Delaware Riverkeeper Network v. Sec Pa Dept Environmental Prot ( 2017 )


Menu:
  •                                 PRECEDENTIAL
    UNITED STATES COURT OF APPEALS
    FOR THE THIRD CIRCUIT
    _____________
    No. 17-1533
    _____________
    DELAWARE RIVERKEEPER NETWORK;
    MAYA VAN ROSSUM, the Delaware Riverkeeper,
    Petitioners
    v.
    SECRETARY OF THE PENNSYLVANIA DEPARTMENT
    OF ENVIRONMENTAL PROTECTION;
    PENNSYLVANIA DEPARTMENT OF
    ENVIRONMENTAL PROTECTION,
    Respondents
    Tennessee Gas Pipeline Co.,
    Intervenor
    On Petition for Review from the Pennsylvania Department of
    Environmental Protection
    WQ02-002
    E52-253
    E63-305
    FERC-1 : FERC CP16-4
    Argued July 13, 2017
    Before: SMITH, Chief Judge, NYGAARD, and FUENTES,
    Circuit Judges
    (Filed: August 30, 2017)
    Aaron J. Stemplewicz       [ARGUED]
    Delaware Riverkeeper Network
    925 Canal Street, Suite 3701
    Bristol, PA 19007
    Counsel for Petitioners
    Alexandra C. Chiaruttini
    Joseph S. Cigan III      [ARGUED]
    Commonwealth of Pennsylvania
    Department of Environmental Protection
    2 Public Square
    Wilkes-Barre, PA 18701
    Kimberly Hummel Childe
    Office of Attorney General of Pennsylvania
    Department of Environmental Resources
    9th Floor
    P.O. Box 8464
    Harrisburg, PA 17105
    Counsel for Respondents
    Pamela S. Goodwin
    Saul Ewing
    650 College Road East, Suite 4000
    Princeton, NJ 08540
    2
    Patrick F. Nugent
    John F. Stoviak    [ARGUED]
    Saul Ewing
    1500 Market Street
    Centre Square West, 38th Floor
    Philadelphia, PA 19102
    Elizabeth U. Witmer
    Saul Ewing
    1200 Liberty Ridge Drive, Suite 200
    Wayne, PA 19087
    Counsel for Intervenor Respondent
    ________________
    OPINION OF THE COURT
    ________________
    SMITH, Chief Judge.
    Tennessee Gas Pipeline Co. (“Tennessee Gas”) submitted
    applications to several federal and state agencies seeking
    approval to build an interstate pipeline project. One such
    agency is the Pennsylvania Department of Environmental
    Protection (“PADEP”),1 which issued a permit approving the
    1
    A companion case, also before this panel, raises
    challenges to the United States Army Corps of Engineers. See
    Del. Riverkeeper Network v. U.S. Army Corps of Eng’rs, No.
    17-1506 (3d Cir. 2017).
    3
    project. The petitioners, Maya van Rossum and Delaware
    Riverkeeper Network (collectively, “Riverkeeper”), argue that
    we lack jurisdiction to rule on its petition because PADEP’s
    order was not final. As to the merits, Riverkeeper challenges
    PADEP’s decision on the grounds that the agency made an
    erroneous “water dependency” finding and improperly rejected
    a “compression” alternative to the pipeline project.
    We will exercise jurisdiction because PADEP’s decision
    was final. We will also uphold PADEP’s decision on the merits
    because the agency’s unique interpretation of water
    dependency is reasonable and worthy of deference.
    Furthermore, the agency considered and rejected the
    compression alternative for reasons that are supported by the
    record. We will therefore deny the petition for review.
    I
    At issue is the so-called Orion Project—12.9 miles of
    pipeline looping that would transport 135,000 dekatherms of
    natural gas per day via Pennsylvania. Approximately 99.5% of
    the new pipeline would run alongside existing pipelines.
    Full background information on the Orion Project is
    provided in a companion case, Delaware Riverkeeper Network
    v. U.S. Army Corps of Engineers, No. 17-1506 (3d Cir. 2017).
    For purposes of this opinion, we will focus on the aspects of
    the state administrative procedures at issue here.
    Under the Natural Gas Act of 1938, the Federal Energy
    Regulatory Commission (“FERC”) is the “lead agency” for
    evaluating interstate pipeline projects. 15 U.S.C. § 717n(b). As
    4
    a condition of FERC approval, the applicant is required to
    obtain any other state or federal licenses required by law. One
    such license is called a Water Quality Certification governed
    by Section 401 of the Clean Water Act. 
    33 U.S.C. § 1341
    . “A
    Water Quality Certification confirms that a given facility will
    comply with federal discharge limitations and state water
    quality standards.” Del. Riverkeeper Network v. Sec'y Pa. Dep’t
    of Envtl. Prot., 
    833 F.3d 360
    , 368 (3d Cir. 2016), as amended
    (March 24, 2017). “For activities affecting Pennsylvania
    waters, . . . Water Quality Certifications are issued by PADEP.”
    
    Id. at 369
    .
    As a condition of obtaining a Water Quality Certification,
    PADEP requires applicants to obtain other state permits,
    including a Water Obstruction and Encroachment Permit
    issued under Pennsylvania’s Dam Safety and Encroachment
    Act and its implementing regulations, 25 Pa. Code Ch. 105.
    Those permits are commonly referred to as “Chapter 105
    permits.”
    Chapter 105 gives special protection to “exceptional value”
    wetlands. Wetlands are considered to have exceptional value
    if, inter alia, they are located along a drinking water supply or
    serve as habitat for endangered species. See 
    25 Pa. Code § 105.17
    (1). It is undisputed that the Orion Project would affect
    ten exceptional-value wetlands in Pike County and three in
    Wayne County.
    PADEP cannot issue a Chapter 105 permit for a project
    affecting exceptional-value wetlands unless it certifies in
    writing that seven requirements are met. 
    25 Pa. Code § 105
    .18a. Two are relevant here:
    5
    (2) The project is water-dependent. A project is
    water-dependent when the project requires
    access or proximity to or siting within the
    wetland to fulfill the basic purposes of the
    project.
    (3) There is no practicable alternative to the
    proposed project that would not involve a
    wetland or that would have less effect on the
    wetland, and not have other significant adverse
    effects on the environment.
    
    Id.
     § 105.18a(a)(2)–(3).
    On September 20, 2016, PADEP issued a conditional Water
    Quality Certification for the Orion Project. Then, on February
    23, 2017, PADEP issued two Chapter 105 permits approving
    the Orion Project’s stream and wetland crossings—Permit Nos.
    E52-253 (Pike County) and E64-305 (Wayne County). In
    doing so, PADEP certified that the Orion Project “[i]s water
    dependent” and would be “the least environmentally damaging
    alternative.” JA 49, 180.
    On March 10, 2017, Riverkeeper filed this petition for
    review. We granted Tennessee Gas’s motion to intervene on
    March 17, 2017. Riverkeeper filed a motion for an emergency
    stay, which this Court denied on April 7, 2017. Riverkeeper
    then filed a motion to expedite the case. We granted that motion
    on May 8, 2017.
    6
    II
    The parties ask us to resolve two jurisdictional issues:
    (1) whether we may review nonfinal administrative orders
    under the Natural Gas Act; and (2) whether the petition was
    timely filed. We need not reach the first question. The agency
    decision at issue is final, and therefore jurisdiction would be
    proper under either interpretation of the Natural Gas Act. As
    for the second question, we conclude that the petition was
    timely filed.
    A
    First, Riverkeeper argues that we lack jurisdiction because
    we may only review final orders, and PADEP’s order is not
    final until it has been reviewed by a separate administrative
    entity, Pennsylvania’s Environmental Hearing Board.
    Riverkeeper asks us to transfer the case to the Board.2 We
    conclude that jurisdiction is proper because PADEP’s order is
    final.
    1
    Our jurisdiction is controlled by Section 19(d) of the
    Natural Gas Act, as amended in 2005. Where an interstate
    pipeline project is proposed to be constructed, see 15 U.S.C.
    2
    Because we conclude that jurisdiction is proper, we
    need not address Riverkeeper’s request for a transfer. See
    McLaughlin v. Arco Polymers, Inc., 
    721 F.2d 426
    , 430 (3d Cir.
    1983); see also Moravian Sch. Advisory Bd. of St. Thomas, V.I.
    v. Rawlins, 
    70 F.3d 270
    , 276 (3d Cir. 1995).
    7
    § 717f, this Court has “original and exclusive jurisdiction over
    any civil action for the review of an order or action of a . . .
    State administrative agency acting pursuant to Federal law to
    issue . . . any permit, license, concurrence, or approval . . .
    required under Federal law,” id. § 717r(d)(1).
    In a recent precedential opinion, this Court exercised
    jurisdiction over a similar PADEP decision involving the
    “Leidy Line” pipeline project. Del. Riverkeeper, 
    833 F.3d 360
    .
    The petitioner, also Riverkeeper, challenged PADEP’s decision
    to issue a Water Quality Certification. This Court concluded
    that “the issuance of a Water Quality Certification is not purely
    a matter of state law” because the certification “is an integral
    element of the regulatory scheme established by the Clean
    Water Act.” 
    Id. at 371
    . Thus, PADEP was “acting pursuant to
    Federal law” within the meaning of the Natural Gas Act. 15
    U.S.C. § 717r(d)(1). We also exercised jurisdiction over
    various permits issued by the New Jersey Department of
    Environmental Protection, even though some permits were
    “governed by state law rather than the Clean Water Act.” Del.
    Riverkeeper, 833 F.3d at 374. Because those state-law permits
    were, “in effect, a set of conditions” on obtaining approval
    under the Clean Water Act, id. (citing 
    33 U.S.C. § 1341
    (d)),
    they were issued “pursuant to Federal law,” 15 U.S.C.
    § 717r(d)(1). Likewise here, the Chapter 105 permits were
    conditions of federal approval and therefore were issued
    “pursuant to Federal law.” Id.; see Del. Riverkeeper, 833 F.3d
    at 386 (“Because the Chapter 105 Permit was a condition of
    the Water Quality Certification, it is inextricably intertwined
    with the Water Quality Certification.”).
    8
    After the Leidy Line ruling, the First Circuit decided
    Berkshire Environmental Action Team, Inc. v. Tennessee Gas
    Pipeline Co., LLC, 
    851 F.3d 105
     (1st Cir. 2017). Berkshire
    ruled on an issue that was not raised in the Leidy Line case:
    finality.
    First, Berkshire held that § 717r(d)(1) includes an unstated
    finality requirement. Even though the statute does not use the
    word “final,” the First Circuit read that word into the statute
    based on the “strong presumption . . . that judicial review will
    be available only when agency action becomes final.” Id. at
    109 (quoting Bell v. New Jersey, 
    461 U.S. 773
    , 778 (1983));
    see also Columbia Riverkeeper v. U.S. Coast Guard, 
    761 F.3d 1084
    , 1092 (9th Cir. 2014). But see Tenn. Gas Pipeline Co.
    LLC v. Del. Riverkeeper Network, 
    921 F. Supp. 2d 381
    , 391
    (M.D. Pa. 2013).3
    Second, Berkshire concluded that the particular agency
    decision at issue was not final. It evaluated “[t]he substance of
    the Massachusetts regulatory regime,” Berkshire, 851 F.3d at
    112, and concluded that the applicant (also Tennessee Gas) was
    required to go through an additional adjudicatory hearing
    3
    But see also Energy Transfer Partners, L.P. v.
    F.E.R.C., 
    567 F.3d 134
    , 139 (5th Cir. 2009) (“Our court
    has long recognized that [§ 717r(b), governing appeals
    from FERC,] does not require that an order be a ‘final’ one[.]”);
    Atl. Seaboard Corp. v. Fed. Power Comm’n, 
    201 F.2d 568
    , 572
    (4th Cir. 1953) (“The commission argues that the order which
    we are asked to review is not a definitive or final order of the
    commission; but our power to review is not limited to final
    orders.”).
    9
    before the agency action would be ripe for review. Berkshire
    characterized the adjudicatory hearing as a continuation of “a
    single, unitary proceeding” that had not yet finally concluded.
    
    Id.
    Although the Leidy Line case was procedurally similar to
    this one, the finality issue was not presented and remains
    unresolved in this circuit. We must therefore address it. See,
    e.g., Ehleiter v. Grapetree Shores, Inc., 
    482 F.3d 207
    , 211 (3d
    Cir. 2007) (“[A] court of appeals has both the inherent
    authority and a continuing obligation to assess whether it has
    jurisdiction over a case or controversy before rendering a
    decision on the merits.”).
    2
    Riverkeeper argues that we should follow Berkshire’s
    holding and read a finality requirement into § 717r(d)(1).
    Riverkeeper further argues that PADEP’s order is not final
    because Pennsylvania’s administrative scheme is analogous to
    Massachusetts’s. We need not rule on whether § 717r(d)(1)
    includes an unstated finality requirement. In either case, our
    jurisdiction is proper because the agency action here is
    administratively final.
    “Our cases have interpreted pragmatically the requirement
    of administrative finality, focusing on whether judicial review
    at the time will disrupt the administrative process.” Bell, 
    461 U.S. at 779
    . Final agency action “must mark the
    ‘consummation’ of the agency’s decisionmaking process,”
    “must not be of a merely tentative or interlocutory nature,” and
    “must be one by which ‘rights or obligations have been
    10
    determined,’ or from which ‘legal consequences will flow.’”
    Bennett v. Spear, 
    520 U.S. 154
    , 177–78 (1997) (quoting
    Chicago & Southern Air Lines, Inc. v. Waterman S.S. Corp.,
    
    333 U.S. 103
    , 113 (1948) and Port of Boston Marine Terminal
    Assn. v. Rederiaktiebolaget Transatlantic, 
    400 U.S. 62
    , 71
    (1970)).
    According to Riverkeeper, Pennsylvania’s administrative
    process does not reach a final conclusion until PADEP’s order
    has been reviewed by a separate administrative entity, the
    Environmental Hearing Board. In support of that proposition,
    Riverkeeper cites the Pennsylvania statute governing the
    Board’s jurisdiction:
    [N]o action of the department [PADEP4]
    adversely affecting a person shall be final as to
    that person until the person has had the
    opportunity to appeal the action to the board . . . .
    If a person has not perfected an appeal in
    accordance with the regulations of the board, the
    department’s action shall be final as to the
    person.
    4
    Note that the statute defines “Department” as “The
    Department of Environmental Resources of the
    Commonwealth.” 35 P.S. § 7512. Nonetheless, the parties
    appear to agree that the statute applies to that agency’s more
    recent incarnation, the Department of Environmental
    Protection. See Texas Keystone Inc. v. Pa. Dep’t of
    Conservation & Nat. Res., 
    851 A.2d 228
    , 239 (Pa. Commw.
    Ct. 2004).
    11
    35 P.S. § 7514(c). Riverkeeper seizes on the first sentence to
    argue that there has been no “appeal . . . to the board,” id., and
    therefore the administrative process has not culminated in a
    final decision over which we may exercise jurisdiction.
    Assuming (without deciding) that § 7514(c) controls
    appellate ripeness,5 the order in question is nonetheless final
    because Riverkeeper “has not perfected an appeal in
    accordance with the regulations of the board.” Id. The relevant
    regulation provides that an appeal to the Environmental
    Hearing Board must be filed within “[t]hirty days after the
    notice of the action has been published in the Pennsylvania
    Bulletin.” 
    25 Pa. Code § 1021.52
    (a)(2)(i). PADEP published
    notice on October 8, 2016. This petition was filed in March
    2017, and Riverkeeper did not take an appeal to the
    Environmental Hearing Board in the interim. Thus, PADEP’s
    order became “final” under 35 P.S. § 7514(c) in November
    5
    Paradoxically, the Board appears to apply its own finality
    requirement that approximates the federal standard,
    notwithstanding § 7514(c). See Law v. Dep’t of Envtl. Prot.,
    No. 1071 C.D. 2008, 
    2009 WL 9096519
    , at *2 (Pa. Commw.
    Ct. Jan. 23, 2009) (“[A] letter does not constitute an
    adjudication or a final decision or an appealable order from
    which an appeal can be taken from the Department to the
    Board.”); Commonwealth of Pennsylvania Environmental
    Hearing Board, Practice and Procedure Manual at 6–7 (2015
    ed.) (citing multiple decisions for the proposition that the
    Board has jurisdiction “over final Department actions
    adversely affecting personal or property rights, privileges,
    immunities, duties, liabilities or obligations of a person”).
    12
    2016. See Com., Dep’t of Envtl. Prot. v. Cromwell Twp., 
    32 A.3d 639
    , 653 (Pa. 2011) (“[T]he failure to appeal within thirty
    days rendered DEP’s action final.”); Otte v. Covington Twp.
    Rd. Sup’rs, 
    650 A.2d 412
    , 414 (Pa. 1994); cf. Berkshire, 851
    F.3d at 108 (noting that the petitioners dual-filed by “filing a
    Notice of Claim for Adjudicatory Hearing,” and also “hedged
    their bets” by filing a petition before the First Circuit).6
    Apart from § 7514(c), PADEP’s permits also bear the
    traditional hallmarks of final agency action. There is nothing
    left for the agency to do, and thus PADEP’s decision “mark[s]
    the ‘consummation’ of the agency’s decisionmaking process”
    and is not “of a merely tentative or interlocutory nature.”
    Bennett, 
    520 U.S. at 178
     (quoting Chicago & Southern Air
    Lines, 
    333 U.S. at 113
    ). Furthermore, its order is “one by which
    ‘rights or obligations have been determined,’ [and] from which
    ‘legal consequences will flow.’” 
    Id.
     (quoting Port of Boston
    Marine Terminal Assn., 
    400 U.S. at 71
    ). As each permit states,
    6
    Riverkeeper objects, contending that PADEP’s order
    is not final because Riverkeeper may attempt to file an
    appeal nunc pro tunc before the Environmental Hearing
    Board. See 
    25 Pa. Code § 1021
    .53a; Twp. of Robinson v.
    Dep’t of Envtl. Prot., No. 451 C.D. 2007, 
    2008 WL 9405218
    , at *4 (Pa. Commw. Ct. July 3, 2008). But by that
    logic, a PADEP decision would never become final under
    the second sentence of § 7514(c). As the case comes
    before us, there has been no appeal to the Board, and in
    applying the text of § 7514(c), we do not think it would be
    appropriate to speculate about whether the Board would
    accept a nunc pro tunc appeal.
    13
    “This permit authorizes the construction, operation,
    maintenance and normal repair of the permitted structures.” JA
    36; JA 167; see Transcript of Oral Argument at 31:24–32:3
    (“When that permit issued and we had the approval of FERC
    . . . , we started construction . . . .”); NE Hub Partners, L.P. v.
    CNG Transmission Corp., 
    239 F.3d 333
    , 346 (3d Cir. 2001)
    (“Pa.D.E.P. permits are valid pending the E.H.B. outcome . . .
    .”); Com., Dep’t of Envtl. Res. v. Bethlehem Steel Corp., 
    367 A.2d 222
    , 229 (Pa. 1976) (holding that jurisdiction existed to
    enforce a consent order issued by the Department despite a
    pending appeal before the Board seeking modification); cf.
    Berkshire, 851 F.3d at 108 (noting that construction could not
    begin until “the expiration of the Appeal Period set forth below
    and any appeal proceedings that may result from an appeal”).
    Thus, by combination of § 7514(c) and the practical
    significance of PADEP’s permits, we conclude that we are
    reviewing final agency action. Our jurisdiction is proper
    regardless of whether the Natural Gas Act limits our review to
    final orders. We note, however, that there are cases pending
    before this Court where the petitioners dual-filed appeals
    before the Environmental Hearing Board. See, e.g., Docket
    Nos. 16-2212, 16-2218, 16-2400. Those actions ask this Court
    to review orders that are arguably nonfinal under § 7514(c).
    Whether the Natural Gas Act requires finality and how such a
    requirement would interact with Pennsylvania’s administrative
    scheme are issues better resolved in those cases.
    B
    PADEP argues that, because Riverkeeper’s petition would
    be untimely before the Environmental Hearing Board, it is also
    14
    untimely before us. We reject that argument because the
    regulation governing appeals before the Environmental
    Hearing Board does not define the timeliness of petitions
    before this Court.
    Under Rule 15 of the Federal Rules of Appellate Procedure,
    “[r]eview of an agency order is commenced by filing, within
    the time prescribed by law, a petition for review.” Fed. R. App.
    P. 15(a)(1) (emphasis added). “The procedures set forth in
    subsection (a) of Rule 15 are jurisdictional.” Wisniewski v.
    Dir., Office of Workers’ Comp. Programs, U.S. Dep’t of Labor,
    
    929 F.2d 952
    , 954 (3d Cir. 1991).
    According to PADEP, “the time prescribed by law,” Fed. R.
    App. P. 15(a)(1), refers to the state regulatory provision that
    governs appeals from PADEP to the Environmental Hearing
    Board. As described above, the appeal must be filed within
    “[t]hirty days after the notice of the action has been published
    in the Pennsylvania Bulletin.” 
    25 Pa. Code § 1021.52
    (a)(2)(i).
    But this is not an appeal before the Environmental Hearing
    Board, and the Board’s regulations are not binding on us.
    Rather, Rule 15 “defin[es] the time for filing a petition for
    review with reference to the statute providing for review of the
    agency’s orders.” United Gas Pipe Line Co. v. FERC, 
    824 F.2d 417
    , 435 (5th Cir. 1987). That refers to Section 19(d) of the
    Natural Gas Act. See Islander E. Pipeline Co., LLC v. Conn.
    Dep’t of Envtl. Prot., 
    482 F.3d 79
    , 83–84 (2d Cir. 2006) (“[T]he
    NGA . . . provides an expedited direct cause of action in the
    federal appellate courts to challenge a state administrative
    agency’s order . . . .”).
    15
    For appeals from FERC, the Natural Gas Act prescribes a
    sixty-day limitations period. See 15 U.S.C. § 717r(b). For
    appeals from other federal agencies and state agencies,
    however, the statute provides no limitation. See id.
    § 717r(d)(1). Whether timeliness is governed by the four-year
    catchall limitations period established by 
    28 U.S.C. § 1658
    (a),7
    or laches, Schaefer v. NLRB, 
    697 F.2d 558
    , 560–61 (3d Cir.
    1983), we are unable to conclude that Riverkeeper filed its
    petition out of time.
    Accordingly, jurisdiction is proper under the Natural Gas
    Act and under Rule 15 of the Federal Rules of Appellate
    Procedure.
    III
    Turning to the merits, we review for arbitrary or capricious
    agency action. Del. Riverkeeper, 833 F.3d at 377.8 Riverkeeper
    argues that PADEP erred under that standard for two reasons.
    First, Riverkeeper argues that PADEP made an erroneous
    7
    Although not raised by the parties, 
    28 U.S.C. § 1658
    (a)
    establishes a four-year limitations period for any “civil action
    arising under an Act of Congress enacted after” December 1,
    1990. See Jones v. R.R. Donnelley & Sons Co., 
    541 U.S. 369
    ,
    382 (2004); N. Star Steel Co. v. Thomas, 
    515 U.S. 29
    , 34 n.*
    (1995).
    8
    The arbitrary-and-capricious standard derives from the
    Administrative Procedure Act, 
    5 U.S.C. § 706
    (2)(A), which
    does not cover state agencies, see 
    id.
     § 701(b)(1). Nonetheless,
    this court and others have applied that standard. See, e.g., Del.
    Riverkeeper, 833 F.3d at 377; Islander, 
    482 F.3d at 94
    .
    16
    “water dependency” finding. Second, Riverkeeper argues that
    PADEP erred by ruling out a “compression” alternative. We
    reject both arguments in turn.
    A
    PADEP determined that the Orion Project is “water
    dependent.” According to Riverkeeper, that finding was
    erroneous because linear infrastructure projects (like pipelines
    and roads) are categorically not water dependent. PADEP
    acknowledges that, under federal law, Riverkeeper might be
    right. But under Pennsylvania law, PADEP argues, water
    dependency operates differently. We conclude that PADEP has
    provided a reasonable explanation for how its regulations
    differ, and we will defer to its interpretation.
    Because the Orion Project would construct pipeline looping
    through “exceptional value” wetlands, 
    25 Pa. Code § 105.17
    (1), PADEP cannot approve the project without first
    certifying that “[t]he project is water-dependent,” 
    25 Pa. Code § 105
    .18a(a)(2). “A project is water-dependent when the
    project requires access or proximity to or siting within the
    wetland to fulfill the basic purposes of the project.” 
    Id.
    Riverkeeper thus argues, by reference to federal law, that
    pipelines and other types of linear infrastructure are
    categorically not water dependent. It relies on the following
    explanation of water dependency by a federal agency, the
    United States Army Corps of Engineers:
    [T]he purpose of a residential development is to
    provide housing for people. Houses do not have
    17
    to be located in a special aquatic site to fulfill the
    basic purpose of the project, i.e., providing
    shelter. Therefore, a residential development is
    not water dependent. . . . Examples of water
    dependent projects include, but are not limited
    to, dams, marinas, mooring facilities, and docks.
    The basic purpose of these projects is to provide
    access to the water.
    Sierra Club v. Van Antwerp, 
    709 F. Supp. 2d 1254
    , 1261 (S.D.
    Fla. 2009) (quoting Army Corps of Engineers Standard
    Operating Procedures for the Regulatory Program (October 15,
    1999)), aff’d, 362 F. App’x 100 (11th Cir. 2010). Under that
    understanding, Riverkeeper argues that pipeline projects are
    not water dependent because, unlike a dam, marina, or dock,
    pipelines are not by their nature dependent on being in or near
    water—even if the desired construction path would cross a
    wetland or waterbody. See, e.g., Coastal Conservation League
    v. U.S. Army Corps of Eng’rs, No. 4:16-cv-03008, 
    2016 WL 6823375
    , at *14 (D.S.C. Nov. 18, 2016) (noting that a road
    project is not water dependent even though “expanding and
    improving the road cannot occur without impacting special
    aquatic sites”).
    In the context of the federal regulatory scheme, that
    understanding of water dependency makes sense. If a project
    is water dependent, like a dam, it is impossible to construct
    without impacting an aquatic site. But if a project is not water
    dependent, “practicable alternatives that do not involve special
    aquatic sites are presumed to be available, unless clearly
    demonstrated otherwise.” 
    40 C.F.R. § 230.10
    (a)(3). In other
    words, the agency will presume that the applicant can select a
    18
    different pipeline route or other alternative that does not affect
    an aquatic site. If the applicant rebuts that presumption, the
    project does not become “water dependent”; the applicant has
    simply met its burden under the regulation. In other words, the
    water-dependency finding comes first and the alternatives
    analysis comes second.
    PADEP took a different approach. It observed that the
    proposed pipeline looping “needs to cross the wetland areas to
    access land on either side of the wetland system” because
    “there are no practicable crossing alternatives to avoid the
    crossing.” JA 49, 180. Indeed, “[l]inear infrastructure projects
    of any significant length proposed in Pennsylvania will
    encounter surface waters, including wetlands.” Resp. Br. 14.
    By rejecting alternatives to the Orion Project and observing the
    pipeline’s path would unavoidably traverse wetlands, PADEP
    concluded that the Orion Project is water dependent. Rather
    than treating water dependency and alternatives analysis as two
    distinct inquiries, PADEP combined them into one step.
    Riverkeeper argues that the federal understanding of water
    dependency should control. The definition of water
    dependency in 
    25 Pa. Code § 105
    .18a(a)(2) is identical to its
    federal counterpart, 
    40 C.F.R. § 230.10
    (a)(3); see also 
    25 Pa. Code § 105
    .18a(b)(3)(i) (“It shall be a rebuttable presumption
    that there is a practicable alternative, not involving a wetland,
    to a nonwater-dependent project, and that the alternative would
    have less adverse impact on the wetland.”).
    PADEP responds that Riverkeeper’s emphasis on federal
    law is misplaced because PADEP relied on a regulatory
    provision unique to Pennsylvania:
    19
    (b) In reviewing a permit application under this
    chapter, the Department will use the
    following factors to make a determination of
    impact:
    ...
    (7) The extent to which a project is water
    dependent and thereby requires access or
    proximity to or siting within water to fulfill
    the basic purposes of the project. The
    dependency must be based on the
    demonstrated unavailability of           any
    alternative location, route or design and the
    use of location, route or design to avoid or
    minimize the adverse impact of the dam,
    water obstruction or encroachment upon the
    environment and protect the public natural
    resources of this Commonwealth.
    
    25 Pa. Code § 105.14
    (b)(7). This provision endorses a more
    flexible approach to water dependency. Contrary to
    Riverkeeper’s interpretation, this provision states that a water-
    dependency finding “must be based on” the unavailability of
    “alternative[s]” and the project’s ability to “avoid or minimize
    the adverse impact of the . . . encroachment upon the
    environment.” 
    Id.
     This language supports PADEP’s
    interpretation. As contemplated by § 105.14(b)(7), PADEP’s
    conclusion as to water-dependency was based on its finding
    20
    that no “alternative location, route or design” could avoid
    adverse impacts on aquatic sites and the environment. Id.9
    In light of these conflicting provisions, we conclude that the
    meaning of “water dependent” in 
    25 Pa. Code § 105
    .18a(a)(2)
    is ambiguous. If we were reviewing an order of a federal
    agency, we would be required to defer to the agency’s
    reasonable interpretation of its own regulations. See Auer v.
    Robbins, 
    519 U.S. 452
     (1992). The question here is whether a
    state agency should receive similar deference. We conclude
    that such deference is appropriate.
    Pennsylvania specifically recognizes Auer-style deference
    for its agencies. See, e.g., Buffalo Twp. v. Jones, 
    778 A.2d 1269
    ,
    1276 n.8 (Pa. Commw. Ct. 2001) (“In reviewing an agency’s
    interpretation of . . . its own regulations, unless the language is
    clear, we are required to defer to the agency’s
    interpretation . . . .”), aff’d, 
    813 A.2d 659
     (Pa. 2002). Nothing
    in the Natural Gas Act or our system of federalism compels us
    9
    Riverkeeper attempts to downplay the significance of 
    25 Pa. Code § 105.14
    (b)(7) by arguing that it was not cross-
    referenced in the regulation at issue here, 
    25 Pa. Code § 105
    .18a(a)(2) (establishing special protections for
    exceptional-value wetlands). But § 105.14(b)(7) is part of a
    general provision that governs “reviewing a permit application
    under this chapter.” The provision is thus arguably applicable
    even in the absence of an explicit cross-reference. Riverkeeper
    also objects that § 105.14(b)(7) favors its position because
    Tennessee Gas did not “demonstrate[]” the “unavailability” of
    the compression alternative. But that is a separate question that
    we will return to in the next section.
    21
    to strip a state agency of the deference it would otherwise
    receive in its own courts. This Court recognized similar
    deference in Barnes v. Cohen, which concluded that “the
    [Pennsylvania Department of Public Welfare’s] interpretation
    of its own regulations is, of course, entitled to considerable
    deference. . . . [H]owever, we need not accept the agency
    interpretation if it is ‘plainly erroneous or inconsistent with the
    regulation.’” 
    749 F.2d 1009
    , 1018 (3d Cir. 1984) (quoting
    Bowles v. Seminole Rock & Sand Co., 
    325 U.S. 410
    , 414
    (1945)); accord Bldg. Trades Emp’rs’ Educ. Ass’n v.
    McGowan, 
    311 F.3d 501
    , 507 (2d Cir. 2002) (“We defer to
    a state agency’s interpretation of its own regulations, unless
    the interpretation is arbitrary or capricious.”).10
    Applying that deferential standard, we conclude that
    PADEP’s interpretation of water dependency is reasonable.
    10
    State agencies’ interpretations of federal law do not
    ordinarily receive deference. See MCI Telecomm. Corp. v. Bell
    Atl. Pa., 
    271 F.3d 491
    , 516 (3d Cir. 2001). But some federal
    courts have shown deference to state agencies’ interpretations
    of state law. See, e.g., Arizona v. City of Tucson, 
    761 F.3d 1005
    ,
    1014 (9th Cir. 2014) (“Federal courts generally defer to
    a state agency’s interpretation of those statutes it is charged
    with enforcing, but not to its interpretation of federal statutes it
    is not charged with enforcing.”); City Of Bangor v. Citizens
    Commc’ns Co., 
    532 F.3d 70
    , 94 (1st Cir. 2008); Mich. Bell Tel.
    Co. v. MCIMetro Access Transmission Servs., Inc., 
    323 F.3d 348
    , 357 (6th Cir. 2003); Enter. Leasing Co. v. Metro. Airports
    Comm’n, 
    250 F.3d 1215
    , 1217 (8th Cir. 2001).
    22
    First, as noted above, PADEP’s flexible approach to water
    dependency is consistent with the text of 
    25 Pa. Code § 105.14
    (b)(7). That provision appears to be unique to
    Pennsylvania and is fully compatible with PADEP’s
    interpretation.
    Second, PADEP’s flexible approach to water dependency is
    public and longstanding. See, e.g., Barnhart v. Walton, 
    535 U.S. 212
    , 220 (2002) (“[T]his Court will normally accord
    particular deference to an agency interpretation of
    ‘longstanding’ duration.” (quoting North Haven Bd. of Ed. v.
    Bell, 
    456 U.S. 512
    , 522 n.12 (1982))). In 1991, when the
    relevant regulations were first promulgated, PADEP stated its
    intention to evaluate the water dependency of linear
    infrastructure projects on a case-by-case basis. For example, in
    response to a public comment, PADEP stated that “[r]oads may
    be considered water dependent on a case by case basis.” DEP
    Addendum 12; see also DEP Addendum 9 (“[T]he Department
    believes that haul roads, depending on their location, may be
    water dependent and will make that determination on a case by
    case basis.”). Such case-by-case analysis belies the categorical
    approach urged by Riverkeeper.
    And third, water dependency plays a different role in
    Pennsylvania’s administrative scheme. Under the federal
    regulations, water dependency is a procedural consideration
    that affects the applicant’s burden. See 
    40 C.F.R. § 230.10
    (a)(3). In Pennsylvania, water dependency is a
    substantive criterion that must be met in order to obtain certain
    Chapter 105 permits. See 
    25 Pa. Code § 105
    .18a(a)(2). Under
    Riverkeeper’s categorical approach, some projects might be
    impossible to approve even if they would be environmentally
    23
    harmless. It stands to reason that PADEP would retain
    discretion to approve projects, such as this one, where no
    alternatives would minimize or avoid adverse impacts on the
    environment pursuant to 
    25 Pa. Code § 105.14
    (b)(7).
    Thus, we conclude that PADEP did not act arbitrarily or
    capriciously by incorporating an alternatives analysis as part of
    its water-dependency finding. While PADEP’s interpretation of
    water dependency appears to be unique, it is nonetheless
    reasonable in light of the text and structure of Pennsylvania’s
    regulatory scheme. We will therefore defer to PADEP’s
    interpretation and reject Riverkeeper’s categorical approach.
    B
    Riverkeeper finally argues that, even if PADEP’s water-
    dependency finding was not arbitrary or capricious, PADEP’s
    alternatives analysis was erroneous. Specifically, Riverkeeper
    asserts that PADEP was required to embrace a compression
    alternative. That alternative would have increased the amount
    of natural gas transported through existing pipelines—
    avoiding all impacts on wetlands and waterbodies that would
    be caused by constructing new pipeline looping. We conclude,
    however, that PADEP considered the compression alternative
    and rejected it for reasons supported by the record.
    In addition to certifying that the project is water dependent,
    PADEP must also certify that “[t]here is no [1] practicable
    alternative to the proposed project that [2] would not involve a
    wetland or that would have less effect on the wetland, and [3]
    not have other significant adverse effects on the environment.”
    
    25 Pa. Code § 105
    .18a(a)(3). That standard is almost identical
    24
    to its federal counterpart, 
    40 C.F.R. § 230.10
    (a), which we
    discussed at length in the companion case Delaware
    Riverkeeper Network v. U.S. Army Corps of Engineers, No. 17-
    1506 (3d Cir. 2017). There, we held that the United States
    Army Corps of Engineers did not arbitrarily or capriciously
    reject the compression alternative because the agency
    reasonably concluded that the compression alternative would
    have “other significant adverse effects on the environment.” 
    40 C.F.R. § 230.10
    (a). We will uphold PADEP’s decision for the
    same reason.
    The compression alternative would “us[e] gas- and electric-
    powered turbines to increase the pressure and rate of flow at
    given points along the pipeline’s route.” Del. Riverkeeper, 833
    F.3d at 369.11 As part of its application to PADEP, Tennessee
    Gas included an alternatives analysis that rejected that
    approach. Tennessee Gas stated that “adding a new (greenfield)
    compressor station would require Tennessee [Gas] to obtain
    approximately 40-acres per site,” and that construction “would
    require permanent vegetation clearing from the area in order to
    install permanent access roads, fencing, buildings and other
    appurtenance equipment . . . resulting in increased impacts to
    the environment.” JA 266, 279. Tennessee Gas also observed
    that “a new (greenfield) compressor station would be an
    11
    The parties focus primarily on building one or more new
    compressor stations rather than upgrading an existing station.
    See Del. Riverkeeper Network v. U.S. Army Corps of Eng’rs,
    No. 17-1506, slip op. at 6 n.3 (3d Cir. 2017) (“[U]pgrades to
    existing compressor stations, without looping, did not offer the
    same reliability and flexibility on the system.”). We focus our
    analysis accordingly.
    25
    aboveground facility with light pollution and noise impacts and
    may also become a source of [greenhouse gas] emissions.” Id.
    In contrast to those permanent environmental impacts, the land
    affected by construction “will be allowed to re-vegetate to
    minimize and mitigate possible environmental impacts.” Id.;
    see JA 38 (“All disturbed wetland areas are to be restored to
    the original contours and shall be replanted with indigenous
    plant species.”); JA 39 (“The permittee shall monitor the
    restored wetland areas within the ROW for a minimum of three
    growing seasons . . . .”).
    While PADEP did not explicitly mention compression in its
    alternatives analysis, it did consider “System Alternatives,”
    i.e., alternatives that make use of existing transportation
    systems. JA 45, 176. Compression is one type of system
    alternative. See JA 294. PADEP also adopted Tennessee Gas’s
    reasoning as its own: “The Department has reviewed
    [Tennessee Gas’s] report and finds no cause to disagree with
    the conclusions and final alternative presented.” Id.
    As part of a checklist reflecting the criteria for approving
    projects that would affect exceptional-value wetlands, PADEP
    certified that the Orion Project is “the least environmentally
    damaging alternative.” JA 49, 180. In support of that
    conclusion, PADEP references its alternatives analysis, which
    in turn adopted Tennessee Gas’s reasoning. As discussed at
    length in the federal companion case, the agency’s statement
    amounts to a judgment that the permanent environmental
    impacts from the compression alternative are “significant.” See
    Motor Vehicle Mfrs. Ass’n of U.S. v. State Farm Mut. Auto. Ins.
    Co., 
    463 U.S. 29
    , 43 (1983) (“We will . . . uphold a decision of
    less than ideal clarity if the agency’s path may reasonably be
    26
    discerned.” (quoting Bowman Transp., Inc. v. Arkansas-Best
    Freight Sys., Inc., 
    419 U.S. 281
    , 286 (1974))).12
    Accordingly, we conclude that PADEP did not arbitrarily or
    capriciously disregard the compression alternative.
    IV
    For the foregoing reasons, we will uphold PADEP’s
    decision to issue the Chapter 105 permits and deny the petition
    for review.
    12
    The permanent, “significant” environmental impacts of
    the     compression       alternative    reasonably    establish
    “demonstrated unavailability” under 
    25 Pa. Code § 105.14
    (b)(7). See supra note 9. PADEP’s statement that there
    are no “practicable crossing alternatives,” JA 49, 180, does not
    imply that its decision was based purely on costs or logistics.
    Rather, it reflects a judgment that “certain avoidance measures
    were not feasible because they were determined not to be as
    environmentally sound.” JA 25; see also JA 141, 321
    (discussing “other environmental impact considerations”).
    That approach is consistent with § 105.14(b)(7) and thus not
    arbitrary or capricious.
    27
    

Document Info

Docket Number: 17-1533

Filed Date: 8/30/2017

Precedential Status: Precedential

Modified Date: 8/31/2017

Authorities (29)

City of Bangor v. Citizens Communications Co. , 532 F.3d 70 ( 2008 )

building-trades-employers-educational-association-action-electrical , 311 F.3d 501 ( 2002 )

Michael M. Schaefer, an Individual Proprietor v. National ... , 697 F.2d 558 ( 1983 )

Anna Wisniewski, Widow of Edward Wisniewski v. Director, ... , 929 F.2d 952 ( 1991 )

ne-hub-partners-lp-v-cng-transmission-corporation-penn-fuel-gas-inc , 239 F.3d 333 ( 2001 )

Islander East Pipeline Company, LLC v. State of Connecticut ... , 482 F.3d 79 ( 2006 )

United Gas Pipe Line Co. v. Federal Energy Regulatory ... , 824 F.2d 417 ( 1987 )

Atlantic Seaboard Corp. v. Federal Power Commission , 201 F.2d 568 ( 1953 )

Jack Ehleiter v. Grapetree Shores, Inc. , 482 F.3d 207 ( 2007 )

Donna Lee McLaughlin v. Arco Polymers, Inc., a Corporation ... , 721 F.2d 426 ( 1983 )

Energy Transfer Partners, L.P. v. Federal Energy Regulatory ... , 567 F.3d 134 ( 2009 )

the-moravian-school-advisory-board-of-st-thomas-vi-v-helen-rawlins-the , 70 F.3d 270 ( 1995 )

mci-telecommunication-corporation-a-delaware-corporation-mcimetro-access , 271 F.3d 491 ( 2001 )

roseann-barnes-on-behalf-of-herself-and-all-others-similarly-situated , 749 F.2d 1009 ( 1984 )

Buffalo Township v. Jones , 778 A.2d 1269 ( 2001 )

michigan-bell-telephone-company-dba-ameritech-michigan-v-mcimetro-access , 323 F.3d 348 ( 2003 )

Enterprise Leasing Company, Doing Business as Enterprise ... , 250 F.3d 1215 ( 2001 )

Bowles v. Seminole Rock & Sand Co. , 65 S. Ct. 1215 ( 1945 )

Texas Keystone Inc. v. Pennsylvania Department of ... , 851 A.2d 228 ( 2004 )

Sierra Club v. Van Antwerp , 709 F. Supp. 2d 1254 ( 2009 )

View All Authorities »