Manley Architecture Group, L.L.C. v. Santanello , 114 N.E.3d 697 ( 2018 )


Menu:
  • [Cite as Manley Architecture Group, L.L.C. v. Santanello, 2018-Ohio-2200.]
    IN THE COURT OF APPEALS OF OHIO
    TENTH APPELLATE DISTRICT
    Manley Architecture Group, LLC,                     :
    Plaintiff-Appellee/                 :
    Cross-Appellant,                                             No. 16AP-825
    v.                                                  :                   (C.P.C. No. 15CV-4514)
    Steven A. Santanello,                               :               (REGULAR CALENDAR)
    Defendant-Appellant/                :
    Cross-Appellee.
    :
    D E C I S I O N
    Rendered on June 7, 2018
    On brief: Olsheski Law Co., LPA, and Jessica L. Olsheski, for
    appellee/cross-appellant. Argued: Jessica L. Olsheski.
    On brief: Kemp, Schaeffer & Rowe Co., LPA, Michael N.
    Schaeffer, and Richard G. Murray, II, for appellant/cross-
    appellee. Argued: Michael N. Schaeffer.
    APPEAL from the Franklin County Court of Common Pleas
    HORTON, J.
    {¶ 1} Manley Architecture Group, LLC ("MAG"), brought a breach of contract
    action against Dr. Steven Santanello in the Franklin County Court of Common Pleas seeking
    damages for unpaid architectural and construction fees. Santanello counterclaimed,
    alleging that MAG's failure to properly supervise and manage the construction breached
    the parties' agreement and violated R.C. 1345.01 et seq., the Ohio Consumer Sales Practices
    Act ("OCSPA"). After a bench trial, the trial court found that both parties had breached the
    agreement and dismissed the OCSPA claim. The trial court concluded that Santanello owed
    MAG $224,270.68 and offset that amount by $160,000 that MAG owed to Santanello,
    No. 16AP-825                                                                               2
    resulting in a net award of $64,270.68 due to MAG. The parties cross-appealed. For the
    reasons set forth below, we affirm in part and reverse in part.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    {¶ 2} On January 22, 2004, MAG and Santanello entered into a written contract
    governing the architectural design and construction of a 5,800 square foot home, as well as
    a "stable with riding arena, sitework, pond, tennis court and outdoor pool," for an estimated
    total cost of $1.6 million. Patrick Manley, MAG's owner and architect, sent the agreement
    to Santanello, along with a cover letter that explained the cost saving option of having MAG
    operate as the "construction manager" instead of hiring a general contractor:
    The enclosed information is representative of our residential
    proposals, and includes all the services normally required to
    properly complete the project. As we discussed, a typical
    architectural and engineering fee for a luxury home seems to
    fall in the range of 10-15% of the cost of construction. This is
    for a full set of services and would include managing the
    bidding and site visits during construction. My quotation for
    your home is well under that amount.
    Regarding the construction management portion, we would
    work directly for you bidding out to the subcontractors and
    suppliers on your behalf, and managing the entire
    construction process. The advantage to this is we can typically
    save you approximately 10% to 12% over the cost of a general
    contractor. Added benefits are we have more involvement in
    the details from start to finish, you have access to all of the
    subcontractor bids and we can make sure the construction is
    performed properly.
    {¶ 3} Several provisions of the contract detailed the option of having MAG operate
    as the construction manager. The architect's "scope of services" included the following two
    provisions:
    Bidding Phase (Not required under Construction
    Management contract)
    Provide Owner with a list of bidders who perform this
    type of work.
    Meet with prospective bidders to explain design.
    Answer questions from bidders.
    Distribute drawings and other related information.
    Construction Administration Phase (Not required under
    Construction Management contract)
    No. 16AP-825                                                                                3
    Phone support for owner and contractor.
    Assist in resolving on-site problems, conflicts and
    unknown conditions.
    As-needed site visits during construction.
    Review shop drawings.
    Review contractor's payment requests.
    {¶ 4} The architect's maximum fee was capped at 8.0 percent to 9.5 percent of the
    total construction cost. The "bidding phase" and "construction administration phase"
    services were included, and were not to exceed 0.5 percent and 1.5 percent of the total
    construction cost, respectively. However, if the "construction management" option were
    chosen, those services were deleted from the architect's fee, reducing it to a maximum of
    6.0 percent to 7.5 percent of the total construction fee. Instead, 10 percent of the total
    construction cost was imposed for construction management:
    Construction Management Fee: 10% of Construction
    Cost*
    *Typical mark-up on material, equipment and labor, by
    custom remodeling homebuilders acting as General
    Contractor, normally runs between 20% to 25% of
    construction cost. Net savings on project, using construction
    management approach should save 10%-15% overall.
    {¶ 5} The agreement also contained a provision governing payment:
    Progress payments shall be made to the architect at the
    completion of each phase, or for services rendered at the end
    of each month, whichever occurs first. * * * In the unlikely
    event either party shall breach this agreement, the party at
    fault shall be responsible for all attorney's fees and expenses
    of the other party. Invoices shall be due and payable 30 days
    from the date of the invoice. Finance charges after the due
    date shall be 1 ½% per month (18% per annum).
    (Mar. 1, 2016 Mot. of Def. for Partial Summ. Jgmt.; Aff. of Steven A. Santanello, Ex. A.)
    {¶ 6} During construction, problems arose with the barn roof leaking and the water
    height in the pond, and Santanello stopped paying invoices submitted by MAG.
    {¶ 7} A number of years after construction was finished, MAG sued Santanello for
    the unpaid fees. The first complaint that MAG filed stated causes of action for breach of
    contract, quantum meruit and unjust enrichment, but the latter two claims were time
    barred and omitted from an amended complaint. (May 28, 2015 Compl.; June 24, 2015 Am.
    No. 16AP-825                                                                                 4
    Compl.) Santanello filed counterclaims for breach of contract, alleging that MAG had
    breached its obligation to properly oversee the construction of the pond and barn. (July 13,
    2015 Answer.)
    {¶ 8} The matter proceeded to a bench trial held on August 22-25, 2016, after
    which the trial court issued a decision stating findings of fact and conclusions of law. In its
    decision, the trial court stated that the term "construction management" in the parties'
    agreement was ambiguous because "the [parties'] exact expectations" regarding its scope
    were "only loosely defined." (Nov. 18, 2016 Decision at 2.) Thus, the trial court considered
    both the contents of the cover letter and the language of the parties' agreement to interpret
    the term. 
    Id. The trial
    court emphasized MAG's statement in the cover letter that, as
    construction manager, it would be able to "make sure the construction is performed
    properly." (Decision at 3.) After reviewing several cases construing the term, the trial court
    concluded:
    Considering all the evidence, including the credibility of the
    witnesses, this court finds that the construction management
    role these parties mutually agreed upon did not make Manley
    Architecture Group an insurer of the work of trade contractors
    such as the contractor who erected the barn and leaking roof.
    Manley Architecture Group did not obligate itself to, in
    essence, warrant or guarantee that all work by others would
    be "performed properly." Fairly read, the written contract
    documents made that clear to Dr. Santanello. Moreover,
    privity of contract ran between Dr. Santanello and individual
    contractors, even though Mr. Manley made some of the
    contracts as "agent" for Dr. Santanello. Because each
    contractor hired by Dr. Santanello remained responsible for
    their own performance, and any deficiencies in the work,
    ultimate responsibility for enforcing that work rested on the
    owner not Manley Architecture Group.
    Nevertheless, because Manley Architecture Group assumed
    the overarching role of "construction manager," the parties
    plainly did contemplate that Manley would actively monitor
    ongoing work. * * * When problems arose, these parties
    agreed that Manley Architecture Group would alert Dr.
    Santanello in a timely manner. Practically speaking, if a
    contractor was not performing work as called for in the plans
    and specifications properl, Dr. Santanello had a right to expect
    notice from Manley so that the doctor could pursue
    appropriate remedial action with the contractor in question.
    No. 16AP-825                                                                                5
    (Emphasis sic.) (Decision at 4.)
    {¶ 9} After setting forth this interpretation, the trial court made the following
    rulings on the parties' claims. First, the trial court addressed MAG's claims for unpaid
    services under the parties' agreement. The trial court noted that the parties had stipulated
    that MAG had paid $55,577.68 to vendors for which it had not been reimbursed. The trial
    court found that an additional $27,179 in "architect design fees" for a racquetball court, a
    gazebo, and "construction management fees" were unpaid. (Decision at 5.) This amounted
    to "$82,756.68 for unpaid but earned professional fees and unreimbursed out-of-pocket
    expenses reasonably incurred" by MAG. 
    Id. After calculating
    the interest rate for finance
    charges stated in the parties' agreement, the trial court concluded that MAG was owed a
    $141,514, for a total of $224,270.68. (Decision at 5 & 7.)
    {¶ 10} Second, the trial court found that MAG did not breach its obligation when
    building the pond because it "was never mutually intended by the parties to be leak-proof,
    or to always maintain an essentially static water level as Dr. Santanello now desires."
    (Decision at 6.)
    {¶ 11} Third, the trial court ruled on Santanello's counterclaim concerning the
    construction of the barn roof. After receiving an estimate to construct the barn and its roof
    for $265,000, Santanello hired Bill Williams to perform the construction without a written
    contract. The trial court found that MAG's architectural plans for the barn and roof were
    adequate. Williams used a proprietary manufactured barn roof system when constructing
    the barn. After installation, the roof immediately began to leak through a long valley in the
    roof and into an apartment in the upper level of the barn. In addition, flashing was installed
    incorrectly and vents specified in the drawings were missing.
    {¶ 12} The trial court noted that Andy Raile, an expert witness who had examined
    the roof, testified that it was "not repairable and cannot be made fully watertight without
    complete removal and replacement." (Decision at 7-8.) The trial court made the following
    findings and rulings concerning Manley's performance and MAG's liability for the roof:
    Initial installation of the barn roof occurred in August-
    September 2004. Mr. Manley testified that this roof was
    installed very, very quickly. Mr. Manley further acknowledged
    that getting up on a high roof like this one was not one of his
    favorite things to do. Perhaps due to the speed of initial
    No. 16AP-825                                                                   6
    installation, or the fact that getting up on a high roof made Mr.
    Manley uncomfortable, Manley Architecture Group did not
    closely inspect and monitor barn roof installation. Only after
    leaks began to appear did Manley closely examine the roof
    work, which is now conceded to have been deficiently done by
    Williams' crew.
    Although Dr. Santanello was his own general contractor, and
    although Manley Architecture Group had recommended
    against even hiring Williams for the work because they
    thought his proposed contract price was too low, the court
    finds by a preponderance of the evidence that Manley
    Architecture Group itself fell short of its construction
    management responsibilities in monitoring installation of the
    barn roof. Mr. Manley did not perform (or have performed by
    some other person more comfortable working at height) any
    contemporaneous close-hand inspection as the roof was
    installed. Once the roof was completed and closed up, even
    Mr. Manley conceded that it was exceedingly difficult to go
    back and figure out why there were leaks, or precisely identify
    where they were located. More attention ought to have been
    given to these practicalities by Manley Architecture Group as
    the roof work was still being performed, because serious
    discrepancies in the roof would have been readily apparent to
    a trained observer.
    The preponderance of evidence established that, in 2006
    dollars, complete replacement of the barn roof would have
    cost roughly $120,000. With inflation, that figure is roughly
    $160,000 in 2016 prices. Recognizing Manley Architecture
    Group was not a guarantor of work by Williams, it
    nevertheless had construction management obligations that
    were not met. The lack of thorough, timely inspection by
    Manley allowed Williams' substandard work to escape
    detection when, had work been checked, correction of
    deficient work would have been much easier and less costly.
    "To recover upon a breach of contract claim, a plaintiff must
    prove 'the existence of a contract, performance by the
    plaintiff, breach by the defendant, and damage or loss to the
    plaintiff.' " Jarupan v. Hanna, 
    173 Ohio App. 3d 284
    , 2007-
    Ohio-5081, 
    878 N.E.2d 66
    , (10th Dist.) at ¶ 18 (quoting Powell
    v. Grant Med. Ctr., 
    148 Ohio App. 3d 1
    , 10, 2002-Ohio-443,
    
    771 N.E.2d 874
    ) (additional citations omitted.) "In order to
    prove a breach by the defendant, a plaintiff must show that
    the defendant 'did not perform one or more of the terms of a
    No. 16AP-825                                                                             7
    contract.' " Jarupan at ¶ 18 (quoting Little Eagle Props. v.
    Ryan, 10th Dist. No. 03AP-923, 2004-Ohio-3830, ¶ 15).
    (Decision at 8-9.)
    {¶ 13} Accordingly, the trial court awarded Santanello $160,000 in damages for the
    breach based on the defective roof. After offsetting that amount against the damages award
    to MAG on its breach of contract claim, the trial court concluded that a net of $64,270.68
    was due to MAG.
    {¶ 14} Fourth, the trial court dismissed Santanello's claim under the OCSPA.
    {¶ 15} The parties filed cross-appeals concerning the trial court's award of damages
    to MAG under the agreement and the damages awarded for the barn roof. The rulings
    concerning the pond and MAG's OCSPA claim were not appealed. Santanello asserts the
    following assignments of error:
    I. The trial court incorrectly applied the set off in 2016 as the
    damages giving rise to the set off occurred when the roof was
    installed in 2004. The court erred in not concluding that the
    set off should occur on the first date that Appellant
    [Santanello] suffered damage (2004) when the barn roof first
    began to leak.
    II. The trial court erred in its finding that defendant owed
    plaintiff $55,557.68 for reimbursement of monies advanced
    by plaintiff/appellee because defendant/appellant was not
    contractually obligated to pay such sums under the contract
    between appellant and appellee and the court indicated that it
    was not making the damage award based upon [claims of]
    quantum meruit or unjust enrichment.
    {¶ 16} MAG asserts the following cross-assignments of error:
    A. The court erred when it allowed a set-off for the barn roof;
    any deficiency in the installation should have been borne by
    the roofing subcontractor and the general contractor,
    Defendant Santanello, not Mr. Manley.
    B. The court erred when it calculated the barn roof set-off at
    $160,000. There was testimony that the amount of the set off
    should have been significantly less because the entire roof did
    not need to be replaced.
    C. The court erred when it determined that the amount of the
    set-off was $160,000 because Defendant Santanello failed to
    No. 16AP-825                                                                                 8
    mitigate his damages and seek redress with the barn roof
    contractor; instead he used the barn roof for ten years without
    making any repairs and only raised the issue of a complete
    barn roof replacement when Mr. Manley brought claims for
    breach of contract.
    D. The court erred when it did not allow a reduction in the
    amount of the set-off for the use and enjoyment of the roof by
    Dr. Santanello.
    E. The court erred when it found that there should be a set-off
    because the evidence showed that Defendant Santanello
    breached the contract first, thereby relieving Plaintiff of any
    contractual obligation whatsoever.
    {¶ 17} For the reasons discussed below, we sustain Santanello's second assignment
    of error and MAG's first cross-assignment of error. All other assignments of error are
    overruled as moot.
    II. STANDARD OF REVIEW
    {¶ 18} A de novo standard of review applies to matters of law, including the
    interpretation and construction of written contracts. Long Beach Assn., Inc. v. Jones, 
    82 Ohio St. 3d 574
    , 576 (1998). However, a manifest weight of the evidence standard applies to
    appellate review of a judgment entered after a bench trial. App.R. 12(C). Under this
    standard, a reviewing court must be "guided by a presumption that the findings of the trier-
    of-fact were indeed correct." Seasons Coal Co., Inc. v. Cleveland, 
    10 Ohio St. 3d 77
    , 80
    (1984). " 'Judgments supported by some competent, credible evidence going to all the
    essential elements of the case will not be reversed by a reviewing court as being against the
    manifest weight of the evidence.' " 
    Id., quoting C.
    E. Morris Co. v. Foley Constr. Co., 
    54 Ohio St. 2d 279
    , 280 (1978).
    III. ANALYSIS
    {¶ 19} We first consider Santanello's second assignment of error, in which he asserts
    that the trial court erred when it ruled that he breached the parties' agreement. Santanello
    argues that the agreement did not obligate him to reimburse MAG for the $55,557.68 that
    MAG had advanced to subcontractors after he refused to pay them.
    {¶ 20} " 'A contract is generally defined as a promise, or a set of promises, actionable
    upon breach. Essential elements of a contract include an offer, acceptance, contractual
    No. 16AP-825                                                                               9
    capacity, consideration (the bargained for legal benefit and/or detriment), a manifestation
    of mutual assent and legality of object and of consideration.' " Kostelnik v. Helper, 96 Ohio
    St.3d 1, 2002-Ohio-2985, ¶ 16, quoting Perlmuter Printing Co. v. Strome, Inc., 
    436 F. Supp. 409
    , 414 (N.D.Ohio 1976). "A meeting of the minds as to the essential terms of the contract
    is a requirement to enforcing the contract." 
    Id. at ¶
    16, citing Episcopal Retirement Homes,
    Inc. v. Ohio Dept. of Indus. Relations, 
    61 Ohio St. 3d 366
    , 369 (1991). To be enforceable, a
    contract's terms "must be definite and certain." Episcopal Retirement Homes at 369, citing
    James Ward & Co. v. Wick Bros. & Co., 
    17 Ohio St. 159
    , 164 (1867).
    {¶ 21} "In construing any written instrument, the primary and paramount objective
    is to ascertain the intent of the parties. The general rule is that contracts should be
    construed so as to give effect to the intention of the parties." Aultman Hosp. Assn. v.
    Community Mut. Ins. Co., 
    46 Ohio St. 3d 51
    (1989), citing Employers' Liab. Assur. Corp. v.
    Roehm, 
    99 Ohio St. 343
    , 344 (1919), syllabus; Skivolocki v. E. Ohio Gas Co., 
    38 Ohio St. 2d 244
    , 246 (1974), paragraph one of the syllabus. Parties are free to "contract for the terms
    they want, and the 'intent of the parties is presumed to reside in the language they chose to
    use in their agreement.' " Hope Academy Broadway Campus v. White Hat Mgt., L.L.C.,
    
    145 Ohio St. 3d 29
    , 2015-Ohio-3716, ¶ 35, quoting Graham v. Drydock Coal Co., 76 Ohio
    St.3d 311, 313 (1996). "Intentions not expressed in the writing are deemed to have no
    existence and may not be shown by parol evidence." Aultman Hosp. Assn.
    {¶ 22} Here, the parties' agreement contemplated two potential roles for MAG and
    Manley. Under the first option, the project would use a general contractor, and Manley
    would perform "construction administration" duties and oversee bidding. Under the other
    option, which Santanello opted for, Manley was the project's "construction manager." With
    this option, Santanello operated as his own general contractor and enjoyed a reduction in
    certain expenses. This option deleted the "bidding" and "construction administration" fees
    and purported to save the homeowner 10 to 15 percent over the typical cost of construction
    managed by a third party general contractor. With Santanello in that role, MAG charged a
    flat 10 percent fee for Manley to perform "construction management" services.
    {¶ 23} As the trial court noted, both MAG's breach of contract claim and Santanello's
    counterclaim concern the scope of the "construction management" services under the
    agreement. The first question is whether this role authorized MAG to advance fees to
    No. 16AP-825                                                                                         10
    subcontractors after Santanello refused to pay them and then hold Santanello liable for
    those advances. It is undisputed that Santanello operated as his own general contractor. As
    the trial court stated, "privity of contract ran between Dr. Santanello and individual
    contractors," as he was the one who actually hired them. (Nov. 18, 2016 Decision at 4.)
    {¶ 24} However, our de novo review of the contract reveals no provision that
    obligated Santanello to pay MAG for fees advanced to subcontractors that Santanello had
    refused to pay. The trial court simply stated that it found "by a preponderance of the
    evidence that [Manley] was not paid the full amount due under the parties' contract," with
    no mention of what provision of the contract Santanello breached by failing to reimburse
    Manley for the $55,577 in advances to trade contractors. (Decision at 5.) The trial court
    simply referred to "unpaid but earned professional fees and unreimbursed out-of-pocket
    expenses" as the basis for the award. 
    Id. The agreement's
    description of "reimbursable
    expenses," which includes "[b]lueprints, mileage, faxes, etc. estimated at: $2,000.00"
    cannot be read to reflect an intent to include advances to subcontractors for building fees
    totaling tens of thousands of dollars.1 (Aff. of Steven A. Santanello, Ex. A.)
    {¶ 25} Finding that the "construction management" role was "only loosely defined"
    under the agreement, the trial court decided that the term was ambiguous, and decided to
    incorporate language from the cover letter into the agreement in order to define the role.
    (Nov. 18, 2016 Decision at 2.) It is acceptable, of course, to consult extrinsic evidence to
    determine the meaning of an ambiguous contract term or provision. "A court will resort to
    extrinsic evidence in its effort to give effect to the parties' intentions only where the
    language is unclear or ambiguous, or where the circumstances surrounding the agreement
    invest the language of the contract with a special meaning." Kelly v. Med. Life Ins. Co., 
    31 Ohio St. 3d 130
    , 132 (1987), citing Blosser v. Enderlin, 
    113 Ohio St. 121
    (1925). However, in
    this case, the cover letter contains no language suggesting that the parties intended to
    authorize MAG to advance fees that Santanello had refused to pay:
    Regarding the construction management portion, we would
    work directly for you bidding out to the subcontractors and
    suppliers on your behalf, and managing the entire
    construction process. The advantage to this is we can typically
    save you approximately 10% to 12% over the cost of a general
    1The unpaid amount of $27,179 earned architectural fees for the racquetball court and the gazebo are not
    in dispute on appeal.
    No. 16AP-825                                                                                   11
    contractor. Added benefits are we have more involvement in
    the details from start to finish, you have access to all of the
    subcontractor bids and we can make sure the construction is
    performed properly.
    {¶ 26} In addition to the agreement itself not providing a basis for authorizing such
    advances, Manley himself testified that when making the advances, he was not operating
    under the agreement:
    But I, in turn, in order to keep the project moving and to finish
    the project, you know, even though I had no obligation to do
    so, I paid a lot of these contractors and suppliers because I felt
    that it was unfair to them to hold money back like this on
    people who had done such a good job and really didn't have
    much more to finish. That they needed to get paid because I
    was really afraid we were going to lose these contractors and
    the project was just going to come to a grinding halt.
    (Aug. 22, 2016 Tr. Vol. I at 150.)
    {¶ 27} Manley also testified that Santanello "didn't want to pay certain things
    because certain contractors weren't done. And I thought it was withholding too much
    money." (Tr. Vol. I at 151.) Manley felt that "ultimately, [Santanello's withholding] went on
    so long and there were a couple of liens that were filed against the property." (Tr. Vol. I at
    151-52.) Manley testified that because there were "contractors that didn't want to cooperate
    because they weren't getting paid," he "made the decision on [his] own to start to pay some
    of these people just to get them back to finish the work." (Tr. Vol. I at 152.)
    {¶ 28} Manley's testimony demonstrates that he wanted the project to be completed
    and was concerned about his working relationship with the subcontractors. However, by
    creating an agreement that allowed a homeowner with no experience in construction to
    function as his own general contractor, he ran the risk that Santanello might decide to
    withhold payment to subcontractors on the project. In return, MAG was able to offer a
    contract with a reduced rate as a selling point. "It is not the responsibility or function of this
    court to rewrite the parties' contract in order to provide for a more equitable result." Hope
    Academy Broadway Campus at ¶ 37. "A contract 'does not become ambiguous by reason
    of the fact that in its operation it will work a hardship upon one of the parties thereto.' "
    Foster Wheeler Enviresponse v. Franklin Cty. Convention Facilities Auth., 
    78 Ohio St. 3d 353
    , 362 (1997), quoting Ohio Crane Co. v. Hicks, 
    110 Ohio St. 168
    , 172 (1924). "Unless
    No. 16AP-825                                                                                12
    there is 'fraud or other unlawfulness involved, courts are powerless to save a competent
    person from the effects of his own voluntary agreement.' " Hope Academy Broadway
    Campus at ¶ 37, quoting Dugan & Meyers Constr. Co. v. Ohio Dept. of Adm. Servs., 
    113 Ohio St. 3d 226
    , 2007-Ohio-1687, ¶ 29. Although Manley appears to have operated with the
    best of intentions, the agreement between him and Santanello did not give him the
    authority to unilaterally decide that Santanello had withheld "too much money" from
    subcontractors, pay them, and then sue Santanello for those advances. As the existence of
    the liens shows, a remedy existed for the dispute between Santanello and the
    subcontractors.
    {¶ 29} For the foregoing reasons, we conclude that the trial court erred when it
    construed the agreement to allow Manley or MAG the authority to advance monies to the
    subcontractors and subsequently recover those advances from Santanello. Accordingly,
    Santanello's first assignment of error is sustained, and the amount of damages awarded to
    MAG is reduced to $27,179 for the fees for "architect design" and "contract management,"
    plus prejudgment interest of 18 percent, as the contract contemplated.
    {¶ 30} We now turn to MAG's first cross-assignment of error, which asserts that the
    trial court erred by allowing a set-off in the amount of damages for the amount of a new
    barn roof, based on its determination that MAG breached its "construction management"
    responsibilities.
    {¶ 31} As an initial matter, we agree with the trial court's interpretation of the scope
    of those responsibilities. The trial court emphasized MAG's assurance in the cover letter
    accompanying the agreement that it would "make sure the construction is performed
    properly." (Nov. 18, 2016 Decision at 3.) The trial court did not construe this statement as
    a warranty or "guarantee" covering the work of the subcontractors. (Decision at 4.) MAG
    was not "an insurer of the work of trade contracts such as the contractor who erected the
    barn and leaking roof." 
    Id. Furthermore, "each
    contractor hired by Dr. Santanello remained
    responsible for their own performance, and any deficiencies in the work, ultimate
    responsibility for enforcing that work rested on the owner, not Manley Architecture Group."
    
    Id. {¶ 32}
    We also agree with the trial court's observation that when the parties agreed
    that MAG would perform "the overarching role of 'construction manager,' the parties
    No. 16AP-825                                                                                13
    plainly did contemplate that Manley would actively monitor ongoing work." (Decision at
    4.) Thus, it was MAG's responsibility to "alert Dr. Santanello in a timely manner" when
    problems arose during construction, "so that the doctor could pursue appropriate remedial
    action with the contractor in question." 
    Id. {¶ 33}
    Nevertheless, the trial court's reasonable definition of MAG's construction
    management responsibilities cannot be reconciled with its ultimate determination that
    MAG breached them. The trial court ruled that MAG breached "its construction
    management responsibilities in monitoring installation of the barn roof" and did not
    "monitor [the] barn roof installation." (Decision at 8.) Santanello testified that he knew
    about the leaking roof "soon after it was essentially completed," at which time Manley
    "worked hard at trying to figure out what the problem was." (Aug. 22, 2016 Tr. Vol. III at
    36-37.) At that point, Williams was still working on building the barn, and Manley "tried an
    attempt at once" to have Williams fix the roof. (Tr. Vol. III at 37.) Santanello testified that
    Manley then hired a different roofing company "to look at it" and make non-structural
    repairs to the roof. (Tr. Vol. III at 37-38.) Santanello's own testimony demonstrates that
    Manley performed the "construction management" responsibilities as the parties had
    intended under the agreement.
    {¶ 34} By ruling that MAG was liable to Santanello for the entire cost of replacing
    the roof, the trial court essentially made MAG a guarantor of the roof installer, in spite of
    the fact that its definition of construction management expressly stated that MAG was not
    a guarantor for the work of the subcontractors. This ruling imposed a more stringent set of
    responsibilities on MAG than the trial court's own definition required. Accordingly, we
    sustain MAG's first cross-assignment of error, reverse the trial court's ruling in favor of
    Santanello on the counterclaim for breach of contract arising from the barn roof, and vacate
    the $160,000 in damages awarded to Santanello.
    IV. CONCLUSION
    {¶ 35} Under our de novo review of the parties' agreement, the scope of MAG's
    "construction management" role did not authorize MAG to recover for advances to
    subcontractors, nor did it make MAG the guarantor of each subcontractor's work.
    Accordingly, the trial court's judgment is affirmed in part and reversed in part. The
    judgment is affirmed as to the $27,179 in unpaid architectural fees and prejudgment
    No. 16AP-825                                                                          14
    interest that Santanello has not appealed, but is reversed regarding the $55,577.68
    advanced by MAG to subcontractors and the $160,000 for the replacement of the barn roof.
    Thus, we sustain Santanello's second assignment of error and MAG's first cross-assignment
    of error, and render all other assignments of error as moot.
    Judgment affirmed in part and reversed in part.
    BROWN, P.J. and LUPER SCHUSTER, J., concur.
    _________________
    