Gito, Inc. v. Axis Architecture ( 2021 )


Menu:
  • J-A25031-21
    
    2021 PA Super 241
    GITO, INC., D/B/A/ NELLO                   :   IN THE SUPERIOR COURT OF
    CONSTRUCTION, AS ASSIGNEE OF               :        PENNSYLVANIA
    THE CLAIMS OF THE GREATER                  :
    LATROBE SCHOOL DISTRICT                    :
    :
    Appellants              :
    :
    :
    v.                             :   No. 225 WDA 2021
    :
    :
    AXIS ARCHITECTURE, P.C.                    :
    Appeal from the Order Entered January 26, 2021
    In the Court of Common Pleas of Westmoreland County Civil Division at
    No(s): NO. 1706 of 2020
    BEFORE:      KUNSELMAN, J., KING, J., and COLINS, J.*
    OPINION BY COLINS, J.:                         FILED: December 10, 2021
    Gito, Inc., d/b/a/ Nello Construction (Nello), as assignee of the claims
    of the Greater Latrobe School District (School District), appeals from an order
    of the Court of Common Pleas of Westmoreland County (the trial court)
    sustaining preliminary objections in a breach of contract damages action that
    it brought against Axis Architecture, P.C. (Architect) and dismissing the action
    on the ground that an anti-assignment clause in the contract between School
    District and Architect barred assignment of claims for damages for breach of
    that contract. For the reasons set forth below, we reverse.
    ____________________________________________
    *   Retired Senior Judge assigned to the Superior Court.
    J-A25031-21
    This action arises out of contracts entered into by School District for the
    construction of an elementary school (the project). Architect provided design
    and architectural services for the project pursuant to a contract that it and
    School District entered into on October 1, 2015. Complaint ¶5 & Ex. A. The
    contract between School District and Architect contained the following
    provision:
    [School District] and Architect, respectively, bind themselves,
    their partners, successors, assigns and legal representatives to
    the other party to this Agreement and to the partners, successors,
    assigns and legal representatives of such other party with respect
    to all covenants of this Agreement. Neither [School District]
    nor the Architect shall assign this Agreement without the
    written consent of the other, except that [School District]
    may assign this Agreement to an institutional lender
    providing financing for the Project. In such event, the lender
    shall assume [School District’s] rights and obligations under this
    Agreement. The Architect shall execute all consents reasonably
    required to facilitate such assignment.
    
    Id.
     Ex. A at 11 Article 9.5 (emphasis added). Nello was the general trades
    prime construction contractor for the project under a March 2017 contract with
    School District.   Complaint ¶14; Architect’s Preliminary Objections ¶7;
    Plaintiff’s Response to Architect’s Preliminary Objections ¶7.
    Delays occurred during the construction, and the project, which was to
    be substantially completed by August 3, 2018, was not substantially
    completed until November 28, 2018.           Complaint ¶¶9, 13, 20, 23-24;
    Architect’s Preliminary Objections ¶8; Plaintiff’s Response to Architect’s
    Preliminary Objections ¶8.    Nello in February 2019 initiated an arbitration
    against School District in which it claimed that School District owed it over
    -2-
    J-A25031-21
    $1.5 million for work that it performed on the project and additional costs
    caused by project delays.     Architect’s Preliminary Objections ¶9; Plaintiff’s
    Response to Architect’s Preliminary Objections ¶9. School District contested
    Nello’s claims against it and asserted a counterclaim for liquidated damages
    and other damages caused by the delayed completion of the project.
    Architect’s Preliminary Objections ¶10; Plaintiff’s Response to Architect’s
    Preliminary Objections ¶10.
    In February 2020, Nello and School District entered into a settlement
    under which School District paid Nello $831,000 and assigned Nello all of
    School District’s claims against Architect and the project’s construction
    manager for losses sustained by School District due to the delay in the
    completion of the project.    Complaint ¶¶6, 29 & Ex. B.       This settlement
    agreement provided that Nello would bear all costs of prosecuting the assigned
    claims, including attorney fees and expert fees, and that Nello would retain
    85% of any settlement of the assigned claims and pay 15% of any such
    settlement to School District without any reduction for attorney fees or other
    costs of prosecuting the assigned claims. 
    Id.
     Ex. B.
    On April 14, 2020, Nello as School District’s assignee brought this breach
    of contract action against Architect seeking to recover damages that School
    District suffered as a result of Architect’s design and construction documents
    and Architect’s coordination and management of the project. On April 24,
    2020, Architect filed preliminary objections to Nello’s complaint that included
    -3-
    J-A25031-21
    an objection that Nello lacked standing to bring suit as School District’s
    assignee because Architect did not give any written consent to School District’s
    assignment of its claims and the assignment was therefore prohibited by the
    contract between School District and Architect. On January 26, 2021, the trial
    court sustained this preliminary objection and dismissed the action with
    prejudice on the ground that the anti-assignment provision in the contract
    between School District and Architect invalidated School District’s assignment
    of its damages claims to Nello.           Trial Court Order, 1/26/21; Trial Court
    Opinion, 3/31/21.1 This timely appeal followed.
    Appellant presents the following single issue for our review:
    Whether the Trial Court committed an error of law by holding that
    the language of Article 9.5 of the Contract prohibits another party
    from prosecuting the Greater Latrobe School District’s claims.
    Appellant’s Brief at 4. This is a question of law as to which our review is
    plenary and de novo.              Hospital & Healthsystem Association of
    Pennsylvania v. Department of Public Welfare, 
    888 A.2d 601
    , 607 n.12
    (Pa. 2005) (whether preliminary objections were properly sustained is a
    question of law subject to plenary, de novo review); Rosiecki v. Rosiecki,
    
    231 A.3d 928
    , 933 (Pa. Super. 2020) (contract interpretation is a question of
    law over which this Court’s review is plenary and de novo).
    ____________________________________________
    1 The trial court overruled Architect’s other preliminary objections as moot.
    Trial Court Order, 1/26/21, at 3.
    -4-
    J-A25031-21
    The issue in this appeal is a matter of first impression, as there is no
    Pennsylvania appellate precedent addressing whether an anti-assignment
    clause in a non-insurance contract that merely provides that neither party
    shall assign the contract or agreement or rights thereunder bars assignment
    of a post-performance claim for damages for breach of the contract.
    Two decisions of our Supreme Court from the 1930s and 1940s involving
    construction contracts that had anti-assignment clauses, Nolan v. J. & M.
    Doyle Co., 
    13 A.2d 59
     (Pa. 1940) and Concrete Form Co. v. W. T. Grange
    Const. Co., 
    181 A. 589
     (Pa. 1935), have held or stated that an assignment
    of rights under a contract that prohibits assignment is void. Neither of those
    cases, however, involved application of a general prohibition on assignment
    of the contract or assignment of the agreement to an assignment of a post-
    performance claim.
    In Nolan, the rights assigned in the parties’ agreement included the
    assignor’s performance of services under the contract and the assignment was
    made before the contract work was performed. 13 A.2d at 60-61. In addition,
    the Court’s statement concerning the effect of an anti-assignment clause was
    not part of its holding, as the defense based on the anti-assignment clause
    was in fact rejected because the defendant was the assignor and was not the
    party whose consent to assignment was required. Id. at 63.
    In Concrete Form Co., the Court held that an anti-assignment clause
    in a construction contract barred assignment of the right to payment after the
    -5-
    J-A25031-21
    construction was complete. The anti-assignment clause before the Court in
    Concrete Form Co., however, did not merely prohibit assignment of the
    contract or agreement.         Rather, it specifically provided that the assignor
    “would not ‘sub-let any portion of the work of this contract or * * *
    hypothecate, pledge or assign any payments thereunder except by and
    in accordance with the consent of [the] contractor.’” 181 A. at 589 (emphasis
    added) (brackets and ellipses in original). Here, the anti-assignment provision
    prohibits only assignment of “this Agreement” and does not reference
    payments, claims for damages, or any post-performance claims. Complaint
    Ex. A at 11, Article 9.5.2
    ____________________________________________
    2 The cases other than Nolan and Concrete Form Co. on which the trial court
    based its ruling or that Architect contends show that Pennsylvania law
    invalidates this assignment provide even less authority on the issue before us.
    In Pennsylvania Co. for Insurances on Lives & Granting Annuities v.
    Lebanon Building & Loan Ass’n, 
    10 A.2d 418
     (Pa. 1940), the Supreme
    Court held that there was no provision in the parties’ contract prohibiting
    assignment and the language considered by the Court, which it held was not
    part of the contract, expressly prohibited assignment of the specific right that
    was assigned. 
    Id.
     at 419 & n.2. The ruling in Fran & John's Doylestown
    Auto Center, Inc. v. Allstate Insurance Co., 
    638 A.2d 1023
     (Pa. Super.
    1994) that the assignment was invalid was specifically rejected by our
    Supreme Court in Egger v. Gulf Insurance Co., 
    903 A.2d 1219
     (Pa. 2006)
    and is therefore not good law. CGU Life Insurance Co. of America v.
    Metropolitan Mortgage & Securities Co., 
    131 F. Supp. 2d 670
     (E.D. Pa.
    2001) and In re Greenly, 
    481 B.R. 299
     (Bkcy. E.D.Pa. 2012) are federal court
    decisions that, like Concrete Form Co., involved contractual language that
    explicity prohibited assignment of the particular right that was assigned, not
    language that merely prohibited assignment of the contract or the agreement.
    CGU Life Insurance Co. of America, 
    131 F. Supp. 2d at 673
    ; Greenly, 481
    B.R. at 304, 307. Not only is Amico v. Radius Communications, 
    2001 WL 1807391
     (C.P. Phila. Co. Oct. 29, 2001) a trial court decision not binding on
    (Footnote Continued Next Page)
    -6-
    J-A25031-21
    More recent decisions of our Supreme Court and this Court have rejected
    contentions that anti-assignment clauses bar assignment of rights to payment
    and claims for damages under insurance contracts.           In Egger v. Gulf
    Insurance Co., 
    903 A.2d 1219
     (Pa. 2006), the Supreme Court held that an
    anti-assignment clause in an insurance policy that prohibits assignment of
    “rights and duties under this policy” without the insurer’s written consent does
    not bar post-loss assignment of claims for payment of insurance coverage
    because a post-loss assignment does not alter the risk that the insurer agreed
    to insure. Id. at 1220, 1222-29. In Chiropractic Nutritional Associates,
    Inc. v. Empire Blue Cross & Blue Shield, 
    669 A.2d 975
     (Pa. Super. 1995),
    this Court held that an anti-assignment clause in a group medical insurance
    policy providing that “[t]he right of a Member to receive payment is not
    assignable” did not bar assignment of a cause of action for failure to pay
    benefits and prosecution of the claim by the assignee. 
    Id. at 982-84
    . Neither
    of these decisions resolves the question before us, however, because the
    Court in Egger based its ruling not only on the purpose of the anti-assignment
    clause, but also on the conclusion that an insurance policy prohibition of
    assignment of post-loss claims is void as against public policy and
    Chiropractic Nutritional Associates, Inc. was decided under federal law,
    not Pennsylvania law.           Egger, 903 A.2d at 1224-25; Chiropractic
    ____________________________________________
    this Court, but the court in that case held that it was unclear that there was
    any assignment. 
    2001 WL 1807191
     at *7 n.9.
    -7-
    J-A25031-21
    Nutritional Associates, Inc., 
    669 A.2d at 978-80
    . Because our case law
    has not addressed the issue here, we look to authorities outside our
    Commonwealth for their persuasive value. Newell v. Montana West, Inc.,
    
    154 A.3d 819
    , 823 & n.6 (Pa. Super. 2017).
    Courts throughout the country have repeatedly held that anti-
    assignment clauses that prohibit assignment of the contract or agreement or
    prohibit assignment of rights or interests under the contract or agreement do
    not bar the assignment of post-contract performance claims for damages.
    See, e.g., Holland v. United States, 
    74 Fed. Cl. 225
    , 255-58 (2006)
    (provision that “this Agreement may not be assigned to any party nor may
    any rights or obligations under it be transferred or delegated to or vested in
    any other party, through merger, consolidation, or otherwise, without the
    prior written consent of the [FSLIC]” did not bar assignment of claim for
    breach of the agreement) (brackets in original); Missouri Bank & Trust Co.
    v. Gas–Mart Development Co., 
    130 P.3d 128
    , 134 (Kan. App. 2006)
    (contract provision that “[t]he parties hereto agree not to assign this Contract
    without the prior written consent of the other party hereto” did not bar
    assignment of breach of contract and other damages claims under the
    contract) (emphasis omitted); Folgers Architects Ltd. v. Kerns, 
    633 N.W.2d 114
    , 125-27 (Neb. 2001) (anti-assignment clause that “[n]either the
    Owner nor the Architect shall assign, sublet or transfer any interest in this
    Agreement without the written consent of the other” did not bar assignment
    -8-
    J-A25031-21
    of architect’s breach of contract claims for non-payment of its fees); Korte
    Construction Co. v. Deaconess Manor Association, 
    927 S.W.2d 395
    , 400-
    03 (Mo. App. 1996) (contract provision that “[n]either party to the Contract
    shall assign the Contract or sublet it as a whole without the consent of the
    other, nor shall the Contractor assign any money due or to become due to him
    hereunder, without the previous written consent of the Owner” did not bar
    assignment of post-performance cause of action for breach of the contract)
    (emphasis omitted); Berschauer/Phillips Construction Co. v. Seattle
    School District, 
    881 P.2d 986
    , 993-94 (Wash. 1994) (anti-assignment clause
    that “[n]either the Owner nor the Architect shall assign, sublet or transfer any
    interest in this Agreement without the written consent of the other” did not
    bar owner’s post-performance assignment to general contractor of its cause
    of action against architect for breach of contract); Ford v. Robertson, 
    739 S.W.2d 3
    , 4-5 (Tenn. App. 1987) (provision in architect’s contract that
    “[n]either the Owner nor the Architect shall assign, sublet or transfer any
    interest in this Agreement without the written consent of the other” did not
    bar post-performance assignment of owner’s claim for damages for breach of
    contract); Cordis Corp. v. Sonics International, Inc., 
    427 So.2d 782
     (Fla.
    App. 1983) (contract provision that “[t]he rights of Distributor [Mexcor],
    hereunder shall not be assigned or transferred, either voluntarily or by
    operation of law, without [Sonics International’s] written consent, nor shall
    the duties of Distributor hereunder be delegated in whole or in part” and that
    -9-
    J-A25031-21
    “[a]ny such assignment, transfer or delegation shall be of no force or effect”
    did not invalidate assignment of accrued cause of action for unpaid
    commissions) (brackets in original); Fuller v. Favorite Theaters Co., 
    230 P.2d 335
    , 336 (Utah 1951) (provision that “[t]his license shall not be assigned
    by either party without the written consent of the other” did not bar
    assignment of cause of action for breach of contract).
    The courts in these jurisdictions have persuasively explained that the
    purpose of a general anti-assignment clause is to prevent a party from
    assigning its performance of the contract to a third-party without the consent
    of the other party and that assignment of a claim for damages is entirely
    different from assignment of performance and does not implicate the purpose
    of the anti-assignment clause.         See, e.g., Omicron Safety & Risk
    Technologies, Inc. v. UChicago Argonne, LLC, 
    181 F. Supp. 3d 508
    , 511
    (N.D. Ill. 2015) ( “The logic behind this rule is that it should make no difference
    to [the other party to the contract] whether [the party with whom it
    contracted] or an assignee sues to recover money allegedly owed under a fully
    performed contract”); Folgers Architects Ltd., 633 N.W.2d at 126 (“the
    intent of the provision against assignment of rights under a contract, which
    generally is to allow the parties to choose with whom they contract, is not
    affected by allowing an assignment of a right to collect damages for breach of
    contract”); Korte Construction Co., 
    927 S.W.2d at 403
     (holding that “the
    prohibition in the contract against assignment of the contract without the
    - 10 -
    J-A25031-21
    consent of the other party does not bar assignment of causes of action
    accruing from breach of the contract” because “contract rights are distinct
    from causes of action which accrue from the violation of such rights”); Ford,
    
    739 S.W.2d at 5
     (holding that “[t]he law draws a distinction between the right
    to assign performance under a contract and the right to receive damages for
    its breach” and that therefore the anti-assignment clause’s “‘any interest’
    language must be construed to mean any interest in the performance of the
    executory contract”)(emphasis in original).
    In addition, consistent with these decisions, Section 322 of the
    Restatement (Second) of Contracts states:
    (1) Unless the circumstances indicate the contrary, a
    contract term prohibiting assignment of “the contract”
    bars only the delegation to an assignee of the performance
    by the assignor of a duty or condition.
    (2) A contract term prohibiting assignment of rights under the
    contract, unless a different intention is manifested,
    (a) does not forbid assignment of a right to damages for breach
    of the whole contract or a right arising out of the assignor’s due
    performance of his entire obligation;
    (b) gives the obligor a right to damages for breach of the terms
    forbidding assignment but does not render the assignment
    ineffective;
    (c) is for the benefit of the obligor, and does not prevent the
    assignee from acquiring rights against the assignor or the obligor
    from discharging his duty as if there were no such prohibition.
    - 11 -
    J-A25031-21
    Restatement (Second) of Contracts § 322 (emphasis added).3
    We find the above decisions and the Restatement (Second) of Contracts
    § 322 persuasive and hold that under Pennsylvania law a contractual clause
    that prohibits only assignment of the contract or assignment of the agreement
    does not bar assignment of a post-performance claim for damages.
    The trial court therefore erred in finding that the assignment here was
    barred by the anti-assignment clause in the contract between School District
    and Architect. That anti-assignment clause prohibited only assignment of “this
    Agreement” and the School District’s assignment to Nello did not assign or
    delegate any of School District’s duties or performance, was made after the
    contract was fully performed, and was an assignment of the right to damages
    for Architect’s breach of contract.
    There is, moreover, no other language in the Architect’s contract with
    School District that shows an intent to prohibit assignment of claims for
    damages.      The language permitting assignment to an institutional lender
    refers to assignment by School District of its obligations under the contract
    and therefore is consistent with an intent to bar only delegation of the
    assignor’s performance. Complaint Ex. A at 11, Article 9.5 (providing that if
    School District assigns the contract to an institutional lender, “the lender shall
    ____________________________________________
    3 Architect is correct that Pennsylvania courts have not previously adopted
    (Second) of Contracts § 322. Our courts, however, have also not rejected it.
    Chiropractic Nutritional Associates, Inc. briefly referred to Section 322,
    but did so in interpreting federal law. 
    669 A.2d at
    980 n.7.
    - 12 -
    J-A25031-21
    assume [School District’s] rights and obligations under this Agreement”). The
    language of Article 9.7 of the contract providing that “[n]othing contained in
    this Agreement shall create a contractual relationship with or a cause of action
    in favor of a third party against either [School District] or Architect,” 
    id.
     Article
    9.7, shows an intent to restrict claims by third parties asserting their own
    rights, not an intent to limit Architect’s or School District’s assignment of
    causes of action they may have against each other under the Contract. The
    complaint in this action asserts only School District’s claims against Architect,
    not Nello’s claim for its own damages.
    Architect argues that the anti-assignment clause here must be held to
    bar assignment of School District’s breach of contract claim to prevent
    duplicative recovery because Nello has filed a separate action against Architect
    in its own right.   Appellee’s Brief at 15.     The damages sought in the two
    actions, however, are not the same. Nello’s claim under the assignment is for
    damages suffered by School District, not for the damages that it suffered, and
    the damages that it seeks in the other action are its own damages. While
    some damages claims could overlap, the risk of duplicative recovery is not
    created by the assignment, as that risk would exist if School District brought
    its own action for damages rather than assigning the cause of action.
    Prevention of duplicative recovery is more appropriately achieved by
    consolidation or coordination of the actions, which Architect had apparently
    - 13 -
    J-A25031-21
    sought before its preliminary objection was sustained. See Plaintiff’s Brief in
    Opposition to Architect’s Preliminary Objections at 8 n.3.
    Because the trial court erred in concluding that the anti-assignment
    clause in the contract between School District and Architect barred School
    District’s assignment of its breach of contract claim to Nello, we reverse the
    trial court’s order sustaining Architect’s preliminary objection and remand this
    case for further proceedings.
    Order reversed. Case remanded for further proceedings.        Jurisdiction
    relinquished.
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 12/10/2021
    - 14 -