
    Prods. Corp. v. Allied-Signal, Inc., 
    772 F. Supp. 124
    , 130
    (W.D.N.Y. 1991) (concluding that, under two broad
    indemnity clauses, the purchaser clearly agr eed to take the
    assets along with any liabilities, including CERCLA
    liabilities, that might attach to them).
    Thus, in a CERCLA contribution action where the parties
    entered into an indemnification agreement, the proper
    inquiry is whether the indemnification provision "is either
    specific enough to include CERCLA liability or general
    enough to include any and all environmental liability which
    would, naturally, include subsequent CERCLA claims."
    Beazer East, Inc., 
    34 F.3d at 211
    . The interpretation of the
    scope of the contractual indemnity provision in this case is
    guided by state law, and the parties agree that New York
    law applies. See SmithKline Beecham Corp., 
    89 F.3d at
    158-
    59 ("We apply state law to determine whether a particular
    indemnification provision encompasses CERCLA response
    costs.") (citing Hatco Corp. v. W.R. Grace & Co., 
    59 F.3d 400
    , 405 (3d Cir. 1995)); Olin Corp., 
    5 F.3d at 15
    (concluding that federal courts should incorporate state law
    when interpreting contractual agreements allocating
    CERCLA liability).
    The Court in Olin summarized the relevant principles of
    New York contract law developed by the New Y ork Court of
    Appeals in Slatt v. Slatt, 
    477 N.E.2d 1099
    , 1100 (N.Y.
    1985). Under that law, "it is our function to`discern the
    intent of the parties to the extent their intent is evidenced
    by their written agreement.' " Olin, 
    5 F.3d at
    15 (citing
    Commander Oil Corp. v. Advance Food Serv. Equip., 
    991 F.2d 49
    , 51 (2d Cir. 1993) (quoting Int'l Klafter Co. v.
    Continental Casualty Co., 
    869 F.2d 96
    , 99 (2d Cir. 1989)
    (citing Slatt, 477 N.E.2d at 1100 (N.Y . 1985)))). "Where the
    intention of the parties is clearly and unambiguously set
    forth, effect must be given to the intent as indicated by the
    language used." Slatt, 477 N.E.2d at 1100. However, we
    note that "in New York[,] indemnification agreements are
    strictly construed; a court cannot find a duty to indemnify
    absent manifestation of a `clear and unmistakable intent' to
    indemnify." Commander Oil, 
    991 F.2d at
    51 (citing
    17
    Heimbach v. Metropolitan Transp. Auth. , 
    553 N.E.2d 242
    ,
    246 (N.Y. 1990)).
    The District Court's discussion of this issue is
    unfortunately conclusory:
    [R]egardless . . . whether the New Y ork action can or
    cannot be characterized as one seeking CERCLA
    damages, the thrust of the New York pr oceeding was
    exclusively an action on a contract to deter mine if
    Paramount was entitled to indemnity from [Horsehead]
    under the contract provision dealing with
    environmental damage claims in Palmerton,
    Pennsylvania and elsewhere for which Paramount may
    be liable. Accordingly, there are no factual issues over
    environmental damages which would preclude
    summary judgment on the indemnity question.
    Dist. Ct. Op. at 7. The District Court granted summary
    judgment in favor of Paramount, concluding that"[w]e can
    find no reason for proceeding with this second case
    between the parties when in the first case in New York
    there is a claim which was litigated and may very well moot
    this action." Id. at 10. The District Court, in reading the
    Paramount decision of the Appellate Division of the New
    York Supreme Court, was satisfied that the indemnification
    provision encompassed all of the environmental claims,
    including the CERCLA contribution claims befor e it, such
    that the identical issue was present to pr eclude litigating
    the CERCLA contribution claim in the District Court.
    The indemnification provision in this case is considerably
    broad, holding Horsehead responsible for the costs
    associated with all environmental liabilities stemming from
    "Seller's Business" and the "Purchased Assets" at the
    Palmerton site. Specifically, Horsehead must indemnify
    Paramount for "all liabilities, damages, costs, obligations
    and requirements . . . under any envir onmental, safety and
    health or reclamation law." The indemnification provision
    applies to "the maintenance or operation of the Purchased
    Assets or to the conduct of the Seller's Business at any
    time prior to or after the Transfer Date."
    This provision shows a clear and unmistakable intent to
    include all environmental claims, including claims for
    18
    contribution under CERCLA. The circumstances
    surrounding the transfer of assets, most notably that
    Horsehead was formed by officials of Paramount's
    predecessor for the purpose of transferring the
    environmental liability associated with the Palmerton site,
    id. at 719, confirm that intent. W e agree with the New York
    Supreme Court, Appellate Division, which made a thorough
    inquiry as to the scope of the indemnification pr ovision,
    that "[t]he language of the broad indemnification clause
    itself clearly and unambiguously requir es indemnification
    for all liabilities arising from environmental laws and
    regulations, without any exclusion of CERCLA liabilities."
    Id. at 722.
    However, the indemnification provision was accompanied
    by contractual limitations on Horsehead's liability.
    Horsehead argues that these limitations, notably the
    exceptions enumerated under Subparagraphs I.F(2)[a]-[f] of
    the APA and Schedule VIII appended to it, defeat the
    identicality between contractual liability and CERCLA
    liability. Contractually, Horsehead would not be r esponsible
    for certain contingent liabilities it expressly declined. See
    supra, note 9. Yet under CERCLA's statutory liability,
    Horsehead posits that it may be responsible for those same
    contingent liabilities. Horsehead contends that the District
    Court's decision in this case sidesteps CERCLA's
    contribution mechanism and requires Horsehead to
    reimburse Paramount for all CERCLA claims, even those
    expressly excepted in the APA and those associated with
    the assets not purchased by Horsehead. In other words,
    Horsehead argues that the universe of CERCLA liabilities
    may exceed those liabilities for which Horsehead must
    reimburse Paramount under the indemnification
    agreement, and thus the requisite identicality of issues is
    missing.
    Where an indemnification agreement exists, the threshold
    inquiry in a CERCLA contribution case is the same as the
    inquiry the New York Supreme Court, Appellate Division,
    undertook: whether the scope of the indemnification
    provision is broad enough to encompass liability for
    CERCLA response costs. With respect to Horsehead's
    arguments, we first note that Horsehead is confusing the
    19
    determination of CERCLA liability with the function of an
    indemnification agreement, which covers the allocation of
    cleanup costs among its parties. Similar to an insurance
    policy, the indemnification agreement transfers the
    responsibility for who pays the response costs regardless of
    liability. Moreover, CERCLA recognizes the parties' right to
    indemnify each other by agreement for r esponse costs, as
    they have done. See SmithKline Beecham Corp., 
    89 F.3d at 158
     ("Thus responsible parties can lawfully allocate
    CERCLA response costs among themselves while r emaining
    jointly and severally liable to the government for the entire
    clean-up.").
    We have also reviewed the limitations on Horsehead's
    liability in Subparagraphs I.F(2)[a]-[f] of the APA and
    Schedule VIII attached thereto, and find nothing that
    changes the intent of the parties or renders the
    indemnification provision ambiguous such that it would not
    include CERCLA response costs. In GNB Battery
    Technologies, a case with relevant similarities, the Seventh
    Circuit held that the plain language of the assumption
    agreement unambiguously transferred all of seller's
    liabilities, including CERCLA liabilities, despite the fact that
    specific exemptions from liability wer e enumerated. 
    65 F.3d at 623
    . The Court concluded that "[t]he enumeration of
    these exemptions indicates that the parties intended to
    exempt only the situations that they specifically itemized."
    
    Id.
     Therefore, because CERCLA liabilities specifically were
    not itemized as exemptions, they were intended to be
    included by the parties. Moreover, the fact that the
    exemptions existed did not operate to defeat the inclusion
    of CERCLA liabilities.
    In this case, Horsehead argues that the CERCLA
    liabilities and the exceptions listed in Schedule VIII overlap.
    Under Subparagraphs I.F(2)[a], [b],[c], and [e] of the APA,
    Horsehead assumes the full performance and costs
    associated with specific litigation or consent or ders except
    where Paramount agrees to reimburse Horsehead for some
    portion of those costs. In Subparagraph I.F(2)[d], Horsehead
    expressly declines any contingent liability associated with
    certain fugitive emissions at the Palmerton site. In
    Subparagraph I.F(2)[f], Horsehead declines liability from an
    20
    industrial accident not related to the Palmerton site. These
    limitations on liability will likely be consider ed in the
    damages phase of the New York litigation. However, they do
    not alter our holding here that the plain language of the
    APA demonstrates the intent that Horsehead indemnify
    Paramount for all environmental claims, including claims
    for contribution under CERCLA.
    Moreover, that these exceptions to Horsehead's liability
    do not specifically mention CERCLA liability supports the
    view that the parties intended that CERCLA liability be
    included within the broad scope of envir onmental claims for
    which indemnification exists. As the New Y ork appellate
    court noted, "the parties' failure to include CERCLA
    liability, by name, does not render the agr eement
    ambiguous where the broad language of the agreement
    clearly encompasses all environmental liabilities of which
    CERCLA is one. More significant is the fact that CERCLA
    liability is not listed in [Subparagraphs] I.F(2)[a]-[f], which
    delineates certain limitations on the liabilities that were
    otherwise assumed by Horsehead . . . ." Paramount, 
    660 N.Y.S.2d at 723
    .
    Further support for this view comes from the other side
    of the same coin. That the parties to the AP A knew well of
    CERCLA, and thus could have dealt with it by name in the
    APA, is made clear by the memorandum attached to
    Schedule VIII specifically mentioning CERCLA. While the
    Trial Division of the New York Supr eme Court found the
    language in the memorandum mentioning CERCLA, and
    declaring that "[t]he former owner may not use an
    indemnification agreement to shift liability to any other
    person, but may obtain insurance against his own liability,"
    to create an ambiguity as to the parties' intent to include
    CERCLA costs within the broad indemnity pr ovision, the
    Appellate Division disagreed. "[The memorandum] merely
    makes a correct statement of the applicable law, as set
    forth in the statute. . . . Thus, this sentence[quoted in this
    paragraph, above] does not conflict with, or override, the
    clearly delineated obligations set forth in the
    indemnification clause, to which Horsehead agr eed." 
    Id. at 722-723
    .
    21
    In sum, we are satisfied that the broad indemnification
    provision here includes CERCLA contribution claims.
    Therefore, for collateral estoppel purposes the issue
    litigated in the New York state courts is identical to the
    issue that was before the District Court. For the District
    Court to have concluded otherwise would thwart
    Paramount's right to indemnification for CERCLA costs
    established in the first action in the New Y ork state courts.
    (3) Full and Fair Opportunity to Litigate
    Under New York law, the doctrine of collateral estoppel
    applies to preclude relitigation of an issue where it is found
    that the litigant against whom preclusion is sought in the
    current proceeding had a full and fair opportunity to litigate
    the issue in the prior proceeding. See Gilberg v. Barbieri, 
    53 N.Y.2d 285
    , 291 (1981). "The party attempting to defeat the
    application of collateral estoppel has the bur den of
    establishing the absence of a full and fair opportunity to
    litigate the issue in the prior action." In r e Juan C. v.
    Cortines, 
    679 N.E.2d 1061
    , 1065 (N.Y. 1997).
    As already noted, Horsehead has fully litigated the
    interpretation of the indemnity clause in the New York trial
    and appellate courts. Even though this judgment may later
    be overturned during the proper course of appellate review
    of damages, New York law does not prohibit the application
    of collateral estoppel. While we acknowledge that the courts
    of New York have refused to give pr eclusive effect to an
    interlocutory order, see, e.g., Morley v. Quinones, 
    208 A.D.2d 813
     (N.Y. App. Div. 1994), this line of decisions did
    not confront the situation where the or der was reviewed by
    at least one appellate court. The case befor e us more
    closely resembles a pending appeal wher e finality can be
    found than an interlocutory order in which the parties had
    no opportunity to file an appeal.
    * * * * *
    Accordingly, we conclude that all three r equisite elements
    of New York collateral estoppel law exist-- finality, identical
    issues, and a full and fair opportunity to litigate-- and we
    affirm the decision of the District Court on this issue.
    22
    B. Rule 60(b)(5)
    Horsehead also argues that the District Court erred by
    proactively invoking Rule 60(b)(5) of the Federal Rules of
    Civil Procedure to shield its decision-making, suggesting
    that if its decision were wrong, it could easily be reopened.
    Rule 60(b)(5) provides:
    On motion and upon such terms as are just, the court
    may relieve a party . . . from a final judgment, order,
    or proceeding for the following reasons: (5) the
    judgment has been satisfied, released, or discharged,
    or a prior judgment upon which it is based has been
    reversed or otherwise vacated, or it is no longer
    equitable that the judgment should have prospective
    application.
    Fed. R. Civ. P. 60(b)(5).
    We agree with Horsehead that this Rule should not be
    relied on by district courts when facing difficult decisions.
    However, the District Court in this case did no such thing.
    Analyzing the case before it under New Y ork law, the
    District Court found adequate grounds to give preclusive
    effect to the New York appellate court's judgment. Its
    reference to Rule 60(b)(5) was to note that the Rule
    specifically contemplates relief wher e a judgment given
    preclusive effect was subsequently r eversed, the very
    situation complained of by Horsehead. The District Court
    did not misuse Rule 60(b)(5), and we are not persuaded by
    Horsehead's argument on this point.
    IV. Conclusion
    For the reasons stated, we affirm the District Court's
    entry of summary judgment in favor of Paramount based on
    the preclusive effect of the New Y ork Supreme Court,
    Appellate Division, decision in Paramount Communications,
    Inc. v. Horsehead Industries, Inc., 660 N.Y .S.2d 718 (App.
    Div. 1997).
    23
    A True Copy:
    Teste:
    Clerk of the United States Court of Appeals
    for the Third Circuit
    24
    

Document Info

Docket Number: 99-3865

Filed Date: 7/17/2001

Precedential Status: Precedential

Modified Date: 10/13/2015

Authorities (27)

In Re Rosemary BROWN, Debtor. FIRST JERSEY NATIONAL BANK v. ... , 951 F.2d 564 ( 1991 )

hatco-corporation-v-wr-grace-co-conn-a-corporation-of-the-state-of , 59 F.3d 400 ( 1995 )

Lummus Company v. Commonwealth Oil Refining Company, Inc., ... , 297 F.2d 80 ( 1962 )

commander-oil-corporation-v-advance-food-service-equipment-slater , 991 F.2d 49 ( 1993 )

olin-corporation-plaintiff-counter-claim-defendant-appellee-v , 5 F.3d 10 ( 1993 )

International Klafter Company, Inc., International ... , 869 F.2d 96 ( 1989 )

Beazer East, Inc. v. The Mead Corporation , 34 F.3d 206 ( 1994 )

Nos. 95-5067, 95-5078 , 72 F.3d 385 ( 1995 )

Olga Zdanok v. The Glidden Company, Durkee Famous Foods ... , 327 F.2d 944 ( 1964 )

Smithkline Beecham Corporation v. Rohm and Haas Company v. ... , 89 F.3d 154 ( 1996 )

Dockets Nos. 98-7269, 98-7270 , 146 F.3d 99 ( 1998 )

infocomp-inc-v-electra-products-inc-electra-font-technologies-inc , 109 F.3d 902 ( 1997 )

metromedia-company-v-william-d-fugazy-travelco-inc-fugazy , 983 F.2d 350 ( 1992 )

koppers-company-inc-v-the-aetna-casualty-and-surety-company-zurich , 98 F.3d 1440 ( 1996 )

Gilberg v. Barbieri , 53 N.Y.2d 285 ( 1981 )

Morley v. Quinones , 617 N.Y.S.2d 841 ( 1994 )

Paramount Communications, Inc. v. Horsehead Industries, Inc. , 660 N.Y.S.2d 718 ( 1997 )

Gnb Battery Technologies, Incorporated, Formerly Known as ... , 65 F.3d 615 ( 1995 )

kerr-mcgee-chemical-corporation-a-delaware-corporation-v-lefton-iron , 14 F.3d 321 ( 1994 )

65-fair-emplpraccas-bna-828-65-empl-prac-dec-p-43247-john-p , 32 F.3d 768 ( 1994 )

View All Authorities »