International Union of Operating Engineers, Local Union No. 542 v. Allied Erecting & Dismantling Co. , 556 F. App'x 109 ( 2014 )


Menu:
  •                                                            NOT PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    _____________
    No. 13-2160
    _____________
    INTERNATIONAL UNION OF OPERATING ENGINEERS, LOCAL UNION NO. 542
    v.
    ALLIED ERECTING & DISMANTLING CO., INC,
    Appellant
    ______
    On Appeal from the United States District Court
    for the Eastern District of Pennsylvania
    (D.C. Civil No. 2:12-cv-06579)
    District Judge: Honorable Berle M. Schiller
    ______
    Argued on December 16, 2013
    Before: JORDAN, VANASKIE, and VAN ANTWERPEN, Circuit Judges.
    (Filed: February 04, 2014)
    ______
    Edward R. Noonan, Esq. [ARGUED]
    Eckert, Seamans, Cherin & Mellot
    1717 Pennsylvania Avenue, N.W., 12th Floor
    Washington, DC 20006
    Counsel for Appellant
    Regina C. Hertzig, Esq. [ARGUED]
    Cleary, Josem & Trigiani
    325 Chestnut Street
    Constitution Place, Suite 200
    Philadelphia, PA 19106
    Counsel for Appellee
    ______
    OPINION OF THE COURT
    ______
    VAN ANTWERPEN, Circuit Judge.
    Appellant Allied Erecting & Dismantling Co., Inc. (“Allied”) appeals the District
    Court for the Eastern District of Pennsylvania’s declaratory judgment in favor of the
    International Union of Operating Engineers, Local Union No. 542 (“Union”), holding
    that their collective bargaining agreements were indefinite, contrary to the aims of federal
    labor law, and terminable by either party with reasonable notice. Int’l Union of Operating
    Eng’rs, Local Union No. 542 v. Allied Erecting & Dismantling Co., No. 12-6579, 
    2013 WL 1234729
    , at *3–4 (E.D. Pa. Mar. 26, 2013). For the reasons that follow, we will
    vacate the decision of the District Court and remand for further proceedings.
    I.     BACKGROUND
    Writing solely for the parties, we briefly review the essential facts. In 1992, the
    parties entered into two collective bargaining agreements pertaining to work dismantling
    a closed steel plant in Fairless Hills, Pennsylvania.1 The agreements established wages,
    working conditions, and other terms.2 The Fairless Hills project continues to date, and the
    Union anticipates it to continue at least another five years. (Compl. ¶ 13.)
    1
    Each agreement covers a separate bargaining unit. The “Operator Agreement” covers
    equipment operators and utility personnel. The “Helper Agreement” covers helpers. The
    relevant provisions are identical.
    2
    The agreements provided no method to renegotiate these terms. However, in 2004,
    Allied agreed to wage and benefit increases. Allied also recently agreed to increase
    contributions to the employees’ healthcare plan. The record is unclear when this
    occurred, but the precise date does not affect our decision. (Appellant Br. at 4 (most
    2
    The agreements define the Fairless Hills project as “[Allied’s] jobsite at the USX
    Corporation Fairless Hills Pennsylvania facility at which [Allied] performs dismantling
    work on decommissioned property pursuant to a contract with USX Corporation (herein
    referred to as the ‘Project’).” (Joint Appendix “JA” at 63, 83.) USX decides what is to be
    dismantled by Allied at the Fairless Hills project. Article I, Section 4 of the agreements
    states that “[i]n the event [Allied] is successful in procuring dismantling work at jobsites
    other than the Project within the Union’s geographical jurisdiction, [Allied], in its
    complete discretion, may elect to extend this Agreement to such other jobsites on a
    jobsite-by-jobsite basis.” (Id. (emphasis added).) The termination provision of each
    agreement provides that
    this Agreement shall terminate upon [Allied’s] completion of the Project.
    As to any jobsite to which this Agreement is extended on a jobsite-by-
    jobsite basis[,] . . . the Agreement and [Allied’s] recognition of the Union
    for employees employed at such jobsite shall terminate upon the
    completion of [Allied’s] work at such jobsites.
    (Id. at 78, 97.) The agreements also contain a severability clause3: “Any provision of this
    Agreement which now or subsequently is found . . . to contravene [the] law . . ., shall be
    suspended in operation . . . . Such suspension shall not affect the operation or validity of
    the remainder of the provisions of this Agreement.” (Id. at 77, 96.)
    In August, 2011, the Union notified Allied that it intended to terminate the
    agreements and requested negotiations for successor agreements. Allied filed a complaint
    recent modification occurred in 2009)); (Appellee Br. at 5 (2010)); (Compl. ¶ 11 (2008));
    (Answer & Countercl. ¶ 12 (2009)).
    3
    The severability clause is Article XXI of the Operator Agreement and Article XX of the
    Helper Agreement.
    3
    with the National Labor Relations Board (“NLRB”), alleging that such notice violated the
    National Labor Relations Act (“NLRA”). The NLRB Regional Director dismissed the
    charge and Allied appealed. The NLRB held Allied’s appeal in abeyance during the
    pendency of the proceedings below. The NLRB Office of Appeals then terminated its
    consideration of Allied’s appeal following the issuance of the District Court’s opinion.
    The Union requested the District Court to declare the agreements terminable upon
    reasonable notice, which the Union claimed it provided.4 (See Compl. ¶¶ 18, 20.) Allied
    argued that the termination provisions were valid and sought a declaration that the
    agreements remained in effect until completion of the Fairless Hills project. (See Answer
    ¶ 3.) The District Court held that the agreements were of “indeterminate duration” and
    were “inconsistent with the aims of federal labor law.” Allied Erecting & Dismantling
    Co., 
    2013 WL 1234729
    , at *3. Therefore, the parties could terminate them upon
    reasonable notice. 
    Id. at *4.
    Allied appealed.
    II.5    DISCUSSION
    “[F]ederal law governs the construction of collective bargaining agreements, [and]
    traditional rules of contract interpretation apply when not inconsistent with federal labor
    law.” Teamsters Indus. Emps. Welfare Fund v. Rolls–Royce Motor Cars, Inc., 
    989 F.2d 4
      In the alternative, the Union claimed that the agreements were invalid due to unilateral
    mistake, mutual mistake, and because they failed to reflect the true intention of the
    parties. (Compl. ¶¶ 26, 30, 33.)
    5
    The District Court had jurisdiction pursuant to Section 301 of the Labor Management
    Relations Act of 1947, 29 U.S.C. § 185. See, e.g., Mack Trucks, Inc. v. UAW, 
    856 F.2d 579
    , 587 (3d Cir. 1988). This Court has jurisdiction under 28 U.S.C. § 2201. We exercise
    plenary review over conclusions of law when reviewing a decision to grant a declaratory
    judgment. Borden v. Sch. Dist. of E. Brunswick, 
    523 F.3d 153
    , 174 n.17 (3d Cir. 2008).
    4
    132, 135 (3d Cir. 1993) (citation omitted). “If less than all of an agreement is
    unenforceable [as against public policy], a court may nevertheless enforce the rest of the
    agreement in favor of a party who did not engage in serious misconduct if the
    performance as to which the agreement is unenforceable is not an essential part of the
    agreed exchange.” Restatement (Second) of Contracts § 184(1) (1981); see also Puleo v.
    Chase Bank USA, N.A., 
    605 F.3d 172
    , 186 (3d Cir. 2010). A severability analysis requires
    that we determine whether a contract provision is unenforceable, and, if so, whether it
    may be severed from the remainder of the agreement. See 
    Puleo, 605 F.3d at 186
    .
    A.     Article I, Section 4 is unenforceable.
    Labor contracts of indefinite duration contravene federal labor policy and are
    terminable at will. E.g., Montgomery Mailers’ Union No. 127 v. Advertiser Co., 
    827 F.2d 709
    , 715 (11th Cir. 1987). However, a contract may terminate upon a specified event
    rather than a predetermined date. E.g., UAW v. Randall Div. of Textron, Inc., 
    5 F.3d 224
    ,
    229 (7th Cir. 1993).
    The District Court concluded that the agreements were of indefinite duration and
    terminable by both parties with reasonable notice. Allied Erecting & Dismantling Co.,
    
    2013 WL 1234729
    , at *3. It concurred with the Eleventh Circuit’s reasoning in
    Montgomery Mailers’ 
    Union, 827 F.2d at 715
    –16. The contract therein “continue[d] in
    effect for such reasonable time . . . as may be required for negotiation of a new
    agreement.” 
    Id. at 715.
    The union argued that under this provision, the agreement
    terminated only upon successful negotiation of a new agreement. 
    Id. 5 The
    Eleventh Circuit noted that the union, which was disinclined to enter into a
    new agreement, “could perpetuate the existing contract by continuing negotiations but
    never reaching an agreement.” 
    Id. “The side
    not desiring a change could refuse to agree .
    . . . Each side could stand entrenched knowing the contract would continue as it was. The
    side desiring to alter the terms or conditions of the relationship would never have a prayer
    of success.” 
    Id. (quoting Kaufman
    & Broad Home Sys. v. Int’l Brotherhood of Firemen,
    
    607 F.2d 1104
    , 1110 (5th Cir. 1979)). This was “contrary to fundamental principles of
    law, our established national labor relations policy and the intent of Congress expressed
    in the Labor Management Relations Act of 1947.” 
    Id. The District
    Court found that the instant agreements reached the same untenable
    result. Allied Erecting & Dismantling Co., 
    2013 WL 1234729
    , at *3. It reasoned that, as
    in Montgomery Mailers’ Union, one party (Allied) could extend the agreements
    indeterminately. 
    Id. It enumerated
    three examples: Allied could stall the Fairless Hills
    project, contract for additional work on that project, or “in its complete discretion,
    contract for additional work on other projects, extend the agreements to that additional
    work, and subsequently bind the Union to the agreements for an unknown and
    perpetually endless time period.” 
    Id. This would
    freeze wages and benefits indefinitely
    and prevent workers from negotiating pay raises or additional benefits. 
    Id. The District
    Court concluded that the aims of federal labor law required allowing the parties to
    terminate such indefinite agreements. 
    Id. (citing 29
    U.S.C. § 151). Therefore, either party
    could terminate the agreements upon reasonable notice. 
    Id. at *4.
    6
    On appeal, Allied argues that the agreements are not indefinite because they
    terminate upon the occurrence of a specified event—the completion of the Fairless Hills
    project. See, e.g., Randall Div. of 
    Textron, 5 F.3d at 229
    . Even if Allied extended the
    agreements to other projects, Allied claims those agreements would also terminate when
    the projects concluded. Furthermore, Allied argues that the District Court’s analogy to
    Montgomery Mailers’ Union is misplaced because that case narrowly applies only when
    post-expiration clauses extend an agreement indefinitely pending the negotiation of a new
    agreement.
    Allied argues that, even if Montgomery Mailers’ Union applies, the District Court
    erred in concluding that Allied has unilateral control over the agreements’ termination. It
    notes that Allied’s client, and not it, controls the length of the project and that there is no
    allegation Allied is stalling. Next, it advances numerous reasons why its “complete
    discretion” over extending the agreement does not render it “indefinite.”
    First, it argues that “each extension creates a new and separate project agreement,”
    which terminates upon completion of that particular project. (Appellant Br. at 14.)
    Second, because each extension creates a “new” agreement for a distinct bargaining unit,
    Allied claims that the Union completely controls whether it is bound because it can
    always “refus[e] the extension through a valid disclaimer of interest in representing such
    bargaining unit.” (Id.) Third, even if the District Court correctly uncovered the possibility
    of perpetual agreements, it failed to recognize that, as pertains to Fairless Hills, the
    agreements distinctly terminate when work is completed. (Id. at 14–15.) Thus “even
    7
    assuming that the agreements could ‘go on forever’ [by extension to other jobsites] it is
    impossible for either to go on forever at Fairless Hills.” (Id. at 15.)
    We concur with the District Court that Allied’s complete discretion in Article I,
    Section 4 of the agreements over whether to extend these agreements to other jobsites
    renders the agreements indefinite. The agreements’ plain language rebuts Allied’s claim
    that each extension creates a “new and separate project agreement.” (Id. at 14.) Article I,
    Section 4 and the termination provision refer to the extension of “this Agreement.” (JA at
    63, 78, 83, 97 (emphasis added).) Article I, Section 4 merely grants Allied the power to
    “extend” the agreements; it does not create “new and separate” agreements. Cf. Nibbs v.
    Felix, 
    726 F.2d 102
    , 104–05 (3d Cir. 1984) (holding that arbitration provisions were still
    binding after contract’s termination because they were informally extended). Thus, the
    1992 agreements (including modifications), and no others, would apply to other jobsites.
    Allied unpersuasively contends that the agreements are not indefinite because they
    terminate upon completion of the Fairless Hills project (and that extensions terminate
    upon completion of work at new jobsites). Article I, Section 4 allows Allied, in its sole
    discretion, to extend the agreements to new projects. Even worse, at each new jobsite, the
    governing agreements would still contain this extension clause, permitting Allied to
    unilaterally extend the agreements to still other projects, ad infinitum. This would be true
    long after work at Fairless Hills concludes. All the while, Allied need never update the
    employment terms.6
    6
    Allied’s brief does not contest the District Court’s conclusion that perpetuating the
    agreements indeterminately would “lock in the wages and benefits designated in the
    8
    Thus, although the facts here are distinguishable from Montgomery Mailers’
    Union, the rationale is consistent. The agreements are indefinite because one party
    unilaterally controls the termination event.7 Allied may, in its complete discretion, extend
    the agreements indefinitely into the future. “The side desiring to alter the terms or
    conditions of the relationship would never have a prayer of success.” Montgomery
    Mailers’ 
    Union, 827 F.2d at 715
    (quoting Kaufman & Broad Home 
    Sys., 607 F.2d at 1110
    ).
    The District Court also rested its conclusion on Allied’s hypothetical ability to
    “stall” the project indefinitely, thereby rendering the agreements potentially indefinite as
    applied to the Fairless Hills project. 8 Allied Erecting & Dismantling Co., 2013 WL
    agreements indefinitely, depriving workers of the ability to negotiate pay raises or
    additional benefits.” Allied Erecting & Dismantling Co., 
    2013 WL 1234729
    , at *3.
    7
    Allied’s argument that the Union can refuse the extension by disclaiming interest in
    future bargaining units serves only to demonstrate how pervasive is Allied’s control over
    termination. This is even more extreme than Kaufman & Broad Home Systems in which
    the Court noted that “there is nothing in the agreement as interpreted by [the employer]
    that would keep it from continuing year after year, thus forcing the [u]nion to choose
    between termination of the entire agreement and [indefinite 
    continuation].” 607 F.2d at 1109
    .
    8
    The District Court also concluded that Allied could hypothetically render the
    agreements indefinite by contracting for additional work on the Fairless Hills Project.
    However, the Union concedes that one jobsite cannot contain an infinite amount of work.
    (See Brief of Appellee at 6 n.4 (“[T]he Fairless Hills dismantling projects could only
    necessarily involve a finite number of buildings.”).) Indeed, the Union believes the work
    at Fairless Hills could conclude in five years. (Compl. ¶ 13.) Obviously, under the terms
    of the agreements, the work will terminate at some point in time. Additionally, the
    agreements limit the term “Project” to “[Allied’s] jobsite at the USX Corporation Fairless
    Hills Pennsylvania facility at which [Allied] performs dismantling work on
    decommissioned property pursuant to a contract with USX Corporation.” (JA at 63, 82–
    83). Nothing in the agreements or the record purports to permit Allied to “contract[] for
    additional work” beyond this bargained-for scope. See Allied Erecting & Dismantling
    Co., 
    2013 WL 1234729
    , at *3.
    9
    1234729, at *3. We find the trajectory of this argument troubling and reject it. We note
    especially that the District Court only found that Allied “could” extend the project by
    stalling, not that it ever had done so. 
    Id. To begin
    with, it is difficult to understand how
    Allied “could” unilaterally stall the project since the dismantling is being done pursuant
    to a contract with a third party, USX. Furthermore, it is obvious that such a theoretical
    analysis, taken to its extreme, could render indeterminate all contracts that terminate upon
    completion of a project rather than a pre-determined date because one party could always
    hypothetically stall. We do not say that in an appropriate case a district court may never
    consider stalling—hypothetical or otherwise—as a factor; however, we reject the District
    Court’s approach, in which hypothetical stalling is a sufficient cause of indefiniteness.
    We also reject any notion that contracts which terminate upon completion of work at a
    particular jobsite are per se indeterminate.
    We are required to construe labor contracts in light of the “practice, usage and
    custom pertaining to all such agreements.” Transp.–Commc’n Emp. Union v. Union Pac.
    R.R., 
    385 U.S. 157
    , 161 (1966). Additionally, we must recognize the “‘dual purpose’ in
    the Taft–Hartley Act—to substitute collective bargaining for economic warfare and to
    protect the right of employees to engage in concerted activities for their own benefit.”
    NLRB v. Lion Oil Co., 
    352 U.S. 282
    , 289 (1957) (citing Mastro Plastics Corp. v. NLRB,
    
    350 U.S. 270
    , 284 (1956)). In light of these considerations, we hold that permitting
    Article I, Section 4 to extend the agreements indefinitely into the future “would be
    inconsistent with the aims of federal labor law.” Allied Erecting & Dismantling Co., 
    2013 WL 1234729
    , at *3 (citing 29 U.S.C. § 151 (finding that “protection by law of the right
    10
    of employees to organize and bargain collectively safeguards commerce” and declaring a
    policy of “encouraging the practice and procedure of collective bargaining”)).
    B.     Article 1, Section 4 is severable.
    This does not end the analysis, however. The agreements contain a severability
    clause which suspends the operation of any provision found “to contravene a national,
    state, or local law.” (JA at 77, 96.) If such suspension occurs, the operation or validity of
    the remainder of the agreements’ provisions is to remain unaffected. (Id.)
    “[T]raditional rules of contract interpretation apply when not inconsistent with
    federal labor law.” 
    Rolls–Royce, 989 F.2d at 135
    . “If less than all of an agreement is
    unenforceable [as against public policy], a court may nevertheless enforce the rest of the
    agreement . . . if the performance as to which the agreement is unenforceable is not an
    essential part of the agreed exchange.” Restatement (Second) of Contracts § 184(1); see
    also 
    Puleo, 605 F.3d at 186
    . Whether performance is essential turns on its “relative
    importance in the light of the entire agreement between the parties.” Restatement
    (Second) of Contracts § 184, cmt. a; see also Nino v. Jewelry Exch., Inc., 
    609 F.3d 191
    ,
    206 (3d Cir. 2010)).
    In supplemental briefing and at oral argument in open court both parties conceded
    that, if Article I, Section 4 is found to be unenforceable, the severability clause suspends
    its operation. Furthermore, the parties also agree, and we find, that Article I, Section 4 is
    not an essential part of the agreed exchange. The primary purpose of the agreements at
    issue is to establish wages, benefits, working conditions, and dispute resolution
    procedures for the covered bargaining units at Allied’s Fairless Hills project. (See JA at
    11
    62, 82.) This goal can be accomplished without the extension provision, which pertains to
    other jobsites. Cf. Prusky v. Reliastar Life Ins. Co., 
    445 F.3d 695
    , 699–700 (3d Cir. 2006)
    (holding that nonessential and illegal late-trading provisions in life insurance contract
    were severable).
    To the extent that Article I, Section 4 and the portions of those Sections which
    reference it permit the agreements to be extended indefinitely into the future, these
    provisions should be deemed unenforceable and severed pursuant to the severability
    clause. What remains of the agreements is not indefinite because it terminates upon the
    occurrence of a specified event—completion of the Fairless Hills project. See, e.g.,
    Randall Div. of 
    Textron, 5 F.3d at 229
    . This outcome is consistent with federal labor
    policy and our jurisprudence. The federal labor policy promoting labor relations stability
    does not permit parties to unilaterally repudiate collective bargaining agreements during
    the agreed-to term. See Int’l Assoc. of Bridge, Structural & Ornamental Iron Workers,
    Local 3 v. NLRB, 
    843 F.2d 770
    , 778 (3d Cir. 1988) [Deklewa].9 While protecting
    9
    The Union attempts to distinguish Deklewa as applying only to § 8(f) agreements;
    however, Deklewa suggests a broader application for its principle. See, 
    e.g., 843 F.2d at 773
    , 778 (resolving in the affirmative “whether during its term a § 8(f) agreement is as
    binding and enforceable as any other union agreement” and noting the NLRB’s rationale
    that “a right of unilateral repudiation is . . . antithetical to traditional principles of
    collective-bargaining under the [NLRA]” (emphasis added)); see also Builders,
    Woodworkers & Millwrights, Local Union No. 1 (Glen Falls Contractors Ass’n), 
    341 N.L.R.B. 448
    , at *1 n.2 (2004) (“Regardless of whether this may have been a 9(a) or 8(f)
    relationship, the . . . employers were not free to unilaterally repudiate their agreement
    with the Carpenters and recognize the Respondent.”); John Deklewa & Sons, 
    282 N.L.R.B. 1375
    , 1386 (1987) (“Our new analytic framework also better fulfills general
    statutory policies and integrates Section 8(f) with other sections in the Act. In this regard,
    the policy of labor relations stability in the Act generally favors requiring parties to
    adhere to a voluntarily adopted collective-bargaining agreement.”).
    12
    collective bargaining is also an overarching objective of the NLRA, we have recognized
    that this goal is strengthened by requiring adherence to the terms of labor contracts. See,
    e.g., Michota v. Anheuser-Busch, Inc., 
    755 F.2d 330
    , 335 (3d Cir. 1985) (“Integrity of the
    collective bargaining process under the [NLRA] is critical to the stability of labor
    relations. The ability of duly elected bargaining representatives to bargain effectively is
    dependent in part upon its ability to bind the employees it represents to the terms of a
    negotiated agreement.”).
    The District Court’s opinion did not address the Union’s remaining claims:
    unilateral mistake, mutual mistake, and reformation based on party intent. (See Compl. ¶¶
    26, 30, 33.) We decline Allied’s invitation to decide these issues on appeal.
    III.   CONCLUSION
    For the foregoing reasons, we will vacate the District Court’s declaratory
    judgment in favor of the Union and remand the case to that Court to determine the
    Union’s remaining claims in a manner consistent with this Opinion.
    13
    VANASKIE, Circuit Judge, concurring in part and dissenting in part.
    I agree with the majority’s conclusion that the extension provision of Article I,
    Section 4 of the agreements is unenforceable. I part company with the majority,
    however, with respect to the holding that the collective bargaining agreements are not of
    indeterminate duration because they will terminate upon completion of the Fairless Hills
    project, a project that has spanned more than three decades since the agreements were
    negotiated. Indeed, there is no end in sight for the project, and I believe that is the
    quintessential example of an indeterminate duration. Therefore, I respectfully dissent
    from the majority’s conclusion that the collective bargaining agreements at issue are not
    terminable at will by either party upon reasonable notice.
    As the majority notes, “[f]ederal law governs the construction of collective
    bargaining agreements, [and] traditional rules of contract interpretation apply when not
    inconsistent with federal labor law.” Teamsters Indus. Emps. Welfare Fund v. Rolls–
    Royce Motor Cars, Inc., 
    989 F.2d 132
    , 135 (3d Cir. 1993). In interpreting labor
    contracts, the Supreme Court has instructed federal courts to “fashion from the policy of
    our national labor laws” a body of substantive federal law. Textile Workers Union of
    America v. Lincoln Mills of Ala., 
    353 U.S. 448
    , 456 (1957).
    Employing this authority, federal courts have articulated the principle that “[l]abor
    contracts of indeterminate duration are generally terminable at will upon reasonable
    notice to the other party.” Communications Workers of America v. Southwestern Bell
    Telephone Co., 
    713 F.2d 1118
    , 1123 n. 4 (5th Cir. 1983); Boeing Airplane Co. v. NLRB,
    
    174 F.2d 988
    , 991 (D.C. Cir. 1949); Montgomery Mailers’ Union No. 127 v. Advertiser
    1
    Co., 
    827 F.2d 709
    , 715 (11th Cir. 1987). This is because our labor laws encourage
    collective bargaining between labor organizations and employers as a means of both
    ensuring “the friendly adjustment of industrial disputes arising out of differences as to
    wages, hours, or other working conditions,” as well as safeguarding the “equality of
    bargaining power between employers and employees.” 29 U.S.C. § 151. In the absence
    of a periodic opportunity to adjust wages, hours, or working conditions, an indefinite
    labor agreement becomes a tool that exacerbates the inequality of bargaining power
    between employers and laborers, rather than providing a bulwark against it.
    The majority acknowledges that the agreements as written cannot stand, as they
    purport to give Allied the unilateral ability to extend the agreements indefinitely to any
    new jobsites they desire. Rather than taking the remedial step of declaring the
    agreements terminable at will by either party, the majority seeks to reform the indefinite
    contracts to limit them to a definite duration. To do this, the majority strikes Article I,
    Section 4. but leaves in place the provision indicating the agreements will terminate upon
    the completion of “[Allied’s] jobsite at the USX Corporation Fairless Hills Pennsylvania
    facility.” (App. 78)
    The majority believes this fix renders the agreements definite and enforceable,
    noting that the “Union concedes that one jobsite cannot contain an infinite amount of
    work.” Maj. Op. at 9, fn. 8 (emphasis added). But indeterminate does not mean infinite.
    Indeterminate is defined as “uncertain; not ascertained; not fixed; not made certain.”
    Ballentine’s Law Dictionary 610 (3rd ed. 1969). For instance, an agreement that
    provided that it would terminate upon a certain person’s death would be indeterminate
    2
    because, although a human lifespan is not infinite, its duration is not capable of being
    ascertained in advance by the parties to the contract.
    Although I agree that this case does differ from Montgomery Mailers Union, upon
    which the District Court relied, in that neither party to the contracts possesses the
    unilateral ability to extend the collective bargaining agreements in perpetuity, this case
    similarly presents contracts whose duration cannot be fixed or ascertained by the parties
    in advance of termination. The majority comforts itself that “the work at Fairless Hills
    could conclude in five years” (Maj. Op. at 9, fn. 8), but when pressed at oral argument,
    Allied’s counsel conceded that he had “no idea how long it could take” for the Fairless
    Hills project to be completed. (Oral Arg. At 31:46-31:50). Uncertainty about the amount
    of time the contracts will govern the relationship between the parties prevents the
    members of the union from knowing how long they will have to continue to labor under
    the existing contractual terms—negotiated more than twenty years ago—before being
    permitted to renegotiate. The duration of the agreements is, therefore, “uncertain; not
    ascertained; not fixed; not made certain.” Ballentine’s Law Dictionary at 610.
    The majority’s conclusion that the agreements are not indeterminate because the
    projects will be completed at some unknown time in the distant future thwarts federal
    labor law’s preference for the negotiated adjustment of “industrial disputes arising out of
    differences as to wages, hours, or other working conditions.” 29 U.S.C. § 151. In this
    instance, it is the laborers whose terms and conditions of employment are frozen
    indefinitely. In another instance, it may be the employer who becomes hostage to a
    collective bargaining agreement of indefinite duration, negotiated perhaps at a time when
    3
    organized labor had the upper hand in bargaining. The point is that neither labor nor the
    employer should be unable to negotiate the terms and conditions of employment on a
    periodic basis. The majority’s holding effectively forecloses the union from doing so on
    behalf of its members for however long it may take to complete the Fairless Hills project.
    The majority notes that “federal labor policy promoting labor relations stability
    does not permit parties to unilaterally repudiate collective bargaining agreements during
    the agreed-to term.” Maj. Op. at 9 (citing Int’l Assoc. of Bridge, Structural &
    Ornamental Iron Workers, Local 3 v. NLRB, 
    843 F.2d 770
    , 778 (3d Cir. 1988)
    [Deklewa]). But Deklewa concerned a very different factual scenario—an employer’s
    attempt to renege on a collective bargaining agreement with a fixed three-year term. 
    Id. at 772.
    I would not extend Deklewa to the type of agreements at issue here, which have
    no ascertainable duration. In such cases, federal labor law’s interest in stability is
    outweighed by its concern with equalizing bargaining power between labor organizations
    and employers and preventing the ossification of disputed wages, hours, and working
    conditions. See 29 U.S.C. § 151.
    Because I believe considerations of federal labor policy weigh in favor of
    allowing the parties to terminate the agreements at issue upon giving reasonable notice, I
    respectfully dissent.
    4
    

Document Info

Docket Number: 13-2160

Citation Numbers: 556 F. App'x 109

Judges: Jordan, Van Antwerpen, Vanaskie

Filed Date: 2/4/2014

Precedential Status: Non-Precedential

Modified Date: 8/31/2023

Authorities (18)

Montgomery Mailers' Union No. 127 v. The Advertiser Company , 827 F.2d 709 ( 1987 )

Eurice Nibbs v. Otis Felix, Commissioner of Public Safety, ... , 726 F.2d 102 ( 1984 )

Puleo v. Chase Bank USA, N.A. , 605 F.3d 172 ( 2010 )

In No. 84-5182 , 755 F.2d 330 ( 1985 )

paul-m-prusky-individually-and-as-trustee-windsor-securities-inc , 445 F.3d 695 ( 2006 )

mack-trucks-inc-v-international-union-united-automobile-aerospace-and , 856 F.2d 579 ( 1988 )

Boeing Airplane Co. v. National Labor Relations Board , 174 F.2d 988 ( 1949 )

Kaufman and Broad Home Systems, Inc. v. International ... , 607 F.2d 1104 ( 1979 )

Communications Workers of America, Afl-Cio v. Southwestern ... , 713 F.2d 1118 ( 1983 )

international-union-of-united-automobile-aerospace-and-agricultural , 5 F.3d 224 ( 1993 )

Borden v. School District of the Township of East Brunswick , 523 F.3d 153 ( 2008 )

Nino v. JEWELRY EXCHANGE, INC. , 609 F.3d 191 ( 2010 )

in-re-teamsters-industrial-employees-welfare-fund-teamsters-industrial , 989 F.2d 132 ( 1993 )

international-association-of-bridge-structural-and-ornamental-iron , 843 F.2d 770 ( 1988 )

Mastro Plastics Corp. v. NLRB , 76 S. Ct. 349 ( 1956 )

National Labor Relations Board v. Lion Oil Co. , 77 S. Ct. 330 ( 1957 )

Textile Workers v. Lincoln Mills of Ala. , 77 S. Ct. 912 ( 1957 )

Transportation-Communication Employees Union v. Union ... , 87 S. Ct. 369 ( 1966 )

View All Authorities »